I-394 MnPASS Express Lanes Project Update. Guidestar Board Meeting September 7th, 2005. Project Update. Customer Service Center Opened April 11 th MnPASS Express Lane Opened May 16 th. What is Working. Dynamic Pricing Speeds are being maintained - PowerPoint PPT Presentation
13
I-394 MnPASS Express Lanes Project Update Guidestar Board Meeting Guidestar Board Meeting September 7th, 2005 September 7th, 2005
Transcript
Page 1: I-394 MnPASS Express Lanes Project Update

I-394 MnPASS Express Lanes

Project UpdateGuidestar Board MeetingGuidestar Board Meeting

September 7th, 2005September 7th, 2005

Page 2: I-394 MnPASS Express Lanes Project Update

Project Update• Customer Service Center– Opened April 11th

• MnPASS Express Lane– Opened May 16th

Page 3: I-394 MnPASS Express Lanes Project Update

What is Working

• Dynamic Pricing– Speeds are being maintained– Transit reports no impact on operations

• Enforcement– Very low violation rate– Technology aiding in enforcement

• Access points– Relatively low violation of striping

• Customer Service– Satisfaction with usability of system and reasonable

pricing

Page 4: I-394 MnPASS Express Lanes Project Update

Operations Changes

• Hours changed for Diamond Lane– Changed on June 9th – AM: Tolled Eastbound 6 AM to 10 AM– PM: Tolled Westbound 2 PM to 7 PM– Reversible road section always tolled for SOVs

• Auxiliary lane construction– Westbound from Hwy 100 to Hwy 169– Two lane exit to Hwy 169/General Mills– Started August 22nd, complete late November

Page 5: I-394 MnPASS Express Lanes Project Update

Transponder Leases

-

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

Opening Day

Page 6: I-394 MnPASS Express Lanes Project Update

Tolled Trips per Week

-2,0004,0006,0008,000

10,00012,00014,00016,00018,00020,000

May

16t

h

May

30t

h

June

13t

h

June

27t

h

July

11th

July

25th

Aug 8

th

Aug 2

2nd

Page 7: I-394 MnPASS Express Lanes Project Update

Average Toll Paid by Week

$-

$0.10

$0.20

$0.30

$0.40

$0.50

$0.60

$0.70

$0.80

$0.90

May

16t

h

May

30t

h

June

13t

h

June

27t

h

July

11th

July

25th

Aug 8

th

Aug 2

2nd

Page 8: I-394 MnPASS Express Lanes Project Update

Weekly Tolls Collected

$-

$2,000

$4,000

$6,000

$8,000

$10,000

$12,000

$14,000

May

16t

h

May

30t

h

June

13t

h

June

27t

h

July

11th

July

25th

Aug 8

th

Aug 2

2nd

Page 9: I-394 MnPASS Express Lanes Project Update

Enforcement• Violations

– HOV violations very low– Double white line violation rate

is very low– “No violation” stops a challenge– Traffic flow not being impacted– Enforcing/assisting other events

• Technology is key– Mobile readers a first– Beacons a deterrent

Page 10: I-394 MnPASS Express Lanes Project Update

Customer Response• Favorable feedback from customers• Transponder leases

– Leasing 92 per week since beginning of July– 1% account cancellation rate

• 90% of sign ups are web based• Most frequent customer interaction:

– “What’s my PIN number?”

Page 11: I-394 MnPASS Express Lanes Project Update

Next Steps• Finish westbound auxiliary lane

• Continue to market the system to new users

• Data collection for Evaluation

• Winter Operations

Page 12: I-394 MnPASS Express Lanes Project Update

How to Subscribe• Online

– www.mnpass.net

• By phone – 1-866-397-4334

• In person – Customer Service Center, 2055 N. Lilac

Drive, Golden Valley

Page 13: I-394 MnPASS Express Lanes Project Update

Questions and More InformationVisit www.mnpass.net

Contact Nick Thompson, Project Manager

651-634-5310

[email protected]