+ All Categories
Home > Documents > IEEE/PES Transformers Committee - IEEE-SA - Working...

IEEE/PES Transformers Committee - IEEE-SA - Working...

Date post: 26-May-2018
Category:
Upload: nguyentram
View: 215 times
Download: 0 times
Share this document with a friend
245
Transformers Committee Chair: Stephen Antosz Vice Chair: Sue McNelly Secretary: Bruce Forsyth Treasurer: Greg Anderson Awards Chair/Past Chair: Don Platts Standards Coordinator: Jim Graham IEEE/PES Transformers Committee Fall 2016 Meeting Minutes Vancouver, British Columbia, CANADA October 24, 2016 Unapproved (These minutes are on the agenda to be approved at the next meeting in Spring 2017)
Transcript

Transformers Committee

Chair: Stephen Antosz Vice Chair: Sue McNelly Secretary: Bruce Forsyth

Treasurer: Greg Anderson Awards Chair/Past Chair: Don Platts Standards Coordinator: Jim Graham

IEEE/PES

Transformers

Committee

Fall 2016 Meeting Minutes

Vancouver, British Columbia,

CANADA

October 24, 2016

Unapproved (These minutes are on the agenda to be approved at the next meeting in Spring 2017)

Page 2 of 56

TABLE OF CONTENTS

OPENING SESSION – MONDAY OCTOBER 24, 2016

1.0 Agenda

2.0 Attendance

3.0 Approval of Agenda and Previous Minutes – Stephen Antosz

4.0 Meeting Schedule

5.0 Chair’s Remarks & Report – Stephen Antosz

6.0 Vice Chair’s Report – Susan McNelly

7.0 Secretary’s Report – Bruce Forsyth

8.0 Treasurer’s Report – Gregory Anderson

9.0 Awards Report – Don Platts

10.0 Administrative SC Meeting Report – Stephen Antosz

11.0 Standards Report – Jim Graham

12.0 Editor’s Report – Sanjib Som

13.0 Liaison Reports

13.1. CIGRE – Raj Ahuja

13.2. IEC TC14 Technical Advisor to USNC – Phil Hopkinson

13.3. Standards Coordinating Committee, SCC No. 18 (NFPA/NEC) – David Brender

13.4. Standards Coordinating Committee, SCC No. 4 (Electrical Insulation) – Paulette Payne

Powell

14.0 Hot Topics for the Upcoming – Subcommittee Chairs

15.0 Opening Session Adjournment

CLOSING SESSION – THURSDAY OCTOBER 27, 2016

16.0 Chair’s Remarks and Announcements – Stephen Antosz

17.0 Meetings Planning SC Minutes & Report – Gregory Anderson

18.0 Reports from Technical Subcommittees (decisions made during the week)

19.0 Report from Standards Subcommittee (issues from the week)

20.0 New Business

21.0 Closing Session Adjournment

ANNEXES – MINUTES OF TECHNICAL SUBCOMMITTEES

Annex A. Bushings SC – Peter Zhao

Annex B. Dielectric Tests SC – Michael Franchek

Annex C. Distribution Transformers SC – Steve Shull

Annex D. Dry Type Transformers SC – Charles Johnson

Annex E. HVDC Converter Transformers & Reactors – Mike Sharp

Annex F. Instrument Transformers SC – Ross McTaggart

Annex G. Insulating Fluids SC – David Wallach

Annex H. Insulation Life SC – Sheldon Kennedy

Page 3 of 56

Annex I. Meetings SC – Greg Anderson

Annex J. Performance Characteristics SC – Ed teNyenhuis

Annex K. Power Transformers SC – Joe Watson

Annex L. Standards SC – Jerry Murphy

Annex M. Underground Trans & Network Protectors SC – Dan Mulkey

APPENDIXES – ADDITIONAL DOCUMENTATION

Appendix 1 – Meeting Schedule

Appendix 2 – Semi-Annual Standards Report

Page 4 of 56

Monday Opening Session

1.0 AGENDA

Opening Session

Monday, October 24; 8:00 am - 9:15 am

(rosters circulated and attendance recorded as eligibility for Committee membership)

1. Welcome and Announcements ..................................................................... Stephen Antosz

2. Meeting Minute .............................................................................................. Greg Anderson

3. Approval of Agenda ...................................................................................... Stephen Antosz

4. Approval of Minutes from Spring 2016 Meeting ......................................... Stephen Antosz

5. Chair’s Report & Administrative Subcommittee Report .............................. Stephen Antosz

6. Transformers Committee Member Vote on O&P and WG P&P ................... Stephen Antosz

7. Vice Chair’s Report ...................................................................................... Sue McNelly

8. Secretary's Report ......................................................................................... Bruce Forsyth

9. Treasurer's Report ......................................................................................... Greg Anderson

10. Standards Report ........................................................................................... Jim Graham

11. Editor’s Report .............................................................................................. Sanjib Som

12. Liaison Representative Reports

12.1. CIGRE .............................................................................................. Raj Ahuja

12.2. IEC TC-14 Technical Advisor to USNC ......................................... Phil Hopkinson

12.3. Standards Coordinating Committee, SCC No. 18 (NFPA/NEC) ..... David Brender

12.4. Standards Coordinating Committee, SCC No. 4 (Elect. Ins’n) ........ Paulette Payne Powell

13. Hot Topics for the Upcoming Week ............................................................. Subcommittee Chairs

14. New Business & Wrap-up ............................................................................ Stephen Antosz

Closing Session

Thursday, October 27, 11:00 am - 12:00 pm

1. Chair's Remarks and Announcements .......................................................... Stephen Antosz

2. Meetings Planning Subcommittee ................................................................ Greg Anderson

3. Reports from Technical Subcommittees (decisions made during the week)

3.1 Standards ........................................................................................... Jerry Murphy

3.2 Underground Transformers & Network Protectors ......................... Dan Mulkey

3.3 Bushings ........................................................................................... Peter Zhao

3.4 Dielectric Tests ................................................................................ Ajith Varghese

3.5 Distribution Transformers ................................................................ Steve Shull

3.6 Dry Type Transformers ................................................................... Chuck Johnson

3.7 HVDC Converter Transformers & Reactors .................................... Mike Sharp

3.8 Instrument Transformers .................................................................. Ross McTaggart

3.9 Insulating Fluids .............................................................................. David Wallach

Page 5 of 56

3.10 Insulation Life .................................................................................. Sheldon Kennedy

3.11 Performance Characteristics ............................................................ Ed teNyenhuis

3.12 Power Transformers ......................................................................... Joe Watson

4. Additional Report from Standards Subcommittee (issues from the week) ... Jim Graham

5. New Business (continued from Monday) and Wrap-up ............................... Stephen Antosz

Page 6 of 56

2.0 ATTENDANCE

2.1 COMMITTEE MEMBER ATTENDANCE

Legend:

CM Committee Member

CM-LM Committee Member-IEEE Life Member

CM-EM Committee Member-Emeritus

Committee Member Attendance (Red designates CM added at present meeting)

Member

Type Name Company Mon Thu

CM Ahuja, Raj Raj Ahuja Consulting

CM Anderson, Gregory GW Anderson & Associates, Inc. X X

CM Ansari, Tauhid Haque ABB Inc. X

CM Antosz, Stephen Stephen Antosz & Associates, Inc X X

CM Arteaga, Javier ABB Inc. X X

CM-LM Ayers, Donald Ayers Transformer Consulting X X

CM Ballard, Robert Schaffner X X

CM Balma, Peter Retired

CM Beaster, Barry H-J Enterprises, Inc. X X

CM Beauchemin, Claude TJH2b Analytical Services X X

CM Betancourt, Enrique Prolec GE

CM Blaydon, Daniel Baltimore Gas & Electric X X

CM-LM Boettger, William Boettger Transformer Consulting LLC X X

CM Boman, Paul Hartford Steam Boiler X

CM Brender, David Copper Development Assn. X X

CM Bromley, Adam Fort Collins Utilities X X

CM Callsen, Thomas Weldy-Lamont Associates X

CM Castellanos, Juan Prolec GE X X

CM Chiu, Bill Southern California Edison X X

CM Claiborne, C. Clair ABB Inc. X

CM Colopy, Craig EATON Corporation X X

CM Crotty, John Ameren X X

CM Damico, Frank TAMINI Transformers USA X

CM Davis, Eric Burns & McDonnell X

CM Del Rio, J. Arturo Trench Limited X X

CM Denzer, Stephanie General Electric X X

CM Dix, Larry Quality Switch, Inc. X X

CM Dorris, Don Nashville Electric Service

CM-LM Elliott, Fred Retired X X

CM-LM Fairris, James KMS Electrical Products X

CM Faulkenberry, Michael Georgia Power Co. X

CM Feghali, Pierre N. American Substation Services

CM-LM Foldi, Joseph Foldi & Associates, Inc. X

CM Forsyth, Bruce Weidmann Electrical Technology X X

CM Franchek, Michael Weidmann Electrical Technology X X

CM-LM Ganser, Robert Transformer Consulting Services X

CM Garcia, Eduardo Siemens X X

CM Gaytan, Carlos Prolec GE X

CM Ghafourian, Ali H-J Enterprises, Inc, X

Page 7 of 56

Committee Member Attendance (Red designates CM added at present meeting)

Member

Type Name Company Mon Thu

CM Ghosh, Saurabh Essex Group Inc. X

CM-LM Girgis, Ramsis ABB Inc. X

CM Graham, James Mott MacDonald, Inc. X X

CM Griesacker, Bill Doble Engineering Co. X

CM Gromlovits, Mark EMC OEM Products Division X

CM Hachichi, Said Hydro-Quebec X

CM Hakim, Shamaun CG Power Systems USA Inc. X

CM Hardin, Michael H-J Enterprises, Inc. X

CM Harley, John FirstPower Group LLC X

CM Hayes, Roger General Electric X X

CM Hernandez, Ronald Doble Engineering Co. X

CM Herz, Josh Qualitrol X X

CM Hochanh, Thang Surplec HV Solutions X X

CM Hoffman, Gary Advanced Power Technologies X

CM Holifield, Thomas Howard Industries X X

CM-LM Hopkinson, Philip HVOLT Inc. X X

CM Jordan, Stephen Tennessee Valley Authority X X

CM Kaineder, Kurt Siemens AG X

CM-LM Kennedy, Gael GR Kennedy & Associates LLC X X

CM Kennedy, Sheldon Niagara Transformer X X

CM King, Gary Howard Industries X X

CM Kinner, Robert FirstPower Group LLC X

CM Kiparizoski, Zan Howard Industries X

CM Klaponski, Brian Carte International Inc. X X

CM Kraemer, Axel Maschinenfabrik Reinhausen X X

CM Kulasek, Krzysztof ABB Inc. X

CM-LM Lackey, John PowerNex Associates Inc. X X

CM Lau, Michael Weidmann Electrical Technology X X

CM Levin, Aleksandr Weidmann Electrical Technology X X

CM Li, Weijun Braintree Electric Light Dept. X X

CM Lopez-Fernandez, Xose Universidade de Vigo X X

CM-LM Marek, Richard DuPont X X

CM Matthews, Lee Howard Industries X X

CM McClure, Phillip Weschler Instruments X

CM McNelly, Susan Xcel Energy X X

CM McShane, Charles Patrick Cargill, Inc. X X

CM McTaggart, Ross Trench Limited X

CM Mehrotra, Vinay SPX Transformer Solutions, Inc. X X

CM Melle, Thomas HIGHVOLT X X

CM Millward, Paul Utility Equip Consulting X X

CM Mukerji, Amitav Consultant X

CM Mulkey, Daniel Mulkey Engineering Inc X X

CM Murphy, Jerry Reedy Creek Energy Services X X

CM Murray, David Tennessee Valley Authority X X

CM Narawane, Aniruddha CG Power Systems USA Inc. X

CM Parkinson, Dwight EATON Corporation X

CM Patel, Poorvi ABB Inc. X X

CM Patel, Sanjay Smit Transformer Sales, Inc. X

Page 8 of 56

Committee Member Attendance (Red designates CM added at present meeting)

Member

Type Name Company Mon Thu

CM Payerle, George Carte International Inc. X X

CM Penny, Brian American Transmission Co. X X

CM Perjanik, Nicholas Weidmann Electrical Technology X X

CM Perkins, Mark ABB Inc. X

CM Pezzin, Justin IFD Corporation X X

CM Platts, Donald OMICRON electronics Corp USA X X

CM Ploetner, Christoph ABB AG X X

CM Pointner, Klaus Trench Austria GmbH X X

CM Poulin, Bertrand ABB Inc. X X

CM Prevost, Thomas OMICRON electronics Corp USA X

CM Radbrandt, Ulf ABB AB X X

CM Rasco, Jimmy Ergon, Inc. X

CM Rave, Martin ComEd X

CM Ray, Jeffrey JLR Consulting, Inc. X

CM Recksiedler, Leslie Manitoba Hydro X

CM Reed, Scott MVA Diagnostics, Inc. X

CM Riffon, Pierre Pierre Riffon Consultant Inc. X

CM Robalino, Diego Megger X X

CM Roussell, Marnie Entergy X X

CM Sampat, Mahesh EMS Consulting Inc. X

CM Sauer, Daniel EATON Corporation X X

CM Schappell, Steven SPX Transformer Solutions, Inc. X X

CM Schroeder, Stephen ABB Inc. X

CM Schweiger, Ewald Siemens AG X

CM Sewell, Adam Quality Switch, Inc. X X

CM Sewell, Jeremy Quality Switch, Inc. X X

CM-LM Sharma, Devki Entergy X X

CM Sharp, Michael Trench Limited X X

CM Sharpless, Samuel Rimkus Consulting Group X X

CM Shekelton, James H-J Enterprises, Inc.

CM Shertukde, Hemchandra University of Hartford X X

CM Shull, Stephen The Empire District Electric Co. X X

CM Sizemore, Thomas ABB Inc. X X

CM Smith, Edward H-J Enterprises, Inc. X X

CM Snyder, Steven ABB Inc. X X

CM Solano, William Siemens Energy X

CM Som, Sanjib Pennsylvania Transformer X X

CM-LM Stahara, Ronald Stahara Consulting X X

CM Stiegemeier, Craig ABB Inc. X

CM Sweetser, Charles OMICRON electronics Corp USA X

CM Swinderman, Craig Mitsubishi Electric Power Products X X

CM Tanaka, Troy Burns & McDonnell X X

CM Tarlapally, Susmitha ABB Inc. X

CM-LM Tendulkar, Vijay ONYX, a Division of Smiths Power X

CM teNyenhuis, Ed ABB Inc. X X

CM Termini, Giuseppe PECO Energy Company X X

CM Thompson, James T&R Service Company

CM Thompson, Robert RST Consulting, P.C. X

Page 9 of 56

Committee Member Attendance (Red designates CM added at present meeting)

Member

Type Name Company Mon Thu

CM Tostrud, Mark Dynamic Ratings, Inc. X X

CM Traut, Alan Power Partners X X

CM Trummer, Edgar Transatlantic Transformer Consulting X X

CM Varghese, Ajith SPX Transformer Solutions, Inc. X X

CM Vedante, Kiran Meramec Instrument Transformer Co. X X

CM Verdolin, Rogerio Verdolin Solutions Inc. X X

CM Vijayan, Krishnamurthy PTI Manitoba Inc. X X

CM Vir, Dharam SPX Transformer Solutions, Inc. X X

CM-LM Walia, Sukhdev EATON Corporation X

CM Wallace, David ABB Inc. X X

CM Wallach, David Duke Energy X X

CM Watson, Joe JD Watson and Associates Inc. X X

CM Weisensee, Matthew PacifiCorp X X

CM Wicks, Roger DuPont X

CM-LM Wilks, Alan Consultant X X

CM Yu, Jennifer Pacific Gas & Electric X

CM Zhang, Shibao PCORE Electric

CM Ziomek, Valdemar PTI Manitoba Inc. X X

Total Members present: 145 93

% of Members Present of 219 members: 66.2 42.4

Based upon the above attendance totals:

Quorum was achieved at Monday Opening Session.

Quorum not achieved at Thursday Closing Session.

Page 10 of 56

2.2 GENERAL ATTENDANCE

Legend:

AP Active Participant

AP-LM Active Participant-IEEE Life Member

II Interested Individual

II-LM Interested Individual-IEEE Life Member

PCM Past Committee Member

General Attendance

Member

Type Name Company Mon Thu

II Abbott, Scott PPG Industries

II Abdelkamel, Hamid Ameren X

II Abril, Vladimir ABB Inc. X

AP Ahmed, Omar Transformer Protector Corp X X

II Aikens, Thomas Virginia Transformer Corp.

AP Allen, Jerry Metglas, Inc.

II Alonso, Mario Georgia Transformer X X

II Alvarado, Natasha IEEE

II Alvarado, Natasha X

II An, Kyung Chan Hyosung X X

II Antosz, Steve Pennsylvania Transformer X X

AP Antweiler, James Schneider Electric X

AP Armstrong, James Siemens Energy

II Armstrong, Rodney Mitsubishi Electric Power Products X

II Attard, Jason Con Edison X

II Audouard, Bernard M.S. Resistances

II Avarguez, Jean-Baptiste X

AP Averitt, Ralph Reinhausen Mfg. X

AP Baranowski, Derek Baron USA, Inc.

II Barnes, Jeff Norplex-Micarta X

AP Barnes, Michael Retired (Qualitrol)

AP Bartek, Allan C-K Composites X

II Basel, Cheryl CG Power Systems USA Inc.

AP Baumgartner, Christopher We Energies X X

II Bayman, Greg Mitsubishi Electric Power Products X

II Beaudoin, Jason Weidmann Electrical Technology X X

AP Behrens, Tammy SPX Transformer Solutions, Inc.

II Bekmezian, Sevag Southern California Edison X

AP Bell, Myron Delta Star Inc. X

AP Benach, Jeffrey Weidmann Electrical Technology

II Bentley, Logan Stark International X

II Berler, Daniel ZTZ Services International X

AP Bernesjo, Mats ABB Inc. X

II Bidwell, David Qualitrol X X

AP Bigham, Lee Instrument Transformer Equip Corp X

AP Blackmon, Jr., James Georgia Power Co. X

II Blackwell, Zack TCI Sales, Inc.

II Blake, Dennis Pennsylvania Transformer

II Blankenbeckler, Nicole DuPont

Page 11 of 56

General Attendance

Member

Type Name Company Mon Thu

II Blaszczyk, Piotr The Specialty Switch Co LLC X

II Blew, David PSE&G X X

II Boege, Alan X

AP Bolliger, Alain HV Technologies, Inc. X

II Bolliger, Dominique HV Technologies, Inc. X

II Bozich, Bradford Cargill, Inc.

II Bradford, Ira Pennsylvania Transformer X

II Bradshaw, Jeremiah Bureau of Reclamation X

AP Brafa, John ABB Inc. X X

AP Brasher, Jon ABB Inc.

AP Bressan, Natalia Siemens Energy

II Brett, John Delta-X Research Inc. X

AP Brinkman, Steve Cindus Corp. X

AP Britton, Jeffrey Phenix Technologies, Inc. X X

II Brown, Chris X

AP Brown, Darren Howard Industries X X

II Bruno, Mirvil X

II Brusetti, Robert Doble Engineering Co. X

II Brzoznowski, Steven Bonneville Power Administration X

II Burkes, Klaehn Savannah River Nat. Laboratory X

AP Cai, Jim JSHP Transformer X

II Cameron, Stephen Siemens AG X

AP Campbell, James Dominion X X

AP Cantrell, Rick M&I Materials, Inc. X

AP Caskey, John NEMA

AP Castillo, Alonso M&I Materials, Inc.

II Caverly, David Trench Limited X X

II Chakraborty, Arup Delta Star Inc. X X

II Chambers, Stuart Powertech Labs Inc. X

II Chapa, Raymundo WEG Electric Corp. X

AP Cheatham, Jonathan General Electric X

AP Cheim, Luiz ABB Inc. X

II Chen, Binzhan BC Hydro X

AP Chiang, Solomon The Gund Company X X

II Chiodo, Vincent HICO America X

AP Chisholm, John IFD Corporation X

AP Christodoulou, Larry Electric Power Systems X X

AP Chrysler, Rhett ERMCO X X

AP Clonts, Jermaine Power Partners X X

AP Collin, Jean-Francois Nomos Systems X

II Cooke, Henry ABB Inc. X X

II Corsi, Domenico Doble Engineering Co. X X

AP Costa, Florian Corimpex USA, Inc.

AP Cox, Paul GE Grid Solutions

II Craig, Douglas Richards Manufacturing Co.

AP Craven, Michael Phoenix Engineering Services X X

II Cruz Cienfuegos, Jorge Partner Technologies Inc.

AP Cunningham, Kelcie Delta Star Inc.

Page 12 of 56

General Attendance

Member

Type Name Company Mon Thu

II Dahlke, Michael Central Moloney, Inc. X X

II Dauzat, Thomas General Electric X

AP Dave, Nikita Georgia Transformer X

AP Davydov, Valery Mr. Valery Davydov X X

II del Valle, Yamille NEETRAC X X

II DelValle, Ruben NV Energy

II Dennis, Scott ABB Inc.

II DeRouen, Craig ERMCO X X

AP Dhawan, Anil ComEd X

II Di Biase, Antonio Tempel X

AP Diaby, Mohamed ABB Inc. X X

II Dicks, Michael PPL Electric Utilities X X

AP Digby, Scott Duke Energy X

AP Dorpmanns, Luc Royal SMIT Transformers B.V. X

II Dorsten, James Alabama Power X X

AP Drees, Terry Cindus Corp. X

II Drobnick, Jason Jordan Transformer X

AP-LM Dukarm, James Delta-X Research Inc. X

II Dulac, Hakim Qualitrol X X

AP Ebbert, Alexander HICO America

II Elassad, Yann M.S. Resistances

AP Elliott, Will General Electric X

II Emry, Greg IFD Corporation

II Epperson, Hazel ME Consultants, LLC X

II Faherty, Joseph OTC Services X

II Fattal, Feras Manitoba Hydro X X

AP Faulkner, Mark EATON Corporation X

AP Fedor, Ken Smit Transformer Sales, Inc. X

II Fenton, Roger City of Riverside X

PCM Ferreira, Marcos Advisian-Worley Parsons X

AP Field, Norman Teshmont Consultants LP X X

II Fields, Ryan E. Kentucky Power Cooperative X X

AP Flores, Hugo CG Power Systems USA Inc. X

II Foata, Marc Maschinenfabrik Reinhausen X

II Fombang, Emmanuel American Electric Power X X

II Ford, Seaira Baron USA, Inc.

II Foschia, John SPX Transformer Solutions, Inc. X

II Franchitti, Anthony PECO Energy Company X X

II Friend, Fredric American Electric Power X X

AP Frimpong, George ABB Inc. X

AP Frotscher, Rainer Maschinenfabrik Reinhausen

AP Gagnon, Jean-Francois Siemens Transformers Canada

II Gamboa, Jose Siemens Energy X X

II Gao, Addie BC Hydro X

AP Garcia, Benjamin Southern California Edison X

AP Garcia, Victor Siemens X X

II Garrity, Jonathan Tagup X

II Gaun, Alexander Coil Innovation X

Page 13 of 56

General Attendance

Member

Type Name Company Mon Thu

AP Geibel, David ABB Inc. X X

II Giang, Rebecca Sherwin-Wiiliams Co.

AP Golner, Thomas SPX Transformer Solutions, Inc. X X

AP Gonzalez de la Vega, Jorge Orto de Mexico X

II Goydich, Shane Roechling X

AP Gragert, Jeffrey Xcel Energy X X

AP Gross, Detlev Power Diagnostix X X

AP Guilbault, Frank Cogent Power Inc. X

AP Guner, Ismail Hydro-Quebec X X

AP Hamilton, Kendrick Power Partners X X

AP Harden, Kenneth Schneider Electric X X

AP Harder, Steven Siemens Energy

AP Harrison, Ken N. American Substation Services

AP Hartmann, Thomas Delta Star Inc. X

II Henault, Paul IFD Corporation

II Herman, Bryan Isberg-Nott X

II Hirayama, Jun Vicksmetal Company X

II Hochreiter, Erich Siemens AG X

II Holden, Andrew Ergon, Inc. X

II Holleran, Joseph Ameren X

AP Holmes, Jill Bureau of Reclamation X

II Huang, Chengjun Power Monitoring & Diagnostic Technology X X

II Huang, Yao-Te Hitachi Fortune Transformer, Inc. X X

II Humphrey, Eric Electro Composites ULC

II Jain, Mike Powertech Labs Inc. X

AP Jakob, Fredi Consultant X

AP Jarman, Paul National Grid X X

AP Jaroszewski, Marion Delta Star Inc. X X

II Jensen, Darin Hitachi T&D Solutions, Inc.

AP Johannson, Larry T&D Products Ltd.

AP John, John Virginia Transformer Corp. X X

II Johnson, Reeve ABB Inc.

AP Johnstone, Ted Cogent Power Inc. X X

II Joshi, Akash Black & Veatch X X

AP Joshi, Arvin General Electric X

II Kalicki, Tomasz Hydro One X

AP Kampshoff, Ken Equisales X X

AP Kang, Jinho Hyundai Heavy Industries X X

II Karim, Ibrahim Salt River Project X

II Kelley, Robert N. American Substation Services

II Kessler, Stacey Basin Electric Power Cooperative X X

AP Kirchenmayer, Egon Siemens AG X

AP Kirchner, Lawrence Siemens Industry X

II Kleine, Peter US Army Corps of Engineers X

II Knapp, Catherine Cogent Power Inc. X

II Kopf, Jon Power Asset Recovery Corp.

AP Kornowski, Marek Polycast International X

II Koshel, Anton Delta Star Inc. X

Page 14 of 56

General Attendance

Member

Type Name Company Mon Thu

II Kostich, Nicholas Ameren X

AP Kranich, Neil Jordan Transformer X

II Kuppuswamy, Raja Dynamic Ratings Inc. X X

AP Kurth, Bernhard Reinhausen Mfg. X

AP Lachman, Mark Doble Engineering Co. X X

II Lamorey, Maria PPG Industries

AP Larochelle, David NDB Technologies X

II Larzelere, William Evergreen High Voltage X

II Lavallee, Laurie IFD Corporation

II Leal, Fernando Prolec GE X

AP Leal, Gustavo Dominion Virginia Power X

II Lee, Jongwon X

II Lee, Shawn HICO America

II Lee, So-young Hyundai Heavy Industries X X

AP Leishman, Gary American Electric Power X X

II Leite, Andre Toshiba

II Leitgeb, Mario Siemens AG X

II Leutwyler, Irina ABB Switzerland Ltd. Micafil

II Levi, Raka AMforum X

II Li, Qian Powertech Labs Inc.

II Lin, David IFD Corporation X X

II Lively, Parry Tempel X

AP Livingston, Kerry Great River Energy X X

II Lobo, Gregorio Mitsubishi Electric Power Products X X

AP Locarno, Mario Doble Engineering Co. X

AP Lopes, Ana Efacec Energia, SA

II Lopez, J. Benjamin --

II Lugge, Andrew Mitsubishi Electric Power Products X

AP Luksich, John Cargill, Inc. X

II Luo, Shawn Seattle City Light X

II Ma, William BC Hydro X

II Macdonald, Nigel Trench Limited X

AP Macias, Alejandro CenterPoint Energy X X

II Malde, Jinesh M&I Materials, Inc. X

AP Mango, Joseph NextEra Energy Resources

II Mansuy, Bruno Trench France SAS X X

AP Marquardt, Bryan AK Steel X

AP Martin, Terence Doble Engineering Co. X

AP Martin, Zach Delta Star Inc.

II Martinel, Lorenzo ABB Switzerland Ltd. Micafil

II Martinez, Bene Metglas, Inc.

AP Mayer, Robert San Diego Gas & Electric X

II Mayer, Robert Siemens AG X

AP McBride, James JMX Services, Inc. X X

AP McCullough, Douglas Maxima / Hyundai

II McIntosh, John Savannah River Nat. Laboratory X

AP McIver, James Siemens Energy

II McKinney, Kenneth UL LLC X

Page 15 of 56

General Attendance

Member

Type Name Company Mon Thu

PCM-LM Mehta, Shirish Mehta Consultants X

II Middleton, Robert RHM International X

II Miecznikowski, Alexei Northern Transformer X X

II Minhaz, Rashed Transformer Consulting Services Inc. X X

II Misur, Slobodan Trench Limited X

II Momme, Thomas American Electric Power X

II Montanha, Juliano Siemens Ltda X X

II Montpool, Rhea Schneider Electric X

II Morakinyo, Paul PSE&G X

AP Morgan, Charles Eversource Energy X X

II Munn, William Southern Company Services X

II Munoz Molina, Martin Orto de Mexico X

II Musgrove, Ryan Oklahoma Gas & Electric X X

AP Mushill, Paul Ameren X

AP Naderian, Ali Metsco X

II Natale, Anthony HICO America X

II Neild, Kristopher Megger X X

II Nellen, Andre ABB Switzerland Ltd, Micafil

II Niccum, Daniel N. American Substation Services

AP Nikoley, Ingo Electrical Consultants, Inc.

AP Nims, Joe Allen & Hoshall, Inc. X

AP Oakes, Stephen Instrument Transformer Equip Corp X

II Ocon, Rodrigo Industrias IEM X X

AP Ogajanov, Rudolf ABB Inc. X

II Ojeda, Sam LumaSense Technologies X

II Olan, David BC Hydro

II O'Malley, Anastasia Consolidated Edison Co. of NY X X

II Ortiz, Jow NextEra Energy

AP Ostrander, David Ameren X X

II Otten, Daniel ABB Inc.

II Owen, John Powertech Labs Inc.

II Palakandy, Rahul Black & Veatch X

AP Panetta, Sergio I Gard Corporation

AP Patel, Dhiru Hammond Power Solutions X X

II Patni, Prem NV Energy

AP Patoine, Barbara Weidmann Electrical Technology X X

II Paukszto, Kelly IFD Corporation

II Pellon, Verena Florida Power & Light X

II Pepe, Harry Phenix Technologies, Inc. X X

II Pereira, Paulo Efacec Energia, SA

II Pesnel, Pierre X

AP Peterson, Alan Utility Service Corporation X

II Pimentel, Reginaldo Toshiba

AP Pinon, Oscar WEG-Voltran X X

II Pitts, Chris Howard Industries X

II Plante, Nicolas IREQ X

AP Prince, Jarrod ERMCO X

AP Pruente, John SPX Transformer Solutions, Inc. X

Page 16 of 56

General Attendance

Member

Type Name Company Mon Thu

II Raines, Summar ABB Inc.

II Ramakrishna, Manjunath M&I Materials Ltd. X

AP Rashid, Adnan Measurement Canada/Industry Canada X

II Ratcliffe, Robert Georgia Transformer

II Rathi, Rakesh Virginia Transformer Corp. X

AP Razuvayev, Sergiy Delta Star Inc. X

AP Reagan, Ashley ELTEK International Labs

AP Reiss IV, Clemens Custom Materials, Inc. X X

II Rezai, Hossein Transformer Consultant, Inc. X

II Riley, Jeff Cogent Power Inc. X

AP Riopel, Sebastien Electro Composites ULC

II Riordan, Kevin CG Power Systems USA Inc. X X

AP Rivers, Mark Doble Engineering Co. X

AP Robey, Dennis RL Components X

AP Rock, Patrick American Transmission Co. X X

II Rodriguez, Leopoldo Georgia Transformer X X

II Roizman, Oleg IntellPower Pty Ltd X

II Roll, Kevin San Diego Gas & Electric

AP Roman, Zoltan General Electric X

AP Ronchi, Rodrigo WEG-Voltran X X

II Saad, Mickel ABB Inc. X

II Saad, Mickel X

AP Sahin, Hakan ABB Inc. X

II Salgado, Pedro Electronic Technology Inc. X

II Samardzic, Marko IFD Corporation

II Samuelsson, Sofia ABB Switzerland Ltd. Micafil

II Sanchez, Oliverio Pacific Gas & Electric X X

II Sandhu, Surinder Sanergy Consulting X

AP Sauls, Roderick Southern Company Services

AP Sauzay, Mathieu JST Transformateurs X X

II Sbravati, Alan Cargill X

AP Scarborough, Mark DuPont X

AP Scardazzi, Alaor Siemens Ltda X X

AP Schickedanz, Frank Maschinenfabrik Reinhausen X

II Schiessl, Markus Starkstrom-Geraetebau GmbH X X

AP Schleismann, Eric Southern Company Services X

AP Schrammel, Alfons Siemens AG X

II Schubert, Juergen Starkstrom Geraetebau GmbH

II Schwarz, Carl Phoenix Electric Corporation X X

II Sen, Cihangir Duke Energy X

AP Sewell, Russell Quality Switch, Inc. X

AP Shannon, Michael Rea Magnet Wire X

II Sharifi, Masoud Siemens Wind

II Sharifnia, Hamid Stantec X

II Sheehan, David HICO America X

AP Shem-Tov, Mark Von Roll Transformers X X

AP Sheridan, Peter SGB USA, Inc. X

AP Shirasaka, Yukiyasu Hitachi Ltd. X X

Page 17 of 56

General Attendance

Member

Type Name Company Mon Thu

AP Shor, Andre Von Roll Transformers X

AP Siebert, Stefan BROCKHAUS MESSTECHNIK

II Siebert-Timmer, Audrey IFD Corporation X X

AP Simon, Preston Electrical Technologies X

AP Simonelli, Richard SPX Transformer Solutions, Inc.

II Simonov, Igor Toronto Hydro X X

II Simons, Andre Cogent Power Inc. X

II Singh, Kushal ComEd X

AP Slattery, Christopher FirstEnergy Corp. X X

AP Smith, Shane Delta Star Inc. X

II-LM So, Eddy National Research Council of Canada

AP Sohn, Yong Tae Hyosung X X

AP Sordo, Salvador WEG Electric Corp. X

II Spangler, Laura DuPont

AP Sparling, Brian Dynamic Ratings, Inc. X X

II Spaulding, James City of Fort Collins X

AP Spiewak, Erin IEEE X

II Spoone, Travis EATON Corporation X X

AP Spurlock, Michael American Electric Power X

II Stacy, Fabian ABB Inc. X X

AP Stank, Markus Maschinenfabrik Reinhausen X X

AP Stankes, David 3M X

II Stefanski, Tom KEMA Laboratories X

AP Steineman, Andrew Delta Star Inc. X X

AP Steineman, Christopher Meramec Instrument Transformer Co. X

AP Stem, Gregory Cardinal Pumps & Exchangers X

II Stinson, Robert General Electric X X

II Stockton, David H-J Family of Companies X

AP Stranko, Jennifer HPN Global

II Stuber, Tina ABB Inc.

II Su, Roy Fortune Electric X X

II Subramany, Shankar KEMA Laboratories, DNV GL X X

II Suddarth, Wes Nashville Electric Service X

AP Sullivan, Christopher Westmark Partners X

AP Sullivan, Kevin Duke Energy X X

II Sullivan, Liz ABB Inc. X

AP Sundin, David Ambit Technical Consulting X

II Thibault, Michael Pacific Gas & Electric X X

II Thompson, Ryan X

II Tillery, Timothy Howard Industries X X

II Tolcachir, Eduardo Tubos Trans Electric S.A. X

AP Tozzi, Marco Camlin Power X

AP Trivitt, Donnie Oklahoma Gas & Electric X

II Turner, Justin GE Energy Connections X

II Uhlmann, Olivier Reinhausen Canada Inc. X

AP Valentin, Reinaldo Duke Energy X

II Valmus, Jeff Cargill Inc. X

AP Van Horn, Jeremy IFD Corporation X X

Page 18 of 56

General Attendance

Member

Type Name Company Mon Thu

II Vandermaar, John Powertech Labs Inc.

AP VanderWalt, Alwyn Public Service Co. of New Mexico X X

II Varnell, Jason SPX Transformer Solutions, Inc. X

II Vartanian, John National Grid X

AP Veens, Jos Royal SMIT Transformers B.V. X X

II Veillette, Michel Morgan Schaffer X X

AP Verdell, Joshua ERMCO X X

II Vermette, Yves Electro Composites ULC

II Villagran, Deniss GE Grid Solutions X X

II Virelli, Greg Virelli & Associates Inc. X

II Viswasam, Anselm Hyperion

AP vonGemmingen, Richard Dominion X

II Vora, Shekhar Georgia Transformer X

II Voss, Stephan Siemens AG X X

II Vuittenez, Emmanuel X

II Wahid, Waqar Mitsubishi Electric Power Products

AP Walker, David MGM Transformers X X

II Wang, Evanne DuPont X X

II Wang, May Powertech Labs Inc. X

II Watkins, James N. American Substation Services

AP Weatherbee, Eric PCORE Electric

AP Weathington, Larry N. American Substation Services

II Weiser, Brandon Westar Energy X X

AP Welch, Lee Georgia Power Co. X

AP Werelius, Peter Megger X

II Whitehead, William Camlin Power X

II Wilford, Chris Cam Tran Co.

AP Williams, Randy ABB Inc.

II Williams, Trenton Advanced Power Technologies X X

II Wilson, Barnes Avista Utilities X X

AP Wimberly, Barrett GE Grid Solutions X X

II Wimmer, Julia Starkstrom-Geraetebau GmbH X

II Winstanley, Gerard NEMA X

II Winter, Dr. Alexander HIGHVOLT Pruftechnik Dresden X

II Wright, Jeffrey Mitsubishi Electric Power Products X

II Wu, Shawn Shihlin Electric

II Yeboah, Kwasi GE Energy Management X

II Yun, Jiyoung Hyundai Heavy Industries X X

II Yun, Joshua CG Power Systems USA Inc. X X

II Zaman, Malia IEEE X

II Zarmandily, Hassan Sigma Consulting Group

II Zhu, Hanxin BC Hydro

II Zibert, Kris Allgeier, Martin and Associates X X

II Ziger, Igor KONCAR - Instrument Transformers X X

Mon Thu

Total Non-Committee Member Attendance: 315 129

Total Committee Member Attendance: 145 93

Total Attendance: 460 222

Page 19 of 56

In addition to the above totals, there were 214 of the total attendees that attended both the Monday and

Thursday Sessions and 467 that attended either the Monday or the Thursday Session.

3.0 APPROVAL OF AGENDA AND PREVIOUS MINUTES – STEPHEN ANTOSZ

The Chair presented the Agenda and asked if there was any opposition to unanimous approval of the Agenda.

Hearing none, the Agenda was approved.

The Chair asked if there was any opposition to unanimous approval of the minutes of the Spring 2016

meeting that have been posted on the website. Hearing none, the minutes of the Spring 2016 meeting were

approved as written.

4.0 MEETING SCHEDULE

The meeting schedule is provided as Attachment 1

5.0 CHAIR’S REMARKS & REPORT – STEPHEN ANTOSZ

The Chair’s Report was presented at the Monday General Session.

5.1 IEEE PES TECHNICAL COUNCIL

The Technical Council of the IEEE Power Energy Society (PES) is presently composed of the Chairpersons

of the PES Technical Committees, plus the Chairpersons of Standing Committees reporting to it. For

operating functions it is responsible to the IEEE Technical Advisory Board and for technical activities to the

IEEE Technical Activities Board.

The PES Technical Committees report to the Technical Council on matters concerning membership,

technical publications, recognition, scope and the coordination of the Power Energy Society generated

standards. For standards relating to their technical scope, the Technical Committees work directly with the

IEEE Standards Board and the Power Energy Society Standards Coordinating Committee.

For further details on the Statement of Purpose and Scope of Activities for the PES Technical Council Please

see; http://www.ieee-pes.org/statement-of-purpose-and-scope-of-activities-for-the-pes-technical-council.

5.1.1 Technical Council Officers & Members

The officers and members of the Technical Council are listed below for your reference. Each individual

listed here is the chair of that respective committee.

TECHNICAL COUNCIL OFFICERS 2015-2017

Miriam Sanders, Chair (SEL University)

Farnoosh Rahmatian, Vice Chair (Quanta Technology)

Secretary, Vijay Vittal (Arizona State University)

Past-Chair, Jeffrey Nelson (TVA)

Page 20 of 56

STANDING COMMITTEES CHAIR

Awards Jeffrey H. Nelson

Technical Sessions Farnoosh Rahmatian

Organization & Procedures Vijay Vittal

Standards Coordination Ted Burse

COORDINATING COMMITTEES CHAIR

Emerging Technologies Nouredine Hadjsaid

Intelligent Grid Steve Pullins

Marine Systems Dwight Alexander

Wind and Solar Power Richard J. Piwko

TECHNICAL COMMITTEES CHAIR

Electric Machinery Kiruba Haran

Energy Development and Power Generation Michael J Basler

Insulated Conductors Frank Frentzas

Nuclear Power Engineering Stephen Fleger

Power System Analysis, Computing, & Economics Joydeep Mitra

Power System Communications Dan Nordell

Power System Dynamic Performance Pouyan Pourbeik

Power System Instrumentation & Measurements Jim McBride

Power System Operations Hong Chen

Power System Planning and Implementation M. L. Chan

Power System Relaying Mike McDonald

Stationary Battery Rick Tressler

Substations Markus Etter

Surge Protective Devices Ronald W. Hotchkiss

Switchgear Paul Sullivan

Transformers Stephen Antosz

Transmission and Distribution John McDaniel

5.1.2 PES Technical Council Activities

• Put a couple of our WG Chairs in contact with Debbie Lew IEEE PES Wind and Solar Power

Coordinating Committee Chair. To coordinate, not duplicate to our list of wind and solar-related

working groups, subcommittees, and task forces.

• Tech Council retreat for Chairs, to discuss the future direction of PES.

• IEEE/PES is assembling a team of experts to collaborate with the Department of Energy (DOE) on

Grid Modernization Metrics. Sent an email to Transformers Committee members for people

interested to participate. Got 3 or 4 volunteers.

Page 21 of 56

5.2 TRANSFORMERS COMMITTEE ACTIVITIES

5.2.1 New Subcommittee Chairs. Appointments by Committee Chair.

5.2.2 Dielectric Test SC -- Ajith Varghese replaced Michael Franchek, after the Spring 2016 meeting.

5.2.2.1 Power Transformers SC -- Bill Griesacker will replace Joe Watson, after Vancouver Fall 2016

meeting.

5.2.2.2 Insulation Life SC -- Sheldon Kennedy replaced Bruce Forsyth on Jan 1, 2016.

5.2.3 Liaison Representatives. Appointed by Committee Chair.

• CIGRE - Raj Ahuja

• IEC TC-14 Technical Advisor to USNC - Phil Hopkinson

• Standards Coordinating Committee, SCC No. 18 (NFPA/NEC) – David Brender replaces Ned Brush

• Standards Coordinating Committee, SCC No. 4 (Electrical Insulation) - Paulette Payne Powell

5.2.4 New CD with compilation of C57 documents

Instead of the printed edition, IEEE put out a CD in 2002, 2008, and 2011. Now we have done another one

this year in 2016, since the new main Standards C57.12.00 and C57.12.90 were published in March 2016.

Peter Balma is leading this effort again. The CD is ready and was for sale as part of the registration process

at the Fall meeting in Vancouver. 57 are already sold, which exceeds expectations.

5.2.5 IEEE Membership Status Elevation

5.2.5.1 All membership issues will be covered in detail by our Committee Secretary Bruce Forsyth, but I just

want to take a moment to have everyone stop and think a few moments about your membership level and

encourage you to step it up to the next level.

If you are a regular Member, then consider becoming a Senior Member. See Bruce for how to do this.

If you are an Interested Individual, then step up and get involved in some activity and become an Active

Participant. If you are an Active Participant, then apply to be a Committee Member. Observers are

welcome, but after a few meetings more active participation is encouraged.

There are over 570 people here today; many are IEEE Members and many are not. I want to encourage

everyone to become an IEEE Member, and to renew that membership every year. Furthermore, many of us

are PES and IEEE-SA Members as well. These membership categories are necessary to do much of the work

of developing IEEE Standards, so please consider adding the PES and IEEE-SA memberships to your

profile.

5.2.5.2 Emeritus Members (EM)

The Administrative Subcommittee has formed a Task Force to investigate the requirements of emeritus

membership, create a list of past and existing EM’s, review the policies and procedures regarding EM’s, and

to make suggestions for future direction regarding EM’s.

5.2.6 RFID

This issue will be covered by our Meeting Planner, Greg Anderson. We are using RFID tags on the name

badges for this Vancouver meeting in a similar manner as the last meeting. Bear with us as we implement

this new technology, which is intended to make our meetings better.

Page 22 of 56

5.2.7 Thursday morning Tutorials

We always continue to look for new and exciting topics. Tom Prevost is the leader of this activity for

coordination efforts. If interested, see Tom or any of the officers. Any feedback by attendees is welcome.

5.2.8 Association Management System

All WG’s should be using AMS to track their membership and meeting attendance. If unable to so, then

please assign it to someone who can do it.

5.2.9 Website Password Usage

It is not for public dissemination. It is for use by our meeting attendees (CM, AP, II) and associated work of

the Transformers Committee. One can think of it as a benefit of attendance and participation. Use it for

yourself and within your immediate workplace, but not beyond that.

5.2.10 100 year celebration in 2018

Based on research of AIEE and IEEE, the first recorded meeting of a transformers committee was in 1918,

making 2018 the 100 year anniversary of our committee. We will use the Spring 2018 meeting in Pittsburgh

to celebrate the occasion. We intend to have a formal banquet on Sunday with special guests and speakers, a

reunion of former members, significant honors and awards, a sumptuous reception, etc. More info to come

in the future.

5.2.11 Call for Patents (Essential Patent Claims)

We have long had the requirement imposed upon us by IEEE-SA to have a call for patents at every WG

meeting. We used to show a slide presentation at every WG meeting, but since we have 6 to 8 WG meetings

in every time slot, six times a day on Mondays and Tuesdays, this became burdensome and took up a lot of

unnecessary time. So, several years ago we implemented an alternate approach whereby we asked the patent

questions at registration. At that time, this was an approved approach. In recent days, it has been questioned

whether or not this actually meets the requirement, and we are again being asked to have a call for patents in

EVERY WG meeting. So, until we sort this out, we will ask all WG Chairs in every meeting here in

Vancouver to present the following “call for patents” in every WG meeting. Please add this “Call for

Patents” to your Agenda:

“If any individual believes that Patent Claims might be Essential Patent Claims, that fact

should be made known to the entire working group and duly recorded in the minutes of

the working group meeting.”

The Chair is required to ask any patent holder or patent applicant of a patent claim that might be or become

an Essential Patent Claim to complete and submit a Letter of Assurance.

That’s it. Don’t spend a lot of WG time on this issue. Proceed with the meeting. Record it in the minutes

and report it up the chain of command to the Subcommittee Chair (and Don Platts) for the next action, if any.

If attendees need more details about what is an essential patent claim, they should refer to our website where

there is a link for more information.

Respectfully submitted,

Page 23 of 56

Stephen Antosz

Chair, IEEE/PES Transformers Committee

6.0 VICE CHAIR’S REPORT – SUSAN MCNELLY

The Vice Chair’s Report was presented at the Monday General Session.

6.1 IEEE PES CALENDAR OF UPCOMING EVENTS

The following are upcoming PES sponsored conferences and committee meetings. Please check the PES

website at www.ieee-pes.org for further details, and additional events.

2017 IEEE/PES Joint Technical Committee Meeting (JTCM)

January 8-12, New Orleans, Louisiana

2017 IEEE/PES General Meeting

July 16-20, 2017, Chicago, Illinois

6.2 CONFERENCE PAPER SUBMITTALS FOR 2017

6.2.1 General

PES plans to continue the initiative for promoting the work of the technical committees under PESs (AKA

PES’ “best kept secret”). Working Groups are encouraged to produce a poster on the activity of their WGs

for the T&D and General Meetings.

Interested WGs are requested to provide the below information to Maria ([email protected]) and Farnoosh

Rahmatian ([email protected]). Email subject line should read: “Poster session for WGs - IEEE PES GM

Conference” or “Poster session for WGs - IEEE PES T&D Conference”, as applicable. Deadlines for the

next conference will be provided in the spring 2017 Vice Chair report. See Example Poster for ideas on

content and composure of Poster. A special thank you to Bob Rasor for providing the first poster for the

Transformer Committee WG at the 2016 IEEE PES T&D Conference and Expo.

• Technical Committee Name: Transformers Committee

• Working Group name

• Project title (if different from WG name)

• PAR number (if relevant)

• Who from the WG will be presenting the poster at the IEEE PES T&D Conference and Expo

The following information is suggested to be included on each poster:

• Technical Committee Name

• Working Group name

• Project title

• PAR number (if relevant)

• Project Scope

• Target completion date

• Project status

• Key technical points being addressed in the work

Page 24 of 56

6.2.2 IEEE/PES General Meeting - July 16-20, 2017, Chicago, Illinois

On Oct 10, 2016 the paper submission website was opened to authors for 2017 General Meeting. It will be

open until November 7, 2016. Papers will be peer reviewed and accept/reject decision made by March 1,

2017.

Respectfully,

Susan McNelly

Vice Chair

October 20, 2016

7.0 SECRETARY’S REPORT – BRUCE FORSYTH

The Secretary’s Report was presented at the Monday General Session.

7.1 MEMBERSHIP REVIEW

The Committee welcomes and encourages active participants to become Members of the Committee.

Requirements and application forms can be found in the Organization and Procedures (O&P) Manual,

accessible on the Committee website. A link to the Membership Application form can be found on the

TransformersCommittee.org homepage in the Committee Information Box. Subcommittee Chairs are

encouraged to recommend new members and to communicate the process of attaining membership through

active participation and contribution at the WG and SC level. WG and SC Chairs are reminded also that

signing an application sponsoring a new member signifies their sponsorship that the applicant has met the

requirement of membership and active participation for at least one year in the WG or SC they Chair. New

member applications may be submitted to the Committee Secretary’s attention at any time. Applications will

be collected for review and approval in batches at each Administrative Subcommittee meeting.

7.1.1 New Committee Member Approvals

At the Spring 2016 Administrative Subcommittee meeting in Atlanta, six new committee member

applications were reviewed and approved. The new members are listed in the following table.

Name Affiliation Sponsor #1 Sponsor #2 Sponsor #3 Membership

Category

Stephanie

Denzer GE

Mike Lau

C57.93

(2 yr.)

Charles Patrick

McShane

C57.147

(2 yr.)

David Wallach

Insulating Fluids

SC

(2 yr.)

General

Interest

Shamaun

Hakim

CG Power

Systems

Michael

Franchek

Dielectric Test

SC

(3 yr.)

Bertrand Poulin

WG Rev. of Low

Frequency Tests

(3 yr.)

Pierre Riffon

WG Ext

Dielectric

Clearances

(3 yr.)

Producer

Ronald

Hernandez

Doble

Engineering

Company

Ali Naderian

WG Dielectric

Frequency

Response

(2 yr.)

Thomas Prevost

WG PC57.162

(2 yr.)

Sheldon

Kennedy

Insulation Life

SC

(2 yr.)

Producer

Page 25 of 56

Name Affiliation Sponsor #1 Sponsor #2 Sponsor #3 Membership

Category

Ryan

Thompson

Burns &

McDonnell

David Wallach

Insulating Fluid

SC

(3 yr.)

James Thompson

C57.130

(3 yr.)

James Thompson

C57.637

(2 yr.)

User

Ajith M.

Varghese

SPX

Transformers

Solutions

Michael

Franchek

Dielectric Test

SC

(5 yr.)

Bertrand Poulin

WG Rev. of Low

Frequency Tests

(5 yr.)

Mark Perkins

WG PCS Rev. to

C57.12.90

(5 yr.)

Producer

Zan

Kiparizoski

Howard

Industries

Robert Rasor

WG C57.106

(2 yr.)

Thomas Prevost

WG PC57.162

(2 yr.)

David Wallach

Insulating Fluids

SC

(2 yr.)

Producer

7.1.2 New Member Applications

Eight new applications for Committee Membership have been received for consideration since the Spring

2016 meeting in Atlanta. The following tables lists the names of the applicants and a summary of their

supporting eligibility information.

Name Affiliation Sponsor #1 Sponsor #2 Sponsor #3 Membership

Category

Saurabh Ghosh

IEEE/PES/SA

Status

Confirmed

Essex Group

Gary Hoffman

C57.12.10

2 yrs.

Joe Watson

Power

Transformers SC

4 yrs.

Mike Lau

C57.93

3 yrs.

Producer

Kurt Kaineder

IEEE/PES/SA

Status

Confirmed

Siemens

Oesterreich AG

Mike Franchek

P1276

3+ yrs.

Jane Ann Verner

C57.163

2 yrs.

Sheldon

Kennedy

Insulation Life

SC

3+ yrs.

Producer

Shankar Nambi

IEEE – YES

PES – YES

SA - NO

Bechtel

Casey Ballard

PC57.12.01

2 yrs.

E. Betancourt

PC57.158

2 yrs.

Joe Watson

Power

Transformers SC

5 yrs.

User

Nick Perjanik

IEEE/PES/SA

Status

Confirmed

Weidmann

Electrical

Technology

David Wallach

Insulating Fluids

SC

4 yrs.

Paul Boman

DGA Guide for

Ester Fluids

4 yrs.

Bob Rasor

C57.106

4 yrs.

Producer

Jeff Ray

IEEE/PES/SA

Status

Confirmed

JLR Consulting

Sheldon

Kennedy

Insulation Life

SC

several years

Bruce Forsyth

ILS TF Metallic

Parts

several years

Gary Hoffman

WG Guide to

XFMRS

Connected to

Generators

duration?

General Interest

Sam Sharpless

IEEE/PES/SA

Status

Confirmed

Rimkus

Consulting

Group

Rick Marek

WG PC57.110

2 yrs.

Adam Bromley

WG PC57.105

2 yrs.

Sheldon

Kennedy

Insulation Life

SC

2 yrs.

User

Page 26 of 56

Name Affiliation Sponsor #1 Sponsor #2 Sponsor #3 Membership

Category

Weijun Li

IEEE/PES/SA

Status

Confirmed

Braintree

Electric Light

Department

Joe Watson

Power

Transformers SC

>2 yrs.

Gary Hoffman

WG C57.12.10

~2 yrs.

Shibao Zang

WG C57.19.01

>2 yrs.

User

Matt Weisensee

IEEE/PES/SA

Status

Confirmed

PacifiCorp

Sanjib Som

WG C57.21

2 yrs.

Joe Watson

Power

Transformers SC

3 yrs.

Craig Colopy

WG Tap

Changer Guide

60214-2

2 yrs.

User

These applications will be reviewed at the Fall 2016 Administrative Subcommittee meeting in Vancouver.

7.1.3 Association Management System (AMS) Database

The Transformers Committee AMS database of people currently has three general categories of participation

in our activities. These are: Interested Individual, Active Participant, and Committee Member. In

addition, the Committee Secretary maintains a list of Past Committee Members. Anyone can join the AMS

123 system as the system is designed for self-registration. A new participant will automatically be assigned

the role of Interested Individual when they first sign up. Based on the level of participation, the committee

administrative staff will upgrade the participation status to “Active Participant” when appropriate. The

Committee Member status however, can only be attained through a formal application with the sponsorship

of a minimum of three WG or SC chairmanships. Details of the application requirements and approval

process by the Administrative Subcommittee are outlined in our O&P manual.

The following table contains a count of the participants grouped by the four general categories (CM totals do

not include those requesting membership at this meeting).

Membership Status Oct-13 Mar-14 Oct-14 Apr-15 Nov-15 Mar-16 Oct-16*

Interested Individual 1376 1381 1386 1362 1462 1471 1507

Interested Individual - IEEE Life Member 16 12 10 9 11 11 11

Total Interested Individuals 1392 1393 1396 1371 1473 1482 1520

Active Participant 178 192 201 205 240 242 258

Active Participant - IEEE Life Member 5 5 6 6 7 5 5

Total Active Participants 183 197 207 211 247 247 263

Committee Member 170 166 170 173 161 172 175

Committee Member – Emeritus 3 09 10 10 10 9 9

Committee Member - IEEE Life Member 25 21 20 22 23 25 27

Total Committee Members 198 196 200 205 194 206 211

Past Committee Member 15 18 19 28 32 31

Past Committee Member - IEEE Life Member 6 6 7 6 5 5

Total Past Committee Members 21 24 26 34 37 36

TOTAL IN AMS DATABASE 1773 1810 1827 1813 1948 1972 2028

*Oct-16 data is as of 10/18/2016

It is the responsibility of each individual to keep his/her profile updated (except for the category).

