ASGC - Taipei• On Feb 21, Academia Sinica, Taipei
informed CERN DG that they intended to withdraw support for CMS as a Tier 1 and as a Tier 2 at ASGC- CMS have no physicists in Academia Sinica- ASGC has lost part of its funding from the
National Science Council
• Response sent March 6- Asking for clarification of intended timescales
and to inform WLCG OB and RRB
March 6, 2013
Update on KISTI-GSDC• 1512 cores (63 WNs) with 3GB memory/core• 1.042 PB Disks: old SE(100TB) will be removed; new storage will be delivered
• 1 Gbps Network to be upgraded to 2Gbps in coming April• EMI-2 Migration done and on production (better behaviour than gLite-3.2)• Tape
– 1 PB capacity (expandable up to 3 PB, 2GB/s throughput) with 200 TB xrootd pool + 275 TB tape buffer
– Functional tests done, Policy tuning on-going for xrootd, GPFS– Periodic test by ALICE shows good -> p-Pb data transfer scheduled to start on 7th March
JINR CMS Tier-1 progress
● Disk & server installation and tests: done● Tape system installation: done● Organization of network infrastructure and
connectivity to CERN via GEANT (2 Gbps): done
● LHC OPN integration: postponed*● Registration in GOC DB and APEL: done● Tests of WLCG services via Nagios: done● CMS-specific tests: in process
* restructurising local network to ease integration with LHC OPN
2012(done)
2013 2014
CPU (HEPSpec06) 14400 28800 43200
Disk (Terabytes) 660 3168 4224
Tape (Terabytes) 72 5700 8000
RRC-KI Tier-1 progress
● Disk & server installation and tests: done● Tape system installation: done● Network connectivity to CERN via GEANT
(2 Gbit/sec): done● LHC OPN integration: postponed*● Registration in GOC DB and APEL: done● Tests of WLCG services via Nagios: done● ATLAS-specific tests: in process, have
preliminary results that look good* restructurising our network to ease integration with LHC OPN
ATLAS-specific activity
● Prepared services and data storage for the reprocessing of 2011 2.76 TeV reprocessing
● Currently commissioning Tier-1 resource for ATLAS:– Stress tests via HammerCloud– Reconstruction tests submitted by ATLAS experts– Functional tests via Panda and DDM
● Transferred 54 TB of input data to our storage element with transfer efficiency around 90%
Data accumulated
March 6, 2013
Data written into Castor per week
Volume of CERN archive
2012/13 Data written 2012/13 Data read
Preparation for April RRB• Met with RSG chair + LHCC referees in February• Agreed an assumed running scenario for 2015, in order to
produce requirements- 5.10^6 s of operation; less pileup in first part, increased in 2nd part
of year
• Discussed how to present 2015 needs- Potentially significantly increased trigger rates- Aggressive work during LS1 to enable the needs to be met with
reasonable resource increases• The estimates for 2015 are now somewhat less than the x2 feared;
except for tape needs;
- Ramp-up during 2015 – clearly early in the year less will be needed
• [Also agreed to set the disk usage “efficiency” to 1 to avoid confusion]
March 6, 2013
2013 2015 resources
March 6, 2013
CPU TapeDisk
2013: pledge OR actual installed capacity if higher
Use of Tier 0 and HLT during LS1
• During LS1; the Tier 0 resources will be used for analysis as well as re-processing- This is a different use pattern; requires more
disk that Tier 0 functions
• Also the HLT farms will be extensively used to supplement the grid resources
March 6, 2013
14 January 2013 IT Department Meeting 17
WIGNER Data CenterAfter full refurbishment, hosting CERN Tier-0From 1 january 2013
IT Department Meeting 18
Data Center Layout & ramp-up
14 January 2013
IT Department Meeting 19
Connectivity (100 Gbps)
14 January 2013
IT Department Meeting 20
513 Consolidation Project: Goals
• Solve the cooling issue for the critical UPS room- New UPS systems in a different location
• Increase critical UPS capacity to 600kW
• Restore N+1 redundancy for both critical and physics UPS systems
• Secure cooling for critical equipment when running on UPS and extend stored cooling capacity for physics when on diesel
• Decouple the A/C for CC from the adjacent office building
