+ All Categories
Home > Documents > I-405 Sepulveda Pass Improvements...

I-405 Sepulveda Pass Improvements...

Date post: 29-Sep-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
62
I-405 Sepulveda Pass Improvements Project Community Meeting August 15, 2013 1
Transcript
Page 1: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

I-405 Sepulveda Pass Improvements ProjectCommunity Meeting August 15, 2013

1

Page 2: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

2

Mulholland Segment

Page 3: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

• Sound wall construction along southbound Valley Vista ramps is complete

• Traffic switch in September will create space for construction along the freeway.

• Final configuration of Valley Vista on-ramp will have three lanes

• Southbound Valley Vista on-ramp traffic was switched in June

Sherman Oaks and Valley Vista Work

3

TaskComplete

(%)

Sepulveda Undercrossing (near Valley Vista)

65

Valley Vista SB On-Ramp 80

Page 4: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sherman Oaks and Valley Vista Work

4

• Wednesday, August 21 and Thursday, August 22

• Sepulveda Bl will be fully closed between the northbound I-405 on-ramp from Getty Center Dr to the southbound off-ramp to and on-ramp from Getty Center Dr.

• Nighttime closures between 10PM to 5AM.

Deck pour for Bridge 19 occurs later this week

Page 5: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

• Upcoming construction of bridge deck, sound/retaining walls, and final drainage work; girders are installed

• Sepulveda Bl overpass/bridge widening ongoing until Fall 2013

Sepulveda Bl Overpass/ Bridge Widening

5

Nighttime lane reductions from 10pm-6am on Sepulveda Bl near bridge

Page 6: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

6

Sound Wall Construction—Sherman Oaks

Page 7: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Valley Vista Area Construction

7

Page 8: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Valley Vista Area Construction (Contd.)

8

More than just girders now, crews are working on building diaphragms. Sepulveda Bl can be seen to the right.

Page 9: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Valley Vista Area Construction (Contd.)

9

Retaining wall under construction along west side of southbound on-ramp from Valley Vista

Work on wing wall of Wall 23.

Page 10: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Mulholland Bridge (North Half ) Reconstruction

• Majority of bridge deck concrete pours are complete

• Anticipated occasional full closures of the Mulholland Bridge

• Anticipated completion of construction in late 2013

10

Removing false work on the Mulholland bridge requires full directional freeway closures from Valley Vista to Skirball, 11pm-9am.

Saturday, August 17: Southbound directional freeway closure

Saturday, August 24: Northbound directional freeway closure

Page 11: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

• Girders have been installed• NB freeway widening and NB ramps realignment ongoing• Anticipated completion of construction in late 2013

Skirball Bridge (South Half ) Reconstruction

11

Page 12: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

• Intermittent full Sepulveda Bl closures have begun and will last for 10 months

• Sepulveda Bl widening will allow addition of northbound auxiliary lane to Skirball Center Dr

• Widening of Sepulveda Bl (south of Skirball Bridge) will require frequent reduction of Sepulveda Bl from Mountaingate Dr to Skirball Center Dr.

• At times reductions will limit Sepulveda Bl to one northbound lane open from 10pm to 6am (southbound lanes will be closed). These intermittent closes are anticipated to last 10 months.

Sepulveda Bl Widening—Wall 1921

12

Page 13: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sepulveda Bl Widening—Wall 1921

13

Excavation, grading 50 percent complete

Page 14: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Southbound Skirball Ramps—Traffic Lanes

14

Page 15: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Completion of Skirball Southbound Ramps

15

Southbound I-405 off-ramp at Skirball Center Dr opening late 2013

Page 16: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Segment 3 Accomplishments—Last Quarter

16

Task Status

Complete Bridge 19 (Sepulveda Bloverpass north of Getty Center Dr)

Setting girders complete 6.17.13

Complete Bridge 21 (Skirball) Setting girders complete 6.21.13

Complete Bridge 22 (Mulholland) Top deck pour complete 7.1.13; false work removal 50 percent complete; false work anticipated to be complete end of August

