I-495 EXPRESS LANES
NORTHERN EXTENSION (495 NEXT)
LOCATION & DESIGN PUBLIC HEARING
Virginia Department of Transportation
October 5, 2020
Introductions and Opening Notes
Public Hearing includes a formal presentation of Environmental Assessment findings and
draft design plans.
Following presentation, public comment session to begin. Begin with pre-registered
speakers, followed by others wanting to provide comments.
Speakers limited to 3 minutes to speak as an individual and 5 minutes if speaking for a
group.
Question-and-answer session after public comment period, if time allows.
Tonight’s hearing is being recorded and streamed on VDOT Live on YouTube. Recording will
be posted after the meeting on 495NorthernExtension.org.
Attendees will be muted throughout duration of the meeting to minimize background noise
and ensure that all participants can hear.
Call 703-691-6715 if you have technical difficulties.
2
Welcome
Virginia Department of Transportation 2
Project Overview
Environmental Assessment Findings
Proposed Design and Limited
Access Line Changes
Agency Stakeholder Coordination
Transit Study
Schedule and Next Steps
Order of Presentation
3Virginia Department of Transportation
Scope Extend the 495 Express Lanes by approximately three miles from
the I-495 and Dulles Toll Road interchange to the George
Washington Memorial Parkway in the vicinity of the American
Legion Bridge
Replace existing bridges
Add bike and pedestrian trails
Replace existing noise walls and construct new walls where
needed
Provide stormwater management facilities
Goals and Objectives Reduce congestion
Provide additional travel choices
Improve travel reliability
Enhance safety
Project Overview
4Virginia Department of Transportation
Proposed Express Lanes Access Points
5 5Virginia Department of Transportation
Adds new capacity
Provides new travel choices
Decreases travel times during peak periods
Reduces cut-through traffic on local roads
Improves safety in the study area by:
Taking cars off local roads
Reducing the weaving needed to access the
George Washington Memorial Parkway
Project Benefits
6Virginia Department of Transportation
The National Environmental Policy Act (NEPA) requires:
Environmental Review Process
Virginia Department of Transportation
Consideration of potential environmental consequences of transportation improvements;
Documentation of the environmental analyses; and
Making the information available to the public for comment
7
Environmental Review Process –
Technical Studies
Conducted an Environmental Assessment (EA) in
accordance with NEPA including:
Air quality analysis
Alternatives analysis
Hazardous materials
Historic resources
Indirect and cumulative effects
Natural resources
Preliminary noise analysis
Socioeconomic and land use analysis
Traffic analysis
88Virginia Department of Transportation
9
Environmental
Assessment Findings
Virginia Department of Transportation 9
Environmental Resource Resource Summary
Property Impacts 89 properties with potential impacts
No relocations
Community Facilities 5 community facilities: Partial property acquisition
9 existing trail/bicycle facilities: Temporary impacts
4 proposed trail/bicycle facilities by others: Temporary impacts
Environmental Justice
(Minority/Low-income)
No disproportionately high and adverse effects
Historic Properties Anticipated “ No Adverse Effect” determination from the Virginia State Historic
Preservation Officer (SHPO)
Section 4(f) Protected Properties Anticipated de minimis impact finding for Scott’s Run Nature Preserve and the
George Washington Memorial Parkway
Section 6(f) Protected Properties Anticipated impacts to Scott’s Run Nature Preserve
Noise – Based on Preliminary Noise
Study
9 existing barriers physically affected will be replaced
3 of the 9 existing barriers would be lengthened
1 new barrier determined to be feasible and reasonable
10
Environmental
Assessment Findings
Virginia Department of Transportation 10
Environmental Resource Resource Summary
Air Quality No adverse impacts to air quality; no violation of the National Ambient Air Quality
Standards
Wetlands and Streams Streams: Approximately 13,000 linear feet located within the LOD (Anticipated
3,000 linear feet of impact)
Wetlands: 20 acres within the LOD (Anticipated 4.5 acres of impact)
Floodplains Approximately 60 acres of floodplains are within LOD
No increase in flood levels or probability of flooding expected
Wooded Areas Approximately 118 acres within the LOD
Wildlife and Habitat Approximately 234 acres within the LOD (Anticipated 66 acres of impact)
No new habitat fragmentation or elimination of existing wildlife passages is
anticipated
Threatened and Endangered Species Tree clearing could impact potential suitable habitat for three bat species
Streams and floodplains that contain potential habitat for wood turtles would be
impacted
These impacts are based on the proposed Limits of Disturbance (LOD). During final design, efforts will be
made to reduce the project footprint and minimize impacts.
