Hutch Construction in Far Experimental Hall. David Saenz – Project Manager June 08, 2009. Scope Design Status/Deliverables Schedule Estimated Construction Cost Present Status Summary. Scope. Approximately 7,000sf of new facilities for (3) Hutches, (3) Control Rooms and (1) Common Room - PowerPoint PPT Presentation
18
1 David Saenz [email protected] du 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager June 08, 2009
Transcript
Page 1: Hutch Construction  in Far Experimental Hall

1 David [email protected]

1Hutch Construction in FEHJune 08, 2009

Hutch Construction in

Far Experimental Hall

David Saenz – Project ManagerJune 08, 2009

Page 2: Hutch Construction  in Far Experimental Hall

2 David [email protected]

2Hutch Construction in FEHJune 08, 2009

Scope

Design Status/Deliverables

Schedule

Estimated Construction Cost

Present Status

Summary

Page 3: Hutch Construction  in Far Experimental Hall

3 David [email protected]

3Hutch Construction in FEHJune 08, 2009

Scope

Approximately 7,000sf of new facilities for (3) Hutches, (3) Control Rooms and (1) Common Room

Specifications have been developed, are well defined, and present no major challenges

Page 4: Hutch Construction  in Far Experimental Hall

4 David [email protected]

4Hutch Construction in FEHJune 08, 2009

Scope – Cont’d

Utilities (MEP)

Process chilled water

Chilled water

Compressed air @ 100psi

HVAC 72° ± 1 °F

RH 45% ± 10%

24” cable trays

Standard lighting

Surface mounted conduits

Standard 110V and 208V outlets

1 ton capacity cranes

Radiation protection

Standard door sizes

Existing common floor

Standard wall/ceiling finishes

No acoustic requirements

Page 5: Hutch Construction  in Far Experimental Hall

5 David [email protected]

5Hutch Construction in FEHJune 08, 2009

Engineering Specification Documents

LCLS ESD’s approved by key stake-holders.

ESD 1.9-112

Hutch 4

ESD 1.9-113

Hutch 5

ESD 1.9-114

CXI Room

ESD 1.9-115

XCS Room

ESD 1.9-116

Common Room

ESD 1.9-117

Page 6: Hutch Construction  in Far Experimental Hall

6 David [email protected]

6Hutch Construction in FEHJune 08, 2009

Access Tunnel (looking south)

Page 7: Hutch Construction  in Far Experimental Hall

7 David [email protected]

7Hutch Construction in FEHJune 08, 2009

FEH (looking west)

Page 8: Hutch Construction  in Far Experimental Hall

8 David [email protected]

8Hutch Construction in FEHJune 08, 2009

FEH Floor Plan

Hutch 4 – XCS Hutch 5 – CXI Hutch 6 - MECi

Existing X-Ray Tunnel

Existing Restrooms

Existing Access Tunnel

Page 9: Hutch Construction  in Far Experimental Hall

9 David [email protected]

9Hutch Construction in FEHJune 08, 2009

Building Sections

Building Section – Looking North

Building Section – Looking South

Hutch 4 Hutch 6Hutch 5

Hutch 6 Hutch 5 Hutch 4

Page 10: Hutch Construction  in Far Experimental Hall

10 David [email protected]

10Hutch Construction in FEHJune 08, 2009

TI/TII/TIII StatusDesign was awarded Oct 10, 08

Title I completed on Nov 6, 08

Title II 60% completed Jan 15, 09

Title II 90% completed for Mar 09, 09

Title II 100% completed for Mar 16, 09

Issue for Bid documents completed Mar 23, 09

Bidder jobwalk conducted on April 29, 09

7 General Contractors (Butler, Gordan-Prill, DPR, Rudolph Sletten, XL, Dome and Lyncon)

5 GC’s have performed work at SLAC/LCLS/DOE/SU)

Bids received May 18, 09

Note: The structural steel design was advanced prior to final package for early release to bid.