Complete Bridge 23 Setting girders complete 6.21.13

Page 17: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Segment 3 Accomplishments—Last Quarter

17

Task Status

Valley Vista on-ramp Traffic switched 6.24.13

NB Getty Center Dr on-ramp Reopened 7.31.13

New sound wall at Valley Vista Completed 8.2.13

New 1985 sound wall (north of Mulholland Dr, along southbound lanes)

Seventy-five percent complete

Mass excavation along Sepulveda Bl Fifty percent complete

Page 18: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

18

Wilshire Segment

Page 19: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Northbound I-405 On-Rampfrom Eastbound Wilshire Bl

90-Day ClosureAugust 22

19

Page 20: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Wilshire Ramps Rendering

20N

Page 21: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Northbound Lane Opens

21

On June 9, a 2.7-mile segment of new lane opened from I-10 to Wilshire Bl.

Page 22: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Wilshire Segment—Extended Closures

Ramp Tentative DateMaximum Duration

(Days)

WB Wilshire on-ramp to NB I-405 Complete 90

NB I-405 off-ramp to WB Wilshire Complete 90

SB I-405 off-ramp to WB Wilshire Complete 14

WB Wilshire on-ramp to SB I-405 NOT NEEDED 14

NB I-405 off-ramp to EB Wilshire NOT NEEDED 21

EB Wilshire on-ramp to NB I-405 August 22 90

SB I-405 off-ramp to EB Wilshire NOT NEEDED 90

NB I-405 on-ramp at Olympic (Cotner) NOT NEEDED 21

SB I-405 off-ramp to Santa Monica NOT NEEDED 14

NB I-405 on-ramp from Santa Monica NOT NEEDED 7

SB on-ramp from Santa Monica NOT NEEDED 7

22

Page 23: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Wilshire Segment—90-Day Closure

The 90 day closure of the eastbound Wilshire Bl on-ramp to northbound I-405 is scheduled for August 22.

Existing ramp: 824 feetCompleted ramp: 3,129 feet280% increase in capacity

23

Page 24: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Wilshire Segment—90-Day Closure

24

During the 90-day closure, the existing northbound on-ramp from eastbound Wilshire (in the center of the photo) will be demolished.

Page 25: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

90-Day Closure-Existing Conditions

• Northbound I-405 off-ramp to eastbound Wilshire complete

• Olympic Bl on-ramp to northbound I-405 complete

• Santa Monica Bl on-ramp to northbound I-405 complete

• Northbound I-405 additional lane complete from I-10 to Wilshire Bl

• Demolition of the existing I-405 off-ramp to eastbound Wilshire complete

25

Page 26: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

90-Day Closure Work Overview

August 2013• Demolition of existing bridge

and abutments• Drive piles (Total of 10)• Erect false work

September 2013• Erect overhang, install rebar• Pour deck, cure time for false

work

October 2013• Strip False work• Sandblast, install conduit

26

The lower half of Bridge 8 curves to meet its northern half.

Page 27: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

90 Day Closure Map

27

Page 28: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

90-Day Closure—Detour Routes

Detour Route: Southbound Sepulveda Bl to westbound Santa Monica Bl to northbound I-405

Alternate Route: Southbound Sepulveda Bl to westbound Pico Bl to northbound Cotner Av to northbound I-405

Nighttime Route: Federal Av to Santa Monica Bl to NB on-ramp. Westwood Bl to Santa Monica Bl to NB on-ramp

28

Northern half of Bridge 8 curves to meet the I-405

Page 29: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

90-Day Closure—Temporary Measures

• Dedicated eastbound Wilshire right-turn lane to southbound Sepulveda Bl

• Extension of the right-turn pocket on southbound Sepulveda Bl to Santa Monica Bl

• Westbound Santa Monica 3 lane modified from dedicated through lane to shared through/right-turn lane. This will require the removal of the north side of crosswalk. Detour will be to the south side of crosswalk.