Scope of Traffic Analysis
11
Operational and safety analysis I-495 and Dulles Toll Road mainlines
Arterials within study corridor
Traffic and Transportation Technical Report
Interchange Justification Report
Comparison of build alternative (with
options) versus no-build alternative 2025 interim year
2045 design year
Traffic analysis shows benefits to: Person throughput
Travel times and traffic delay
Local streets
Virginia Department of Transportation
Traffic Analysis Results
12
Move More People
2045: Moves 7,600 more people per hour in both directions combined
2025 with Maryland Managed Lanes System: Moves 5,400 more
people per hour in both directions combined
2025 Prior to Maryland Managed Lanes System: Moves 2,500 more
people per hour in both directions combined
Virginia Department of Transportation
Traffic Analysis Results
13
Reduce Cut-through Traffic On Local Roads
Virginia Department of Transportation
Measure of Effectiveness
Analysis Year
2025 with
Maryland
Managed Lanes
in Place
2025 Prior to
Maryland
Managed
Lanes in Place
2045
No-Build
BuildNo-
BuildBuild
No-Build
Build
Intersections operating at LOS A thru D 47% 60% 53% 57% 47% 55%
Intersections operating at LOS E 17% 10% 13% 17% 17% 15%
Intersections operating at LOS F 37% 30% 33% 27% 37% 30%
Reduction in peak period demand – Georgetown Pike
intersections – Build vs No Build conditions-14% -9% -12%
Reduction in intersection delay – Georgetown Pike
intersections – Build vs No Build conditions-44% -40% -49%
2025 Build (Prior to Maryland
Managed Lanes System)
2025 Build (With Maryland
Managed Lanes System in Place)No Build vs.
Build Forecast
(2025) Volume
Change
Roadway Segment PM Peak Hour
Volume Change (2025 Build vs. 2025
No Build)
Volume Increase of More than 5 %
Volume Increase of 0-5%
Volume Decrease of 0-5%
Volume Decrease of More than 5%
Old Dominion Dr
2025 Build (With Maryland
Managed Lanes System in Place)
Old Dominion Dr
Traffic Analysis Results
15
Improve Travel Time Reliability in Northbound Direction Northbound Travel Time Comparison: Route 123 to Clara Barton Parkway - Build vs. No Build
Virginia Department of Transportation
Scenario
AM Rush Hour Travel Time
Difference between
Build and No-Build
PM Rush Hour Travel Time
Difference between
Build and No-Build
Build via GP
Lanes
Build via Express
Lanes
Build via GP
Lanes
Build via Express
Lanes
2025 Prior to MD
Managed Lanes
System
4 min increase 5 min savings 6 min increase 24 min savings
2025 With MD
Managed Lanes
System
3 min savings 3.5 min savings 4 min savings 4.5 min savings
2045 4 min savings 6 min savings 4.5 min savings 18 min savings
Scenario
AM Rush Hour Travel Time
Difference between
Build and No-Build
PM Rush Hour Travel Time
Difference between
Build and No-Build
Build via
GP Lanes
Build via Express
Lanes
Build via GP
Lanes
Build via Express
Lanes
2025 Prior to MD
Managed Lanes
System
No difference 1 min savings No difference 2 min savings
2025 With MD
Managed Lanes
System
1 min savings 1.5 min savings 6 min savings 8 min savings
2045 4 min savings 6 min savings No difference 2 min savings
Traffic Analysis Results
16
Improve Travel Time Reliability in Southbound Direction Southbound Travel Time Comparison: Clara Barton Parkway to Route 123 - Build vs. No Build
Virginia Department of Transportation
Traffic Analysis Results
17
Improve Safety
Project safety and operational improvements reduce crashes by 20 percent
in 2045.
New direct access ramps to the Express Lanes at the DTR and the George
Washington Memorial Parkway – eliminates need to cross four lanes to
access the express lanes entrances / exit points.
The project improvements that would make the corridor safer:
Roadway features, such as increased acceleration and deceleration lanes, and new
auxiliary lanes; and
Reconfigured shoulder in the northbound direction during peak periods.
These types of improvements are expected to reduce rear-end and side-
swipe collisions.
Virginia Department of Transportation
Noise Analysis Process
18Virginia Department of Transportation 18
WE ARE
HEREPresent noise study results and
preliminary noise wall locations at public
hearings
Obtain VDOT Chief Engineer approval
Perform noise measurements at
representative receptors along the
corridor
Finalize noise barrier designs once the
project has received design approval
Identify impacts
(is noise mitigation warranted?)
