Date post: | 03-Apr-2018 |
Category: |
Documents |
Upload: | mansiagrawal |
View: | 218 times |
Download: | 0 times |
of 34
7/28/2019 Hydro Final
1/34
ISSUES &
STRATEGIES FOR
ENHANCING BHEL
HYDRO BUSINESS
7/28/2019 Hydro Final
2/34
Hydro Scenario in the World
++++ Hydro Scenario in IndiaBHEL Current Share in BusinessBusiness Potential Available
AGENDA FOR THE DAY
Customer Expectations & Priorities+ Present Issues- BHEL v/s Competitors+ Issues for Future Business+ Strategies to Increase Competitiveness
New Ways to Enhance Business
7/28/2019 Hydro Final
3/34
HYDRO
WORLD SCENARIO
TRENDS SEEN AROUND THE GLOBE
7/28/2019 Hydro Final
4/34
FUEL WISE GENERATION OVER THE YEARS
Used in 159 countries-provides 16% of worlds electricity
4.8%
7/28/2019 Hydro Final
5/34
HYDRO GENERATION OVER THE YEARS
Slowdown due to local &
international controversies
over large dams
52%
High growth era ushered in
particularly by rapid growth
in China
Hydro Installed capacity worldwide reached 1000 GW by 2010 end
(Current annual growth rate of 2.5% owing to huge base)
7/28/2019 Hydro Final
6/34
SKEWED DISTRIBUTION OF HYDRO POWER
India is sixth largest generator of hydro power3.7 % of world generation
11.5%
10.7%
9.3%
18.7%
30%
4 countries accountfor 50% of world
generation
10 countries account for 70% ofworld generation
7/28/2019 Hydro Final
7/34
UNDEVELOPED POTENTIAL AVAILABLE
7/28/2019 Hydro Final
8/34
HYDRO GENERATION FORECAST
India & China expected to take the lead in hydro generation GoI launched 50,000
MW initiative in 2003
7/28/2019 Hydro Final
9/34
OVERVIEWOF HYDRO PLANTS
INTRODUCTION TO VARIOUS HYDRO SYSTEMS
7/28/2019 Hydro Final
10/34
7/28/2019 Hydro Final
11/34
TYPES OF HYDRO POWER STATIONS
Sl.No Type of Plant Features
1Run of River
(RoR)
Harnesses energy from mainly the available flow of
the river
May include short term storage or pondage for flexibility in
adapting to load demand profile
Generation profile driven by natural river flow conditions
2 Reservoir
Water stored in artificially created reservoirs by makingdams or natural reservoirs
Water storage provides greater flexibility to match
generation with demand & reduce dependence on river flow
Small reservoir HPP can serve as base plant & large ones as
peaking plants
3Pumped
Storage
Water pumped from lower reservoir to upper reservoir
when supply exceeds demand
When demand increases, water released from upper
reservoir to flow back through turbines & generate power
Effective electricity storage
7/28/2019 Hydro Final
12/34
TYPES OF HYDRO TURBINES
S.No Turbine Type Features
1 Pelton
Used for high head (300 m & above) & low discharge
Water passes through nozzles and strikes spoon-shaped
buckets arranged on the periphery of a wheel
2 Francis
Variety of heads (30 m to 600 m) & medium discharge
Guide vanes direct the water tangentially to the turbinewheel, water enters the wheel and exits it in the middle
Guide vanes can be adjusted to optimise output & efficiency
Most commonly used
3 Kaplan Used for low (10 m to 80 m) heads & high discharge
Turbine selection done based on operating head & discharge required
Other turbine types like Bulb turbines, tubular turbines & reversible Francis also used
7/28/2019 Hydro Final
13/34
1
3
HYDRO SCENARIO IN INDIACURRENT ECOSYSTEM FOR HYDRO POWER IN INDIA
7/28/2019 Hydro Final
14/34
INDIAS INSTALLED CAPACITY
S.No Fuel
Installed
Capacity
(MW)
%
ShareRemarks
1 Thermal - Coal 1,30,371 67%Fuel shortage, reluctance to import due to
power becoming costlier
2 Thermal - Gas 20,110 10% Dwindling gas supplies- no gas projectsplanned till 2015-16
3 Hydro 39,623 20%Huge potential exists- underdeveloped
Problems of clearances, R&R etc exist
4 Nuclear 4,780 3% Public perception negative regarding safety
TOTAL 1,94,884
Given the increased focus on renewables & impact on climate, imperative to
expeditiously develop hydro power & increase its share in nations generation
(contributes only 16% generation of nations generation)
7/28/2019 Hydro Final
15/34
EVOLUTION OF HYDRO POWER OVER THE YEARS
S.
