+ All Categories
Home > Documents > Hydro Final

Hydro Final

Date post: 03-Apr-2018
Category:
Upload: mansiagrawal
View: 218 times
Download: 0 times
Share this document with a friend

of 34

Transcript
  • 7/28/2019 Hydro Final

    1/34

    ISSUES &

    STRATEGIES FOR

    ENHANCING BHEL

    HYDRO BUSINESS

  • 7/28/2019 Hydro Final

    2/34

    Hydro Scenario in the World

    ++++ Hydro Scenario in IndiaBHEL Current Share in BusinessBusiness Potential Available

    AGENDA FOR THE DAY

    Customer Expectations & Priorities+ Present Issues- BHEL v/s Competitors+ Issues for Future Business+ Strategies to Increase Competitiveness

    New Ways to Enhance Business

  • 7/28/2019 Hydro Final

    3/34

    HYDRO

    WORLD SCENARIO

    TRENDS SEEN AROUND THE GLOBE

  • 7/28/2019 Hydro Final

    4/34

    FUEL WISE GENERATION OVER THE YEARS

    Used in 159 countries-provides 16% of worlds electricity

    4.8%

  • 7/28/2019 Hydro Final

    5/34

    HYDRO GENERATION OVER THE YEARS

    Slowdown due to local &

    international controversies

    over large dams

    52%

    High growth era ushered in

    particularly by rapid growth

    in China

    Hydro Installed capacity worldwide reached 1000 GW by 2010 end

    (Current annual growth rate of 2.5% owing to huge base)

  • 7/28/2019 Hydro Final

    6/34

    SKEWED DISTRIBUTION OF HYDRO POWER

    India is sixth largest generator of hydro power3.7 % of world generation

    11.5%

    10.7%

    9.3%

    18.7%

    30%

    4 countries accountfor 50% of world

    generation

    10 countries account for 70% ofworld generation

  • 7/28/2019 Hydro Final

    7/34

    UNDEVELOPED POTENTIAL AVAILABLE

  • 7/28/2019 Hydro Final

    8/34

    HYDRO GENERATION FORECAST

    India & China expected to take the lead in hydro generation GoI launched 50,000

    MW initiative in 2003

  • 7/28/2019 Hydro Final

    9/34

    OVERVIEWOF HYDRO PLANTS

    INTRODUCTION TO VARIOUS HYDRO SYSTEMS

  • 7/28/2019 Hydro Final

    10/34

  • 7/28/2019 Hydro Final

    11/34

    TYPES OF HYDRO POWER STATIONS

    Sl.No Type of Plant Features

    1Run of River

    (RoR)

    Harnesses energy from mainly the available flow of

    the river

    May include short term storage or pondage for flexibility in

    adapting to load demand profile

    Generation profile driven by natural river flow conditions

    2 Reservoir

    Water stored in artificially created reservoirs by makingdams or natural reservoirs

    Water storage provides greater flexibility to match

    generation with demand & reduce dependence on river flow

    Small reservoir HPP can serve as base plant & large ones as

    peaking plants

    3Pumped

    Storage

    Water pumped from lower reservoir to upper reservoir

    when supply exceeds demand

    When demand increases, water released from upper

    reservoir to flow back through turbines & generate power

    Effective electricity storage

  • 7/28/2019 Hydro Final

    12/34

    TYPES OF HYDRO TURBINES

    S.No Turbine Type Features

    1 Pelton

    Used for high head (300 m & above) & low discharge

    Water passes through nozzles and strikes spoon-shaped

    buckets arranged on the periphery of a wheel

    2 Francis

    Variety of heads (30 m to 600 m) & medium discharge

    Guide vanes direct the water tangentially to the turbinewheel, water enters the wheel and exits it in the middle

    Guide vanes can be adjusted to optimise output & efficiency

    Most commonly used

    3 Kaplan Used for low (10 m to 80 m) heads & high discharge

    Turbine selection done based on operating head & discharge required

    Other turbine types like Bulb turbines, tubular turbines & reversible Francis also used

  • 7/28/2019 Hydro Final

    13/34

    1

    3

    HYDRO SCENARIO IN INDIACURRENT ECOSYSTEM FOR HYDRO POWER IN INDIA

  • 7/28/2019 Hydro Final

    14/34

    INDIAS INSTALLED CAPACITY

    S.No Fuel

    Installed

    Capacity

    (MW)

    %

    ShareRemarks

    1 Thermal - Coal 1,30,371 67%Fuel shortage, reluctance to import due to

    power becoming costlier

    2 Thermal - Gas 20,110 10% Dwindling gas supplies- no gas projectsplanned till 2015-16

    3 Hydro 39,623 20%Huge potential exists- underdeveloped

    Problems of clearances, R&R etc exist

    4 Nuclear 4,780 3% Public perception negative regarding safety

    TOTAL 1,94,884

    Given the increased focus on renewables & impact on climate, imperative to

    expeditiously develop hydro power & increase its share in nations generation

    (contributes only 16% generation of nations generation)

  • 7/28/2019 Hydro Final

    15/34

    EVOLUTION OF HYDRO POWER OVER THE YEARS

    S.

