+ All Categories
Home > Documents > IJEPES-D-13-01721

IJEPES-D-13-01721

Date post: 03-Jun-2018
Category:
Upload: vasukoneti5124
View: 216 times
Download: 0 times
Share this document with a friend

of 23

Transcript
  • 8/11/2019 IJEPES-D-13-01721

    1/23

    International Journal of

    Electrical Power and Energy Systems

    Manuscript Draft

    Manuscript Number: IJEPES-D-13-01721

    Title: Service Restoration for Unbalanced Distribution Networks Using aCombination Two Heuristic Methods

    Article Type: Research Paper

    Keywords: service restoration, unbalanced distribution network, switches

    index, graph-based, three phase load flow

    Abstract: In this paper, two heuristic methods are proposed to find

    effective and fast solution in unbalanced three phase distribution

    networks. Switch selection indices based on analytically approach and

    practicable heuristic graph-based method are proposed for solving the

    service restoration problem in unbalanced distribution networks. The

    problem formulation proposed, consists of three different objectivefunctions: First, minimizing the de-energized customers' load, second,

    minimizing the number of switching operation, and finally, customer's

    priority. A suitable assignment of switch indices to all tie switches

    (ts) in networks are used to find best solution and decrease number of

    switching operation. New graph-based approach for finding best

    sectionalizes switch (ss) and minimizing voltage drop's amount is

    utilized. The validity of these approaches has been tested on the two

    unbalanced three phase distribution networks. Results have been presented

    for modified IEEE 13-node and IEEE 37-node test case. The fastness and

    effectiveness convergence of these approaches helps finding best solution

    for service restoration problem.

  • 8/11/2019 IJEPES-D-13-01721

    2/23

    1

    Service Restoration for Unbalanced Distribution Networks Using a Combination Two

    Heuristic Methods

    Meysam Gholami

    a,*

    , Jamal Moshtagh

    b

    a,* ,Department of electrical engineering, university of Kurdistan, sanandaj, Iran.

    b, Department of electrical engineering, university of Kurdistan, sanandaj, Iran.

    (a,[email protected],tel:+989181706749)

    (b

    ,[email protected],tel:+988716660073)

    ABSTRACT

    In this paper, two heuristic methods are proposed to find effective and fast solution in

    unbalanced three phase distribution networks. Switch selection indices based on analytically

    approach and practicable heuristic graph-based method are proposed for solving the service

    restoration problem in unbalanced distribution networks. The problem formulation proposed,

    consists of three different objective functions: First, minimizing the de-energized customers

    load, second, minimizing the number of switching operation, and finally, customers priority.

    A suitable assignment of switch indices to all tie switches (ts) in networks are used to find

    best solution and decrease number of switching operation. New graph-based approach for

    finding best sectionalizes switch (ss) and minimizing voltage drops amountis utilized. The

    validity of these approaches has been tested on the two unbalanced three phase distribution

    networks. Results have been presented for modified IEEE 13-node and IEEE 37-node test

    case. The fastness and effectiveness convergence of these approaches helps finding best

    solution for service restoration problem.

    Key wordsservice restoration, unbalanced distribution network, switches index, graph-

    based, three phase load flow.

    anuscript

    ck here to view linked References

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]://ees.elsevier.com/ijepes/viewRCResults.aspx?pdf=1&docID=8830&rev=0&fileID=176957&msid={DE9CFA2E-68AA-4381-A3AF-1359C2266D85}http://ees.elsevier.com/ijepes/viewRCResults.aspx?pdf=1&docID=8830&rev=0&fileID=176957&msid={DE9CFA2E-68AA-4381-A3AF-1359C2266D85}mailto:[email protected]:[email protected]
  • 8/11/2019 IJEPES-D-13-01721

    3/23

    2

    1. Introduction

    With significant extension of the modern power distribution networks in the world, the

    likelihood of occurrence of fault and then blackout for one or more area will increase.

