    In-Building Coverage Project 

     

    ContentsIntroduction ............................................................................................................................................ 2

    Why is In-building Coverage Important? ................................ ............................. .......................... ....... 2

    Objectives ............................................................................................................................................... 3

    Assumptions ............................... .......................... .......................... .......................... .......................... ..... 3

    Project scope statement ............................... .......................... .......................... .......................... ............. 4

    Work breakdown structure.......................................... .......................... ............................ ...................... 5

    WBS Dictionary........................................................................................................................................ 6

    Project Management Plan ........................................... .......................... ........................... ....................... 7

    Schedule management plan............................................... .......................... .......................... .............. 7

    Staffing Management Plan............................ .......................... .......................... .......................... ......... 9

    Risk Register ........................................................................................................................................ 9

    Case Study Calculations ........................... .......................... .......................... .......................... ................ 10

    HR Calculations ........................... .......................... .......................... .......................... ......................... 10

    Material Calculations ........................... .......................... .......................... .......................... ................ 10

    Overall Project Calculations ............................................... .......................... .......................... ............ 11

    Conclusion ............................. ........................... .......................... .......................... .......................... ....... 12

  • 8/18/2019 IBS Project - Cost report

    2/12

    In-Building Coverage Project 

     

    Introduction

    There are numerous challenges, both from a business and a technical

    perspective, when designing and implementing indoor coverage solutions. Indoor

    radio planners carry a major responsibility for the overall business case and

    performance of the network. In many countries 80% of users are inside buildings,

    and providing high-performance indoor coverage, especially on higher data rates,

    is a challenge. It is much more than a technical challenge; the business case must

    also be evaluated, as well as future-proofing of the solutions implemented, among

    other considerations.

    Why is In-building Coverage Important?

    There are many reasons for the mobile operator, both technical and commercial,

    for providing sufficient in-building coverage. The technical motivations are typical;

    lack of coverage, improvement of service quality, need for more capacity, need for

    higher data rates and to offload the existing macro network. In 3G (UMTS)

    networks, the need to offload the existing macro network is an especially important

    parameter. The need for higher-speed data rates inside buildings also plays an

    important factor. It is evident that you will need dedicated in-building (IB) solutions

    to provide high-speed data service on UMTS and especially when deploying

    HSDPA/HSUPA high-speed data services.

    However, even the most hardcore technical RF design engineer must realize that

    the main driver for any mobile network operator must be to increase the revenue

    factor. The purpose is to maximize the revenue of the network and to lower the

    production cost of the traffic. The cost of producing a call minute (CM) is a crucial

  • 8/18/2019 IBS Project - Cost report

    3/12

    In-Building Coverage Project 

     

    factor for the mobile operator, and so is the production cost per Mb of data

    transmitted in the network.

    Objectives

    -  Determine the cost estimation to one activity for in-building coverage

    project.

    -  Explain how the cost estimation inputs influence the activity’s cost.

     Assumptions

    -  Assume that the company has a clear forecast to the further projects.

    -  The company has their own templates, like a site survey reports.

    -  The company has their own commercial data base with the employee

    salaries ranges.

    -  The overheads costs are not included in cost estimates because it is not aone of the project manager’s tasks as defined in the company’s policy.

    -  The employee skills are defined before the start of project.

    -  One of the project scope statements is using genuine programs, and

    calibrated equipment.

  • 8/18/2019 IBS Project - Cost report

    4/12

    In-Building Coverage Project 

     

    Cost Estimating Methodology

    Costing is important because it provides a quantified basis for defining poverty

    reduction strategies and programs, as well as for forecasting resource gaps and

    needs, and for mobilizing additional resources, either internally or externally. While

    it is usually not possible to obtain reliable cost estimates for the long-term, costing

    is essential for coordinating the national budget and aid allocations with the

    prioritized development goals. The price tag and the financing plan of the programs

    or projects can only be ascertained meaningfully within a short-to-medium time

    horizon.