    No Plan Period

    Total Capacity at

    the end of Plan(MW)

    Hydro Capaci

    ty at the end

    of Plan

    (MW)

    % Share

    1 4th Plan 1969-74 14988 7140 48

    2 5th Plan 1974-79 23542 10672 45

    3 Annual Plan 1979-80 25859 11269 44

    4 6th Plan 1980-85 40950 14457 35

    5 7th Plan 1985-90 62043 18125 29

    6 Annual Plan 1990-92 67969 18808 28

    7 8th Plan 1992-97 84783 21422 25

    8 9th Plan 1997-02 104188 26186 25

    9 10th Plan 2002-07 132330 34654 26

    10 11th Plan 2007-12 187294 38990 21

  • 7/28/2019 Hydro Final

    16/34

    CAPACITY PLANNED FOR XIIIth PLAN

    S.

    No Fuel

    Capacity

    (MW) Remarks

    1 Thermal - Coal63,400

    Under question due to fuel constraints,

    environmental impact2 Thermal - Gas

    3 Hydro 12,000 Potential for increase exists problems of clearances, R&R etc. to be sorted

    4 Nuclear 18,000Safety issue, slow progress of Nuclear parks p

    utting the same under question

    TOTAL 93,400

    As per Working Group on Power report, Feasible hydro capacity addition of 12,000 MW and

    nuclear capacity addition of 18,000 MW has been considered as must run during 13th Plan

    With thermal fuel constraints & nuclear safety concerns, hydro remains only feasible avenue for

    increase in capacity addition

  • 7/28/2019 Hydro Final

    17/34

    MARKET POTENTIAL AVAILABLE

    S.

    No Category

    Capacity

    (GW) Remarks

    1 Installed 39

    2 Under Construction 12

    Projects in these categories to be acceleratedfor achievement of 12th & 13th Plan targets

    3 DPR Approved 13

    4 DPR Under Approval 13

    5 Stand Awarded 37

    6 Yet to be Awarded 39

    TOTAL 153 GW

    Issues of projects for benefit of 12th & 13th Plan to be resolved before addressing concerns

    for balance projects

  • 7/28/2019 Hydro Final

    18/34

    MARKET POTENTIAL AVAILABLE- BASIN WISE

    S.

    NoRiver Basin

    Capacity

    (MW)

    Potential at 60% PLF

    (MW)

    1 Indus 33832 19988

    2 Ganga 20711 10715

    3 Central Indian rivers 4152 2740

    4 West flowing 9430 6149

    5 East flowing 14511 9532

    6 Brahmaputra 66065 34920

    TOTAL 148701 84044

    Only 16% of identified potential developed. Market potential of 71 GW still exists

    (excluding Pump Storage)

  • 7/28/2019 Hydro Final

    19/34

    MAJOR PLAYERS ALONGWITH BHEL

    INDIAN SUPERCRITICAL

    POWER MARKET

    BHEL

    VOITH SIEMENS

    ANDRITZ ALSTOMINDIANHYDRO POWER

    MARKET(Rangit 120 MW,

    Kashang 195 MW,

    Pare 110 MW)

    (Singoli Bhatwari 99 MW,

    Rongnichu 96 MW,

    Sainz 100 MW)

    (Teesta VI 500 MW, Jorethang

    Loop 96 MW, Bhasmey 55

    MW, Tidong I 100 MW,

    Phatabayang 76 MW, Tehri

    1000 MW, Ratle 850 MW)

    (Kishanganga 330 MW,

    Lata Tapovan 171 MW)

  • 7/28/2019 Hydro Final

    20/34

    HYDRO MARKET SHARE (2009-12)

    COMPANY 2009-10 2010-11 2011-12 2012-13 TOTAL

    BHEL330 MW

    (35%)

    171 MW

    (17%)

    501 MW

    (12%)