    Therefore, customers satisfaction and service reliability are the important topic where most

    of the paper localizes in this issue. Revenue earned by the Power Distribution Companies and

    customerssatisfaction is closely depending on reliability in distribution networks. In order to

    satisfy users demand and maintain profit of power Supply Company, it is necessary to

    restoring power service as soon as possible [1]. Due to a high number of switches, feeders

    and branches in typical distribution systems, it is not easy to restore an out-of-service area

    solely depending on the past experiences of human operators [2]. Therefore, with the advent

    of quick computers and changing technology, to reduce the out of service area as efficiently

    as possible, a computer aided decision supports assist the operators. How to arriving a fast

    and effective service restoration in power distribution networks (PDNs), considering

    unbalanced distribution network is of major concern in this paper. Protection devices in

    network detect the fault location, when a fault is occurred in the PDN. After isolating the

    fault by operation line switches, the PDN is divided to three sections: First, the upstream

    section that is supplied from same feeder, second, the downstream un-faulted section that are

    transferred to neighboring feeders according to presented approaches in this paper, and

    finally, damage buses and lines that are isolated from network. In service restoration problem,

    several issues must also be considered that are described as follow:

    Service restoration plan must be restored maximum safe out-of-service loads.

    Service restoration plan is implemented by changing switches state in PDNs,

    therefore, the time taken by the service restoration depends on the number of

    switching operation. Therefore, the number of switching operation should be kept to

    minimum as possible.

  • 8/11/2019 IJEPES-D-13-01721

    4/23

    3

    Hospital, police station, firehouse, etc, are the highest priority in PDNs. This issue

    must be considered in service restoration plan that the supply must be restored to

    highest priority customers.

    In each PDN, most important constraint is radial structure due to various reasons,

    such as ease of fault location detection, fault isolation and protective devices

    coordination. When the structure of the network is changed during the service

    restoration, this constraint must be kept on.

    Buses voltage, lines current and elements loading also changes during the service

    restoration plan. Therefore, it is important that these constraints dont cross their

    respective operational limits.

    Customers satisfaction and reliability ofdistribution networks are closely dependent

    on interruption frequency and duration. Therefore, the restoration plan runtime must

    be minimized for finding a quick solution.

    In past years, many methods have been proposed to find solution for restoration problem

    from different perspective. Considering complexity PDNs, analytic method for solving the

    restoration problem can hardly be applied. Therefore, heuristic search method [3-8] or expert

    system approach [9] have been adopted. In [10] G-net inference mechanism with operation

    rules is applied. In [11] Petri Net combined with a rule-based expert systems have been

    applied to implement the service restoration. In [12] fuzzy cause-effect networks are used to

    model the heuristic knowledge inference involved in the restoration plan. In [13] a fuzzy

    decision-making approach has been applied to determine the most desirable restoration plan

    with consideration different practical factors, but fuzzy method doesnt guarantee the optimal

    solution. In [14] non- dominated sorting genetic algorithm-II (NSGA-II) for solving the

    service restoration problem is presented and to reduce the software runtime, a faster version

    of NSGA-II has been implemented. In [15] mathematical programming is presented to

  • 8/11/2019 IJEPES-D-13-01721

    5/23

    4

    reconfigure the network to restore un-faulted section of the system. In [16, 17] combination

    methods are applied. In [16] objective functions are modeled with fuzzy sets, and then

    optimization problem is solved by the Genetic Algorithm (GA). [17] consist of two stages:

    First, the fuzzy multi criteria evaluation, and afterward, the Grey relational analysis. In [18],

    service restoration with Load curtailment of in-service customers via direct load control has

    been implemented. In [19], reliability assessment of complex radial distribution systems is

    presented, however this paper simplifies the restoration plan. In [20, 21], restoration problem

    in distribution network with dispersed generation is implemented. In this paper, a fast and

    effective methods based on two new heuristic algorithms for service restoration in

    unbalanced PDNs ispresented. Unbalanced distribution network, customers priority, buses

    voltage, lines current, equipments loading and minimum software runtime consideration, are

    the main features of the proposed method.