Identify noise receptors
Perform noise modeling
Design and assess mitigation (typically
noise walls)
NE
PA
an
d P
relim
ina
ry D
es
ign
Obtain FHWA concurrence
Solicit public input from benefited
property owners and renters
(voting process)
Incorporate approved noise wall(s) into
the final road design construction plans
Fin
al D
es
ign
Preliminary Noise Analysis Findings
19
Preliminary noise
wall study results:
9 existing walls to be
replaced at same
elevation or higher
3 of 9 existing walls
lengthened
1 new wall
Virginia Department of Transportation
If you have a noise wall today, you’ll have one in the future
Noise Walls
Replaced /
LengthenedNoise Walls
Replaced /
Lengthened
Potential Noise
Wall ExtensionPotential New
Noise Wall
Examples of noise wall locations near Live Oak Drive and George Washington Memorial Parkway
Preliminary Engineering
20
Concepts for widening and connections
Pedestrian/bicycle facility improvements
Conceptual drainage and stormwater
management requirements
Replacement of existing bridges
I-495 Northbound general lanes over Dulles Toll Road
Old Dominion Drive (VA 783)
Georgetown Pike (VA 193)
Live Oak Drive
Possible right of way impacts
Changes to interstate limited access lines
Conceptual cost estimate and project schedule
Virginia Department of Transportation
Bicycle and Pedestrian Facility Improvements
21
Preliminary design coordinated with Fairfax
County to advance county bike plan
Trails added along I-495 corridor
Shared-use path behind the noise wall between
Lewinsville Road and Live Oak Drive
Connection to future crossing at American
Legion Bridge to Maryland
Facilities improved on bridges
Old Dominion Drive (VA 783)
Georgetown Pike (VA 193)
Live Oak Drive
Virginia Department of Transportation
Virginia Department of Transportation
Typical Section: I-495 Between
Dulles Toll Road and Georgetown Pike
22
Future*
*The future roadway design replaces the part-time shoulder-use lane on 495 NB with a permanent shoulder
Existing
*
DTR Interchange Phasing – Phase 1
23Virginia Department of Transportation
Dulles Toll Road Interchange
Phasing – Phase 1
DTR Interchange Phasing – Future Phases
24Virginia Department of Transportation
Dulles Toll Road Interchange
Phasing – Future Phases
25
Northern Terminus – GWMP Phase 1
Virginia Department of Transportation
Northern Terminus – George Washington
Memorial Parkway – Phase 1
Drainage Improvements
26
Partnering with Fairfax County to provide
outfall enhancements
Potential collaboration with Fairfax
County stream restoration projects
Active and/or future projects
Implementing quality and quantity
stormwater management
Address runoff at Scotts Run
Virginia Department of Transportation
Agency Stakeholder Coordination
27
Fairfax County Department of Transportation (FCDOT)
Fairfax County Park Authority (FCPA)
Federal Highway Administration (FHWA)
Maryland Department of Transportation (MDOT)
Metropolitan Washington Airports Authority (MWAA)
Metropolitan Washington Council of Governments (MWCOG)
National Park Service (NPS)
Northern Virginia Transportation Authority (NVTA)
Virginia Department of Rail and Public Transportation (DRPT)
Virginia Department of Historic Resources (VDHR)
Virginia Department of Environmental Quality (DEQ)
Virginia Department of Transportation
Project Delivery – Partnership with Transurban
28
January 2019: Development Framework Agreement with Transurban to
extend 495 Express Lanes under current agreement; no Commonwealth
funding
Subject to VDOT approval, Transurban to submit a binding proposal that
meets project-delivery technical and financial criteria
Virginia Department of Transportation
VDOT Responsibilities Transurban Responsibilities
Planning and environmental approvals
Interchange Justification Report (IJR)
Federal, state and local agency
coordination
Preliminary engineering, design, procure
design-builder, construct project
Finance plan
Operate and maintain
Key Milestones
2929Virginia Department of Transportation
Regional Coordination with Maryland
30
495 NEXT is an independent, stand-
alone project
495 NEXT is being coordinated with
Maryland to: Ensure that both projects are compatible
Support the delivery of Maryland’s project
Capital Beltway Accord Agreement between Virginia and Maryland to fund
a new American Legion Bridge and infrastructure
for connections between George Washington
Memorial Parkway and River Road
Virginia Department of Transportation
GWMP Interchange Capital Beltway Accord
31Virginia Department of Transportation
George Washington Memorial Parkway
Interchange – Capital Beltway Accord
I-495 Regional Transit Study
32
High-level transit needs study
Joint study between Virginia Department of Rail and Public
Transportation and Maryland Transit Administration
Independent of ongoing environmental studies in both states
Anticipated results in 2020
Virginia Department of Transportation
33
PUBLIC COMMENTS
Virginia Department of Transportation 33
Speakers limited to 3 minutes to speak as an individual and 5 minutes if speaking
for a group.