    ANDRITZ120 MW

    (12%)

    305 MW

    (33%)

    425 MW

    (10%)

    ALSTOM500 MW

    (53%)

    523 MW

    (56%)

    1096 MW

    (85%)

    850 MW

    (83%)

    2969 MW

    (71%)

    VOITH

    SIEMENS

    99 MW

    (11%)

    196 MW

    (15%)

    295 MW

    (7%)

    TOTAL 950 MW 927 MW 1292 MW 1021 MW 4190 MW

  • 7/28/2019 Hydro Final

    21/34

    ISSUE STATUS

    INCREASED

    COMPETITION

    Foreign suppliers set up manufacturing base in India (Andritz Hydro, Voith &

    Alstom)

    Preference for foreign manufacturers shown by private developers (BHEL share

    only 26% in 11th Plan orders placed by IPPs)- ordering on firm basis

    Chinese also started participating in tenders

    MARKET SCENARIO - HYDRO

    MARKET

    POTENTIAL

    Huge market potential with close to 1,00,000 MW potential assessed in thesegment

    Segment in focus keeping in mind the fuel situation in non-renewable sources

    Increased focus on EPC tenders (~2,000 MW tenders in the market)

    BHEL share falling down from 40% in 11th Plan to 12% in 12th Plan

  • 7/28/2019 Hydro Final

    22/34

    ISSUE STATUS

    REFERENCE

    FOR MEETING

    QR

    (FRANCIS

    TURBINES)

    4 x 150 MW Ranjit Sagar: Cannot be used any more as machine commissioned

    more than 10 yrs ago

    3x135 MW Ranganadi, 8x125 MW Indira Sagar: Can be used for qualification of

    projects upto 165 MW capacity

    Qualification an issue for 4x194 MW Luhri, 7x307 MW Etalin as per present QR

    issued

    Qualification for 4x205 MW Ratle managed after relaxation by developer

    Need to commission projects like Koldam, Parbati III & Kameng at the earliest

    REFERENCE

    FOR MEETING

    QR

    (PELTON

    TURBINES &HYDRO

    GENERATOR)

    BHEL can qualify to quote upto 212.5 MW only on base of 6x170 MW Tala project

    commissioned in Feb, 2007

    For qualification in projects upto 250 MW capacity, Parbati II to be commissioned

    at the earliest

    QUALIFICATION A BIG HURDLE

  • 7/28/2019 Hydro Final

    23/34

    2

    3

    BUSINESS DRIVERS

    CHOICES SHAPING BUSINESS FOR TODAY AND THE FUTURE

  • 7/28/2019 Hydro Final

    24/34

    KEY ISSUES-AFFECTING ORDERING OF HYDRO PROJECTS

    InternationalWater treaties Longgestationperiod

    Large financialcommitmentwith nobankability ofreturns

    R&R IssuesEnvironmentalClearanceLaw & Ordersituation/Terrorist threat

    Logistical/InfrastructureRoadblocks

    Limited linksbetween NEGrid & NationalGrid

    Poor Healthof SEBs

  • 7/28/2019 Hydro Final

    25/34

    STEPS TAKEN BY GOVERNMENT

    STEP DESCRIPTION

    50, 000 MW

    Initiative

    Govt. identified hydro scheme of 50,000 MW in may

    2003.

    PFRs of all 162 have been prepared.

    Incentives to

    DevelopersLower interest rates for financing offered to developers

    Cabinet Committee

    on Investment

    Set up to fast track large investment projects

    Many hydro projects cleared in meeting held in May

    Basin wise EIA

    studies

    Changing basis of EIA studies from basin wise to sub-basin

    wise in order to enhance potential

    Standardization of

    SpecsStandard specs for Hydro projects developed by CEA

    Transmission

    Systems

    Transmission system planning by Power Grid to be done in

    accordance with status of DPRs of hydro projects esp. in

    North East India

    CEA central

    advisory body for

    Hydro

    CEA appointed central advisory body to cater to all issues

    pertaining to development of hydro projects from concept

    to commissioning

    Agreement with

    Bhutan

    5,000 MW of hydro power from Bhutan by 2020 signed-

    market potential further augmented

    Govt. looking

    to address

    issues

    concerning

    Hydro

    business

  • 7/28/2019 Hydro Final

    26/34

    BIDS ALREADY SUBMITTED - STATUS

    S.

