Date post: | 07-Apr-2018 |
Category: |
Documents |
Upload: | nazi-sweet |
View: | 217 times |
Download: | 0 times |
of 26
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
1/26
DG Interconnection
Ian Bradley
Manager P&C Programs
Hydro One Networks Inc.January 22, 2009
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
2/26
2
Outline
Anti-Islanding Protection
Requirement Transfer Trip Requirement
New technologies being studied
DG Interconnection Transformer New Requirements
Hydro One Feeder Protections
Resynchronization of DG facilities to Hydro One
Example of sequence of events for temporary andpermanent faults
Conclusions
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
3/26
3
Anti-Islanding Requirement
Islanding of DG facilities shall not be permitted in Hydro Ones
Distribution System
Electric island DG continues to supply HONI customers after
HONI has disconnected via breaker/recloser
TS
F1
F2
F3DG
Recloser/Breaker Closed
DG
CB1
CB2 CB3
CB4
Recloser/Breaker Open
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
4/26
4
Anti-Islanding Requirement
Islanding of DG facilities shall not be permitted in Hydro Ones
Distribution System
Electric island DG continues to supply HONI customers after
HONI has disconnected via breaker/recloser
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
5/26
5
Anti-Islanding Requirement
Reasons for Anti-Islanding protection
Prevent Power Quality problems to HONIs customers
Prevent Out-of-Phase Reclosing
Mitigate safety hazards
Solutions will vary depending on size and type of DG
and load profile of feeder
Under/Over Frequency and Voltage protections required.
Directional overcurrent/power, negative sequence overcurrent, zero
sequence voltage, transfer trip may be required
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
6/26
6
Transfer Trip Requirement
HONI requires that all exporting DGs be equipped with a Transfer
Trip (TT) signal unless:
the maximum generation is less than 50% of the minimum feeder load not
able to sustain island
Consistent with CSA, international standards & major utility
practices
TS
F1
F2
F3DG
Recloser/Breaker
Transfer Trip
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
7/26
7
Transfer Trip Requirement
Transfer Trip may be costly for smaller DG installations especially
when multiple devices need TT to the DG Facility
Hydro One is working on solutions which will replace the Transfer
Trip Requirements for DG facilities interconnecting sized 500kW
and below, which include:
Pulse-based Signaling (Connectivity-based)
Rate-of-change-of-frequency (ROCOF) local based
Vector Surge (Vector Jump) local based
Each technology will be evaluated and tested to determine its
suitability for use as Anti-Islanding Protection for these projects
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
8/26
8
DG Interconnection Transformer
(DGIT) Hydro One has initiated a task force of experts to determine the
most efficient, safe and reliable method of connecting generation to
the distribution system
New standards have been created and will apply to all future DG
interconnections
Issues associated with the DGIT:
(HV):(LV) Delta:Wye-Gnd causes damaging temporary overvoltages
to Hydro One during ground faults
(HV):(LV) Wye-Gnd:Delta adds a ground source to system and
desensitizes feeder ground protections
(HV):(LV) Wye-Gnd:Wye-Gnd also acts as a ground source and
allows harmonics to pass
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
9/26
9
DG Interconnection Transformer
(DGIT)
3-Wire Distribution Systems
Delta (HV) : Wye-Gnd (LV) DGIT
Grounding transformers may be required on LV side to limit TOV to
DG
Not a ground source will not affect Hydro Ones feeder ground
protection
No TOV on Hydro Ones distribution system
High Voltage Interrupter not a requirement
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
10/26
10
DG Interconnection Transformer
(DGIT) 4-Wire Distribution Systems
Wye-Gnd (HV) : Delta (LV)
Neutral reactor required on HV side to limit ground current infeed
Shall be sized to ensure TOV is limited to 125% of nominal will not have a TOV
problem
Is a ground source
For DG installations greater than 500kW, HVI is required to trip DGIT from system
eliminating ground source
For DG facilities smaller than 500kW
Wye-Gnd (HV) : Wye-Gnd (LV) DGIT will be allowed
Does not require HVI
If single phase switching is present upstream three single phase transformers shall be
used
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
11/26
11
Hydro Ones Feeder Protections
Hydro One will utilize distance protection for low set instantaneous phase
and ground protection If the low set protections operate, the DGIT and DG shall trip via Transfer
Trip or other approved Anti-Islanding Protections
DGIT is removed from system ground source is also removed
