IHEP-02 1.3 GHz 9-cell Cavity R&D Status and Plan

Date post: 20-Mar-2016
Category:
Upload: stacey
View: 39 times
Download: 4 times
Share this document with a friend
Description:
IHEP-02 1.3 GHz 9-cell Cavity R&D Status and Plan. GAO Jie, ZHAO Tongxian, ZHAI Jiyuan, LI Zhongquan, LI Dazhang, LIU Zhenchao Institute of High Energy Physics, Chinese Academy of Sciences CHEN Jinzhe, QIAO Jianqiang Beijing Hejieli Science and Technology Development Co. Ltd. - PowerPoint PPT Presentation
23
IHEP-02 1.3 GHz 9-cell Cavity R&D Status and Plan The Third IHEP-KEK 1.3GHz SC Technology Collaboration Meeting Dec. 7-8, 2010, IHEP, Beijing GAO Jie, ZHAO Tongxian, ZHAI Jiyuan, LI Zhongquan, LI Dazhang, LIU Zhenchao Institute of High Energy Physics, Chinese Academy of Sciences CHEN Jinzhe, QIAO Jianqiang Beijing Hejieli Science and Technology Development Co. Ltd. YUAN Hong, YU Huai, WANG Jinxue Beijing Institute of Aviation Materials
Transcript

IHEP-02 1.3 GHz 9-cell CavityR&D Status and Plan

The Third IHEP-KEK 1.3GHz SC Technology Collaboration MeetingDec. 7-8, 2010, IHEP, Beijing

GAO Jie, ZHAO Tongxian, ZHAI Jiyuan, LI Zhongquan, LI Dazhang, LIU ZhenchaoInstitute of High Energy Physics, Chinese Academy of Sciences

CHEN Jinzhe, QIAO JianqiangBeijing Hejieli Science and Technology Development Co. Ltd.

YUAN Hong, YU Huai, WANG JinxueBeijing Institute of Aviation Materials

OUTLINE

• Backgound of the IHEP 9-cell cavity

• IHEP-02 R&D goal and schedule

• IHEP-02 Fabrication Procedure

• HOM coupler

BACKGROUND

IHEP-01: Low-Loss Type 9-cell Cavity with Bare Tubes (VT) IHEP-02: Low-Loss Type 9-cell Cavity with Full End Groups (VT&HT)

IHEP-01 First Vertical Test Result Of IHEP-01

20MV/m (2010.07.01@KEK,STF)

IHEP-02 R&D GOAL, SCHEDULE

• IHEP-02 with full end groups for the horizontal test

• Achieve the requirement of ILC 25-35MV/m for the vertical test 20-31.5MV/m for the horizontal test

IHEP-02 2010-1011 2010 2011Fabrication 2010.06-2011.01 IHEP

Surface treatment 2011.02-03 IHEP

Vertical test 2011.04-06 Other Lab

weld helium vessel 2011.07 IHEP

assemble and HT 2011.08-12 IHEP

OUTLINE

• Backgound of the IHEP 9-cell cavity

• IHEP-02 R&D goal and schedule

• IHEP-02 Fabrication Procedure

• HOM coupler

Large Grain Niobium Sheets

The cavity material• disks from Ningxia OTIC (Nov., 2008)

• inspection, CP, annealing

• ultrasonic and eddy current scanning tests

• mechanical behavior sample test at room temp. and 4K• RRR measurement

• We do that when we made the IHEP-01

Nb sheets thickness measurement

The problem : uneven thickness like the above sketch map(1) will lead to large crack, the Uniform thickness maybe good, but we think uneven thickness like the good cketch map(2) may be better.

1: NOT GOOD

2: GOOD

IHEP-02 Progress

Annealing @900OC, 3HoursHeating and cooling speed : 300OC/H4: After annealing, we deep drawing the half cell again.

1: deep drawing 2: trimmingAfter trimming,Waiting for measurement

Some half cells3: Annealing after first trimming

Comparing of the twice deep drawing

37# 0.26 0.22 6# 0.33 0.11 1# 0.15 0.10 9# 0.22 0.17 15# 0.16 0.17 36# 0.14 0.05 11# 0.03 0.16 43# 0.22 0.10 17# 0.10 0.10 4# 0.19 0.09

Half cell No.