    This paper is organized as follows: Section 2 describes the problem formulation of a

    typical restoration problem. In section 3, indices for ranking the networks switch are

    described. In section 4, graph-based method is described. Section 5 reviews two new heuristic

    algorithms for service restoration. Section 6 briefly describes three-phase load flow program

    for fast response to the network change inducted by system reconfiguration. Section 7 shows

    a numerical example to demonstrate the fastness and effectiveness of the proposed methods

    and the conclusion are drawn in section 8 finally.

    2. Problem formulation

    Service restoration in unbalanced distribution networks considering customers priority

    are formulated as multi-constraint and multi-objective optimization problem. In this paper,

    three different objective functions are presented. Maximizing total load to be restored,

    minimizing the number of the switching operations and maximizing priority load restored are

  • 8/11/2019 IJEPES-D-13-01721

    6/23

    5

    these objective functions. Besides, important constraints consists of network radial structure,

    buses voltage, lines current, equipments loading have also been considered in this paper.

    Objective function briefly:

    (1)

    (2)

    (3)

    Where

    Energized loads in network;

    Total buses are restorable;

    Buses with high priority those are restorable;

    Number of switching operation;

    Constraints:

    1) Radial network structure should be maintained.

    2)

    Bus voltage limits (for all buses):

    (4)

    Where

    Minimum acceptable bus voltage;

    Voltage at bus k, phase p;

    Maximum acceptable bus voltage.

    3) Line current limits (for all lines):

    (5)

    Where

    Minimum acceptable line current;

    Current in line j, phase p;

    Maximum acceptable line current.

    tNk

    kLmax

    HPNk

    kLmax

    opNmin

    kL

    tN

    HPN

    opN

    maxmin

    k

    p

    kk VVV

    min

    kV

    p

    kV

    max

    kV

    maxmin

    j

    p

    jj III

    p

    jI

    max

    jI

    min

    jI

  • 8/11/2019 IJEPES-D-13-01721

    7/23

    6

    4) Equipment loading limits (for transformers):

    (6)

    Where

    Loading for i transformer;

    Rated loading for i transformer.

    Operational constraint can be obtained from three phase load flow calculation. In actual

    practice, the minimum limit of the line current should not be taken and, in fact, this limit has

    been taken as zero [14]. In this study, we are used two heuristic approaches based on switch

    indices and graph-based for finding best solution to restore maximum total customers in de-

    energized area. In most restoration plan, there are several plans available for a restoration

    problem, however, how to select best plan, two methods must describe. These methods are

    presented in next sections.

    3. Switch ranking

    In this paper, two switch indices for best selection have been used. the base of the

    proposed algorithm for these indices is voltage drop. A first and most important index is VD

    that is proportionate with voltage drop between substation bus and primary side of each tie

    switch (ts). For each ts, VD is defined as follow:

    (7)

    Where

    Sum of active loads between substation bus and primary side of tie switch i, for each

    three phase;

    Sum of reactive loads between substation bus and primary side of tie switch i, for

    each three phase;

    Sum of real segment of positive impedance sequence of lines between substation bus

    max

    itr

    itr

    max

    ii trtr

    cbapV

    XQRPVD i

    p

    ii

    p

    i ,,

    p

    iP

    p

    iQ

    iR

  • 8/11/2019 IJEPES-D-13-01721

    8/23

    7

    and primary side of i tie switch;

    Sum of imaginary segment of positive impedance sequence of lines between

    substation bus and primary side of i tie switch;

    and V is substation voltage.

    This index is shown in Fig.1. Suppose that one fault took place at point A. Therefore,

    area1 is downstream un-faulted area and ts1 is one candidate switch for service restoration

    implementation. For ts1, VD is obtained from node number 5, 6, that is proportionate with

    direction1 (dir1). ts3 is another candidate switch for service restoration implementation. For

    ts3, VD is obtained from node number 10, 12 and 13 that is proportionate with direction2

    (dir2). A second index (Zpath) is direction impedance (per-unit) for lines lying in the path

    between the secondary side of each ts and end buses in network. For each ts, this index is

    defined as follow:

    (8)

    Where Zbis positive impedance sequence of branch b and Nbris lines lying in the path

    between the secondary side of each ts and end buses in network. This index is shown in Fig.1.

