Hybrid Grid and Energy Storage: A Step towards Adaptation, Application and
Development
BY
J.S. CHANDOK AGM(NETRA)
NETRA , NTPC LTD.
• India’s MAHARATNA & Leading Power Generating Company with 48 GW of Installed capacity with decent fuel mix. (www.ntpc.co.in)
• Installed Renewable power (Solar and Wind) of 410 MW and more than 600 MW Solar and Wind projects are in pipeline.
• Major contributor to mission of 175 GW of Renewable power by GOI : 25 GW of Solar Power.
• Solar PV with Storage project for Green Andaman : a. 8 MW SPV, WITH 3.2 MW, 1.6 MWHR b. 17 MW SPV, 6MW, 24 MWHR.
• NETRA (NTPC Energy Technology Research Alliance), R&D Wing of NTPC : focus areas of Energy and Efficiency Improvement, Renewable Energy and Climate change.
About NTPC and NETRA
• With Large Renewable penetration, Maintaining stable supply of high-quality electricity : Urgent issue with large Renewable.
• Integration with thermal power : a great Responsibility for NTPC to bring flexibility in thermal plants and in the power system as well.
• Hybridization of Renewable Resources: Complement each other and also optimize size of battery storage.
• Hybridization of Renewable resources and Battery energy storage systems : Promising option to mitigate this issue and gaining popularity.
• Combination of Battery storage ( high power & High Energy) : Required to cater short cycle and long cycle fluctuations
• Requires Adaption, Suitable applications and development of low cost battery system, NETRA is positioned to take up this.
Introduction
Development
Cost Effective Innovations
• A new kind of redox flow battery development with IISc , Banglore –Soluble Lead Redox Flow Battery(SLRFB)
• Development of Control and Protection for Hybrid Renewable Integration with IIT Kanpur
Adaptation
Trial of existing Technology
• Field trial of NAS battery under the Indian Climate and under Indian grid Condition followed by Modification in battery system as per Indian Grid .
Application
Possible applications
• Solar wind Hybrid system Installation .
• In future Solar wind Hybrid with storage.
• Setup of pilot plant for 24X7 Solar PV with Energy Storage System at NTPC, KAWAS
Hybrid Grid & Storage Activities: NTPC NETRA
NETRA – NTPC Energy Technology Research Alliance, R&D wing of NTPC Limited
NAS BATTERY DEMO PROJECT AT NETRA—FIELD TRAIL OF NAS
BATTERY
Technology Adaptation
1.2 MWHR test system
ITEMS SPECIFICATION
Battery Size 200 KW
ACTIVE POWER 180 KW
CONNECTION VOLTAGE 3 PHASE/3 WIRE/400V
Cell Temp 300 Deg C
VOLTAGE RANGE DC138~DC228 V
CURRENT RANGE ~1050 A TO +1500 A
DC RIPPLE CURRENT <10% P-P
STORAGE ENERGY 1080 kWh-ac
AC/DC CON. EFFICIENCY
95%
AUX POWER 3 PHASE/3 WIRE/400V 35 KW/UNIT
Fast response Full power charge and discharge in 1 ms
1. Under Research agreement M/s NGK Insulator Pvt Ltd Japan, NETRA is conducting field trials and testing of 1.08 MWhr NaS battery system
2. Intent : Evaluate the efficacy of system for various charging discharging pattern, including solar variation etc, In Indian environment and grid condition