Page 27 of 56

7.2 COMMITTEE, SUBCOMMITTEES, AND WORKING GROUP ROSTERS

In order to provide indemnification to working group and subcommittee members it is crucial that

membership lists be maintained. The AM system has these functions built-in to ease these administration

tasks. It is important that each subcommittee and working group chair keep the rosters updated so that this

information can be provided to the IEEE SA.

A similar main committee roster has also been developed to track attendance for the Main Committee

General Session meeting on Monday & Thursday. The data will be used to update participant’s membership

profile.

7.3 IEEE/PES AND IEEE/SA MEMBERSHIP REQUIREMENTS

As a reminder, all members of the Transformers Committee must also be members in good standing of the

Power & Energy Society (IEEE/PES) and the Standards Association (IEEE/SA).

WG Chairs must be members in good standing of the sponsoring subcommittee SC as well as the Power &

Energy Society (IEEE/PES) and the Standards Association (IEEE/SA).

7.4 COMMITTEE MEMBERSHIP MAINTENANCE

Since the spring 2016 meeting one member, Ned Brush, passed away and was removed from the membership

list. The membership list will be reviewed after the upcoming meeting and notices will be sent to members

who appear to be inactive (based on attendance) to inquire about their intentions of attending/participating in

the Committee.

7.5 ESSENTIAL PATENT CLAIMS

The Transformers Committee asks each participant at the time of meeting registration if they are aware of an

essential patent claim, and if so to provide details. An Essential Patent Claim is any Patent Claim the use of

which was necessary to create a compliant implementation of the IEEE Standard when there was no

commercially and technically feasible non-infringing alternative. In other words, if an IEEE Standard

REQUIRES the use of a product or process that is already patented, then this could be an essential patent

claim. If they did, they would be instructed to have the patent holder’s legal team file a Letter of Assurance

(LOA) with the IEEE-SA Standards Board Patent Committee. There is a link to this information on the

transformerscommittee.org website under Patent Disclosure Requirements.

For the Fall 2016 meeting in Vancouver, most people answered “NO” to the Patent question. There were 10

people who answered “YES” that they were aware of an essential patent claim. Of these 7 provided no

details and were therefore not considered any further. The remaining 3 were reviewed:

1. One registrant prefers to raise any EPC issues per the IEEE-SASB Operations Manual Clause 6.3.2

Call for Patents.

2. PC57.147 (Insulating Fluids SC) – There was a negative vote on the revision of PC57.147 in which

the voter's comment stated the document may contain one or more potential standard essential

patents for which no letter of assurance has been filed.

3. PC57.147 (Insulating Fluids SC) – A registrant referenced a patent and asked if there is some sort of

agreement between IEEE and the patent holder in lieu of an LOA, and inquired as to the details of

such an agreement.

Page 28 of 56

7.6 AFFILIATION

According to the IEEE Standards Board Bylaws, there is a requirement that participants of an IEEE meeting

disclose their employer and affiliation. Consultants must state if they are sponsored or not. It is not

sufficient to simply announce "My name is John Smith, and I'm a consultant." If a consultant is sponsored

by a client, it must be disclosed. If the consultant does not have a sponsor, the proper introduction is

something such as “My name is John Smith, I am a consultant, and I represent myself at this meeting.”

7.7 MEETING MINUTES

The minutes of the Spring 2016 meeting in Atlanta were posted to the committee website in September of

2016.

Subcommittee Chairs are asked to submit their respective subcommittee meeting minutes for the Vancouver

meeting to the Committee Secretary no later than Dec. 4, 2016. It is strongly recommended that meeting

minutes be prepared soon after the meeting while the activities are still fresh in member’s minds. This helps

ensure the minutes accurately reflect the activities and decisions made during the meeting.

Subcommittee meeting minutes should be submitted via e-mail to the Committee Secretary, Bruce Forsyth

[[email protected]], who will forward then on for posting on the Committee website.

The submittal file should be saved as a Word document formatted similar to this document. Attendance,

indication of quorum, names of members making any motion, seconding any motion, and the result of any

votes (affirmative and negative count) for each SC, WG, and TF meeting shall be included in all minutes.

Respectfully submitted,

Bruce Forsyth

Secretary

IEEE/PES Transformers Committee

October 23, 2016

8.0 TREASURER’S REPORT – GREGORY ANDERSON

Greg reported that the finances of the Committee are in good condition. As of 31st of August 2016 (end of

this reporting period), the balance was $60,111,54.

FYI: August 31st is essentially a "snap-shot" in time after all income & expenses are resolved from the

previous Spring 2016 Atlanta Meeting, and before we start spending significant funds for the Fall 2016

Vancouver Meeting.

No significant assets (PC projectors, etc.) were purchased during this reporting period.

See attached summary of the balance of this reporting period, and the previous periods.

Page 29 of 56

Page 30 of 56

9.0 RECOGNITION AND AWARDS REPORT – DON PLATTS

9.1 SPECIAL TRIBUTES

During the past several months since our previous meeting in March 2016 in Atlanta, GA, the Transformers

Committee and the industry lost another of our long time contributors. At our Awards luncheon on Tuesday,

the meeting attendees gathered to pay special tribute to another of our friends and collogues who passed

away in May.

Edwin “Ned” Brush II (1941 – 2016)

Edwin “Ned” Franklyn Brush Jr., 74, of New Harbor, passed away on the afternoon of May 31 at his home

after a long and courageous battle with cancer, with his loving family by his side.. Born July 17, 1941 in

Cleveland, Ohio, he was the son of Ruth and Edwin F. Brush.

Ned attended local schools in Cleveland Heights, OH and went on to receive four degrees at M.I.T.,

including a Doctorate of Science in 1967 in Materials Science and Engineering. He was fascinated by how

metallurgical processes worked and how they could be improved. His business career focused on

consulting and he worked closely with both the copper development industry and electrical transformer

industry. Ned enjoyed traveling both for work and for leisure.

He was very active and involved with M.I.T., his fraternity, and the many life-long friends he made while

attending school there. He lived a full and productive life and was loved and respected by all who were

privileged to know him.

Ned is survived by his wife of 29 years, Deborah Whitaker of Boston, Mass.; a sister; son; daughter; step-

daughter and step-son; and grandchildren.

9.2 COMMITTEE MEMBERSHIP CERTIFICATES

The Transformers Committee welcomes six new full committee members, and a Past Member, who has been

re-instated. Each of the following new members was presented with a membership certificate:

New Member Affiliation

Weijun Li Braintree Electric Light Department

Jeff Ray JLR Consulting

Matt Weisensee PacifiCorp

Sam Sharpless Rimkus Consulting Group

Kurt Kaineder Siemens Oesterreich AG

Nick Perjanik Weidmann Electrical Technology

Reinstated

Saurabh Ghosh Essex Group

9.3 GENERAL SERVICE AWARDS

Certificates of Appreciation were presented to the following list of recipients for their contributions to the

Transformers committee:

Page 31 of 56

Name of Award Recipients Affiliation Contributions

Paul Chisholm IFD Corporation Meeting Host – Fall 2016

IFD Corporation IFD Corporation Host Company– Fall 2016

Mike Franchek Weidmann Electrical

Technology

Chair of Dielectric Test Subcommittee

(2013–2016)

9.4 OUTSTANDING CONTRIBUTOR AWARDS & CERTIFICATE OF APPRECIATION

In any successful organization, there are always a handful of hard working individuals, laboring behind the

scene that put in the sweat equity year after year to provide great contributions to the success of the group.

Often these contributors are not necessarily those who held the official titles. Similarly, in the Transformers

Committee, we also have a long list of these outstanding contributors. At our recent meetings, the Awards

subcommittee has started the process of recognizing the individuals who provided long tenured contributions

to our organization. As we look across the many contributors we have in the organization, we realize that

there are many deserving candidates. We hope to continue to recognize these awardees at each of our future

meeting.

The criteria for the evaluation of the nominees are primarily based on the long tenure of significant

contributions in either technical subject matter expertise and/or broader organizational impacts in our ability

to reinvent our thinking and continue our industry leadership and relevancy.

At the Awards Luncheon on Tuesday, the Transformers Committee presented a special certificate of

appreciation to Mr. Pierre Riffon for his many years of service to the Transformers Committee and also to

the industry. He has been a steadfast technical contributor over the past several decades and has brought us a

level of expertise in the dielectric test arena. As a result, the committee has benefited greatly from this

experience, wisdom, and practical expertise on testing and measurements. A brief description of his career

highlights and contributions is included below.

Mr. Riffon received his B.Sc.A. in electrical engineering from École Polytechnique de Montréal in 1980

after which he joined Hydro-Québec's Research Institute (IREQ) as a Test Engineer for the High Power

Laboratory. From 1988 to 2013, he was working as a Test Specialist for the Hydro-Québec's Quality

Control Department and was responsible for type tests on high voltage substation equipment and special

project apparatus (static and series compensation, HVDC Converter, etc...). He retired from Hydro-

Québec in 2013 and is now working as an independent consultant on high voltage equipment testing.

Pierre is a member of the IEEE Transformers Committee where he participates in several Subcommittees

and Working Groups. In particular, he is Chairman of IEEE Working Group on Test Requirements for

Instrument Transformers for Nominal Voltage 115 kV and above, and is also the Chairman of the WG on

Revision to Impulse Tests C57.12.90.

He is also the Chairman of the Canadian IEC Technical Committee TC17 and Subcommittees SC17A and

SC17C, Switchgear and control gear. Mr. Riffon is also the convener of a WG on High-Voltage

alternating current by-pass switches and the Canadian representative on SC17A/MT36 for the revision of

IEC 62271-100 High Voltage Circuit Breakers.

Page 32 of 56

Pierre is a member of IEEE Power Engineering Society and registered as a Professional Engineer in the

Province of Québec.

9.5 IEEE SA STANDARDS BOARD AWARDS

In addition to the Committee Awards above, the IEEE SA SB presents its own Award to the WG Chair upon

publication of a new or revised document, and offers the WG Chair the opportunity to nominate significant

contributors to the project for an IEEE SA SB Certificate of Appreciation.

IEEE SA Award Recipients:

We have had a number of working groups that have completed their projects, their standards documents have

been published, but IEEE SA has failed to recognize them by awarding the SA plaques and Certificates of

Appreciation. At our spring meeting in Atlanta, the 9 Working Groups were again recognized as a group, at

our Tuesday luncheon, with the understanding that they may still request that the official plaque award

ceremony be at a future Transformers Committee meeting.

Several of these Working Groups will finally be recognized in Vancouver with the presentation of their SA

Award plaques. In addition, there are a few other projects that were completed in 2015, and we also have

the opportunity to recognize these Working Groups for their accomplishments.

Revision to C57.12.00- 2015- Standard for General Requirements for Liquid Immersed Distribution,

Power, and Regulating Transformers

Steve Snyder - Working Group Chair

Peter Balma - Vice Chair

TF Chair Ramsis Girgis

Other Significant Contributors

Enrique Betancourt Mats S. Bernesjö

Mike Franchek Bruce Forsyth

Phil Hopkinson Steve Shull

Ed teNyenhuis David Wallach

Revision to C57.12.90- 2015- Standard Test Code for Liquid Immersed Distribution, Power, and

Regulating Transformers

Steve Antosz - Working Group Chair

Peter Balma - Vice Chair

Other Significant Contributors

Plaques Cert Appreciation

TF Chairs Loren Wagenaar

Ramsis Girgis Ed teNyenhuis

Bertrand Poulin Mats S. Bernesjö

Pierre Riffon Paulette Powell

Mark Perkins Marcel Fortin

Revision to C57.13- 2015- IEEE Standard Requirements for Instrument Transformers

Ross McTaggart - Working Group Chair

Thomas Sizemore - Vice Chair

Nigel Macdonald - Technical Editor

Other Significant Contributors

Page 33 of 56

Vladimir Khalin

Randolph Mullikin

Pierre Riffon

Revision to C57.32- 2015- Standard Requirements, Terminology, and Test Procedures for Neutral

Grounding Devices

Sheldon Kennedy - Working Group Chair

Tom Mele - Vice Chair

Other Significant Contributors

Donald E. Ayers

Fred Elliott

Peter Balma

Klaus Pointner

Sergio A. Panetta

Michael R. Sharp

Revision to C57.94- 2015- Recommended Practice for Installation, Application, Operation, and

Maintenance of Dry Type Distribution and Power Transformers

S (Dave) Stankes - Working Group Chair

Sanjib Som- Vice Chair

Other Significant Contributors

Rick Marek

Robert Ballard

Chuck Johnson

Tim Holdway

Jerry Murphy

Revision to C57.139- 2015- Guide for Dissolved Gas Analysis in Transformer Load Tap Changers

Dave Wallach- Working Group Chair

Mark Cheatham- Vice Chair

Other Significant Contributors

Sue McNelly

Jim Dukarm

Fredi Jakob

Rainer Frotscher

Michel Duval

John Pruente

The list of Working Groups that chose to have their awards shipped to their contributors directly follows:

Number Title WG Chair

C57.157 2015

Guide for Conducting Functional Life Tests on

Switch Contacts Used in Insulating Liquid

Transformers

Phil Hopkinson

C57.130 2015

Guide for the Use of Dissolved Gas Analysis

Applied to Factory Temperature Rise Tests for the

Evaluation of Mineral Oil Immersed Transformers

and Reactors

Jim Thompson

Page 34 of 56

Number Title WG Chair

C57.12.37 2015 Standard for the Electronic Reporting of

Distribution Transformer Test Data Tom Callsen

C57.637 2015 Guide for the Reclamation of Mineral Insulating

Oil and Criteria for Its Use Jim Thompson

C57.155-2014

IEEE Guide for Interpretation of Gases Generated

in Natural Ester and Synthetic Ester-Immersed

Transformers

Paul Boman

Despite getting many of our working groups recognized, we still have a backlog of projects that must be

resolved. The Awards Chair will be working to correct this promptly. The list of Working Groups that

remain in the category where their award production is still in progress is as follows:

Number Title WG Chair Awards Lunch

C57.125 2015

Guide for Failure Investigation,

Documentation, Analysis, and Reporting

for Power Transformers and Shunt

Reactors

Wally Binder F2015

C57.12.01

General Requirements for Dry- Type

Distribution and Power Transformers

Including Those with Solid Cast and/or

Resin Encapsulated Windings

Tim Holdway S2015

1538a 2015

Guide for Determination of Max Winding

Temp Rise in Liquid

Transformers Amendment#1

Rick Marek

C57.106-2015

Guide for Acceptance and Maintenance of

Insulating Mineral Oil in Electrical

Equipment

Bob Rasor

PC.57.159-2016 Guide for DPV Grid Transformers Hem Shertukde

Since our last meeting, we had 3 New Transformer Standards documents that were approved by RevCom,

and subsequently the SA Board.

Number Title

60076-57-1202 International Standard Requirements for Liquid-Immersed Phase-Shifting Transformers

C57.156 Guide for Tank Rupture Mitigation of Liquid-Immersed Power Transformers and Reactors

C57.159 Guide on Transformers for Application in Distributed Photovoltaic (DPV) Power Generation

Due to the process of identifying the recipients and producing the awards, we will not have awards ready for

these projects at this meeting, but we still want to provide recognition and notice of these accomplishments.

9.6 BEST SUBCOMMITTEE AWARD

This relatively new program has been discontinued. Therefore, we will not have anyone trying to attend all

of the meetings and trying to evaluate which has the best run meeting. We want to thank all of our

Subcommittees for their hard work, and celebrate all of their accomplishments.

Page 35 of 56

9.7 OTHER IEEE PES AWARDS (AVAILABLE UPON APPLICATION TO PES)

The IEEE PES recognizes important technical, educational and service contributions through the conferral of

numerous awards. The listing below highlights the various other awards that are available through the IEEE

PES organization.

• IEEE PES Award for Excellence in Power Distribution Engineering

• IEEE PES IAS A.P. Seethapathy Rural Electrification Excellence Award

Nominations due by February 1st

• IEEE PES Charles Concordia Power Systems Engineering Award

Nominations due by January 31st

• IEEE PES Cyril Veinott Electromechanical Energy Conversion Award

Nominations due by February 1st

• IEEE PES Douglas M. Staszesky Distribution Automation Award

Nominations due by January 1st

• IEEE PES Lifetime Achievement Award

Nominations due by February 1st

• IEEE PES Leadership in Power Award

Nominations due by February 1st

• IEEE PES Meritorious Service Award

• IEEE PES Nari Hingorani Custom Power Award

Nominations due by January 31st

• IEEE PES Nari Hingorani FACTS Award

Nominations due by January 31st

• IEEE PES Outstanding Chapter Award

• IEEE PES Outstanding Power Engineering Educator Award

Nominations due by January 31st

• IEEE PES Outstanding Young Engineer Award

Nominations due by Februrary 1st

• IEEE PES Prabha S. Kundur Power System Dynamics and Control Award

Nominations due by January 31st - Call for Nominations

• IEEE PES Prize Paper Award

• IEEE Power & Energy Society Ramakumar Family Renewable Energy Excellence Award

• IEEE PES Robert P. Noberini Distinguished Contributions to Engineering Professionalism Award

Nominations due by February 1st

• IEEE PES G. Ray Ekenstam Memorial Scholarship

Nominations due by June 30th

• IEEE PES Scholarship Plus Initiative

Applications due by June 30th

• IEEE PES Roy Billinton Power System Reliability Award

Nominations due by February 1st

• IEEE PES Student Prize Paper Award in Honor of T. Burke Hayes

Nominations due by December 15th

Page 36 of 56

• IEEE PES Uno Lamm High Voltage Direct Current Award

Nominations due by November 30th

• IEEE PES Wanda Reder Pioneer in Power Award

Nominations due by January 15th

• IEEE PES Working Group Recognition Awards

The PES Working Group Recognition Awards recognize “the most outstanding and timely

publications” by a PES Working Group (or Committee or Subcommittee) from among the

nominations. The PES Recognition Award is divided into two categories: 1) for technical reports; 2)

standards and guides. Each Technical Council Committee may nominate one report from each

category, published by IEEE, during the previous three year period.” This award consists of a plaque

which will be presented to the Working Group Chair at the PES Summer Meeting Awards

Luncheon. A framed certificate will be presented to each Working Group member at a designated

meeting of the parent Technical Committee.

Respectfully submitted,

Donald W Platts

Chair, Recognitions and Awards Subcommittee

10.0 ADMINISTRATIVE SUBCOMMITTEE MEETING REPORT

10.1 INTRODUCTION OF MEMBERS AND GUESTS

The Chair called the meeting to order and asked attendees to introduce themselves and their affiliation.

Consultants were asked to identify the company they were representing if they were not representing their

own consulting interest. Introductions were made by members and guests.

Members and Guests Present:

Chair .................................................................................................................. Stephen Antosz

Vice Chair.......................................................................................................... Susan McNelly

Secretary ............................................................................................................ Bruce Forsyth

Treasurer/ Meetings Planning SC ..................................................................... Gregory Anderson

Standards Coordinator ....................................................................................... Jim Graham

Awards/Past Chair ............................................................................................. Donald Platts

Bushings ........................................................................................................... Peter Zhao

Dielectric Tests ................................................................................................. Ajith Varghese

Distribution Transformers ................................................................................ Stephen Shull

Dry Type Transformers .................................................................................... Casey Ballard

HVDC Converter Transformers & Reactors .................................................... Michael Sharp

Instrument Transformers .................................................................................. Ross McTaggart

Insulating Fluids ............................................................................................... David Wallach

Insulation Life .................................................................................................. Sheldon Kennedy

Performance Characteristics ............................................................................. Ed teNyenhuis

Power Transformers ......................................................................................... Joe Watson/Bill Griesacker

Page 37 of 56

Standards ........................................................................................................... Jerry Murphy

Underground Transformers & Network Protectors .......................................... Dan Mulkey

Guests: Peter Balma (by phone, partially), Erin Spiewak, IEEE, Malia Zaman (IEEE),

Natasha Alvarado (IEEE), Gary Hoffman, Paul Jarmin (TC14 Chair)

10.2 APPROVAL OF PREVIOUS MEETING MINUTES

The Chair asked for comments of the minutes from the Spring 2016 Administrative Subcommittee meeting

in Atlanta. There were no comments and objections to unanimous approval, therefore the minutes were

approved.

10.3 ADDITIONS TO AND/OR APPROVAL OF THE AGENDA

The Chair reviewed the draft agenda and noted the addition of a new item under New Business (IEEE/IEC

issue regarding dual references) since the initial preliminary agenda was sent to members. In addition, the

Chairs asked that the issues involving Peter Balma be covered first since Peter was calling in and had other

commitments. There were no additional changes requested and no objections to unanimous approval of the

revised agenda, therefore the following agenda was approved.

Approved Agenda:

1. Introduction of Members and Guests (:05) .............................................. All

2. Approval of Fall 2015 Minutes from Memphis (:03) .............................. Stephen Antosz

3. Additions to and/or Approval of the Agenda (:02) .................................. Stephen Antosz

4. Chair’s Report (:05) ................................................................................. Stephen Antosz

5. Vice Chair’s Report (:05) ........................................................................ Sue McNelly

6. Secretary’s Report & New Committee Membership Approval (:10) ...... Bruce Forsyth

7. Treasurer’s Report (:05) .......................................................................... Greg Anderson

8. Recognition & Awards Report (:05) ........................................................ Don Platts

9. Standards Report (:30) ............................................................................. Jim Graham

10. IEEE Staff Update (:10)........................................................................... Erin Spiewak

11. Meeting Planning (:10) ............................................................................ Greg Anderson

11.1. Vancouver Meeting Update

11.2. Future Meetings

Time Check (3:30 pm) & Break (20 min max)

12. Old Business

12.1. Status of TC O&P Manual and WG P&P Manual (:05) ............. S. Antosz/P. Balma

12.2. IEEE Fellows Representative (:03) ............................................ S. Antosz/P. Balma

12.3. New C57 Compilation CD (:03) ................................................. E. Spiewak/G. Anderson

13. New Business

13.1. Emeritus Membership (:10) ........................................................ S. Antosz/P. Balma

13.2. 100 Year Anniversary of Transformers Committee (:04) .......... S. Antosz/P. Balma

13.3. IEEE/IEC issue regarding dual references ................................. Paul Jarmin

Time Check – 4:15 PM

14. Subcommittee Reports – Roundtable (not intended to indicate order of reporting)

Bushings (:03) ................................................................................ Peter Zhao

Dielectric Test (:03) ....................................................................... Ajith Varghese

Distribution Transformers (:03) ..................................................... Steve Shull

Page 38 of 56

Dry Type Transformers (:03) ......................................................... Casey Ballard

HVDC (:03) ................................................................................... Mike Sharp

Instrument Transformers (:03) ....................................................... Ross McTaggart

Insulating Fluids (:03) .................................................................... David Wallach

Insulation Life (:03) ....................................................................... Sheldon Kennedy

Performance Characteristics (:03) .................................................. Ed teNyenhuis

Power Transformers (:03) .............................................................. Joe Watson/Bill Griesacker

Standards (:03) ............................................................................... Jerry Murphy

Underground Transformers & Network Protector (:03) ................ Dan Mulkey

15. Adjourn

10.4 CHAIR’S REPORT – STEPHEN ANTOSZ

Refer to Section 5.0 of the Main Minutes for a complete “Chair’s Report.”

Highlights:

• Topics from the last Technical Council meeting were reviewed.

• The Chair will be attending the upcoming Technical Council Retreat.

• New and recent Transformer Committee Subcommittee Chair appointments – Ajith Varghese

(Dielectric Test), Bill Griesacker (Power Transformers), Sheldon Kennedy (Insulation Life).

• Liaison representatives updates – David Brender (Standards Coordinating Committee No. 18 –

NFPA/NEC))

• The C57 collection CD is complete and some have been mailed already.

10.5 VICE CHAIR’S REPORT – SUE MCNELLY

Refer to Section 6.0 of the Main Minutes for a complete “Vice Chair’s Report.”

Highlights:

• Joint Technical Committee meeting on January 8-12, 2017 in New Orleans.

• General Meeting on July 16-20, 2107 in Chicago.

10.6 SECRETARY’S REPORT – BRUCE FORSYTH

Refer to Section 7.0 of the Main Minutes for a complete “Secretary’s Report.”

Highlights:

• There were eight applications for Committee Membership since the last meeting. One application

was from a Past Committee Member (Saurabh Ghosh). Mr. Ghosh was reinstated since his status

was changed to Past Committee Member less than two years ago. SA membership for one applicant

(Shankar Nambi) has not been verified, and he has been notified. A motion was made by Bruce

Forsyth (seconded by Stephen Antosz) to approve all new applications except Shankar Nambi’s.

The motion was approved unanimously.

• There were 10 positive responses to the essential patent claim question on the registration form. Of

those, only 3 provided any further detail and are noted in the full report.

• SC Chairs are asked to submit their minutes not later than December 4.

10.7 TREASURER’S REPORT – GREGORY ANDERSON

Refer to Section 8.0 of the Main Minutes for a complete “Treasurer’s Report.”

Page 39 of 56

Highlights:

• It has become tricky to show funds for certain advance payments for future meetings. Some venues

require payments so far in advance that they get mixed in with the timing of previous meeting costs.

• Overall our funds are in good shape.

• Greg noted challenges related to predicting foreign exchange rates.

10.8 RECOGNITION & AWARDS REPORT – DON PLATTS

Refer to Section 9.0 of the Main Minutes for a complete “Recognition & Award’s Report.”

Highlights:

• 6 WG awards will be handed out during the Tuesday luncheon.

• 7 WGs had awards mailed but will also be recognized.

• A candidate for the young engineer award has been identified.

• Don asked for any recommendations or suggestions for award recipients.

• A question was asked about the process to notify award recipients in advance to ensure they show up

for the awards luncheon. Should recipients be notified in advance? Don stated he would take this

under consideration.

10.9 STANDARD’S REPORT – JIM GRAHAM

Refer to Section 11.0 of the Main Minutes for a complete “Standards Report.”

Highlights:

• All PARs expiring this year are either complete or extensions have been requested, so none will be

administratively withdrawn.

• 3 new standards have been approved.

• Several PARs for revision have been submitted.

• October 17, 2017 is next year’s deadline.

• Will be seeking input from SC Chairs for updates on activity leaders.

• Working on guides for WG leaders (and SC Chairs).

10.10 IEEE STAFF UPDATE – ERIN SPIEWAK

Erin Spiewak introduced Malia Zaman who will be taking over Erin’s current responsibilities as program

manager for the Transformers Committee.

The current patent policy followed by the Transformers Committee does not strictly adhere to IEEE-SA

Standards Board Operations Manual requirements. The patent policy will be discussed during the Monday

luncheon. Moving forward, the patent question will continue to be asked at registration, but the patent

question (IEEE-SA SB 6.3.2) must be asked at each Working Group meeting with the results documented in

the minutes. This process is necessary since some meeting attendees may not see the patent question (e.g.

people who do not register online). A discussion related to past practice and current requirements took place.

Further discussion took place regarding what is required versus what is recommended with respect to the

patent slide presentation. Attention was made to IEEE-SA SB 6.3.2. which states:

“6.3.2 Call for patents

The chair or the chair's delegate of an IEEE standards-developing working group or the chair of an

IEEE standards Sponsor shall be responsible for informing the participants at a meeting that if any

individual believes that Patent Claims might be Essential Patent Claims, that fact should be made

Page 40 of 56

known to the entire working group and duly recorded in the minutes of the working group meeting.

This request shall occur at every standards-developing meeting once the PAR is approved by the

IEEE-SA Standards Board.

“The chair or the chair's delegate shall ask any patent holder or patent applicant of a Patent Claim

that might be or become an Essential Patent Claim to complete and submit a Letter of Assurance in

accordance with Clause 6 of the IEEE-SA Standards Board Bylaws. Information about the draft

standard will be made available upon request.”

It was noted that showing the patent slides that have been shown in the past does not comply with the

requirements stated in 6.3.2. Working Groups must make the verbal call and record the results in the WG

meeting minutes. Note that the WG Chair is not responsible for resolving any patent issues, only to ensure

potential patent claims are documented and requesting a Letter of Assurance from patent holders. Stephen

Antosz stated that he, Bruce Forsyth, Gary Hoffman, Erin Spiewak, and Don Platts will put together and

instruction for WG Chairs to provide them with the correct question to ask and instructions regarding actions

based upon response. Since this won’t be completed for this meeting, the issue will be discussed in the main

Committee tomorrow and WG Chairs will be asked to make a good faith effort to ask the question and record

the results. Gary Hoffman will provide a set of PowerPoint slides for that purpose.

IEEE has withdrawn its seat on the US National Committee (USNC) in an effort to be viewed as more

global. This does not affect its current dual logo agreement with IEC. As a result, IEEE cannot adopt IEC

documents and a process to include IEC content in our documents will have to be developed. A question

was raised regarding getting access to IEC information for use in our standards. Erin noted we would go

through ANSI since we are still accredited by ANSI.

10.11 MEETING PLANNING REPORT – GREGORY ANDERSON

No written report provided.

Highlights:

• Preliminary registration shows about 570 registrants, with about 126 companions

• The Spring 2017 meeting will be held in New Orleans, Louisiana, on April 2-6, 2017. The meeting

will be hosted by Marnie Roussell (Entergy).

• The Fall 2017 meeting location has not been determined, but the date will likely be October 29 –

November 2, 2017.

• The Spring 2018 meeting will be held in Pittsburgh, PA on March 25-29, 2018.

10.12 OLD BUSINESS

10.12.1 Status of TC O&P Manual and WG P&P Manual – Stephen Antosz & Peter Balma

Stephen Antosz noted that the Committee will be voting on proposed changes to the Transformers

Committee Organization and Procedures (O&P) Manual and the WG Policies and Procedures (P&P) Manual

during Monday’s meeting.

Peter Balma gave an overview of the proposed WG P&P Manual. First item for discussion is related to the

timing required for minutes to be completed. After some discussion, Steve Schull moved that the WG

meeting minutes be submitted within 15 days (seconded by Dan Mulkey). Stephen Antosz noted this is what

is currently in the WG P&P proposal up for vote. The motion was unanimously approved.

Page 41 of 56

Peter reviewed a few other changes and clarifications in the WG P&P proposal. Regarding quorum, the

question of whether quorum should be 50% or not less than 50% of the membership took place, but no

decision or action was taken.

Peter went on to discuss the proposed TC O&P Manual. Some of the more significant changes were

presented. Some concerns raised by Gary Hoffman based upon the direction the IEEE-SA is currently

moving. AudCom may have has some concerns that certain items related to standards development in the

TC O&P manual may need to be moved into the sponsor P&P. Gary mentioned that after reviewing the TC

O&P in more detail he believes the document really defines roles within the TC and not standards

development, and as such does not oppose the document as written.

A discussion related to who initiates reappointments of SC Chairs, Vice Chairs, Secretaries, etc. Stephen

Antosz noted the RC Chair appoints and reappoints SC Chairs.

A change for the scope of the Insulation Life Subcommittee was discussed. The proposal is to change “safe”

to “recommended” and this will be discussed during the main Committee meeting on Monday.

10.12.2 IEEE Fellow Representative – Stephen Antosz & Peter Balma

Someone from the TC needs to serve on the PES committee that evaluates people associated with

transformers. Bob Degeneff served during a recent review process. Sheldon Kennedy has agreed to serve

for the coming year.

10.12.3 New C57 Compilation CD – Erin Spiewak & Greg Anderson

The CD compilation was published and copies have been mailed those who made advanced purchases during

registration.

10.13 NEW BUSINESS

10.13.1 Emeritus Membership – Stephen Antosz & Peter Balma

Our adherence to rules related to emeritus membership has not been great. We need to follow the rules in the

sponsor P&P or recommend revisions that should be made. Stephen Antosz announced he has formed a

Task Force to review and resolve. Bruce Forsyth will chair the TF, and the members shall be Don Platts,

Stephen Antosz, Sheldon Kennedy, Steve Shull.

10.13.2 100 Year Anniversary of Transformers Committee – Stephen Antosz & Peter Balma

Peter’s research found the first reference to a Transformers Committee in 1918, making 2018 the 100 year

anniversary. A proposal has been made to make the spring 2018 a special celebration with special speakers

and events. Greg Anderson has assembled a small group to plan the meeting.

10.13.3 IEEE/IEC Issue Regarding Dual References – Paul Jarmin

Paul Jarmin discussed a problem related to dual logo documents with specific reference to the phase shifting

transformer standard. The IEC Standardization Management Board (SMB) raised a question regarding

listing normative references for both IEEE and IEC even though there is language in the document stating

that one or the other (IEEE or IEC) standard must be selected but not both. TC14 members met recently and

have informed SMB they are satisfied with the document the way it is, but this introduces the possibility that

SMB could reject the document. If that occurs the likely resolution will be to split the document into two –

one for IEEE and one for IEC.

Page 42 of 56

10.14 SUBCOMMITTEE REPORTS

Subcommittee Report/Hot Topic

Bushings

(S. Shull)

No pressing issues reported.

Dielectric Test

(A. Varghese)

3 new topics to be discussed this week, one of which

is from China (SGCC) related to filed measurement

of partial discharge.

Distribution Transformers

(S. Shull)

No pressing issues reported.

One regulator document going through the balloting

process.

Dry Type Transformers

(C. Ballard)

2 main standards have PARs approved.

12.60 (thermal issues) now in TC14 and PC112.

HVDC

(M. Sharp)

2 groups meeting this week.

HVDC converter transformer standard (dual logo) is

in comment resolution.

12.77 HVDC smoothing reactor standard – putting

together a scope for a PAR.

Instrument Transformers

(R. McTaggart)

A draft for a PAR for CCVT standard is under

review.

A recent proposal was made by CSA to make the

station service voltage standards a dual logo

document or to adopt it as is. This will be discussed.

Insulating Fluids

(D. Wallach)

C57.104 work will continue (new WG Chair).

C57.147 needed an extension for ballot resolution.

No response to request for LOA has been received.

A presentation on “Where Does The Air Go?” will be

made by Don Platts at the SC meeting.

Insulation Life

(S. Kennedy)

C57.162 work in process.

1276 requesting PAR extension.

C27.119 in recirculation balloting process.

New groups on Guide for Transformer Temperature

Measurements needs a PAR approval.

Jeff Ray raised a question related to interpretation of

cooling curve requirements.

Performance Characteristics

(E. teNyenhuis)

4 guides in various stages of balloting.

7 more in 2018 or beyond.

New group on short circuit design criterion.

2 Chairs stepping down.

Page 43 of 56

Subcommittee Report/Hot Topic

Power Transformers

(J. Watson)

Bill Griesacker taking over as SC Chair.

Kip Yule raised questions about minutes – too many

variations; suggestion for new template and possibly

a TF do develop the template.

Standards SC

(J. Murphy)

Need to update website data.

A few corrigenda under way.

Underground Transformers & Network Protectors

(D. Mulkey)

4 standards in progress.

2 in balloting stage.

2 working through changes.

10.15 ADJOURNMENT

The meeting was adjourned at 5:35 PM.

Submitted by:

Bruce Forsyth,

Secretary, Transformers Committee

January 1, 2017

Attachments (3): Annex 1 – Peter Balma’s Presentation to the Administrative Subcommittee

Annex 2 – IEC-SMB Decision 156/26 on IEC/IEEE Dual References

Annex 3 – TC 14 Response to IEC-SMB Decision 156/26 on IEC/IEEE Dual References

NOTE: The Attachments can be found in the full Administrative Subcommittee report on the Transformers

Committee website.

11.0 STANDARDS REPORT – JIM GRAHAM

Jim reported that the full Standards Report is available on the website.

The final day to have activities considered for approval in 2017 is October 16, 2017.

Jim reviewed the list of active documents and PARS.

The topic for the Monday luncheon will be on the IEEE patent process.

The semi-annual Standards Report is included as Attachment 2.

12.0 EDITOR’S REPORT – SANJIB SOM

Sanjib reported there were 36 papers submitted for consideration. Of those, 9 were accepted, 14 were

returned to be revised and resubmitted, and 7 are currently under review.

Page 44 of 56

13.0 LIAISON REPORTS

13.1 CIGRE – RAJ AHUJA (PRESENTED BY BRUCE FORSYTH)

Raj Ahuja’s overview of CIGRE activities was presented.

Page 45 of 56

Page 46 of 56

13.2 IEC TC14 TECHNICAL ADVISOR TO USNC – PHIL HOPKINSON (PRESENTED BY PAUL JARMIN)

Paul Jarmin presented an overview of TC14 activities.

Page 47 of 56

Page 48 of 56

Page 49 of 56

Page 50 of 56

Page 51 of 56

13.3 STANDARDS COORDINATING COMMITTEE NO. 18 (NFPA/NEC) – DAVID BRENDER

13.3.1 Changes to the 2017 NEC of interest to IEEE Transformers Committee

Article 450 specifically addresses transformers. There were no significant changes to Art. 450.

However, there were changes to other articles that may be of interest to utilities and affect certain operations

of those utilities. Briefly, they were:

Art 210.17 requirements for electric vehicles relocated to 625.40 which has been revised. A new section

was added entitled “Wireless Power Transfer Equipment”

Art. 210.18(B) expanded

Branch circuit for electric vehicles has been relocated to Art. 210.17. For 150V or less circuits, GFCI at

“other than dwelling units” expanded from 20 A to 50 A

Art. 230.24(B)(5) New requirement for 24.5 ft. clearance for overhead service conductors over railroad

tracks.

Art. 240.67 A new article has been added to require arc-energy reduction for fuses rated 1200 amps or

larger. In 2014 code, circuit breakers rated 1200 amps or greater were covered by 240.67. Now, fuses have

been added.

Table 310.15(B)(3)(c) was removed. This was the temperature adjustment table for wire and cable on

rooftops in sunlight. The only adjustment needed now is wire and cable mounted below 7/8 inch above a

rooftop. In my opinion, this change was political, not scientific.

Table 310.15(B)(7) revised to allow and recognize 208/120 services. Had been 240/120 only.

New Art. 691 Large Scale PV Arrays

New Art. 691 covers PV overs 50 kW and larger and not under exclusive utility control

Result of NFPA Large Scale PV Task Group.

New Part IV added to Art 705 added, recognizing Microgrid Systems

Sometimes called “separately islanded systems” or “stand-alone systems”.

New Art. 706 Energy Storage Systems added

2014 NO SEPARATE ARTICLE EXISTED.

Applies to all permanently installed energy storage systems

12 other Standards are referenced

Art 708.10 (A)( 2)

Indicator lights required on CRITICAL outlets where power stays on

New Art 710 for “Stand Alone Systems” was added

New Art 712 was added covering DC Microgrids

Page 52 of 56

Includes AC systems powered by DC – AC inverters

There is some confusion over whether “microgrid” refers to utility wiring and premises. It is not

meant to.

There are a number of opportunities to represent IEEE at numerous NEC Panels.

Respectfully,

David Brender, P.E.

13.4 STANDARDS COORDINATING COMMITTEE NO. 4 (ELECTRICAL INSULATION) – PAULETTE PAYNE

(REPORTED BY BRUCE FORSYTH)

13.4.1 Scope:

• To formulate guiding principles for the evaluation of insulation materials and systems for electrical

and electronic applications.

• To formulate principles for the identification of insulation materials and systems based on functional

tests and/or experience.

• To coordinate the preparation of standards for functional test programs and diagnostic methods for

the evaluation of insulation materials and systems.

13.4.2 Standards:

• IEEE 1-2000 (R2011) Recommended Practice – General Temperature Limits in the Rating of

Electrical Equipment and for the Evaluation of Electrical Insulation

• IEEE 98-2016 Standard for the Preparation of Test Procedures for the Thermal Evaluation of Solid

Electrical Insulating Materials

• IEEE 99-2008 Recommended Practice for the Preparation of Test Procedures for the Thermal

Evaluation of Insulation Systems for Electrical Equipment

13.4.3 Current Activities:

• IEEE 99 –PAR expires Dec 2020. Initial draft has been prepared but some details still need

development. Anyone interested in joining the P99 WG can contact the chairperson, Evanne Wang:

[email protected]

For those interested in joining the SC contact Paulette Payne Powell, Chairperson SCC 04:

[email protected]

Respectfully submitted,

Paulette Payne Powell

14.0 HOT TOPICS FOR THE UPCOMING WEEK

The Subcommittee Chairs gave a very brief update on topics of special importance being addressed during

the week.

Page 53 of 56

15.0 OPENING SESSION ADJOURNMENT

The meeting adjourned at 9:15am.

Page 54 of 56

Thursday Closing Session

16.0 CHAIR’S REMARKS AND ANNOUNCEMENTS

The Chair called the meeting to order at 8:00 AM.

17.0 MEETINGS PLANNING SC MINUTES & REPORT – GREGORY ANDERSON

Greg welcomed everyone and presented a summary of events of the past week. On Wednesday evening 245

people attended the social event.

Future meetings (also see Transformers Committee website):

Meeting Date Location

2017 Spring April 2 – 6 New Orleans, LA

2017 Fall Oct 29 – Nov 2 Louisville, KY

2018 Spring March 25 - 29 Pittsburgh, PA

Greg acknowledged the help of Tom Prevost for organizing the technical presentations and encouraged

participants to contact Tom with suggestions for future technical presentations.

Greg reminded attendees to avoid cancelling hotel rooms at the last minute since the Transformers

Committee may have to pay for rooms not filled. He asked everyone to coordinate the hotel rooms with

travel arrangements.

Participants were thanked for wearing their name badges in the meeting areas and a request was made to

drop the plastic badge holders in the designated boxes for reuse at future meetings.

Greg introduced Paul Chisolm with IFD Corporation and thanked him and his team for their efforts as hosts

of this meeting. Paul thanked his team for their hard work.

18.0 REPORTS FROM TECHNICAL SUBCOMMITTEES (DECISIONS MADE DURING THE WEEK)

Reports from each Technical SC were presented. Their minutes are included in full in the attached Annexes.

18.1 DIELECTRIC TEST SC (AJITH VARGHESE)

See full minutes in the Annex.

18.2 DISTRIBUTION TRANSFORMERS SC (STEVE SHULL)

See full minutes in the Annex.

The WG on C57.12.20 is continuing to work on the current ballot. C57.12.32 continues to review previous

issues. C57.12.34 has an active PAR. A possible patent issue has been raised and appropriate action is being

taken. C57.12.36 has been balloted and work on addressing ballot issues is ongoing. An error was

discovered in C57.12.38 and has been corrected. Work on a future revision has started. C57.12.39 has been

balloted and an extension request has been filed.

Page 55 of 56

18.3 DRY TYPE TRANSFORMERS SC (CHARLES JOHNSON, PRESENTED BY CASEY BALLARD)

See full minutes in the Annex.

C57.12.57 is out for ballot. C57.12.51 is trying to join with C57.12.50. New PARs have been approved for

C57.12.01 and C57.12.91. Discussion is taking place regarding C57.124 and how it can be based on other

documents. Work has started on C57.16.

18.4 HVDC CONVERTER TRANSFORMERS SC (MIKE SHARP)

See full minutes in the Annex.

Mike presented a summary of recent ballot activity.

18.5 INSTRUMENT TRANSFORMERS SC (ROSS MCTAGGART)

See full minutes in the Annex.

Ross was not able to attend the closing session but notified the Chair that there were no major

announcements to be reported.

18.6 INSULATING FLUIDS SC (DAVID WALLACH)

See full minutes in the Annex.

A presentation on “where the air goes” was made by Don Platts. Work on C57.104 continues. Draft 3 of

C57.147 is in ballot resolution. The TF on consolidation of insulating liquid guides continues to collect

information.

18.7 INSULATION LIFE SC (SHELDON KENNEDY)

See full minutes in the Annex.

PC57.162 has 10 task forces working on separate portions of the document. A PAR extension for P1276 has

been submitted. PC57.119 is in recirculation ballot. A new working group is about to be formed related to

temperature measurements.

18.8 PERFORMANCE CHARACTERISTICS SC (ED TENYENHUIS)

See full minutes in the Annex.

Ed presented an overview of the activities and status of current activities.

18.9 POWER TRANSFORMERS SC (JOE WATSON)

See full minutes in the Annex.

C57.12.10 was approved to go to sponsor ballot. C57.143 has had a change of leadership. Three new task

forces were formed (see full minutes for details). Joe announced he is stepping down as Chair but will

remain active. Bill Griesacker will be the new Chair and Kipp Yule will be the Vice-Chair.

18.10 STANDARDS SC (JERRY MURPHY)

See full minutes in the Annex.

Page 56 of 56

Reports on the ongoing revisions of C57.12.00 and C27.12.90 as well as C57.163 were presented during the

subcommittee meeting. A corrigendum for C57.12.70 is in process.

18.11 UNDERGROUND TRANSFORMERS & NETWORK PROTECTORS SC (DAN MULKEY)

See full minutes in the Annex.

Dan gave a presentation of a few leadership changes as well as the status of several activities.

18.12 BUSHINGS SC (PETER ZHAO, PRESENTED BY STEVE SHULL)

See full minutes in the Annex.

19.0 REPORTS FROM STANDARDS SUBCOMMITTEE AND STANDARDS (ISSUES FROM THE WEEK)

Jim Graham reported to the Chair that there was nothing to report.

20.0 NEW BUSINESS

A member raised the issue of gas insulated transformers and whether this falls under the scope of the

Insulating Fluids SC. This was raised as a topic for future discussion.

Another comment was raised that no overloading specifications are including in the bushing standards and

suggested this should be addressed. The member noted this was raised during the Bushing SC meeting but

that it was not mentioned in the summary discussion today.

No other new business was raised.

21.0 CLOSING SESSION ADJOURNMENT

The meeting was adjourned at 12:00 PM.

Page 1 of 15

ANNEX A Bushings Subcommittee

October 26, 2016

Vancouver, BC, Canada

Chair: Peter Zhao was unable to attend, therefore Eric Weatherbee filled in as Chair for this meeting Secretary: Eric Weatherbee, JD Brafa filled in as Secretary for this meeting

A.1 Opening of the Meeting

A.1.1 Introductions

The Chair opened the meeting with group introduction.

A.1.2 Attendance

Membership count was taken with the following results: 26 of 43 members were present with 106

guests and 2 corresponding members for a total of 134 attendees. There were 16 new membership

requests. There was a quorum.

A.1.3 Chairman’s Remarks

The Chair asked for a motion to approve the meeting agenda that was distributed prior to the meeting,

a motion was made by Mr. Dave Geibel and seconded by Mr. Raj Ahuja with no objections.

The Chair asked for a motion to approve the S16 Georgia minutes that were distributed prior to the

meeting, a motion was made by Mr. Craig Stiegemeier and seconded by Mr. Dave Geibel with no

objections.

Three new members were introduced to the SC and added to the roster. The new members were Mr.

Alwyn VanderWalt, Mr. Yves Vermette and Mr. Matthew Weisnsee. All three new members were in

attendance and therefore the member count was increased to 29 of 46 members in attendance.

The Chair presented the Standards Status Report for bushings, see Appendix A. It was noted that

C57.19.00-2004 will expire at the end of 2020 and that Mr. Peter Zhao, the Chair of the SC, would like

to have the standard updated prior to the expiration.

A.2 Working Group and Taskforce reports

A.2.1 C57.19.00-2004 – Keith Ellis, Chair (not present)

Mr. Keith Ellis was not in attendance; as such no new information was relayed to the SC.

A.2.2 WG PC57.19.01-2000 – Dr. Shibao Zhang, Chair; David Wallach, Secretary

Dr. Zhang informed the SC that the WG voted and would like to proceed to ballot with the document.

Mr. Dave Geibel made a motion for the SC to vote on proceeding to ballot which was seconded by Mr.

Sebastien Riopel. The vote count was taken with a unanimous agreement to proceed to ballot and

therefore there were no objections. See complete WG minutes in Appendix B of this report.

A.2.3 C57.19.100-2012 – Tommy Spitzer, Chair (not present)

Mr. Tommy Spitzer was not in attendance; as such no new information was relayed to the SC.

A.2.4 WG PC57.19.04 – Scott Digby, Chair; JD Brafa, Vice Chair; Secretary, Jim Campbell

See complete WG minutes in Appendix C of this report.

A.2.5 IEC/IEEE 65700.19.03 – Les Rechsiedler (IEEE) and John Graham (IEC), Co-Chairs

The first dual logo standard was approved June of 2014, as such no meeting was held.

Annex A

Page 2 of 15

A.2.6 WG PC57.19.02 Distribution Transformer Bushings – Steven Shull, Chair; Ed Smith, Vice Chair

See complete minutes in Appendix D of this report.

A.2.7 TF Composite Bushings – John Graham, Chair; Secretary, Robert Middleton

The Chair informed the SC that Mr. John Graham, TF Chair, had submitted the TF report to Mr. Peter

Zhao at the conclusion of the last conference with their suggestions. As this TF as completed its tasks

no new information was relayed to the SC at this time.

A.3 External Liaison Reports

A.3.1 IEC Bushing Standards Activity – John Graham, IEEE Liaison (not present)

Mr. John Graham was not in attendance but did submit a report for the SC to review during the

meeting. Mr. Dave Geibel noted a slight correction to a statement in the report. Mr. Geibel is a member

of A2:43 Bushing Reliability and it was stated that the brochure was recently published. However, Mr.

Geibel assured the SC it actually has not been released at this time. See complete report in Appendix

E of this report.

A.3.2 IEEE 693 – Eric Weatherbee, IEEE Liaison

Mr. Eric Weatherbee informed the SC that 693 is in the ballot process and the vote took place at the

beginning of August. He had contact Mr. Eric Fujisaki, the Chair for IEEE 693, for any information that

could be shared to the SC at this time. Mr. Fujisaki provided the following information:

“We went through our first ballot and fell 1 vote short of approval. We received 400+ comments and have made a quick review. I feel that most can be accommodated. I plan to reconvene the comment resolution subcommittee to get some concurrence on disposition, then recirculate, date TBD. We requested an extension to our PAR expiration date which is 12/31/2016 in order to address the comments and recirculate.”

A.3.3 WG PC57.160 Guide for PD Meas. in Bushings and Inst. Trans. – Thang Hochanh, Chair

Mr. Thang Hochanh informed the SC that during the last WG meeting it was noted that the document

discusses DC bushing however, they are not listed in the PAR. The WG did vote and approve

proceeding to revise the PAR and he would also like a vote from the Bushing SC in the matter. Motion

was made by Mr. Sanjib Som and seconded by Dr. Shibao Zhang to vote on seeking a revision to the

PAR to include DC bushings. A vote was taken and 25 of 46 members voted to precede with the

revision with no objection, therefore the motion carried. See complete WG minutes in Appendix F of

this report.

A.4 Unfinished Business

A.4.1 No unfinished business to discuss at this time

A.5 New Business

A.5.1 Mr. Jim Zhang had submitted an inquiry to the SC in regards to 500kV bushings.

Although Mr. Zhang was unable to attend this meeting or thus provide additional feedback, his inquiry

was presented for discussion as it was submitted:

“Current IEEE standard has only one voltage level for 500 kV systems, which is 500 kV nominal, 550 kV max. As we also know, some of the utilities operate 500 kV system at 525 kV Nominal, therefore 550 kV max. voltage is too low for this nominal voltage. Suggested is if additional voltage level of 525 kV (nom.) will be introduced into the standard.”

Most of the comments from the SC stated that they could not offer any pertinent feedback at this time.

However, they felt if Mr. Zhang can provide some additional information at the next meeting they may be

able to share a more substantial opinion on the subject.

Annex A

Page 3 of 15

Mr. Fred Elliott, former Chair of this SC, did offer a plausible explanation. Mr. Elliott stated there is some

confusion on the 500kV nominal with a 550kV maximum. For all the bushing ratings there is only a +5%

allowance for the maximum. However, it was decided that 500kV nominal and 525kV nominal are close

enough together it could cover both by extending the maximum over 500kV up to +10% i.e. 550kV

maximum. As such, 525kV nominal with its +5% maximum is included within this range.

A.5.2 Mr. Gustavo Leal stated there is a need to have On-Line Bushing Monitoring covered in one of the

standards or guides.

Mr. Leal Stated that his company has been doing pilot testing with On-Line Bushing Monitoring and ran

into an issue when a bushing manufacturer recommending not using online bushing monitoring on their

product due to a bushing design issue. Because of this recommendation, executive management at the

utility put a hold on the bushing monitoring project. The lack of any IEEE TX standard in this area

prevented him from being able to provide suitable information to keep the bushing monitoring project

active.

A.5.3 Mr. Ajith Varghese asked that draw lead cable sizes be added to the bushing standards.

It was noted that many, if not all bushing manufacturers can provide their recommendations for the cable

sizes for their specific products.

Mr. Fred Elliott stated that it was attempted to have these values provided in the standard as Mr.

Varghese suggested. However, they could not reach a consensus amongst the bushing manufacturers,

as such it was decided that each manufacturer should provide recommendations upon request.

A.5.4 Mr. Raj Ahuja proposed that Dry Switching Impulse test be required for all bushing design tests and the

values stated on the sales drawings.

A.5.5 Several commenters raised concerns and express the need for easier determination of bushing overload.

The initial commenters stated they would like to have bushings derated so that they have a “built” in

overload capability and therefore do not have to calculate it for each application. Another commenter said

there are parameters for in-service transformers stated in the transformer standards that could be used to

determine the overload capability.

Mr. Dave Geibel stated that bushing manufacturers provide the thermal constants for their bushing so that

their capabilities can be calculated for any applications. Mr. Geibel also stated that the bushing standards

do not require any overload capabilities beyond the rated current as specified on the bushing name plate.

Some OIP bushing may have some extra capabilities but is dangerous to assume resin type bushings

have any at all. At the rated current these types of bushings may be at or very close to the Tg rating of the

material and it is dangerous to cross that threshold. Mr. Geibel stated he would like to see something

added in the bushing or transformer standards similar to IECs 120% rule-of-thumb.

Dr. Shibao Zhang commented that the first step should be to calculate the overload capability for the

specific application as the rule-of-thumb is not always sufficient and it should only be used as the last

option if you cannot obtain the needed values for calculation. Mr. Geibel also agreed that calculation is

the best/first method that should be used.

The Chair noted that Mr. Tommy Spitzer, Chair for C57.19.100, has stated he will be working on getting a

consensus for overload recommendations and add it back into the Bushing Application Guide and that he

will start work on the next revision soon.

*Note: following the meeting Mr. Fred Elliott commented to the Chair and Secretary that their SOP for

overload was to use 130% bushing rating over that of the transformer. But they had some cases that this

still wasn’t enough and found they needed 150%.

A.6 Adjournment 10:25 am

Annex A

Page 4 of 15

Annex A

Page 5 of 15

Annex A

Page 6 of 15

Annex A

Page 7 of 15

Annex A

Page 8 of 15

Annex A

Page 9 of 15

Annex A

Page 10 of 15

Annex A

Page 11 of 15

Annex A

Page 12 of 15

Annex A

Page 13 of 15

Annex A

Page 14 of 15

Annex A

Page 15 of 15

Page 1 of 20

Annex B Dielectric Tests Subcommittee

October 26th, 2016 Vancouver Canada.

Dielectric Tests Subcommittee

Chair: Ajith M. Varghese Vice-Chair: Thang Hochanh Secretary: Poorvi Patel

Room : Grand Ballroom Date : October 26th, 2016 Time: 11:00 am to 12:15 pm

Members : 118 Present at time of checking : 77 Present per attendance roster & recorded to AM System: 86

Guests present : 139 Membership requested : 19 Membership accepted: 8

B.1 Chair’s Remarks

The Chair briefly highlighted the requirement that while introducing one need to state their employer/ company and sponsor if difference from company. Chair also reminded that IEEE and transformer committee are non-commercial organizations and standards shall focus only in developing performance and functional requirement and not design and construction details.

The Chair reminded the WG on attendance requirement for new membership and for continuation and the requirement to have attendance updated in AM system. Chair welcomed .the new members during the meeting.

