Click here to load reader
Click here to load reader
Real time feedback control of synchronous
generator.
Slim Tnani and Gerard Champenois
University of Poitiers
LAII-ENSIP
Poitiers, France
Email: [email protected]
Email: [email protected]
Emile MOUNI
Leroy Somer Motors
Angouleme France
Email: [email protected]
Abstract—Presently, the most synchronous generator’s excitersare based on the use a reverse synchronous generator whichfeeds the revolving field cross a three-phase diodes bridge. Thesestructures are often controlled by a traditional ProportionalIntegral Derivative controller. In this paper, a new excitationstructure using a permanent magnet synchronous generator ispresented and the synchronous generator output voltage controlis achieved by using a predictive strategy. The proposed structureallows not only to improve signal quality but thanks to theinvolved controller, some other interesting effects such as timeresponse reduction are also obtained. An experimental valida-tion is provided to illustrate the proposed structure efficiencycompared to the classical approach.
I. INTRODUCTION
In the normal operating mode of a synchronous generator
(SG), a main field is needed to produce energy on its terminals.
To do that, the machine’s revolving field is fed by direct cur-
rent provided by several approaches called excitation structures
which bases have been formulated in 60’s [1], [2]. In [3] pure
derivative excitation type is presented. This method consists in
deriving the SG’s output voltage by using transformers. This
last three-phase voltage is rectified via a Silicon Controlled
Rectifier (SCR) bridge generally controlled by a Proportional
Integral Derivative (PID) regulator and allows to force the
main SG output voltage to follow a pre specified reference.
Another excitation technique is the compound which combines
the above structure with power current transformers on each
phase [3] and diodes bridge. Nevertheless, both these struc-
tures require a starter system. In order to solve this problem,
companies choose to use a reverse SG coupled to the main
SG as given in Fig.1.
GS
If
LVf
A
B
Exc
Iex
Fig. 1. Synchronous generator classical excitation scheme
In this case, one deals with current source which is
combined with diodes bridge. Then the rectified voltage
is used to feed the main SG excitation winding. In order
to supply the reverse SG, several strategies are used. The
first consists in deriving voltage from the main SG terminal
and is called shunt type. This structure presents a low
short-circuit/overload capability. This explains why it is often
associated to a booster system. The second one is based on the
use of auxiliary windings rightly positioned among the main
windings (AREP:Auxiliary Winding Regulation Excitation
Principle). Thanks to this strategy, a source of energy is
created and allows feeding the exciter with appropriate current
whatever in load operation or in short-circuit one. The last
type uses a permanent magnet synchronous generator [4], [5],
[6] which is placed on the same shaft that the main machine.
Note that all these structures generally use a traditional PID
controller to find the right excitation current and even if they
provide interesting results, they face to limitations as regards
the signal quality and the time response. These limitations are
partially due to the excitation nature (current source) which
presents a very low dynamics.
Loadvf
Voltage sensors
references
PMSG
Thyristors
SG
Bridge
Controller
Fig. 2. Proposed control structure of the synchronous generator
In order to improve the machine performances, one proposes
a new excitation structure based on the use of a voltage source.
In this case, the above reverse SG or the pure derivative
Proceedings of the 2011 International Conference on Power Engineering, Energy and Electrical Drives Torremolinos (Málaga), Spain. May 2011
978-1-4244-9843-7/11/$26.00 ©2011 IEEE
excitation (current source) is replaced by a permanent magnet
synchronous generator (voltage source) and the traditional
diodes bridge by a thyristors one which triggers are controlled
thanks to modern algorithm. One proposed a new excitation
structure given by Fig.2. The central problem in control is to
find a technically feasible way to act on the given process
so that it adheres, as closely as possible to some desired
behaviour. Thanks to the use of voltage source coupled with
thyristors bridge, no free wheel phenomenon is noticed and
any control law is immediately effective.