29

Page 30: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

• Optimized signal timing

• 24 Traffic Control Officers (TCO)s + 6 TCO Strike Teams for both closures

• Ramp meter modifications• Increase metering rate for northbound Olympic Bl on-ramp• Turn off the ramp meter for northbound Santa Monica Bl on-

ramp, Monday through Sunday from 2:30pm to 6:30pm

30

90-Day Closure—Temporary Measures

Page 31: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

• For Santa Monica Bl traffic relief, a sign providing an alternate route for Santa Monica Bl motorists will be posted.

• The contingency route will be northbound Westwood Bl to westbound Wilshire Bl to the northbound I-405 on-ramp.

90-Day Closure—Contingency Plan

31

Page 32: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Wilshire Segment—Bridge Status

32

Bridge Location Status (%)

1 I-10/Exposition Bl 95

2 Expo/Pico 80

3 Olympic Bl 95

4 Santa Monica Bl 95

5 Ohio Av 95

6 SB to EB Wilshire Off 95

7 NB to EB Wilshire Off 95

8 EB Wilshire to NB On 65

9 Wilshire Bl Undercrossing 95

10 NB to WB Wilshire Off 100

11 WB Wilshire to NB On 100

12 Constitution Av 95

Bridges 13 to 18 are in Segment 2Bridges 19 to 23 are in Segment 3

Page 33: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Wilshire Segment—Wall Update

33

Significant progress in retaining wall and sound wall work• Approximate total linear feet of retaining walls 17,375 ft.

• About 99% of this is complete

• Approximate total linear feet of sound walls 8,650 ft.• About 98% of this is complete

Page 34: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

• Continuation of top deck construction until the end of August

• Most of the work will take place during the day except for rebar installation and top deck pour. o Rebar installation: Sunday night, 8/11 to Friday night, 8/23.o Deck will be poured at night in the first week of September.

9pm to 5am:Pico Bl (Sawtelle to Cotner) and EB 10 connector to NB 405 closure needed during nightly work as noted above.

Wilshire Segment—Pico Bl

34

Page 35: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Demolition and reconstruction of curb, gutter, and sidewalk • EB Santa Monica Bl, Beloit to Cotner: Completed 8/9 - 8/12

• WB Santa Monica Bl, Cotner to Beloit: Will be 8/16-8/19:

o Day- 6am to 9pm: WB Santa Monica lane #3 closedo Night- 9pm to 6am: WB Santa Monica lanes 2, 3 closed,

NB on-ramp closed

Wilshire Segment—Santa Monica Bl

35

Page 36: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Demolition of asphalt, excavate/base roadway and pave new asphalt

• 2 lane on SB Sepulveda from Wilshire to 500 ft north of Wilshire

• 4 lane on WB Wilshire from 200 ft east to 200f ft west of Sepulveda Bl

• Continuous, starting Friday, August, 16h at 9pm to Sunday, August 18 at 5am

Westbound Wilshire NB on-ramp will not be impeded

Wilshire Segment—Wilshire Bl

36

Page 37: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

37

Sunset Segment

Page 38: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

38

NB I-405 Sunset Off-Ramp120-Day Closure

Underway

Page 39: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Prior Ramp Configuration• One northbound left-turn lane to

westbound Sunset• One northbound right-turn lane to

eastbound Sunset

Final Ramp Configuration• One northbound left-turn lane to

westbound Sunset• Two northbound right-turn lanes to

eastbound Sunset• Increased length and capacity by 60

percent

39

120-Day Closure—Reconstruction

Page 40: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—120-Day Closure

Completed Northbound I-405 Sunset Bl Off-Ramp

40

Page 41: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—120-Day Closure

Where the northbound off-ramp recently stood, workers excavate the remaining support structures on August 5 41