3. The system is installed in Oct 2016 and shall tested and evaluated for six months upto April 17.
Basic working Principle
Operation Profiles for NAS TEST
[1-1 Rectangular] To learn the most basic performance
-200
-150
-100
-50
0
50
100
150
200
0:00 3:00 6:00 9:00 12:00 15:00 18:00 21:00 0:00
Po
we
r [k
W-a
c]
Pattern (a)
Pattern (b)
Pattern (c)
Pattern (d)
-200
-150
-100
-50
0
50
100
150
200
0:00 3:00 6:00 9:00 12:00 15:00 18:00 21:00 0:00
Pow
er [
kW-a
c]
Pattern (e)
Pattern (f)
Pattern (g)
Charge: 180kW x ~10H Discharge:(a)180kWx6.1H (b)170kWx7.0H (c)160kWx7.5H (d)150kWx8H
Charge: 180kW x ~10H Discharge:(a)Peak: 180kW x3H (b)Peak: 170kW x3H (c)Peak: 160kW x3H
Charge Discharge
BES
S P
ow
er
[kW
]
Charge Discharge
[1-2 Trapezoidal] To learn the performance in typical Load Leveling
1. Basic Profiles
Time
Operation Profiles for NAS TEST
D
C
Po
we
r [
kW]
2. Typical Profiles from the Solar PV simulation
D
Smoothing & Energy Shift
C
Energy Shift
[2-1 Typical Sunny Day] Actual Energy Shift Capability
[2-2 Typical Cloudy] Actual Smoothing & Energy Shift capability
PV
NAS + PV
Time Time
NAS Charge
NAS Discharge
1. 24X7 PV-BATTERY STAORAGE SYSTEM AT NTPS
KAWAS
2. MULTITECHNOLOGY TEST BED FOR 5 MWp NTPC
ANDAMAN PROJECT
3. SOLAR WIND HYBRID SYSTEM AT NTPC KUDGI
Technology Application : Storage & Hybrid Grid
Solar with Battery Storage at NTPC, KAWAS
Salient Details
Location : NTPC Kawas
Area available :5 Acres
Power evacuation : Isolated colony load (290-310 KW) by two
feeder)
Configuration:
1 MW Solar and min 500 kW battery storage power, 3.6 MWHR
Flat load 24 X 7 :170 KW with 10 solar hrs and 14 battery hrs
Objective
To achieve 24 X 7 power and power on demand
Realizing Isolated grid Operation
Reliable power with both islanded and grid control operation
Smart grid features like load control, advanced protection for both operation
Solar with Battery Storage at NTPC, KAWAS
Objective: To Integrate battery storage with Floating PV & Forecasting and analyze techno-
economics for the utility of Floating PV and different battery storage system.
Configuration: 5 MW is divided into three parts of 1.67 MW each, and separate storage system is
proposed for the same.
Part Calculated Base load and
battery capacity
Proposed battery capacity*
Part 1 (1.67 MWp Solar),
8 hr operation
0.82 MW,
1 MWHR
1 MW ,
1 MWhr
(Li-ion battery / Advance Lead Acid)
Part 2 (1.67 MWp Solar), 12 hrs
operation
0.53 MW,
2.6 MWHR
0.6 MW,
2.4 MWhr (Li-ion/ NaS / Advance Lead)
Part 3 (1.67 MWp Solar)
24 hrs operation
0.25 MW,
5.0 MWHR
0.8 MW,
4.8 MWhr (NaS / Flow Battery)
*The proposed battery capacity has been selected based on available size in the market. The above sets of battery system will be procured separately as
different battery suits to different application and suitability of a particular battery for a given option can be studied
Multi Technology Test Bed
MultiTechnology Test Bed
Intent 1. Flat load operation of the 5 MWp PV Plant
2. Understanding different battery technologies for
integration with solar PV and grid.
3. Applicability of various battery technologies for
different applications.
4. Cost economic studies of different batteries in
different applications.
5. Grid stabilization study
6. Understanding O&M requirements of different
batteries in different applications.
7. Finalization of effective, cost economic application
for battery storage for renewable integration for
present and future scenarios.
8. Development of control algorithm for different
DoDs of batteries.