No Plan Period
Total Capacity at
the end of Plan(MW)
Hydro Capaci
ty at the end
of Plan
(MW)
% Share
1 4th Plan 1969-74 14988 7140 48
2 5th Plan 1974-79 23542 10672 45
3 Annual Plan 1979-80 25859 11269 44
4 6th Plan 1980-85 40950 14457 35
5 7th Plan 1985-90 62043 18125 29
6 Annual Plan 1990-92 67969 18808 28
7 8th Plan 1992-97 84783 21422 25
8 9th Plan 1997-02 104188 26186 25
9 10th Plan 2002-07 132330 34654 26
10 11th Plan 2007-12 187294 38990 21
7/28/2019 Hydro Final
16/34
CAPACITY PLANNED FOR XIIIth PLAN
S.
No Fuel
Capacity
(MW) Remarks
1 Thermal - Coal63,400
Under question due to fuel constraints,
environmental impact2 Thermal - Gas
3 Hydro 12,000 Potential for increase exists problems of clearances, R&R etc. to be sorted
4 Nuclear 18,000Safety issue, slow progress of Nuclear parks p
utting the same under question
TOTAL 93,400
As per Working Group on Power report, Feasible hydro capacity addition of 12,000 MW and
nuclear capacity addition of 18,000 MW has been considered as must run during 13th Plan
With thermal fuel constraints & nuclear safety concerns, hydro remains only feasible avenue for
increase in capacity addition
7/28/2019 Hydro Final
17/34
MARKET POTENTIAL AVAILABLE
S.
No Category
Capacity
(GW) Remarks
1 Installed 39
2 Under Construction 12
Projects in these categories to be acceleratedfor achievement of 12th & 13th Plan targets
3 DPR Approved 13
4 DPR Under Approval 13
5 Stand Awarded 37
6 Yet to be Awarded 39
TOTAL 153 GW
Issues of projects for benefit of 12th & 13th Plan to be resolved before addressing concerns
for balance projects
7/28/2019 Hydro Final
18/34
MARKET POTENTIAL AVAILABLE- BASIN WISE
S.
NoRiver Basin
Capacity
(MW)
Potential at 60% PLF
(MW)
1 Indus 33832 19988
2 Ganga 20711 10715
3 Central Indian rivers 4152 2740
4 West flowing 9430 6149
5 East flowing 14511 9532
6 Brahmaputra 66065 34920
TOTAL 148701 84044
Only 16% of identified potential developed. Market potential of 71 GW still exists
(excluding Pump Storage)
7/28/2019 Hydro Final
19/34
MAJOR PLAYERS ALONGWITH BHEL
INDIAN SUPERCRITICAL
POWER MARKET
BHEL
VOITH SIEMENS
ANDRITZ ALSTOMINDIANHYDRO POWER
MARKET(Rangit 120 MW,
Kashang 195 MW,
Pare 110 MW)
(Singoli Bhatwari 99 MW,
Rongnichu 96 MW,
Sainz 100 MW)
(Teesta VI 500 MW, Jorethang
Loop 96 MW, Bhasmey 55
MW, Tidong I 100 MW,
Phatabayang 76 MW, Tehri
1000 MW, Ratle 850 MW)
(Kishanganga 330 MW,
Lata Tapovan 171 MW)
7/28/2019 Hydro Final
20/34
HYDRO MARKET SHARE (2009-12)
COMPANY 2009-10 2010-11 2011-12 2012-13 TOTAL
BHEL330 MW
(35%)
171 MW
(17%)
501 MW
(12%)
ANDRITZ120 MW
(12%)
305 MW
(33%)
425 MW
(10%)
ALSTOM500 MW
(53%)
523 MW
(56%)
1096 MW
(85%)
850 MW
(83%)
2969 MW
(71%)
VOITH
SIEMENS
99 MW
(11%)
196 MW
(15%)
295 MW
(7%)
TOTAL 950 MW 927 MW 1292 MW 1021 MW 4190 MW
7/28/2019 Hydro Final
21/34
ISSUE STATUS
INCREASED
COMPETITION
Foreign suppliers set up manufacturing base in India (Andritz Hydro, Voith &
Alstom)