Page 42: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—120-Day Closure

Northbound I-405 Sunset Bl Off-Ramp Work Area

42

Abutment 1

Span 1Span 2

Span 3

Abutment 4

2 cranes

Wall 1738A

Bent 3Bent 2

Page 43: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

120-Day Closure—Detour Routes

Westbound Sunset Detour• NB I-405 off-ramp to westbound Wilshire Bl, to northbound Sepulveda Bl,

to eastbound Sepulveda Way, to westbound Sunset Bl• Alternate: Moraga Dr off-ramp, to southbound Sepulveda, right on

Church Ln to Sunset Bl (14’-2” height restriction at Church Bridge)

• NB I-405 off-ramp to westbound Wilshire Bl, right on northbound San Vicente Bl, right onto north Barrington Av, left onto westbound Sunset Bl

Eastbound Sunset Detour• NB I-405 off-ramp to eastbound Wilshire Bl, to northbound Veteran Av to

eastbound Sunset Bl

43

Page 44: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

120-Day Closure—Temporary Measures

• Since Monday 8/5, 24 traffic control officers (TCOs) were deployed to key locations during AM and PM peak hours throughout both closures plus six-TCO strike team to patrol and monitor entire area

• AM Peak Hours: 6:45am to 9:45am

• PM Peak Hours: 4 to 7pm

• Locations vary based on daily observations

• TCOs at key locations, such as Church & Sepulveda, Church & Sunset, Wilshire & Sepulveda will remain. Locations flexible based on observations

44

Page 45: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Implemented Throughout Entire Closure• Portable changeable message signs in use.

• Signal re-timing/coordination improvements.

• Adding a “closed” sign to the freeway overhead signs next to “Sunset” to encourage more drivers to use Wilshire.

• There are “Local Access Only” signs on several neighborhood streets to reduce cut thru traffic.

• Nighttime signage on a changeable message board that faces EB Moraga traffic exiting the NB Moraga off-ramp.

• Southbound Sepulveda traffic also sees a “Local Access Only” sign on the south side of the Bellagio/Moraga intersection facing EB traffic.

45

120-Day Closure—Ongoing Mitigations

Page 46: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Northbound Moraga Dr Off-ramp (alternate route)-Implemented on Aug. 9th• Lane 2 will be a dedicated right turn lane (currently shared with through)• Lane 1 will be a shared left and through lane (currently exclusive left turn)

Traffic patterns are being monitored for two weeks to allow adjustment prior to contingency plan recommendations.

Available Contingency Measure:Northbound Veteran Av and Eastbound Sunset Intersection• Right turn pocket onto eastbound Sunset will be extended 500 ft to

accommodate added volume

46

120-Day Closure—Contingency Measures

Page 47: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—120-Day Closure

Sunset Off-ramp ReconstructionAugust 2013• Demolish existing bridge, abutments, retaining wall- complete• Erect bent false work- in progress• Excavate for new abutments- complete• Initiate construction of footings at abutments- in progress• Backfill MSE Wall 1738A & Paving- in progress• Pile driving for abutment foundation- complete (ahead of schedule)

47

Page 48: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—120-Day Closure

Next Month’s Activities

September 2013• Continue construction of footings at

abutments; cure wall• Complete MSE Wall 1738A construction• Set girders• Install drainage and backfill at abutment• Initiate deck construction

48

The new northbound off-ramp points toward Sunset Bl

Page 49: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—120-Day Closure

October 2013• Continue construction of top deck & diaphragms• Initiate construction of approach slabs• Initiate cure of top deck, bents and diaphragm

November 2013• Finalize construction of approach slabs• Finalize cure of top deck, bents and diaphragm• Construct concrete barrier• Post tensioning & grouting• Remove false work• Stripe and tie-in at Sunset Bl

49

Page 50: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Public Outreach Strategy

• E-blasts

• Posted detour and alternative route maps

• Online and print advertising

• Go511 radio ads

• Changeable message signs

• Updates on Hotline, website, social media

50

Page 51: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Public Outreach Strategy

• Media and social media networking

• Briefing sessions to key stakeholder groups

• Metro Commute Services outreach

• Community meetings

51

Page 52: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Media Outreach Campaign—Key Messages

• Plan ahead to determine alternate routes• Make extra time to reach destinations• Eliminate unnecessary trips to avoid peak congestion

impacts• Work with employers to adjust work hours or telecommute

to avoid peak hour congestion• Work with Metro to find rideshare partners• Take public transit when possible

52

Page 53: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

• There are approximately 18,775 linear ft of retaining walls in the Sunset Segment

• 15,639 linear ft of retaining wall have been built

• This means that approximately 83% of all retaining wall for the Sunset segment has been built.