In section II, a modeling of the synchronous generator is
presented. The predictive control method [7], [8], [9], [10]
strategy is already used in power electronics domains [11],
[12], [13] and have proved its effectiveness. We will not
develop these control method theory in the paper. The ex-
perimental test bench presentation, algorithms implementation
and results are given in section III. In this section special tests
are performed to check the validity of the proposed structure
compared to the classical one and a qualitative analysis ends
the paper.
II. CLASSICAL MODELING OF THE SYNCHRONOUS
GENERATOR
It is well known that the synchronous generator can be
described in three axes frame as follows [14], [15], [16], [17]:
vabc = −rs.iabc +ddtΨabc
vf = rf .if + ddtΨf
0 = rD.iD + ddtΨD
0 = rQ.iQ + ddtΨQ
(1)
The study will be done in Park’s framework thanks to Park’smatrix defined below according to θe. In this expression the
factor
√
2
3ensure the conseravtion of the instantaneous power
in the new frame.
P (θe) =
√
2
3
(
cos(θe) cos(θe −2π3) cos(θe +
2π3)
− sin(θe) − sin(θe −2π3) − sin(θe +
2π3)
)
such as:
P (θe).vabc = vdq (2)
Then, the equation (1) becomes
vd = −rs.id +ddtΨd − ωe.Ψq
vq = −rs.iq +ddtΨq + ωe.Ψd
vf = rf .if + ddtΨf
0 = rD.iD + ddtΨD
0 = rQ.iQ + ddtΨQ
J ddtωm = Te − Tr
(3)
Tr depends on the external load.
Te is expressed according to the machine current as given by
[14]:
Te =3
2p(Ψdiq −Ψqid) (4)
In this work, ωm is supposed to be constant. Indeed, in
the test bench which is being achieved for validating the
algorithms, the synchronous generator is involved by a DC
motor controlled by a double thyristors bridge motor drive
(WNTC4075 from Alstom Company). Thanks to a right con-
figuration of this last one, the speed can be considered as
constant during all the tests. The constant speed assumption
allows us to generate a model which suits very well to the
involved control strategy. A classical state space modeling of
the machine, taking into account the rated load (r1, l1),as given
in Fig.3, is considered:
r1, l1
r1, l1 r1, l1
vf
Fig. 3. Synchronous generator scheme with inside load
In the following, the currents in the three resistances (r1) are
represented by ia1, ib1, ic1 and those in the three inductances
(l1) by ia2, ib2, ic2. Thanks to this scheme, the output voltage
can be written in Park’s frame as follows:(
vdvq
)
=
(
0 −ωel1ωel1 0
)
.
(
id2iq2
)
+
(
l1 00 l1
)
.d
dt
(
id2iq2
)
or(
vdvq
)
=
(
r1 00 r1
)
.
(
id1iq1
)
=
(
r1 00 r1
)
.
(
id − id2iq − iq2
)
with:
(
id1iq1
)
= P (θe).
ia1ib1ic1
;
(
id2iq2
)
= P (θe).
ia2ib2ic2
(5)
Thus, the partial equation of the synchronous machine in the
Park’s frame is given by equation (6).
From this equation, the model can be written in the state
space modeling shape as follows:
x = Ax+Bu
y = Cx+Du(7)
where:
A = −M−1.R is the state matrix,
B = M−1.(
0, 0, 0, 0, 1, 0, 0)T
is the control matrix,
C =
(
−r1, 0, r1, 0, 0, 0, 00,−r1, 0, r1, 0, 0, 0
)
is the observation matrix,
D =
(
00
)
is the direct transmission matrix,
x =(
id2, iq2, id, iq, if , iD, iQ)T
is the state vector, y =
0000vf00
=
r1 −l1ωe −r1 0 0 0 0l1ωe r1 0 −r1 0 0 0r1 0 −(rs + r1) lqωe 0 0 −ωemsQ
0 r1 −ldωe −(rs + r1) ωemsf ωemsD 00 0 0 0 rf 0 00 0 0 0 0 rD 00 0 0 0 0 0 rQ
.
id2iq2idiqifiDiQ
+
l1 0 0 0 0 0 00 l1 0 0 0 0 00 0 −ld 0 msf msD 00 0 0 −lq 0 0 msQ
0 0 −msf 0 lf mfD 00 0 −msD 0 mfD lD 00 0 0 −msQ 0 0 lQ
.d
dt
id2iq2idiqifiDiQ
= R.
id2iq2idiqifiDiQ
+M.d
dt
id2iq2idiqifiDiQ
(6)
(
vd, vq)T
is the output voltage and u = vf is the control
vector.