The Chair reminded to start every meeting, conference calls if there are any patents that are known to be applicable for within the area of WG scope. If yes, patent claim type should be noted but not discussed at the working group meetings

The Chair shared details of upcoming PES sponsored meeting as well as details of next transformer committee. PES T&D Expo will be at Denver Colorado from 2018 April 16th – 19th. The next IEEE PES General Meeting will be in July 16th-20th,2017 in Chicago. The next transformer committee will be from April 2nd – 6th, 2017 at New Orleans, Louisiana.

Current Status of PARs was presented. C57.138 Recommended Practice for Routine Impulse Tests for Distribution Transformers – par expires 2016 however a par extension has been requested. C57.161 Guide for DFR Measurements, par expires December 2017.

Last meeting in Atlanta GA, 24 requested membership and 11 request were accepted. 9 participants status went from member to guest due to lack of attendance.

B.2 Quorum, Approval of Minutes and Agenda

The membership list was shown and a show of hands of committee members present showed that a quorum of members were in attendance at the start of the meeting. 77 out of 118 members were present at time of checking, so there was a quorum.

Annex B

Page 2 of 20

All attendance is recorded in AM System. Per verification of roster 86 members and 139 guests attended the SC in Vancouver, Canada.

The agenda was presented by the chair and it was unanimously approved. Motion for approval was made by Daniel Sauer and second by Sanjib Som

The minutes of the Spring 2016 meeting at Atlanta meeting was approved unanimously. Motion for approval of meeting minutes was made by Daniel Sauer and seconded by Vijay Mehrotra.

Annex B

Page 3 of 20

B.3 Taskforce and Working Group Reports B.3.1 TF on External Dielectric Clearances

Eric Davis, Chair; Troy Tanaka, Secretary

The Working Group on External Dielectric Clearances met on Monday October 24, 2016 at 9:30 AM in the Sheraton Vancouver Wall Centre. There were 53 people in attendance; 14 of 18 members, and 39 guests. Two guests requested membership, but will not be granted membership because the working group activities are coming to an end. A quorum was achieved. The full attendance record is available in the AM System.

Dan Sauer moved that the meeting agenda be approved. David Wallace seconded the motion. The agenda was unanimously approved.

Joshua Verdell moved that the spring 2016 meeting minutes be approved as written. Dan Sauer seconded the motion. There were no revisions or additions to the minutes. The motion passed unanimously.

The chairman asked if there were any known essential patent claims. None were stated.

The chair stated that he will be sending the text and table to the Dielectric Test Subcommittee, immediately following the fall 2016 meeting in Vancouver. He then asked for volunteers to help with resolution of the comments from the Dielectric Test Subcommittee. Dan Sauer, Javier Arteaga and Eric Davis volunteered to make up the comment resolution team. Dan Sauer moved to adjourn the meeting. David Wallace seconded and the meeting was adjourned at 9:40 AM.

Annex B

Page 4 of 20

B.3.2 WG on Dielectric Frequency Response Analysis (DFR) Ali Naderian, WG Chair; Peter Werelius, Vice Chair, Poorvi Patel, Secretary

Monday, October 24, 2016 – (3:15 -4:30PM) The meeting was called to order by the WG chair Ali Naderian at 3:15 PM. This is the 7th Working group meeting. There were a total of 97 attendees; 24 members and 73 guests and 8 requested to become members. 6 memberships were granted. 1. With 24 members attending the meeting we had a quorum (out of 37 members) 2. The minutes of meeting from the WG Spring 2016 meeting in Atlanta, GA, was approved- motion for

approval from Mark Perkins and Diego Robalino. 3. Ali presented the timeline of this working guide- The WG was established in 2013. 7 TF was created

and a first draft of document was produced in 2014. It modified by working group and task force members to create D1.3. This draft document was circulated for review in 2015 and about 125 comments was received. Over several conference calls and meeting in accordance to the fall or spring meeting the comments were addressed and a second revision of the document was produced. The review of the document generated comments from 2 reviewers (thanks reviewers) which was addressed in 2 conference calls between the Atlanta meeting and Vancouver meeting. The latest draft D2.0 was created October 3rd 2016 and uploaded to the website. D2.0 draft was also sent to the Dielectric Test Subcommittee Oct 10th 2016 for review.

4. The Par is expiring on 31st of December 2017. 5. The document is ready for Ballot voting. 2/3 of the members need to approve to take the document to

ballot a) Mark Perkins questioned if the document has been reviewed by the subcommittee? b) Chuck Sweetser commented that some review of editorial nature was needed c) Don Plats indicated that the graphs may not be according to the IEEE standard practice d) If we go for review mode- volunteers are needed to review the document that has not

been produced by them e) Mario indicated that this is what happens in the ballot process –many many fresh eyes

will review the document and come with comments f) Dan Sauer indicated that if we don’t move to ballot we will probably need to have a par

extension- this can however be decided in the spring meeting and if we have come far we may also go for ballot then.

g) Ballot are fresh eyes looking at the document h) Mario Motioned to send the document for ballot- second motion came from Tom Prevost i) If we pass the voting to send the document for ballot- a second approval process needs to

be done in the Subcommittee level. j) Dan Sauer and Mark Perkins had a motion to amend the existing motion- to do send the

document to the subcommittee for review and go for ballot next meeting. k) Ajit indicated we should go for clearing out the first motion made by Tom and Mario l) The outcome from the subcommittee level could very well be go for a review and not

ballot. m) The document was voted for ballot – 16 members voted to go for ballot and 3 opposed-

thus 2/3 majority was received. The document will be recommended to the subcommittee to go for ballot

6. Peter Werelius presented a study about DFR measurements on HV-bushings. Very interesting results was presented.

7. This DFR guide produced in this WG does not include DFR on Bushings, this could be a future TF.

Annex B

Page 5 of 20

8. Ali concluded to thank all the task Force leaders and contributors for their hard work on producing this DFR Guide.

9. Meeting was adjourned 4.15 pm- motion to adjourn by Diego Robalino and Tauhid Ansari. 10. Attendance was recorded in AM system after the meeting.

Ali Naderian, WG Chair Peter Werelius, Vice WG Chair Poorvi Patel, Secretary

Annex B

Page 6 of 20

B.3.2 Working Group for Revision of the Distribution Impulse Test Guide C57.138 Recommended Practice for Routine Impulse Test of Distribution Transformers; Arthur Molden, Chair; Susmitha Tarlapally, Vice-Chair

Vancouver, Canada, October 24th, 2016 The ballot and recirculation of a final Draft 4 of the document was successfully completed and that draft has now been accepted for final review by RevCom. The RevCom meeting at which acceptance will be voted on will be in December. A. Molden

Annex B

Page 7 of 20

B.3.4 TF on Revision of Impulse Tests

Pierre Riffon, Chair; Daniel Sauer, Vice-Chair Vancouver, October 25th – 4.45pm-6.00 pm The TF met on October 25, 2016, from 4:45 pm to 6:00 pm. Twenty-one (21) members and fifty-one (51) guests attended the meeting. Seven (7) guests requested membership. The meeting was chaired by Pierre Riffon, chair of the TF. Mr. Daniel Sauer was the vice-chair. Attendance has been recorded in the AM system. Required quorum was met, presence of at least 19 members was required. Twenty-one members were present. The TF membership and guest roster has been reviewed after the Atlanta meeting and members who did not attend the last two meetings were moved as guests. Guests (114) who did not attend the last five meetings have been deleted from the TF roster. Revision 1 of the agenda has been approved unanimously. Mr. D. Wallace made the motion and Mr. B. Poulin seconded it. The Memphis meeting minutes were approved as written by all members present. The motion has been made by Mr. M. Perkins and seconded by Mr. J. McBride. The Atlanta meeting minutes were also approved unanimously. The motion has been made by Mr. D. Wallace and seconded by Mr. M. Perkins. The first item of business was related to the 4th survey on the impulse front time test parameters and tolerances. This survey was sent on March 27, 2016 to the TF and Dielectric Tests Subcommittee rosters. Out of 592 individuals who were asked to participate, 88 provided a reply (return rate of 14.9%). Out of these 88, 80 were approved or approved with comments (100% approval rate), none disapproved and 8 abstained. The proposal is making consensus and will be sent to Steve Antosz for inclusion in the next revision of C57.12.90. The second item of business was related to the 2nd survey on the way that the chopping time during chopped-wave tests is defined and measured. This survey was sent on March 27, 2016 to the TF and Dielectric Tests Subcommittee rosters. Out of 645 individuals who were asked to participate, 87 provided a reply (return rate of 13.5%). Out of these 87, 67 were approved or approved with comments (89.3% approval rate), 8 disapproved and 12 abstained. The negatives have been discussed and in order to satisfy most of them, a TF Chair counterproposal has been discussed and agreed upon. This counterproposal will be surveyed to the TF and Dielectric Tests Subcommittee rosters prior to next meeting. The motion for making new survey has been made by Mr. A. Varghese and was seconded by Mr. M. Perkins. The third item of business was related to the 2nd survey on the instantaneous voltage level at instant of chopping. This survey was sent on March 27, 2016 to the TF membership. Out of 303 individuals who were asked to participate, 48 provided a reply (return rate of 15.8%). Out of these 50, 28 were approved or approved with comments (68.2% approval rate), 13 disapproved and 7 abstained. The negatives have been discussed. In addition to the Chair proposal, a question of principle related to the need of having such additional criteria was also surveyed. 48.8 % replied "yes" and 34.8% did answer that this is not needed. Since there is no clear and large consensus, this subject will be dropped from the TF agenda unless a member will come with something which may make a better consensus. On the new business, the Chair received an Email from Phil Hopkinson regarding the need of revising impulse testing procedures and adding new transient tests in order to improve transient test severities for

Annex B

Page 8 of 20

covering resonance related failures during service. The TF Chair considers that this is too early for discussion and needs to be, first, fully discussed and agreed within the C57.142 TF and Dielectric Tests SubCommittee. The meeting adjourned at 5:40 pm on October 25, 2016. The adjournment motion was made by Mr. J. McBride and was seconded by Mr. A. Bolliger. The next meeting is planned to be held in New Orleans, LA, on April 4, 2017. Pierre Riffon P. Eng. TF Chair October 25, 2016.

Annex B

Page 9 of 20

B.3.5 TF on Revision of Low Frequency Tests Bill Griesacker, Chairman; Daniel Blaydon, Vice Chairman; Myron Bell, Secretary

Vancouver, BC – October 25, 2016, 1:45 p.m..

1. There were 129 attendees, 31 members and 98 guests present at the meeting; 10 guests requested membership, 5 of those will be granted. More than 50 % of the working group members were in attendance at the meeting, therefore a quorum was present.

2. The meeting was called to order at 1:45 PM

3. The agenda for the meeting was presented and unanimously approved.

4. A motion was made to approve the minutes from the Spring 2016 meeting in Atlanta, GA. The minutes were unanimously approved with no objections or comments voiced. One editorial correction was made to the minutes concerning the year referenced for the previous meeting.

5. New business

6. a. A presentation was given by Edgar Trummer concerning PD level criteria during induced

voltage tests. I. The presentation triggered a discussion concerning the current PD level

criteria covered in IEEE standards. The general consensus of the group was that the guaranteed PD levels in the current standards need to be reduced.

II. Edgar Trummer made a motion to “Reduce allowable PD levels to 100 pC, allow no PD up to max operating voltage, call for a maximum PD @ 110% max operating voltage to be 20 pC, require maximum background noise level of 40 pC, and determine PD inception and extinction voltage.” The motion was rejected based on 0 votes in favor, 22 in opposition, and 4 abstentions.

III. A second motion was made by Steve Antosz to form a study group, under this Task Force, to investigate standard PD limits during induced voltage testing. The motion passed unanimously and volunteers were asked to approach the Chairperson after the meeting to participate in the study group. Volunteers are still needed and are encouraged to contact Bill Griesacker, Dan Blaydon, or Myron Bell if they would like to participate. A meeting time slot has been requested for Monday of the next Transformers Committee meeting to be held in New Orleans.

b. A suggestion was made to explore the idea of a Low Frequency Dielectric Test Guide, similar to the other companion guides that already exist for other sections of 12.90. Bertrand said this would be an issue for the SC to discuss and he would follow up with them.

Annex B

Page 10 of 20

7. Old business

a. Tap changer position during induced test (survey results).

Bertrand Poulan presented the results and comments of the survey conducted after the last meeting. A positive approval rate was observed, however, there is still no agreement. Bertrand offered a few options on how we could proceed and will follow up with an updated text for the survey and report back.

b. Applying pressure inside a transformer tank during induced test (survey results)

Bertrand Poulan once again presented results and comments from the survey with an overall good approval rate. There are still too many valid comments opposing the wording and requirements, but has overall made everyone aware of the possibility occurring during factory testing. Bertrand will follow up with new wording of the proposal. Don Platts’ survey response noted that some of the new wording sounded like more like a guide. It was suggested that one option would be to undertake a low frequency test guide, and maybe for now move the text to an informative annex until a guide is written.

c. Alternative Applied test method for HV Delta windings.

No further progress, this topic was tabled until the next meeting.

d. Gassing issue for certain types of transformers with wound cores: proposal for new design test

Carried over from last meeting, this topic was tabled until next meeting.

e. Dielectric testing in the field.

Carried over from last meeting. Mark Perkins will write the details of a motion to generally require field tests on transformers with new insulation to be tested in accordance with C57.12.00 test voltage levels and transformers with other than new insulation to be tested in accordance with C57.12.90 test voltage levels. Background levels for PD can be a problem in the field and will need to be addressed.

8. This Task Force plans to meet next in April of 2017 at the Spring Transformer Committee meeting

to be held in New Orleans, Louisiana.

9. The meeting adjourned at 3:00 p.m.

Annex B

Page 11 of 20

B.3.6 WG - IEEE Guide for the Detection of and Location of Acoustic Emissions from Partial Discharges in Oil-Immersed Power Transformers and Reactors (C57.127) Chair: Detlev Gross Chairs Vice Chair: Jack Harley Secretary: David Larochelle Vancouver, October 25th 2016 Room: Port Alberni

Annex C Meeting Attendance The working group met at 11:00 AM. 74 persons were in the room and 20 members out of 22 were present. Quorum requirement was met. Complete attendance record is available in the AM System.

Annex D Discussions

The meeting started with the unanimous approval of the agenda (motion by Gregorio Lobo, second by Mike Franchek. The minutes from the Atlanta meeting were also unanimously approved (motion by Hemchandra Shertukde, second by Mike Franchek).

During call for patents potentially essential to the implementation of the proposed guide, Hemchandra Shertukde, Ph.D., declared his patent number US6178386. Subsequent review of the US Patent Office website indicates that this patent was recorded January 24, 2001 and expired February 18, 2013. Unless there is further information to the contrary, this patent will not be included in the Guide.

A presentation was given to the group about certain acoustic principles that will be added to the guide. Details were given about the way the mechanical energy from the partial discharges disperses in a spherical way. The energy drops with the square of the distance. It was also mentioned that oil temperature will have an effect on the propagation speed which will affect the precision of the location results if not compensated.

Different examples of wave shapes were presented with characteristics corresponding to the direct path to the sensor (oil only) and to the combined oil-steel propagation path. Internal structure of the transformer will sometimes prevent direct propagation of the waves to the tank wall. In some case, the waves will propagate through channels that will guide the waves to an exit point from where normal propagation can take place. In these cases, localisation results will change when changing the sensors position on the tank. Having the schematics of the transformer is a great advantage for identifying the possible propagation paths.

Raja Kuppuswamy mentioned that there are calculations on the waves that can be used to extract the time of arrival. Although this is usually a process correctly done manually by the users, Arturo Nunez mentioned that it can be of great use when acoustic is used in a monitoring perspective.

Annex B

Page 12 of 20

Two additions to chapter 6 were shown to the group highlighting differences from factory test to field test regarding power frequency and available sensors to acquire electrical signal.

A call was made to the group to gather examples of documented localisation cases for potential inclusion in the guide. The cases would ideally represent different contexts of localisation and highlight the procedures that led to successful results.

The group will meet again in New Orleans for the spring 2017 meeting.

Annex E Adjournment The meeting was adjourned at 12:10 PM.

David Larochelle

Annex B

Page 13 of 20

B 3.7 Working Group for PD in bushings, PTs and CTs – PC57.160 WG Secretary: Thomas Sizemore; WG Chair: Thang Hochanh Meeting Minutes October 24, 2015 at 4:45 – Vancouver, BC Canada Attendees: 57 Members attending: 20/34 Rosters: Circulated for members and guests. Agenda: An agenda was presented for the meeting. Essential Patent Claims: Text was displayed and the Chair inquired as to if anyone knew of essential patent claims. None were brought up during the meeting. Minutes: Motion approved David Wallace (1st) & Pierre Riffon (2nd) Items discussed based upon comments received: A total of 17 comments were received for discussion many were editorial or minor in nature. Details of the discussion points are below. Comments accepted and which will be in the next draft:

• Introduction – An introduction will be added to the draft. • IEEE C57.13 was not in the list of references. • 6.3.1 Figure 3 text is to be updated for consistency of wording which references test taps. • 6.3.2.1 Pierre Riffon proposed text for the bushing section to match the instrument transformer

section regarding the measured PD limits once the calibration is completed. • 6.4 It was proposed to move the list of abbreviations from 6.4 up in the document to 3.2 as they

are used throughout the document. • 6.4 Shibao Zhang proposed an editorial change from ‘is’ to ‘are’. • 6.4 Shibao Zhang proposed an editorial change in paragraph 1 to match the indication of bushing

tap for consistency. • 6.5.1 Shibao Zhang proposed to add the following text to the end of the section. "Calibration

circuits in Figures 10 and 11 may be slightly adjusted to reflect the point that the ambient noise during the test can be as high as the testing circuits in Figures 5, 6, and 9. However, the calibration injection points should always be the outlet of the capacitance C1 of the test object, points A and B. “

• 6.6.1 Pierre Riffon indicated that a precision need to be mentioned to reflect the point that the verification of a valid calibration is performed at a level not necessarily at 50% of the partial discharge limit for DC bushings.

• Thomas Sizemore indicated that several figures need to be updated to improve consistency of line weights, etc.

• Pierre Riffon: Correction to figure 17 labeled as a balanced circuit (unbalanced circuit). • Figure 10: For the clarity of the figure, the chair proposes a dotted line box around the capacitor

and the square wave signal generator. • 7.2.1 Vladimir Khalin indicated that no explicit instructions were provided for the testing of line

to line VTs. • The annex 'PD Measuring Circuits' (initially annex A), covers many of the same topics as the

guide. It was decided to remove it, due to duplication of definitions and explanations • Thomas Sizemore propose an introduction to be added to the annex related to PD patterns.

The follow comments were discussed but not accepted.

• 6.5.1 Jitendra Mamtora indicated a potential error in the calibrator circuits used in the guide. • An additional pattern taken from an online monitoring system was discussed. The PD pattern

cannot be positively identified being in the bushing installed on a transformer.

Annex B

Page 14 of 20

Additional items discussed: The wording of the PAR was discussed. It currently does not cover DC bushings which are in the draft document. The working group agreed to pursue a change in the PAR to incorporate DC bushings in the guide. Tom Provost indicated that he is willing to assist the Chair in this process. Motion to adjourn: A motion was presented by David Wallace and was seconded by Detlev Gross. Spring meeting 2017: The chair plans to wrap-up the draft for the New Orleans meeting and submit the Draft for approval by the WG. Date: 2016-10-25 Secretary: Thomas Sizemore Chair: Thang Hochanh

Annex B

Page 15 of 20

B 3.8 Task Force Winding Insulation Power Factor & Winding Insulation Resistance Limits WG Secretary: Diego Robalino; WG Chair: Susmitha Tarlapally Tuesday 10/25/16– Vancouver, Canada Meeting initiated at 08:00 AM at the Jr. Ballroom CD, Sheraton Wall Center, Vancouver, BC, Canada

Susmitha Tarlapally (Chair) and Diego Robalino (Secretary) at the meeting

Quorum identified 25 members attending at the beginning of the session. Attendee Sesion Report from the electronic System shows;

Activity Name: TF Winding Insulation PF/Resistance Limits Activity ID: 2186 Number of Members in Activity = 46 Number of Members Present = 25 Quorum Present = 54.3% Number of attendees = 79

• Susmitha requested a motion for Approval of S16 meeting minutes, Ajith Varguese first and David Wallach second to approve the minutes. None oppose. Unanimous approval.

• Diego Robalino presented 7 general examples of different PF and IR tests performed and results were used for general discussion.

o Mark Lachman pointed out that looking only at PF values may not be important, need to look at C and current, watt loss.

o It was emphasized that probably using only PF and IR values is not sufficient and best practices together with better diagnostic references should be considered

• A generic survey flyer is distributed among the group to get an idea of the limits in the mind of the attendees to this TF session.

o Suggested to add if the person completing the survey is a Member or Guest o Suggested to go back to factory and get a better and more accurate number o Peter Werelius suggested not to use PI for acceptance/commissioning. o Requested to submit the survey information via e-mail if no need for confidentiality o Aniruddha Narawane, questioned the scope and the validity of the survey. Susmitha

explained the need for having some benchmark information from the group. • Survey flyers collected. • Any new topic for discussion:

o Mark Perkins: Temperature correction of parameters is an issue. Major change on Temperature correction procedure. Mentioned the use of DFR as part of the analysis, mentioned geometrical parameters having an influence on the temperature correction. The importance of temperature correction has been highlighted.

o Susmitha responded that condition might be different for distribution transformers vs power transformers and factory test might be performed at temperatures away from 20C.

o Mark Lachman: Mentioned the influence of bushings or other components on the overall PF.

• Ajith Varguese: Asking what is next step. How to use this survey? Susmitha explained the use of information for reference and statistical analysis.

Annex B

Page 16 of 20

• Data Base question: Michael Franchek had no updates and Ajith will ask and provide feedback later to TF leaders.

• Ramsis: discussed the influence of wound core technology, high resistance among the core, would this affect the PF measurement? Suggested to include the core design for PF limits.

• Poorvi Patel also mentioned the differences that may be observed between different capacitances tested.

• Survey table will be submitted to the members and guests covering the topics for survey from the first meeting. Requested motion to proceed.

o Mario Locarno: Motion to send the survey to members of the TF detailing information to gather and begin the task of collecting general reference for what limits should look like for PF and IR.

o Dan suggested to submit to members and guests o Uannimus approval

• No more topics for discussion • Motion to adjourn Vijay Tendulkar, Aniruddha Narawane second • Meeting adjourn 8:55AM

Annex B

Page 17 of 20

E.1 Liaison Reports

E.1.1 Voltage Test Techniques (HVTT), IEEE Standard 4 - Arthur Molden

HVTT LIAISON REPORT OCTOBER 2016, VANCOUVER BC CANADA The IEEE High Voltage Test Techniques (HVTT) Subcommittee of the Power Systems Instrumentation and Measurement (PSIM) Committee met in conjunction with the IEEE PES Fall 2016 Switchgear Committee Meeting, in Pittsburgh, PA. The meeting took place at 2PM, Tuesday October 11th, in the hotel and on line via a video web conferencing service. There were 6 members and 3 guests present onsite for the meeting, 1 member and 3 guests attending via web conference, and 1 member attending via teleconference. The membership attendance was sufficient to achieve a quorum, and the Minutes of the last HVTT meeting held in Memphis, TN in January 2016 were approved. Prior to this meeting, members of the HVTT Subcommittee made a presentation to the Switchgear Committee members and guests on Monday October 10th, which included a brief history of IEEE Standard 4, a presentation on measurement uncertainties, and a presentation on impulse parameter extraction by the k-factor method. On the morning of Tuesday October 11th, the working groups met who are responsible for the revisions of IEEE 1122 and IEEE 510. IEEE 1122 is the Standard for Digital Recorders for Measurements in High-Voltage Impulse Tests. The minutes of this meeting will be included in the HVTT minutes when published later this year. There is an active PAR for the revision of this standard, which was last reaffirmed in 2008. IEEE 510 is the Recommended Practices for Safety in High-Voltage and High-Power Testing. The minutes of this meeting will be included in the HVTT minutes when published later this year. This document was last reaffirmed in 1992, and although it is presently considered as inactive by the IEEE, it is still commonly referenced in other active standards and in work safety procedures utilized by private HV testing organizations. A PAR has been submitted for consideration at the December 2016 IEEE NESCOM meeting to rewrite and reissue this document in the form of an IEEE Guide. Both working group meetings were conducted from the hotel meeting room and also included web conferencing attendance. The web conferencing service was a new experience for this working group, and while it enables higher meeting attendance levels and more technical discussion, the service requires a more disciplined coordination of member comments, both in the room and over the web. Audio and video quality can vary during the meeting, and can be compromised by inadvertent interruptions to a comment, the results of which may require repetition of a discussion and some loss in productivity. However the overall result was quite successful. Actual Standard 4 business discussed at this meeting included: • Progress of AC voltage measurement Round Robin • Differences between IEEE Standard 4 and IEC 60060 Step Response testing procedures used in the qualification of impulse measuring systems

Annex B

Page 18 of 20

• Slightly different definitions for the peak value of an AC voltage in IEEE Standard 4 versus IEC 60060-1 • Corrections required in Table 5 of IEEE 4-2013 to correct the units given for the column specifying the water resistivity values to be used during wet tests of insulators • The need to provide more information and guidance on the use of Type B (systematic) uncertainties in the estimation of the combined expanded uncertainty, as required in the calibration of HV measuring systems made in accordance with IEEE Standard 4-2013. Finally, there was interest expressed by the Switchgear Committee in having a general IEEE Guide for Partial Discharge Measurement, as a horizontal (non-apparatus specific) document, as their former PD Guide (IEEE 1291) is expired. The HVTT Subcommittee agrees that such a guide would be beneficial, and we believe that HVTT would be the correct group within IEEE to organize its development. Following some investigation into what level of support may be available to develop such a guide, discussion of this topic will continue at the next HVTT meeting in January 2017. The High Voltage Testing Techniques Subcommittee is actively soliciting members. Should anyone be interested in joining HVTT or it’s working groups, please contact Jim McBride or Jeff Britton for details. The next HVTT meeting will be at the IEEE Joint Technical Committee Meeting in New Orleans, LA, January 8th to 12th, 2017. END A. Molden / jab 10/26/2016

Annex B

Page 19 of 20

E.2 Discussions

• The working group chair for DFR Ali Naderian requested a motion to send the current version of DFR guide to ballot. Second motion was made by Diego Robalino. 36 approved to move for ballot, 8 opposed and 9 abstentions. The Current version of the DFR guide was approved to send for ballot.

• Thang Working Group chair for PD in bushings, PTs and CTs – PC57.160- presented a motion to expand the current scope to also include DC Bushings. Second motion was made by Raj Ahuja. Motion was passed unanimously. This motion was also passed in the Bushing Subcommittee meeting.

• Bertrand Poulin proposed a motion to modify the wording on proposed section related to tap changer position during induce test by moving the detailed explanation and examples to annexure of C57.12. 90 until a guide of low frequency testing is developed. Second to this motion was Sanjib Som. 44 approved the motion, 2 opposed and 9 abstentions. There was also a discussion on having a WG for creating the guide on low frequency test but no decision was made.

• Motion to survey the new section on air clearance that was approved by TF on External clearance was passed unanimously.

• Motion to survey for the 3rd time the modified wording related to way that the chopping time during chopped-wave tests is defined and measured was also passed unanimously

E.3 Old Business

Motion Approved during S16 to Request Performance subcommittee to expand scope of Task Force on “ Switching transients induced by transformer-Breaker interaction PC57.142 to “Investigate effect of high frequency transient on transformer and identify mitigation which may including additional factory testing or prevent transients from reaching unit”

Performance Subcommittee Chair agreed to this request.

Phil Hopkinson presented on the subject of transformer failures related to high frequency transient during PC57.142 WG Meeting. This presentation is posted on Dielectric Subcommittee home page - “ Fall Presentation - Impulse Test Concepts “

Annex B

Page 20 of 20

E.4 New Business

• Request for PAR “ Guide for Field Measurements and Pattern Recognition of Partial Discharges in Oil-immersed Power Transformers

• A PAR request was received by IEEE –SA from SGCC for new guide prior to F16 meeting, but was not discussed in transformer committee earlier.

• Representative from State Grid Corporation of China made a presentation to support the case.

• Due to limited time, discussion of the request and presentation could not be taken up. DTSC chair will forward the presentation to members by email before next meeting.

• Concern with bushing PD affecting transformer induce test. • A concern was raised during F15 Bushing SC meeting regarding need for bushings to

be vented to have transformer pass partial discharge limits during induce test. This resulted in lengthy discussion where many transformer manufactures and utilities shared similar views and expressed concerns with warranty and field performance. Bushing manufacturer in general acknowledge the concern but reported there has been no field defects and issue has been there forever with OIP design. Bushing SC requested DTSC to evaluate next steps

• Due to lack of time, this was not taken up for discussed during this meeting.

• Review of accuracy requirement for power factor test defined under C57.12.90 – 10.10.2 o Due to lack on time, this item was not taken up for discussion during this meeting

E.5 Adjournment

Meeting adjourned 12.05 PM. Motion to adjourn made by Dan Sauer and Sanjib Som

Minutes respectfully submitted by: Poorvi Patel Secretary DTSC.

1 of 14

Annex C Distribution Subcommittee – Chair: Stephen Shull

October 26, 2016 Vancouver, BC, Canada

Chair: Stephen Shull Vice-Chair: Jerry Murphy

C.1 General Opening

Steve opened the meeting welcoming everyone to the meeting. Jerry circulated the rosters. To establish a quorum, a list of members were displayed and a count of was made. We did have a quorum with 36 of the 63 members in attendance by count of those identified on a slide presented in the meeting. Recorded attendance gave 136 in attendance, 42 members and _ requesting membership.

The agenda was reviewed and motion made by Dan Sauer, seconded by Martin Rave and approved by unanimous acclamation of the members in attendance.

The Spring 2016 meeting minutes were reviewed and motion made by Ron Stahara, seconded by Josh Verdell and approved by unanimous acclamation of the members in attendance.

C.2 Working Group and Task Force Reports

C.2.1 C57.15/IEC 60076-21 – Step-Voltage Regulators – Craig Colopy

Craig presented the following minutes from the working group meeting on October 24, 2016 at 4:45 p.m. with 41 people in attendance.

Craig Colopy opened the meeting and introductions were made by the attendees. Rosters were distributed. The Essential Patent call was made by Craig Colopy with none received from attendees. Check for Quorum was made - 22 Members of 36 member were in attendance - Quorum achieved. Approval of agenda - Dan Sauer made Motion, Martin Rave seconded, no opposition to approval. Approval of minutes from Spring meeting in Atlanta - Motion for approval by Said Hachichi and second by Dan Sauer, no opposition to approval

IEEE ballot status and results Draft 2.0 ended Oct 23, 2016. 122 in ballot pool 99 returned ballots 81% return rate 94% affirmative rate 5 negative votes 101 comments

Chair discussed the IEC-TC Meeting that was held in Frankfort Germany Oct 11-12, 2016. Craig reviewed the current status with the IEC WG for MT 60076-21 IEC 2CD (Draft 2.0). 1CD (IEEE D1.5) sent January 16 6 Countries responded with comments IEEE Ballot issued on D2.0 (September 2016) Expired Oct 23, 2016

Annex C

2 of 14

2CD (IEEE D2.0) sent out September 16; expires end Nov 16 Original CDV - scheduled for Aug 16; reschedule planned for Dec 16; expires March

2017 IEEE Recirculation Ballot planned for March 2017

Craig reviewed key comments of ballot process from Friday meeting, Oct 21 discussions. See attachment 1.

Craig then reviewed some of the comments received that had not previously been discussed.

All 101 comments are noted on the Ballot Comment Resolution spreadsheet. Spreadsheet and next draft for CDV and recirculation will be posted to Distribution website. The next meetings will be held the spring 2017 in New Orleans, Louisiana

Motion made to adjourn by Lee Mathews, seconded by Scott Wilson, Motion carried. Recorded and submitted by: Craig A Colopy/Gael R Kennedy

C.2.2 C57.12.20 – Overhead Distribution Transformers – Al Traut

Al presented the following minutes from the working group meeting on October 24, 2016 at 11:00 a.m. with 59 in attendance.

The meeting was called to order at 11:05am on 10/24/2016 immediately followed by introductions and circulation of rosters. Electronic recording of attendance was not available at this meeting.

Chair made a call for Essential Patent Claims and none were brought forward

Based on the WG members listed on the roster and projected at the meeting a quorum was declared after a showing of hands (26 of 37 members present).

A motion was made (Stahara) and seconded (Pezin) for approval of the agenda. Unanimously approved

A motion was made (Stahara) and seconded (Hachichi) for approval of the S16 (Atlanta, GA) minutes. S16 Minutes were unanimously approved

Chair reported the results of the Sponsor Ballot. Closed 4/8/2016, 88% return, 100% Affirmative, 81 Comments.

Chair reported that our PAR expires 12-2016 and a 1 year PAR extension request was submitted 9/24/2016 and is on the Dec NESCOM agenda.

The remainder of the meeting was devoted to resolution of comments received from Draft 4 ballot.

4.3 Minimum Impedance voltage

“For each transformer design, the manufacturer shall determine the nominal impedance. The impedance of individual transformers shall be within the tolerance on impedance as specified in IEEE Std C57.12.00. The minimum nominal impedance shall be per Table 12 which applies to all distribution transformers with low voltage ratings 600 V and below. Two winding distribution transformers with low voltage ratings above 600 V should be designed to withstand short circuits limited only by the impedance of the transformer. There is no requirement for ratings not shown in Table 12.” A motion was made by Marty Rave and Ron Stahara to the user may specify. Motion was unanimously approved.

Annex C

3 of 14

Clause 5.1 Basic Lightning Impulse & 5.2 Dielectric Test. A suggestion was made on clause 5 that is more rating related to test levels and Clause 6 is related to the actual tests. Al Suggested that we change title of 5.1 to Basic Impulse Insulation Levels and 5.2 to Dielectric Test Levels. This distinguishes clause 5 which outline insulation level requirements from clause 6 which addresses tests. A motion was made by Ron Stahara and seconded by Steve Shull. The motion was approved unanimously

Clause 7.3 Polarity Terminal Markings. The title of the clause does not include all the content. Al suggested “The title and arrangement of this clause has been in use for many revisions of this standard. Expanding the title of 7.3 would result in a lengthy, confusing title”. Al suggested that we consider reviewing in detail for the next standard revision. No vote was taken but everyone agreed.

Clause 8.2. The angle of tilt was discussed. Al Suggested that we reject the comment and stated “The existing clause sufficiently instructs users when an angle of tilt requirement may be needed. Users may further describe the angle of tilt from vertical or horizontal”. No vote was taken but everyone was OK with Al’s suggested comment

Clause 9.1. There were three parts of this comment the first part, Al stated that “The comment does not offer a clear proposal for the revision”. The recommendation was to reject the with Al’s justification. The second part pf Clause 9.1 Al stated that “The present wording is sufficient and conveys that each transformer enclosure is limited to no more than two tests”. The recommendation was to reject the with Al’s justification. The third part of Clause 9.1, Al stated that “The proposal is not sufficiently different than the existing wording”. The recommendation was to reject the with Al’s justification. Again, Al was suggesting that we reject the comment for consideration for a future revision. There was no strong feeling or objection brought forward by the WG. No vote was taken but there was no objection to moving forward with AL’s comment.

Clause 7.1.1 The comment was reviewed by AL with the WG . . . Al Suggested that we replace Low Voltage with ALL bushings shall be sidewall type . . . Also the shaded area “zone” of acceptability was not consistent with the 1 bushing and 2 bushing. Carlos Gaytan brought up a question ...Base on discussion Al suggested we accept the comment as written... No vote was taken at the time but the WG agreed

Clause 7.2.1 ...Tap Change ...The comment was this was awkwardly worded...It was suggested that we change it to "A written caution statement to de-energize the transformer before operating, shall be located on or adjacent to the operating mechanism." Al’s suggestion was that we accept the comment. No vote was taken at the time but the WG agreed

Clause 7.2.2 ...The exact same thing... The comment was this was awkwardly worded. . . It was suggested that we change it to "A written caution statement to de-energize the transformer before operating, shall be located on or adjacent to the operating mechanism." Al’s suggestion was that we accept the comment. No vote was taken at the time but the WG agreed

Clause 7.2.6.1 Excluding the cover gaskets and insulating fluids leaks of the component gaskets activation. There was considerable discussion on pressure and pressure relief device. Carlos Gaytan discussed what was being discussed in his working group. The comment was to re-word the following sentence (excluding the cover gasket and insulating liquid leaks of component gaskets). It was suggested that we change it to (excluding the cover gasket and insulating liquid leaks of component gaskets). Al asked if there were any objections with going with the statement and accepting the comment. No vote was taken at the time but the WG agreed

Annex C

4 of 14

Clause 7.3.4. It was stated that “The location of the instruction nameplate is already given in detail per Clause 7.3.4.1.” It was suggested that the sentence be removed . . . Al stated that he agreed with the comment . . . No vote was taken at the time but the WG agreed. . .

Clause 7.3.4.1 ...The comment suggested we change “Instruction nameplates shall contain the information specified in IEEE Std C57.12.00 (see item 11 in Figure 7 through Figure 14) except that the BIL rating shall be shown for all single-phase ratings above 16 340 V. The instruction nameplate shall be in accordance with nameplate A as described in IEEE Std C57.12.00.” Al reviewed with the WG his cleaned up sentence rather than have two separate sentences, Al suggested, “The instruction nameplate type and information provided shall be in accordance with Nameplate A as described in IEEE Std C57.12.00 except that the BIL rating shall be shown for all single-phase ratings above 16 340 V”. No vote was taken at the time but the WG agreed. Al suggest that we go with this now and consider changes to future revisions.

It was agreed that we would pick up where we left off for the next meeting and vote on the recommendations all at one time.

The next meeting will be April 2017 in New Orleans.

The meeting was adjourned at 12:21pm, Ed Smith recording.

C.2.3 C57.12.28, .29, .30, .31 & C57.12.32 – Enclosure Integrity – Dan Mulkey

Dan Mulkey presented the following minutes from the working group meeting on October 25, 2016 at 8:00 a.m. in with 57 in attendance. 1. Dan Mulkey called the meeting to order at 8:02 AM.

2. Introductions were performed

3. Quorum was verified. The working group consisted of 42 members, requiring 22 for Quorum. 25 members were confirmed at the time of counting. 35 members were confirmed afterwards through the roster.

4. A call for was made for essential patent statement and responses. None were raised.

5. A motion was made by Ron Stahara and seconded by Justin Pezzin to approve the minutes from the previous meeting in Atlanta. The motion passed unanimously.

6. A motion was made by Ron Stahara and seconded by Alan Wilks to approve the agenda for the meeting. The motion passed unanimously.

7. Status of Standards:

a. C57.12.28 Standard for Pad-Mounted Equipment – Enclosure Integrity, Published July15, 2014, Revision Due: 12/31/2024

b. C57.12.29 Standard for Pad-Mounted Equipment – Enclosure Integrity for Coastal Environments, Published August 8, 2014, Revision Due date 12/31/2024

c. C57.12.31 Standard for Pole Mounted Equipment – Enclosure Integrity, Published September 20, 2010, Revision Due: 6/17/2020, Corrigenda approved May16, 2014

d. C57.12.32 Standard for Submersible Equipment – Enclosure Integrity, Reaffirmed 3/7/2008, Revision Due: 12/31/2018, PAR expiration: 12/31/2019

8. Revision of C47.12.32 – Continuation of reports from Atlanta Meeting:

a. Darren Brown – comparison of FS-40 bulb versus UVB-313EL

Annex C

5 of 14

Summary of discussion & conclusions:

Darren presented a Howard Industries test report comparing FS-40 bulbs with UVB-313EL bulbs. The test was performed using a UV accelerated weathering chamber and brand new bulbs.

The findings were that grey panels were more impacted with the UVB bulb than green panels. The green and grey panels acted differently between the two bulbs indicating that there is a difference between the two bulbs using this basic test. All test panels passed the test.

Dan Mulkey commented that we need a quick test which will pass good units and fail bad ones and is also reflective of real-world environments.

It was noted that a letter was received from one supplier of the FS-40 bulbs indicating that they were not being discontinued as indicated by a ballot comment.

It was also noted that if a change in lamps is made, new baselines will need to be established.

The question was asked if any testing had happened using samples with black paint. Darren mentioned it likely has been in the past but we don’t have the results documented.

b. Tom Holifield – citation of paper on 409 stainless steel

Summary of discussion & conclusions:

Tom presented a historical paper which investigated suitable tank materials. The investigators looked at 3 types of stainless steel: SS304, SS316 and SS409. The paper concluded that SS409 was the best material to use. It discussed that SS316 performed better with respect to pitting corrosion from sea water, but was more susceptible to stress corrosion.

9. New Business

a. Maria Lamorey – PPG comparative QUV testing on FS40 bulbs

Summary of discussion & conclusions:

Scott Abbott of PPG presented a comparison study between the QUV-A and QUV-B lamps.

The study indicated that in tests using QUV-B testing, powder systems did not perform as well as liquid systems, but this does not necessarily correlate to real world test data based on tests performed in Florida. He explained that the QUV-A bulb mimics sunlight better than the QUV bulb.

The study made the following conclusions:

• QUV-B testing is too variable and depends very much on irradiance (power output) level of the bulbs

• Current QUV test is not irradiance controlled • QUV-B testing may eliminate a system which is cost effective and suitable for

IEEE end use • QUV-A mimics real world (Florida) better than QUV-B and is more reliable if

specification (gloss retention and test time) is set correctly • QUV-A can still “weed out” poor performing systems in a short time period • QUV-A bulbs would still use the current QUV cabinets used today

Annex C

6 of 14

• Recommend the use of “irradiance control” on new QUV hardware moving forward

• Irradiance control cabinets are easier to run and can provide significant savings on bulb costs

• Payback from cost saving can often be within one year

Scott recommended the following settings for tests: • 0.9 irradiance, • 1000 – 1500 hours minimum, • 80-90% glossary retention

After this presentation, a prolonged discussion took place:

The point was raised that the time required for QUV-A testing may be longer than current testing duration, which is a concern for manufacturers. Alan Wilks mentioned that QUV testing is not labor intensive since it can be left alone after the test is setup, so it can be used for “screening tests” of materials prior to running other types of tests.

Brian Klaponski mentioned that the ozone layer changes over time and asked how that would influence the “Florida test” in the report. Scott replied that there is a lot of Florida data over the years and we may need to investigate if there has been a change in performance over the years.

The question was asked if the presented test data was sufficient to develop the standard, or if further testing was required. Ron Stahara suggested that if we feel that further testing would be of value, we ought to pursue it, even if we don’t use it for this version of the document.

Further testing using black paints may also be helpful, since this color is also used for underground transformers. Brian Klaponski proposed that there is not currently an issue with black paint, so it is not worth spending further time testing it. It was asked if PPG could repeat the test using black. They indicated it would be best if samples were provided by manufacturers. Alan Traut mentioned that Power Partners could provide all three colors.

It was suggested that manufacturers should send samples to the lab for further testing, instead of paint manufacturers providing test samples to ensure the testing was done on the actual substrates.

It was also mentioned that a defined irradiance needs to be set for further testing moving forward.

There was a discussion about whether the impact of the coating effects performance or aesthetics. It was suggested that durability, not aesthetics, must be the purpose of this standard.

It was suggested that underground transformers may not need as long of a coating lifetime because they are installed below surface. However, they may wait in the yard for a long time prior to installation. In some cases they are also installed above ground.

There was further discussion about the impact of percent gloss. Brian Klaponski asked if a higher percent gloss yielded higher durability. Scott Abbott responded that generally, a higher initial gloss tends to give higher durability or better gloss retention than a similar product at lower gloss. Tom Holifield mentioned that they have coatings with low gloss that are better than coatings that do have gloss. Scott clarified that

Annex C

7 of 14

different families will behave differently, so one type of coating with a high percent gloss may not perform as well as a different type of coating with a lower percent gloss. If comparing similar types of coatings, generally a higher percent gloss results in higher durability.

It was noted that percent gloss impacts aesthetics, durability and thermal characteristics. It was asked if emissivity is a function of percent gloss. Al Traut mentioned that radiation heat transfer doesn’t play a large impact in a vault. It was also noted that both percent gloss and irradiance should be specified in the standard.

On a pad-mount transformer, a higher gloss shows irregularities more, so lower gloss may be preferred by some manufacturers. Some manufacturers prefer high gloss.

It was noted that in C57.12.40, the specification simply states a “dark color”, and suggested that this be more thoroughly defined in C57.12.32.

There was a discussion about how change in percent gloss should be described. Dan Mulkey suggested that since gloss is measured in percentage, the change in percent gloss should be a subtractive difference, not a divisive difference. For example, a change of 0.02 to 0.01% is a 0.01% change, not a 50% change.

Carlos Gaytan clarified the difference between percentage points and percentage:

• Percentage point loss: the subtracted difference between initial and final percentage

• Percentage loss: the divided percent between initial and final percentage

In the paint industry, percent change in gloss is usually based on percent gloss retention of the initial gloss (divisive, not subtractive). For example, the gloss must remain above 90% of the initial gloss.

Brian Klaponski stated that if a higher gloss provides better durability, we should specify a higher gloss.

It was noted that the response to the ballot comment stating “Working to see if we have an equivalent – potentially QUVA-303 with lower irradiance level” should state QUVA-340 instead of QUVA-303.

A motion was made by Mike Thibault and seconded by Alan Wilks to change the language in paragraph 4.5.6 from “Expose two test panels” to “Expose three test panels”. The motion passed unanimously.

A motion was made by Ron Stahara and seconded by Mike Thibault to change from two to three test panels for all long-term tests. The motion passed unanimously.

A task force was formed to develop proposed final wording for paragraph 4.5.6 Ultraviolet accelerated weathering test (QUV). The following attendees joined the task force:

• Scott Abbot, PPG Industries • Darren Brown, Howard Industries • Martin Rave, ComEd • Maria Lamorey, PPG Industries • Rebecca Giang, Sherwin-Williams Co. • Mike Thibault, PG&E

The following members agreed to provide coating samples for further testing.

Annex C

8 of 14

• Alan Traut, Power Partners • Dwight Parkinson, EATON Corporation • Darren Brown, Howard Industries • Josh Verdell, ERMCO

10. Next meeting—April 4, 2017 in New Orleans, Louisiana, USA

Copies of any handouts and/or subgroup reports will be made available as separate items but referenced by these minutes.

The following attendees were added to membership:

• Maria Lamorey, PPG Industries • Scott Abbott, PPG Industries

The meeting adjourned at 9:15am, Jeremy Van Horn recording.

C57.12.34 – Three Phase Pad-Mount Transformers – Ron Stahara

Ron Stahara presented the following minutes from the working group meeting on October 24, 2016 at 3:15 p.m. with 71 in attendance.

Ron Stahara called the meeting to order and introductions were made. The rosters were circulated. The names of those in attendance are recorded in the AM system. To establish a quorum, a members list was displayed on the screen and those who saw their names were asked to hold up their hand. From this count of hands, it was determined that a quorum was established. A motion was made by Gael Kennedy and seconded by Jerry Murphy to accept the agenda as shown. The motion pasted unanimously. The Patent Slide statement calling for Essential Patent Claims was read and none were brought up at this point. A motion was made by Gael Kennedy to accept the minutes of the Spring 2016 meeting as written. This was seconded by Cory Morgan. The motion pasted unanimously.

Ron Stahara stated that the PAR had been approved.

Ron went on to state that we had two items that we need to pursue on the new standard. The first is to review the exiting standard for any updates from other standards that have recently been published. These would include IEEE C57.12.00, IEEE 386, and others that are pending such IEEE C57.12.39. Ron suggested to the Working Group that a taskforce be created to do this. The Working Group agreed and Dan Mulkey was appointed as chair and the following individuals were added as members; Steve Snyder, Carlos Gaytan, Brett Chrysler, and Justin Pezzin. This Task Force would work on this during the next few months and report their progress at the spring 2017 meeting. The second item would be to review the figures for clarity and correctness. Again a Task Force was suggested to do this work. The Working Group agreed and Gary King was appointed chair and the following individuals were added as members; Dwight Parkinson, Scott Dahlke, and Alex Macias. This Task Force would work on this during the next few months and report their progress at the spring 2017 meeting.

The Working Group had discussed how to present various items that users purchase on these units. These could be classified as accessory items that are provided on or in the transformer and should not be considered a part of the standard. This document would be provided as informational for an unsophisticated user. This suggestion resulted in a rather lively discussion. Some of the comments were concerns about liability or attempting to provide a transformers 101 document. Other comments were that this was a good idea to help these unsophisticated users to understand the need for items like sight glasses, gauges, under-oil fuses, and their

Annex C

9 of 14

applications, etc. This resulted in a motion by Brian Klaponski and seconded by Alex Macias to make an “Attempt to make an informative annex for application of accessories as they relate to this standard”. This motion pasted unanimously. Steve Shull volunteered to gather these items into some type of outline to be presented at the next meeting. After this, Brian Klaponski, stated that he was not sure but with this addition we may have an Essential Patent Claim. He believed that the “third door” was a patent that was held by ComEd created by Martin Rave and Tom Callsen in 2004. Tom Callsen confirmed that this was true. Steve said he would send the LOA informational letter and form to Martin Rave since he was remaining person of the two working for ComEd.

The last comment of the day was made from Aniruddha Narawane concerning a couple of items that seem to be in error in the current document and should be reviewed for correctness in the next version. He stated that he would send this detail to Steve Shull so that he could include it correctly in the minutes. It is as follows:

The yellow highlighted items enumerate the concerns.

With this, the meeting was adjourned, Stephen Shull recording.

C.2.4 C57.12.36 – Distribution Substation Transformers – Jerry Murphy

Jerry reported the working group met Tuesday, October 25, 2016 at 1:45pm with 48 people in attendance.

Jerry Murphy called the meeting to order at 1:50 PM. Introductions were made. The names of the members were projected on the screen. By a show of hands the quorum was reached by having 12 out of the 21 members present. The approval of the agenda was moved by Terry Martin, seconded by Steve Schroeder. The motion was approved. Steve Shull made a motion to approve the minutes of the Spring 2016 meeting in Atlanta; Gael Kennedy seconded, and the motion was approved.

After Jerry asking the question, there were no patent claims brought up to the working group.

Annex C

10 of 14

Jerry reviewed the comments from the latest ballot recirculation. The first was a general comment from Peter Balma, indicating that a number of changes approved by the WG were not reflected in the latest draft. Jerry proposed to accept this comment, and receive from Peter a list with the approved changes, in order to add them to the document. Three comments related to corrections to figures and metric conversions were accepted. Next a comment about figures in Annex A showing dimensions in inches was discussed. Gary Hoffman stated that since this was an informative annex, the use of dimensions in U.S. Customary units was allowed. The disposition of the comment was to accept it and include a note indicating that the dimensions were in inches.

Next the comment about the reference to PC57.12.39 was reviewed. It was agreed to keep the reference to Draft 4 of this project standard, since it had been balloted. The last comments related with editorial corrections were reviewed and accepted.

Gary Hoffman made a motion, seconded by Steve Shull, to permit the chair to incorporate the changes that should have been included in the document, and initiate a ballot recirculation process. The motion was approved unanimously.

The next WG meeting will be in April 2-6 in New Orleans, LA.

The meeting adjourned at 2:50 pm., Carlos Gaytan recording.

C.2.5 C57.12.38 – Single-Phase Pad-Mounted Transformers – Ali Ghafourian

Mike Faulkenberry presented the following minutes from the working group meeting on October 25, 2016 at 1:45 p.m. with 59 in attendance. The meeting was called to order at 1:45 p.m. by Ali Ghafourian.

A quorum was established with 22 of 27 working group members present.

The agenda for the meeting was presented and unanimously approved.

The minutes of the spring 2016 meeting in Atlanta have been posted on the web site since shortly after that meeting for the working group members to review. There were no suggested changes to the minutes and a motion was made by Justin Pezzin and seconded by Marty Rave that the meeting minutes be approved. The approval of the minutes was unanimous.

A call for essential patents was made as required using the statement provided in the general session. No essential patents were brought forward.

The status of the document was discussed. The ballot on Corrigenda 1 correcting an error in Figure 1 of the published standard has closed. 89% of the ballots were returned. 100% approved. The document is currently at RevCom. A PAR cannot be submitted until the corrigenda is published, and Ali announced his intentions are to file for a PAR when he is permitted to do so.

A discussion was begun of proposed changes to be considered for inclusion in the next revision of the document.

• Ali proposed that two new tables be added to the document. One for dual voltage ratings would be added as Table 4 and a potential table was presented for review. A question was raised as to why 34.5 kV dual voltage units were not included. Ali answered that the attempt was to match a similar table in C57.12.20, and it does not include 34.5 kV as that is not a common application.

Annex C

11 of 14

• Another table for minimum percent impedances was proposed and would be added as Table 5. There were no objections to adding the table, but the consensus was that the table needed to match the table in C57.12.20. The proposed table, as presented for review, did not match C57.12.20 but will be changed to do so.

• Mike Faulkenberry stated that he had received an email from a user asking why there was no table with voltage ratings for live front transformers while there was a table (Table 3) for dead front transformers. The first two columns of Table 3 are actually voltage ratings for both live front and dead front transformers. The remaining columns of the table are ratings for dead front bushings. The working group was asked if we needed to consider separating out the transformer ratings into one table and the dead front bushing ratings into a separate table, similar to Table 2 for live front bushings. After some discussion, the decision was to leave the table as currently published.

• A question was raised as to why the Phase-to-Ground clearances in Table 2 were smaller than the Phase-to-nonhygroscopic insulating barrier clearances. It was noted that this was actually only true for the first three lines of the table. After comparing this table to the similar table in C57.12.34, it was determined that the first three lines should not have contained values. They should have been grayed out as in C57.12.34 to indicate that values are not applicable for these system voltages. This will be corrected in the next revision.

• Ali asked the working group to consider if we wanted to include in the next revision any of the transformer components. The current scope states that components are not covered. These could be included as an informative annex to the standard. A task group was selected to formulate a list of components for possible consideration and provide the reason why they should be addressed. The members of that task group are Giuseppe Termini, Wes Suddarth, and Craig DeRouen.

• A question was raised as to the potential for inclusion of phase-to-phase voltage ratings. Ali responded that the use of those voltage ratings is not common and is why they are not included in the standard.

Mike Faulkenberry, Vice-Chair, announced that he will be retiring in April of 2017 and will most likely not be attending future meetings. Therefore, the working group will need a new Vice-Chair, preferably a utility member, to take his place. The working group members were asked to consider volunteering for the position.

The meeting adjourned at 1:45 pm.

Submitted by Mike Faulkenberry.

Steve appointed Martin Rave as the new vice chair for the working group.

The Distribution Subcommittee recognized and applauded Mike Faulkenberry for his many years of dedicated service and wished him all the best as he retires.

C.2.6 C57.12.39 – Tank Pressure Coordination – Carlos Gaytan

Carlos reported the working group met Tuesday afternoon at 4:45 p.m. with 44 in attendance. The meeting was called to order at 4:45 PM. Quorum was reached by having 22 of 30 members present. The approval of the agenda was moved by Al Traut, seconded by Ron Stahara, and the motion was approved unanimously. The approval of the minutes from the Spring 2016 meeting was moved by Dan Mulkey, seconded by Jerry Murphy, and the motion was approved

Annex C

12 of 14

unanimously. No patents were declared. On chair remarks, Carlos informed that a PAR extension was requested, and it was expected to be approved at the Dec. 7 IEEE-SA Standards Board meeting. The question about essential patent claims was posed. The results of the ballot of Draft 4 were presented. They were successful, with a 95% approval rate, and a total of 32 comments.

The group then reviewed the comments and proposed resolutions. First question was a disapproval vote from Gary Hoffman. The concern was related with the clarity of the purpose of the document related to distribution transformers. After some discussion related with the risks associated with modifying scope and purpose on approved PARs that may invalidate the ballot, Gary agreed with the proposed disposition. Dan Mulkey suggested that any editorial changes we thought were required, should be made before submitting a new draft for ballot.