Page 11: Hutch Construction  in Far Experimental Hall

11 David [email protected]

11Hutch Construction in FEHJune 08, 2009

Design Deliverables

√ Existing Conditions Report

√ 30% Design Review

√ Structural Design Review

√ Preliminary Cost Estimate

√ 60% Design Review

√ Detailed Cost Estimate

√ Value Engineering

√ Structural 3rd Party Peer Review

√ Engineering Coordination Presentation

√ 90% Design Review

√ Updated Cost Estimate

√ 100% Design Review

√ Issue For Bid (IFB) documents

√ 100% Cost Estimate

•Sufficient quantity of deliverables were established to manage progress and complete development of a final package ready for bid!

Page 12: Hutch Construction  in Far Experimental Hall

12 David [email protected]

12Hutch Construction in FEHJune 08, 2009

Schedule

Design Complete Mar 16, 09

Procurement 4/09-5/09

Construction Commence 5/26/09

Project Complete!!

•Steel package has been awarded and is being managed by LCLS direct

•Fabrication drawings have been approved by EOR

•Steel is currently under fabrication and scheduled for on site erection 6/15/09 – 7/3/09

Page 13: Hutch Construction  in Far Experimental Hall

13 David [email protected]

13Hutch Construction in FEHJune 08, 2009

Construction Cost Estimate H4 and H5Initial 30% AE estimate (Nov 5, 08) at $4.1M includes direct/in-direct cost, and escalation

60% AE estimate (Feb 2, 09) at $3.58M

Value Engineering items included

Strategy for construction delivery method is consistent with expectations

Design → Bid → Build

Structural steel package has been released early for bid and erection

A cross-check estimate was provided by a GC at $3.1M

Same GC successfully completed LCLS Sector 20 and MMF projects

90% AE estimate (Feb 20, 09) at $3.48M

100% AE estimate (Mar 23, 09) at $3.34M

WBS (1.9.3.14.2) budget is $3.4M for H4 and H5

Page 14: Hutch Construction  in Far Experimental Hall

14 David [email protected]

14Hutch Construction in FEHJune 08, 2009

Construction Cost Estimate H6

60% AE estimate (Feb 2, 09) at $.77M

A cross-check estimate was provided by a GC at $.70M

Same GC successfully completed LCLS Sector 20 and MMF projects

90% AE estimate (Feb 20, 09) at $.76M

100% AE final estimate at $.67M

Independent Cost Review provided by SMSI rec’d Mar 23, 09

Hutch 6 can be constructed in conjunction with H4/H5 without impacting schedule

BCR CF-109 was approved ($800K) to include Hutch 6 construction as part of the CF WBS 1.9 in April 09.

Page 15: Hutch Construction  in Far Experimental Hall

15 David [email protected]

15Hutch Construction in FEHJune 08, 2009

Independent Cost Review

SMSI - Professional estimating consulting firm located in the bay area and familiar with bay area economy- Has experience with projects within DOE environment- Understand the requirements involved with DOE complex projects

Page 16: Hutch Construction  in Far Experimental Hall

16 David [email protected]

16Hutch Construction in FEHJune 08, 2009

WBS

WBS 1.9 for FEH Hutches $4.2MSteel awarded at $390K

To be managed by LCLS CF group

Concrete deck estimated at $75KNot yet awarded

To be managed by LCLS CF group4 bids received (range $46.7K to $87.8K)

Remaining build-out construction balance in WBS budgeted $3,735K

All bids received were < estimated budgetThree bids received were 50% < estimated budget!

Construction schedule is sufficient allowing for 26 weeks of construction (not including steel erection)

Page 17: Hutch Construction  in Far Experimental Hall

17 David [email protected]

17Hutch Construction in FEHJune 08, 2009

Summary√ Design parameters are clearly defined

√ Sufficient quantity of deliverables are in process

√ Title I complete

√ Value Engineering complete

√ Title II complete

√ Issue for Bid set complete

√ Structural steel released for bid with favorable results

Cost

Safety

Schedule

√ Adequate resources are available for successful execution of the FEH hutches!

Page 18: Hutch Construction  in Far Experimental Hall

18 David [email protected]

18Hutch Construction in FEHJune 08, 2009

end of presentation