For numeric application, the table III is considered. The
conversion method from these data (time constants, reactances)
to those involved in the state matrices (inductances, mutual
inductances,...) uses the classical electrical scheme. The reader
is referred to [18], [19] for more details on the transformation
procedure.
III. REAL TIME APPLICATION
A. Experimental test bench presentation
Several ways can be used for experimental implementation
of the control algorithm [20], [21], [22]. In our case a DSpace
architecture [23] is considered due to its flexibility, accuracy
and easy to take control.
The figure 4 gives an overview of the test bench involving the
main components used during the tests.
Equipment
User
Process
dc motor PMSG SGLoad 1
RL
Load 2
RL or ASM
Tachometer Resolver
PD2
PD3
Source
3ph
50Hz
Emergency
control
speed
+ −
Reference
Ωref
Ωmes
Cond
PD3
Arcos
α
DAC
Algorithmcontrol
Control desk
referenceVoltageparameters
ControllersVisualizationvs, is, vf , if
Iex
Command
Measurement system
(VISION R©)
Cond Cond Cond
Cond
if vf
ADC
ADC
ADC
ADC
if
vf
Ωmes vs is vf if
output files
vs, is, vf , if et Ωmes
33
DSpace +PC
2
3
: digital signal
Legend
: Analogue signal
vs
is
: Power
vfif
vsis
is
3
r2ci
Parameters references
θ
6
Idcm 3
3 3
3 3
stop
(AU)
speed
Fig. 4. Experimental test bench scheme
As we can see on this scheme, the process is composed of
3 machines: the main SG, a permanent magnet synchronous
generator (PMSG) equipped with a resolver for mechanical
angle measurement and a DC motor involving the two first
machines at rated speed thanks to a motor drive. Resis-
tances/inductances load (RL) and Asynchronous motor (ASM)
are used to performed tests.
In order to allow the process to work porperly, equipment is
used. It consists in several electronics circuits (cond, DAC,
ADC, r2ci on Fig.4) which interface the analogue environ-
ment with the DSpace. For example the circuit r2ci allows
transforming the resolver output signal to coder data required
by the DSpace. Then, thanks to the information on the shaft
angle, all calculations can be done in Park framework using
controller parameters, voltage sensing and references.
From these calculations a firing angle is generated for the
thyristors bridge connected to the PMSG terminal and then the
main SG can be fed with the right excitation current depending
on the machine output voltage.
To perform tests such as impact load and shedding test, Load
1 and/or load 2 are used. During all the tests, a powerful
measurement instrument (VISION R©) is used to record data
in files.
Fig.5 depicts the global test bench with apparatus.
Fig. 5. Global experimental test bench
The main components of the experimental test bench can
be listed as follows
• The WNTC4075 thyristors converter is a motor drive
which controls the DC motor in order to maintain the
mechanical speed on the shaft to 1500rpm. Then the main
SG output voltage’s frequency is about 50Hz (the main
SG is a 4-poles machine).
• The passive variable load is composed by a 6KW
variable active power and a 6KVAR variable reactive
power and is connected to the main SG terminals.
• The Dspace 1104 and controldesk: they allow to im-
plement developed algorithms. The generator’ states are
given to the controldesk via Currents and voltages
sensors.
• The Vision: it is a 16 channels measurement instrument
allowing to record data during the tests.
The predictive controller has been implemented on
Matlab/SimulinkTM and downloaded in the DSpace 1104.
In the following section, several results will be given and
discussions on the validity of the excitation structures and
controllers will be done.
B. Load impact and shedding load tests
The main test, used to validate the proposed structure is
the load impact and shedding one. To do that the main
synchronous generator is involved at rated speed until it
reaches its rated state in terms of output voltage. Then a load
impact is performed. When the system reaches again its steady
state a shedding test is done to bring it back to its initial state.