Next the group discussed a negative vote related with Sect. 3 definitions, proposing to simplify the text. After some discussion, Dan Mulkey moved to remove the Nominal Pressure definition from the document. Steve Shull seconded. Robert Stinson offered a friendly amendment to add to move the text from the current text of the definition into sect. 4.2. The amendment was accepted, and the motion was approved unanimously. The ballot disposition changed to Revised.

Next the comment to modify the definition of Rapid Transient Pressure was reviewed. It was accepted as Revised. Comment about definition of Pressure-vacuum bleeder was discussed. It was agreed to modify the text as per the comment, and changing to “air / gas” in last sentence.

Next comment was related with section 4.3.1, applicability of fault current capability test to overhead and submersible transformers with round tank construction. A comment was made that trying to incorporate test criteria for rectangular tanks should be left for a future revision. Group believed that the current language was acceptable.

Next the comment related with the use of words distortion vs. deformation. There was agreement that deformation was a more accurate term to use. Dan Mulkey made a motion to change distortion to deformation, only if we were able to change the purpose of the PAR and the document without invalidated the ballot. Ron Stahara seconded. The motion was approved unanimously. Steve Shull later identified that the purpose could be changed.

Next comment discussed was on PRV location in section 4.2.2.3. It was concluded that reference to tank wall was not needed in the first part of the statement. The text was changed to Draft 5.

Near the end of the meeting, a suggestion was made to create a ballot resolution task force in light of the need to move forward quickly to complete before the end of the 1 year PAR extension. Carlos will form the task force in order to complete the review and resolution of the comments prior to the next meeting.

The next WG meeting will be in April 2-6, 2017, in New Orleans, LA

The meeting adjourned at 5:55 pm, Justin Pezzin recording.

Carlos concluded his report saying he would be requesting a one year PAR extension.

C.2.7 Task Force on Transformer Efficiency and Loss Evaluation – Phil Hopkinson

The Phil Hopkinson welcomed the members to the meeting and noted that the high attendance (129) indicted the level of interest in the topic.

Annex C

13 of 14

This was the first meeting of the task group so there were no minutes to approve. The agenda was approved as submitted. Since this was the first meeting a quorum verification was not needed.

Presentations for the meeting from Mr. Hopkinson and Mr. Mulkey have been uploaded to the IEEE Transformer Committee Website under Distribution Transformers Subcommittee.

Background

The DOE Energy Efficiency rules will be due for renewal or revision by January 1, 2022. The current loading is estimated at 50% of nameplate rating load for medium voltage transformers and 39% for low voltage transformers. There is a need for real data to replace these estimates. The quality and availability of data have benefited from the expanding use of smart meters. Utilities may be capable of providing data on transformer loading broken down into load types, geographic locations and other useful categories.

PG&E Data

Dan Mulkey provided the perspective from PG&E who have extensive loading data that has been made public on their website. He presented data for the 2006 which was noted for a heat storm that caused a great number of transformer failures. His report has been uploaded and made available to members.

Mr. Mulkey reported that the loading RMS was very close to the 50% used by DOE.

Transformer capability was based on limits of the following:

a) Thermal – Hot Spot ≤ 190°C – Top Oil ≤ 110°C

b) Life loss – Total Aging ≤ 13140 hours

• 5% of expected life / 1.5 years of aging in one year c) Voltage regulation

– Voltage drop < 6.5 volts for transformer secondary – Flicker drop < 8.0 volts for transformer, secondary and service

He noted that typically distribution transformers are run to failure or run until a problem is encountered. He explained that the cost of a transformer is outweighed by the installation costs so replacement is preferred to relocation. PG&E’s experience showed that most transformers have an average life of 40 years with 2.5% of total installed being returned each year. Distribution transformers are pulled from stock so there cannot be any optimization when picking the transformer for the application. This is in contrast to power transformers which are purchased for a specific location even though these can be redirected to other locations as urgent needs arise.

The chair asked members representing utilities if they thought the disclosure of data similar to that from PG&E could raise conflict of interest concerns for them. Only one individual said that it might be a concern. After some discussion, it was decided that a template should be developed to provide a method in which this information could be provided. The work group chair will create a task force to develop this by the spring 2017 meeting, which will be held in New Orleans.

The meeting was adjourned, Gerard Winstanley recording.

Annex C

14 of 14

C.3 Old Business

• None

C.4 New Business

• Impulse Test Concepts – Phil Hopkinson

Phil gave a presentation (posted to website) on how it is time our factory impulse tests were upgraded. Phil gave examples of how factory tests are not achieving as much winding stress as field conditions with the troubling fact of failed windings from the field returned to the factory and passed the standard impulse test. BIL tests for dry type transformers are reduced compared to liquid filled with no basis today.

Phil concluded that impulse testing should add stress with higher BIL levels, faster front waves, higher chopped waves, longer switching waves and specific open terminals in addition to shorted terminals of non-tested windings.

• Hemchandra Shertukde commented to the subcommittee that solar transformers needed to be addressed for tank pressure issues.

• Brian Klaponski asked for clarification around patent claims requests in working group meetings. Gary Hoffman clarified that if a claim is made then a letter of assurance (LOA) must be requested and this should be recorded in the minutes. There is no need for discussion in the meetings as it is a matter for PatCom. There is a listing of all filed LOAs on the PatCom web page.

C.5 Chairman’s Closing Remarks and Announcements

Steve had no closing comments to the SC except to see them in New Orleans in spring of 2017.

C.6 Adjournment

Steve adjourned the meeting as provided in the meeting agenda at 10:47am.

Page 1 of 14

Annex D Dry Type Transformers Subcommittee

October 26, 2016 Vancouver, British Columbia Canada

Chair: Charles Johnson (absent) Vice-Chair: Casey Ballard Secretary: David Stankes

D.1 Introductions and Approval of Agenda and Minutes The Subcommittee met on October 26, 2016 at 1:30 PM in the Jr. Ballroom A,B Room of the Sheraton Vancouver Wall Centre Hotel. There were 13 of 24 members present (therefore we had a quorum of 50+%), and 19 guests present, 3 guests requested membership. The attendance roster will be kept in the AMS. The agenda was approved unanimously after a motion from David Walker and a second from Rick Marek. The minutes of the Atlanta, Georgia meeting were approved unanimously after a motion from David Walker and a second from Dhiru Patel.

D.2 Chairs Remarks The Vice-Chair described new deadlines for days allowed before submitting meeting minutes: Working Group: 15 days Subcommittee: 30 days Main Committee: 60 days Vice-Chair reviewed the new “essential patent claim” disclosure statement/requirements, and reminded WG and TF Chairs to review this at the beginning of every meeting. Vice-Chair announced that Malia Zaman is the new IEEE Standards Technical Community Program Manager. Malia has replaced Erin Spiewak who has assumed a new position within IEEE. There will be a one year transition period as Malia assumes her new role. Malia’s contact information is posed on the Transformer Committee Standards Development webpage.

D.3 Working Group/Task Force Reports The next order of business was the presentation of the reports of the various working groups and task forces. See the following sections for the individual reports:

D.3.1 IEEE PC57.12.01 - Dry Type General Requirements Chair Casey Ballard

The working group met in the Port McNeill Room of the Sheraton Vancouver Wall Centre Hotel The meeting was called to order at 1:45 PM by Chairman Casey Ballard The meeting was convened with 34 participants, 15 of them requested membership. Quorum was reached as this was the first meeting of WG. The attendance was reported in the AMS. Introductions were made by all participants. The agenda was approved unanimously being no negative votes.

Annex D

Page 2 of 14

The Task Force minutes of the Atlanta, GA, March, 21, 2016 meeting was approved unanimously being no negative votes. The chair made a call for patents using the request recommended by IEEE TC. No patents were claimed. Old business

- The chair noted that he has distributed the Draft 1 of the document well in advance of the WG meeting and all changes that TF agreed upon in Atlanta Spring 2016 meeting were included in this Draft.

- Then WG started discussion on the open questions. a) Cooling ratings – Section 5.1

• The chair mentioned that C 57.12.01 uses the cooling indexes that are different from IEC and oil type IEEE standards. Harmonization with IEC was proposed and supported by the TF.

• The usage of IEC terminology is straight forward with the exception of the case of sealed transformers. After discussion and several proposals, D. Patel volunteered to review IEC and CSA standards and develop a proposal for the WG consideration.

b) Words “power” and “kVA” in the text of the Standard. • C57.12.00 revision uses “kilovoltamperes” when describing transformer’s capability. • The motion was made by D. Walker: “Replace word “power” with word “kilovoltampers”.

This was seconded by V. Tendulkar. In the discussion, P. Hopkinson proposed to use the full word just in the titles of the Chapters and to use the abbreviation ”kVA” otherwise. The motion was amended and WG approved the amended motion unanimously.

c) Maximum system voltage – Table 5. • Suggestion was made to add the column “Maximum System Voltage” to table 5. After

discussion about what maximum system voltage means, the differences between the system voltages in the USA and Canada, M. Gromlovits made a motion that was seconded by J. Antweiler: “Include maximum system voltage column in Table 5, but revise the values of the maximum voltages. In the discussion, R. Thompson and C. Ballard agreed that to have the clear separation of systems by maximum voltages is a positive improvement that will help in the selection of the transformer voltage class. Motion passed with 15 members-to-be voted for, 1 abstained (D. Patel) and no negative votes.

• V. Tendulkar volunteered to review IEC standards and provide the proposal for the WG consideration.

d) Fuzzy figures 3 and 4. • Updated figures are available and will be included in the next Draft.

e) SC thermal limits – Table 15. • R. Marek provided the proposal to change the temperature limits for Cu and Al

transformer conductors that are in line with IEC. • The comment was made that 200 deg. C limit for Al conductor is too low as it is on the

level of normal loading winding temperature. WG agreed with this. • D. Patel commented that IEC based their limits on the consideration of the potential

cracking of the cast resin insulation. • R. Marek and D. Patel agreed to review the physical properties of the different Cu and Al

alloys used in the winding conductors and provide the proposal for the WG consideration. f) SC thermal limits – Section 7.1.

Annex D

Page 3 of 14

• R. Marek proposed to use IEC calculation equations for the average winding temperature after SC instead of IEEE ones from section 7.1. He thinks that the results between IEEE and IEC are pretty close, but IEC version is much less cumbersome.

• D. Walker agreed with this and volunteered to provide an example comparing those 2 calculation methods.

• C. Ballard will request whether the IEC equations can be borrowed for C57.12.01. g) BIL – Table 5.

• The chair informed about a survey on proposed changes in main BIL levels: 95 kV vs. current 60 kV or 75 kV vs. 60 kV for 15 kV transformers; 75 kV vs. current 45 kV for 8.7 kV transformers. Out of 14 received replies, votes split 50/50.

• D. Patel composed the Table with comparison of the correlation of LF test voltages and BIL test voltages with nominal system voltage for different voltages. He showed that the change to 95 kV BIL for 15 kV system and to 75 kV BIL for 8.7 kV system would place the correlation coefficients for the respective voltage systems out of a normal range. That is why he voted against changes, but may agree with moving from 60 kV to 75 kV level.

• P. Hopkinson commented that traditional rational behind the selection of BIL test voltages is not sufficient anymore as we discuss how to improve a reliability of transformers (both dry-type and oil-type). Many failures can be associated with fast switching transient voltages and respective resonances; BIL test may not address this type of the stresses.

• Phil made a presentation on the failure investigation of several transformers feeding data center. The root cause was identified as a voltage resonance at switching transient voltage. The factory BIL test is done with no load and wasn’t generating the same resonance. Test decisions need more discussions.

• Protection solutions are available to prevent or mitigate fast transients and resonance: shielding, damping, circuit energization / de-energization control.

• Phil thinks that dry-type transformers may have the same test levels as oil-type transformers of the same voltage class, but Phil agrees with D. Patel and V. Tendulkar that the increase of the BIL test level alone may not solve the discussed problems.

• Phil will continue the discussion on the adequate transformer testing in other Sub-Committees.

• J. McBride informed that Dielectric Test Subcommittee will continue the discussion aimed to address the fast transients and resonances in transformers: maybe test with steep front wave, etc.

• The chair proposed separation the discussion on the test modification (which this WG will follow) from our current decision on the BIL levels in Table 5 of the standard. We would need to agree on what we want to do until the next WG meeting in Spring 2017.

New business

- No new business.

Next meeting: Spring 17, New Orleans, LA, April 2-6, 2017 With no further business, the meeting was adjourned at 3 PM by the chair. Chairman: Casey Ballard Secretary: Sasha Levin

Annex D

Page 4 of 14

D.3.2 IEEE PC57.12.60 - Dry Type Thermal Aging Chair Roger Wicks

The meeting was called to order at 9:30 AM by Chairman Roger Wicks. Introductions were made and attendance sheet was circulated. The meeting was convened with 34 people in attendance / 8 members present (No Quorum reached.). Two of the guests present requested membership. Because of lack of Quorum, the minutes from spring 2016 WG meeting could not be approved. The Chairman will circulate these unapproved minutes to the members of the WG in an effort to approve minutes electronically. The Chairman reviewed the proposed Agenda. The Agenda was slightly different than the one circulated earlier to the WG in that it added the review of “essential patent claim”. The Chairman posted the new “essential patent claim”. No one at the meeting presented any essential patent claims.

Old Business / Review of last meeting:

1. Partial discharge as a trending test Summary of problem - Partial Discharge measurements can be used as in indication of movement within a winding or separation of solid insulation elements leaving voids or air leading to highly electrical stressed areas. This can be especially important when testing solid cast coils. At last meeting the WG discussed PD as an indicator of transformer health and its use as a trending test to be included in the Annex of the document. Tim Mai had volunteered to submit a proposal toward this end. The Chair presented Tim’s’ proposal, and summary of its review by the WG is as follows.

• The Chair commented that the written proposal reads more like a requirement, as it describes Pass/Fail limits and was suggested to be in main body of document.

• Dihru Patel commented that PD measurement may be influenced by environmental factors such as temperature. Chair agreed that the standard in general may not always include the level of detail needed to conduct tests by someone not in transformer industry and who does not routinely conduct these types of tests.

• The WG agreed that that submitted document is a good start for discussion on PD, but we should plan to limits its use to data collection (trending) at this point in time.

2. Major Insulation materials and method for changes Summary of problem - 12.60 currently defines how to evaluate a new insulation system, but does not have any direction for how to modify one.

• Reviewed a proposal for an updated list of materials that would be considered as Major insulation. The biggest change to this list is the inclusion of Varnish as a Major. Previously it had been considered a Minor insulation, and changes were allowed using Chemical Compatibility Testing (CC) aka Sealed Tube Test.

• Reviewed a proposal by Solomon Chaing (flowchart) that utilized a method of chemical analysis to determine if a material can be substituted. (If materials is shown to be chemically the same using DSC, TG, IR, it may be substituted without any additional testing.)

Annex D

Page 5 of 14

• Casey Ballard noted that the exact criteria used by UL to determine chemical equivalency is not well identified. The WG agreed that this must be better defined prior to adding this proposal into the Working Draft of the document. He will work with Mark Raymond of UL to get clarity on this.

3. Ratioing up or down from a test Electrical Insulation System (EIS) that was tested at a

particular BIL level a. Casey Ballard had volunteered to review proposal as last meeting. He determined that

ratioing down may be feasible, although ratioing up would not. Details would be presented at 12.01 meeting, as this is an issue being addressed in this standard. Thought that 12.60 would refer to 12.01 when dealing with this issue.

b. Casey also agreed to develop an example which could be included in the document (for ratioing down).

1. Extension of cold shock testing A discussion regarding the possible extension of Cold Shock testing to all types of dry-type transformers was held. Currently cold shock is only required for solid-cast and resin-encapsulated transformers only.

a. At spring meeting, a motion was approved to modify Clause 4.6, striking reference “solid-cast and resin-encapsulated designs only” in the working Draft document.

b. Mark Gromlovits noted that adding this requirement would require manufacturers to have special test equipment.

2. Review of IEC 61857-41 Document has been approved as a new item work proposal, and has been assigned to Working Group 6 (Insulation system testing) of IEC TC112. During recent meetings in Frankfurt of TC112 and TC14, this document was broadly discussed, and a taskforce has been proposed for work between IEC TC112 and IEC TC14 personnel. It was also stated (by TC14), that this work should take into account IEEE C57.12.60 wherever possible.

• Broad discussion regarding dielectric strength used to evaluate new EIS with proposed IEC test proposal, and its lack of ability to take into account power frequency and partial discharge found in an actual transformer.

• Rick Marek proposed that it is difficult to use a model to simulate an actual transformer. • Dhiru thought there was some merit to the new IEC proposal, but that an additional

(single point) test on actual full size transformer may be needed. • Chairman suggested that the IEC test may be useful as a replacement to Sealed Test as

method to approve changes to a system. • A call for volunteers was made for membership in IEC taskforce to review how new

proposed 61857-14 document between TC 112 and TC 14. Casey Ballard, Rick Marek and Ashley Reagan volunteered to participate.

The meeting was concluded at this point due to no more time. It was confirmed that the WG would meet again at the spring 2017 Transformer Committee Meeting in New Orleans.

Meeting was adjourned at 10:45AM Chair: Roger Wicks Co-Chair: Dave Stankes

Annex D

Page 6 of 14

D.3.3 IEEE PC57.12.58 - Dry Type Transient Analysis Chair Roger Wicks

This WG did not meet in person in Vancouver, but the document is out for ballot and expected to be completed on time.

D.3.4 IEEE PC57.12.91 - Standard Test Code Chair Derek Foster (absent) Vice Chair David Walker presented minutes from meeting

The Working Group met in the Port McNeill meeting room There were 7 members out of 15 members and 1 guests present. A quorum was not reached. The agenda and minutes from Atlanta meeting will need to be approved by email vote. Patent Disclosure -No patents were noted. Old Business

• Looking for volunteers for section 11 – Temp test, section 12 Short Circuit tests and section 13 – audible sound level measurements. Review in New Orleans

• Section 12 – short circuit test will be discussed at the next meeting in New Orleans. • Section 13 – audible sound-level measurements Find out what they did in 12.90 • IEC 60076-10 was just published in 2015. In TC14. David Walker to review IEC and

C57.12.90. Discuss in New Orleans.

New Business

• Tim-Felix Mai’s proposed by email that we consider adding language about transformers with load tap changers (similar to C57.12.00 and C57.12.90). Casey Ballard will bring up in new business in 12.01. If C57.12.01 adds LTC language then C57.12.91 will add LTC testing language.

• Tim-Felix Mai proposed by email that the corrections for altitude in C57.12.91 Section 11.7.3 were inconsistent with both C57.96 and IEC 600076-11. In fact, the corrections are 10X smaller in C57.12.91 than in either of the other sources. Tim Proposed either correcting the formula in C57.12.91 or simply adopting the simpler language from the IEC and C57.96 sources. It was also pointed out that the reference for this issue should be in C57.12.91 which is a standard rather than C57.96 which is a guide. After discussion it was agreed by members present to adopt the language from C57.96 for corrections for altitude in the case of testing <=100m and operation >1000m and also the case of testing >1000m and operation <=1000m. Because of the lack of a quorum this with be balloted by email.

• Casey Ballard presented some issues that had been mentioned at previous meeting but where no decisions were made:

o There is no mention of environmental testing in either C57.12.01 or C57.12.91 that is equivalent to IEC C or E ratings and some customers are asking for this. In those cases they are using IEC standards since no IEEE standards exist. Casey Ballard to bring up this issue in the next C57.12.01 meeting. If C57.12.01 add these test requirements then C57.91 will need to add test definitions. In the interim we will review the IEC CD and existing standards to better understand the requirements in the IEC standards. If we

Annex D

Page 7 of 14

adopt these requirements it was felt that we should be similar to the IEC requirements. It was felt that these tests would fall into the “other” test category and could be put into an annex to C57.12.91

o There was previously a suggestion that C57.12.91 specify how to do temperature tests with a harmonic load. It is mentioned in other standards such as C57.18.10. After discussion the members present agreed that this should not be in C57.12.91 and that it was not a practical and cost effective test to do. Especially given the wide variety of harmonic spectra that might need to be simulated. This will be settled by an email vote.

With no further business, the meeting was unofficially adjourned at 5:41 pm. The Working Group will meet again at the Spring 2016 meeting in New Orleans.

Chairman: Derek Foster Vice Chairman: David Walker Secretary: Henry Blake Cooke

D.3.5 IEEE PC57.16 – Dry Type Reactors Chair Art Del Rio

The working group for the revision of C57.16 met in the Port McNeill room of the Sheraton Vancouver Hotel on Tuesday October 25,2016, at 3:15 PM. The meeting was called to order at 3:15 PM by the WG Chair Art Del Rio. There were a total of 17 participants: 6 Members and 11 Guests out of which 1 Guest requested membership. The meeting was opened with the introduction of participants and the circulation of attendance rosters

and mandatory call for potentially essential patents. 6 of the current 10 WG Members were present and quorum to carry out business was met. Meeting notes:

Meeting Agenda Meeting agenda, which was circulated by email among members and guests on October 18,

2016, was presented to the participants. Motion to approve the agenda was made by Klaus Pointner and seconded by Robert Ballard. There were no objections or comments and the agenda was approved unanimously.

Minutes from previous meeting

The minutes from the S16 meeting in Atlanta, which were circulated on October 18, 2016 by email, were presented to the participants.

There were no objections or comments and the S16 meeting minutes were approved.

Annex D

Page 8 of 14

Old Business:

1. The existing Scope and Purpose sections of the C57.16 standard were discussed. The following comments were made:

a. On the second paragraph, the Scope states that: “with some restrictions” the standard is applicable to filter reactors, and other types of series-connected air-core reactors. Clarification on the specific restrictions is required in order to address and remove such restrictions.

b. The Purpose of the standard also refers to “some restrictions” in the application of the standard to filter reactors and other types of reactors.

c. The list of devices for which the standard does not apply need to be revised to remove “Arc Suppression Coils” since they already included in the neutral grounding devices category. Also, year of the standard should be removed from the references in the Scope section.

d. The Scope refers to the annexes within the standard that should be removed. e. The inclusion or not in the Scope of converter reactors used in the AC side of multilevel

converters needs further discussion especially for MV-DC applications.

2. Open item: Charles Johnson volunteered to compile meeting minutes from old meetings related to the 2011 revision and send them to the Chair as background information and to share the existing recent history on the C57.16 standard with others. Carry over to next meeting.

3. The Chair will request from Ms Malia Zaman (Standards Program Manager) the MSWord document version of the 2011 revision in order to start the changes. The document will be distributed to the WG Members and Guests before the next meeting in New Orleans.

4. A volunteer for the role of Secretary was requested at the meeting. The position remains open and a request will be done at Subcommittee level for a volunteer.

No new businesses were presented. Meeting adjournment: Motion to adjourn the meeting by Klaus Pointner, seconded by Mike Sharp, the meeting was adjourned at 4:00 PM. Next meeting: Spring 2017, New Orleans, LA, April 2-6, 2017. Respectfully submitted, Chairman: Art Del Rio ([email protected]) Secretary: TBA

D.3.6 IEEE PC57.124 – Dry Type Partial Discharge Guide Chair Tom Prevost (absent) Rick Marek presented minutes from meeting

PC57.124, Revision of IEEE Recommended Practice for the Detection of Partial Discharge and the Measurement of Apparent Charge in Dry-Type Transformers October 25, 8:00 am

Annex D

Page 9 of 14

This was the first meeting as a WG with 40 in attendance and 13-16 requesting membership. Introductions were made and the patent call resulted in one claim by H. Shertukde for patent # 6178386. P. Hopkinson requested an addition to the agenda concerning the rationale for establishing 10 pc as the limit for cast coil transformers. A motion to approve the amended agenda was made by M. Gromlovits and seconded by R. Ballard. Having approved the addition, the Chair explained that the scope of the document was for procedure only and limits were given IEEE Std C57.12.01. Therefore the agenda addition was out of scope for this document. Agenda:

• Welcome & Chairs Remarks for First Meeting of WG

• Introduction of Attendees – request for membership

• Approval of Agenda

• Call for patents

• Review of Scope & Purpose

• Other Transformer Committee Documents re PD

– C57.113- 2010

• Scope and Purpose Statement for revised C57.124

• Submittal of PAR

• Next steps

• New Business

– Discussion of PD acceptance levels

• Adjourn

In the Chair’s remarks: • He noted that the document was last revised in 1999 and then reaffirmed in 2004, which is a long

time ago. When the PD limits were reduced recently to match more closely with IEC standards, the SC requested that the referenced procedure, C57.124 be revised to make sure the new requirements could be supported by the test procedure.

• He reviewed C57.12.01 changes in limits and the added procedure • All members will receive a copy of C57.12.01

o D. Gross noted that IEC 60270 was revised this year and the upper cutoff frequency was changed from 500kHz to 1MHz.

• The scope and purpose defined in last TF meeting was reviewed o Approved by SC and Committee o Key was wide band apparent charge

• J. Britton is HVTT chair and compared IEC to IEEE o Group met to develop PD document for general apparatus o May include diagnostic pattern recognition o Will need support from equipment manufacturers and looking for interest and support o This is a parallel group

Annex D

Page 10 of 14

• A. Naderian proposed adding on site testing as part of scope noting this is requested more especially for very large dry units and possible establishing TF

o Chair did not think field testing should be included and that it may fit better in C57.152 • J. Britton then qualified that pattern recognition would be general for all equipment and not

specific to transformers o D. Gross added these would be generic patterns

• B. Larzelere noted TC met in Frankfurt two weeks ago and it was decided that 60270 needs to have pattern recognition added to that document and that there is a lot of information from a CIGRE study group. As an example a cable showed 100pc but was actually due to connections and not the cable insulation.

• Chair said PD on bushings and instrument transformers, C57.113 has patterns in an annex and specific to the apparatus. What is needed is generic patterns.

• T. Hochanh noted that it is important to obtain the pattern at the inception voltage…. And suggested referring to the PD in bushing and instrument transformers standard.

o The Chair noted that the patterns in this document are quite generic and could be added to C57.124

• H. Shertukde stated that rather than pattern recognition it should be called data interpretation. o D. Gross agreed that the term pattern recognition should be avoided o The Chair agreed

• Chair stated 60270 and 60076-3 will be provided to the members and Erin agreed this could be done.

• B. Larzelere noted that as a member of the ANSI TAG you have access to these documents and others and the cost was only a few hundred dollars

• The Chair compared C57.124 to C57.113 o C57.124 needs major revision o C57.12.01 already provides procedure o Some parts of C57.113 could be referenced

• Chair showed the dielectric test table from C57.12.01 noting that PD was a routine test for cast coil but optional for resin encapsulated

• The Chair noted that there are eight different connections shown in C57.124 and questioned if all were needed, but he needs input from the dry-type manufacturers and request that these be carefully evaluated when reviewing the document.

• H. Shertukde commented that the Navy and Army are requesting PD during impulse test and proposed adding a circuit for this test.

o Chair does not feel scope includes type of test since it is not specifically wide band o D. Gross agreed that this document is not suitable for that test and that pc is not the

correct measurement. o Chair suggested that this could be provided as an informative annex and he requested H.

Shertukde to provide wording which he agreed to do. • The Chair noted again that this was the first meeting but the members need to determine the

content and more discussion is warranted after reviewing the document before the next meeting. • Chair said the PAR has not yet been submitted but he will submit it soon and an approved PAR is

expected by the next meeting. • There was no new business • No new business • Meeting adjourned at 9:10 AM

Annex D

Page 11 of 14

D.3.7 IEEE PC57.12.51 - Dry Type Product Standard “> 500kVA Ventilated” Chair Sanjib Som

• Meeting came to order at 11:02 AM 10/24/16. • Started attendance sheet around the room. • Chair reviewed the new patent statement - no patent issues. • Only 8 members present out of 26 hence there was no quorum. • Total participants were 24 (16 guests). • Chair mentioned that this will probably be the last meeting before balloting starts. • Last meeting minutes could not be approved due to lack of quorum. • Chair showed the previous minutes on the screen for attendees to review - no

comments. • Previous comments from Atlanta were shown on the screen - no additional comments. • Chair asked for comments on the title shown in the PAR document - no initial

comments. • Robert Ballard (Casey) asked if we were going to ask for a PAR amendment, chair said

yes. Casey also asked if there is intention to ask for extension. Chair clarified there is no intent.

• Casey requested that we review PAR requirements for the group to see - discussion followed.

• We reviewed the new title - chair clarified voltages for several guests. • Blake Cooke pointed out the word safety still remained in the scope - chair addressed

the issue. • The statement "recommended practice" was also reviewed, chair addressed same. • Casey asked about combining C57.12.50 and C57.12.51 - he said the subcommittee

approved this previously. • Chair pulled up the Atlanta minutes - he confirmed that the group agreed to combine

C57.12.50 and C57.12.51. • Chair pointed out that we were trying to get the PAR submitted and to focus on that

effort in this meeting. • The group agreed with the chair that the "heavy lifting" on the document is done - it is

nearly ready. • Casey reviewed C57.12.50 scope and purpose - discussion followed. • More discussion surrounding kVA - chair mediated discussion between Robert

Thompson(Bob), Diru Patel (Dhiru), Casey and others. • Suggestion made to remove low voltage 208Y/120 - 4160Y inclusive - discussion

followed. • Diru asked that "500kVA and smaller" along with the last sentence in the scope be

removed. • Discussion regarding consistency with C57.12.01 - Casey quoted purpose and scope for

the group, we reviewed both and insured that every type of transformer was now included.

• The group reviewed the scope one final time and agreed it was ok.

Annex D

Page 12 of 14

• In the purpose the group agreed to change to 5KV class low voltage and 1.2KV class to 36KV class.

• Chair changed scope, purpose and title to include ventilated transformers. • Casey reiterated proper steps for a PAR - PAR must also go through the WG. • Casey asked "do we need to have a PURPOSE in this document, it seems redundant". • The group voted unanimously to simply remove the PURPOSE. • A bit more discussion on submitting the PAR.

The final version of title and scope is provided below, this will circulated among members for approval.

Title Guide for mechanical interchangeability of ventilated dry type transformers Scope This standard sets forth characteristics of ventilated dry type transformers relating to

performance, limited electrical and mechanical interchangeability, as well as recommended practice for installation of the equipment described, and to assist in the proper selection of such equipment. Specific rating combinations are described up to base of 7500 kVA, high-voltage class from 1.2 kV to 36 kV inclusive, and low-voltage class up to 5 kV. This standard does not apply to other types of transformers such as specialty, sealed dry-type, pad-mounted dry-type, instrument, step and induction voltage regulators, arc-furnace, mining, testing, welding, and rectifier transformers.

The meeting adjourned at 12:15.

Respectfully submitted,

Chairman: Sanjib Som

Secretary: Mark Gromlovits

D.4 Old Business

D.4.1 Status of Dry Type Transformers Standards Chair reviewed status of standards activity including: - IEEE PC57.12.51 - The Chair expressed concern regarding timing for the

completion of PC57.12.51, as PAR expires in 2018. This document is in need of a PAR revision and ballot be sent out for comments prior to Spring 2017 meeting in order to comfortably meet 2018 deadline.

- IEEE PC57.12.58 - This document has been sent out for ballot and expected to be completed on time.

- IEEE 259 - David Stankes volunteered to review this document with Sub Committee Chair to determine path forward in support of document revision. Revision Due date of 12/31/20.

- IEEE C57.16 - Art Del Rio pointed out that this document is listed as “Inactive” in WG / Task Forces table on Dry-Type Transformers Subcommittee webpage. Vice Chair agreed to investigate updating this to “Active” status.

Annex D

Page 13 of 14

D.5 New Business

D.5.1 UL/IEC MVDT Thermal aging - Roger Wicks provided update regarding Future IEC 61857-41 New Work Proposal,

a test procedure for the thermal evaluation of an electrical insulation system, for use in dry-type, cast-coil and resin encapsulated transformers operating at voltages of l kV and above. This review was part of the C57.12.60 meeting minutes that was delayed to the end of the SC meeting due to expected length of discussion.

- Roger pointed out that although he is Chair of IEC TC 112, the technical committee this standard would fall under, he was not made aware that this new work proposal would be submitted prior to it being entered this past summer.

- Roger said that this NWP was discussed at length at recent TC 112 meeting held in Frankfurt, and that is was agreed that both TC 112 (Systems) and TC 14 (Transformers) would work together in the development of this procedure, taking into account work being conducted in IEEE C57.12.60 WG.

- Ken McKinney (UL) confirmed that UL will certify to IEEE C57 transformer standards, which now only references use of MV electrical insulation systems approved per IEEE C57.12.60. Ken said, however, that UL is interested in working with both IEEE and IEC and will continue to do so.

- Roger pointed out that current C57.12.60 may not be written a way that it can be easily followed by those who do not routinely run tests described in the standard, and that better examples and clarification may be needed.

- Roger felt that there was merit to the test procedure described in the Future IEC 61857-41 document, and it may be useful as a screening test or a method to approve new minor insulations inside of 12.60.

There was some discussion regarding the relationship between IEEE and IEC, as this was brought up during October 3, 2016 UL Round Table discussion regarding the new IEC 61857-41 test procedure. At the meeting it was described that IEEE would no longer be interested in cooperating with IEC. Casey Ballard had reviewed this with Erin Spiewak (IEEE) and presented the following summary of his discussion. - IEEE will continue to cooperate and work with IEC in the effort of standards

development. This is demonstrated by recent promotion of Erin Spiewak to new IEEE role, where part of her responsibility will to investigate how IEEE and IEC can work better together.

- Confirmed that IEC / IEEE duel logo projects will continue. - Described that IEEE has decided not to engage as member of (future) US TAG’s, but

will continue to maintain participation in current TAG’s. The decision to not participate in future US TAG’s is in support of IEEE desire to expand relevance outside of US, and participation in US TAG (only) did not support this goal.

- Rick Marek described that IEC and IEEE standards do not always align. Rick asked that the IEC 60076-11 CDV (Dry-type Transformer) be circulated to members of the IEEE Dry-type SC to help show differences between it and corresponding IEEE documents.

Annex D

Page 14 of 14

D.5.2 IEEE PC12.57.51 A motion to approve the wording in the new PAR was made by Casey Ballard (with minor editorial change relating to spacing) and seconded by Vijay Tendulkar. This motion passed unanimously. The Subcommittee subsequently approved sending the revised PAR to Revcom for approval.

D.5.3 C57.16 Secretary The Chair made a call for volunteers to be the Secretary of C57.16. Ulf Radbrant graciously volunteered.

D.6 Adjournment With no further business, the meeting was adjourned at 2:35 PM. Vice Chairman: Casey Ballard Secretary: David Stankes

Page 1 of 5

Annex E HVDC Converter Transformers and Smoothing Reactors Subcommittee

October 24, 2016, 3.15 pm Vancouver, British Columbia, Canada

Chair: Michael Sharp Vice Chair: Les Recksiedler Secretary: Ulf Radbrandt

E.1 Introduction / Attendance

Introductions were made and the attendance list circulated.

There were 14 members and 24 guests present. One guest requested membership,

The total membership of the SC is 17. We needed at least a total of 9 members to be present in order to have a quorum. This was achieved.

The agenda for this meeting was approved after a motion by Eric Davis, which was seconded by Paul Jarman. As an addition to the agenda, a presentation on Medium Voltage Direct Current (MVDC) Series Resonant Converters was added.

E.2 Approval of the minutes of the March 21, 2016 meeting in Atlanta

The minutes from the Atlanta meeting (Spring 2016) were approved after a motion by Pierre Riffon, which was seconded by Klaus Pointner.

E.3 Brief report on the meeting of the Administrative SC

Clarification was made that a task force should develop the scope and purpose for a PAR and obtain a PAR before a working group is created and working group officers are appointed.

It was confirmed that a quorum is defined as having 50% or more members in attendance. (Not 50% plus one).

The word “safety” should be avoided in standards. We should e.g. use “recommended” instead.

A WG chair must always ask the members if they are aware of any essential patent claims that could affect the work by the WG. That should then be brought to the knowledge of all WG members and to the minutes of the meeting. The following suggested wording was provided, “If any individual believes that patent claims might be essential patent claims that fact should be made known to the entire working group and duly recorded in the minutes of the working group meeting” This is only required for working groups and not task forces, ad hocs etc.

Steve Antoz will be heading a task force to clarify the qualification requirements, benefits and duration of Emeritus Member classification.

There will be a 100th anniversary celebration at the spring 2018 meeting in Pittsburg. Please let Greg Anderson know if you would like to help with planning.

The minutes from the sub committees must be submitted before December 4th 2016.

Annex E

Page 2 of 5

E.4 Working Group Reports

E.4.1 WG IEC/IEEE 60076-57-129 – Ulf Radbrandt (IEEE) and Mats Berglund (IEC), Co-Chairs

Ulf Radbrandt made a presentation regarding the work with the dual logo document since the Atlanta meeting. The highlights of that presentation are as follows:

• After the Atlanta meeting, the latest draft of the dual logo document was distributed within the IEEE SC

- A voting, if we should go for ballot, took place via e-mail. The results were:

- WG SC

- Number of members 7 17

- Voted 6 (85.7%) 11 (64.7%)

- Voted yes 6 11

- Voted no 0 0

- For the WG, only IEEE members of the joint WG were considered.

- The 2/3 majority of the WG and the 1/2 majority of the SC were thereby met.

- The decision was then to go for ballot which took place between 23-Aug-2016 and 23-Sep-2016.

- In parallel with the ballot a CDV (Committee Draft Voting) took place in IEC.

• Results of IEEE ballot of IEC/IEEE 60076-57-129

- 66 eligible people in this ballot group.

- 57 received = 86% returned

- 53 votes

- 51 affirmative votes, 96%

- 2 negative votes with comments

- 0 negative votes without comments

- 4 abstention votes: (Lack of expertise: 1, Lack of time: 3)

- The 75% affirmation requirement was met.

- Comments: 45 4 technical, 31 editorial and 10 general

- Must Be Satisfied Comments: 10 1 technical, 3 editorial and 6 general

• Results of IEC CDV of IEC/IEEE 60076-57-129

Annex E

Page 3 of 5

- Members (national committees) voting: 22

- Members in favour: 22 = 100%

- Number of comments: 7 2 technical, 3 editorial and 2 general

- Paul Jarman pointed out that it is possible that editorial comments will come after the IEC general meeting in Frankfurt, October 2016.

- Decision by Standardization Management Board (SMB) SMB agreed that standards with many alternative requirements were an unsatisfactory response to the objectives of international standardization. This affects the possibility to publish the dual logo standard for HVDC transformers. It affects also the other dual logo standards. This decision will be reviewed by SMB in February 2017.

• There has not been any meeting, with the joint WG, since (prior to) the Atlanta meeting. Mats Berglund, Anders Lindroth (former IEC chair) and Ulf Radbrandt met October 19th to propose actions to the comments from the Ballot (IEEE) and CDV (IEC). The comments and the proposed actions have been circulated within the joint WG for comments.

• Summary of the proposed actions (IEC and IEEE combined):

- Totally 52 comments

- 6 technical comments

- 1 must be satisfied 1 rejected

- 5 don’t have to be satisfied 5 agreed

- 34 editorial comments

- 3 must be satisfied 3 agreed

- 31 don’t have to be satisfied 28 agreed, 1 partly agreed, 2 rejected

- 12 general comments

- 6 must be satisfied 5 agreed, 1 partly agreed

- 6 don’t have to be satisfied 1 agreed, 1 agreed/open (more info needed) 1 partly agreed, 3 rejected

• The most critical comments and the actions were shown and discussed. The discussion were as follows:

- It is too late to change the scope (regarding Line Current Commutated (LCC) technology or Voltage Source Converters (VSC) technology). This standard covers all HVDC transformers including VSC where applicable.

- A comment to put safety aspects in caution boxes was partly agreed. This was related to remaining charge after DC voltage tests. The word “safety” was proposed to be removed from the wording “Appropriate safety precautions should be taken”. The reason was that the use of "safety precautions" in the document does not refer to personnel safety or damage of equipment but rather to consequences for the test result.

Annex E

Page 4 of 5

During the discussion regarding this, it was pointed out that it still can be a safety issue for testing personnel since there can be remaining voltage at terminals and that could lead to electric shock if touched. Maybe we should add caution boxes about caution to avoid electric shock. This will go back to the joint WG for review.

- A comment to include a reference to the report detailing various gasket materials by the Canadian Electrical Association (CEA) was proposed. It was agreed to include this if we can find that report. The report is mentioned in Annex C (Design review). The SC members are encouraged to search for that report and (if found) send an e-mail with the document number and title to Mike Sharp and Ulf Radbrandt. If the report is not found then the sentence “The Canadian Electrical Association (CEA) has produced a report detailing various gasket materials as compared to each other.” will be removed.

- Comments to add captions to the table and to the figure in the Annex was rejected. That might also be requested by the IEC editorial review. In that case we can add the captions.

• Planned coming work with this document

- Decide on action regarding the Canadian Electrical Association (CEA) report (detailing various gasket materials).

- Wait for the final decision by the Standardization Management Board (SMB), if we can have the dual references (IEC or IEEE).

- Based on the SMB decision, decide if we should continue with the dual logo standard or make two separate but identical standards where the alternative references are removed. E.g. if the document states today “according to IEC 60076-1 or IEEE C57.12.90”, then “to IEC 60076-1” will be removed from the IEEE standard and vice versa.

- Recirculation ballot within IEEE.

- FDIS within IEC. This might not be necessary due to the 100% approval rate.

E.5 Old Business

E.5.1 Revision of IEEE Std 1277

The task force chair, Klaus Pointner, presented the draft PAR for revision of IEEE 1277.

• The proposed title is “Standard General Requirements and Test Code for Dry-Type and Oil-Immersed Smoothing Reactors and for Dry-Type Converter Reactors for DC Power Transmission”.

• The standard should also cover dry-type converter reactors for voltage source converters (VSC).

• A discussion followed regarding if the standard should cover converter reactors for all topologies or VSC converters.

- A conclusion was that the standard should cover converter reactors that are in series with the semiconductor valves where the reactors see both DC current (a third of the DC current at the DC side) and AC current (half of the AC current at the AC line). The stresses of those reactors are quite similar to stresses of smoothing reactors.

Annex E

Page 5 of 5

- Another conclusion was that the standard should not cover converter reactors e.g. for 2 or 3 level converters when those reactors are in series with the AC line where the reactors don’t see DC currents.

- The final conclusion of this discussion was to include in the standard only those converter reactors that carry some DC current. It was also agreed that this should be included in the scope.

• There was also a discussion if the standard should cover oil immersed converter reactors. The conclusion was not to include these as it is too early. No one was aware of their application in service.

• The present standard does not include a “Purpose” but it includes a “Need”. The “Need” should be transformed to a “Purpose” in the revised standard.

• The draft PAR will be circulated within the SC.

• The SC should agree about the title, scope and purpose of the standard and the PAR should be updated.

• We should have a definition of converter reactors for Statcoms (SVC),

• If the PAR is approved then we should try to arrange a first WG meeting in the next committee meeting (Spring 2017). That WG meeting should then precede the SC meeting. A discussion followed regarding if we could handle the revision of this standard directly in the SC (as we did for the last revision). In that case, no separate WG meetings would be needed. The decision was to perform the work in the SC after a motion by Christoph Plötner, which was seconded by Klaus Pointner.

• The present standard is in a good shape and most work will be regarding converter reactors.

• We should also follow, and perhaps harmonize the work with, the revision of IEC 60076-6 (Power transformers – Part 6: Reactors). That IEC standard covers smoothing reactors today and might cover converter reactors later.

E.6 New Business Les Recksiedler made a presentation regarding work with Medium Voltage Direct Current (MVDC) Series Resonant Converters with voltages up to 100kV. A Cigré - WG (C6.31 Medium Voltage Direct Current (MVDC) Grid Feasibility Study) is started. The converters are e.g. intended for feeding remote villages and for military applications (e.g. marine) The converters should be small, compact and modular. They should also be of Plug and Play function. The conclusion, following a discussion, was that the transformers (for this applications) probably should be covered by the converter transformer standard (IEEE 60076-57-129) in the future but that it is too early to include them now.

E.7 Adjournment

The meeting was adjourned at 4.20 pm after a motion by Eric Davis, which was seconded by Pierre Riffon.

Unrestricted Page 1 of 6

Annex F Instrument Transformers Subcommittee

Chair: Ross McTaggart

F.1 Introductions

The attendees introduced themselves and reported affiliations.

F.2 Quorum

18 of 30 members were present - quorum attained

Also 36 guests attended

F.3 Approval of minutes – Atlanta, GA meeting

Motion by David Wallace & seconded by Pierre Riffon

F.4 Review of Agenda

F.5 Status of C57.13 Standards

Ross presented the status of the various standards handled by the ITSC. Pierre Riffon is the chair of the working group revising C57.13.5 currently. A PAR is to be written and work started on the revision of C57.13.2, Thomas Sizemore is to chair this working group. The milli-ampere standard C57.13.7 led by Henry Alton is currently in the balloting process. The SSVT standard C57.13.8 development effort led by David Wallace is continuing. A task force is being led by Zoltan Roman to revise the PLC Caps and CCVT standard. It is expected this will be a working group by the New Orleans meeting.

F.6 Working Group Reports

F.6.1 Working Group on Current Transformers with mA range (WG C57.13.7) -

Chair: Henry Alton, Vice-Chair: Adnan Rashid

This WG did not meet in Vancouver. The Standard is in the balloting process

F.6.2 WG on Station Service Voltage Transformers - D Wallace

The meeting of the C57.13.8 Working Group met at 8:00 AM as convened by Chair David Wallace. Roster sheets were circulated for attendees to sign in. A total of 33 people were in attendance with 18 members and 15 guests. 18 out of 26 members were present, therefore quorum was met. One guest requested membership. The agenda was presented and accepted with no discussion. The Patent Claims Statement was presented to the workgroup with no claims being identified. The minutes were presented and approved with no discussion.

Annex F

Unrestricted Page 2 of 6

In new business, Ross McTaggart made a motion to pursue a dual logo with CSA for C57.13.8. The motion was seconded by Barrett Wimberly. The motion passed with no objections. There was a discussion on the requirements to obtain the dual logo and if it was possible to obtain a triple logo with IEC. Various concerns were expressed during the discussion. Ross will give a presentation on the requirements for the dual logo at the Spring 2016 meeting in New Orleans, La. In old business, the list of comments from the request for comments on C57.13.8 D3 were discussed. 26 of the 77 comments received were either accepted or rejected. Time ran out for the meeting. It was agreed to continue the discussion at the Instrument Transformer Subcommittee meeting on 10/26 if time is permitting. If the review of the comments cannot be completed on 10/26, a conference call or web meeting will be setup to finish the review. A motion to adjourn the meeting was offered by Patrick Rock and seconded by Steve Oakes. The motion carried unanimously without discussion. The next meeting will be at the Spring 2017 Transformers Committee meeting in New Orleans, La.

F.6.3 WG PD in Bushings & PTs/CTs PC57.160 - Thang Hochanh

Attendees: 57 Members attending: 20/34 Rosters: Circulated for members and guests. Agenda: An agenda was presented for the meeting. Essential Patent Claims: Text was displayed and the Chair inquired as to if anyone knew of essential patent claims. None were brought up during the meeting. Minutes: Motion approved David Wallace (1st) & Pierre Riffon (2nd) Items discussed based upon comments received: A total of 17 comments were received for discussion many were editorial or minor in nature. Details of the discussion points are below. Comments accepted and which will be in the next draft:

• Introduction – An introduction will be added to the draft.

• IEEE C57.13 was not in the list of references.

• 6.3.1 Figure 3 text is to be updated for consistency of wording which references test taps.

• 6.3.2.1 Pierre Riffon proposed text for the bushing section to match the instrument transformer section regarding measured PD limits after the calibration step.

• 6.4 It was proposed to move the list of abbreviations from 6.4 up in the document to 3.2 as they are used throughout the document.

• 6.4 Shibao Zhang proposed an editorial change from ‘is’ to ‘are’ to correct grammar.

• 6.4 Shibao Zhang proposed an editorial change in paragraph 1 to change the indication of bushing tap for consistency.

Annex F

Unrestricted Page 3 of 6

• 6.5.1 Shibao Zhang proposed to add the following text to the end of the section. "Calibration circuits in Figures 10 and 11 may be slightly adjusted to reflect the testing circuits in Figures 5, 6, and 9. However, the calibration injection points should always be the outlet of the capacitance C1 of the test object, points A and B. “

• 6.6.1 Pierre Riffon indicated that a precision need to be mentioned to reflect the point that the verification of a valid calibration is performed at a level not necessarily at 50% of the partial discharge limit for DC bushings.

• Thomas Sizemore indicated that several figures need to be updated to improve consistency of line weights, etc.

• Pierre Riffon: Correction to figure 17 labeled as a balanced circuit (unbalanced circuit).

• Figure 10: For the clarity of the figure, the chair proposes a dotted line box around the capacitor and the square wave signal generator.

• 7.2.1 Vladimir Khalin indicated that no explicit instructions were provided for the testing of line to line VTs.

• The annex 'PD Measuring Circuits' covers many of the same topics as the guide. It was decided to remove it due to duplication of definitions and explanations.

• Thomas Sizemore propose an introduction to be added to the annex related to PD patterns.

The follow comments were discussed but not accepted.

• 6.5.1 Jitendra Mamtora indicated a potential error in the calibrator circuits used in the guide.

• An additional pattern taken from an online monitoring system was discussed. The PD pattern cannot be positively identified being in the bushing installed on a transformer.

Additional items discussed: The wording of the PAR was discussed. It currently does not cover DC bushings which are in the draft document. The working group agreed to pursue a change in the PAR to incorporate DC bushings in the guide. Tom Provost indicated that he is willing to assist the Chair in this process. Motion to adjourn: A motion was presented by David Wallace and was seconded by Detlev Gross. Spring meeting 2017: The chair plans to wrap-up the draft for the New Orleans meeting and submit the Draft for approval by the WG.

F.6.4 Working Group on Revision of C57.13.5 "Standard of Performance and

Test Requirements for Instrument Transformers of a Nominal System Voltage

of 115 kV and Above.

The WG met on October 25, 2016, from 9:30 am to 10:45 pm. Thirteen (13) members and forty-three (43) guests attended the meeting. Eight (8) guests requested membership. The meeting was chaired by Pierre Riffon, chair of the WG. Mr. David Wallace was the vice-chair.

Annex F

Unrestricted Page 4 of 6

This was the second WG meeting.

Attendance has been recorded in the AM system.

Required quorum was met, presence of at least 7 members was required.

Revision 2 of agenda has been reviewed and a motion to approve the agenda has been made by Mr. T. Sizemore and seconded by Mr. S. Oakes. The revision 2 of the agenda was approved by all members present.

Minutes of Atlanta meeting were approved unanimously. The motion was made by Igor Ziger and seconded by Thomas Sizemore.

Call for patents has been made and no essential patent claims have been reported.

As the first item of business, the Chair proposed a new relaying accuracy designation when an anti-remanence gap is added within magnetic circuits. The proposal was to add a "R" suffix after the C class designation as it is done in IEC 61869-2. After discussion, a motion made by Zoltan Roman and seconded by Igor Ziger to survey if this rating is really needed. The motion was accepted by 12 members, one abstained. The chair will initiate a survey in this respect within the Instrument Transformers Subcommittee membership prior to the next meeting. The Chair will also ask if this class is better to be added, for the time being, to C57.13 (amendment) or to C57.13.5.

Draft 1.2 of the revision of C57.13.5 was circulated by Email to the members and guests prior to the meeting on September 11, 2016.

Changes proposed in D1.2 have been reviewed one by one up from clauses 10.9.2 to A.2, Several changes were mainly editorial in nature such as reference clause numbers and date of referenced standards.

Among the proposed major technical changes, the following items have been discussed:

• Only external visual inspection will be required after short-time current test;

• The choice of fuse wire dimension and material for arc initiation during internal arc test will be let to manufacturer. The only criteria is that the fuse wire shall melt within 30 electrical degrees after current initiation;

• Alternative gases will be allowed and suggested for the internal arc test. The Chair will make a proposal prior to the next meeting;

• Additional details have been added regarding the documentation to be supplied to the test laboratory for test sample identification;

• The temperature rise test procedure for CTs having dielectric losses greater than 20% of the RI2 losses has been discussed but we were running of time. Zoltan Roman will make a proposal for the next meeting in New Orleans, LA.

Clauses A.2 and beyond will be reviewed during the next meeting in New Orleans.

The meeting adjourned at 10:45 am on October 25, 2016. The adjournment motion was made by Mr. T. Sizemore and was seconded by Mr. R. Ogajanov. The motion was approved unanimously.

Annex F

Unrestricted Page 5 of 6

The next meeting is planned to be held in New Orleans, LA on April 4, 2017.

F.6.5 C57.13.9 Task Force for PLC Capacitors and CCVT’s – Zoltan Roman

The Task Force held its second meeting at 11:00 AM.

A total of 31 people were in attendance, down from 41 at the previous meeting. 14 of the 21 members were present. 1 additional person requested membership.

After introductions the minutes of the previous meeting and the agenda for this meeting were presented and approved.

The draft PAR has been reviewed. It will be submitted as-is with the exception of the date of the draft submittal for the ballot. It has been reiterated that one of the objectives is to harmonize the new standard with the existing C57.13, C57.13.5 IEEE standards, as well with the current IEC and CSA CCVT standards.

The existing CCVT standard, ANSI C93.1, has been reviewed and the chair pointed out the need for restructuring. Rather than modifying this document the preference is to start from scratch using the IEEE template. There were no objections to this approach.

The chair presented a table with the proposed structure and a schedule for development of the new standard. The plan is to complete the standard in 7 meetings and some teleconferences in between. There were no objections.

The TF reviewed and compared the voltage ratings and dielectric test requirements between C93.1, C57.13, C57.13.5, CSA and IEC. It was noted that the test levels in C93.1 were in some cases much higher than in the IEEE or IEC requirements and it was suggested that they should be the same as for other instrument transformers. This was questioned by S. Misur, stating that there may have been a good reason for this so we should be careful. However, nobody in attendance knew the reasons for the higher levels. D. Sharma offered to provide a switchgear standard as another reference.

The chair offered to prepare a table summarizing the dielectric test requirements for the next meeting and make initial proposals for levels to include in the draft, which will be discussed and voted on in the next meeting.

The meeting was adjourned shortly before 12:15 PM.

The next meeting will be at the Spring 2017 Transformers Committee meeting in New Orleans, LA, between April 2 and 6, 2017

F.7 Special Presentation

Zoltan Roman presented the results of several CTs measured and plotted in both the current parallelogram and the proposed square for accuracy classes. Eddy So gave a presentation regarding the applicability of TCF/RCF in current applications. Some questions were raised concerning how utilities and other groups such as Measurement Canada would adapt to the proposed changes.

Annex F

Unrestricted Page 6 of 6

F.8 New Business:

It was determined by unanimous vote that a new task force would be initiated to investigate the proposed changes to the accuracy classes. This work should being in the New Orleans meeting. At this time a chair has not been determined.

F.9 ITSC Adjournment

Motion to adjourn by David Wallace and seconded by Marek Kornowski

The next meeting will be at the Spring 2017 Transformers Committee meeting in New Orleans, LA

1 of 14

Annex G Insulating Fluids Subcommittee

October 26, 2016 Vancouver, BC, Canada

Chair David Wallach Vice-Chair Jerry Murphy Secretary C. Patrick McShane

G.1 Introductions, Roll Call of Members for Quorum, Meeting Agenda Approval, F13 Minutes Approval, and Chair’s Comments

G.1.1 Chair’s comments:

a. Shared the scope statement of the SCIF

b. Reminded WG and TF Chairs that their meeting minutes are due for submittal to the SCIF Secretary within 15 days of their meetings. In turn, the SCIF minutes are due on Dec 4.

G.1.2 Roll Call of SC members: (Quorum requirement: 25 minimum)

a. 29 Members signed in. Quorum was achieved

b. 60 Guests of which 9 requested membership:

c. Paul (Randy) Cox, Roger Hayes, Michel Veillette, Kwasi Yeboah, Dominique Bolliger, Marcos Ferreira, Victor Garcia, Thomas Golner, Jinesh Malde.

d. The roster sign-in has attendance of 89, vs. Cloud-in Hand electronic badge reader spreadsheet count of 82.