    Suppose that one fault took place at point B. Therefore, area2 is downstream un-faulted area

    and ts2 is one candidate switch for service restoration implementation. For ts2, Zpathis

    impedance of direction3 and direction4 (dir3 and dir4). These utilized indices, help both

    reducing the solution search space and ranking switches to find best solution for service

    restoration plan. Indeed, when search space is reduced then runtime software will decrease

    and this issue makes guarantee to fast service restoration implementation. In next section

    graph-based method is described and how to utilize these methods is described in section 5.

    4. Graph-based method

    brNb

    bpa th ZZ

    iX

  • 8/11/2019 IJEPES-D-13-01721

    9/23

    8

    Before description this method for finding the minimum voltage drop in network (tree or

    graph) we must define three groups. For any bus (node) belongs to the graph, the following

    definition is valid:

    Sub-graph D, which consists of nodes that have already been added to the graph.

    Sub-graph UD, which consists of nodes that have not been added to the graph.

    Sub-graph B, which consists of branches that can connect nodes from sub-graph D.

    When one branch from tree with minimal weights is selected in each iteration, one node

    (node S) of each branch is in sub-graph D and the other node (node R) is in sub-graph UD.

    Therefore, node R is added to the sub-graph D and deleted from sub-graph UD. This method

    is shown in Fig. 2. This approach is utilized for finding best sectionalizes switch (ss) after

    finding best tie switches (ts). The evaluation of weighting coefficient has been described in

    follow:

    (9)

    Where

    X is branch state (0 for close branches and inf for open branches), Zbis positive sequence

    impedance of branch b, Nbris branches lying in the path between the secondary node (node

    R) of branch is in sub-graph UD and substation node. The starting state and the major steps in

    the first iteration has been described as follows:

    Starting state:

    1, 2 are branches between sub-graph D and sub-graph UD.

    First iteration (selection of branch with minimum weight, (a) in Fig. 2):

    Weighting coefficient for branch 1 and 2:

    W1= X1+Z1 and W2= X2+Z2

    Nbrb

    bZXW

    B

    UD

    D

    2,1

    12,11,10,9,8,7,6,5,4,3,2

    1

  • 8/11/2019 IJEPES-D-13-01721

    10/23

    9

    Therefore, branch with minimum of W is selected (suppose this is W1).

    Updating sub-graphs:

    Second iteration (selection of branch with minimum weight, (b) in Fig. 2):

    Weighting coefficient for branch 2, 3 and 4:

    W2= X2+Z2 , W3=X3+Z1+ Z3 and W4= X4+Z1+ Z4

    Therefore, branch with minimum of W is selected (suppose this is W2).

    Updating sub-graphs:

    Updating D, UD and B will be done for next iteration. When sub-graph UD was emptied,

    the iteration procedure is finished and after last iteration, all branches belong sub-graph B

    must be opened. This state that is final structure is shown in (f), Fig. 2.

    5. Service restoration algorithm

    To describe the problem of multi-objective service restoration in distribution networks,

    the faults scenario must be described. When a short-circuitsfault is occurred on the feeder,

    circuit breaker at the outset of feeder is operated to clear the fault. All boundary line switches

    are operating to isolate the faulted area. The feeders circuit breaker is then closing to restore

    the upstream customers. For the downstream area, best switch indices for best switches

    selection based on first heuristic approach is implemented. This approach is described in this

    section. The proposed approach is calculated fast and implemented using remotely controlled

    switches in unbalanced distribution networks. In this paper, three objective functions are

    prioritizing as: 1) maximizing the amount of total load to be restored, 2) minimizing the

    B

    UD

    D

    4,3,2

    12,11,10,9,8,7,6,5,4,3

    2,1

    B

    UD

    D

    5,4,3

    12,11,10,9,8,7,6,5,4

    3,2,1

  • 8/11/2019 IJEPES-D-13-01721

    11/23

    10

    number of the switching operation and 3) customers priority consideration. Proposed

    algorithm considering five steps are described in follow.