Objective To maximize the yield from an identified piece of land : High eff Panel
Establish the benefits of solar wind hybrid plant over the individual solar or wind plant. : Hybrid system (at DC or AC)
The effective land utilization by installing the solar PV panels in area around wind turbine avoiding shadow of the wind turbine is the objective of the project. : Land Optimization (shadow free zone 9-15 hrs)
Development of control strategy for active power control when cumulative generation of the solar and wind is above the evacuation capacity is the integral part of the project. Control with lower Evac
Pilot Plant : Solar Wind Hybrid at Kudgi
Configuration : 2 MW Wind + min 1 MW solar
Advantage : Land Optimization, Reduced cost of Evacuation, Improved Power Generation profile,
Reduction in O&M cost, Optimal sized battery storage.
Different Configurations Proposed by Different Wind
DC Integration of Solar Wind (Type 4) and storage DC Integration of Solar & storage with Type 3 Wind AC integration
AC Integration of Solar, Wind (type 4) & storage DC Integration of Solar, Type3 Wind
1. 500 W X 5 hr SOLUBLE LEAD ACID FLOW BATTERY
WITH – With IISc Bangalore
2. DEVELPOMENT OF CONTROL AND PROTECTION
FOR HYBRID RENWABLE INTEGRATION” - WITH IIT
Kanpur
Technology Development : Storage & Hybrid Grid
Soluble Lead Redox Flow Batteries
At anode,
Pb(CH3SO3)2 + 2e- Pb + 2CH3SO3- Eo = -0.13 V vs. RHE
At cathode,
Pb(CH3SO3)2 + 2H2O PbO2 + 2CH3SO3- + 2H+ + 2e- Eo = 1.49V vs. RHE
Overall cell reaction,
2Pb(CH3SO3)2 + 2H2O Pb + PbO2 + 4CH3SO3H Eo = 1.62V
Advantages :
• No membrane is required
• Single electrolyte and hence single pump
• No expensive catalyst required
• Materials are available abundantly
Electrolyte : Lead methanesulphonate salt in Methanesulphonic acid
Electrodes: Graphite foam at anode, Inter-digital fluid-flow design at cathode
“DEVELPOMENT OF CONTROL AND PROTECTION FOR HYBRID RENWABLE INTEGRATION”
Renewable Integration
Platform
Battery
Battery
Inverter
Solar
InverterSolar
PV
Solar
Inverter
440V 440V
PCC
Switch
Battery
Inverter
Solar
PV
Loads-3
Loads-2
Ethe
rnet
Control and
Monitoring PC
Control
Control
DC-
DC
Battery
DC-
DC
Control
Wind
(PM Gen)
AC-
DC
DC
Bus
Wind
(DFIG)
Control
Control
Control
Control
RTDS
1. Development of master controller for power sharing among sources and storage elements
Local controller for wind /solar/battery. Islanding/ grid connected operation, Proportional power sharing. Voltage / freq response
2. Protection scheme and load control
Fault level or grid connected or islanded operation. Adaptive protection scheme. Optimal load shedding/curtailment
3. Communication
Between various renewable sources, Battery power
4. Establishing software and management system
ADVANTAGE TO POWER SECTOR
• Controllers for AC/DC Hybrid Renewable Integration (HRI) system
• Testing and validation of controller using real time digital simulator (RTDS) to minimize uncertainty of performance in high power installations.
• In future, the developed platform could be used to conduct viability study of integrating HRI systems to the grid.
• Integrated communication to support both control and monitoring
• Coordination between the developed protection schemes and the associated controller operation
“DEVELPOMENT OF CONTROL AND PROTECTION FOR HYBRID RENWABLE INTEGRATION”
Conclusion
• With large Renewable penetration Technology Adaption, development and Pilots applications are important aspects to make path for future
• Hybrid Grid integration and sizing of optimal battery system around this is important for cost effective solution for dispatchable power
• Flexibility in the power system through Renewable resource forecasting and demand side management, smart grid aspects should be initiated.
• Understanding of Indian grid condition and modification in the control of battery PCS control is an important aspect
• Evaluation criteria for different battery system, combination of battery system with different life cycle, efficiency and application (power and Energy Intensive) is important
Hybrid Grid and Battery storage System
21
Thank You!