G.1.3 Agenda Approval:

a. The motion was Approved without objection

G.1.4 Corrections and Approval of minutes from Spring 2016 meeting in Atlanta, GA:

a. SC A correction was made by the Secretary, noting that the number of guest requesting

membership at the S16 meeting were inadvertently left out of the minutes. The minutes

were approval with the pending correction completion. It will only be corrected in the

individual minutes, not the main.

Annex G

2 of 14

G.1.5 Technical Presentation

a. “Where Does the Air Go?” by Don Platts

b. Don showed a video of test risk of air bubble taking a sample while tank has a negative value. Simulated tank pressure of values between -100k Pa to +175k Pa

c. Different valve types impact probability and quantity of possible air ingress. The valve types tested were Ball, Gate, and Globe.

d. Conclusion: Recommend Globe Valves for oil sampling and avoid negative tank pressure during sampling procedure.

e. The presentation will not be posted within IEEE TC site. However, Don plans to release a paper in the near future. If interested in receiving a copy, people should make a request directly to Don Platts or Dave Hanson.

G.1.6 WG & TF Reports Presented at the SC Meeting

G.1.6.1 C57.104 – IEEE Guide for the Interpretation of Gases Generated in Oil – Immersed Transformer (PAR Expiration: 12/31/17)

WG Chair - Claude Beauchemin

The report of the WG Meeting was presented at the SCIF meeting by Claude Beauchemin.

a. Rick Ladroga had to resign as Chair due to other commitments. Claude is the new Chair, and Susan McNelly is the WG Secretary. Quorum achieved. The meeting included a presentation of work done last 6 months. This WG has been meeting 8 or 9 years, and the PAR will expire next year. More work needs to be done, but it is expected that the 1st draft will be sent to WG roster in a couple of weeks for review and comments. Quick presentation one annex was voted out.

b. During New Discussion, Tom Prevost made motion to remove sample section, but includes warning. After that, figure relative gas generation during fault Question difference for generation transformer. Most data comes from lab, not utility, be surprise of errors of info sheet provided by sampler.

See Appendix I for the Minutes (unapproved) of C57.104 WG Meeting as Submitted.

G.1.6.2 IEEE C57.147 Guide for Acceptance and Maintenance of Natural Ester Fluids in Transformers

WG Chair: Patrick McShane, Vice-Chair: Clair Claiborne, Secretary: Jim Graham

The WG Report at the Sub-Committee Meeting: Presented by Patrick McShane:

a. Since A two-year extension of the PAR was approved in June this year. The PAR now expires in December 2016.

b. PC57.147 Draft 3.0 is currently in comment resolution. 126 balloters of which 87% approved the draft. There are 240 comments being addressed by the BRC.

Annex G

3 of 14

c. Several comments received requesting continued service limits table be updated

based on data gained since 2008. The Chair made a request to testing laboratories if they would be willing to share NE sample test data. Data was received from 3 test companies, totaling approximately 50,000 samples. Luis Cheim and Claude Beauchemin both stated due to the huge data base, an analysis could not be completed for many months, maybe take over a year. A call for volunteers to analyze the data and make recommendations to the BRC was made. The following agreed to join a task force: Luis Cheim, Claude Beauchemin, Scott Reed, Alan Sbravati, and John Luksich.

d. A recommendation was made by David Wallach that to avoid excessive delay in

the publication of the revision of the Guide, that this WG suggest to the TF of Consolidation of the Guide to take over the proposed data analysis.

e. Still awaiting input from 5 BRC members in order to finalize Draft 4 for

recirculation

See Appendix II for the Minutes (unapproved) of C57.147 WG S15 Meeting as Submitted

G.1.6.3 TF on Consolidation of Insulating Liquid (Fluid) Guides

Chair: Tom Prevost

The TF Report given at the Sub-Committee Meeting by Tom Prevost:

a. The focus of the meeting was to work on the content of the Scope of the consolidated Guide.

Option A. Create a Mineral Oil Guide and Guide for all other Insulating Liquids.

Option B. Create a Guide that includes all Insulating Liquids for Equipment with the exception Load Tap Changers.

Option C. Create a Guide that includes all Insulating Liquids and includes Load Tap Changers

b. A motion was made by David Sundin and seconded by Luiz Cheim that Option C be selected. The motion carried.

c. A motion was made by Mark Perkins and seconded by Jim Graham that the Scope should be limited to Transformers, LECs, Regulators, and Reactors. The motion carried.

d. The Chair stated that “now we have the first line completed. Next we will need to focus on different use parameters.

See Appendix III for the S16 Minutes (unapproved) of TF Consolidation of Insulating Liquid Guides as submitted.

Annex G

4 of 14

Old Business

a. C57.12.00 Revision – Unresolved Ballot Comments forwarded to the SCIF as follows:

Balloted document: Page 32, 6.6.1, line 13; Standard needs to maintain the sentence "There are other insulating fluids that may be suitable and are commercially available..." from previous version; nowadays, there are other liquids as synthetic esters that are commercially available.

This was rejected as out of scope but could be considered in the future. It was noted that at the time of the revision, neither ASTM specifications nor IEEE Guides for use of other alternative insulating liquids for use in transformers existed.

b. This issue remains unresolved and needs review and consideration by Insulating Fluids/Working Group. If this suggestion has merit, consider making a suggestion to WG C57.12.00. The Chair assigned Patrick McShane to study the issue and make a recommendation of the next meeting.

G.2 New Business

a. C57.12Fredi Jacob stated that he believes while C57.155 DGA of Esters covers many needed aspects, there is more information needed regarding gas evolution vs. the severity of faults.

b. A question was raised by a user that they are considering gas insulated transformers and wondered if the SCIF has considered working on a guide for insulating gases. The Chair said up to this point there has been no demand but would make some preliminary investigation on the issue

G.3 Adjournment

The motion passed unanimously.

Respectively Submitted, Patrick McShane, Secretary SCIF

Annex G

5 of 14

Unapproved Minutes from the S16 SCIF WG and TF Meetings

Appendix I – WG C57.104 Minutes

IEEE Guide for the Interpretation of Gases Generated in Oil – Immersed

Transformers

C57.104 – IEEE Guide for the Interpretation of Gases Generated in Oil – Immersed Transformers

Tuesday, October 25, 2016

Vancouver, BC Canada

Minutes of WG Meeting

The meeting was called to order at 4:45pm by Chair Claude Beauchemin. Vice-Chair Norm Field, Vice Chair Don Platts, and Secretary Susan McNelly (writer of Minutes) were also present. Claude Beauchemin made an announcement that he will be taking on the role of Chair. He also introduced the two new Vice-Chairs and explained that due to the limited time remaining and the amount of work, he felt it was important to have two vice-chairs with specific duties.

Patent disclosure announcement: The Chair asked if there were any individuals that were aware of any patent claims might be Essential Patent Claims. The following statement was shown on the screen during the meeting:

If any individual believes that Patent Claims might be Essential Patent Claims, that fact should be made known to the entire working group and duly recorded in the minutes of the working group meeting.

There were no patents claims identified. Details on patent information can be found at:

https://development.standards.ieee.org/myproject/Public/mytools/mob/slideset.pdf

There were 47 of 83 members present. There were 48 guests, and 4 guests requesting membership. A membership quorum was achieved. The WG does plan to meet at the Spring 2017 Transformers Committee Meeting in New Orleans, Louisianna.

The following guests requesting membership are listed below. Those listed with an asterisk will be added to the WG membership. However, to maintain membership, participation in the development of the guide will be reviewed.

Paul Cox* Jon Garrity Mickel Saad

Annex G

6 of 14

Trenton Williams*

List of Meeting Attendees is provided below. Those identified in bold are WG Members in attendance.

Aikens, Tom Jakob, Fredi Ray, Jeffrey Alonso, Mario John, John Reed, Scott Attard, Jason Joshi, Arvin Rezai, Hossein Ayers, Donald Kampshoff, Ken Riordan, Kevin Beauchemin, Claude Karim, Ibrahim Roizman, Oleg Benach, Jeff Kinner, Robert Saad, Mickel Bolliger, Dominique Kiparizoski, Zan Sandhu, Surinder Boman, Paul Kuppuswamy, Raja Scarborough, Mark Brett, John Lackey, John Schrammel, Alfons Brusetti, Robert Lau, Michael Sen, Changir Cantrell, Rick Livingston, Kerry Sharifnia, Hamid Castellanos, Juan Luo, Shawn Sheehan, David Cheim, Luiz Malde, Jinesh Shem-Tov, Mark Chiu, Bill Martin, Terence Simonelli, Richard Christodoulou, Larry McNelly, Susan Sparling, Brian Claiborne, C. Clair Musgrove, Ryan Stiegemeier, Craig Cox, Paul Mushill, Paul Sullivan, Kevin Davydov, Valery Naderian, Ali Sweetser, Charles Diaby, Mohamed Nims, Joe Thompson, Robert Dicks, Michael Nunez, Arturo Thompson, Ryan Dukarm, James Ocon, Rodrigo Tozzi, Marco Duval, Michel O'Malley, Anastasia VanderWalt, Alwyn

Ferreira, Marcos Palakandy, Rahul Rajendran Veillette, Michel

Field, Norman Patel, Poorvi Wallach, David Fields, Chase Pellon, Verena Wang, Evanne Foata, Marc Perjanik, Nicholas Weber, Brandon Frimpong, George Pinon, Oscar Williams, Trenton Frotscher, Rainer Platts, Donald Wilson, Barnes Garrity, Jon Prevost, Thomas Yeboah, Kwasi Golner, Thomas Pruente, John

Graham, James Ramakrishna, Manjunat Hayes, Roger Rasco, Jimmy Holden , Andy Ratcliffe, Robert

A motion to approve the Fall 2016 Vancouver Agenda was made by Tom Prevost and seconded by Brian Sparling. There were no objections or additions to the agenda. The agenda was unanimously approved.

Annex G

7 of 14

Agenda 1. Attendance Roster Circulation 2. Member Roll Call & Quorum Check 3. Patent Call 4. Approval of Agenda 5. Approval of the Spring Atlanta minutes 6. Document Status 7. New Business 8. Adjournment

A motion to approve the Spring 2016 Minutes was made by Brian Sparling and seconded by Tom Prevost. There was no opposition to approval of the minutes.

Document Status

Claude indicated that a draft 3 has been sent out for review. He asked the WG for feedback on whether we are moving in the right direction. A straw ballot will need to be sent out by early next year to be able to move forward.

Claude Beuchemin presented a short history of the guide and how that has led to where we are today. For more details, see the presentation and the draft attached at the end of the minutes.

Claude asked if anyone knew the source of the 90% Norms (No hand were raised!). It originated in the early (1972) CEGB (Central Electricity Generating Board, UK) use of DGA.

The first revision occurred in 1991. The analysis and sampling sections were removed and transferred to ASTM. The Halstead graph was introduced. TDCG was introduced. Key gas graphs and Table 1 were also introduced. Numbers for table 1 were carried from the 1978 version with the addition of two higher value sets, probably from the same source. Four conditions describing the transformer status were added.

Use of the 1991 guide with the selected limits resulted in a large amount of false positives, due principally to the too low limits for CO and CO2. In the early 2000s, an important revision process was undertaken and generated a large amount of new text, but the guide expired in 2005 before that work could be completed.

The guide was re-installed "as is" with minor corrections in 2006 (The actual version. labelled 2008)

Work was immediately started on collection of data to improve the values in the tables, as well as continuing the work for general improvement of the guide. A study presented during a IEEE meeting at that time indicated that approximately half of the DGA were above condition 1 (Caution) and a third were above condition 2 (Warning).

The result of this revision work was presented at this meeting. A draft (3.0) was sent to all the WG members and guests at the beginning of October for comment and review.

Annex G

8 of 14

The draft guide contains 6 main sections, 9 annexes, 4 tables, and a new flowchart and figures.

A short presentation of the content of each sections and annexes was made.

It is to be noted that the 4 tables in the draft do not contain numbers. The reason is that the TF on data analysis has yet to complete the work. It is to be done before the Straw ballot is issued.

The work remaining to be done was presented as follows:

- Complete text with comments

- Update bibliography with WG suggestions

- Decide if we add recommendation to use on-line monitor on gassing transformer

- Decide if we maintain sampling section

- Finish data analysis and select norms

- Straw ballot

- Ballot

- Ballot resolution

- Prepare a tutorial

- Write a white paper on the data analysis

The floor was open for discussion

Tom Prevost made a motion that the Annex on Sampling be removed and was seconded by Jim Dukarm. Tom indicated that this is more of a guide for interpretation and ASTM is more of a guide for taking the samples and the analysis.

Valery Davydov commented on a presentation he gave in the moisture in insulation WG. From this, the location that the oil sample is taken was found to be very important. Claude commented that this is not exactly what is presently being discussed.

Rainer Frotcher – Indicated that the new guide is much improved and a tremendous amount of work has been done.

Brian Sparling indicated that the guide is meant to be used worldwide, while the ASTM guides are not. He indicated that he refers people to the ASTM document but it is not well known outside of the US and they may not have access to those documents.

Tom Prevost indicated he understood where Brian is coming from, but that if we followed this line of thought in all of our standards and guides, they would be very long. He expressed concerns that by having the information in this guide, then there is a risk

A call for vote was made. There was 1 abstention, 3 negatives, and 43 in favor of the motion. The motion passed.

Annex G

9 of 14

Claude reviewed the remaining work to be done.

• Complete text with comments needs to be reviewed. • Update bibliography with WG suggestions • Decide if we add recommendation to use on line monitor on gassing

transformers.

Claude asked if there was a motion to recommend the use of on-line monitors. No motion was made. Clair Claiborne indicated that there are other documents that adequately cover on-line monitoring and did not feel a need to include this in C57.104.

Fredi Jakob indicated a concern with the figure in Section 4. The figure shows a rapid drop in H2 concentration at low temperatures, followed by a gradual rise with increasing temperature, which is misleading. H2 generation caused in abundance by partial discharge occurs independent of temperature, and in fact can occur at low temperatures (i.e. normal operating temperatures). This causes the peak in H2 generation shown at low temperatures in the figure, which is an electrical phenomenon and not a thermal one.

Michel Duval explained the background of the figure. Claude indicated that maybe the temperatures could be removed if that is causing concern with the figure. More discussion will be needed on this topic.

Juan Castellanos – Asked if we are planning to segregate the data by type of transformer. Claude indicated that there is not enough information in the database to support this.

Claude closed by requesting that the WG members provide their comments within the next couple of weeks if not sooner.

The meeting was adjourned at 6:00PM

Claude Beauchemin WG Chair

Norm Field WG Vice-Chair

Don Platts WG Vice-Chair

Susan McNelly WG Secretary

Page 10 of 14

Unapproved Minutes from the S16 SCIF WG and TF meetings

Appendix II – WG PC57.147 Minutes

Guide for Acceptance and Maintenance of Natural Ester Insulating Liquid in Transformers

March 21, 2016 ATLANTA, GA

Chair: Patrick McShane, Vice-Chair: Clair Claiborne, Secretary: Jim Graham

• Call to Order was made at 3:15 PM. • Introductions/Membership Attendance/Quorum Check • Attendance

o 18 of 30 members present, quorum was achieved o 84 guests o total attendance = 102

• A motion to approve the agenda motion passed.

• A motion to approve the Spring 2016 meeting minutes was passed.

• A call for essential patents was made. No new patent issues were raised.

• Chair's Remarks, Patrick McShane:

o A two-year extension of the PAR was approved in June this year. The PAR now expires in December 2016.

• Old Business

o PC57.147 Draft 3.0 is currently in comment resolution. 126 balloters of which 87% approved the draft. There are 240 comments being addressed by the BRC.

o Several comments received requesting continued service limits table be updated based on data gained since 2008. The Chair made a request to testing laboratories if they would be willing to share NE sample test data. Data was received from 3 test companies, totaling approximately 50,000 samples.

o Still awaiting input from 5 BRC members in order to finalize Draft 4 for recirculation

• New Business: Discussion of Ballot Comments of special interests:

o Essential Patent Claims LoA: Negative vote received due to lack of LoA. Susan McNelly said the discussion is out of the hands of the WG, to be addressed by IEEE SA during their approval process.

o “Allowable free breathing exposure: Statement in draft that would take 5 7 years exposure before free breathing could become a practical issue was challenged, stating a lack of references. Alan Sbravati discussed test and field case history results of service aged ester fluid exposed to atmosphere for a long period. A technical paper presented by Alan will be made available to the BRC.

Annex G

Page 11 of 14

o Comment requesting the addition of corrosive sulfur to acceptance value Table 2. Discussion included that NEs naturally lack content of corrosive sulfur. Some supported inclusion due to possible contamination.

o Several comments requested validation and expansion of values in the service aged NE limits. A task force comprising Luis Cheim, Claude Beauchemin, Scott Reed, Alan Sbravati, and John Luksich was formed to analyze data on service aged fluids received from three laboratories. Luis and Claude both stated due to the huge data base, an analysis could not be completed for many months, maybe over a year. A motion by Dave Wallach to defer analysis of the service aged fluids to the consolidated fluids guide task force was passed. The data analysis will not be done within this working group. If the TF on Consolidation agrees, the gentlemen list above agreed to volunteer. The Chair stated that with this decision, the next recirculation balloting could occur even before end of this year.

o There was discussion of allowable fluid temperature limit should be for vacuum processing. Concerns included loss of inhibitors and boiling of NE at the current temperature limit in the draft.

o There was discussion of whether or not corrosiveness values for ester fluid should be established.

o There was discussion on issue of some Medium/Large OEMs that use vapor dryout, fill with MO, test with MO, and then field fill with NE. There seemed to be a consensus that factory testing with the NE. .

• The meeting adjourned by acclimation at 3:30 pm.

Respectively submitted, Jim Graham, Secretary Chair Post Meeting Notes: The need for the WG to meet in S17 is probably very low. When Draft 4 is finalized by the BRC, it will be sent to the WG members for review, prior to submittal to IEEE SA recirculation vote. Nick Perjanik was inadvertently left of the list, but he is also a member of the BRC. Action: Summarize issue of Lab data analysis and forward names of volunteers to TF Consolidation Chair Tom Prevost.

Annex G

Page 12 of 14

Unapproved Minutes from the S16 SCIF WG and TF meetings

Appendix III – TF Insulating Liquids Guides Consolidation Minutes

Chairman Tom Prevost Secretary Scott Reed The meeting was called to order at 9:35 am by Chair Tom Prevost. There were 25 of 50 members present. There were 36 guests, 15 guests requesting membership and 76 visitors requesting to become a guest. A membership quorum was achieved. Guests attending the WG meeting for the first time who request membership or who have not attended 2 meetings in a row (including the present meeting), will be deferred until the next meeting attended. Agenda

1) Introductions 2) Approval of agenda 3) Approval of March 2016 minutes 4) Review of current document status

a. C57.147 “Guide for Acceptance and Maintenance of Natural Ester Insulating Fluids in Transformers and Other Electrical Equipment”

i. In Revision process, PC57.147 ii. PAR opened 6-Feb-2012

iii. PAR Expiration 31-Dec-2016 iv. Ballot Status

5) New Document: a. Title b. Scope c. Purpose

6) Establishment of Task Forces a. Editorial b. Test methods c. Mineral Oil d. High Molecular Weight Hydrocarbons e. Silicon f. Natural ester g. Synthetic Ester h. Others?

7) New Business Due to the time constraints, attendees did not introduce themselves.

Annex G

Page 13 of 14

A motion to approve the Spring 2016 Agenda was made Jim Graham . Patrick McShane seconded the motion. There were no objections to the approval of the Agenda. Next, a motion was made by David Sundin and seconded by Mario Lacarno to approve the Spring 2016 Atlanta meeting minutes. There were no objections to the approval of the minutes. Chairman Tom posted the Patent Claim. No notifications or comments were received. Chair’s Remarks: As a review of the current document status:

-Patrick McShane announced that C57.147 will have the Par extended to 2018 because there were 220 comments to the last ballot.

A presentation was given by Chairman Tom Prevost to discuss the Scope, Title and Purpose and he referenced the Scopes of C57.106 and C57.147. In response, Rainer Frotscher gave a presentation suggesting to separate this guide into two separate guides—one for less flammable and one for flammable insulating fluids. Three options were proposed by the chair on what the Scope of this WG should be: Option A. Create a Mineral Oil Guide and Guide for all other Insulating Fluids. Option B. Create a Guide that includes all Insulating Fluids for Equipment with the exception Load Tap Changers. Option C. Create a Guide that includes all Insulating Fluids and includes Load Tap Changers. A motion was made for Option C by David Sundin and seconded by Luiz Cheim. The motion carried. Next, it was discussed which equipment should be included as part of this Scope. A motion was made that this Scope should be for Transformers, LTC, Regulators and Reactors by Mark Perkins and seconded by Jim Graham. The motion carried. Finally, after discussion whether to include Bushings as part of this Scope, Jim Graham made a motion to exclude Bushings as part of Option C. Rich Simonelli seconded the motion and the motion carried. The chairmen summarized the discussion of the scope as follows. Only the applicable equipment has been agreed to so far: This guide applies to insulating liquids used in transformers, tap changers, regulators and reactors. Agree 10-24-16 The guide discusses the following:

• Analytical tests and their significance for the evaluation of mineral insulating oil. • The evaluation of new, unused mineral insulating oil before and after filling into equipment.

Annex G

Page 14 of 14

• Methods of handling and storage of mineral insulating oil. • The evaluation of service-aged mineral insulating oil. • Health and environmental care procedures for mineral insulating oil.

The characteristics of the liquids discussed in this guide do not include liquids that is in factory fill lines, nor does this guide cover reclaimed oil installed in new equipment. The qualities of such oil, if used, should be agreed upon by the manufacturer and the user of the equipment. The next meeting we will discuss the remaining bullet points in the scope and more specifically the following bullet:

• The evaluation of new, unused mineral insulating oil before and after filling into equipment. No New Business was discussed and the meeting was adjourned at 10:47 am.

Page 1 of 11

Insulation Life Subcommittee

October 26, 2016 Vancouver, BC

Chair: Sheldon Kennedy Vice-Chair: Barry Beaster Secretary: Sam Sharpless

The Insulation Life Subcommittee was called to order by the Chair in Vancouver, BC on October 26, 2016 at 8:11 AM. Due to the size of the group, general introductions were not made. The chair requested that each person state their name and affiliation when addressing the subcommittee.

The secretary reported that according to the electronic check-in system, 59 of 106 members were present at the start of the meeting and that a quorum had been achieved.

The chair presented the Spring 2016 meeting minutes. Gary Hoffman made a motion to approve the minutes as written. Phil McClure seconded the motion and there was unanimous approval.

The chair presented the agenda for the current meeting. Stephen Antosz noted that a representative the Chinese Society of Electrical Engineers desired to address the group and requested that they be placed on the agenda as new business and the Chair agreed to do so. Sanjib Som made a motion to approve the amended agenda. Don Ayers seconded the motion and there was unanimous approval.

Consolidation of the electronic check-in records and the written attendance rosters after the meeting provided the following final attendance totals;

Total Present 224

Members 76

Guests 148

11 guests requested membership

H.1 Chair’s Report

The chair provided the dates of upcoming TC meetings as follows;

2017 Spring Meeting; April 2 – 6, 2017, New Orleans, Louisiana, USA

2017 Fall Meeting; October 29-30, 2017, location TBD

2018 Spring Meeting; March 25-29, 2018, Pittsburgh, Pennsylvania, USA

The chair requested that any person with knowledge of a patent essential to meet the requirements of any subcommittee standard to bring the issue forward for discussion. No one responded to this request.

The chair requested the following items be included in all activity group minutes;

- The name of the activity

Annex H

Page 2 of 11

- The date and time of the meeting

- The number of members and guests in attendance. Full attendance should be recorded in the AMS system

- The presence or absence of a quorum

- Any essential patent issues raised during the meeting.

- A summary of discussion. Intricate detail not required. Use a separate document to explain decisions that are made.

- A record of the decisions made in the meeting

- If there will be another meeting. If so, state the time and place.

- Submit minutes as soon as possible, but no more than 15 days after the meeting.

The chair discussed the membership requirements and recognized the following new members; Hamid Abdelkamel, Dieter Dohnal, Don Dorris, Attila Gyore, Kurt Kaineder, Sam Ojeda, Rakesh Rathi, Alwyn VanderWalt, Matthew Weisensee, Trenton Williams, and Kwasi Yeboah

The chair discussed the requirements for continued membership and noted that the following members had been placed on guest status; RajAhuja, Tauhid Haque Ansari, Julio Caldeira, Jose Izquierdo, Tamyres Machado Junior, Emilio Morales-Cruz, Ali Naderian, Leslie Recksiedler, Michael Shannon, James Thompson, and Peter Zhao.

H.1.1 Project Status Reports

C57.91 IEEE Guide for Loading Mineral-Oil-Immersed Transformers

C57.91 is valid until 2021.

C57.100 IEEE Standard Test Procedure for Thermal Evaluation of Liquid-Immersed Distribution Transformers

C57.100 is valid until 2021.

C57.119 IEEE Recommended Practice for Performing Temperature Rise Tests on Oil-Immersed Power Transformers at Loads Beyond Nameplate Ratings

C57.119 is valid until 2018 and is Chaired by Gael Kennedy.

C57.154 Design, Testing and Application of Liquid-Immersed Transformers with High-Temperature Insulation

C57.154 is valid until 2022.

Annex H

Page 3 of 11

C57.162 - Guide for the Interpretation of Moisture Related Parameters in Dry, Gas Insulated and Liquid Immersed Transformers and Reactors

The C57.162 PAR expires December 31, 2017. The standard is valid until 2018 and is Chaired by Tom Prevost

1276 Guide for the Application of High Temperature Insulation Materials in Liquid-Immersed Power Transformers

The 1276 PAR expires December 31, 2016 and an extension has been requeseted. The standard is valid until 2018 and is Chaired by Roger C. Wicks.

1538 IEEE Guide for Determination of Maximum Winding Temperature Rise in Liquid-Filled Transformer

1538 is valid until 2021 and is Chaired by Richard Marek. An amendment was approved in September 2015.

Annex H

Page 4 of 11

H.1.2 Working Group and Task Force Reports

Working group on PC57.162 – Guide for the Interpretation of Moisture Related Parameters in Dry, Gas Insulated and Liquid Immersed Transformers and Reactors – Tom Prevost

A meeting was held on October 24, 2016 for the working group on PC57.162 – Guide for the Interpretation of Moisture Related Parameters in Dry, Gas Insulated and Liquid Immersed Transformers and Reactors (Moisture in insulation systems) Tom Prevost - Chair Valery Davydov- Vice Chair Deanna Woods – Secretary Stephanie Denzer – Secretary for this meeting Attendance: Members: 39 of 88 Guests: 49 guests with 8 requesting membership The following guests requested membership

Roger Hayes Marcos Ferreira Shane Goydich Kiran Vedante Sheldon Kennedy Kevin Sullivan Jeffrey Ray

The meeting was called to order at 11:00 am. Introductions of the Vice Chair and (temporary) Secretary were made. Members of the working group present at the meeting were asked to stand and be counted to assess whether there was a quorum. We had 39 of 88 members present so we did not have a quorum. The chair noted that since we did not have a quorum, we could not do any official business. The agenda of the meeting was presented for comment. No additional agenda items were suggested. Meeting Agenda: • Introduction of attendees • Establishment of Quorum • Approval of Agenda • Approval of Minutes from March, 2016 • Call for Patent Claims • Review of PAR

– Project Scope – Project Purpose – Project Timeline

• Chair’s Remarks • Presentation, “Case Study: Investigation into High Risk Associated with Wet Oil Resulted in

Transformer Failure”, Valery Davydov • Update on Task Force Activity

Annex H

Page 5 of 11

The following call for patents was shown to the members and guests. No one responded.

If any individual believes that Patent Claims might be Essential Patent Claims, that fact should be made known to the entire working group and duly recorded in the minutes of the working group meeting.

The scope and purpose of the project were reviewed by the chair. A request for volunteers to edit the document once the TF reports have provided their drafts was made. If anyone is interested, please contact Tom Prevost. Valery Davydov gave a presentation “Case Study: Investigation into Transformer Failure and Positioning of On-Line Moisture Probes” for Task force 6. A question was presented by Roger Fenton and a response for follow up offline was given. Task Force Reports; Task Force 1 – Terminology and Definitions Task Force Leader (Jeff Golarz) Tom Prevost presented as Jeff was not present. Jeff has compiled all of the terminology and definitions that have been submitted by the task forces. This is ready to be included in the main document. Task Force 2 – Measurement and evaluation of moisture-in-gas insulation parameters. Task Force Leader – Tom Melle Progress is being made, a presentation summary is available on the transformer committee website. The first draft of the chapter was requested to be completed by the end of January 2017. Task Force 3 – Measurement and evaluation of moisture in – liquid insulation parameters. Task Force Leader – Claude Beauchemin CIGRE is currently working on this effort and should be completed 1Q or 2Q 2017 – we are hoping to utilize this information. A draft was requested by end of January 2017. Task Force 4 – Measurement of moisture in solid insulation. Task Force Leader – Ron Hernandez The task force has completed its work and the chapter has been submitted to the WG chair for inclusion in the document. The chair complimented the members of the task force for completing their assignment. Task Force 5 – Estimation of moisture in solid insulation using dielectric response methods Task Force Leader George Frimpong The task force has completed its work and the chapter has been submitted to the WG chair for inclusion in the document. The chair complimented the members of the task force for completing their assignment. Task Force 6 – Inferring of moisture in solid insulation from measurements conducted in liquid or gaseous medium. Task Force Leader – Valery Davydov A presentation was given on the position of moisture sensors. It was suggested that the TF considers including into a draft a discussion on the issue of positioning of moisture sensors in the

Annex H

Page 6 of 11

main oil circulation and away from it. A draft of this section should be ready by the end of January 2017. Task Force 7 – Evaluation of aging and end of life of solid insulation parameters Task Force leader – Roger Wicks No update – draft to be completed by the end of January 2017. Task Force 8 – Factory/workshop application of knowledge on moisture; establishing baselines Task Force leader – Poorvi Patel The task force has completed its work and the chapter has been submitted to the WG chair for inclusion in the document. The chair complimented the members of the task force for completing their assignment. Task Force 9 – Field application of knowledge on moisture * Note: This section lists the risks associated with moisture Task Force leader – Jim Thompson The chair presented TF chair Thompson’s summary of progress to date;

“I am reviewing papers and guides on moisture risks including bubble evolution in oil, dielectric failure, and premature aging of paper. I authored the Cold Start VDE response curve in the C57.106-2015 Annex and can provide more details. Other guides already have bubble evolution risk information. I will search the IEEE Explore site for aging vs moisture in paper/oil systems. I hope to have a draft in two weeks. I still don’t have e current C57.91 but will get a new C57 series CD after this meeting. Most of the text regarding risks will be discussion and references to C57 guides. I will also add a bibliography.”

It was suggested that this document must include moisture levels associated with known risks. The chair commented that this should be included in the work of TF 9. Rough Draft of this section to be completed by end of January 2017. Task Force 10 –Moisture Migration, Distribution and Moisture Equilibrium Charts Task Force leader – Bruce Forsyth The task force received additional volunteers since last meeting and a scope has been developed. TF 10 Scope:

This chapter presents the best known information related to a) Moisture migration in insulation systems; b) How moisture distributes throughout an insulation system; c) Moisture equilibrium charts applicable to transformer insulation systems.

The initial focus will be on liquid-filled insulation systems, but an effort will be made to provide similar information for gas-filled insulation systems. Oleg Roizman commented that basic adsorption isotherm curves for cellulose were developed in 1960 and came from the textile industry. He asked a question on whether or not to use these existing “Jeffries” curves or create new ones. The chair commented that the development of new adsorption curves, although preferred, may take too long for inclusion in this document. (Task force is looking for input from material suppliers) A draft as was asked to be completed by the end of Jan 2017.

Annex H

Page 7 of 11

This meeting was adjourned at 12:15pm

Working Group for Application of High-Temperature Materials IEEE P-1276 – Roger Wicks

Sheraton Hotel – Vancouver, BC Canada Room – Grand Ballroom AB October 25, 2016, 3:15 - 4:30pm

A. Welcome & Chairman's Remarks R. Wicks

Roger opened the meeting at 3:15pm with a brief description of the scope of the Working Group. The chair reviewed the patent topic and there were no essential patented described for work in the area of this standard.

B. Circulation of Attendance Rosters J. Arteaga

Circulated

C. Attendance for Quorum J. Arteaga

19 members were in attendance meeting the quorum requirement of 18 members. The attendance will be reviewed and new members will be added if they meet current attendance requirements. The attendance will be recorded in the AMS system. The automated attendance records (scanning system) recorded 19 members and 60 guests.

D. Approval of Spring 2016 Meeting Minutes – Atlanta, GA J. Arteaga

Mike Shannon made a motion to approve the minutes as written, John Luksich seconded it and these were unanimously approved without changes.

E. Approval of Meeting Agenda R. Wicks

Eduardo Tolcachir made a motion to approve the agenda as written, Mike Shannon seconded it and these were unanimously approved without changes.

F. Status of PAR/Document R. Wicks

The PAR of this standard was requested for extension for 2 year. The standard expires at the end of 2018.

G. Assignments from Last Meeting R. Wicks

The assignments for the elaboration of the draft are as follows. Chair requested groups to complete the draft work before the end of year. Section 5 – Insulation-system temperature ratings, test procedures, and material aging

qualification: Chair - Roger Wicks

Annex H

Page 8 of 11

Volunteers – Mike Franchek, Ken McNeish, Tom Golner, David Stankes, Solomon Chiang, Joshua Verdell, Dave Sundin, Jinesh Malde, and Mohamed Diaby.

Section 6 – Insulating Materials. Chair – Javier Arteaga Volunteers – Clair Claiborne, Julio Caldeira, Patrick McShane, Dave Sundin,

Attila Gyore, Chuck Stevens, Shane Goydich, Jinesh Malde, Dustin Davis, and Mike Shannon.

Section 7 – Description of high-temperature transformers. Chair – Mike Franchek Volunteers – Kurt Kaineder, Arup Chakraborty and Evan Langran.

Section 8 – Loading guidelines for high-temperature transformers. Chair – John Luksich Volunteers - Arup Chakraborty and Jinesh Malde

Section 10 – Heat run test and average winding temperature. Chair – Juan Castellanos Volunteers – Mike Franchek, Alan Sbravati

Working Group on C57-119 IEEE Recommended Practice for Performing Temperature Rise Tests on Oil-Immersed Power Transformers at Loads Beyond Nameplate Ratings – Gael Kennedy

The document is undergoing ballot resolution. It is still on track to be completed prior to the end of 2018. This working group did not meet during the Vancouver Conference.

Submitted by: Gael R Kennedy

H.2 Old Business

The PAR for the Proposed WG – PC57.165 “IEEE Guide for Temperature Measurements for Liquid Immersed Transformers and Reactors” has been submitted and should be considered in December. The activity chair is Phil McClure.

A study group was formed to address comments related to C57.91, “Guide for Loading Mineral Oil-Immersed Transformers and Step-Voltage Regulators” consisting of Gary Hoffman and Bruce Forsyth.

A C57.12.00 Ballot Comment was addressed. The comment concerned clause 4.3.1 and was raised by Mark Perkins; operation at high altitude also affects the cooling performance, and this should be addressed in addition to dielectrics.

• C57.12.00 clause 4.3.1 refers the reader to C57.91.

• Reviewer Response: The balloter is correct that high altitude affects cooling performance, however IEEE Std. C57.91 is cited in Clause 4.3.1. In IEEE Std. C57.91-2010, the normative Annex E, titled "Unusual temperature and altitude conditions" the text of sub-clause E.2 specifically addresses the balloter's concern as follows: "The effect of the decreased air density due to high altitude is to increase the temperature rise of transformers since they are dependent upon air for the dissipation of heat losses." Hence it is the judgment of the reviewers that no change is required to C57.12.00-2015 to address this concern as it is referenced in Clause 4.3.1 of IEEE Std. C57.12.00-2015 by referencing IEEE Std. C57.91 and IEEE Std. C57.91-2010 adequately explaining the consideration of air density on air circulation as noted above.

Annex H

Page 9 of 11

H.3 New Business Jeff Ray expressed a concern about the temperature rise test procedure found in C57.12.90-2010 Section 11.2.2 Hot-Resistance Method. He has noted variations in the way that these tests are performed among various manufacturers and plants. He spoke in favor of a task force to survey owners and manufacturers to determine the current methods and expectations from all sides. The survey information would be published without identifying the individual responses from each party. Mr. Ray then made a formal motion to produce and publish such a survey. The motion was seconded by Matt Weisensee. Stephen Antosz noted that a 2015 version of this standard has been published and there were changes to the subject section. The chair asked Mr. Antosz about the workability of a confidential survey and Mr. Antosz said that it could be done. Gary Hoffman stated that the standard is clear and that the owners should ensure that it is followed. Mr. Antosz suggested that Mr. Ray may want to perform a review of the standard instead of a survey. The motion failed with a vote of 2 for and 57 against. Stephen Antosz introduced Jianbin Fan, representing the Chinese Society of Electrical Engineers. Mr. Fan provided a presentation regarding a CSEE standard for lead exits, 1000 volts and above. Mr. Fan said that the standard had been presented to IEEE for adoption. It was initially rejected, but Mr. Fan was eventually referred to the Insulation Life Subcommittee for further consideration. Mr. Gary Hoffman spoke warmly in support of working together in global initiatives. Sajib Som noted that the CSEE standard directly specifies means and methods in a way that will block development and hamper introduction of new ideas. Mr. Som suggested that the document could potentially be considered a guide, but not a standard. Tom Prevost stated that the document does not fit the scope of the ILS. He stated that the document may be more appropriate for ASTM rather than IEEE. Don Platts stated that the document fits the TC scope, but perhaps not the ILS. Mr. Platts said that IEEE standards are focused on focused on functionality but the CSEE document is focused on means and methods. Mr. Hoffman countered that construction methods were in the purview of the TS, but agreed that the ILS may not be the correct subcommittee. Mr. Fan responded to each of the comments and said that he thought that the document would be appropriate for the IEEE. The Chair thanked Mr. Fan for his presentation and agreed to consult the TC leadership for guidance on how to proceed. Shamaun Hakim raised an issue about testing in C57.12.90. Jeff Ray, Chair of the C57.12.90 Task Force, said that he would like to study the issue further and report at the next meeting. Based upon issues raised in the Working Group meeting for the revision of IEEE Std 1276, the chair asked for formation of a Task Force to perform a procedural evaluation C57.154, Annex B, clause B.5 and provide a recommendation regarding this data. Unfortunately, there was not enough time to organize this work during the meeting. Mr. Patrick McShane desired to make comment about the work of the Working Group for P1276. However, he could not be heard due to a lack of time. The chair requested that Mr. McShane provide his comments in writing.

Annex H

Page 10 of 11

H.4 Adjournment The meeting was adjourned at 9:15AM.

H.5 Post Meeting Notes Following the meeting, A task force titled “C57.154 Annex B Clause B.5 Recommendation” was formed. Robert Thompson has volunteered to chair the group, and it will meet during the next Transformers Committee meeting in New Orleans. The group was organized as follows:

Scope: This TF is tasked to evaluate the content of C57.154 Annex B, Temperature Limits and to specifically recommend the disposition of Clause B.5 to the Insulation Life Subcommittee. The TF is not authorized to make any changes to Annex B or to take any other action. Background: C57.154 Annex B Clause B.5, titled Temperature Limits, proposes equations and alternate tables to the body of the C57.154 standard based on curves composed of historical test data, which are incorporated in the annex. A presentation was made at the WG for the revision of IEEE Std 1276 in the Fall of 2016 that presented these curves without the mineral oil comparison data points. The claim was made that this data was insufficient to define such equations and alternate tables. The presentation further recommended the removal of Clause B.5 from the annex. In consideration of this request, the Chair of the Insulation Life Subcommittee requested that a task force be formed to evaluate this request and make a recommendation to the Subcommittee. Expected Result: It is expected that a small, balanced group of 5 – 8 invited members of the Insulation Life Subcommittee would form this task force to be chaired by one of these members with no ties to the ester liquid industry. It is expected that no more than two members from different companies will represent the ester liquid industry. The rest of the members will be composed of Insulation Life Subcommittee members who are relatively unrelated to the ester liquid industry. The Chair of C57.154 will serve in an advisory capacity with no vote.

Mr. McShane was recognized by the chair during the meeting, but his comments regarding issues raised at the P1276 working group meeting could not be heard due to a lack of time. Mr. McShane kindly provided his commentary following the meeting and the substance of his commentary is included here;

1. The bulk of the meeting time for working group P1276 related to the annex of C57.154. A task force should be formed to consider modifications to this annex. 2. There was discussion in the working group meeting which suggested that there is confusion about the loading guide. However, there was only one comment on this issue during the voting process for the C57.154 standard. 3. Data that is created under the methods described in previous versions of a standard should not necessarily be invalidated by newer standard revisions.

Annex H

Page 11 of 11

Respectfully submitted,

Samuel L. Sharpless Secretary, Insulation Life Subcommittee

Annex J Performance Characteristics Subcommittee

October 25, 2016 Vancouver, BC, Canada

Chair: Ed teNyenhuis Craig Stiegemeier Vice Chair: Craig Stiegemeier Secretary: Sanjib Som

J.1 Introduction / Attendance

The Performance Characteristics Subcommittee (PCS) met on Wednesday, October 25th, 2016 at 3pm with 171 people attending. Of these, 67 were members and 104 were guests. There were 41 first time attendees. Prior to this meeting, the total membership of PCS was 87 members; therefore, quorum was achieved with 77% of the membership in attendance.

There were 18 guests requesting membership (those guest’s meeting attendance will be reviewed and if acceptable will be added to PCS before the Spring 2017 meeting).

The Vice-Chair distributed rosters for the seating arrangement in the room.

J.2 Chairman’s Remarks

The Chair provided the following updates and comments. Status of Pars Neutral Grounding Devices PC57.32 approved 2016 PAR’s

Distributed Photo-Voltaic Grid Transformers C57.159 IEEE/IEC Wind Turbine Generator Transformers, P60076-16 Tertiary/Stabilization Windings PC57.158 Loss Evaluation Guide C57.120

2018 PAR’s Non-sinusoidal Load Currents C57.110 Shunt Reactors C57.21

2019 PAR’s 3-ph Transf. Connections C57.105 C57.109 - Through-Fault-Current Duration

Status of Standards C57.18.10 Semiconductor Rectifier Transformers (2019 PAR to be submitted) C57.136 Sound Abatement Guide (2018 – will let expire) C57.123 Loss Measurement Guide (2020) C57.142 Transient Guide (2020) C57.149 SFRA Guide (2022) C57.133 Guide for Short Circuit Testing (Expired)

Future Technical Presentation TF Report on HV & EHV Transients C57.142

Attendance and Quorum The chair requested attendees to record their attendance on one of the rosters being

circulated – only attendees name was required if it is not on the roster

Annex J

Page 2 of 31

PCS now has 87 members after a review of the Spring 2016 meeting attendance, along with the 4 previous meetings

10 “Corresponding Members” are counted as “Guests” in terms of attendance for a quorum

Requests for membership will be granted if an attendee made the past 3 of the last 5 meetings

Today meeting quorum will be reached if 44 members are in attendance The following 7 Members missed 3 or more of the last 5 meetings and have been moved to “Guest” status:

Raj Ahuja Fred Elliott George Frimpong Alexander Kraetge Mario Locarno Michael Miller Peter Zhao

The following 10 Corresponding Members are being counted as guest status to support reaching the meeting quorum. They continue to receive communications and their guidance for the working group is most welcome.

Donald Chu Larry Coffeen Jerry Corkran Alan Darwin Richard Dudley John Lackey Tamyres Machado Junior Dennis Marlow Paulette Powell Loren Wagenaar

The following 13 Guests requested membership at the Spring 2016 meeting, attended the past 2 meetings and have been added as Members for the fall meeting:

Hamid Abdelkamel Christopher Baumgartner Marcos Ferreira Hugo Flores Anthony Franchitti Kristopher Neild Harry Pepe Kirk Robbins Rodrigo Ronchi Yong Tae Sohn Kiran Vedante David Walker Matthew Weisensee

The following 7 Guests requested membership but have not participated in the past 2 meetings

Annex J

Page 3 of 31

Myron Bell Florian Costa Sidney Johnson Tim-Felix Mai Andre Shor Michael Spurlock Alwyn VanderWalt

Current breakdown of the Working Group: 87 Members 10 Corresponding Members (counted as guests) 87 total members; 44 are needed for a quorum

The Chair all stressed that attendees must be sure that their e-mail address is up to date in the AMS system – many undeliverable notices were received during WG communication attempts

Next the Chair made attendance roll call and requested attendees raise their hand if they see

their name on the screen.

J.3 Approval of Agenda

The Chair presented the agenda. A motion to accept as proposed was given by Dan Sauer and seconded by Rogerio Verdolin. The chair requested comments or objections - there were none. The agenda had been earlier sent to the members by email several weeks prior to the meeting

J.4 Approval of Last Meeting Minutes

The chairman presented the minutes of the last meeting held in Atlanta, Georgia – April, 2016. A motion to accept as proposed was given by Dan Sauer and seconded by Hemchandra Shertudke. The acceptance of the minutes was passed by unanimous vote.

J.5 Minutes from Working Groups and Task Force

The following WG and Task Force reports were received next (the reports are below):

• WG on Tertiary/Stabilization Windings PC57.158 E. Betancourt

• WG on PCS Revisions to Test Code C57.12.90 M. Perkins

• WG on C57.109 - Through-Fault-Current Duration V. Mehrotra

• TF on Audible Sound Revision to Clause 13 of C57.12.90 B.Beaster in place of R. Girgis

• WG on Non-sinusoidal Load Currents C57.110 R. Marek

• WG on PCS Revisions to C57.12.00 (by Craig S) T. Ansari

• WG Shunt Reactors C57.21 S. Som

• IEEE/IEC WG Wind Turbine Generator Transformers, P60076-1 P.Hopkinson in place of D. Buckmaster

• WG on C57.18.10 S. Kennedy

• Loss Evaluation C57.120 Rogerio Verdolin

• WG 3-ph Transf. Connections C57.105 A. Bromley

• WG on Distributed Photo-Voltaic Grid Transformers C57.159 H. Shertukde

• TF on HV & EHV Transients C57.142 J. McBride

• TF Short Circuit Criteria S. Patel

Annex J

Page 4 of 31

J.6 Unfinished (Old) Business

None

J.7 New Business

For C57.110, Rick Marek proposed a motion to take the standard to ballot. This was seconded by Sam Sharpless. The proposal was carried unanimously by voice vote.

Sheldon Kennedy stated that the C57.32 guide for neutral grounding devices received comments from ‘MS Resistance’ in France. Sheldon led a task force to review these comments and the TF agreed that changes to the recently published C57.32 are needed. Sheldon proposed a motion to the SC to form a WG to seek a PAR and make the revision to the guide. This was seconded by Tom Melle. The motion was accepted through unanimous voice vote.

For C57.105, the current chair Adam Bromley is stepping down. The Chair announced that the new chair will be Rogerio Verdolin.

Sanjib Som stated that he had a question during the Bushing Subcommittee meeting and it came out that bushing overloading capability is not as clear as it is for transformers. Hence transformer engineers need to look into this while selecting bushings for their transformers.

There was a question about the C57.12.00 system voltages and why some of the voltage variations are not +/- 5% (most are). Steve Snyder commented that this was investigated some years ago in C57.12.00 and it was established that the table reflects the North American practices.

Adjournment was proposed by Ramsis Girgis and seconded by Dan Sauer.

The meeting was adjourned at 4.15 pm.

Annex J

Page 5 of 31

J.8 Minutes of Meetings of Working Group (WG) and Task Force (TF) Reports (all unapproved)

J.8.1 WG on Tertiary/Stabilization Windings PC57.158 E. Betancourt

PCS Working Group on Guide for Application of Tertiary and Stabilizing Windings PC57.158

Performance Characteristics Subcommittee

IEEE / PES Transformers Committee

October 24, 2016 9:30 AM The Sheraton Vancouver Wall Centre Hotel, Jr. Ballroom CD

Vancouver, BC, Canada

UNAPPROVED MINUTES The WG C57.158 met at 9:30 AM on October 24, 2016. 18 Members out of 31 were present so we had a quorum to conduct regular business. 4 Corresponding Members and 55 Guests were also present and seven of them requested membership.

Javier Arteaga ABB Inc. Markus Schiessl SGB YT Sohn HICO Matt Weisensee PacifiCorp Anton Koshel Delta Star Kris Neild Megger Jeffrey Wright Mitsubishi

The Agenda was approved with no comments or amendments. A motion for approval of the Atlanta WG meeting minutes was made by Hemchandra Shertukde, seconded by Hugo Flores and approved. The Essential Patent Claim notification to the working group was requested with no response from those in attendance. A. Old Business The Vice Chair discussed the present status of Draft 6 rev. A of the Guide and change in figures due to copyright issues. The draft is out for ballot. A motion to create a comment resolution group was made by Hemchandra Shertukde, seconded by Xose M Lopez-Fernandez second and approved. Volunteers for the comments resolution group were asked to sign-up after the meeting.

Annex J

Page 6 of 31

B. New Business No new business was presented before the WG. Motion to adjourn WG meeting was made by Hemchandra Shertukde and seconded by Hugo Flores. Meeting was adjourned at 09:55 am. Respectfully submitted, Enrique Betancourt, WG Chair Brian Penny, Vice Chair

Marnie Roussell, Secretary

J.8.2 Working Group on PCS Revisions to C57.12.90 - Mark Perkins

Meeting Minutes Task Force on PCS Revisions to C57.12.90

October 24, 2016, 11:00am-12:15pm Grand Ballroom CD, Sheraton Vancouver

Mark Perkins, Chairman; Craig Stiegemeier, Secretary 1. PCS Chair Comments

• Ed teNyenhuis, PCS Chair, called the meeting to order. Ed informed all that the Working Group would become a Task Force in the future. Since C57.12.90 revisions are the responsibility of the Standards Subcommittee (not PCS,) this must become a Task Force. The Task Force would still be responsible for providing PCS comments to the Standards SC for future updates to C57.12.90.

• Ed informed all that this will be Mark’s last meeting as Chair of the Task Force. The attendees thanked Mark for all his efforts to keep C57.12.90 current. Hakan Sahin will take over as the new Chair of the Task Force at the end of this task force meeting.

2. Introduction of members and guests

• Mark Perkins presided over the meeting as Chair. Craig Stiegemeier was secretary. Three (3) attendance rosters were circulated for those in attendance to record their presence and confirm their membership or guest status.

3. Attendance

• A review of the adjusted membership was conducted and 38 of the 57 TF members

were in attendance. This resulted in attendance of 66% of the membership, making

this meeting “official” as a quorum was reached. In addition, 79 guests were present

at the meeting, of which 28 were first time attendees. 20 of those guests requested

membership on the Task Force. A review of past attendance will be conducted, and

those that meet the requirement of participating in the TF and have either attended

the previous 2 meetings or 3 of the past 5 TF meetings will become TF Members.

They will be on the roster for the Spring 2017 New Orleans meeting. Also, any of the

current members will be removed if they have not attended 3 of the past 5 meetings.

Also, anyone who has not attended any of the past 10 meetings will be removed

from the rosters circulated at the Spring meeting to help control the size of the roster.

Annex J

Page 7 of 31

4. Agenda approval

• Dan Sauer made a motion to approve the agenda and Bertrand Poulin seconded the motion. Unanimous approval was confirmed by all in attendance.

5. Minutes of the Spring 2016 meeting

• A review of the Spring 2016 Atlanta minutes was conducted by the chair. Bertrand Poulin made a motion, and it was seconded by Dan Sauer to approve the Spring 2016 minutes as written. Minutes were approved by the membership unanimously.

6. Old Business

• A review of the discussion that occurred at the Atlanta meeting on the voltage test of the LTC.

o Test range with current at load loss connection

Rainer Frotscher from Reinhausen cleared up that the full current test is to test the tap changer. He attributed the suggestion to Joe Foldi.

Joe Foldi stepped up and explained that the intention of the test was to run through the full range of the LTC. IEC requires that the test take place for 10 times going 2 steps up and down so the reversing switch operates for 10 operations.

Pierre Riffon suggested that the test follow the IEC test. Bertrand Poulin noted that the end-to-end test is ideal. If it is not

practical, the IEC approach is a reasonable engineering compromise. His opinion is that 5 complete cycles (10 operations of the reversing switch) should be the minimum number of operations.

Ajith Varghese from SPX suggested that +2 and -2 should be operated at least 3 times. There would be

Don Ayres suggested that going from one end through the reversing switch and returning to the end, at the highest power rating of the transformer.

Joe Foldi believes that it is not unreasonable to go through the complete range of the LTC.

Shamaun Hakim of CG Power Manitoba made a comment. Jason Varnell of SPX Transformers noted that the specific type of

regulation (coarse/fine, linear, buck/boost) should be considered. Kushal Singh of ComEd noted that end to end testing is in their

specification. They’ve never had a manufacturer object to the end to end at full rated current as shown on the nameplate.

Javier Artega from ABB noted that most times LTC’s are plus/minus type with a reversing switch. He noted that linear type LTC’s do not have reversing switch and the testing should apply to all types of LTC’s.

Matt Weisensee at PacifiCorp noted that is an OEM has an obligation to test per the nameplate.

Steve Schroeder ABB South Boston is concerned that this test helps determine that a reactive type LTC is properly connected. The test makes sure that the leads are corrected properly. Steve’s opinion was that connection issues are found only with a current test, as a voltage test would not find the problem.

Mark Perkins was under the opinion that a voltage test would find the problem.

Annex J

Page 8 of 31

Jeorg Olin from SMIT Netherlands – end to end testing is a challenge with very large autotransformers. He suggests that we stick with the 2 steps up and then two down, causing operation of a reversing switch (if present.)

Mike Spurlock from AEP noted that they require an overload test at 25% above maximum nameplate rating.

Leopoldo Rodriguez of EFACEC commented that testing the LTC with full current and full voltage from end-to-end is essential in finding problems before the transformer ships. Anything less that that would not identify all issues.

The Chair summarized that the group seems split about evenly, with half preferring end to end and others preferring two steps up and down through the reversing switch

Dan Blaydon, BG&E suggested we confirm a quorum before any motions to vote. As noted above, a quorum was confirmed.

Ajith Varghese of SPX suggested that the TF vote, Rogerio Verdolin seconded. The motion was that we take a vote of end to end or +/- through the neutral.

1. 21 voted that the test be performed from end to end of the tap range; with 11 voting to go 2 steps up and then down while going through the reversing switch if present.)

2. We will include end to end in the first draft o A discussion of the current level during the test took place during the

meeting.

Krishnamurthy Vijayan of PTI Manitoba suggested the test always be

conducted at the top rating on the nameplate.

Dan Blaydon of BG&E suggested that the overload requirement be

left up to the user to specify an overload condition as they seem to

vary quite a bit from user to user.

Bertrand Poulin motioned, and Dan Sauer seconded that the test

specified in the standard be limited to the top rating of the transformer.

Dave Ostrander mentioned that the rating should be made clearer,

there may be a need for a minimum test level at 80% of the top

nameplate rating. Bertrand clarified that his intent was that the

current on the nameplate would apply for each tap. Shamaun Hakim

of CG comment that 85% was in line with the minimum heat run test

levels in our standards. Rainer Frotscher from Reinhausen suggested

that it wasn’t necessary to adjust the current for each tap as this is a

significant burden. Joe Foldi reinforced Dave Ostrander’s comment

that by putting an 80% minimum current would accomplish the goal of

performing the test with significant current without putting an undue

burden on the OEM. Javier Arteaga from ABB suggested that

changing the current at each tap would be an undue burden. The

amended motion is that the test be performed as close as possible to

the top nameplate rating, but not less than 80% of the top rating. The

motion passed with 32 member voting for the motion and no one

against the motion.

o Mark called for a discussion on the pass/fail criteria for the test.