    There are several common costing methodologies, and they all have their

    usefulness in specific situations. However, no one single methodology is

    appropriate for every situation. All cost estimates must be interpreted with caution

    and scrutinized carefully. Nobody should be utterly confident of their precision. In

    short, there is no universally robust or best way of costing programs or projects.

    Since it is better to be broadly right than to be precisely wrong, cost estimates are

    sometimes best seen as orders of magnitude, expressed as a range rather than a

    single figure.

    The determine resource cost rates is the methodology that used to estimate the

    costs.

    Project scope statement

    95% of building’s area should be covered with a signal strength not less than

    -85dBm.

  • 8/18/2019 IBS Project - Cost report

    5/12

    In-Building Coverage Project 

     

    Work breakdown structure

    The work breakdown structure (WBS) provides the relationship among all the

    components of the project and the project deliverables.

    The below table show the WBS for the in-building solution project:

    Table 1 Work Breakdown Structure

    WBS Task Name Duration Start Finish Predecessors

    1  In-Building Coverage Project  110 days  Mon 11/16/15  Sun 4/17/16 

    1.1  Site Survey & Design  15 days  Mon 11/16/15  Sun 12/6/15 

    1.1.1  Site Survey  9 days  Mon 11/16/15  Thu 11/26/15 

    1.1.1.1 Building information 1 day Mon 11/16/15 Mon 11/16/15

    1.1.1.2 Surrounding networkinformation 1 day Tue 11/17/15 Tue 11/17/15 4

    1.1.1.3 Draft solution design 2 days Wed 11/18/15 Thu 11/19/15 5

    1.1.1.4 Propagation Measurements 2 days Tue 11/17/15 Wed 11/18/15 4

    1.1.1.5BTS, Microwave & Antenna

    location1 day Thu 11/19/15 Thu 11/19/15 7

    1.1.1.6 Cable routing 3 days Sun 11/22/15 Tue 11/24/15 8

    1.1.1.7Photos of Ant. , BTS & MW

    locations1 day Wed 11/25/15 Wed 11/25/15 9

    1.1.1.8 Site survey report submitted 1 day Thu 11/26/15 Thu 11/26/15 10

    1.1.1.9 Site survey report approved  0 days Thu 11/26/15 Thu 11/26/15 11

    1.1.2  Design 14 days  Tue 11/17/15  Sun 12/6/15 

    1.1.2.1 Import the layout to iBwave 1 day Tue 11/17/15 Tue 11/17/15 4

    1.1.2.2 Design building 5 days Wed 11/18/15 Tue 11/24/15 14

    1.1.2.3 Perform prediction 1 day Wed 11/25/15 Wed 11/25/15 15

    1.1.2.4 Generate reports 1 day Thu 11/26/15 Thu 11/26/15 16

    1.1.2.5Building Design complete and

    approved4 days Sun 11/29/15 Wed 12/2/15 17

    1.1.2.6 BoQ ready and approved 2 days Thu 12/3/15 Sun 12/6/15 18

    1.1.2.7Design complete and BoQ

    approved 0 days Sun 12/6/15 Sun 12/6/15 19

    1.2  Ordering & Delivery  44 days  Thu 12/3/15  Tue 2/2/16 

    1.2.1 Material Ordering 6 days Thu 12/3/15 Thu 12/10/15 18

    1.2.2 Material Delivery 28 days Sun 12/13/15 Tue 1/19/16 22

    1.2.3 Custom Clearance 10 days Wed 1/20/16 Tue 2/2/16 23

    1.2.4

    Material out of custom clearance

    and delivered to the warehouse 0 days Tue 2/2/16 Tue 2/2/16 24

  • 8/18/2019 IBS Project - Cost report

    6/12

  • 8/18/2019 IBS Project - Cost report

    7/12

    In-Building Coverage Project 

     