Reminder that all attendees should remain muted until it is your turn to provide your
comment.
Beginning with pre-registered speakers, we will call your name and unmute you so
that you can state your comment.
Following pre-registered speakers, we will open it up to others who want to provide
formal comments.
Questions and answers, if time allows.
Providing Comments at Virtual Public Hearing
34Virginia Department of Transportation
Using the Chat function, write in your name and that you would like to provide
your comment. At the appropriate time, we will call upon you and unmute you so
that you can state your comment.
If you want us to read your comment, type in your comment using the Chat
function, and we will read your comment aloud in the order received.
We will turn the Chat function “on and off” in intervals, so that we can be sure to
keep up with the comments and keep the process manageable.
When the Chat function is “on,” all participants will be able to see all
messages. We ask that you only write in your formal comments. The Chat
function should not be used for any other type of commentary or discussion
during the hearing.
35
How to Provide Comment Using the “Chat” Feature
Virginia Department of Transportation 35
Press *3 to "raise your hand" and to be added to the queue to state your
comment.
We will announce when it is your turn to state your comment, and we will
unmute your phone line.
You will hear "your line has been unmuted" after which you will be able to state
your comment. Once you have stated your comment, press *3 again to “lower
your hand.” You will be muted again at this time to avoid echo and feedback
due to the number of participants.
36
How to Provide Your Comment if “Calling by Phone”
Virginia Department of Transportation 36
37
CLOSING ANNOUNCEMENTS
Virginia Department of Transportation 37
Thursday, October 8, 2020 (4 – 8 p.m.)
McLean Community Center, 1234 Ingleside Avenue, McLean, VA 22101
Hearing Format:
Attendees must schedule an appointment to attend in-person hearing, and should
register in advance to provide comments. Go to 495NorthernExtension.org or call
703-691-6715.
Attendees can complete a written comment form and leave in comment box.
Attendance limited to one person per time-slot, or two people if from the same family.
Public hearing presentation to be displayed on TV monitor on continuous loop.
CDC-recommended health measures, including mask requirements and social
distancing, will be in place.
Limited, on-site staffing to comply with Covid-19 restrictions; additional staff to
participate via laptop/computer screens.
In-Person Public Hearing
38Virginia Department of Transportation
Public comments on the Environmental Assessment and proposed design can be submitted
until October 23, 2020, to be formally considered and included in public record.
Materials have been available to the public since February 26, 2020. Comments received to
date will be included in public record and do not need to be resubmitted.
Ways to Provide Comments After Hearing:
Online Comment Form: Accessible at 495NorthernExtension.org
Email: Send emails to [email protected] (reference “495 Express
Lanes Northern Extension Project” in subject line)
Mail: Mail comments to VDOT Northern Virginia District Office, Attn: Abi Lerner, P.E., 4975
Alliance Drive, Fairfax, VA 22030
Phone: Comments/testimony can be provided by phone by calling 703-691-6715
Video: Comments/testimony can be provided by video submitted via the project email
address.
Ways to Provide Comments
39Virginia Department of Transportation
Continued availability of EA and draft design plans on project website.
Hard copies of EA and draft design plans available at following public locations
Availability of Hearing Materials
40Virginia Department of Transportation
Name Hours Notes
VDOT NOVA Office
4975 Alliance Drive, Fairfax
Mon-Fri 9 a.m.-5 p.m. Public access by appointment only
Dolley Madison Library
1244 Oak Ridge Ave, McLean
Mon-Tues 10 a.m.-8 p.m.
Wed-Sat 10 a.m.-6 p.m.
Public access (limited to 30 min.)
Great Falls Library
9830 Georgetown Pike, Great Falls
Mon-Tues 10 a.m.-8 p.m.
Wed-Sat 10 a.m.-6 p.m.
Public access (limited to 30 min.)
Tysons-Pimmit Library
7584 Leesburg Pike, Falls Church
Mon-Tues 10 a.m.-8 p.m.
Wed-Sat 10 a.m.-6 p.m.
Public access (limited to 30 min.)
McLean Community Center
1234 Ingleside Avenue, McLean
Mon–Thurs: 8 a.m.–11 p.m.
Friday: 8 a.m.–Midnight
Saturday: 9 a.m.–Midnight
Sunday: Noon–6 p.m.
New location, across the street from library in
McLean.
Fairfax County Department of Transportation
4050 Legato Road, Suite 450, Fairfax
Mon-Fr 8 a.m.-4:30 p.m.
495 Express Lanes
Northern Extension (495 NEXT)
41