• Increase overall power capacity to 3.5MW
14 January 2013
2114 January 2013 IT Department Meeting
EC projects• EMI (middleware) ends April 2013• EGI-SA3 (support for Heavy User communities) –
ends April 2013- Although EGI-Inspire continues for 1 more year
• These have impact on CERN groups supporting the experiments, as well as NGI support
• Consequences:- Re-prioritisation of functions is needed - Need to take action now if we anticipate attracting EC
money in the future• But there is likely to be a gap of ~1 year or more
March 6, 2013
Short term: Consolidation of activities at CERN
• WLCG operations, service coordination, support- Consolidate related efforts (daily ops, integration, deployment, problem
follow-up etc)- Broader than just CERN – encourage other labs to participate
• Common solutions- Set of activities benefitting several experiments. Coordinates
experiment work as well as IT-driven work. Experiments see this as strategic for the future; beneficial for long term sustainability
• Grid monitoring- Must be consolidated (SAM/Dashboards). Infrastructure becoming
more common; focus on commonalities, less on experiment-specifics
• Grid sw development+support- WLCG DM tools (FTS, DPM/LFC, Coral/COOL, etc), information
system; Simplification of build, packaging, etc. open source community processes; (See WLCG doc)
Longer term• Need to consider how to engage with EC and
other potential funding sources• However, in future boundary conditions will be
more complex: (e.g. for EC)- Must demonstrate how we benefit other sciences
and society at large- Must engage with Industry (e.g. via PPP)- HEP-only proposals unlikely to succeed
• Also it is essential that any future proposal is fully engaged in by CERN (IT+PH) and experiments and other partners
March 6, 2013
Background• Requested by the LHCC in December: need to see
updated computing models before Run 2 starts• A single document to:
- Describe changes since the original TDRs (2005) in• Assumptions, models, technology, etc.
- Emphasise what is being done to adapt to new technologies, to improve efficiency, to be able to adapt to new architectures, etc.
- Describe work that still needs to be done- Use common formats, tables, assumptions, etc
• 1 document rather than 5
March 6, 2013
Timescales• Document should describe the period from LS1 –
LS2- Estimates of evolving resource needs
• In order to prepare for 2015, a good draft needs to be available in time for the Autumn 2013 RRB, so needs to be discussed at the LHCC in September: Solid draft by end of summer 2013 (!)
• Work has started- Informed by all of the existing work from the last 2
years (Technical Evolution groups, Concurrency forum, Technology review of 2012)
March 6, 2013
Opportunities• This document gives a framework to:
- Describe significant changes and improvements already made- Stress commonalities between experiments – and drive
strongly in that direction• Significant willingness to do this• Describe the models in a common way – calling out differences
- Make a statement about the needs of WLCG in the next 5 years (technical, infrastructure, resources)
- Potentially review the organisational structure of the collaboration
- Review the implementation: scale, quality of service of sites/Tiers; archiving vs processing vs analysis activities
- Raise concerns:• E.g. staffing issues; missing skills;
March 6, 2013
Draft ToC• Preamble/introduction • Experiment computing models• Technology review and outlook• Challenges – the problem being addressed• Distributed computing• Computing services• Software activities and strategies• Resource needs and expected evolution• Collaboration organisation and management
March 6, 2013
[email protected] 30March 6, 2013
Summary• WLCG operations in good shape, • Use of computing system by experiments
regularly fills available resources- Concern over resources vs requirements in the
future
• Tier 0 consolidation work close to complete, deployment beginning
• Important to take concrete steps now for future planning for support
March 6, 2013