    1.1.1.3 Draft solution designMake a draft design for the antenna locations ,

    component and cables

    1.1.1.4 Propagation MeasurementsUse transmitter and receiver to measure the

    penetration loss for the walls

    1.1.1.5 BTS, Microwave & Antenna location

    Looking for the suitable location for the Base

    Station Transceiver , Microwave dish and the

    Antennas

    1.1.1.6 Cable routingInvestigate the cable routing and how can we

    route the cables

    1.1.1.7 Photos of Ant. , BTS & MW locations Take photos to the component locations

    1.1.1.8 Site survey report submittedPrepare the site survey report and submit it to

    the PMO to approve

    1.1.1.9 Site survey report approved Milestone

    1.1.2 Design Stage

    1.1.2.1 Import the layout to iBwaveImport DWG files or the sketch to iBwave design

    tool

    1.1.2.2 Design building

    1.1.2.3 Perform predictionWhen the design completed, we do prediction to

    emulate the design

    1.1.2.4 Generate reportsSuch as BoQ, Magnetic field, Complaint distance,

    and etc.

    1.1.2.5 Building Design complete and approved

    1.1.2.6 BoQ ready and approved

    1.1.2.7 Design complete and BoQ approved Milestone

    Project Management Plan

    Schedule management plan

    The project schedule is the roadmap for how the project will be executed.

    Schedules are an important part of any project as they provide the project team,

    sponsor, and stakeholders a picture of the project’s status at any given time. The

    purpose of the schedule management plan is to define the approach the project

    team will use in creating the project schedule.

  • 8/18/2019 IBS Project - Cost report

    8/12

    n-Building Coverage Project 

     

  • 8/18/2019 IBS Project - Cost report

    9/12

    In-Building Coverage Project 

     

    Staffing Management Plan

    The Staffing Plan defines the required human resources needed to deliver the

    desired project deliverables. It involves the selection and assignment of a Project

    Team. The Staffing Plan must provide the appropriate skill sets to manage the

    project and to perform the tasks that produce the specified project deliverables. It

    also needs to provide for any additional non-labor resources such as tools,

    equipment, or processes used by the project team.

    Risk Register

    Risk register lists all identified risks that may affect the project. It should be as

    comprehensive as possible to include all identifiable items that have probability

    of occurrences and generally includes estimated probability of the risk event to

    occur, severity or possible impact of the risk, probable timing and anticipated

    frequency.

  • 8/18/2019 IBS Project - Cost report

    10/12

    In-Building Coverage Project 

     

