+ All Categories
Home > Documents > Ian Bradley - APPrO Presentation on DG, Jan 22 2009

Ian Bradley - APPrO Presentation on DG, Jan 22 2009

Date post: 07-Apr-2018
Category:
Upload: nazi-sweet
View: 217 times
Download: 0 times
Share this document with a friend

of 26

Transcript
  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    1/26

    DG Interconnection

    Ian Bradley

    Manager P&C Programs

    Hydro One Networks Inc.January 22, 2009

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    2/26

    2

    Outline

    Anti-Islanding Protection

    Requirement Transfer Trip Requirement

    New technologies being studied

    DG Interconnection Transformer New Requirements

    Hydro One Feeder Protections

    Resynchronization of DG facilities to Hydro One

    Example of sequence of events for temporary andpermanent faults

    Conclusions

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    3/26

    3

    Anti-Islanding Requirement

    Islanding of DG facilities shall not be permitted in Hydro Ones

    Distribution System

    Electric island DG continues to supply HONI customers after

    HONI has disconnected via breaker/recloser

    TS

    F1

    F2

    F3DG

    Recloser/Breaker Closed

    DG

    CB1

    CB2 CB3

    CB4

    Recloser/Breaker Open

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    4/26

    4

    Anti-Islanding Requirement

    Islanding of DG facilities shall not be permitted in Hydro Ones

    Distribution System

    Electric island DG continues to supply HONI customers after

    HONI has disconnected via breaker/recloser

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    5/26

    5

    Anti-Islanding Requirement

    Reasons for Anti-Islanding protection

    Prevent Power Quality problems to HONIs customers

    Prevent Out-of-Phase Reclosing

    Mitigate safety hazards

    Solutions will vary depending on size and type of DG

    and load profile of feeder

    Under/Over Frequency and Voltage protections required.

    Directional overcurrent/power, negative sequence overcurrent, zero

    sequence voltage, transfer trip may be required

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    6/26

    6

    Transfer Trip Requirement

    HONI requires that all exporting DGs be equipped with a Transfer

    Trip (TT) signal unless:

    the maximum generation is less than 50% of the minimum feeder load not

    able to sustain island

    Consistent with CSA, international standards & major utility

    practices

    TS

    F1

    F2

    F3DG

    Recloser/Breaker

    Transfer Trip

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    7/26

    7

    Transfer Trip Requirement

    Transfer Trip may be costly for smaller DG installations especially

    when multiple devices need TT to the DG Facility

    Hydro One is working on solutions which will replace the Transfer

    Trip Requirements for DG facilities interconnecting sized 500kW

    and below, which include:

    Pulse-based Signaling (Connectivity-based)

    Rate-of-change-of-frequency (ROCOF) local based

    Vector Surge (Vector Jump) local based

    Each technology will be evaluated and tested to determine its

    suitability for use as Anti-Islanding Protection for these projects

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    8/26

    8

    DG Interconnection Transformer

    (DGIT) Hydro One has initiated a task force of experts to determine the

    most efficient, safe and reliable method of connecting generation to

    the distribution system

    New standards have been created and will apply to all future DG

    interconnections

    Issues associated with the DGIT:

    (HV):(LV) Delta:Wye-Gnd causes damaging temporary overvoltages

    to Hydro One during ground faults

    (HV):(LV) Wye-Gnd:Delta adds a ground source to system and

    desensitizes feeder ground protections

    (HV):(LV) Wye-Gnd:Wye-Gnd also acts as a ground source and

    allows harmonics to pass

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    9/26

    9

    DG Interconnection Transformer

    (DGIT)

    3-Wire Distribution Systems

    Delta (HV) : Wye-Gnd (LV) DGIT

    Grounding transformers may be required on LV side to limit TOV to

    DG

    Not a ground source will not affect Hydro Ones feeder ground

    protection

    No TOV on Hydro Ones distribution system

    High Voltage Interrupter not a requirement

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    10/26

    10

    DG Interconnection Transformer

    (DGIT) 4-Wire Distribution Systems

    Wye-Gnd (HV) : Delta (LV)

    Neutral reactor required on HV side to limit ground current infeed

    Shall be sized to ensure TOV is limited to 125% of nominal will not have a TOV

    problem

    Is a ground source

    For DG installations greater than 500kW, HVI is required to trip DGIT from system

    eliminating ground source

    For DG facilities smaller than 500kW

    Wye-Gnd (HV) : Wye-Gnd (LV) DGIT will be allowed

    Does not require HVI

    If single phase switching is present upstream three single phase transformers shall be

    used

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    11/26

    11

    Hydro Ones Feeder Protections

    Hydro One will utilize distance protection for low set instantaneous phase

    and ground protection If the low set protections operate, the DGIT and DG shall trip via Transfer