In order to get a right comparison between the two structures,
the experimental conditions have been the same. The table I
gives the electric conditions before and during the load impact
test.
TABLE IEXPERIMENTAL CONDITIONS
P(kW) S(kVA) Q(kVAR) PF I(A)
Before 0.81 3.99 3.91 0.2 5.8
After 1.53 7.18 7.01 0.21 10.5
By considering this table, one can notice that this test
induces a current increase from 5.8 A to 10.5 A (roughly
the rated current as given in Table III) corresponding to a
50% increase of the rated apparent power. The two following
figures give the phase currents and voltages during load impact
and shedding test according to the involved control structure.
2 2.5 3 3.5 4 4.5 5
−1
−0.5
0
0.5
1
Phase voltage (p.u)
2 2.5 3 3.5 4 4.5 5−20
−10
0
10
20
Time(s)
phase current (A)
load impact shedding test
Fig. 6. Phase voltage and current with proposed structure
0.5 1 1.5 2 2.5 3 3.5
−1
−0.5
0
0.5
1
Phase voltage (p.u)
0.5 1 1.5 2 2.5 3 3.5−20
−10
0
10
20
Time(s)
phase current (A)
load impact shedding test
Fig. 7. Phase voltages and current with classical structure
The next figure denotes a comparison of phase-to-phase rms
voltage depending on the involved excitation structure.
0.5 1 1.5 2 2.5 3 3.5 40.7
0.8
0.9
1
1.1
Urms(p.u)
2 2.5 3 3.5 4 4.5 5 5.50.7
0.8
0.9
1
1.1
Time(s)
Urms(p.u)
Proposed structure
Classical structure
Fig. 8. Comparison between phase-to-phase rms voltage
During the load impact test, a little voltage drop is noticed
on Fig.6. Thanks to the predictive controller and the excitation
structure, this disturbance is rejected in about 120 millisec-
onds. As regards the output current, it rightly corresponds to
what we were supposed to get with this kind of test. When
the system reaches again its steady state in terms of output
voltage, a shedding test is performed to bring back the system
to its initial state. This induces a voltage overshoot which is
also quickly eliminated by the predictive controller.
The Fig.7 denotes the generator behaviour under the same
conditions as those presented by Fig.6. The voltage drop is
more important even if the overshoot is not very different.
When a load impact is performed, the system takes more
time to reach its steady state (roughly 300 milliseconds).
The current’ shape and magnitude are very similar to those
presented in Fig.6. By observing the voltage on the Fig.7, one
can notice a poor signal quality due to the excitation structure.
This is confirmed in Fig.8. In this last figure the superiority of
the proposed structure and control is checked as regards the
time response, voltage overshoot/drop and signal quality.
During the modeling process, one has assumed that the rota-
tion speed is considered as constant. Fig.9 allows to confirm
this assumption.
2 2.5 3 3.5 4 4.5 50.5
0.6
0.7
0.8
0.9
1
1.1
Time(s)
Mechanical speed (p.u)
Load impact Shedding test
Fig. 9. Mechanical speed during load impact and shedding test
This figure is recorded during the load impact and shedding
test and the data are given in p.u (1 p.u corresponds to
1500rpm). Thanks to the use of the motor drive, the speed
drop and overshoot can be considered are negligible during
the tests.
C. Results analysis
In the following table, Tr denotes the time response in
milliseconds which corresponds to the necessary time for the
system to reach again its steady state after a disturbance.
Or and Dr are respectively the relative voltage overshoot
and drop compared to the rated output voltage. In order to
examine the output signals quality, the voltage and current
THD are given respectively by THDv and THDc.
The Table II shows data during the load impact and shedding
test.