    Case Study Calculations

    HR Calculations

    Material Calculations

    # Resource Name   Salary Car Health Care Pension Accommodation Cost / Year Cost / Month Cost / day

    1 Head of PMO 120000 40000 1200 13500 0 174700 14558.33333 485.2778

    2 Procurment Manager 120000 40000 1200 13500 0 174700 14558.33333 485.2778

    3 Logistics 18000 21000 1200 2025 0 42225 3518.75 117.2917

    4 Senior Engineer 27300 21000 1200 3071.25 0 52571.25 4380.9375 146.0313

    5 Telecom Engineer 24000 0 1200 2700 0 27900 2325 77.5

    6 RF Engineer 1 25200 0 1200 2835 0 29235 2436.25 81.20833

    7 RF Engineer 2 25200 0 1200 2835 0 29235 2436.25 81.20833

    8 Technician 1 9600 0 1200 0 200 11000 916.6666667 30.55556

    9 Technician 2 9600 0 1200 0 200 11000 916.6666667 30.55556

    10 Technician 3 9600 0 1200 0 200 11000 916.6666667 30.55556

    11 Technician & Driver 16200 21000 1200 1822.5 0 40222.5 3351.875 111.7292

    12 Technician 4 9600 0 1200 0 200 11000 916.6666667 30.55556

    13 jounir Engineer 21000 0 1200 2362.5 0 24562.5 2046.875 68.22917

    # Resource Name Head costs Annual Costs Operation Costs Cost / Year Cost / Month Cost / day

    1 Tool Box 1 600 0 0 600 50 1.666666667

    2 Tool Box 2 600 0 0 600 50 1.666666667

    3 Site Master 10000 750 0 10750 895.8333333 29.86111111

    4 Nemo Handy 1500 0 0 1500 125 4.166666667

    5 TEMS 3500 0 0 3500 291.6666667 9.722222222

    6 Laptop 1100 0 0 1100 91.66666667 3.055555556

    7 Car 21000 0 300 21300 1775 59.16666667

    8 iBwave 100000 5000 0 105000 8750 291.6666667

    9 Transmitter and Reciever 5000 0 0 5000 416.6666667 13.88888889

    10 Label machine 700 0 0 700 58.33333333 1.944444444

  • 8/18/2019 IBS Project - Cost report

    11/12

    In-Building Coverage Project 

     

    Overall Project Calculations

    Based on the previous estimated calculations here are the overall project calculation:

    WBS Task Name Resource Names Cost

    1  In-building Coverage Project LYD 38,838.60 

    1.1  Site Survey & Design  LYD 7,211.76 

    1.1.1  Site Survey  LYD 2,192.13 

    1.1.1.1 Building information Senior Engineer,Car[1] LYD 205.17

    1.1.1.2 Surrounding network information Senior Engineer,Laptop[1],TEMS[1],Car[1] LYD 217.95

    1.1.1.3 Draft solution design Laptop[1],iBwave[1] LYD 294.73

    1.1.1.4 Propagation MeasurmentsTransmitter and Reciever[1],RF Engineer

    1LYD 176.29

    1.1.1.5BTS, Microwave & Antenna

    locationTechnician 1,Senior Engineer,Car[1] LYD 235.73

    1.1.1.6 Cable routingTechnician 1,Senior Engineer,Technician

    2,Car[1]LYD 680.53

    1.1.1.7Photos of Ant. , BTS & MW

    locationsTechnician 1,Senior Engineer,Car[1] LYD 235.73

    1.1.1.8 Site survey report submitted Senior Engineer LYD 146.00

    1.1.1.9 Site survey report approved  Head of PMO LYD 0.00

    1.1.2  Design LYD 5,019.63 

    1.1.2.1 Import the layout to iBwave RF Engineer 2,iBwave[1] LYD 372.87

    1.1.2.2 Design building RF Engineer 2,iBwave[1] LYD 697.67

    1.1.2.3 Perform prediction iBwave[1],RF Engineer 1 LYD 372.87

    1.1.2.4 Generate reports iBwave[1],RF Engineer 1 LYD 372.87

    1.1.2.5Building Design complete and

    approvedHead of PMO,iBwave[1] LYD 2,232.79

    1.1.2.6 BoQ ready and approved Head of PMO LYD 970.56

    1.1.2.7Design complete and BoQ

    approved Head of PMO LYD 0.00

    1.2  Ordering & Delivery  LYD 17,672.32 

    1.3  Installation & Integration  LYD 12,191.93 

    1.4  Verification & Acceptance  LYD 1,762.59 

    1.5 Project Completed  LYD 0.00

  • 8/18/2019 IBS Project - Cost report

    12/12

    In-Building Coverage Project 

     

    Conclusion

    -  The clear forecast of the further projects helps us to decide to buy iBwave

    program which is the design software instead of designing the project using

    third party.

    -  Using the templates mitigate the mistakes and help to reduce the cost.

    -  By using genuine programs, and calibrated equipment influence the cost

    estimate and this is one of the cost estimates inputs which is project scope

    statements constraints.

    -  Determine the employees’ salaries influencing the cost estimates as a one of

    the enterprise environmental factors.

    -  WBS helps to get the estimation of the project more accurate.

    -  By taking the inputs of cost estimates into account, resulting the ability to

    determine the cost estimates to the project.