53

Sunset Segment—Retaining Wall Status

Approximately 83 percent of retaining walls in Sunset Segment have been built

Page 54: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

54

Sunset Segment—Bridge Status

Bridge LocationStatus

(%)13 Montana Undercrossing 95

14 NB Sunset Off-ramp 50

15 NB Sunset On-ramp 95

16 Sunset Bl Overcrossing 10017 Church Ln Undercrossing 5018 Getty Center Dr Undercrossing 95

Bridges 1 to 12 are in Segment 1; bridges 19 to 23 are in Segment 3

Page 55: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—Sepulveda/Montana

• Retaining wall construction from south of Cashmere to Montana.• Includes demolition of pre-existing retaining wall

(completed 8/8 and 8/9)• Erecting panels and soil compaction• Construction of sound wall upon completion of retaining

wall• Work hours: 9:00pm to 6am and 6am to 5pm

• Daytime lane closure only: 9am-3pm• Northernmost portion of wall will be completed after

Montana off-ramp is closed.

55

Page 56: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—Sepulveda/Homedale

• “Shotcrete” of retaining walls east of Sepulveda Bl, between Montana and Bronwood (walls 1720, 1730)• Consists of covering the façade of these walls

with concrete• Wall preparation, shotcrete, and finish:

• Started August 5, will continue to Friday, November 1

• Work hours are 10pm to 6am.• Requires full closure of Sepulveda Bl, 10pm

to 6am, Montana Av to Moraga Dr.

56

Page 57: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—Sepulveda Bl Closures

Required to facilitate NB Sunset off-ramp construction, 1720/30 wall façade finishing and adjacent retaining wall work.

One to One Lane ConfigurationMontana to Sepulveda Way9am-3pm

57

Page 58: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—Sepulveda/Church Ln

• Widening of Church Lane Bridge (ongoing):• August: Continue erecting false work, commencement of

top deck construction.• September: Finalize top deck construction, initiate false

work removal• Work is being conducted within ongoing nighttime closure of

Sepulveda Bl: Montana to Moraga, 10pm to 6am• Anticipated completion: End of February 2014• One to one lane configuration on Church Ln with temporary

height restriction of 14’-2”.

58

Page 59: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—Sepulveda/Moraga Dr

• Ongoing retaining wall construction.• Intermittent closures of on-ramp and off-ramp• Work involves demolition of pre-existing walls, excavation,

setting of wall panels and compaction.• Sound walls will be constructed atop retaining walls.

59

Page 60: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—Moraga Dr Ramps

NB Moraga On and Off-Ramp Permitted Closure Times

Monday to FridayNighttime: Moraga Off-Ramp- 7pm to 6am

Moraga On-Ramp- 8pm to 6amDaytime: Moraga Off-Ramp- 9am to 3pm

Moraga On-Ramp- 9am to 12pm

Saturday and SundayMoraga ramps can be closed at any time.

60

Page 61: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

Sunset Segment—Moraga Dr Wall Work

61

Page 62: I-405 Sepulveda Pass Improvements Projectmedia.metro.net/projects_studies/I405/images/community...2013/08/15  · 405 on-ramp from Getty Center Dr to the southbound off-ramp to and

For More Information

Project Hotline: (213) 922-3665

[email protected]

www.metro.net/I-405

www.facebook.com/I-405project

Twitter: http://twitter.com/I-405

62


Recommended