TABLE IIRESULTS FOR LOAD IMPACT AND SHEDDING TEST
Approaches Tr(ms) Or(%) Dr(%) THDc(%) THDv(%)Classical 300 4 12 1.12 5.41
Proposed 120 5 6 0.67 1.76
The new approach gives very satisfactory results compared
to the classical one. From time response to voltage THD, the
new method’s efficiency is noticeable. Both these tables allows
us to see that it is very interesting to use a voltage source
(PMSG) instead of current one (reverse SG) for synchronous
generator excitation. Thus, thanks to this structure, the output
voltage quality is strongly improved. The combination of such
a structure with a modern control strategy such as predictive
controller leads to interesting results as presented above.
IV. CONCLUSION
In this paper an original excitation structure for synchronous
generators is given. The particularity of such a structure is
based on the use of a voltage source (PMSG) combined
to thyristors bridge to feed the excitation winding instead
of the classical reverse SG combined with diodes bridge
which presents a low dynamics. To control this new structure,
one chooses a R S T type controller computed thanks to a
predictive strategy and using a classical synchronous gener-
ator model which integrates the rated load. The test bench
composed by electronics circuits, apparatus and a DSpace
1104 is presented and tests have been performed. The main
test presented in this paper is the load impact/shedding one.
The experimental results, comparing the proposed structure
and the classical one are presented. Thanks to these tests, one
has noticed that the new approach provides interesting results
as regards the signal distortion reduction and time response
improvement. These results show that improvements can be
obtained by right modification in the machine structure. The
next step of the study is the way to have a rotating thyristors
bridge and how it can be controlled by high frequency waves
for example. This will be an important innovation in electrical
machine performances improvement.
APPENDIX
Characteristics of the lsa371
The real time tests have been performed thanks to a syn-
chronous generator which parameters are given by Table III.
TABLE IIICHARACTERISTICS OF THE LSA371 4-POLES
Labels Values
Rated Power Sn (KVA) 7.5Stator resistance rs (Ω) 1.19Rotor resistance rf (Ω) 3.01Phase-to-phase rated voltage Urms (V) 400Direct synchronous reactance xd (p.u) 1.4Transverse synchronous reactance xq (p.u) 0.7
Open-circuit Transient time constant T′
do(ms) 522
Direct transient synchronous reactance x′
d (p.u) 0.099
Direct sub transient synchronous reactance x′′
d (p.u) 0.049
Direct transient time constant T′
d (ms) 40
Direct sub transient time constant T′′
d (ms) 3.7Armature time constant Ta (ms) 6
NOMENCLATURE
vabc machine three-phase voltage
vf main field voltage
iabc machine three-phase current
if main field current
id, iq stator direct and transverse currents
iD, iQ direct and transverse dampers currents
Ψabc stator total flux
ΨD direct dampers total flux
ΨQ transverse dampers total flux
Ψf main field total flux.
rs stator phase resistance
rD, rQ direct and transverse dampers resistances
rf main field resistance
r1, l1 load resistance and inductance
ld, lq stator direct and transverse main inductances
lf main field main inductance
lD, lQ direct and transverse damper main inductances
msf stator and main field mutual inductance
mfD main field and direct damper mutual inductance
msQ stator and transverse damper mutual inductance
msD stator and direct damper mutual inductance
ωe, θe electrical speed and position
2p machine number of poles
ωm mechanical speed
Te electromechanical torque
Tr load torque
J machine inertia
P active power
Q reactive power
S apparent power
I root mean square phase current
PF power factor
REFERENCES
[1] rIEEE commitee Report, “Proposed excitation system definitions forsynchronous machines,” AIEE Transactions on power apparatus and
systems, vol. 80, pp. 173–180, 1961.
[2] rIEEE commitee Report, “Proposed excitation system definitions forsynchronous machines,” IEEE Transactions on power apparatus and
systems, vol. PAS-88, nr8, pp. 1248–1258, 1969.
[3] R. Schaefer, “Application of static excitation systems for rotating exciterreplacement,” in Pulp and Paper Industry Technical Conference, 1997.
[4] V. Vadher, I. Smith, and B. Fanthome, “Simulation of permanent magnetgenerator/rectifier combination,” IEEE Transactions on Aerospace and
Electronic Systems, vol. AES-22, Issue 1, pp. 64 – 70, 1986.[5] R. Esmaili and X. Longya, “Sensorless control of permanent magnet
generator in wind turbine application,” in 41st IAS Annual Meeting.