Annex J

Page 9 of 31

Bertrand Poulin noted that a pass/fail would have to be applied to

some measurement or observation. He noted that most people go by

what they hear during the test, and observations of the current during

the transition (such as unusually high during the transition.) He noted

that DGA varies dramatically based on LTC, transformer design and

application of the LTC

Rainer Frotscher suggested that one criteria would be requiring that

DGA in the main tank should not change during the test. In tank

LTC’s should not exceed 12ppm, as some contacts will produce low

level of gasses.

Detlev Gross from Power Diagnostics suggested that DC resistance

performed before and after test should show no change. He also

noted that a requirement be placed on the compartment containing

the selector switch not produce any combustible gas during the test.

Rainer Frotscher from Reinhausen noted that vacuum switching

makes no difference based on the current of the test, but some small

amount of combustible gas may take place during selector switch

operation.

Bertrand Poulin from ABB suggested that test should be proposed,

and then voted on once the proposed text was reviewed. He

suggested the Chair should put together the material, circulate the

suggestion before the next meeting and the members come to the

meeting ready for a discussion and acceptance.

7. New Business

• As the discussion of the details of the Load Tap Changer Performance Test Procedure took the entire meeting, there was no time for new business as the time for the meeting expired.

8. Adjournment

Bertrand Poulin motioned and Dan Sauer seconded that the TF adjourn as the meeting time expired, The motion was accepted unanimously, and the meeting was adjourned at 12:17 pm.

J.8.3 Working Group for Revision of C57.109

IEEE Guide for Liquid-Immersed Transformer Through–Fault-Current Duration

Vancouver, BC, Canada, October, 24 2016

Minutes of the Working Group Meeting The meeting was held on Monday October 24, at 1.45 pm and four of the nine members were present and therefore there was not a quorum. There were a total of 35 people present which consisted of 4 members and 31 guests. Eight guests requested membership.

Annex J

Page 10 of 31

The Working group reviewed comments that were submitted by the K16 Working Group on Revisions to C37.91 IEEE Guide for Protecting Power Transformers. The first comment provided by the K16 group was to make an editorial correction to consistently refer to the “times rated winding current” instead of “times rated current.” There was no discussion on this topic and therefore the recommendation was upheld and the change will be made. The next comment was regarding inconsistencies between the values in Table 2 and the associated plot in Figure 1. Raj Ahuja added to the discussion by suggesting that the working group examine the history and source for the values that were originally in Table 2 before agreeing to change the values per the K16 recommendation. The next comment by the K16 working group was regarding the term “symmetrical currents” in section 4.0. They requested that the term be changed to “symmetrical winding currents.” There were no objections or additional discussion and therefore the working group will make the change. The next topic was regarding the term “% transformer impedance” as found on Figures 2a, 3a, and 4. They requested that the term be changed to “% transformer short-circuit impedance.” There were no objections or additional discussion and therefore the working group will make the change. The next comment from the K16 working group was an editorial comment regarding the deletion of a sentence from section 4.3. It was determined that the sentence was removed by error and will be added back to the next draft. Discussion about the changes to Table 4 were discussed in great detail. The K16 working group recommended that the old values from Table 4 remain in the guide but perhaps in a different table for historical reference. The working group decided to include the old Table 4 as an informative annex. Some additional comments were provided by the PC37.91 working group that related to the usage of the C57.109 guide but not particularly about the content of the guide. The C57.109 working group determined that the chair would respond to their comments. The topics included fault durations in excess of 2 seconds, pre-fault conditions, and single-line to ground faults. Next the working group reviewed the redline version of the D1 draft. Raj Ahuja had a comment regarding the statement in section 4.1 regarding low current values that may be the result of overloads up to 3.5 times rated current. Raj stated that the 3.5 times rated current for an overload condition exceeds that of C57.91 and should be removed. Kushal Singh commented that distribution transformers that are only protected by fuses may experience current close to 3.5 times. It was then noted that section 4.1 refers to category I transformers and therefore Raj retracted his comment. It was agreed to leave the section unchanged. A motion was raised by Bill Griesacker to adjourn. Hemchandra Shertukde seconded the motion. The working group unanimously approved the adjournment. The meeting adjourned at 2:50pm. Respectfully submitted Vinay Mehrotra WG Chair

Annex J

Page 11 of 31

J.8.4 TF on Audible Sound Revision to Clause 13 of C57.12.90 - R. Girgis

Unofficial Minutes of fall 2016 Meeting of TF “Audible Sound Revision to Test Code C57.12.90”, in Vancouver, BC Canada

The TF met at 1:45 PM, on Monday, October 24, 2016. Chairman Dr. Ramsis Girgis presided over the meeting. Secretary Barry Beaster assisted with the administrative duties.

After the Spring meeting, the membership had been adjusted to 52 members. For meeting preparation, a meeting agenda along with the unapproved Spring 2016 minutes were circulated to all members and guests of the last meeting. A copy of the prior meeting attendance for the past six years was circulated to the members for any possible oversight in recording attendance.

The meeting was attended by 26 of the 52 members and 65 guests for a total of 91 persons; the largest in the records for this TF. A quorum was established by a review of the meeting rosters after the end of the meeting. The proposed agenda was presented with one addition after the preliminary mailing. This additional agenda item: “Need for an IEEE Noise measurement Application Guide”, was proposed by Bertrand Poulin at the spring meeting of the TF. The revised agenda was unanimously approved without change. The spring 2016 meeting minutes had no requested changes nor corrections and was unanimously approved. Since a quorum was determined after the meeting, the agenda and prior meeting minutes were officially approved.

There were nine requests for TF membership; which will be reviewed based on previous meeting attendance.

After the introductions, Chairman Dr. Ramsis Girgis presided over the technical portion of the meeting.

The first item of business was a presentation by Dr. Chris Ploetner on the status of the IEC Sound Measurement Standard and Application Guide. Both have already been published earlier in 2016. He also presented the similarities and the small differences between the IEEE and IEC Standards. Chris commented that both IEC and IEEE Standards are widely comparable and, due to some small differences between these Standards, that the maximum difference to be expected between the Sound level measured using the two Standards is within ± 1.0 dB. He also stated that the harmonization process will continue with a target to fully align sound level measurements in the two Standards. Chris recommended to the attendees to read the IEC Application Guide (IEC 60076-10-1) for educational purposes. The Chairman supported that and stated that the Application Guide has excellent tutorial information on both transformer noise and measuring transformer noise.

The next item on the Agenda was the development of “REFERENCE Load noise levels for single-phase power transformers”. The Chairman presented measured Load noise Sound Power levels received, as provided by a number of transformer manufacturers, at a wide range of rated MVA vs. calculated load noise using Reiplinger’s Equation for both 50 and 60 Hz transformers separately. The data again showed that measured values of load noise can be as much as 10 dB higher than the levels calculated using Reiplinger’s equation. Therefore, adding 10 dB to the calculated values would represent a reasonable calculated REFERENCE levels for load noise of single-phase transformers.

The next topic was an open discussion of the purpose of developing ‘REFERENCE Noise Levels’. For this discussion, the Chairman presented slides showing how measured and guaranteed no-load noise levels of a large number of transformers compare to the NEMA TR1 levels. The data demonstrated that these levels can have a spread of as much as 25 – 30 dB

Annex J

Page 12 of 31

from the NEMA TR1 levels. The Chairman then presented two possible objectives of establishing “REFERENCE Noise Levels”. One objective is to use them as a measuring stick to determine how much lower a guaranteed noise level of a transformer is from the REFERENCE level. The second possible objective is providing ranges of sound levels for No-load and Load Noise for certain transformer classes per the CIGRE WG plan. The Chairman stated that noise levels of Power transformers should be specified based on the required sound level at the first recipient or boundary.

The attendees were encouraged to participate in the discussion on the above. Joe Foldi supported the purpose of REFERENCE noise levels as a measuring stick to determine how much lower a guaranteed noise level of a transformer is from the REFERENCE level. He also stressed the importance of specifying the noise level based on the noise level required at the first recipient or boundary. Joe commented that it does not justify spending additional money for a transformer quieter than necessary. On the other hand, Robert Ganser indicated a concern that providing REFERENCE noise levels” could result in a possible drop in quality by some manufacturers that may get relief if the “REFERENCE noise levels” are set too high, as well as possible hardship for others. It was also suggested to introduce a note that the total noise of a transformer on site could be higher than the guaranteed level if the user does not consider load noise in the guaranteed value.

It was proposed that perhaps the term “REFERENCE” is not the appropriate wording. It was suggested that perhaps a wording like “Maximum Noise Level Limit” would be more appropriate. The Chairman then presented a preliminary wording for a note to be added to Table 17 of C57.12.00 explaining the objective of the “REFERENCE Noise levels”. This wording will be circulated to members of the TF, as well as to the guest participants, to review and propose any editing needed. The Note will read as follows:

Noise Levels given in NEMA TR1 Tables for No Load noise and in Appendix – C for Load Noise correspond to noise levels of designs where no special mean (s) of noise reduction is / are used / needed. The objective of these levels is to be used as a measuring stick to how much lower a guaranteed noise level of a transformer is from these maximum levels. Specifying the noise level of a transformer should be based on the required sound level at the first recipient / boundary.

At this point, Steve Antosz reminded the TF that there was a decision made in a previous meeting of the TF to add a new IEEE table to replace the NEMA TR1 Table. This table would be incorporated in Annex C and referred to in Table 17 of the C57.12.00 Standard.

The following new items were brought up by attendees:

Measuring noise level above the transformer cover as one customer has a need for this data

Effect of temperature on core noise and load noise. The Chairman commented that available test data shows an impact of temperature on core noise in the case of some core steels; while the effect of temperature on Load noise is small and could be either higher or lower since a large number of other factors influence the magnitude of this impact. A consequence is what temperature should transformer core and load noise be measured

What Tap position should transformer load noise be measured at?

There is a need to understand the cost impact of requiring low no load and load noise transformers

Annex J

Page 13 of 31

Introducing noise level on the transformer Name plate as transformers can be moved from one are to another

The Chairman suggested addressing these at the Spring TF meeting. In the meantime, the TF will attempt to collect the data needed for these items.

Time expired and the meeting concluded at 3:00 PM.

Respectively submitted,

Ramsis Girgis (Chairman) and Barry Beaster (Secretary)

J.8.5 WG on Non-sinusoidal Load Currents C57.110 - R. Marek

WG for Revision of C57.110

Sheraton Vancouver Wall Centre Hotel; Vancouver BC, Canada

Monday, October 24, 2016

3:15 PM – 4:30 PM

Chair: Rick Marek Secretary: Sam Sharpless

Administrative Call to Order and Introductions at 3:18 PM

Patent call: None reported

Attendance sheets passed out and introductions were made.

Quorum was achieved with 16 members and 38 guests

Approval of agenda with no comments

- Motion: Sasha Levin and seconded by Casey Ballard with unanimous

approval.

Approval of amended Spring minutes

- Motion: Sheldon Kennedy and seconded by Casey Ballard with unanimous approval.

Draft 4 Summary of changes

Chair sent out draft four with only a few changes:

- Revised Clause 6.2

- Added Annex F - Derivation of the ratio of highest winding eddy loss to

average

- Added Annex G - Sample transformer loss data

- Received one comment regarding units by Sasha Levin – Chair will

investigate Style Manual to determine proper formatting

Noted extra “for” in title that will be removed Reviewed section 6.2:

Annex J

Page 14 of 31

- As discussed in the Spring meeting, a note was added in a box to emphasize

that the loss values provided in the new table are conservative estimates.

- Ramsis Girgis noted that there is a large variation in eddy and stray losses for

power transformers and the table shows > 3MVA.

- The Chair stated that this document would not generally be used above 50

MVA, which was the upper limit in the scope of the original document. Also,

the losses in the new annex are all for distribution transformers. Ramsis

Girgis recommended a note not to use the table of loss estimates above 20

MVA.

- Motion: Ramsis Girgis to change the table from > 3000 to 3000-20 000 with

a note not to use the table above 20 MVA since these estimates do not apply

and it is suggested that the reader consult the manufacturer for specific loss

information.

- Eduardo Tolcachir suggested also adding the same caution to specialty

transformers.

- Motion: Don Ayers and seconded by Ramsis Girgis with unanimous

approval.

Appendix F reviewed:

- This annex addresses the basis for the statement in Clause 6.2.e: “The maximum eddy-current loss density is assumed to be in the region of the winding hottest spot and is assumed to be 400% of the average eddy-current loss density for that winding.”

- This statement has raised a number of questions over the years. The Annex is based on theoretical calculations for small transformers taken from a derivation by Max Cambre. - The Chair requested all to read the annex and comment.

Appendix G reviewed:

- This annex is a collection of winding eddy and stray loss data provided by the members in various formats. - The results are quite varied for different kVA’s and voltages, demonstrating the significant differences due to winding style.

The Chair asked for volunteers to check the four examples to make sure no errors were made in transcribing to the new document format. The results were requested by Thanksgiving.

- David Walker: 6.1.1 - Dhiru Patel: 6.3 - Eduardo Tolcachir: 6.1.2 - Javier Arteaga: 6.4

The Chair noted that he has received very few comments and the document is ready to go to ballot. The Chair asked for a motion to request PCSC approval to go to ballot

- Motion: Ramsis Girgis and seconded by Phil Hopkinson with unanimous

approval.

Annex J

Page 15 of 31

The Chair will send the updated document to the membership with a request for comments before submission to ballot. He also noted that the WG PAR expires Dec 31, 2018 but that we should finish well ahead of that time. No new business. Adjourn Motion: Phil Hopkinson and seconded by David Walker with unanimous approval

Adjourn at 4:00 PM.

J.8.6 WG on PCS Revisions to C57.12.00 - T. Ansari

October 24, 2016 4:45 PM Sheraton Wall Hotel

Vancouver, BC, Canada

UNAPPROVED MINUTES The PCS Working Group on General Requirements for C57.12.00 met on Monday, October 24, 2016. The Chair Tauhid Ansari called the Group to order at 16:45 and explained purpose and scope of the Task Force. Enrique Betancourt, the TF secretary, was not able to attend and Craig Stiegemeier recorded the minutes during the meeting. WG. 53 Members and 86 guests were present, and as Working Group membership stands at 76 members, we did have a quorum and were able to conduct official business.

The Agenda and the minutes from the Atlanta meeting were approved (Terry, Shem), with Mark Perkins noting that the agenda should reflect Task Force rather than working group. The agenda was corrected and there was unanimous acceptance of the corrected agenda. The minutes from the Atlanta meeting were (Sanjab Sohm, Terry) reviewed. In a vote of those attending, there was unanimous acceptance of the spring 2016 Atlanta minutes. Agenda Items were covered as follows. 1. OLD BUSINESS

A. WG Item 105, Sec.4.1, Sec.7.0 Clarification on Short circuit condition. Survey result, Survey Comments, & Discussion on topic

In Spring 2016, A motion was brought up (Ajit Varghesse/Vinay Mehrotra) as to include a statement in C57.12.00 specifying that for short circuit calculations 1.0 PU is the pre-fault voltage and that anything different has to be specified by user. The motion was amended by Mark Perkins to start first with a survey among the WG’s Membership about this proposal if this is to be discussed in TF C57.12.00.

A review of the comments from those responding to the survey was conducted. The chair sent a survey to 273, and 88 responded to the survey. The Result as follows:

Approve 58 66%

Annex J

Page 16 of 31

Approve with Comment 9 10%

Disapprove 5 6%

Disapprove with comment 9 10%

No comment 7 8%

Total 32% response 88

The approval comments were reviewed for those attending the meeting.

If we are considering real-life operating conditions for short-circuit conditions in the standards then the interconnected system should also be considered. The WG on C57.158 Guide for the Application of Tertiary and Stabilizing Windings in Power Transformers failed to consider the worst case condition for tertiary currents. This is for parallel auto-transformers when a single line-to-ground fault occurs with possible X/R ratios can produce more current in the tertiary than the infinite bus condition. The condition I am describing was the subject of a white paper written some years ago by L.S. McCormick (sic) of Westinghouse Electric which raised this concern.

- Wallace Binder

I think the discussion is good but vote for 1.0pu volts - Philip Hopkinson

Often times, pre-fault level becomes an issue at the stage of design review meeting. It would be better to state the condition somewhere in the current IEEE standard.

- Jinho Kang

A motion was brought up (Ajit Varghesse/Vinay Mehrotra) as to include a statement in C57.12.00 specifying that for short circuit calculations 1.0 PU is the pre-fault voltage and that anything different has to be specified by user

- Neil Kranich

Our transmission planning department is advising that portions of Ameren's system may see 110% as a maximum operating voltage. We believe that other utilities may be in a similar situation with the advent of renewable generation and the retirement of synchronous generators on their systems.

- David Ostrander

The discussion may shed more light on the issue hopefully by other users and suppliers to benefit the process. My personal opinion is that this should be made a requirement for Class II power transformers. 105% operating voltage is more typical for large GSU and auto transformers and would be a good level to use as a pre-fault voltage. The subject is covering the requirement in a major change wise and if not much response received here my suggestion is to go up to the WG or Sub-com level to get a wider response spectrum to help the process. This may not be allowed by the IEEE process but not being sure would like to add here for in-case type scenario.

- Bipin Patel

the requirement should be for 1.05 PU as this is defined as part of the transformer’s continuous operation capability per Section 4.1.6.1 of C57.12.00-2015

- Brian Penny

Annex J

Page 17 of 31

1.0p.u to be used unless specified by customer - Krishnamurthy Vijayan I believe this topic of pre-fault voltage for short circuit calcs should be discussed. I don’t believe we should require the level of margin discussed for ALL transformers which adds cost to applications that does not require it. I think it should be worded such that it is calculated at 100% but add some words that the user may want to increase to 105% or 110% pre-fault for additional margin at the time of tender by the customer.

- David Wallach

A review of those who disapproved was conducted.

TF would not be the place where the technical discussions should initially take place. Because short circuit tests become destructive tests if the device under test fails, a proposal to increase the applied energy level may have a substantial (and in many cases unnecessary) negative economic impact on both manufacturers and end users. I think that such a significant proposal should begin discussions in the Performance Characteristics Subcommittee itself. PCS can choose to deliberate the technical issue directly, or to assign it to your TF as a work item, or create a separate TF, or whatever. But to me it’s too big a question for the TF to handle without a mandate from the SC.

- Jeffery Britton

If there are some special considerations to be taken into account for the short circuit condition, those should be declared in the contract documentation (specifications, questionnaires, etc.), but not as a change to the standard.

- Juan Castellanos

This does not qualify for discussion. There is already a statement addressing this in 7.1.5.5(d) - Bruce Forsyth

This 110 % condition needs to be clarified and understood first. System voltages are generally limited to 105 %. Even the 500 kV system voltage that has a limit of 550 kV is truly ~ 5 % of the 525 kV reference transformer Voltage. GSUs also can not have more than 105 % of its rated Voltage, I do not think. Som there is a need for clarifications from Customers who buy GSUs and System transformers. It should not be an agree disagree vote until this whole thing about 110 % V is understood operationally. Only then one can decide what the right thing is.

- Ramsis Girgis

The voltage should remain 1.0 PU. The higher voltage is already specified in the standard as an application conditions requiring special considerations. That can be specified by the end user for this special condition without increasing cost of ALL transformers.

- Marion Jaroszewski

The 100% voltage condition has been used for many years and also is used in other world standards. If some particular utility wishes to add a special clause for prefault overvoltage, it can be addressed in their particular specification.(and many do already) Thus there is no need to add this topic to agenda

- Dennis Marlow

Annex J

Page 18 of 31

This should be discussed outside C57.12.00 - Stephen Oakes

Unless a pre-fault condition is specified, it is imperative that 1.0PU is used for short circuit force calculation. C57.12.00 adequately covers other conditions

- Dinesh Sankarakurup

100% voltage should be considered a base level, however the user may specify a higher pre-fault voltage, i.e. 110%. Rationale: I am not aware of a significant number of the short circuit failures in USA due to a weak design under current specification (i.e. 100% voltage).

- Waldemar Ziomek

Shedan CG Power – he has disapproved and still has the same opinion Vadim Rooter SPX – pre-fault condition needs to be clarified Joe Foldi clarified that the Canadian utilities have a strong opinion that the pre-fault condition needs to be 1.1 for the purposes of calculation of short circuit currents. Ed teNyenhuis – he noted that we can have this discussion as a part of PCS duties Joe Foldi suggested that we’re not prepared to have this discussion and maybe we should postpone to the next meeting. Bob Thompson – RST consulting noted that some transformers are overexcited. Ramsis Girgis noted that the voltage at the primary and secondary are limited to 5%. The excitation of the curve may be higher for certain types of transformers. Ramsis does not understand where the 110% comes from. He believes that a more basic question is to determine the basis of the 110%, as it’s an excitation issue and not a voltage issue. The 105% makes sense, as that is an actual operating voltage condition. Bob Ganzer – We have many customers that can run 110% for 24-36 hours to look at the quality. His belief was that this was a maximum value to avoid saturation and the resulting other problems, like heating. Bob noted that one could get into legal issues if the real operating voltage is not used. Mat Weise – PacifiCop asks for 105% Chris – Commonwealth Edison – they have seen conditions that during the summer when all capacitors are on and the load is decreasing when the voltage on 138kV goes up to 153kV. They then will turn on the cap banks. David Murry – TVA – the operating voltages are defined in defined in ASNI 48.1 Raj – C57.12.00 is the defining standard, and other guides also define the voltage. It should be left to the customer to call out differences. Abnormal conditions should be specified by the user. Jason Hornel – SPX – he agrees with Ramsis and Raj. Jason wants to change the working in Section 4.1.6. Guy from SMIT – Need to be careful what is changed – operating condition or service condition. This will cause an issue in low impedance high-voltage transformers. Neil Kranish – Jordan Transformer – short circuit calculations at 110% result in a stronger, bigger transformer. Not all customers want that. Sanjab Som – Siemens – this is a matter of margin Should a statement be added to the standard that the customer Chris Slatterly – FirstEnergy – they call out 110%, and they’re dealing with that 110% at a real operating condition. Black and Veatch – Need to specify the value Tauhid summarized that we should keep it at the current limit, but offer more clarification. Bob Ganser – suggested the differences between a standard and guide is that a standard must be a “shall”, where a guide offers a suggestion using “will” and “should” do something. The

Annex J

Page 19 of 31

standard is a default for protection of the transformer. Any value other than 105% at full load or 110% at no load must be defined by the individual users. Robert Thompson – asked if it makes sense that the user would be able to energize to 105% voltage, and not require that short circuit forces be calculated at that voltage. Mark Perkins noted that the TF agreed to consider the motion that 1.1pu is the pre-fault voltage. Matt Weisen – PacifiCorp is using 105%. They run their system at 105%. Shell Sain – ComEd – they don Jill Holmes – Bureau of Reclaimation – they operate at 105% and 110% of voltage. She suggested that we put Scott Digby – Duke – they do not set the operating tap to correspond to the voltage. They set it for other reasons – such as the making sure the LTC goes through neutral David Ostrander – Ameren – They operate parts of the system at 110% as a real operating condition. He’s wondering if other utilities are seeing these higher voltage levels. Upon majority in survey approved to keep the motion initiated by Ajit and Vinay, that 1.0pu be used as the pre-fault voltage and that any other value should be specified by the user. A vote was taken and 28 approval, 6 disapproval, 2 abstain. The next step is to survey the Subcommittee PCS before sending to ballot. Shamaun Hakim brought up a topic and it was decided to move this to discussion for the next meeting. 2. NEW BUSINESS The allocated time for the meeting was expended before any new business could be considered. 3. ADJOURNMENT

The meeting was adjourned at 5:30 PM. Respectfully submitted, Tauhid Ansari Craig L Stiegemeier for Enrique Betancourt WG Chair Secretary

J.8.7 Shunt Reactors C57.21 - S. Som

IEEE Standard Requirements, Terminology, and Test Code for

Shunt Reactors Rated Over 500 kVA C57.21

Vancouver, BC Canada

Sheraton Wall Centre Hotel

Tuesday October 25, 2016 The working group met in the Grand Ballroom AB of the Sheraton Vancouver Hotel on Tuesday October 25, 2016, at 9:30 AM.

The meeting was called to order at 9:30 AM by Chairman Sanjib Som There were a total of 72 participants: 13 Members and 59 Guests out of which 14 Guests requested membership.

Annex J

Page 20 of 31

The meeting was opened with the introduction of participants and the circulation of attendance roasters and call for potentially essential patents.

13 of the current 22 WG Members were present and quorum to carry out business was met. Meeting notes:

Meeting Agenda

• Meeting agenda, which was circulated among members and guests on October 12, 2016 by email, was presented to the audience.

• Motion to approve the agenda was made by Dharam Vir and seconded by Raj Ahuja.

• There were no objections or comments and the agenda was approved unanimously.

Minutes from previous meeting

• The minutes from the S16 meeting in Atlanta, which were circulated on October 12, 2016 by email, were presented to the audience.

• Motion to approve the agenda was made by Luc Dorpmanns and seconded by Arup Chakravarty.

There were no objections or comments and the S16 meeting minutes were approved.

Old Business: WG was advised that the PAR will expire in 2018. Work on the comments and draft for the standard revision will have to advance for prompt circulation among the WG members. This is the last WG meeting for general discussions.

1. Field Measurement for vibration: Joe Meisner to provide some examples and technical

background regarding field measurements, vibration test and vibration tracking over time

being easier to perform and also help troubleshoot installation problems with the foundation:

Joe Meisner was not present in the meeting and the chair will contact him by email.

2. Measurements be performed at rated MVA instead of rated voltage (Bertrand Poulin) referred

to working subgroup: work is on-going but not completed yet. Expected to be completed by

November 15, 2016; by which date Bertrand will send to the Chair.

3. Insulation class 150 or 155 for dry type – referred to working subgroup:

3.1. Table 3: The insulation temperature class in table 3 for dry-type shunt reactors was

discussed. Is it 150 or 155? Solomon Chiang pointed out that the proper denomination

is 155 as there is no 150 insulation class.

3.2. The table 3 needs a minor editorial change to center the DRY TYPE legend its column

for clarification. Other columns specify temperature rise limits.

Annex J

Page 21 of 31

3.3. No further clarifications required. Solomon Chiang will be asked to provide a write up on

insulation temperature classes.

4. Vibration level proposal by L. Dorpmanns: Presentation was done in previous meetings.

Inputs on the draft required.

5. Section 4 – Inputs from Gael Kennedy: inputs provided in the previous meeting.

6. Inputs from Dieter Dohnal: tap changer as applied to variable shunt reactors. Inputs from

Dieter were distributed to the WG on October 13, 2016, by email. Tap changer selection,

applications, bibliography are included. Input and comments required from the WG.

Subgroups as set by the Chair to work on different sections of the standard. The following members volunteered to work on:

Sections 1 through 4: Sanjib Som, A. Del Rio. Sections 5 through 9: Joe Meisner, Subash Tully, Rogerio Verdorin, Raj Ahuja. Adding Mike Spurlock and Mat Weisensee. Section 10: Bertrand Poulin, Shamum Hakim, Subash Tully, Klaus Pointner, Kris Ploetner Sections 11: Dharam Vir. Section 12: Mike Sharp Pictures, figures and drawings: Rogerio Verdolin. Adding: Sanjib Som, Art Del Rio, Kris Zibert. If anyone wishes to participate in the above groups or if anyone’s name is not included inadvertently in the list, please contact the WG Chair. Target for first draft completion and circulation by email is before the next meeting which will be Spring 2017. No new businesses were presented. Meeting was adjourned at 10:10 am.

Next meeting: Spring 2017, New Orleans, LA, April 2-6, 2017. Respectfully submitted, Chairman: Sanjib Som ([email protected]) Secretary: Arturo Del Rio ([email protected])

Annex J

Page 22 of 31

J.8.8 IEEE/IEC WG Wind Turbine Generator Transformers, P60076-16 - D. Buckmaster

WG P60076-16 Standard Requirements for Wind Turbine Generator Transformers Chairman: Phil Hopkinson; Secretary: Donald Ayers The Working Group on Wind Turbine Generator Transformers was called to order at 9:30 a.m. EST on Tuesday, October 25, 2016 at the Sheraton Hotel Wall Center in Vancouver, British Columbia. There were 89 attendees, 31 members present of a membership of 54 and 58 guests. A quorum was present. It was announced by the new Chairman that David Buckmaster, prior Chairman, has resigned from office due to health problems. A large thank you to David for his effort in propelling this standard forward. Our prayers and well wishes go out to David. The following guests requested Membership on the Working Group. After two consecutive meeting attendance they will become members. Javier Artega, ABB, Raleigh, NC Mark Gromlovits, EMC OEM Products Division, Bristol, VA Amitav Mukerji, Consultant, Cary, NC Rahul Palakandy, Black & Veatch, Overland Park, KS Alan Sbravati, Cargill, Campinas, Brazil William Solano, Siemens Energy, Pearl, MS Stephan Voss, Siemens, AG, Nuremberg, Germany David Walker, MGM Transformers, Commerce, CA Joshua Yun, CG Power Systems, Wildwood, MO Hemchandra Shertukda made a motion to accept the agenda for the meeting and was seconded by Rogerio Verdolin. The motion passed unanimously. Hemchandra Shertukda made a motion to accept the minutes from the Spring 2016 meeting and was seconded by Rogerio Verdolin. The motion passed unanimously. A call for patents was made and none were reported. The Secretary reviewed the comments from the second ballot recirculation with resolution status. New comments were not addressed under re-balloting rules. Of the 41 comments, two were rejected, five were identified as new comments and the remaining 34 comments were addressed as editorial and accepted. The standard document was then reviewed which showed the editorial changes in red. A motion was made by Rick Marek to accept the recommendations made on the comment resolution matrix. The motion was seconded by Rogerio Verdolin. The motion passed unanimously. A motion was made by John John to accept the modified standard made with the comments in red. The motion was seconded by Sukhdev Walia. Under discussion, Paul Jarman commented that the IEC editors were against the use of dual references in the document, but was working to getting the issue resolved. The last version of

Annex J

Page 23 of 31

the standard has not been recirculated as a CDV (Committee Draft to Vote). He is investigating whether present document can be circulated as both a CDV and Final Draft. It was reported by the Chairman that a question about the arc-flash information was raised at the IEC TC-14 meeting recently, but did not consider it an impediment to the standard. Joe Mango explained how his company analysed for arc-flash conditions and how they handle the transformer. The vote was unanimous to accept the modified document. A motion was made by Hemchandra Shertukda to send the modified standard out for a recirculation ballot. The motion was seconded by Rogerio Verdolin. Under discussion Masoud Sarifi commented on the complexity of creating a standard where there are many different parties involved. It was emphasized that the standard does not take away from special customer requirements. Sukhdev Walia gave a brief history of how the standard work began and the need. The question was raised as to what would happen if IEEE passed the ballot but the IEC has objections or comments. This question will be referred to IEEE for explanation. The motion for recirculation passed unanimously. With no new business, the meeting was adjourned at 10:25 a.m. Respectfully submitted, Donald E. Ayers Secretary

J.8.9 WG on Semi-Conductor Rectifier Transformers -C57.18.10 - S. Kennedy

Working Group on Semiconductor Power Transformers – C57.18.10

Unapproved Meeting Minutes

Sheraton Wall Center Hotel, Vancouver, BC Grand Ballroom AB

11:00 am, October 25, 2016 The Working Group met in the Grand Ballroom AB meeting room

There were 27 people present. 7 old members plus 5 new members and 15 guests present. The patent call was given. Nobody replied with any patent issues.

Annex J

Page 24 of 31

The minutes of the April, 2016 meeting in Atlanta were approved as written. Old Business

• Sheldon presented the approved PAR. Bill Whitehead to update draft standard with new scope from PAR.

• Want to harmonize with IEC standards as much as possible.

New Business

• Topics for discussion in new standard, Phase Shifted Windings, Electrostatic Shields, Interphase applications, Circuit Break Interactions and Snubbers, non-classical harmonics associated with new inverters and drives.

o Some phase shifted transformers are covered by patents. Standard will only cover general phase shifted windings rather than specific examples.

o Will mention circuit breaker interactions due to use of these transformer. However, this will be covered in detail elsewhere.

• Eddy Currents and Stray Losses. Paul Buddingh- Would like guidance on Eddy currents to remain in standard because it is an issue in the field. Eduardo Tolcachir - Need to keep division between eddy and stray losses to be able to calculate currents for testing. Rick Marek thinks simple percentages are dangerous to use for complicated rectifier transformers. John John- When harmonic information is available then we use information from customer. Not always available. Vijay Tendulkar- dual secondary’s with uneven loads can cause effect on heating. % values are ok for two winding but are not good for more complicated windings. Stephan Voss - For multiple winding transformers simple values are not good enough.

• Paul Buddingh - Suggested mentioning high resistance grounding can cause common mode noise problems in drive transformers.

• - IEEE has “rectifiers” while IEC uses “converter”. Why not change? Sheldon said that title of standard has rectifier listed but scope covers the more general case. Also, need to mention rectifiers could be in source as well as in the load.

With no further business, the meeting was adjourned at 11:55. The Working Group will meet again at the Spring 2017 meeting in New Orleans, LA

Chairman: Sheldon Kennedy Vice Chairman: Bill Whitehead Secretary: David Walker

J.8.10 WG Loss Evaluation C57.120 - R. Verdolin

Meeting Minutes Fall 2016 IEEE Transformers Committee Meeting — Vancouver, BC,

CANADA

Annex J

Page 25 of 31

PC57.120 LOSS EVALUATION GUIDE FOR DISTRIBUTION AND POWER TRANSFORMERS AND REACTORS

Tuesday, October 25, 2016 — (11:00 AM – 12:30 PM)

Chair: Rogerio Verdolin Vice-Chair: Rod Sauls (Rod was not able to attend the meeting) Secretary: Marcos Ferreira / Hamid Sharifnia

1. Attendance

a. Members: 14

b. Guests: 77

c. Guests granted membership: 4

d. Guests requested membership 7

e. Total (Members + Guests): 91

2. The meeting was called to order at 11:00 am on Tuesday, October 25, 2016.

3. Circulating the Rosters.

4. Call for Patents – No claims

5. Introduction was made.

6. Attendance was checked to see if a quorum was established. There were 24 active

members on the roster and at least 12 were needed for a quorum. There were 14

members present.

7. Agenda of meeting was approved.

8. A motion was made to approve the minutes of meeting from the Working Group Spring

2016 meeting in Atlanta, GA. The meeting minutes was approved.

9. Rogerio reported the results of the IEEE-SA sponsor ballot draft 15, Rev02 and draft 16.

10. The PC57.120 Draft 15, Rev02, went to ballot and had an excellent approval rate of 93%.

The minimum approval rate requirement to have the draft approved is 75%.

11. A Ballot Resolution Committee was created in order to review the comments: Rogerio

Verdolin, Rod Sauls, and Wallace Binder.

12. Conference calls were performed with the Ballot Resolution Committee to review the

comments from the ballot group: September 9th, 15th, and 19th 2016.

13. Before the chair recirculated the comments reviewed by the Ballot Resolution Committee,

the chair requested on September 19th, 2016 the endorsement from the members to

accept the changes to the document. More than 2/3 approval rate was obtained from

members.

14. Result of the recirculation of the comments: 100% approval rate.

15. The approved draft 16.1 will be sent to IEEE Standard Association RevCom for

submission.

16. No New Business

17. The meeting was adjourned at 12:30 PM

Respectively submitted, Rogerio Verdolin, Chair Marcos Ferreira / Hamid Sharifnia, Secretary

Annex J

Page 26 of 31

J.8.11 WG 3-ph Transf. Connections C57.105 - A. Bromley

Fall 2016 - IEEE Transformers Committee Meeting — Vancouver, British Columbia, Canada

IEEE / PES Transformers Committee Performance Characteristics SC

C57.105 – IEEE Guide for Application of Transformer Connections in Three-Phase Electrical Systems

Tuesday, October 25th, 2016 - (1:45 PM – 3:00 PM)

Chair: Adam Bromley Vice-Chair: Rogerio Verdolin

1. Attendance

a. Members: 13

b. Guests: 24

c. Guests requested membership 0

d. Total: 37

2. The meeting was called to order at 1:45 pm on Tuesday, October 25th, 2016.

3. A motion to approve agenda for the meeting was made. The agenda was approved

unanimously.

4. Call for patents were made by the Chair. Patents were not claim by members and

guests.

5. A motion was made by Samuel Sharpless and seconded by Said Hachichi to approve

the meeting minutes from the Working Group Spring 2016 meeting in Atlanta, GA. By

unanimous vote, the minutes were approved.

6. Par status: Par expires December 31st, 2019, which represents 4 meetings before we

have to conclude the guide. The PAR was approved March 2015. The draft has to go to

ballot the end of 2018. So we have to conclude our draft by fall of 2018.

7. The chair went through the comments provided my members and David Jacobson, from

Manitoba Hydro.

8. Chair has informed that he has to step out from the chair position due changes on his

position in his company and the chair will not be able to attend the meetings anymore.

Roger Verdolin and Benjamin Garcia will become the chair and vice-chair of the WG

C57.105 respectively.

9. Figures and Tables were updated.

10. Changes were made from symbols to texts, such as ∆ (Delta) Υ (wye). Additional

changes need to be done. Members stated that it is really difficult to read with symbols.

11. John John and Samuel Sharpless reviewed Sections 4 and 5, Electrical Connections

and Magnetic Circuits.

12. Group to review specific sections. Samuel Sharpless send his updated on Sections 4

and 5. The chair went through some specific sections. There are a lot of symbols to be

checked. Tables and Figures were relocated in different subsections in the draft. Section

4.5 - Connection Application Characteristics was added in the draft. The chair asked for

Annex J

Page 27 of 31

volunteer to review Section 4.6.1 - Terminal Designation. Charles Morgan volunteered to

review Section 4.6.1. Including the review the reference standards (maybe add new

standards, such pad mount transformers.

13. Maybe adding a diagram to clarify the connections. Samuel Sharpless volunteered to

review this topic. C57.12.10 will be used as a reference.

14. Section 4.4 T-T Connections was discussed. Charles Morgan supplied some further

information to help with developing possible figures regarding these connection types.

Giuseppe Termini also volunteered to provide some information to help add to this

section.

15. Section 5 – Magnetic Circuits was discussed. Some Figures were relocated in different

subsections.

16. A motion was made by Dan Mulkey and seconded by Thomas Callsen to approve the

revision on Section 5.3.1- Inrush Current Transient provided by David Jacobson. The

motion was approved by majority of the members.

17. The chair went through some additional comments and recommended all members to

review the changes provided by some of the members.

18. Charles Morgan offered to review Section 4.6.1 Terminal Designation.

Respectively submitted, Adam Bromley, Chair Rogerio Verdolin, Vice-Chair

J.8.12 WG on Distributed Photo-Voltaic Grid Transformers C57.159 - H. Shertukde

Unapproved Meeting Minutes Vancouver, BC, Canada

Tuesday, October 25, 2016 AGENDA 1. Roster and Quorum Verification 2. Meeting Agenda Approval 3. Call for patents. 4. Approval of the S2016 Atlanta Meeting Minutes 5. Update on the editorial review and publishing of the Guide 6. New Business 7. Dissolving of WG IEEE C57.159 The Working Group met in the Grand Ballroom CD of Sheraton Vancouver Wall Center Hotel. This was ninth meeting of the WG. The meeting was called to order at 1:45 pm by Chairman H. Shertukde. The meeting was convened with 35 participants present, 15 of them are members (this constitutes a quorum out of 28 current members in the roster). Meeting Agenda was approved. Spring 2016 Atlanta Meeting Minutes were approved.

Annex J

Page 28 of 31

Call for patents was made. No patent claims were presented. 1. Chair H. Shertukde updated WG that RevCom approved IEEE C57.159 Guide for publishing. We have finalized the process of the editorial review with minor editorial changes and the Guide is going to be published on November 3, 2016. The chair expressed thanks to the officers and members of the WG for their work and valuable contribution that allowed to complete the WG assignment on time. 2. There were no new business items proposed to the WG. 3. Chair has asked for a motion to dissolve WG C57.159, A. Narawane made a motion, M. Sauzay seconded the motion. WG approved the motion unanimously. With no more old or new business the Meeting adjourned at 2:15 PM. Chairman: H. Shertukde Vice-Chairman: M. Sauzay Secretary: S. Levin

J.8.13 TF on HV & EHV Transients C57.142 - J. McBride

Meeting Minutes IEEE / PES Transformers Committee

Performance Characteristics Subcommittee TF to Investigate the Interaction between Substation Transients

and Transformers in HV and EHV Applications Vancouver BC, Canada

Tuesday, October 25, 2016

3:15 PM – 4:30 PM

Grand Ballroom CD

Chairman – Jim McBride Secretary – Tom Melle

1) Welcome and Chair’s Remarks. TF objective presented: to prepare a report addressing the need to revise the C57.142 guide to extend to HV and EHV applications.

2) Circulation of Attendance Sheets

3) Initially Quorum was not achieved. It was noted that those members who had not attended two of the prior three meetings were moved to Guest status.

4) Status of TF Paper Submission • TF paper is ready for immediate submission after completion of formatting and

Annex J

Page 29 of 31

small editorial changes.

5) Discussion of Additional Topics for the C57.142 Revision – Topics were:

A) Incorporation of more mitigation techniques B) Include information on stress in the transformer due to the method of neutral

grounding - Waldemar Ziomek. C) Include information on reactor switching (C37.015 and C57.21) - Pierre Riffon D) Include information on upstream and downstream interactions in low power factor

and highly inductive circuits - Phil Hopkinson

6) Attendance was retaken: Total attendance was 87, with 25 Members and 62 Guests present. Quorum (25 of 44 members) was achieved. Eleven guests requested membership and 8 were granted based on attendance of 2 of the last 3 meetings.

7) Approval of Agenda and Spring 2015 Minutes

8) PAR Discussion continued and a motion was made by Phil Hopkinson to remove the statement indicating that Reactor Switching does not apply and include some information regarding effects of reactor switching. The motion was Seconded by Sanjib Som. Motion carried.

9) Xose Lopez-Fernandez reviewed CIGRE work on white box, black box, grey box modeling methods that are described in detail in the CIGRE brochure on interactions. One of the goals for the working group is to provide standardization of the format used to identify transformer requirements. Another goal is to create a way to link the system model to the transformer model in order to study and predict possible interactions.

10) Phil Hopkinson presentation - Discussion of Mitigation Methods, Factory Testing, and Field Service Conditions related to regarding the effect of High frequency transient from breaker operation on transformer (will be available on TF web page).

A) Discussion followed as to whether certain PD techniques or SFRA analysis being studied by CIGRE A2 may be used to help judge the immunity of impulsed windings.

B) Mark Perkins commented that some circa 1960’s core-form transformers with RC

snubbers attached failed in circuits where shell-form transformers did not. The design differences should be considered.

C) Phil Hopkinson suggested mitigation possibilities should include part-winding

arrestors

D) Bertrand Poulin provided information of a transient estimation study by IREQ for GSU’s in backfeed mode that resulted in predictive voltage distribution.

E) Further discussion centered around utilizing special termination impulse, special

design simulations, and adapting winding designs for “worst case” scenarios.

Annex J

Page 30 of 31

F) Phil Hopkinson stated that in his experience, standard switching impulse testing is not necessarily helpful in preventing these types of failures. Recommendations include “Front of Wave” (aka Steep Front, Fast Front, or FFSI, VFF).

11) The Chair commented that field measurements of the transients generated very near the transformer terminal many times have a much faster front than 1 micro-second.

12) Phil Hopkinson commented that a system load will dampen the oscillations and therefore shorting the non-impulsed windings is not necessarily an adequately strenuous test. Pierre Riffon added that special terminated lightning impulse can produce much higher stress in the affected winding and suggested stronger designs and improved testing.

13) Phil Hopkinson asked if a longer impulse tail time would be beneficial. Pierre Riffon suggested that it would not be as stressful as the other suggested methods.

14) Sanjib Som suggested including an analysis of the electrical circuit prior to design of the affected transformer(s).

15) Considering the importance of the discussion, the Chair suggested forming a survey group to collect additional information. The following members volunteered: Phil Hopkinson, Mike Spurlock, Hamid Sharifnic, Akash Joshi, Shekhar Vora

16) Motion to adjourn the meeting made by Sanjib Som and the meeting was adjourned at 4:30 PM.

Respectfully Submitted, Tom Melle, TF Secretary 10/25/2016

J.8.14 TF on short Circuit Criteria - S. Patel

MINUTES WG PC57.164,

Guide for Establishing Short Circuit Withstand Capabilities of

Liquid Immersed Power Transformers, Regulators, and Reactors

• WG met on Tuesday October 25th, from 4:45 PM in Jr. Ball Room CD

• Invitation was sent to all TF members and guests to attend the meeting

• 86 attended the first meeting, out of which 36 requested WG membership, which was accepted (Membership status will be reviewed after 3 meetings)

Annex J

Page 31 of 31

• Since this was first Meeting, No prior REVIEW & APPROVAL OF MINUTES was required

• Patent Disclosure statement was made

• Scope and status on approval of PAR was communicated

• Presentation was made by Shankar from KEMA lab on SC Testing of transformers in last 10 years

• Outline of the Sections of Draft Guide was reviewed – There was detailed discussions by few members on the content of few sections, and these topics will be included in the draft

• 12 members volunteered for working on the Draft

• Meeting adjourned at 6:02 PM

Annex K

Page 1 of 15

Annex K Power Transformers Subcommittee

October 26, 2016 Vancouver, BC Canada Meeting Time: 1:30 p.m.

Chair: Bill Griesacker Vice Chair: Kipp Yule Secretary:

K.1 Meeting Attendance

The Power Transformers Subcommittee met on Wednesday, October 26, 2016, at 1:30 PM. The attendance recorded indicated that 74 out of 113 members of the subcommittee were in attendance; a quorum at the meeting was achieved. A total of 225 individuals attended the meeting; 20 guests requested membership.

K.2 Approval of previous meeting minutes, and meeting agenda

The Chair presented the Agenda, Attachment K.2, and it was approved.

The Chair requested a motion to approve the Spring 2016 Atlanta meeting minutes. The motion was made by Dan Sauer and seconded by Marcos Ferreria, and the minutes were subsequently approved by unanimous vote.

K.3 Chair’s Remarks Joe Watson is stepping down from chair position, Bill Griesacker will assume chair responsibilities after the Vancouver meeting, Kip Yule will be Vice Chair and the secretary position will be filled.

K.4 Working group reports

K.4.1 Revision of C57.12.10 IEEE Standard Requirements for Liquid-Immersed Power Transformers – Gary Hoffman See details of meeting minutes in Attachment K.4.1. A quorum was achieved. A 30-day straw ballot was conducted following the Spring-2016 meeting; draft D2.0 was compiled and transmitted to the WG membership as a proposal to approve Draft D2.0 for IEEE Sponsor Ballot. The Chair discussed the decision to use the letter (email) ballot method to proceed “quickly” and desired to see if there was consensus to go to ballot and identify remaining issues. The Chair indicated that based on the results of this letter ballot it was his intent to request approval of the Power Transformers SC at the Wednesday SC meeting to go to sponsor ballot. There was discussion that the process was not following procedures including not allowing discussion, not addressing negatives adequately, and if a true consensus had been attained. A motion was made to re-open the draft to address the negatives, however this motion did not carry. Motion to send to IEEE for final mech. review and balloting was approved.

Annex K

Page 2 of 15

K.4.2 Revision of C57.93 IEEE Guide for Installation and Maintenance of Liquid-Immersed Power Transformers – Mike Lau See details of meeting minutes in Attachment K.4.2. The WG voted to form a taskforce to study the commonality between C57.93 and C57.152, regarding testing transformers before unloading and prior to placing on a pad. A straw ballot will be held regarding C57.93 draft version 1.4. A table of various electrical tests to consider performing while the transformer is under vacuum will be included in the document with a maximum test voltage of 100 VDC or 100 VAC.

K.4.3 Revision of C57.125 Guide for Failure Investigation, Documentation, Analysis and Reporting for Power Transformers and Shunt Reactors – W. Binder No meeting was held.

K.4.4 TF to Compare C57.131-2012 Standard for Load Tap Changers and IEC 60214-1 ED 2.0 for consideration of recommending adoption of IEC standard (Also WG 60214-2 Tap-Changer Application Guide) - Craig Colopy See details of meeting minutes in Attachments K.4.4.1. and K.4.4.2.

TF Comparison of IEC 60214-1 and IEEE C57.131: Chairman created a PAR for adopting IEC 60214-1 for revision of IEEE C57.131-2012. PAR is planned to be reviewed at the December or January 17 board meeting. A preview of the PAR by IEEE and IEC has brought into question the process of adopting an IEC standard which is not currently available. A working copy of 60214-1 from IEC has met some resistance. Axel Kraemer mentioned that with stability date of 2019 showing for the IEC 60214-1 document, work on a revision would likely begin after 60214-2 Tap-Changer Application guide is published, which would likely be in 2019. It is planned for a dual logo joint revision with IEEE. WG TC Application Guide IEC 60214-2: A recommendation was made to change LTC to OLTC as most joint IEEE-IEC documents have done. IEC CD and IEEE Ballot are planned in Q3, 2017, with a CDV to follow likely before the end of 2017. Next meeting planned for Q1 2016.

K.4.5 C57.140 Guide for the Evaluation and Reconditioning of Liquid-Immersed Power Transformers – Paul Bowman See details of meeting minutes in Attachment K.4.5. Draft 7 ballot results were reviewed and resolution of items discussed. The comment spreadsheet will be sent out (draft 7) for review and electronic ballot by the WG. A simple majority will be needed to recirculate Draft 7 to the Sponsor Ballot pool

K.4.6 C57.143 – Guide for Application of Monitoring Equipment to Liquid-Immersed Transformers and Equipment – Mike Spurlock Mike Spurlock will be the new working group chair to start work on the next revision of the guide. The document was published in 2012 and the next revision is due in 2023. The work will be started somewhat early since this technology changes rapidly.

K.4.7 Revision of C57.148 Guide for Control Cabinets for Power Transformers The PAR for revision of the control cabinet guide, C57.148, was approved on 6/30/2016 and is valid until the end of 2020. A motion was approved to conduct a straw ballot within the Working Group to solicit comments and recommend changes for all sections of the document. General

Annex K

Page 3 of 15

questions will also be included with the Straw Ballot to find out how widely the standard is being used and how familiar Users (utilities, manufacturers, consultants, control cabinet suppliers, etc.) are with the Standard.

K.4.8 Revision of C57.150 Guide for the Transportation of Transformers and Reactors Rated 10,000 kVA or Larger – Greg Anderson Will submit a PAR for revision. Will meet in New Orleans to start on revising guide.

K.4.9 Development of PC 57.153 Guide for Paralleling Transformers - Tom Jauch No meeting was held.

K.4.10 Development of PC57.156 Guide for Transformer Tank Rupture Mitigation of Liquid-Immersed Power Transformers and Reactors - Peter Zhao Working group did not meet.

K.4.11 Development of PC57.157 Guide for Conducting Functional Life Tests for De-Energized Tap Changer Contacts - Phil Hopkinson Working group did not meet.

K.4.12 Development of Standard Requirements for Phase Shifting Transformers - IEEE/IEC 60076-57-12 - Raj Ahuja No meeting. Work was completed in February of 2016. IEEE approved the document. The Draft can be published once IEC gives approval.

K.5 Old Business The PTSC will sponsor a tutorial on LTC testing techniques since there is a perceived need for an LTC field testing guide. Craig Stiegemeier is leading and helping organize this effort. A meeting was held in Vancouver with interested parties to coordinate the panel speakers for the tutorial. Others are requested to participate that have a testing technology that they would like to introduce or discuss. It was requested that those interested in working on a taskforce to investigate if a section on Volts per Hertz should be added to C57.116 give their name. Ramsis Girgis expressed interest in this work.

K.6 New Business A taskforce was formed to provide a recommendation if a working should be formed to write a transformer condition assessment standard guide. Brian Sparling is leading the taskforce and plans to hold a taskforce meeting before the next PTSC meeting. Joe Watson wants to form a task force to come up with a standard template for working group meeting minutes.

K.7 Adjournment The meeting adjourned as scheduled.

Annex K

Page 4 of 15

K.8 Attachments –Working Group Meeting Minutes and Agenda Attachment K.2 – S16 PTSC Agenda Attachment K.4.1 – PC57.12.10 Standard Requirements Attachment K.4.2 – PC57.93 Installation Guide Attachment K.4.4.1 – TF IEC 60214-1 / IEEE C57.131 Tap Changer harmonization Attachment K.4.4.2 – WG 60214-2 IEC Tap Changer Part 2 Application Guide Attachment K.4.5 – PC57.140 Evaluation and Reconditioning Guide Attachment K.4.6 – PC57.148 Control Cabinets

Annex K

Page 5 of 15

Attachment K.2

AGENDA IEEE Transformers Committee / Power Transformers Subcommittee

Wednesday, March 23, 2016, 1:30-2:45 PM Sheraton Atlanta Hotel, Capital Ballroom, Atlanta GA, USA

Joe Watson – Chair, Bill Griesacker – Vice Chair, Kipp Yule - Secretary 1. Call to order 2. Introduction and distribution of attendance

sheets 3. Determination of a quorum 4. Approval/correction of the spring 2015 minutes

5. Report from the Administrative Subcommittee meeting

6. New Business 7. Working Group and Task Force report

Project Title Chair IEEE/IEC 60076-57-1202

Development of Standard Requirements for Phase Shifting Transformers (PAR to 12/31/2016) *

Raj Ahuja

C57.12.10

Revision of IEEE Standard Requirements for Liquid-Immersed Power Transformers (Next revision due 9/30/2020, PAR to 12/31/2019)

Gary Hoffman

C57.17 Revision of Requirements for Arc Furnace Transformers (Published in 2012, next revision due in 2022) *

Robert Ganser

C57.93 Revision of IEEE Guide for Installation and Maintenance of Liquid-Immersed Power Transformers (Published in 2007, next rev. due in 2018, PAR to 12/31/2016)

Mike Lau

PC57.116 Revision of Guide for Transformers Directly Connected to Generators (Published in 2014, next revision due in 2024) *

Gary Hoffman

PC57.125 Revision of Guide for Failure Investigation, Documentation, Analysis and Reporting for Power Transformers and Shunt Reactors (Published in 2015, next revision due in 2025) *

Wallace Binder

C57.131 IEC 60214-1 IEC 60214-2

IEEE Standard Requirements for Load Tap Changers – Joint IEEE/IEC revision Craig Colopy

C57.135 IEEE Guide for the Application, Specification and Testing of Phase-Shifting Transformers (Published in 2011, next revision due in 2021) *

Jin Sim

PC57.140 Revision of Guide for Evaluation and Reconditioning of Liquid-Immersed Power Transformers (Published in 2006, next revision due in 2018) (PAR to 12/31/2017)

Paul Boman

C57.143 Guide for Application for Monitoring Equipment to Liquid-Immersed Transformers and Equipment (Published in 2012, next revision due in 2023) *

Donad Chu

C57.148 Standard for Control Cabinets for Power Transformers (Published in 2011, next revision due in 2021)

Joe Watson

C57.150 Guide for the Transportation of Large Power Transformers and Reactors (Published in 2012, next revision due in 2022) *

Greg Anderson

PC57.153 Development of Guide for Paralleling Transformers (Published in 2015, next revision due in 2025) *

Tom Jauch

PC57.156 Development of Guide for Transformer Tank Rupture Mitigation of Liquid-Immersed Power Transformers and Reactors (PAR extended to 12/17) *

Peter Zhao

PC57.157 Development of Guide for Conducting Functional Life Tests for De-Energized Tap Changer Contacts (Published in 2015, next revision due in 2025) *

Phil Hopkinson

IEEE 638 Revision of IEEE Standard for Qualification of Class 1E Transformers for Nuclear power Generating Stations (Published in 2013, next revision due in 2023) *

Craig Swinderman

* No meetings were scheduled during this time for these documents

Annex K

Page 6 of 15

8. Old Business 9. Collection of Attendance Sheets 10. Adjournment

Annex K

Page 7 of 15

Attachment K.4.1

PC57.12.10 - WG for the Revision of IEEE Standard Requirements for Liquid-Immersed Power Transformers

8:00 to 9:15 AM, October 25, 2016 Sheraton Vancouver Wall Centre Hotel, Vancouver, CA

Unapproved Meeting Minutes

WG Chair Gary Hoffman called the meeting to order at 8:02 a.m., Tuesday, October 25, 2016, with WG Vice-Chair Brian Penny and WG Secretary Scott Digby also present. Introductions were made and rosters circulated.