    Step 1) isolation the fault;

    Step 2) creation the candidate tie switches list;

    Step3)selection one ts due to first proposed algorithm, three phase unbalanced load flow

    implementation, and network constraints survey. If no constraints violation

    exists, go to step 5;

    Step4)selection next ts due to first proposed algorithm, selection respective sectionalize

    switch (ss) due to graph-based method, three phase unbalanced load flow

    implementation and network constraints survey. If no constraints violation exists

    go to step 5, else repeat this step;

    Step 5) return best service restoration plan.

    Step 1) isolating the fault

    When a fault is occurring in each PDN, faults line, sending and receiving bus sides for

    this line are detected. The adjacent buses and lines are wended in each direction sequentially

    and to clear the fault, first circuit breaker in these directions is founded and operated.

    Therefore, feeder that fault has been occurred on it and feeders circuit breaker is detected.

    For fault isolation, the adjacent buses and lines are wended in each direction sequentially.

    The first switches in each direction is found and operated. Therefore three areas are formed in

    network: First, the upstream out-of-service area that is first restored by closing the feeders

    circuit breaker, second, the damage area that must been repaired, and finally, the downstream

    un-faulted area then is transferred to the neighboring feeders according to the proposed

    algorithms.

    Step 2) creation candidate switch lists

  • 8/11/2019 IJEPES-D-13-01721

    12/23

    11

    Candidate tie switches are identified from energized feeder that can connect directly into

    the out-of-service area. Candidate sectionalizes switches (ss) that are located in the out-of-

    service area and identified from graph-based method. For each candidate ts, VD and Zpathare

    obtained. In this section, new weighting factor is utilized to converts of these two indices into

    an equivalent single index. Final index has been described as follow:

    (10)

    Where and are two weight factors, that have two continues amounts between 0 and 1

    (0< and

  • 8/11/2019 IJEPES-D-13-01721

    13/23

    12

    4.4) if an overload or voltage violation exists, open previously ts, close previously ss and

    repeat step 4.1, 4.2, 4.3, until iteration procedure is finished. If no restoration plan exists, go

    to step 4.5.

    4.5) first switch pair (ts, ss) in the step 4 is operated and for restoration procedure

    continuance, this step (step 4) is repeated.

    Step 5) restoration plan (final step).

    In this step sequence operations for ts and ss that have been selected is described. First, all

    ss that have been selected must be opened and afterward, all of ts that have been selected

    must be closed. To illustrate the fastness and effectiveness of the proposed algorithm, two

    unbalanced distribution networks consists of: modified IEEE 13-node and IEEE 37-node

    have been tested and presented in section 7.

    6. Fast load flow technique

    After network restoration, the three phase unbalanced distribution load flow has to be

    calculated to examine the voltage, current and capacity constraints for feeders, lines and

    elements with additional of new load points. In this paper, we are used fast load flow

    technique for fast service restoration. For receipt more information about this technique,

    please refers to [22]. In this section, summary of this technique [22] is described. The

    fundamental idea discussed here is how to obtain the power flow solution by using the

    elements of a unique quasi-symmetric matrix called TRX in the iterative process. The

    proposed TRX matrix constitutes a complete database by including information of network

    topology structure as well as branch impedances of the distribution feeder. The method is

    described in six steps: data preparation, initialization, current and voltage calculations, quasi-

    symmetric matrix calculation, and convergence process. This formulation is given including

    three phase line shunt-admittances and loads are modeled as constant power. The input data

  • 8/11/2019 IJEPES-D-13-01721

    14/23

    13

    is given by three-phase per-unit node-branch oriented information. The basic data required is:

    three-phase injected powers and sending and receiving nodes of a given line impedance. The

    branch impedances are given as a rectangular 3nx3 phase impedance matrix Zabc.

    (11)

    Where is the 3-phase matrix impedance corresponding to ij line section:

    (12)

    Shunt admittances modeled by a rectangular 3nx3 matrix Yabc:

    (13)

    Fig. 3 shows a radial distribution network with n+1 nodes, and n branches and a single

    voltage source at the root node 0. Under the unbalanced approach, nodal power injection

    vector S is given per node and per phase.