Preference for foreign manufacturers shown by private developers (BHEL share
only 26% in 11th Plan orders placed by IPPs)- ordering on firm basis
Chinese also started participating in tenders
MARKET SCENARIO - HYDRO
MARKET
POTENTIAL
Huge market potential with close to 1,00,000 MW potential assessed in thesegment
Segment in focus keeping in mind the fuel situation in non-renewable sources
Increased focus on EPC tenders (~2,000 MW tenders in the market)
BHEL share falling down from 40% in 11th Plan to 12% in 12th Plan
7/28/2019 Hydro Final
22/34
ISSUE STATUS
REFERENCE
FOR MEETING
QR
(FRANCIS
TURBINES)
4 x 150 MW Ranjit Sagar: Cannot be used any more as machine commissioned
more than 10 yrs ago
3x135 MW Ranganadi, 8x125 MW Indira Sagar: Can be used for qualification of
projects upto 165 MW capacity
Qualification an issue for 4x194 MW Luhri, 7x307 MW Etalin as per present QR
issued
Qualification for 4x205 MW Ratle managed after relaxation by developer
Need to commission projects like Koldam, Parbati III & Kameng at the earliest
REFERENCE
FOR MEETING
QR
(PELTON
TURBINES &HYDRO
GENERATOR)
BHEL can qualify to quote upto 212.5 MW only on base of 6x170 MW Tala project
commissioned in Feb, 2007
For qualification in projects upto 250 MW capacity, Parbati II to be commissioned
at the earliest
QUALIFICATION A BIG HURDLE
7/28/2019 Hydro Final
23/34
2
3
BUSINESS DRIVERS
CHOICES SHAPING BUSINESS FOR TODAY AND THE FUTURE
7/28/2019 Hydro Final
24/34
KEY ISSUES-AFFECTING ORDERING OF HYDRO PROJECTS
InternationalWater treaties Longgestationperiod
Large financialcommitmentwith nobankability ofreturns
R&R IssuesEnvironmentalClearanceLaw & Ordersituation/Terrorist threat
Logistical/InfrastructureRoadblocks
Limited linksbetween NEGrid & NationalGrid
Poor Healthof SEBs
7/28/2019 Hydro Final
25/34
STEPS TAKEN BY GOVERNMENT
STEP DESCRIPTION
50, 000 MW
Initiative
Govt. identified hydro scheme of 50,000 MW in may
2003.
PFRs of all 162 have been prepared.
Incentives to
DevelopersLower interest rates for financing offered to developers
Cabinet Committee
on Investment
Set up to fast track large investment projects
Many hydro projects cleared in meeting held in May
Basin wise EIA
studies
Changing basis of EIA studies from basin wise to sub-basin
wise in order to enhance potential
Standardization of
SpecsStandard specs for Hydro projects developed by CEA
Transmission
Systems
Transmission system planning by Power Grid to be done in
accordance with status of DPRs of hydro projects esp. in
North East India
CEA central
advisory body for
Hydro
CEA appointed central advisory body to cater to all issues
pertaining to development of hydro projects from concept
to commissioning
Agreement with
Bhutan
5,000 MW of hydro power from Bhutan by 2020 signed-
market potential further augmented
Govt. looking
to address
issues
concerning
Hydro
business
7/28/2019 Hydro Final
26/34
BIDS ALREADY SUBMITTED - STATUS
S.