Total Attendance 137 Members in Attendance 40 (out of 56 members, quorum was achieved) Guests in Attendance 97 Guests Requesting Membership 16 (9 meeting membership eligibility requirement of

attendance at 2 consecutive meetings)

Guests Requesting Membership: Membership

granted? Membership

granted?

Vladimir Abril No Terence Martin No William Boettger Yes Rashed Minhaz No Hugo Flores Yes Fabian Stacy No Anthony Franchitti Yes Roy Su Yes Saurabh Ghosh No Olivier Uhlmann No Josh Herz Yes Jason Varnell Yes Jill Holmes Yes Trenton Williams Yes Weijun Li Yes Joshua Yun No

Additional guests that were eligible for membership, having met the eligibility requirement of attendance at 2 consecutive meetings, but did not request membership: Donald Ayers, Jeremiah Bradshaw, Jean-Francois Collin, Michael Craven, Eric Davis, James Graham, Shamaun Hakim, Shawn Luo, Joe Nims, Jow Ortiz, David Ostrander, Ulf Radbrandt, Sergiy Razuvayev, Steve Schappell, Yukiyasu Shirasaka, Andre Shor, Andrew Steineman, Gregory Stem, Shankar Subramany, Christopher Sullivan, and Barnes Wilson. The agenda was reviewed and a motion to approve was made by Eduardo Garcia and seconded by Ewald Schweiger, which was approved by unanimous consent. The minutes to the Spring-2016 meeting of this WG had been circulated to the WG membership and guests prior to the meeting and a motion to approve was made by John K. John and seconded by Ryan Musgrove. The motion passed by unanimous consent. The Chair made the requisite Call for Patents and there were none noted by those present. During the Chair’s remarks, the Chair expressed thanks to the working group and task forces for the activities since the Spring-2016 meeting in Atlanta and proceeded to discuss the activities that had been completed. A 30-day straw ballot had been executed immediately following the Spring-2016, resulting in approximately 300 comments which were in turn forwarded to the respective clause TF Chairs to resolve. At the conclusion of the resolution of the comments by the TF’s, Draft D2.0 was compiled and transmitted to the WG membership as a proposal to approve Draft D2.0 for IEEE Sponsor Ballot. The WG membership was provided the time period of September 22nd thru October 22nd to review the draft and vote on the proposal. The Chair discussed the decision to use the letter (email) ballot method, citing the Policies and Procedures manual as stating for WG’s to proceed “quickly” and desired to see if there was consensus to go to ballot, or in the process identify the remaining issues. The results of the letter ballot are as follows:

Votes received 35 out of 56 members 62.5% (quorum achieved) Approve 29 82.9% (2/3 majority, or super-majority,

achieved) Disapprove 6 17.1%

The Chair indicated that based on the results of this letter ballot it was his intent to request approval of the Power Transformers SC at the Wednesday SC meeting to go to sponsor ballot. The Chair encouraged attendees to become members of the ballot pool, emphasizing that they must be members of the IEEE Standards Association in order to do so. Clarification was also stated that

Annex K

Page 8 of 15

comments received during the balloting process must be responded to, with accepted comments going in verbatim into the document but rejected comments receiving an explanation.

Don Platts made a Motion, which was seconded by Sue McNelly, to re-open Draft D2.0 for discussion, thus nullifying the letter ballot to approve for IEEE sponsor ballot.

Don discussed reasons for this motion, stating as reasons failure to follow Policies and Procedures manual, failure to implement material documented in the minutes, terminology changes that had been made, and statements in the document that were changed to “or” statements, creating a type of “menu” not typical of a standard document. Upon request by the WG Chair for additional detail regarding procedural errors, Don stated that Task Forces that are formed are obligated to report back to the WG. The Chair indicated that this was accomplished by way of the letter ballot. Don countered that this process allowed for no discussion, again stating that the TF work needs to be approved by the WG. The Chair stated in opposition to Mr. Platts’ statement that the comment resolution and a revised draft was shared with the WG and Letter Ballot was approved.

Steve Antosz noted that 6 WG members had disapproved the proposal to approve the draft for sponsor ballot and asked what comments were made. The Chair said that should not matter and stated the concept that one person cannot hold up the process.

The motion was called to vote, with the following results: Approve 15 Disapprove 15 + Chair 16 Abstain 9

The motion did not carry. Joe Watson asked whether the Mandatory Editorial Review had been completed. The Chair said not yet, as were waiting for the approval to submit for sponsor ballot before doing so. Steve Antosz expressed concern with this process and that there seemed to be question among the WG as to whether consensus had truly been obtained. The Chair’s response was that the request for approval for Sponsor Ballot gave the WG Members the opportunity to see how the draft was revised and that the Sponsor ballot process that requires a much higher bar of 75% approval would vet this concern. Under New Business, Ronnie Minhaz requested clarification concerning section A.1.2 (VFVV OLTC regulation) around the interpretation of the phrase that the HV system voltage is presumed to be relatively constant therefore the flux density being variable when the LTC is located in the HV. There was some clarifying discussion provided by David Geibel and Sanjay Patel, clarifying that the standard has to assume voltage is stable before considering the effect on the transformer, that the nameplate voltage values set the basis (thus when HV turns change the volts/turn and thus the flux density change), and that the nameplate values are no-load based values. It was noted that the next WG meeting would be in the spring during the IEEE Transformers Committee meetings in New Orleans. The meeting was adjourned at approximately 8:45 a.m. Respectfully Submitted, Scott Digby, WG Secretary

Annex K

Page 9 of 15

Attachment K.4.2

Working Group to Installation of Power Transformers C57.93 Monday, October 24, 2016

1:45 – 3:15 PM Capital Central Ballroom

Sheraton Hotel, Vancouver, BC Chairman Mike Lau Vice Chairman Alwyn VanderWalt Secretary Scott Reed The meeting was called to order at 1:45 am by Chair Mike Lau. There were 14 of 24 members present. There were 58 guests, 18 guests requesting membership and 53 visitors requesting to become a guest. A membership quorum was achieved. Guests attending the WG meeting for the first time who request membership or who have not attended 2 meetings in a row (including the present meeting, will be deferred until the next meeting attended. Agenda

1. Attendance Roster Sign In / Quorum Check

2. Approval of the Agenda

3. Approval of the Spring 2016 minutes

4. Items of Discussion:

-Maximum Oil Temperature during transformer dryout – Consideration on depletion of

oxidation inhibitor content

- Vacuum/Temperature limit for natural ester fluid during dryout? - C57 152 (Field Test Guide) reference this Guide for installation acceptance test. Do we need to add any acceptance test before unloading?

- Removal or retention of informative safety items. - Any other outstanding comments for discussion

5. Straw Ballot amongst WG members on Version 1.4 6. Unfinished Business 7 New Business

Due to the time constraints, attendees did not introduce themselves. The Fall 2016 Agenda was approved and the Spring 2016 Minutes were approved. Chairman Lau posted the Patent Claim. No notifications or comments were received.

Annex K

Page 10 of 15

Chair’s Remarks:

After discussion regarding the potential loss of inhibitor during the vacuum dryout of a new transformer or an in-service transformer, a motion was made motion was made by Larry Christodolou to automatically add inhibitor to 0.3% by weight after the completion of the vacuum filling and or hot oil circulation. Derek Baranowski seconded the motion and the motion carried.

There was discussion regarding testing a transformer before it is unloaded and prior to placing on a pad. Sue McNelly made a motion to establish a Task Force to study commonality between C57.93 and C57.152. Ewald Schweiger seconded the motion and the motion carried. Alwyn VanderWalt agreed to chair the study group.

The committee decided to remove all information related to safety notifications. A straw ballot will be held regarding C57,.93 draft version 1.4. Under Unfinished Business, Chuck Sweetser presented a table of various electrical tests to consider performing while the transformer is under vacuum. It was decided to include the table as part of the document with a maximum test voltage of 100VDC or 100VAC. Under New Business, Ismail Guner is proposing a guide for best practices for asset management. The Scope of proposal will include inspection, diagnosis, and maintenance of transformers. The meeting was adjourned at 3:03 pm.

Page 11 of 15

Attachment K4.4.1

Document #: TF Comparison of IEC 60214-1 and IEEE C57.131

Document Title: Tap-Changers

Chair: Craig A. Colopy Vice-Chair Axel Kraemer

Secretary Adam M. Sewell

Current Draft Being Worked On: NA Dated: NA

Meeting Date: 25 October 2016 Time: 13:45 to 15:00

K.9 Attendance: K.10 Members 22

K.11 Guests 41

K.12 Guests Requesting Membership

0

Total 63

Meeting Minutes / Significant Issues / Comments:

1. Meeting was called to order at 1:45 pm, October 25, 2016. 2. Chairman created a PAR for adopting IEC 60214-1 for revision of IEEE C57.131-2012. PAR is planned

to be reviewed at the Dec or Jan 17 board meeting. A preview of the PAR by IEEE and IEC has brought into question the process of adopting a IEC standard which is not available at this time. A working copy of 60214-1 from IEC has met some resistance.

a. Erin Spiewak (IEEE-SA) spoke about the reason why PAR was meeting resistance currently. Even though there is a process for adopting an IEEE standard into IEC, there IS NOT an approved process in place for IEEE to adopt an IEC standard. Discussions between IEEE and IEC about this process of adoption are scheduled to be discussed in January 2017 according to Erin.

b. This TF will not become a WG until the PAR is approved 3. Axel Kraemer mentioned that with stability date of 2019 showing for the IEC 60214-1 document, work

on a revision would likely begin after 60214-2 Tap-Changer Application guide is published, which would likely be in 2019. It is planned for a dual logo joint revision with IEEE.

4. Meeting closed at 2:30 pm.

Submitted by: Craig A, Colopy Date: 10/25/16

Page 12 of 15

Attachment K.4.4.2

Document #: WG TC Application Guide IEC 60214-2

Document Title: Tap-Changers

Chair: Craig A. Colopy Vice-Chair Axel Kraemer

Secretary Adam M. Sewell

Current Draft Being Worked On: NA Dated: NA

Meeting Date: 25 October 2016 Time: 15:15 to 16:30

K.13 Attendance: K.14 Members 18

K.15 Guests 39

K.16 Guests Requesting Membership

0

Total 57

Meeting Minutes / Significant Issues / Comments: 5. Meeting was called to order at 3:15 pm, October 25, 2016. 6. Chairman provided the WG a background relating to the work being done to adopt the IEC standard

60214-1 as a dual logo document preserving main technical differences between C57.131 and 60214-1 in an Annex. Annex E of C57.131 is included within the latest draft of 60214-2, Tap Changer Application Guide.

7. The latest document draft 6WD of 60214-2 was presented to the WG by Axel Kramer. The draft showed highlighted text which was reviewed at the last meeting in Dresden, Germany and showed red text for any changes to the draft done in Dresden, Germany. Some comments were made by the WG:

a. Page 8-Introduction – add ‘tap-changer’ in front of manufacturer – Axel Kraemer b. Section 11 – Storage – Axel Kraemer to work on changing title c. Paul Jarman requested to see information on manual operation of OLTC’s. Section 13.2.1 of the

draft was displayed showing information about manual operation of OLTC’s. d. Paul Jarman made a comment that OLTC instead of LTC should be adopted. The chairman

commented use of OLTC has been preferred for implementation in majority of joint IEC/IEEE documents where applicable.

8. IEC CD and IEEE Ballot are planned in Q3, 2017, with a CDV to follow likely before the end of 2017. 9. Future Work Sessions:

a. Vancouver, BC Canada, Oct. 27, 2016, 1-5PM, IEEE Transformer Committee meeting b. 1st Quarter 2017, – TBD

10. Meeting closed at 4:30 pm. Submitted by: Craig A, Colopy Date: 10/25/16

Page 13 of 15

Attachment K.4.5 Unapproved Meeting Minutes from Guide for the Evaluation and Reconditioning of Liquid Immersed Power Transformers PC57.140

Meeting was held in Vancouver, BC, Canada, from 3:45-6:00pm October 24, 2016 Chairman: Paul Boman Vice Chairman: Brian Sparling

There were 21 of 64 members present. There were 52 guests present. A membership quorum was not achieved. The WG does not plan to meet at the Spring 2017 Transformers Committee Meeting in New Orleans, Louisiana.

A motion to approve the Fall 2016 Vancouver Agenda was made by Eric Davis and seconded by Roger Verdolin. However, since there was not a quorum, no vote was recorded. There were no objections or additions to the agenda.

Patent disclosure announcement: The Chair asked if there were any individuals that were aware of any patent claims might be Essential Patent Claims. The following statement was read during the meeting:

If any individual believes that Patent Claims might be Essential Patent Claims, that fact should be made known to the entire working group and duly recorded in the minutes of the working group meeting.

There were no patents claims identified. Details on patent information can be found at:

https://development.standards.ieee.org/myproject/Public/mytools/mob/slideset.pdf

Introduction of members and guests were made.

Minutes from previous meetings were provided to the Working Group in advance of the meeting. There were no corrections identified. Since there was no quorum, no motion to approve the Spring 2016 Minutes was made during the Meeting.

The Chairman provided a summary of the Draft 7 ballot.

Page 14 of 15

Most of the comments were editorial in nature.

Ballot Comment from Don Platts: Technical – Section 5.1.1 - Grammar will be corrected.

Ballot Comment from Mario Locarno: Technical – CIGRE picture in Section 5.5.1.

Ballot Comment from Nancy Frost: Editorial – Rewrite Section 5.5.1.

Ballot Comment from George Frimpong: Technical – Copy write issue in Section 5.4.2.

Ballot Comment from Various: Technical – Table 1. Mario Locarno indicated that there is nothing in the table for exciting current or FRA.

Ballot Comment from Rabiz Foda: Technical –Section 5.10.1. – Recommended tests to identify internally generated noise to be considered for inclusion. The Chair asked if anyone was familiar with the proposed inclusion of special tests for identification of internally generated noise. No one indicated any familiarity with the testing that would be done. The Chair will talk to the commenter to request additional information on whether this has been done previously.

Ballot Comment from Alexander Kraetge: Editorial –Section 5.7. – No comments or discussion.

Ballot Comment from Alexander Kraetge: Editorial –Section 5.7. – No comments or discussion.

Ballot Comment from Gary Hoffman: Editorial – Table 4 – The RIP and OIP in parentheses need to be defined. This will be corrected.

The comment spreadsheet will be sent out (draft 7) for review and electronic ballot by the WG. A simple majority will be needed to recirculate Draft 7 to the Sponsor Ballot pool.

Meeting was adjourned at 5:14PM.

Respectfully Submitted, Paul Boman, Chairman

Page 15 of 15

Attachment K.4.6 Revision of C57.148 Guide for Control Cabinets for Power Transformers Joe Watson: Chair, Weijun Li: Vice-Chair, Jean-Francois Collin: Secretary The working group met at 11:00 AM on October 24th, 2016 in Junior Ballroom C-D at the Sheraton Wall Centre Hotel in Vancouver, BC, Canada. 58 attendees were recorded. It was the first official Working Group meeting for this project. All meeting attendees were eligible to join the WG and since all members were in attendance, a quorum was reached. The complete attendance record is available in the AM System. 23 guests were granted membership. The meeting started with the approval of Atlanta Spring 2016 Task Force meeting minutes. There were no recommended changes and the minutes were approved. The revised meeting agenda with added Patent claim section was approved. The Patent question was asked and no essential patents were claimed. The Chair noted that the PAR was approved on 6/30/2016 and is valid until the end of 2020. The occurrence of numerous statements in the Standard saying “unless otherwise specified” was discussed with the suggestion that this could be added as a general statement instead of duplicating it all over the standard document. During the previous meeting of the Task Force to determine whether a revision was required, some Task Force members volunteered to review sections of the standard. The volunteers did not present reports, but Ryan Musgrove raised the question of whether the Standard was being widely used, and specifically how many utilities or manufacturers are using the current standard or are aware of the Standard. The group discussed polling Manufacturers and Users with these questions, but Gary Hoffman made a recommendation to do a straw ballot within the Working Group to solicit comments and recommend changes for all sections of the document. The motion was made by Gary Hoffmann and seconded by Rob Ghosh and approved unanimously. General questions will be also included with the Straw Ballot to find out how widely the standard is being used and how familiar Users (utilities, manufacturers, consultants, control cabinet suppliers, etc.) are with the Standard. The Chair stated that the Standard was not presented to the Committee with a Tutorial, which is the current practice now, and that this would have introduced the Standard to more Users. In light of this, the group should present a tutorial for this revision after it is successfully balloted. The Chair commented that C57.148 doesn’t have an objective to propose unnecessary requirements on the manufacturers. And reminded the group that each section of the document is open for discussion, and that comments need to be specific and not just general statements such as “this section needs to be reworded”, etc. This WG is open to other suggestions such as what else should be or shouldn’t be included in the standard. The Chair proposed a schedule for the straw ballot: 30 days to review. Officials will review the straw ballot results and categorize all comments. Results will be discussed at the next meeting and Task Forces will be formed to address the Straw Ballot comments. A working copy of the Standard has been requested from IEEE and will be posted on the Power Transformers Subcommittee web page on the Transformers Committee site before the straw ballot can start. The group will meet again in New Orleans, Louisiana in April 2017. The meeting was adjourned at 12:00 PM.

Page 1 of 4

Annex L Standards Subcommittee – Unapproved Minutes

October 26, 2016 Vancouver, BC Canada Chair: Jerry Murphy Vice Chair: Kipp Yule Secretary: Daniel Sauer Standards Coordinator: Jim Graham

The Chair, Jerry Murphy opened the meeting calling a show of members to establish quorum which was met.

L.1 Meeting Attendance

The Standards Subcommittee met on Wednesday, October 26, 2016, at 4:30 PM in the Junior Ballroom CD. A show of hands indicated only 17 of 35 members in attendance falling short of quorum at the starting time of the meeting. Quorum was achieved later with arrival of additional members. Overall the attendance roll showed there were 89 attendees, 22 members, 64 guests, including 13 that requested membership. Upon tabulation of the circulated rosters they will be reviewed for eligibility. Steve Shull moved to approve the fall 2015 minutes with second by Steve Antosz; motion was carried with unanimous acclamation approving. Jerry then requested a review of the Agenda which was updated to on section 5.3; motion was made by Steve Shull and seconded by Steve Snyder which was carried unanimously.

L.2 Chair’s Remarks

Jerry welcomed the attendees to the final sub-committee meeting of the day and reviewed our process regarding membership requests. The chair further stated that the roster would be reviewed for further updates based on attendance at this meeting.

L.3 Standards Coordinator’s Report – Jim Graham Jim’s report is on file.

L.4 http://www.transformerscommittee.org/meetings/F2016-Vancouver/Minutes/F16-StandardsReport.pdf

L.5 Working group reports

L.5.1 Continuous Revision of C57.12.00 – Steve Snyder The purpose of this WG is to compile all the work being done in various TF/WG/SC’s for inclusion in the continuous revision of C57.12.00 in a consistent manner. This WG coordinates efforts with the companion Standard C57.12.90 so that they publish together. The current standard was approved by the IEEE-SA Standards Board on December 5, 2015, with an official publication date of May 12, 2016. The standard is good for 10 years, but is under continuous revision and will be next balloted when sufficient new material is available.

Respectfully submitted by Steven L. Snyder, WG Chair, on October 26, 2016

Annex L

Page 2 of 4

L.5.2 Continuous Revision of C57.12.90 – Steve Antosz This is a working group by committee of task forces, for continuous revision of C57.12.90. The purpose of the WG is to keep track of the work being done in various TF/WG/SC’s for inclusion in the continuous revision of C57.12.90 in a consistent manner.

Summary The new Standard C57.12.90-2015 was approved by the Standards Board on December 15, 2015. It was published on March 11, 2016 as IEEE Std C57.12.90-2015.

Status Since this is a continuous revision document, there continues to be ongoing work in the various Task Forces. No new material has yet been submitted for the next revision. Shortly after the document was published in March 2016, it came to Steve’s attention that there was one error and one omission in the document. • There is an error in Equation (2) in subclause 8.3 Waveform correction of no-load losses, where the

exponent “2” was lost during editing. It needs to be added back. • There is a sentence in 10.8 Induced Tests for Class II Power Xfmrs, that refers to this test being

applied to terminals 115 kV and above. Since Class II now extends down to 69 kV, this sentence needs to be revised, changing the 115 to 69.

It was decided that these should be corrected immediately, so a corrigendum would need to be done. Steve took out a PAR and it was approved. With Peter Balma’s help, the Working Group got the Corrigendum done and had a few electronic meetings with the Working Group members and it was approved to go to ballot. With approval of the Standards Subcommittee in Vancouver, I will launch the ballot shortly after this Vancouver meeting. At the Spring 2016 meeting, Steve requested the three Subcommittee Chairs from Dielectric Test, Performance Characteristics, and Insulation Life to rename their 12.90 continuous revision Working Groups to Task Forces, since calling them a WG is incorrect. A WG needs a PAR and those groups do not have a PAR. The PAR exists (will exist) in the Standards Subcommittee only. Therefore, they are really Task Forces. Steve plans to take out a new PAR for future revision to the document, and will do so after the Corrigendum finishes.

L.5.3 Corrigenda for C57.12.70 – Steve Shull

Steve Shull called the meeting to order and welcomed everyone to the working group meeting for the Corrigenda of C57.12.70. The purpose of the Corrigenda was to review Annex A and correct any errors that were found in the document. A quorum was established by hand count using a members list on the screen. Steve asked for patent claims and none were made.

Steve presented the agenda. A motion was made by Jerry Murphy and seconded by Lee Mathews to accept the agenda and the WG approved it by unanimous consent. Steve noted that the minutes of the last meeting were posted and entertained a request for a motion for approval of these. Jerry Murphy made a motion to approve these minutes and it was seconded by Jason Varnell. The WG approved it by unanimous consent.

Jason Varnell made a presentation to the group for the Task Force who reviewed the document. This Task Force consisted of himself, Charles Sweetzer, and Steve Shull. This presentation will be posted on the website.

Annex L

Page 3 of 4

This generated some discussion that resulted in a couple of suggestions. These were that the winding diagrams should be first on the left so that a left to right flow would allow for a better understanding of the phasor development. It was also suggested that some of the phasor diagrams be reordered to help in understanding the phasor development that were used in later drawings. As well, to make the arrows of the phasors be always at the tip away from the common point on wye connected diagrams and so as to provide clarity in the clock diagrams.

This resulted in a motion by Jerry Murphy to have the task force create a new draft of the annex which would incorporate the discussed suggested changes. This was seconded by Jason Varnell and was passed unanimously.

A request came from Blake Cook to join the Task Force. Steve Shull welcomed him to the group.

The next meeting will be held in the Spring 2017.

Respectfully submitted by Steve Shull, WG Chair, on October 26, 2016.

L.5.4 TASK FORCE for Comparison of IEEE & IEC Standards for Cross Reference The task force meeting was held at 4.45pm on October 25, 2016. 4 of 5 members were present, so a quorum was achieved, 4 guests also attended, for a total attendance of 8.

The working group unanimously approved the Vancouver Meeting Agenda. A motion was raised by Hemchandra Shertukde to approve the minutes of the San Antonio, Spring 2015 meeting, Bill Griesacker seconded the motion which was carried unanimously.

A motion was then raised by Hemchandra Shertukde to approve the minutes of the Memphis, Fall 2015 meeting, Richard Marek seconded the motion which was carried unanimously.

This was followed by two presentations on comparison of IEEE and IEC standards. The first presentation was a comparison of the bushing standards C57.19.00 (2004), C57.19.01 (2001), and IEC 60137 (2008) prepared by John Graham chair of the Busing sub-committee (SC36A) and presented by the chair.

The second presentation was prepared by Tom Golner and presented by Rick Marek covering important differences between IEEE and IEC standards for high temperature insulation C57.154 and IEC 60076-14.

The task force meeting was adjourned at 5.50 pm.

Respectfully submitted by Vinay Mehrotra on November 10, 2016

L.5.5 TASK FORCE Report: Unwritten Rules & Procedures for working on and Revising C57.12.00 & C57.12.90 Steve Antosz presented his report on the procedures and rules for the compilation and editing of our two main standards: C57.12.00 & C57.12.90. Based on these recommendations, the groups that work on individual portions of these standards have been converted to Task Forces. The individual groups working directly on the material do not have PARs therefore they cannot be Working Groups. The Working Groups addressing these standards work out of this Sub-Committee and have membership determined by the chairs of the individual Task Forces that contribute to the material in these standards.

L.5.6 Working Group Report: Corrigenda for IEEE C57.163 – 2015

The Ballot of the corrigenda for IEEE PC57.163 – 2015 Guide on “Establishing Power Transformer Capability while under Geomagnetic Disturbances” closed at midnight October 14. It received 96 % response rate and 100 % approval rate. It dealt with a clarification made in the caption of Figure 13 of the Guide where the Figure showed Tie plates hot spot temperature rise measured at the top of the tie plates

Annex L

Page 4 of 4

while the corresponding Figure in the referenced Paper showed those at the middle of the plates. Three minor editorial comments were received and responses were entered. The project is on the agenda for the December 6 RevCom meeting.

L.6 Old Business

• The task force for C57.12.80 working on the definition for a distribution transformer (see Spring of 2016 minutes) has had their scope expanded by a motion to a full revision of this standard. This was moved by Jim Graham and seconded by Hemchandra Shertukde. The motion carried with one objection. Clair Claiborne volunteered as chair, with Jim volunteering as vice-chair.

L.7 New Business

• Steve Antosz reported that a Corrigenda of C57.12.90 is complete and has been sent to ballot to correct the error in the core loss correction formula and the omission in the induced test clause for class 2 power transformers which was discovered after the document was published. The next meeting will be held spring 2017 in New Orleans, LA.

L.8 Adjournment

Steve Antosz moved to adjourn which was seconded by Susan McNelly, there were no objections and the meeting was adjourned by the Chair.

Respectfully submitted by Daniel M Sauer, Standards SC Secretary

Page 1 of 9

Annex M Underground Transformers & Network Protectors Subcommittee

October 26, 2016

Vancouver, BC, Canada

Chair: Dan Mulkey

Vice Chair: George Payerle

M.1 Meeting Administration

Introductions – The meeting was called to order at 11:00 AM in the Jr Ballroom of the Sheraton Vancouver Wall Centre Hotel in Vancouver, BC, Canada. Introductions were made and sign-in sheets were routed.

Quorum – The members were listed on the screen and by a show of hands, it was determined that there was a quorum with 19 of the 24 members in attendance.

Approval of Minutes – The minutes from the Spring 2016 meeting in Atlanta, Georgia were approved with the changes noted in the working group reports below. They were motioned for approval by Brian Klaponski and seconded by Jeremy Sewell. The subcommittee approved these without opposition.

Members and Guests --There were 19 members and 28 guests in attendance. Their names can be found in the AM system.

The chair stated that persons must attend 2 meetings in a row and request membership to become a member. If you miss 3 or 4 meetings in a row, you may be dropped from the member list. Introductions were made and minutes from the previous meeting in Atlanta were presented. Brian Klaponski moved to accept the minutes as presented and Jeremy Sewell seconded the motion. The motion was carried unanimously. In addition to presenting his minutes, Alan Traut reported that his vice-chair Adam Bromley has been promoted at his company and will no longer be attending. He thanked him for his service and announced that Jermaine Clonts will be taking over as secretary of C57.12.23.

Membership Changes – Jermaine Clonts, Mark Faulkner, and Kwasi Yeboah requested and were accepted as members.

M.2 Working Group and Task Force Reports

M.2.1 C57.12.23 Working Group Report – Single-Phase Submersible Transformer

Alan Traut, Chairman, Adam Bromley, Vice-Chair. Revision Due Date: 3/19/2019 PAR Approval Date: 8/21/2014 PAR Expiration Date: 12/31/2018

Call to order - The meeting was called to order on Tuesday 10/25/2016 at 9:30am and everyone was asked to introduce themselves. Rosters were circulated. Electronic check-in was available for this

Annex M 11/21/2016

Page 2 of 9

meeting. Al introduced Jermaine Clonts as secretary and notified the WG of Adams Bromley’s departure in his role as vice chair.

Essential Patent Claims - At the start of the meeting the working group was asked to disclose of any essential patent claims. No essential patent claims were disclosed

Quorum – We had 68 attendees, 26 members present out of 34 active members, 42 guests with 9 of those requesting membership, which gave us enough members to establish a quorum. Attendance is recorded in the AM system.

Approval of agenda - Motion: Ronald Stahara Second: Fredric Friend Unanimous approval of agenda.

Approval of meeting minutes- Motion: Said Hachichi Second: Ronald Stahara. Unanimous approval of S16 Atlanta meeting minutes

Chair Report – Al talked about when the PAR expires and how long we have to complete our work. PAR expires December 31, 2018. 10-year life cycle of the standard is December 31, 2019. Al informed the working group of his desire to send to the ballot in the fall meeting of 2017, which would give us two more meetings.

Old Business

Low Voltage terminals 7.2.2

Al discussed the revision to the low voltage table that was presented in the spring 2016 meeting by the low voltage terminal task force. The primary changes were the addition of a voltage component to the table, updated the cable standard reference to the most recent version and added the statement "The connection between the secondary bushings and the cable shall be fully insulated and sealed to prevent the entrance of moisture."

Al asked for comments and/or discussion in regards to the data presented in the table. No comments were made.

Dan Mulkey made a motion to approve the table as presented below. Ronald Stahara seconded the motion. The table and text were unanimously approved.

Table 4 – Low-Voltage Terminal Sizes

Low-Voltage Terminals

Low-Voltage kVA Ratings

Ratings (V)

2/0 AWG Copper Cable

120/240, 240/120, 240 25 - 37.5 240/480, 480/240, 480 25 - 75

120 - 277, 347 25 - 50

600 25 - 100

4/0 AWG Copper Cable

120/240, 240/120, 240 50 240/480, 480/240, 480 100

120 25 277 - 347 75 600 -

500 kcmil copper 120/240, 240/120, 240, 277 75-100 240/480, 480/240 ,480 167

Annex M 11/21/2016

Page 3 of 9

120 37.5 – 50 347 100 600 167-250

H Spade

120/240, 240/120, 240, 277, 347 167-250 240/480, 480/240, 480 250

120 75-167 600 -

When low-voltage cable leads are specified, they shall extend 350 mm (14 in) above the top of the cover and shall be arranged for vertical takeoff. Cable insulation shall be in accordance with NEMA WC7 1998/ICEA S 65 658 or functional equivalent for continuous operation at a minimum of 90o C and 600 V. Cable flexibility shall be such that bending it into an arc having a radius of 300 mm (12 in) can be accomplished without overstressing the low-voltage bushing. The connection between the low-voltage bushings and the cable shall be fully insulated and sealed to prevent the entrance of moisture into the cable.

Tank Materials

The table detailing the minimum tank, cover and cooler thickness from 12.24 was discussed and displayed. The objective was to identify if we should have a table detailing the minimum material thickness in 12.23 and if so what thickness should be included in the table. Giuseppe Termini and several other members commented that the table has purpose in this standard and should be included

After agreeing the table should be included in the standard, the discussion transitioned to what thickness should be considered the minimum. Said Hachichi commented on the use of copper bearing steel which is included in 12.24, however concerns were expressed in regards to the manufacturability of this type of steel. In addition, Al asked if any OEM's used copper bearing steel for production of units governed by 12.23. None of the present OEMS currently use copper bearing steel. Lee Welch commented that the steel thickness from the table in 12.24 may be overkill for this product line. After discussion, the working group concluded that the best way to address this subject would be by surveying the end users and OEM’s. The survey will identify the what minimum requirements are displayed in the specs of end users, what gage steel OEM’s are currently manufacturing with special consideration to the base material used.

Pressure relief requirements

The discussion started with the presentation of background information, starting with the current text in 12.23 followed by the language in 12.39 and 12.24. The objective of the discussion was to determine what language should be included in the new revision of 12.23, in particular whether we should leave the text as is with modification or adopt the language from the other standards. Mike Hardin mentioned his successful past experience with a 1/2" UNC with nylon washer. Edward Smith commented that pipe threads are more forgiving, however with pipe threads you are counting on the thread to provide the seal and with a UNC bolt you are counting on the gasket to provide the seal. Lee Welch questioned where the fitting should be located. Dan Mulkey commented that the automatic pressure relief valve should always be on the cover and the manual pressure relief can be anywhere due to the fact the manual pressure relief is always performed in the shop. Al asked the working group if any pressure relief fittings were located on the tank wall, no one confirmed this application with certainty. From the discussion, the following text from 12.24 was modified and proposed to be the new language for 12.23

Pressure relief

A fitting shall be located on the transformer cover and used for mounting a manual pressure relief plug or an automatic pressure relief valve.

Annex M 11/21/2016

Page 4 of 9

Manual pressure relief

A ½ inch UNC bolt with a gasket or ½ inch NPT plug shall be provided that allows slow release of pressure without completely removing the bolt or plug.

Automatic pressure relief

If an automatic pressure relief valve is specified, a NPT fitting shall be provided and sized for the flow rate of the valve. The valve shall be operable by using a standard hot-line tool from above.

The group ran out of time and placed section 7.3 Accessories on the agenda for the next meeting.

We adjourned at 10:45 am. We will meet at the Spring 2017 meeting in New Orleans, Louisiana.

M.2.2 C57.12.24 Working Group Report – Three-Phase Submersible Transformers

Giuseppe Termini, Chairman; George Payerle Secretary Revision Due Date: 6/17/2019 PAR Approval Date: 11/9/2011 PAR Expiration Date: 12/31/2017

C57.12.24 did not meet. Giuseppe Termini reported that draft D5 of the document went out and comments came back. Those changes were incorporated as D6. Draft D6 was then recirculated. There was one change to a date and D7 is on the RevCom December 6, 2016 Agenda . C57.12.24 will probably not meet in New Orleans.

M.2.3 C57.12.40 Working Group Report – Secondary Network Transformers

Brian Klaponski, Chairman; Giuseppe Termini, Secretary Revision Due Date: 12/31/2021 PAR Approval Date: 8/30/2012 PAR Expiration Date: 12/31/2017

The WG met on Tuesday, October 25, 2016 at 11:00 am with 14 members and 30 guests.

An agenda was presented and approved; and introductions were made.

The Chairman asked if anyone in the Working Group knew or had knowledge of any existing or pending patents that may affect the work on this standard. There was one positive response. Liz Sullivan from ABB stated that ABB had a patent related to high current fault inside the network transformer tank. She said they had a LOA with the IEEE from a couple of years ago.

The minutes of the March 22, 2016, meeting in Atlanta, GA were reviewed.

George Payerle made a motion to approve the Meeting Minutes as amended above. Mark Faulkner seconded the motion and the minutes were approved unanimously.

The Chairman stated that the balloted standard received a 97% approval rate. The IEEE-SA requires a 75% approval rate. The Chairman also stated that there were 47 comments received with comments from 2 balloters being negative and the other comments were associated with affirmative votes.

Annex M 11/21/2016

Page 5 of 9

Prior to the meeting a Comment Resolution Taskforce was formed by the Chairman to resolve the comments received from the balloting process however, since most of the comments were not negative, the Chairman decided to review and resolve the comments within the Working Group at this meeting.

The Chairman stated there were 3 changes related to the Mandatory Editorial Review required by the IEEE SA prior to the ballot. These were:

a) Introduction Subclause – These are the reasons for the new revision of the standard and they were added to the Introduction subclause.

b) Scope Subclause – For unknown reasons the scope submitted through the PAR does not match the Scope subclause. The Scope was revised to be consistent with the wording in the PAR.

c) Annex B – A comment was received from the mandatory review coordination raised a potential copyright issue regarding the equation used in this Annex. After much research it was discovered that the equation has been used in other IEEE standard and therefore the copy right issue was no longer valid.

The Chairman stated that Draft 9 was created after the Ballot to incorporate draft changes responding to the comments. The rest of the meeting was dedicated to the resolution of the comments ballot comments.

a) Subclause 3.1 – The word “ambient” was added next to “temperature” in the second sentence of this subclause.

b) Table 2 – A comment was received to make editorial changes to add lines for clarity purposes between columns and rows associated with this table. Plus there were some spacing issues in the table in the voltage numbers.

c) Table 8 – The headers of this table were changed to read “oil immersed” instead of “oil filled” and “ insulating liquid” instead of “fluid”.

d) Subclause 5.2 – The Working Group unanimously voted to leave this subclause as is and to consider the ballot comments received on corrosion in the next standard revision.

e) A suggestion was made by Lee Welsh (he had also made this comment in the ballot) to enlarge the figures in the standard so that they can be more legible. The Chairman stated that he will consider this suggestion and try to enlarge the print in the figures prior to submitting the final copy of the standard for publishing.

f) General Comment – A suggestion was made to renumber the dimensions in Figure 1 to remove inconsistencies (e.g.: H1 is used for the high side electrical connection, however H1 is also used to show the height between top and bottom of the network transformer with reference to Table 8).

Based on the above changes the new Draft 9 will be then submitted back through the final steps of the balloting process and approval processes of the IEEE SA.

The meeting was adjourned at 12:15 pm with the next meeting set for New Orleans, LA in March 2017.

Annex M 11/21/2016

Page 6 of 9

M.2.4 -C57.12.44 Working Group Report – Secondary Network Protectors

Mark Faulkner, Chairman, Alex Macias, Secretary Revision Due Date: 12/31/2024 PAR Approval Date: 3/26/2015 PAR Expiration Date: 12/31/2019

Meeting Administration: The meeting was called to order at 1:45 PM Essential Patents Disclosure - None cited Attendance

Rosters passed out Roster Scanned and Sent to DHM

Introductions Quorum Determination

A total of 24 individuals attended the meeting. Membership stands at 10; members present 5, a quorum was met on people in attendance Guillerno Sibucao and Sophie Ndiaye have been reclassified as Guest due to lack of attendance

The following have requested membership to the WG; attendance records will be reviewed Piotr Blaszczyk David Blew Robert Stinson

Approval of the Fall 2014 minutes Mark Faulkner presented the meeting agenda to the WG for review and acceptance. Charles (Cory) Morgan motioned to approve the meeting agenda as presented, Dan Mulkey, seconded the motion, the motion was approved unanimously. No one opposed.

Items Discussed during meeting

Continued review of comments from Lee Welch:

Table 4 Section 9.3 AC voltage ratings

Readdressing the max. rated design voltages

• In response to question on voltage table, Eaton (Mark Faulkner) had commented that they design type test at 600V regardless of NP voltage classification.

• Richards (Douglas Craig) commented that they test per voltage design.

♦ A vote was taken to leave Table 4 as is; unanimously approved with no one opposed.

B.3 Types of Fuses (Sand filled), section D

Elimination of first sentence: “Fuses of this type are used primarily for 480Y/277 V application.”

• Richards noted that sand filled are being utilized at 216Y/125 V

Annex M 11/21/2016

Page 7 of 9

Change the second sentence to read: “Fuses of this type has steep time-current characteristic and is sensitive to changes in ambient temperatures.”

♦ A vote was taken to leave Table 4 as is; unanimously approved with no one opposed.

External Fuse Housing

Clarification from last meeting regarding external fuse enclosures.

• The issue was the design requirements of a single enclosure for the 3 required fuses. A discussion followed and the following is to be added to Section 8 Fuses and Fuse Mounting.

♦ “A single external fusing enclosure shall have fuses that are electrically and physically isolated”

A vote was taken to leave Table 4 as is; unanimously approved with no one opposed.

Pressurizing the fuse enclosure • This was addressed in the Atlanta meeting notes

Section 11.5.2 Spade-type terminals • Figure 8 (A) and (B)

♦ Eaton and Richards will submit a plan view of the terminal bases for inclusion as models differ in pattern and orientation.

External fusing clearances and heights • Eaton and Richards will submit their designs for inclusion in the standard. The drawings

will be reviewed at the next meeting. Internal fusing clearances

• Topic was not discussed A discussion was held on NPL and A4BY fusing and applications

• Review to continue in next meeting A continued discussion from the last meeting on the different type of external fuses available was

not held Annex A Change “normative” to “informative”. A vote was taken; unanimously approved with no one

opposed. Motion by Lee Welch, 2nd by Dan Mulkey Annex B Per Dan: Change “shall” to “should” under General, 3rd paragraph Per Brian: Same paragraph - change last line from “Under no circumstances are fuse to be

applied…” to “Under no circumstances fuses should be applied…” • A vote was taken; unanimously approved with no one opposed. Motion by Dan Mulkey,

2nd by Brian Table B.4

• Per Cory Morgan: change #4 from “2825 A” to “2500 A – 2825 A” B.4 History

• A suggestion was made to include 150kA rating. Annex C C.2.1 Incorrect relay setting

Annex M 11/21/2016

Page 8 of 9

• Remove “normally” from: …the phasing relay function is normally included as part of a single network relay package”

• A vote was taken; unanimously approved with no one opposed. Motion by Lee Welch, 2nd by Cory Morgan

Annex F F.3 Relay settings

• 5th paragraph (Transformer Losses) ♦ Brian volunteer to review, report findings and recommendation for next meeting

Last paragraph • Suggestion to remove “shall” was not approved from the following: “…a three-phase

instantaneous overcurrent element shall also be provided to trip…” The following topics were again noted in the meeting; however, deferred to a possible future

PAR, not considered at this time. Remote Racking

• Lee (GP) indicated that an inspection window or some means be included in the standard • To verify visible break of contacts • Design in place that do not require the door to be open • Include a means to provide SCADA features in relation with remote racking • Note: It was suggested that a new section be created specific to remote racking

Sections: 10.5.4.6. / 10.5.4.7 / 105.4.8 / 10.5.4.8 / 10.5.4.9 • A discussion was held concerning the door hinges placement • Submersible vs. non submersible • Is the operating handle the determining factor • It was decided to not change any section

10.5.14 Spare auxiliary contacts • Request made to define “dry contact” • Not addressed; however, a reference was made to include “no voltage” • include a means to provide contact status

Next meeting: New Orleans

M.3 Old Business None

M.4 New Business

C57.12 57 Ventilated Dry Type Network Transformers also falls under UGTNP. The chair commented that it is currently not meeting but that if someone wanted to, they could volunteer to make it an active working group again.

Following the working group reports, there was discussion of the patent disclosure issue. Brian Klaponski related his conversation with Gary Hoffman. The conclusion seemed to be that if a WG chair asks if there are essential patent claims and if so if a letter of agreement was sent to IEEE that should be the end of the WG chair's involvement.

Lee Welch suggested that there be a check box when we sign in to the meeting where people can indicate if there are any patent issues and also can request membership at that time.

Annex M 11/21/2016

Page 9 of 9

Brian pointed out that there has been a lot of conversation regarding cathodic protection. He suggested having a guide or an informative annex attached to C57.12.00 on the subject. He also said that maybe there is already a guide in existence. He pointed out that there are people in our meeting that have experience in that field including Bob Kinner from First Power and Jason Attard from Con Ed. They both indicated interest in working on the issue. Dan Mulkey said that PG&E has cathodic protection on the gas side of the business but not on the electric side. He also said that cathodic protection requires maintenance. There was general agreement that work on this area will be helpful.

M.5 Adjournment

The meeting was adjourned at 12:00 PM with the next meeting set for New Orleans, Louisiana on April 5, 2017.

APPENDIX 1

Meeting Schedule

page 1

INITIAL ISSUE - August 31

IEEE/PES TRANSFORMERS COMMITTEE www.transformerscommittee.org

Fall 2016 Meeting; October 23-27

Hosted by IFD Corporation

Sheraton Vancouver Wall Centre Hotel; Vancouver BC, Canada See Page 5 for a key to abbreviations. ALL MEETINGS ARE IN THE NORTH TOWER OF THE HOTEL.

DATE/TIME

ACTIVITY

SUB-

COM

ACTIVITY

CHAIR

ROOM

CAP/ARR/AV

MEETING

ROOM

Friday, October 21

8:00 am - 5:00 pm > WG Step-Voltage Regulators 60076-57-15 Dist C. Colopy 14 US Port Alberni (4th FL)

Saturday, October 22

No Committee Meetings, No Technical Tours

7:15 am to 7:30 pm Early Bird Event #1: Vancouver Island & Victoria Tour, a full-day tour. -- Advance on-line registration necessary. Limited attendance. Will sell out quickly! See flyer for details. -- Buses depart Sheraton Hotel at 7:15 am. Return at ~7:30 pm.

6:30 pm to 10:00 pm Early Bird Event #2: "The Comedy Mix" Comedy Club, at nearby Century-Plaza Hotel -- Advance on-line registration necessary. Limited attendance. Will sell out early. See flyer for details. -- Meet in hotel lobby and walk together across street to the Club. Depart lobby at 6:30 pm. Return ~10:00 pm.

Sunday, October 23

No Technical Tours or Social Tours

1:00 pm - 5:30 pm Meeting Registration North Tower Main Lobby

2:00 pm - 5:30 pm Administrative SC -- Closed meeting, by invitation only

Admin. S. Antosz 24 US Port McNeill (4th FL)

2:00 pm - 5:30 pm NEMA Transformers -- Closed meeting, by invitation only

++ J. Caskey 14 US Port Alberni (4th FL)

6:00 pm - 8:00 pm Welcome Reception 500 Reception Pavilion Ballroom with Foyer (3rd FL)

Monday, October 24 -- Monday Breaks Sponsored by R.L. Components ** 7:00 am - 5:00 pm Meeting Registration North Tower

Main Lobby

7:00 am - 7:50 am Newcomers Orientation -- Breakfast Meeting; arrive early! -- Newcomers & Guests are encouraged to attend!

S. McNelly 80 CL S2 (with buffet)

Junior Ballroom CD (3rd FL)

7:00 am - 7:50 am Distribution SC Leaders Coordination -- Closed breakfast meeting, by invitation only

S. Shull 14 BD Port Hardy

7:00 am - 8:00 am Breakfast - Attendees (no spouses/companions please) 300 RT (8/tbl) Pavilion Ballroom ABCD (3rd FL)

8:00 am - 9:30 am Breakfast - Spouses/Companions (no meeting attendees please) 100 RT (10/tbl) S. Tower, 34th Floor Event Space

9:15 am - 3:15 pm Spouses/Companions Tour: Sea to Sky Tour, including stops at Shannon Falls and Horseshoe Bay, with gondola ride and lunch on Mount Habrich. Advance registration required. See flyer for details. -- Bus departs from front of hotel at 9:15 am, and returns at ~3:15 pm.

8:00 am - 9:15 am > Opening Session S. Antosz -- All attendees are encouraged to attend -- See separate document for meeting agenda -- Attendance required to maintain Committee Member status.

550 MX S1 Grand Ballroom ABCD

9:15 am - 9:30 am Break (beverages only) Grand Ballroom & Jr. Ballroom Foyers

** Contact Ed Smith ([email protected]) if you are interested in sponsoring a coffee break at a future meeting.

page 2

DATE/TIME

ACTIVITY

SUB-

COM

ACTIVITY

CHAIR

ROOM

CAP/ARR/AV

MEETING

ROOM

Monday, October 24 (continued)

WG Submersible Transf. C57.12.24 UTNP Work is near completion. Resolving ballots.

9:30 am - 10:45 am WG Thermal Evaluation of Insulation Systems, Dry Type C57.12.60

Dry R. Wicks 60 MX Port Alberni (4th FL)

9:30 am - 10:45 am -- -- -- 80 MX Port McNeill (4th FL)

9:30 am - 10:45 am TF External Dielectric Clearances DiTests E. Davis 80 MX Jr. Ballroom AB

9:30 am - 10:45 am WG Tertiary/Stabilizing Windings PC57.158

PCS E. Betancourt 160 MX S3 (80 CL + 80 TH)

Jr. Ballroom CD

9:30 am - 10:45 am TF Consolidation of Insulating Fluid Guides IF T. Prevost 200 MX S3 Grand Ballroom AB

9:30 am - 10:45 am TF Transformer Efficiency and Loss Evaluation (DOE Activity)

Dist P. Hopkinson 250 MX S3 Grand Ballroom CD (+ Passage)

10:45 am - 11:00 am Break (beverages only) Grand Ballroom & Jr. Ballroom Foyers

11:00 am - 12:15 pm WG Ventilated Dry Type C57.12.51 Dry S. Som 60 MX Port Alberni (4th FL)

11:00 am - 12:15 pm -- -- -- 80 MX Port McNeill (4th FL)

11:00 am - 12:15 pm WG Overhead Distr. Transf. C57.12.20 Dist A. Traut 80 MX Jr. Ballroom AB

11:00 am - 12:15 pm WG Control Cabinets PC57.148 Power J. Watson 160 MX S3 Jr. Ballroom CD

11:00 am - 12:15 pm WG Moisture in Insulation PC57.162 IL T. Prevost 200 MX S3 Grand Ballroom AB

11:00 am - 12:15 pm TF PCS Rev. to Test Code C57.12.90 PCS M. Perkins 250 MX S3 Grand Ballroom CD

12:15 pm - 1:30 pm Lunch Meeting: Standards Development Review J. Graham 240 RT (7/tbl) Pavilion Ballroom

-- Everyone welcome to attend. All SC/WG/TF leaders are highly encouraged to attend. ABCD

-- Doors open ~12:00 pm. Come early, get a good seat, and start eating. -- Advance registration necessary. No paper tickets. Admission verified with name badge at the door. -- Anyone can join us for this luncheon, and sit & listen to the presentation, without eating lunch. Suggested time to arrive for only the presentation (without lunch) is 12:30 pm.

1:45 pm - 3:00 pm WG Sec. Network Protectors C57.12.44 UTNP M. Faulkner 60 MX Port Alberni (4th FL)

1:45 pm - 3:00 pm WG Dry Type Gen. Require. C57.12.01 Dry C. Ballard 80 MX Port McNeill (4th FL)

1:45 pm - 3:00 pm WG 1-ph Padmount Dist Transf C57.12.38 Dist A. Ghafourian 80 MX Jr. Ballroom AB

1:45 pm - 3:00 pm WG Thru-Fault Current Duration PC57.109 PCS V. Mehrotra 160 MX S3 Jr. Ballroom CD

1:45 pm - 3:00 pm WG Installation of Power Transf. C57.93 Power M. Lau 200 MX S3 Grand Ballroom AB

1:45 pm - 3:00 pm TF Audible Sound Revision to Test Code PCS R. Girgis 250 MX S3 Grand Ballroom CD

3:00 pm - 3:15 pm Break (beverages and treats) Grand Ballroom & Jr. Ballroom Foyers

WG Milli-amp Current Transf. C57.13.7 IT Will not meet. Balloting document.

3:15 pm - 4:30 pm SC HVDC Converter Transformers and Smoothing Reactors

HVDC M. Sharp 60 MX Port Alberni

3:15 pm - 4:30 pm -- -- -- 80 MX Port McNeill

3:15 pm - 4:30 pm WG 3-ph Padmount Dist Transf. C57.12.34 Dist R. Stahara 80 MX Jr. Ballroom AB

3:15 pm - 4:30 pm WG Natural Ester-Based Fluids C57.147 IF P. McShane 160 MX S3 Jr. Ballroom CD

3:15 pm - 4:30 pm WG Dielectric Freq. Response PC57.161 DiTest A. Naderian 200 MX S3 Grand Ballroom AB

3:15 pm - 4:30 pm WG Transformer Capability with Non-sinusoidal Loads PC57.110

PCS R. Marek 250 MX S3 Grand Ballroom CD

4:30 pm - 4:45 pm Break (beverages only) Grand Ballroom & Jr. Ballroom Foyers

4:45 pm - 6:00 pm -- -- -- 60 MX Port Alberni (4th FL)

4:45 pm - 6:00 pm WG PD in Bushings & PT/CTs PC57.160 DiTests T. Hochanh 80 MX Port McNeill (4th FL)

4:45 pm - 6:00 pm WG Step-Voltage Regulators C57.15 / 60076-21

Dist C. Colopy 80 MX Jr. Ballroom AB

4:45 pm - 6:00 pm -- -- -- 160 MX S3 Jr. Ballroom CD

4:45 pm - 6:00 pm WG Life Extension C57.140 Power P. Boman 200 MX S3 Grand Ballroom AB

4:45 pm - 6:00 pm TF PCS Revisions to C57.12.00 PCS T. Ansari 250 MX S3 Grand Ballroom CD

6:30 pm - 10:00 pm Technical Tour: IFD Corporation Tour, Vancouver Facility, with BBQ dinner (www.ifdcorporation.com) -- Everyone welcome to attend, but register in advance during on-line meeting registration. -- Buses depart from front of hotel at 6:30 pm, and return by 10:00 pm. See flyer for more info.

page 3

DATE/TIME

ACTIVITY

SUB-

COM

ACTIVITY

CHAIR

ROOM

CAP/ARR/AV

MEETING

ROOM

Tuesday, October 25 -- Tuesday Breaks Sponsored by WEG Electric Corp. **

7:00 am - 12:00 pm Meeting Registration Main Lobby

7:00 am - 8:00 am Breakfast - Attendees (no spouses/companions please) 300 RT (8/tbl) Pavilion Ballroom ABCD

8:00 am - 9:30 am Breakfast - Spouses/Companions (no meeting attendees please) 100 RT (10/tbl) S. Tower, 34th Floor Event Space

7:00 am - 7:50 am EL&P Delegation (end-users only please) -- Breakfast Meeting; arrive early

J. Murphy 30 CL (with buffet)

Parkville

9:15 am - 3:45 pm Spouses/Companions Tour: Vancouver City Tour with Museum of Anthropology, with stops at Stanley Park and Queen Elizabeth Park. Advance registration required. See flyer for details. -- Bus departs from front of hotel at 9:15 am, and returns at ~3:45 pm. VERY LIMITED ATTENDANCE!

TF Composite Bushings Bush Work complete, report submitted in April 2016.

8:00 am - 9:15 am WG Enclosure Integrity C57.12.28, C57.12.29, C57.12.31, C57.12.32

Dist D. Mulkey 60 MX Port Alberni (4th FL)

8:00 am - 9:15 am WG Station Service Volt. Transf. C57.13.8 IT D. Wallace 80 MX Port McNeill (4th FL)

8:00 am - 9:15 am -- -- -- 80 MX Jr. Ballroom AB

8:00 am - 9:15 am TF Limits for Winding Insulation PF/Resistance

DiTests S. Tarlapally 160 MX S3 Jr. Ballroom CD

8:00 am - 9:15 am WG Dry Type PD Detection C57.124 Dry T. Prevost 200 MX S3 Grand Ballroom AB

8:00 am - 9:15 am WG Revision to C57.12.10 Power G. Hoffman 250 MX S3 Grand Ballroom CD

9:15 am - 9:30 am Break (beverages only) Grand Ballroom & Jr. Ballroom Foyers

9:30 am - 10:45 am -- -- -- 60 MX Port Alberni (4th FL)

9:30 am - 10:45 am WG Tests for Instrument Transf. C57.13.5 IT P. Riffon 80 MX Port McNeill (4th FL)

9:30 am - 10:45 am WG 1-Ph Submersible Transf. C57.12.23 UTNP A. Traut 80 MX Jr. Ballroom AB

9:30 am - 10:45 am WG GSU Bushings PC57.19.04 Bush S. Digby 160 MX S3 Jr. Ballroom CD

9:30 am - 10:45 am WG Shunt Reactors C57.21 PCS S. Som 200 MX S3 Grand Ballroom AB

9:30 am - 10:45 am WG Wind Turbine Transf. P60076-16 PCS D. Buckmaster 250 MX S3 Grand Ballroom CD

10:45 am - 11:00 am Break (beverages only) Grand Ballroom & Jr. Ballroom Foyers

11:00 am - 12:15 pm WG PD Acoustic Detection C57.127 DiTests D. Gross 60 MX Port Alberni (4th FL)

11:00 am - 12:15 pm TF PLC Caps & CCVTs (currently C93.1) IT Z. Roman 80 MX Port McNeill (4th FL)

11:00 am - 12:15 pm WG Liquid-immersed Secondary Network Transformers C57.12.40

UTNP B. Klaponski 80 MX Jr. Ballroom AB

11:00 am - 12:15 pm WG Distrib. Transf. Bushings PC57.19.02 Bush S. Shull 160 MX S3 Jr. Ballroom CD

11:00 am - 12:15 pm WG Semiconductor Power Rectifier Transformers C57.18.10

PCS S. Kennedy 200 MX S3 Grand Ballroom AB

11:00 am - 12:15 pm WG Loss Evaluation Guide C57.120 PCS R. Verdolin 250 MX S3 Grand Ballroom CD

12:15 pm - 1:30 pm Awards Luncheon D. Platts 240 RT (7/tbl)

-- Doors open ~12:00 pm. Come early, get a good seat, and start eating.