    (14)

    At given iteration k, the relationship between injected currents Ikand branch currents Jkis

    set through an upper triangular matrix T accomplishing the Kirchhoff Current Laws (KCL) as

    follows:

    (15)

    (16)

    Update voltage:

    (17)

    ][ )1(01 nnabc

    ij

    abcabcabc ZZZZ

    ij

    abcZ

    ij

    cc

    ij

    cb

    ij

    ca

    ij

    bc

    ij

    bb

    ij

    ba

    ij

    ac

    ij

    ab

    ij

    aa

    ij

    ab c

    ZZZ

    ZZZ

    ZZZ

    Z

    ][ )1(01 nnabc

    ij

    abcabcabc YYYY

    cbap

    jQP

    jQP

    jQP

    S

    S

    S

    S

    T

    npnp

    ipip

    pp

    T

    np

    iP

    p

    ,,

    11

    1

    k

    abc

    k

    abc ITJ .

    cbap

    k

    ip

    ij

    ppk

    ip

    ipk

    ip VYV

    SI

    ,,

    *

    kabcabcabc

    Tabcabc

    kabc ITZTVV ...01

  • 8/11/2019 IJEPES-D-13-01721

    15/23

    14

    Where, Vabc-0 is initial voltage vector.

    Convergence check-in and final calculations:

    (18)

    7. Numerical example

    To illustrate effectiveness of proposed algorithms, two different unbalanced distribution

    networks have been considered. These methods have been coded in MATLAB software. this

    section, is demonstrated performance of method. When a fault is occurred on network,

    protection devices are operated immediately for detecting and isolating the fault. In this

    paper, total numbers of switching operations for isolating the fault and service restoration are

    obtained. The impedance of lines, phase impedance matrix and phase admittance matrix are

    calculated from data of these networks in [23]. In some distribution networks, some loads are

    modeled as distributed load; therefore, if every load point is modeled as a node, then systems

    will have a large number of nodes. Thus, these loads are modeled as spot load in this paper.

    In these test cases, one, two, or three phase loads with wye or delta connections can exist. In

    this paper some assumptions for unbalanced distribution networks have been considered that

    are described as follow:

    1) All load are modeled based on constant power model;

    2) The Regulator and Capacitors components is removed from networks;

    3) For all branches in networks, one switch in send side of branch is considered;

    4) Some tie switches are introduced in the networks for illustrating restoration plan.

    5)

    Amount of loads are modified in order to performance restoration plane and regard

    networks constraints.

    6) For conversing distributed loads to spot loads, virtual nodes 2, 3 are introduced in

    IEEE 13-node network.

    cbapniVVk

    ip

    k

    ip ,,,...,11

  • 8/11/2019 IJEPES-D-13-01721

    16/23

    15

    Fig. 4 and 5 are shows the one-line diagram of modified IEEE 13-node and IEEE 37-node

    networks respectively. Introduced tie lines (or tie switches) for service restoration, actual and

    with loss are considered. In this paper, two weighting (, ) are considered 0.8 and 0.2

    respectively. Voltage magnitude range must be within limits of 0.95 and 1.05 per-unit. For

    demonstrates validity of service restoration algorithm, fault simulation in several locations

    are considered.

    7.1.Service restoration results

    Table 1 and table 2 displays the restoration algorithms results for IEEE 13-node and IEEE

    37-node unbalanced distribution networks respectively. In these tables, following information

    is provided:

    Total number of switching operations for isolating the fault and service restoration;

    Runtime software for service restoration plan.

    When fault is occurred on the branch 2-3 in IEEE 13-node network, two switch

    operations have been required to isolate the fault and three switch operations have been

    required to full service restoration implementation. Bus number 3 is damaged bus that cant

    be restored. Bus numbers 4, 5, 10, 11, 12, 13 and 14 are de-energized bus that must be

    restored from neighboring tie lines (ts 6-11 and 9-12). For removing loop in network, one

    switch must be opened; therefore switch number 4-10 is obtained from graph-based method.