No Project
Scope /
Rating
Price Openi
ng / Bid Su
bmission D
ate
Results
Reasons for delay
in ordering
1 KSK Dibbin2x60 MW
(E&M)Nov, 2011
L1- BHEL
L2- Alstom
Forest Clearance,
Land acquisition,
Financial Closure
2SEW Infra
Nafra HEP
2x60 MW
(E&M)Sept, 2011 Bid not opened
Environment
clearance awaited
3Patel
Gongri
2x72 MW
(EPC)Jan, 2012 Bid not opened Financial Closure
4
CVPPPL
Pakaldul
4x250 MW
(EPC) April, 2012Technical evaluati
on in progress PIB Clearance
5CHPLLP
Gulu
2x 12 MW
(E&M)Aug, 2012 Bid not opened Project on hold
7/28/2019 Hydro Final
27/34
BIDS ALREADY SUBMITTED - STATUS
S.
No Project
Scope /
Rating
Price Openi
ng / Bid Su
bmission D
ate
Results
Reasons for delay
in ordering
6UJVNL
Vyasi
2 x 60 MW
(E&M)Aug, 2012 Bid not opened
Environment
clearance, Financial
Closure
7
JKSPDC
New
Ganderbal
3 x 31 MW
(EPC)April, 2012 Bid not opened
Bids of 3154 MW already submitted & ordering not yet done
7/28/2019 Hydro Final
28/34
KEY ISSUES-AFFECTING EXECUTION OF HYDRO PROJECTS
Inter StateDisputes
Huge financialcommitmentwith noguarantee ofrevenue
Long executioncycle resultingin cost overrun
R&R IssuesEnvironmentalClearanceEnvironmentalConditions
LogisticalRoadblocks Non availabilityof skilledmanpower
Revenue infixed termswhile costs inPVC
7/28/2019 Hydro Final
29/34
EXECUTION PERIOD OF HYDRO PROJECTS
S.
NoProject Rating Zero Date
Commissioning
Schedule
(Unit 1)
Months Elapsed
1 Mukerian 2x9 MW June, 2004 21 months 108 months
2 Koldam 4x200 MW July, 2004 48 months 107 months
3 Kameng 3x150 MW Dec, 2004 46 months 102 months
4 TLDP 4 x 40 MW May, 2007 33 months 73 months
5Tapovan
Vishnugarh4 x 130 MW Jan, 2008 43 months 65 months
7/28/2019 Hydro Final
30/34
KEY ISSUES-AFFECTING BHEL COMPETITIVENESS IN HYDRO
Non optimaldesigns/ Highturbineweights
Competitorshaving localmanufacturingbase
Price Estimatesnot aligned tomarket levels
Quality ofBHELsuppliesHigh E&C,BoP prices
Development ofRunner Profiles
QualifyingRequirements Civil/EPCPre-bid tie up
Loading dueto technicalparameters
7/28/2019 Hydro Final
31/34
3
1
STRATEGIES TO BE ADOPTED
MOVES ENABLING US TO WIN THE GAME
7/28/2019 Hydro Final
32/34
SIX PRIORITY AREAS IDENTIFIED
Tech Tie-up
on case to
case basis
Optimisation of
Design
QualityControl
Increasing RunnerProfile database
AligningEstimates to
Market levels
QualificationCriteria
1
2
34
56
Task force set up to look into best practices
available in market
Turbine weights reduced considerably
No dispatch without inspection
Attempt to minimize rework at site
Advance action being taken for
developing new runner profilesReview of estimates along with Units
/ Regions to meet market levels
Commissiong of Parbati II to
create reference for upto 250 MW
7/28/2019 Hydro Final
33/34
1. Reduction of number of BOP agencies within BHEL.
2. Maximizing orders from Centre / State sectors by various
routes like orders on negotiated basis / JVs
3. Time bound program to improve quality-measurable
milestones
4. Timely, complete and Sequential supply of equipment
5. Take special measures to reduce cost of input material by
developing alternative vendors (including Chinese vendors).
6. Make or buy analysis for cost reduction.
Key ini t iat ives helping in achievement o f targets
KEY INITIATIVES TO BE TAKEN
7/28/2019 Hydro Final
34/34
3
4
Thank you for your attention