-- Advance registration necessary. No paper tickets. Admission verified with name badge at the door.

All meeting attendees are encouraged to attend this luncheon. It’s a great way to show your appreciation and help us recognize our accomplishments.

1:45 pm - 3:00 pm WG 3-ph Transf. Connections PC57.105 PCS A. Bromley 60 MX Port Alberni (4th FL)

1:45 pm - 3:00 pm WG Distr. Substation Transf. C57.12.36 Dist J. Murphy 80 MX Port McNeill (4th FL)

1:45 pm - 3:00 pm -- -- -- 80 MX Jr. Ballroom AB

1:45 pm - 3:00 pm TF LTC Std Require C57.131 / 60214-1 Power C. Colopy 160 MX S3 Jr. Ballroom CD

1:45 pm - 3:00 pm TF Revision to Low Frequency Tests DiTests B. Griesacker 200 MX S3 Grand Ballroom AB

1:45 pm - 3:00 pm WG DPV Grid Transformers PC57.159 PCS H. Shertukde 250 MX S3 Grand Ballroom CD

3:00 pm - 3:15 pm Break (beverages and Pretzels!) Grand Ballroom & Jr. Ballroom Foyers

** Contact Ed Smith ([email protected]) if you are interested in sponsoring a coffee break at a future meeting.

page 4

DATE/TIME

ACTIVITY

SUB-

COM

ACTIVITY

CHAIR

ROOM

CAP/ARR/AV

MEETING

ROOM

Tuesday, October 25 (continued)

3:15 pm - 4:30 pm WG Std Terminal Markings C57.12.70 Stds S. Shull 60 MX Port Alberni (4th FL)

3:15 pm - 4:30 pm WG Dry Type Reactors PC57.16 Dry A. Del Rio 80 MX Port McNeill (4th FL)

3:15 pm - 4:30 pm WG Std Require for Bushings C57.19.01 Bush S. Zhang 80 MX Jr. Ballroom AB

3:15 pm - 4:30 pm WG LTC Application Guide 60214-2 Power C. Colopy 160 MX S3 Jr. Ballroom CD

3:15 pm - 4:30 pm WG High-Temp Insulat. Materials, P-1276 IL R. Wicks 200 MX S3 Grand Ballroom AB

3:15 pm - 4:30 pm TF Switching Transients Induced by Transf/Breaker Interaction PC57.142

PCS J. McBride 250 MX S3 Grand Ballroom CD

4:30 pm - 4:45 pm Break (beverages only) Grand Ballroom & Jr. Ballroom Foyers

4:45 pm - 6:00 pm TF Cross Reference of IEEE to IEC Stds V. Mehrotra 60 MX Port Alberni (4th FL)

4:45 pm - 6:00 pm WG Dry Type Test Code C57.12.91 Dry D. Foster 80 MX Port McNeill (4th FL)

4:45 pm - 6:00 pm WG Tank Pressure Coordinat. C57.12.39 Dist C. Gaytan 80 MX Jr. Ballroom AB

4:45 pm - 6:00 pm WG Short Circuit Withstand PC57.164 PCS S. Patel 160 MX S3 Jr. Ballroom CD

4:45 pm - 6:00 pm WG Gas Guide C57.104 IF C. Beauchemin 200 MX S3 Grand Ballroom AB

4:45 pm - 6:00 pm TF Revisions to Impulse Test Sections of C57.12.00 and C57.12.90

DiTests P. Riffon 250 MX S3 Grand Ballroom CD

7:00 pm - 10:00 pm Technical Tour: TRIUMF National Laboratory for Physics and Accelerator-Based Science (www.triumf.ca) -- Everyone welcome, but register in advance during on-line meeting registration. See flyer for more info. -- Dinner on your own (eat beforehand). Buses depart from front of hotel at 7:00 pm, and return ~10:00 pm.

Wednesday, October 26 -- Wednesday Breaks Sponsored by Cogent Power **

No Meeting Registration, No Technical Tours, No Spouse/Companion Tours

7:00 am - 8:00 am Breakfast - Attendees (no spouses/companions please) 300 RT (8/tbl) Pavilion Ballroom

8:00 am - 9:30 am Breakfast - Spouses/Companions (no meeting attendees please) 100 RT (10/tbl) S. Tower, 34th Floor Event Space

7:00 am - 7:50 am SC Meetings Planning Mtgs G. Anderson 30 CL (with buffet)

Parkville

7:00 am - 8:30 am IEC TC-14 Technical Advisory Group ++ -- Breakfast Meeting; arrive early -- All interested individuals welcome

P. Hopkinson 80 CL S2 (with buffet)

Jr. Ballroom CD

8:00 am - 9:15 am SC Instrument Transformers IT R. McTaggart 80 MX Jr. Ballroom AB

8:00 am - 9:15 am SC Insulation Life IL S. Kennedy 350 MX S3 Grand Ballroom

9:15 am - 9:30 am Break (beverages only)

9:30 am - 10:45 am SC Bushings Bush P. Zhao 160 MX S3 Jr. Ballroom CD

9:30 am - 10:45 am SC Distribution Transformers Dist S. Shull 350 MX S3 Grand Ballroom

10:45 am - 11:00 am Break (beverages only)

11:00 am - 12:15 pm SC UG Transf. & Network Protectors UTNP D. Mulkey 80 MX Jr. Ballroom AB

11:00 am - 12:15 pm SC Dielectric Tests DiTests A. Varghese 350 MX S3 Grand Ballroom

12:15 pm - 1:30 pm Lunch (on your own)

1:30 pm - 2:45 pm SC Dry Type Transformers Dry C. Johnson 80 MX Jr. Ballroom AB

1:30 pm - 2:45 pm SC Power Transformers Power J. Watson 350 MX S3 Grand Ballroom

2:45 pm - 3:00 pm Break (beverages and treats)

3:00 pm - 4:15 pm SC Insulating Fluids IF D. Wallach 160 MX S3 Jr. Ballroom CD

3:00 pm - 4:15 pm SC Performance Characteristics PCS E. teNyenhuis 350 MX S3 Grand Ballroom

4:15 pm - 4:30 pm Break (beverages only)

4:30 pm - 5:45 pm SC Standards Stds J. Murphy 160 MX S3 Jr. Ballroom CD

5:45 pm - 10:00 pm Evening Social: Dinner Cruise aboard the MV Britannia. Advance registration is necessary. -- 10-min bus ride to boat. Buses begin loading at front of hotel at 5:45 pm. Last bus departs at 6:30 pm. -- Boarding and appetizers 6:30 to 7:00 pm. Embark at 7:00 pm. Return to hotel ~10:00 pm. -- Paper tickets will not be provided. Admission verified with name badges as you board the boat. -- Temperatures will be cool, so dress appropriately.

** Contact Ed Smith ([email protected]) if you are interested in sponsoring a coffee break at a future meeting.

page 5

KEY Note: A PC projector will be furnished in each meeting room. Arrive early to ensure equipment operates/syncs correctly. > -- activity continued into another session / from another session BD = boardroom; US = U-shape ++ -- not a Transformers Committee activity TBD = "To Be Determined" RT = multiple roundtables FC = flip chart; S1 = sound (special set-up) CL = classroom seating (w/head table for 2) S2 = stand mic in front only; S3 = one stand mic in front & stand mic(s) at mid-room TH = theater seating (w/head table for 2) MX = mix classroom & theater (w/head table)

SUBCOMMITTEES

Bush Bushings HVDC HVDC Converter Transformers and Smoothing Reactors

Mtgs Meetings

DiTests Dielectric Tests Power Power Transformers

Dist Distribution Transformers IF Insulation Fluids UTNP Underground Transformers and Network Protectors Dry Dry Type Transformers IL Insulation Life

IT Instrument Transformers Stds Standards

Thursday, October 27

No Meeting Registration, No Spouses/Companions Tours

7:00 am - 9:30 am Breakfast - Attendees (no spouses/companions please) 250 RT (8/tbl) Pavilion Ballroom

Breakfast - Spouses/Companions (no meeting attendees please) 80 RT (8/tbl) S. Tower, 34th Floor Event Space

8:00 am - 9:15 am Technical Presentation #1: "Changes & Additions to C57.12.00 and C57.12.90 in the 2015 Revisions" by S. Antosz and S. Snyder. See flyer on website. **

350 MX S1 Grand Ballroom ABCD

9:15 am - 9:30 am Break (beverages only) Grand Ballroom Foyer

9:30 am - 10:45 am Technical Presentation #2: "Tacit Knowledge Capture and Brain-Drain at Electric Utilities; an IEEE Perspective" by N. Perjanik and A. VanderWalt. See flyer on website. **

350 MX S1 Grand Ballroom ABCD

10:45 am - 11:00 am Break (beverages only) Grand Ballroom Foyer

> 11:00 am - 12:00 pm Closing Session -- All attendees are encouraged to attend -- See separate document for meeting agenda

S. Antosz 350 MX S1 Grand Ballroom ABCD

Lunch on your own

1:00 pm - 5:00 pm > WG Tap Changer Application Guide

60214-2 (continued Friday)

Power A. Kraemer 14 US Port Alberni (4th FL)

12:30 pm - 5:00 pm Technical Tour: Powertech Test and Research & Development Facility (www.powertechlabs.com) -- Everyone welcome, but register in advance during on-line meeting registration. See flyer for more info. -- Box lunch provided on the bus. Bus departs front of hotel at 12:30 pm, and return ~5:00 pm.

Friday, October 28

No Technical Tours

> 8:00 am - 5:00 pm WG Tap Changer Application Guide

60214-2 (continued from Thursday)

Power A. Kraemer 14 US Port Alberni (4th FL)

** Contact Tom Prevost ([email protected]) if you are interested in making a technical presentation at a future meeting.

FUTURE COMMITTEE MEETINGS

Spring 2017: April 2-6; New Orleans, Louisiana USA

Fall 2017: October 15-19 or 23-26, or October 29-November 2; USA Location (to be determined)

Spring 2018: March 25-29; Pittsburgh, Pennsylvania USA -- Our 100th Year Anniversary Celebration!

Fall 2018: October 14-18 or 21-25, or November 4-8; USA Location (to be determined)

Spring 2019: March 10-14 or 17-21 or 24-28; USA Location (to be determined)

page 6

Sheraton Vancouver Wall Centre Hotel 1088 Burrard Street; Vancouver, BC V6Z 2R9 Canada

+1.604.331.1000

APPENDIX 2

Semi-Annual Standards Report

- Page 1 of 25-

IEEE / PES /TRANSFORMERS COMMITTEE

Standards Report

To: Members of Transformers Committee September 24, 2016

From: Jim Graham Standards Coordinator

Executive Summary This report covers Transformers Committee Standards activity from March 1, 2016 to September 22, 2016. During this time three new Standards and no Revisions were approved by the Standards Board. In this same period, the Standards Board approved four PAR Extensions; no PAR modifications; one PAR for new standards; six PARs for Revisions; and two PARs for Corrigenda.

In this Report:

I. Standards approved .......................................................................pg 1

II. PARs approved ...............................................................................pg 1-2

III. Standards Board 2017 Meeting Schedule ......................................pg 2

IV. Transformer Committee Ballot Status ..........................................pg 3-4

V. Transformers Committee PAR Status ............................................pg 4-9

VI. Transformer Stds Status e .............................................................pg 10- 21

VII. Transformer Stds Org Chart ..........................................................pg 22-23

I. Standards approved since Mar 1, 2016

New Transformer Standards Approved (All expire 31 Dec 2026)

60076-57-1202 International Standard Requirements for Liquid-Immersed Phase-Shifting Transformers

C57.156 Guide for Tank Rupture Mitigation of Liquid-Immersed Power Transformers and Reactors

C57.159 Guide on Transformers for Application in Distributed Photovoltaic (DPV) Power Generation

Systems

REVISIONS to Transformer Standards approved None

II. PARs approved since Mar 1, 2016

PAR Extensions approved (All extended until December 2018 unless noted)

P60076-16 Power Transformers - Part 16: Transformers for Wind Turbine Application

C57.12.40 Standard for Network, Three-Phase Transformers, 2500 kVA and Smaller; High Voltage, 34 500 V

and Below; Low Voltage, 600 V and Below; Subway and Vault Types (Liquid Immersed)

(until Dec 2017)

C57.93 Guide for Installation and Maintenance of Liquid-Immersed Power Transformers

C57.147 Guide for Acceptance and Maintenance of Natural Ester Insulating Liquid in Transformers

PAR Modifcations approved None

(PAR Modifications do not change the Expiration Date)

Fall 2016 Standards Report Page 2 of 23

New Projects approved Approved until December 2020)

PC57.164 Guide for Establishing Short Circuit Withstand Capabilities of Liquid Immersed Power

Transformers

PAR Requests for Revision of Standards (Approved until December 2020)

PC57.12.01 Standard for General Requirements for Dry-Type Distribution and Power Transformers

PC57.12.34 Standard Requirements for Pad-Mounted, Compartmental-Type, Self-Cooled, Three-Phase

Distribution Transformers, 10 MVA and Smaller; High-Voltage, 34.5 kV Nominal System

Voltage and Below; Low-Voltage, 15 kV Nominal System Voltage and Below

C57.12.91 Standard Test Code for Dry-Type Distribution and Power Transformers

PC57.13.5 Standard of Performance and Test Requirements for Instrument Transformers of a Nominal

System Voltage of 115 kV and Above

PC57.18.10 Standard Practices and Requirements for Semiconductor Power Rectifier Transformers

PC57.148 Standard for Control Cabinets for Power Transformers

PARs for Corrigenda approved (Approved until December 2020)

PC57.12.90-2015 Cor 1 Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating

Transformers (2020)

PC57.163-2015 Cor 1 Guide for Establishing Power Transformer Capability while under Geomagnetic

Disturbances (2020)

III. 2016 IEEE Standards Board Meeting Schedule

Starting in 2015, the Standards Board has only three physical board meetings per year. But they

supplement this with three (3) teleconference meetings. The full list of 2017 meetings is shown in

the calendar on the next page.

Deadlines for 2016-2017 Standards Board Submissions:

Please Note: Anything that expires at the end of 2017 must be submitted to Standards

Board (either NESCOM or REVCOM) by October 16, 2017

Standards Board Meeting Submission Deadline

Jan 2017 (teleconference) December 20, 2016

March 2017 February 10, 2017

May 2017 (teleconference) March 24, 2017

June 2017 May 5, 2017

September 2017 (teleconference) July 28, 2017

December 2017 October 16, 2017

Fall 2016 Standards Report Page 3 of 23

IV. Transformers Committee Ballot Status (as of Sep 24, 2016)

PAR Number Title Ballot

Close Date Status

Dielectric Test

PC57.138 Recommended Practice for Routine Impulse Test for Distribution Transformers

9/9/2016 Sponsor Ballot:

Comment Resolution

Distribution Transformers

PC57.12.39 Standard Requirements for Distribution Transformer Tank Pressure Coordination

7/14/2016 Sponsor Ballot:

Comment Resolution

PC57.12.20

Standard for Overhead-Type Distribution Transformers 500 kVA and Smaller: High Voltage, 34 500 V and Below; Low Voltage, 7970/13 800Y V and Below

4/8/2016 Sponsor Ballot:

Comment Resolution

PC57.12.38-2014 /Cor 1

Standard for Pad-Mounted-Type, Self-Cooled, Single-Phase Distribution Transformers 250 kVA and Smaller: High Voltage, 34 500 GrdY/19 920 V and Below; Low Voltage, 480/240 V and Below - Corrigendum 1: Correct an omission in the label of Figure 1.

8/11/2016 RevCom Agenda 06-

Dec-2016

PC57.12.36 Standard Requirements for Liquid-Immersed Distribution Substation Transformers

10/5/2016 Sponsor Ballot: Ballot

PC57.15 Standard Requirements, Terminology, and Test Code for Step-Voltage Regulators

10/23/2016 Sponsor Ballot: Ballot

Dry Type Transformers

PC57.12.58 Guide for Conducting a Transient Voltage Analysis of a Dry-Type Transformer Coil

Sponsor Ballot:

PreBallot

HVDC Converter Xfmrs & Smoothing Reactors

P60076-57-129 Converter Transformers for HVDC Applications 9/23/2016 Sponsor Ballot:

Comment Resolution

Insulating Fluids

PC57.147 Guide for Acceptance and Maintenance of Natural Ester Insulating Liquid in Transformers

3/31/2016 Sponsor Ballot:

Comment Resolution

Insulation Life

PC57.119

Recommended Practice for Performing Temperature Rise Tests on Oil-Immersed Power Transformers at Loads Beyond Nameplate Ratings

3/18/2015 Sponsor Ballot:

Comment Resolution

Instrument Transformers

PC57.13.7 Standard for Current Transformers with a Maximum mA Secondary Current of 250 mA

Sponsor Ballot:

Invitation

Fall 2016 Standards Report Page 4 of 23

PAR Number Title Ballot

Close Date Status

Performance Characteristics

PC57.120 Guide for Loss Evaluation of Distribution and Power Transformers and Reactors

8/3/2016 Sponsor Ballot: Comment Resolution

PC57.158 Guide for the Application of Tertiary and Stabilizing Windings in Power Transformers

Sponsor Ballot: PreBallot

Power Transformers

PC57.140 Guide for Evaluation and Reconditioning of Liquid Immersed Power Transformers

8/31/2016 Sponsor Ballot: Comment Resolution

P60076-16 Power Transformers - Part 16: Transformers for Wind Turbine Application

6/20/2016 Sponsor Ballot: Comment Resolution

Standards

PC57.163-2015 /Cor 1

Guide for Establishing Power Transformer Capability while under Geomagnetic Disturbances - Corrigendum 1

10/14/2016 Sponsor Ballot: Ballot

Underground & Network Protectors

PC57.12.24

Standard for Submersible, Three-Phase Transformers, 3750 kVA and Smaller: High Voltage, 34 500 GrdY/19 920 Volts and Below; Low Voltage, 600 Volts and Below

8/29/2016 Sponsor Ballot: Comment Resolution

PC57.12.40

Standard for Network, Three-Phase Transformers, 2500 kVA and Smaller; High Voltage, 34 500 V and Below; Low Voltage, 600 V and Below; Subway and Vault Types (Liquid Immersed)

10/13/2016 Sponsor Ballot: Ballot

V. Transformer Committee PAR Status (as of Sep 24, 2016)

Bushings

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.19.01 Revision Standard Performance Characteristics and Dimensions for Outdoor Apparatus Bushings

8-Dec-2010 12/31/2017

PC57.19.02 New Standard for the Design and Performance Requirements of Bushings Applied to Liquid Immersed Distribution Transformers

5-Feb-2016 12/31/2020

PC57.19.04 New

Standard Performance Characteristics and Dimensions for High Current Power Transformer Bushings with Rated Continuous Current in Excess of 5000 A in Bus Enclosures

16-Jun-11 12/31/2017

Fall 2016 Standards Report Page 5 of 23

Dielectric Test

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.127 Revision

Guide for the Detection, Location and Interpretation of Sources of Acoustic Emissions from Electrical Discharges in Power Transformers and Power Reactors

16-Feb-15 12/31/2019

PC57.138 Revision Recommended Practice for Routine Impulse Test for Distribution Transformers

2-Feb-2011 12/31/2016

PC57.160 New Guide for the Electrical Measurement of Partial Discharges in High Voltage Bushings and Instrument Transformers

6-Mar-2013 12/31/2017

PC57.161 New Guide for Dielectric Frequency Response Test 23-Aug-13 12/31/2017

Distribution Transformers

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.12.39 New Standard Requirements for Distribution Transformer Tank Pressure Coordination

5-Feb-2016 12/31/2016

PC57.12.20 Revision

Standard for Overhead-Type Distribution Transformers 500 kVA and Smaller: High Voltage, 34 500 V and Below; Low Voltage, 7970/13 800Y V and Below

8-Jun-2012 12/31/2016

PC57.12.38-2014/Cor 1

Corrigendum

Standard for Pad-Mounted-Type, Self-Cooled, Single-Phase Distribution Transformers 250 kVA and Smaller: High Voltage, 34 500 GrdY/19 920 V and Below; Low Voltage, 480/240 V and Below - Corrigendum 1: Correct an omission in the label of Figure 1.

5-Feb-2016 12/31/2020

PC57.12.32 Revision Standard for Submersible Equipment - Enclosure Integrity

11-Jun-15 12/31/2019

Distribution Transformers

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.12.34 Revision

Standard Requirements for Pad-Mounted, Compartmental-Type, Self-Cooled, Three-Phase Distribution Transformers, 10 MVA and Smaller; High-Voltage, 34.5 kV Nominal System Voltage and Below; Low-Voltage, 15 kV Nominal System Voltage and Below

22-Sep-16 12/31/2020

PC57.12.36 Revision Standard Requirements for Liquid-Immersed Distribution Substation Transformers

7-Dec-2011 12/31/2017

PC57.15 Revision Standard Requirements, Terminology, and Test Code for Step-Voltage Regulators

5-Feb-2016 12/31/2018

Fall 2016 Standards Report Page 6 of 23

Dry Type Transformers

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.12.01 Revision Standard for General Requirements for Dry-Type Distribution and Power Transformers

12-May-16 12/31/2020

PC57.12.51 Revision

Standard for Ventilated Dry-Type Power Transformers, 501 kVA and Larger, Three-Phase, with High-Voltage 601 V to 34 500 V; Low-Voltage 208Y/120 V to 4160 V- General Requirements

21-Aug-14 12/31/2018

PC57.12.58 Revision Guide for Conducting a Transient Voltage Analysis of a Dry-Type Transformer Coil

3-Sep-2015 12/31/2019

PC57.12.60 Revision Standard Test Procedure for Thermal Evaluation of Insulation Systems for Dry-Type Power and Distribution Transformers

11-Jun-15 12/31/2019

PC57.12.91 Revision Standard Test Code for Dry-Type Distribution and Power Transformers

3-Mar-2016 12/31/2020

PC57.16 Revision Standard for Requirements, Terminology, and Test Code for Dry-Type Air-Core Series-Connected Reactors

5-Feb-2016 12/31/2020

HVDC Converter Xfmrs & Smoothing Reactors

PAR Number Project Type Title

Approval Date

PAR Expiration

P60076-57-129 Revision Converter Transformers for HVDC Applications 10-Dec-14 12/31/2018

Insulating Fluids

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.104 Revision Guide for the Interpretation of Gases Generated in Oil-Immersed Transformers

5-Feb-2010 12/31/2017

PC57.147 Revision Guide for Acceptance and Maintenance of Natural Ester Insulating Liquid in Transformers

5-Feb-2016 12/31/2018

Insulation Life

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.162 New Guide for the Interpretation of Moisture Related Parameters in Dry, Gas Insulated and Liquid Immersed Transformers and Reactors

23-Aug-13 12/31/2017

P1276 Revision Guide for the Application of High-Temperature Insulation Materials in Liquid-Immersed Distribution, Power and Regulating Transformers

27-Mar-14 12/31/2016

Fall 2016 Standards Report Page 7 of 23

Insulation Life

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.119 Revision Recommended Practice for Performing Temperature Rise Tests on Oil-Immersed Power Transformers at Loads Beyond Nameplate Ratings

27-Oct-14 12/31/2018

Instrument Transformer s

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.13.5 Revision Standard of Performance and Test Requirements for Instrument Transformers of a Nominal System Voltage of 115 kV and Above

3-Mar-2016 12/31/2020

PC57.13.7 New Standard for Current Transformers with a Maximum mA Secondary Current of 250 mA

30-Sep-10 12/31/2016

PC57.13.8 New Standard Requirements for Station Service Voltage Transformers

11-Dec-13 12/31/2017

Performance Characteristics

PAR Number Project Type Title Approval

Date PAR

Expiration

P60076-16 New Power Transformers - Part 16: Transformers for Wind Turbine Application

10-Dec-14 12/31/2018

PC57.164 New Guide for Establishing Short Circuit Withstand Capabilities of Liquid Immersed Power Transformers, Regulators, and Reactors

30-Jun-16 12/31/2020

PC57.105 Revision Guide for Application of Transformer Connections in Three-Phase Electrical Systems

26-Mar-15 12/31/2019

PC57.109 Revision Guide for Liquid-Immersed Transformers Through-Fault-Current Duration

26-Mar-15 12/31/2019

PC57.110 Revision

Recommended Practice for Establishing Liquid-Immersed and Dry-Type Power and Distribution Transformer Capability When Supplying Nonsinusoidal Load Currents

12-Jun-14 12/31/2018

PC57.120 Revision Guide for Loss Evaluation of Distribution and Power Transformers and Reactors

25-Mar-10 12/31/2016

PC57.158 New Guide for the Application of Tertiary and Stabilizing Windings in Power Transformers

15-May-12 12/31/2016

PC57.18.10 Revision Standard Practices and Requirements for Semiconductor Power Rectifier Transformers

30-Jun-16 12/31/2020

PC57.21 Revision Standard Requirements, Terminology, and Test Code for Shunt Reactors Rated Over 500 kVA

21-Aug-14 12/31/2018

Fall 2016 Standards Report Page 8 of 23

Power Transformers

PAR Number Project Type Title Approval

Date PAR

Expiration

P60214-2 New Tap-Changers - Part 2: Application Guide 12-Jun-14 12/31/2018

PC57.12.10 Revision Standard Requirements for Liquid-Immersed Power Transformers

26-Mar-15 12/31/2019

PC57.140 Revision Guide for Evaluation and Reconditioning of Liquid Immersed Power Transformers

31-Mar-11 12/31/2017

PC57.148 Revision Standard for Control Cabinets for Power Transformers

30-Jun-16 12/31/2020

PC57.93 Revision Guide for Installation and Maintenance of Liquid-Immersed Power Transformers

29-Mar-12 12/31/2018

P60214-2 New Tap-Changers - Part 2: Application Guide 12-Jun-14 12/31/2018

Standards

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.12.90-2015 /Cor 1

Corrigendum

Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers - Corrigendum 1: Editorial and Technical Corrections

30-Jun-16 12/31/2020

PC57.12.70-201 1/Cor 1

Corrigendum Standard Terminal Markings and Connections for Distribution and Power Transformers - Corrigendum 1: Correction of Annex A

5-Feb-2016 12/31/2019

PC57.163-2015 /Cor 1

Corrigendum Guide for Establishing Power Transformer Capability while under Geomagnetic Disturbances - Corrigendum 1

30-Jun-16 12/31/2020

Underground & Network Protectors

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.12.23 Revision

Standard for Submersible Single-Phase Transformers: 250 kVA and Smaller; High Voltage 34 500GrdY/19 920V and Below; Low Voltage 600 V and Below

21-Aug-14 12/31/2018

PC57.12.24 Revision

Standard for Submersible, Three-Phase Transformers, 3750 kVA and Smaller: High Voltage, 34 500 GrdY/19 920 Volts and Below; Low Voltage, 600 Volts and Below

9-Nov-2011 12/31/2017

PC57.12.40 Revision

Standard for Network, Three-Phase Transformers, 2500 kVA and Smaller; High Voltage, 34 500 V and Below; Low Voltage, 600 V and Below; Subway and Vault Types (Liquid Immersed)

30-Aug-12 12/31/2017

Fall 2016 Standards Report Page 9 of 23

Underground & Network Protectors

PAR Number Project Type Title Approval

Date PAR

Expiration

PC57.12.44 Revision Standard Requirements for Secondary Network Protectors

26-Mar-15 12/31/2019

P60076-16 New Power Transformers - Part 16: Transformers for Wind Turbine Application

10-Dec-14 12/31/2018

- Page 10 of 25-

VI. Transformers Standards Status (as of Sep 24, 2016)

Bushings Subcommittee

SC Chair: Peter Zhao email: [email protected] phone: (417) 345-5926

Standard Number

Working Group Chair Title Published Yr Expiration Yr

Status PAR

Expiration

C57.19.00 see organization chart IEEE Standard General Requirements and Test Procedure for Power Apparatus Bushings

2004 2020

Complete

C57.19.01 see organization chart IEEE Standard Performance Characteristics and Dimensions for Outdoor Apparatus Bushings

2000 2018

2017

65700-19-03 see organization chart IEC/IEEE International Standard -- Bushings for DC application 2014 2024

Complete

C57.19.100 see organization chart IEEE Guide for Application of Power Apparatus Bushings 2012 2022

Complete

Dielectric Test SC Chair: Ajith Varghese email: [email protected] phone: (262) 442-7197

Standard Number

Working Group Chair Title Published Yr Expiration Yr

Status PAR

Expiration

C57.113 see organization chart IEEE Recommended Practice for Partial Discharge Measurement in Liquid-Filled Power Transformers and Shunt Reactors

2010 2020

Complete

C57.127 see organization chart IEEE Guide for the Detection and Location of Acoustic Emissions from Partial Discharges in Oil-Immersed Power Transformers and Reactors

2007 2018

Draft Stage 2019

C57.138 see organization chart IEEE Recommended Practice for Routine Impulse Test for Distribution Transformers

1998 2018

Complete

C57.98 see organization chart IEEE Guide for Transformer Impulse Tests 2011 2021

Complete

Fall 2016 Standards Report Page 11 of 23

Distribution Transformers SC Chair: Steve Shullemail: [email protected]: (417) 625-6110

Standard Number

Working Group Chair Title Published Yr Expiration Yr

Status PAR

Expiration

C57.12.20 see organization chart IEEE Standard for Overhead-Type Distribution Transformers 500 kVA and Smaller: High Voltage, 34 500 V and Below; Low Voltage, 7970/13 800Y V and Below

2011 2021

Comment Res

2016

C57.12.37 see organization chart IEEE Standard for the Electronic Reporting of Distribution Transformer Test Data

2015 2025

Complete

C57.12.38 see organization chart IEEE Standard for Pad-Mounted-Type, Self-Cooled, Single-Phase Distribution Transformers 250 kVA and Smaller: High Voltage, 34 500 GrdY/19 920 V and Below; Low Voltage, 480/240 V and Below

2014 2024

Complete

C57.12.28 see organization chart IEEE Standard for Pad-Mounted Equipment--Enclosure Integrity 2014 2024

Complete

C57.12.29 see organization chart IEEE Standard for Pad-Mounted Equipment--Enclosure Integrity for Coastal Environments

2014 2024

Complete

C57.12.30 see organization chart IEEE Standard for Pole-Mounted Equipment--Enclosure Integrity for Coastal Environments

2010 2020

Complete

C57.12.31 see organization chart IEEE Standard for Pole-Mounted Equipment--Enclosure Integrity 2010 2020

Complete

C57.12.31-2010 /Cor 1

see organization chart IEEE Standard for Pole-Mounted Equipment--Enclosure Integrity - Corrigendum 1: Correction to the SCAB Corrosion Test in 4.5.6

2014 2024

Complete

C57.12.32 see organization chart IEEE Standard for Submersible Equipment - Enclosure Integrity 2002 2018

Draft Stage 2019

C57.12.34 see organization chart

IEEE Standard Requirements for Pad-Mounted, Compartmental-Type, Self-Cooled, Three-Phase Distribution Transformers, 10 MVA and Smaller; High-Voltage, 34.5 kV Nominal System Voltage and Below; Low-Voltage, 15 kV Nominal System Voltage and Below

2015 2025

Complete

Fall 2016 Standards Report Page 12 of 23

Distribution Transformers SC Chair: Steve Shullemail: [email protected]: (417) 625-6110

Standard Number

Working Group Chair Title Published Yr Expiration Yr

Status PAR

Expiration

C57.12.35 see organization chart IEEE Standard Bar Coding for Distribution Transformers and Step-Voltage Regulators

2013 2023

Complete

C57.12.36 see organization chart IEEE Standard Requirements for Liquid-Immersed Distribution Substation Transformers

2007 2018

Complete

C57.15 see organization chart IEEE Standard Requirements, Terminology, and Test Code for Step-Voltage Regulators

2009 2019

Ballot 2017

Dry Type Transformers SC Chair: Chuck Johnsonemail: [email protected]: (276) 688-3325

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

259 see organization chart IEEE Standard Test Procedure for Evaluation of Systems of Insulation for Dry-Type Specialty and General-Purpose Transformers

1999 2020

Complete

C57.12.01 see organization chart IEEE Standard for General Requirements for Dry-Type Distribution and Power Transformers

2015 2025

Draft Stage 2020

C57.12.51 see organization chart IEEE Standard for Ventilated Dry- Type Power Transformers, 501 kVA and Larger, Three-Phase, with High- Voltage 601 V to 34 500 V; Low- Voltage 208Y/120 V to 4160 V- General Requirements

2008 2018

Complete

C57.12.52 see organization chart IEEE Standard for Sealed Dry-Type Power Transformers, 501 kVA and Higher, Three-Phase, with High-Voltage 601 to 34500 Volts, Low-Voltage 208Y/120 to 4160 Volts--General Requirements

2012 2022

Complete

C57.12.58 see organization chart IEEE Guide for Conducting a Transient Voltage Analysis of a Dry-Type Transformer Coil

1991 2018

Pre ballot 2019

Fall 2016 Standards Report Page 13 of 23

Dry Type Transformers SC Chair: Chuck Johnsonemail: [email protected]: (276) 688-3325

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

C57.12.59 see organization chart IEEE Guide for Dry-Type Transformer Through-Fault Current Duration 2015 2025

Complete

C57.12.60 see organization chart IEEE Standard Test Procedure for Thermal Evaluation of Insulation Systems for Dry-Type Power and Distribution Transformers, Including Open-Wound, Solid-Cast, and Resin-Encapsulated Transformers

2009 2019

Draft Stage 2019

C57.12.60-2009 /Cor 1

see organization chart IEEE Standard Test Procedure for Thermal Evaluation of Insulation Systems for Dry-Type Power and Distribution Transformers, Including Open-Wound, Solid-Cast, and Resin-Encapsulated Transformers

2013 2023

Complete

C57.12.91 see organization chart IEEE Standard Test Code for Dry-Type Distribution and Power Transformers

2011 2021

Draft Stage 2020

C57.124 see organization chart IEEE Recommended Practice for the Detection of Partial Discharge and the Measurement of Apparent Charge in Dry-Type Transformers

1991 2019

Complete

C57.134 see organization chart IEEE Guide for Determination of Hottest-Spot Temperature in Dry-Type Transformers

2013 2023

Complete

C57.16 see organization chart IEEE Standard for Requirements, Terminology, and Test Code for Dry-Type Air-Core Series-Connected Reactors

2011 2021

Draft Stage 2020

C57.94 see organization chart IEEE Recommended Practice for Installation, Application, Operation, and Maintenance of Dry-Type Distribution and Power Transformers

20152025 Complete

C57.96 see organization chart IEEE Guide for Loading Dry-Type Distribution and Power Transformers 2013 2023

Complete

Fall 2016 Standards Report Page 14 of 23

HVDC Converter Xfmrs & Smoothing Reactors

SC Chair: Mike Sharp email: [email protected] phone: (416) 298-8108 x237

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

1277 see organization chart IEEE Standard General Requirements and Test Code for Dry-Type and Oil-Immersed Smoothing Reactors for DC Power Transmission

2010 2020

Complete

Instrument Transformers SC Chair: Ross McTaggart email: [email protected] phone: (416) 751-8570 x127

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

C57.13 see organization chart IEEE Standard Requirements for Instrument Transformers 2016 2026

Complete

C57.13.2 see organization chart IEEE Standard for Conformance Test Procedure for Instrument Transformers

2005 2020

Complete

C57.13.5 see organization chart IEEE Standard of Performance and Test Requirements for Instrument Transformers of a Nominal System Voltage of 115 kV and Above

2009 2019

Draft Stage 2020

C57.13.6 see organization chart IEEE Standard for High Accuracy Instrument Transformers 2005 2020

Complete

60076-C57.129 see organization chart Standard for General Requirements and Test Code for Oil-Immersed HVDC Converter Transformers

2007 2018

Comment Res

2018

Fall 2016 Standards Report Page 15 of 23

Insulating Fluids SC Chair: Dave Wallach email: [email protected] phone: (980) 373-4167

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

C57.104 see organization chart IEEE Guide for the Interpretation of Gases Generated in Oil-Immersed Transformers

2008 2018

Draft Stage 2017

C57.106 see organization chart IEEE Guide for Acceptance and Maintenance of Insulating Mineral Oil in Electrical Equipment

2015 2025

Complete

C57.111 see organization chart IEEE Guide for Acceptance of Silicone Insulating Fluid and Its Maintenance in Transformers

19892019 Complete

C57.121 see organization chart IEEE Guide for Acceptance and Maintenance of Less-Flammable Hydrocarbon Fluid in Transformers

1998 2019

Complete

C57.130 see organization chart IEEE Guide for the Use of Dissolved Gas Analysis Applied to Factory Temperature Rise Tests for the Evaluation of Mineral Oil-Immersed Transformers and Reactors

2015 2025

Complete

C57.139 see organization chart IEEE Guide for Dissolved Gas Analysis in Transformer Load Tap Changers

2015 2025

Complete

C57.146 see organization chart IEEE Guide for Interpretation of Gasses Generated in Silicone-Immersed Transformers

2005 2021

Complete

C57.147 see organization chart IEEE Guide for Acceptance and Maintenance of Natural Ester Fluids in Transformers

2008 2018

Comment Res

2018

C57.155 see organization chart IEEE Guide for Interpretation of Gases Generated in Natural Ester and Synthetic Ester-Immersed Transformers

2014 2024

Complete

C57.637 see organization chart IEEE Guide for the Reclamation of Mineral Insulating Oil and Criteria for Its Use

2015 2025

Complete

Fall 2016 Standards Report Page 16 of 23

Insulation Life SC Chair: Sheldon Kennedy email: [email protected] phone: (716) 896-6500 X105

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

1276 see organization chart IEEE Guide for the Application of High-Temperature Insulation Materials in Liquid-Immersed Power Transformers

1997 2018

Draft Res 2016

1538 see organization chart IEEE Guide for Determination of Maximum Winding Temperature Rise in Liquid-Filled Transformers

2000 2024

Complete

1538a see organization chart IEEE Guide for Determination of Maximum Winding-Temperature Rise in Liquid Immersed Transformers -- Amendment 1

2015 2025

Complete

C57.100 see organization chart IEEE Standard Test Procedure for Thermal Evaluation of Insulation Systems for Liquid-Immersed Distribution and Power Transformers

2011 2021

Complete

C57.119 see organization chart IEEE Recommended Practice for Performing Temperature Rise Tests on Oil-Immersed Power Transformers at Loads Beyond Nameplate Ratings

2001 2018

Comment Res

2018

C57.154 see organization chart

IEEE Standard for the Design, Testing, and Application of Liquid-Immersed Distribution, Power, and Regulating Transformers Using High-Temperature Insulation Systems and Operating at Elevated Temperatures

20122022 Complete

C57.91 see organization chart IEEE Guide for Loading Mineral-Oil-Immersed Transformers and Step-Voltage Regulators

2011 2021

Complete

C57.91-1995 /Cor 1

see organization chart IEEE Guide for Loading Mineral-Oil-Immersed Transformers - Corrigendum 1

2002 2018

Complete

Fall 2016 Standards Report Page 17 of 23

Performance Characteristics SC Chair: Ed teNyenhuis email: [email protected] phone: (905) 460-3210

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

C57.21 see organization chart IEEE Standard Requirements, Terminology, and Test Code for Shunt Reactors Rated Over 500 kVA

2008 2018

Draft Dev 2018

C57.32 see organization chart IEEE Standard for Requirements, Terminology, and Test Procedures for Neutral Grounding Devices

2015 2025

Complete

C57.105 see organization chart IEEE Guide for Application of Transformer Connections in Three-Phase Distribution Systems

1978 2018

Draft Stage 2019

C57.109 see organization chart IEEE Guide for Liquid-Immersed Transformers Through-Fault-Current Duration

1993 2018

Draft Stage 2019

C57.110 see organization chart IEEE Recommended Practice for Establishing Liquid-Filled and Dry-Type Power and Distribution Transformer Capability When Supplying Nonsinusoidal Load Currents

2008 2018

Draft Stage 2018

C57.120 see organization chart IEEE Loss Evaluation Guide for Power Transformers and Reactors 1991 2018

Comment Res

2016

C57.123 see organization chart IEEE Guide for Transformer Loss Measurement 2010 2020

Complete

C57.136 see organization chart IEEE Guide for Sound Level Abatement and Determination for Liquid-Immersed Power Transformers and Shunt Reactors Rated Over 500 kVA

2000 2018

Complete

C57.142 see organization chart IEEE Guide to Describe the Occurrence and Mitigation of Switching Transients Induced by Transformers, Switching Device, and System Interaction

2010 2020

Complete

C57.149 see organization chart IEEE Guide for the Application and Interpretation of Frequency Response Analysis for Oil-Immersed Transformers

2012 2022

Complete

Fall 2016 Standards Report Page 18 of 23

Performance Characteristics SC Chair: Ed teNyenhuis email: [email protected] phone: (905) 460-3210

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

C57.159 see organization chart IEEE Approved Draft Guide on Transformers for Application in Distributed Photovoltaic (DPV) Power Generation Systems

20162026 Complete

C57.18.10 see organization chart IEEE Standard Practices and Requirements for Semiconductor Power Rectifier Transformers

1998 2019

Draft Dev 2020

C57.18.10a see organization chart IEEE Standard for Practices and Requirements for Semiconductor Power Rectifier Transformers Amendment 1: Added Technical and Editorial Corrections

2008 2018

Complete

Power Transformers SC Chair: Bill Griesacker email: [email protected] phone: (412) 264-3266

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

638 see organization chart IEEE Standard for Qualification of Class 1E Transformers for Nuclear Power Generating Stations

2013 2023

Complete

60076-57-1202 see organization chart IEC/IEEE Approved Draft International Standard Requirements for Liquid Immersed Phase-Shifting Transformers

2016 2026

Complete

C57.131 see organization chart IEEE Standard Requirements for Tap Changers 2012 2022

Complete

C57.116 see organization chart IEEE Guide for Transformers Directly Connected to Generators 2014 2024

Complete

C57.12.10 see organization chart IEEE Standard Requirements for Liquid-Immersed Power Transformers 2010 2020

Draft Dev 2019

Fall 2016 Standards Report Page 19 of 23

Power Transformers SC Chair: Bill Griesacker email: [email protected] phone: (412) 264-3266

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

C57.12.10-2010 /Cor 1

see organization chart IEEE Standard Requirements for Liquid-Immersed Power Transformers--Corrigendum 1: Correction of 5.1.9--Sudden Pressure Relay

2012 2022

Complete

C57.12.10-2010 /Cor 2

see organization chart IEEE Standard Requirements for Liquid-Immersed Power Transformers -- Corrigendum 2: Correction of A.3.2.13 Autotransformer LTC application considerations

2013 2023

Complete

C57.93 see organization chart IEEE Guide for Installation and Maintenance of Liquid-Immersed Power Transformers

2007 2018

Draft Dev 2018

C57.125 see organization chart IEEE Guide for Failure Investigation, Documentation, Analysis, and Reporting for Power Transformers and Shunt Reactors

2015 2025

Complete

62032 see organization chart IEC 62032 Ed.1 (IEEE Std C57.135(TM)-2001): Guide for the Application, Specification and Testing of Phase-Shifting Transformers

2005

C57.135 see organization chart IEEE Guide for the Application, Specification, and Testing of Phase-Shifting Transformers

20112021 Complete

C57.140 see organization chart IEEE Guide for Evaluation and reconditioning of Liquid Immersed Power Transformers

2006 2018

Comment Res

2017

C57.143 see organization chart IEEE Guide for Application for Monitoring Equipment to Liquid-Immersed Transformers and Components

2012 2022

Complete

C57.148 see organization chart IEEE Standard for Control Cabinets for Power Transformers 2011 2021

Complete

C57.150 see organization chart IEEE Guide for the Transportation of Transformers and Reactors Rated 10 000 kVA or Higher

2012 2022

Complete

C57.153 see organization chart IEEE Guide for Paralleling Regulating Transformers 2015 2025

Complete

Fall 2016 Standards Report Page 20 of 23

Power Transformers SC Chair: Bill Griesacker email: [email protected] phone: (412) 264-3266

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

C57.156 see organization chart IEEE Approved Draft Guide for Tank Rupture Mitigation of Liquid-Immersed Power Transformers and Reactors

2016 2026

Complete

C57.157 see organization chart IEEE Guide for Conducting Functional Life Tests on Switch Contacts Used in Insulating Liquid--Immersed Transformers

2015 2025

Complete

C57.17 see organization chart IEEE Standard Requirements for Arc Furnace Transformers 2012 2022

Complete

Standards SC Chair: Jerry Murphy email: [email protected] phone: (407) 824-4194

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

C57.12.00 see organization chart IEEE Standard for General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers

2015 2025

Complete

C57.12.90 see organization chart 2015 2025

Complete

C57.12.70 see organization chart IEEE Standard for Standard Terminal Markings and Connections for Distribution and Power Transformers

2011 2021

Complete

C57.12.80 see organization chart IEEE Standard Terminology for Power and Distribution Transformers 2010 2020

Complete

C57.144 see organization chart IEEE Guide for Metric Conversion of Transformer Standards 2004 2020

Complete

C57.152 see organization chart IEEE Guide for Diagnostic Field Testing of Fluid-Filled Power Transformers, Regulators, andReactors

20132023 Complete

Fall 2016 Standards Report Page 21 of 23

Standards SC Chair: Jerry Murphy email: [email protected] phone: (407) 824-4194

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

C57.163 see organization chart IEEE Guide for Establishing Power Transformer Capability while under Geomagnetic Disturbances

2015 2025

Complete

Underground & Network Protectors SC Chair: Dan Mulkey email: [email protected] phone: (707) 776-7346

Standard Number

Working Group Chair Title Published Yr Expiration Yr

PAR Approval

PAR Expiration

C57.12.23 see organization chart IEEE Standard for Submersible Single-Phase Transformers: 167 kVA and Smaller; High Voltage 25 000 V and Below; Low Voltage 600 V and Below

2009 2019

Draft Dev 2018

C57.12.24 see organization chart IEEE Standard for Submersible, Three-Phase Transformers, 3750 kVA and Smaller: High Voltage, 34 500 GrdY/19 920 Volts and Below; Low Voltage, 600 Volts and Below

2009 2019

Comment Res

2017

C57.12.40 see organization chart IEEE Standard for Network, Three-Phase Transformers, 2500 kVA and Smaller; High Voltage, 34 500 GrdY/19 920 and Below; Low Voltage, 600 V and Below; Subway and Vault Types (Liquid Immersed)

2011 2021

Ballot 2017

C57.12.44 see organization chart IEEE Standard Requirements for Secondary Network Protectors 2014 2024

Draft Dev 2019

IEEE/PES Transformers Committee

Chair: Stephen Antosz

Vice Chair: Susan McNelly Secretary: Bruce Forsyth Treas: Greg Anderson

Past Chair: Donald Platts Std. Coordinator: Jim Graham

Instrument

Ross McTaggart

HVDC Converter Xfmrs &

Smoothing Reactors

Michael Sharp

Dry Type

Chuck W. Johnson

Distribution

Steve Shull

Bushing

Peter Zhao

Power

Bill Griesacker

UG & NW Protector

Dan Mulkey

Gen. Req. of Bushings

Rev of C57.19.00

K. Ellis

Bushing App. Guide

C57.19.100

T. Spitzer

OH Dist. Xfmrs

C57.12.20

A. Traut

Eqp Encl. Integrity

C57.12.28, 12.29,

12.30, 12.31, & 12.32

R. Olen

Elec Rpt of Test Data

IEEE 1388/C57.12.37

T. Callsen

General Req.

C57.12.01

R. Ballard

Req. & Test Code for

HVDC Con. Xfmr

C57.129

R. Dudley

Req. & Test Code for

HVDC Smoothing

Reactors IEEE 1277

U. Radbrandt

Step Volt. Regulator

C57.15

C. Colopy

Req for Inst. Xfmrs

C57.13

R. McTaggart

Test Proc. For Inst.

Xfmrs

C57.13.2

J.E. Smith

Test Req. for >= 115kV

PC57.13.5

P. Riffon

Req. for Elect. Rev.

Metering

C57.13.6

J.E. Smith

Guide for Monitoring

C57.143

D. Chu

Directly Connected

GSU C57.116

G. Hoffman

Req. for L.I. Power

Xfmrs C57.12.10

G. Hoffman

Std. Req. for Sec.

Network Xfmrs

C57.12.40

B. Kaplonski

UG 3ph Dist Xfmr

< 2500KVA

C57.12.24

G. Termini

Dry Type Air-Core

Reactors

C57.16

A. Del Rio

Performance

Characteristics

C57.19.01

S. Zhang

Req. & Testing of DC

Bushings

C57.19.03

L. Recksiedler

Req.for Vent. >500KVA

PC57.12.51

S. Som

Req. for Sealed

>500kVA

PC57.12.52

S. Kennedy

Thermal Eval. for Dry-Type

C57.12.60

R. Wicks

Transient Analysis

C57.12.58

R. Wicks

Dry-Type Through Fault

Current Duration

C57.12.59

P/ Payne

Test Code

C57.12.91

D. Foster

IEEE 638 – Std for 1E

Tx at Nuc Gen Stations

C. Swinderman

Guide for Phase-Shift

Xfmrs

C57.135

(Open)

Eval & Reconditioning

C57.140

P.Boman

Std for Control Cabinet

C57.148

J. Watson

Arc Furnace Xfmr

C57.17

R. Ganser

Installation & Maint

Guide C57.93

M. Lau

Req. for 3ph Pad Mount

C57.12.34

S. Schull

UG Self-Cool 1-ph

C57.12.23

A. Traut

Pad-Mount 1ph Self-

Cool <2500kVA

C57.12.38

A. Ghafourian

Bar Coding

C57.12.35

L. Matthews

Perf Characteristics for Distr Xfmr Bushings

PC57.19.02 S. Shull

Transportation Guide

PC57.150

G. Anderson

Tank Rupture

Mitigation C57.156

P. Zhao

Requirements for LTC

C57.131

C. Colopy

Dry-Type Hottest Spot

C57.134

P. Payne

Dry Type Op & Maint.

Guide

C57.94

D. Stankes

Dist. Sub. Xfmrs

C57.12.36

J. Murphy

Guide for Paralleling

C57.153

E.T. Jauch

Page 22 of 23

Failure Investigations

C57.125

W. Binder

Functional Life Tests

for DETC C57.157

P. Hopkinson

Req. for mA CT

C57.13.7

H. Alton

Tank Pressure

Coordination

C57.12.39

C. Gaytan

Revised by J.Graham

19 Oct, 2016

Std Requirements

Phase Shifters

P60076-57-1202

R. Ahuja

Requirements for

SSVTs

PC57.13.8

D. Wallace

TF to compare req’s of composite vs traditional

bushings

Loading Guide for Dry

Type Xfmrs

C57.96

R. Marek

Dry-Type PD & Apparent

Charge Measurement

C57.124

T. Prevost

Std. Req. for Sec.

Network Protectors

C57.12.44

W. Wimmer

Vent Dry-Type Network

Xfmrs <=2500KVA

C57.12.57

A. Robinson

Perf Characteristics for GSU Bushings PC57.19.04 S. Digby

IEEE/PES Transformers Committee

Chair: Stephen Antosz

Vice Chair: Susan McNelly Secretary: Bruce Forsyth Treas: Greg Anderson

Past Chair: Donald Platts Std. Coordinator: Jim Graham

Insulating Fluids

Dave Wallach

Insulation Life

Sheldon Kennedy

Dielectric Test

Ajith Varghese

Performance Characteristics

Ed teNyenhuis

Standards

Jerry Murphy

Req. & Test Code for

Shunt Reactors

>500kVA C57.21

S.Som

Semicon Rectifier Xfmrs

C57.18.10

S. Kennedy

App. Guide for Xfmr

Connections

C57.105

A. Bromley

Sound Level Abatement

C57.136

(Open)

Impulse Test Guide

for Dist Tx C57.138

A Molden

Rev of Low Freq. Tests

B. Poulin

Guide for Acoustic PD

C57.127

D. Gross

DGA Guide

C57.104

C. Beauchemin

Mineral Oil

C57.106

R. Rasor

Silicone Oil

C57.111

P. Boman

DGA During Thermal

Test C57.130

J. Thompson

Less Fammmable

H-C Fluid C57.121

D. Sundin

Loading Guide

C57.91

Don Duckett

TF Investigate Use of

Furan Testing

S. Xu

Max. Wdg Temp Rise

IEEE 1538

R. Marek

Temp Rise Test Above

NP Rating C57.119

G. Kennedy

Thermal Eval Test

C57.100

R. Wicks

Cont Rev of C57.12.00

S. Snyder

Cont. Rev of C57.12.90

S. Antosz

Metric Conversion

C57.144

P. Balma

Terminology

C57.12.80

J.Graham

Meetings

Greg Anderson

Through-Fault Current

Duration

C57.109

V. Mehrotra

Non-Sinusoidal Load

Current C57.110

R. Marek

Xfmr Loss

Measurement

C57.123

E. teNyenhuis

Short Circuit Testing

PC57.133

M. Fortin

Sw Transients CB/Xfmr

C57.142

R. Degeneff

App. Of High Temp

Insulation IEEE 1276

R. Wicks

DGA in LTC

C57.139

D. Wallach

TF – Moisture in

Insulation

B. Rasor

Oil Reclamation

C57. 637

J. Thompson

DGA in Silicone

C57.146

J. Murphy

Website Development

S. McNelly

Terminal Markings &

Connections

S. Schull C57.12.70

Diagnostic Field Testing

J. Verner

IEEE C57.152 /(62)Neutral Grounding

Devices PC57.32

S. Kennedy

Educational

Development

T. Prevost

WG on Dielectric

Test Table

P. Hopkinson

Sound Level

Measurement

PC57.151

TF - Temp Rise Test -

C57.12.90, Clause 11

P. Powell

IEEE /IEC Cross

Reference TF

V. Mehrotra

Guide to Freq Response

Analysis C57.149

C. Sweetser

PCS Rev to

Test Code- 12.90

M. Perkins

PCS Rev. to

Gen Req - 12.00

T. Ansari

PD Measurement

On Bushings & Inst Tx

C57.160

T. Hochanh

Rev of Transient

Voltage Test

P. Riffon/P. Heinzig

WG- External Dielectric

Test Clearance

E. Davis

Page 23 of 23

WG – Std Req. Hi Temp

Insulation C57.154

R. Marek

DGA in Ester Fluids

C57.155

P. Boman

TF for Particle Count

M. Scarborough

App Guide for Ester

Fluids -C57.147

P. McShane

Windfarm Transformers

P60076-16

D. Buckmaster

TF – Winding Temp

Indicators

P. McClure

Tertiary & Stabilizing

Windings PC57.158

E. Betancourt

Loss Evaluation Guide

PC57.120

R Verdolinm

Revised J.Graham

19 Oct, 2016

Moisture in Insulation

PC57.162

T. Prevost

Committee

History

P. Balma

WG- Guide for DFR

testing PC57.161

A. Naderian

DPV Grid Transformers

PC57.159

H. Shertukde

PD Measurement

C57.113

B. Poulin

Transformer Capability

under GMD J. Verner

IEEE C57.163

TF Consolidation of Fluids Guides

T.Prevost


Recommended