    No Project

    Scope /

    Rating

    Price Openi

    ng / Bid Su

    bmission D

    ate

    Results

    Reasons for delay

    in ordering

    1 KSK Dibbin2x60 MW

    (E&M)Nov, 2011

    L1- BHEL

    L2- Alstom

    Forest Clearance,

    Land acquisition,

    Financial Closure

    2SEW Infra

    Nafra HEP

    2x60 MW

    (E&M)Sept, 2011 Bid not opened

    Environment

    clearance awaited

    3Patel

    Gongri

    2x72 MW

    (EPC)Jan, 2012 Bid not opened Financial Closure

    4

    CVPPPL

    Pakaldul

    4x250 MW

    (EPC) April, 2012Technical evaluati

    on in progress PIB Clearance

    5CHPLLP

    Gulu

    2x 12 MW

    (E&M)Aug, 2012 Bid not opened Project on hold

  • 7/28/2019 Hydro Final

    27/34

    BIDS ALREADY SUBMITTED - STATUS

    S.

    No Project

    Scope /

    Rating

    Price Openi

    ng / Bid Su

    bmission D

    ate

    Results

    Reasons for delay

    in ordering

    6UJVNL

    Vyasi

    2 x 60 MW

    (E&M)Aug, 2012 Bid not opened

    Environment

    clearance, Financial

    Closure

    7

    JKSPDC

    New

    Ganderbal

    3 x 31 MW

    (EPC)April, 2012 Bid not opened

    Bids of 3154 MW already submitted & ordering not yet done

  • 7/28/2019 Hydro Final

    28/34

    KEY ISSUES-AFFECTING EXECUTION OF HYDRO PROJECTS

    Inter StateDisputes

    Huge financialcommitmentwith noguarantee ofrevenue

    Long executioncycle resultingin cost overrun

    R&R IssuesEnvironmentalClearanceEnvironmentalConditions

    LogisticalRoadblocks Non availabilityof skilledmanpower

    Revenue infixed termswhile costs inPVC

  • 7/28/2019 Hydro Final

    29/34

    EXECUTION PERIOD OF HYDRO PROJECTS

    S.

    NoProject Rating Zero Date

    Commissioning

    Schedule

    (Unit 1)

    Months Elapsed

    1 Mukerian 2x9 MW June, 2004 21 months 108 months

    2 Koldam 4x200 MW July, 2004 48 months 107 months

    3 Kameng 3x150 MW Dec, 2004 46 months 102 months

    4 TLDP 4 x 40 MW May, 2007 33 months 73 months

    5Tapovan

    Vishnugarh4 x 130 MW Jan, 2008 43 months 65 months

  • 7/28/2019 Hydro Final

    30/34

    KEY ISSUES-AFFECTING BHEL COMPETITIVENESS IN HYDRO

    Non optimaldesigns/ Highturbineweights

    Competitorshaving localmanufacturingbase

    Price Estimatesnot aligned tomarket levels

    Quality ofBHELsuppliesHigh E&C,BoP prices

    Development ofRunner Profiles

    QualifyingRequirements Civil/EPCPre-bid tie up

    Loading dueto technicalparameters

  • 7/28/2019 Hydro Final

    31/34

    3

    1

    STRATEGIES TO BE ADOPTED

    MOVES ENABLING US TO WIN THE GAME

  • 7/28/2019 Hydro Final

    32/34

    SIX PRIORITY AREAS IDENTIFIED

    Tech Tie-up

    on case to

    case basis

    Optimisation of

    Design

    QualityControl

    Increasing RunnerProfile database

    AligningEstimates to

    Market levels

    QualificationCriteria

    1

    2

    34

    56

    Task force set up to look into best practices

    available in market

    Turbine weights reduced considerably

    No dispatch without inspection

    Attempt to minimize rework at site

    Advance action being taken for

    developing new runner profilesReview of estimates along with Units

    / Regions to meet market levels

    Commissiong of Parbati II to

    create reference for upto 250 MW

  • 7/28/2019 Hydro Final

    33/34

    1. Reduction of number of BOP agencies within BHEL.

    2. Maximizing orders from Centre / State sectors by various

    routes like orders on negotiated basis / JVs

    3. Time bound program to improve quality-measurable

    milestones

    4. Timely, complete and Sequential supply of equipment

    5. Take special measures to reduce cost of input material by

    developing alternative vendors (including Chinese vendors).

    6. Make or buy analysis for cost reduction.

    Key ini t iat ives helping in achievement o f targets

    KEY INITIATIVES TO BE TAKEN

  • 7/28/2019 Hydro Final

    34/34

    3

    4

    Thank you for your attention


Recommended