    Trip or other approved Anti-Islanding Protections

    DGIT is removed from system ground source is also removed

    Overcurrent protection will then operate as required DGs will not impede

    feeder protections

    Using this approach and the combination of DGIT configurations, both

    TOV and ground protection problems have been eliminated

    May enable quicker connections as standard modules are being developed

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    12/26

    12

    Resynchronization

    Following a protection operation, the DGIT shall reclose into the

    distribution system within 10 seconds

    This will limit the power quality issues associated with DGIT

    energization for Hydro One customers

    The generator shall stay offline until voltage and frequency has

    been stabilized and within limits for at least a period of 5 minutes

    If voltage and frequency are not restored within a period of 5

    minutes, resynchronization shall lockout and the generators shall

    be kept offline until Hydro One operators contact the DG facility

    The DGIT and generator reconnection may need to be staggered if

    multiple DGs are present on feeder

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    13/26

    13

    Sequence of Events Temporary

    Fault

    TS

    F1

    F2

    F3

    DG

    Recloser/Breaker - Open Transfer Trip

    Fault Wye

    Delta

    HVI

    Recloser/Breaker - Closed

    Fuse (Closed) Fuse (Blown)

    Fault Occurs ex. Bird/Tree Contact on a lateral protected by fuse

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    14/26

    14

    Sequence of Events Temporary

    Fault

    Low Set Instantaneous Feeder Protections senses fault Opens

    feeder breaker (Fuse Saving Scheme)

    Sends Transfer Trip to DG Facility to HVI and generator breaker

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    15/26

    15

    Sequence of Events Temporary

    Fault

    TS

    F1

    F2

    F3

    DG

    Recloser/Breaker - Open

    Wye

    Delta

    HVI

    Recloser/Breaker - Closed Transfer Trip

    Fuse (Closed) Fuse (Blown)

    Fault

    DGIT and generator breakers open

    Fault does not clear

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    16/26

    16

    Sequence of Events Temporary

    Fault

    Feeder breaker recloses

    Fuse blows Fault is cleared Load is Lost

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    17/26

    17

    Sequence of Events Temporary

    Fault

    DGIT recloses within 10 seconds of breaker reclosing

    Generator stays offline

    FaultTS

    F1

    F2

    F3

    DG

    Recloser/Breaker - Open

    Wye

    Delta

    HVI

    Recloser/Breaker - Closed Transfer Trip

    Fuse (Closed) Fuse (Blown)

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    18/26

    18

    Sequence of Events Temporary

    Fault

    Voltage and Frequency is stabilized

    Generator resynchronizes after 5 minutes

    FaultTS

    F1

    F2

    F3

    DG

    Recloser/Breaker - Open

    Wye

    Delta

    HVI

    Recloser/Breaker - Closed Transfer Trip

    Fuse (Closed) Fuse (Blown)

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    19/26

    19

    Sequence of Events Permanent

    Fault

    Fault Occurs ex. Conductor breaks

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    20/26

    20

    Low Set Instantaneous Feeder Protections senses fault Opens

    feeder breaker

    Sends Transfer Trip to DG Facility to HVI and generator breaker

    Sequence of Events Permanent

    Fault

    TS

    F1

    F2

    F3

    DG

    Recloser/Breaker - Open Transfer Trip

    Wye

    Delta

    HVI

    Recloser/Breaker - Closed

    Fault

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    21/26

    21

    DGIT and generator breakers open

    Fault is not cleared after reclose attempts

    Hydro One crews are dispatched to repair line

    After 5 minutes the generator resynchronization will lockout

    Sequence of Events Permanent

    Fault

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    22/26

    22

    Sequence of Events Permanent

    Fault

    Hydro One repairs line Fault is cleared

    Operators close Feeder breaker energizing the line

    DGIT recloses within 10 seconds - Generator stays offline

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    23/26

    23

    Sequence of Events Permanent

    Fault

    Operators contact DG facility

    Generators are restarted manually and synchronized to Hydro One

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    24/26

    Summary

    The new requirements presented here will allow DGs to connect

    with fewer problems, and allow a quicker turn around time.

    They have eliminated two of the major technical barriers faced

    with interconnection of DGs TOV and feeder protections

    Hydro One is working hard to determine best practices and ideal

    solutions to technical problems faced with interconnection of

    DGs

    Focused on safety, reliability, and minimizing cost to DG

    Proponents

    Creating modular equipment which can be implemented quickly

    and efficiently to reduce wait times

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    25/26

    Future

    The new DG Interconnection Requirements Standard shall be

    provided to the public shortly

    Hydro One will continue to develop solutions to enable more

    generation and overcome other technical and financial obstacles

    such as Anti-Islanding Protection for smaller DGs

    P&C Enablement Program for DG Interconnection

  • 8/3/2019 Ian Bradley - APPrO Presentation on DG, Jan 22 2009

    26/26

    Questions


Recommended