Overcurrent protection will then operate as required DGs will not impede
feeder protections
Using this approach and the combination of DGIT configurations, both
TOV and ground protection problems have been eliminated
May enable quicker connections as standard modules are being developed
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
12/26
12
Resynchronization
Following a protection operation, the DGIT shall reclose into the
distribution system within 10 seconds
This will limit the power quality issues associated with DGIT
energization for Hydro One customers
The generator shall stay offline until voltage and frequency has
been stabilized and within limits for at least a period of 5 minutes
If voltage and frequency are not restored within a period of 5
minutes, resynchronization shall lockout and the generators shall
be kept offline until Hydro One operators contact the DG facility
The DGIT and generator reconnection may need to be staggered if
multiple DGs are present on feeder
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
13/26
13
Sequence of Events Temporary
Fault
TS
F1
F2
F3
DG
Recloser/Breaker - Open Transfer Trip
Fault Wye
Delta
HVI
Recloser/Breaker - Closed
Fuse (Closed) Fuse (Blown)
Fault Occurs ex. Bird/Tree Contact on a lateral protected by fuse
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
14/26
14
Sequence of Events Temporary
Fault
Low Set Instantaneous Feeder Protections senses fault Opens
feeder breaker (Fuse Saving Scheme)
Sends Transfer Trip to DG Facility to HVI and generator breaker
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
15/26
15
Sequence of Events Temporary
Fault
TS
F1
F2
F3
DG
Recloser/Breaker - Open
Wye
Delta
HVI
Recloser/Breaker - Closed Transfer Trip
Fuse (Closed) Fuse (Blown)
Fault
DGIT and generator breakers open
Fault does not clear
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
16/26
16
Sequence of Events Temporary
Fault
Feeder breaker recloses
Fuse blows Fault is cleared Load is Lost
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
17/26
17
Sequence of Events Temporary
Fault
DGIT recloses within 10 seconds of breaker reclosing
Generator stays offline
FaultTS
F1
F2
F3
DG
Recloser/Breaker - Open
Wye
Delta
HVI
Recloser/Breaker - Closed Transfer Trip
Fuse (Closed) Fuse (Blown)
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
18/26
18
Sequence of Events Temporary
Fault
Voltage and Frequency is stabilized
Generator resynchronizes after 5 minutes
FaultTS
F1
F2
F3
DG
Recloser/Breaker - Open
Wye
Delta
HVI
Recloser/Breaker - Closed Transfer Trip
Fuse (Closed) Fuse (Blown)
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
19/26
19
Sequence of Events Permanent
Fault
Fault Occurs ex. Conductor breaks
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
20/26
20
Low Set Instantaneous Feeder Protections senses fault Opens
feeder breaker
Sends Transfer Trip to DG Facility to HVI and generator breaker
Sequence of Events Permanent
Fault
TS
F1
F2
F3
DG
Recloser/Breaker - Open Transfer Trip
Wye
Delta
HVI
Recloser/Breaker - Closed
Fault
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
21/26
21
DGIT and generator breakers open
Fault is not cleared after reclose attempts
Hydro One crews are dispatched to repair line
After 5 minutes the generator resynchronization will lockout
Sequence of Events Permanent
Fault
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
22/26
22
Sequence of Events Permanent
Fault
Hydro One repairs line Fault is cleared
Operators close Feeder breaker energizing the line
DGIT recloses within 10 seconds - Generator stays offline
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
23/26
23
Sequence of Events Permanent
Fault
Operators contact DG facility
Generators are restarted manually and synchronized to Hydro One
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
24/26
Summary
The new requirements presented here will allow DGs to connect
with fewer problems, and allow a quicker turn around time.
They have eliminated two of the major technical barriers faced
with interconnection of DGs TOV and feeder protections
Hydro One is working hard to determine best practices and ideal
solutions to technical problems faced with interconnection of
DGs
Focused on safety, reliability, and minimizing cost to DG
Proponents
Creating modular equipment which can be implemented quickly
and efficiently to reduce wait times
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
25/26
Future
The new DG Interconnection Requirements Standard shall be
provided to the public shortly
Hydro One will continue to develop solutions to enable more
generation and overcome other technical and financial obstacles
such as Anti-Islanding Protection for smaller DGs
P&C Enablement Program for DG Interconnection
8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009
26/26
Questions