After the first deep drawing

After the second deep drawing

Standard deviation

IHEP-02 Progress

The half cells

Frequency measurement of the half cell

length, iris and equator diameter measurement

The measurement dataCell No. Freq. Q

MHz  7 1275.25 2300.00 4 1275.23 2000.00 36 1273.93 1900.00 33 1273.90 2000.00 20 1277.40 2200.00 17 1274.08 2100.00 15 1272.08 2000.00 34 1272.96 2090.00 6 1275.57 2150.00 9 1275.62 2350.00 11 1275.48 2800.00 1 1274.27 2100.00 42 1274.71 3000.00 13 1274.70 2700.00 43 1273.64 2900.00 19 1273.90 2900.00 37 1274.53 2200.00 35 1280.45 2400.00 8 1274.73 2900.00 18 1273.32 2680.00 2 1275.91 2700.00

Cell No.

Average/ mm

Standard

deviation/ mm

6 2.63 0.19 2 2.43 0.21 8 2.57 0.24

15 2.59 0.06 34 2.43 0.25 11 2.53 0.19 20 2.33 0.33 18 2.50 0.10 36 2.54 0.11 42 2.59 0.21 43 2.55 0.1613 2.13 0.26 4 2.62 0.16

35 2.52 0.35 19 2.59 0.11 9 2.47 0.21

17 2.64 0.09 1 2.61 0.20 7 2.42 0.20

33 2.55 0.10 37 2.60 0.12

Cell No.

Average/ mm

Standard deviation

/ mm6 60.47 0.23 2 60.25 0.17 8 60.28 0.24

15 60.55 0.05 34 60.28 0.25 11 60.62 0.25 20 60.56 0.14 18 60.53 0.15 36 60.29 0.15 42 60.40 0.27 43 60.74 0.23 13 60.60 0.24 4 60.43 0.24

35 60.24 0.15 19 60.49 0.16 9 60.52 0.12

17 60.35 0.22 1 60.39 0.23 7 60.64 0.19

33 60.51 0.15 37 60.30 0.04

Iris wall thickness

Iris diameter

Frequency of the half cell

IHEP-02 Progress Equator roundness reshaping 20 μm chemical polishing of half cells,

ultrasonic cleaning, rinsing, 3 μm chemical polishing at iris area, Rinsing,

EBW.

New Fixtures for cell equator roundness equator roundness reshaping

equator roundness reshaping result

37# 0.22 0.06 6# 0.11 0.06 1# 0.10 0.03 9# 0.17 0.04

15# 0.17 0.04 36# 0.05 0.03 11# 0.16 0.06 17# 0.10 0.05 4# 0.09 0.03

18# 0.04 0.04

No.

Before reshaping

after reshaping

Standard deviation

IHEP-02 Progress

Dumbell without stiffening ring Dumbell with stiffening ring

stiffening rings forming

stiffening rings forming

OUTLINE

• Backgound of the IHEP 9-cell cavity

• IHEP-02 R&D goal and schedule

• IHEP-02 Fabrication Procedure

• HOM coupler

IHEP-01 Mode; Freq. --- R/Q

Boundary conditions: Electric-Electric & Magnetic-Magnetic

IHEP 01 QE CALCULATION

TM010 : 1.3GHz , Qe2.88e+010 TE111 : Freq. 1.6023GHz , 1.6034GHz Qe: 4.24e+004 , 7.85e+004

TM110 : 1.87GHz , Qe1.37e+004 TM011 : 2.16GHz Qe : 2.97e+004

CST M

odel

Lines per wavelength 55

Lower mesh limit 15

Mesh line ratio limit 10LL cavity with Tesla HOM coupler

HOM coupler material

Nb Stick RRR300 D60 , L500 5 couplers housingNb sheet RRR300 200×150×8.8 6 Inner conductors

5 Tesla HOM couplers

IHEP-02 next plan

• HOM coupler fabrication will be speed up.

• End groups fabrication

• Cavity Welding

• IHEP-02 will be finished at early 2011

Summary

• The multi-cell cavity is one of the key components for 1.3 GHz SRF technology R&D of IHEP.

• We have developed effective methods, procedures, tools and facilities to fabricate and tune the 9-cell cavity.

• The IHEP-01 finished fabrication and EBW, surface treated at IHEP and tested at KEK STF in July 2010. 20MV/m. It will be test at kek again in early 2011.

• The IHEP-02 will finish in early 2011, surface treated at IHEP and test in middle 2011.

Thanks for your attention