Conference Record of the 2006 IEEE Industry Applications Conference,
vol.4, 8-12 Oct., pp:2070 - 2075, 2006.[6] Z. Chen, “Compensation schemes for a scr converter in variable speed
wind power systems,” IEEE Transactions on Power Delivery, vol. 19,Issue 2, pp. 813 – 821, 2004.
[7] D. W. Clarke, C. Mohtadi, and P. Tuffs, “Generalized predictive controlpart 1. the basic algorithm,” Automatica, vol. 23, pp. 137–148, 1987.
[8] D. W. Clarke, C. Mohtadi, and P. Tuffs, “Generalized predictive controlpart 2. extensions and interpretations,” Automatica, vol. 23, pp. 149–160,1987.
[9] Y. XI, “New design method for discrete time multi-variable predictivecontrollers,” International Journal of Control, vol. 49, pp. 45–56, 1989.
[10] S.-M. Moon, R. Clark, and D. Cole, “The recursive generalized predic-tive feedback control: theory and experiments,” Journal of Sound and
Vibration, vol. 279, pp. 171–199, 2005.[11] H. Abu-Rub, J. Guzinski, Z. Krzeminski, and H. Toliyat, “Predictive
current control of voltage-source inverters,” IEEE Transactions on
Industrial Electronics, vol. 51, Issue 3, pp. 585 – 593, 2004.[12] P. Cortes, A. Wilson, S. Kouro, J. Rodriguez, and H. Abu-Rub, “Model
predictive control of cascaded h-bridge multilevel inverters,” in 13th
European Conference on Power Electronics and Applications, 2009.[13] G. Abad, M. Rodriguez, and J. Poza, “Two-level vsc-based predictive
direct power control of the doubly fed induction machine with reducedpower ripple at low constant switching frequency,” IEEE Transaction on
Energy Conversion, vol. 23, Issue 2, pp. 570 – 580, 2008.[14] P. C. Krause, oleg Wasynczuk, and S. D. Sudhoff, Analysis of electric
machinery. IEEE Press, 1994.[15] F. Bruck and F. Himmelstoss, “Modelling and simulation of synchronous
machine,” in IEEE computers in power electronics, 1998.[16] T. Sebastien, G. R. Slemon, and M. Rahman, “Modelling of permanent
synchronous motors,” IEEE transactions on magnetics, Vol. Mag-22, No.
5, 1986.[17] E. Mouni, S. Tnani, and G. Champenois, “Comparative study of three
modelling methods of synchronous generator,” in Conference of the
IEEE Industrial Electronics Society, Paris, France, 2006.[18] E. Mouni, S. Tnani, and G. Champenois, “Synchronous generator mod-
elling and parameters estimation using least squares method,” SimulationModelling Practice and Theory., vol. 16, Issue 6, pp. 678–689, 2008.
[19] J. Verbeeck, Standstill frequency response measurement and identific-
taion methods for synchronous machines. PhD thesis, Vrije Unversiteit,Brussel., 2000.
[20] G. Parma and V. Dinavahi, “Real-time digital hardware simulation ofpower electronics and drives,” IEEE Transactions on Power Delivery,vol. 22, Issue 2, pp. 1235 – 1246, 2007.
[21] S.-J. Huang, T.-M. Yang, and J.-T. Huang;, “Fpga realization of wavelettransform for detection of electric power system disturbances,” IEEE
Transactions on Power Delivery, vol. 17, Issue 2, pp. 388 – 394, 2002.[22] Y. Chen and V. Dinavahi, “Fpga-based real-time emtp,” IEEE Transac-
tions on Power Delivery, vol. 24, Issue 2, pp. 892 – 902, 2009.[23] E. Mouni, S. Tnani, and G. Champenois, “Synchronous generator output
voltage real-time feedback control via h∞ strategy,” IEEE Transactions
on Energy Conversion, vol. 24, Issue 2, pp. 329 – 337, 2009.