    Voltage magnitude per-unit for fault on this branch is shown in Fig. 6. This Fig shows that

    voltage for all buses are in definition limits. When fault is occurred on the branch 4-12 in

    IEEE 13-node network, three switch operations have been required to isolate fault. In this

    case, bus number 12, 13 cantbe restored.

    When fault is occurred on the branch 3-4 in IEEE 37-node network, two switch

    operations have been required to isolate the fault and three switch operations have been

  • 8/11/2019 IJEPES-D-13-01721

    17/23

    16

    required to full service restoration implementation. Voltage magnitude per-unit for all bus for

    this case is shown in Fig. 7.

    8. Conclusions

    In this paper, fast service restoration in unbalanced PDNs, with consideration to priority

    customers as multiple objective functions consists of: 1) maximizing the amount of total load

    to be restored, 2) minimizing the number of the switching operation, 3) customers priority

    considering are implemented. For this work, we are used two new heuristic algorithm based

    on two important indices and graph-based method. Core of the proposed first algorithm is

    voltage drop between candidate ts and substation bus and second algorithm is based on

    graph-based method to minimize voltage dropping in networks. Fast load flow technique

    based on a real quasi-matrix [22] has been utilized. Finally, the proposed algorithm has been

    implemented and tested on two unbalanced distribution networks and results that have been

    obtained, summarized as follow:

    1)

    Total number of switching operation for isolating the fault and service restoration;

    2) Buses that not restored.

    3) Sequence operation for selected ts and ss.

    References

    [1] L. Zhang and L. Sun, "Multi-Objective Service Restoration for Blackout of Distribution

    System with Distributed Generators based on Multi-agent GA," ELSEVIER, Energy

    Procedia, 12 (2011) 253-262.

    [2]

    C. Ming Huang, C. Tao Hsieh and Y. Shan Wang, "Evolution of radial basic function

    neural network for fast restoration of distribution systems with load variations,"

    ELSEVIER, Electrical Power and Energy Systems, 33 (2011) 961-968.

  • 8/11/2019 IJEPES-D-13-01721

    18/23

    17

    [3] S.Dimitrijevic and N. Rajakovicb, "An innovative approach for solving the restoration

    problem in distribution networks," ELSEVIER, Electric Power Systems Research, 81

    (2011) 1961-1972.

    [4] K. N. Miu, H.-D. Chiang, B. B. Yuan, and G. Darling, Fast service restoration for large-

    scale distribution systems with priority customers and constraints, IEEE Trans. Power

    Syst., 13 (3) (Aug. 1998) 789795.

    [5] S. Toune, H. Fudo, T. Genji, Y. Fukuyama, and Y. Nakanishi, Comparative study of

    modern heuristic algorithms to service restoration in distribution systems, IEEE Trans.

    Power Del., 17 (1) (Jan. 2002) 173181.

    [6] K. Miu, H.-D. Chiang, and R. J. McNulty, Multi-tier service restoration through network

    reconfiguration and capacitor control for large-scale radial distribution systems, IEEE

    Trans. Power Syst., 15 (3) (Aug. 2000) 10011007.

    [7] V, Susheela Devi, D. P. Sen Gupta, and G. Anandalingam, Optimal restoration of power

    supply in large distribution systems in developing countries, IEEE Trans. Power Del., 10

    (1) (Jan. 1995) 430438.

    [8] Y. Y. Hsu and H. C. Kuo, A heuristic based fuzzy reasoning approach for distribution

    system service restoration, IEEE Trans. Power Del., 9 (2) (Apr. 1994) 948953.

    [9] S. J. Lee, K. H. Kim, K. Y. Nam, and J. K. Lee, Service restoration expert system

    adopting branch pattern based grouping strategy in distribution systems, Expert Syst.

    Appl.Power Syst. IV, (Jan. 1994) 423427.

    [10] Y. L. Ke, Distribution feeder reconfiguration for load balancing and service restoration

    by using G-nets inference mechanism, IEEE Trans. Power Del., 19 (3) ( Jul. 2004)

    14261433.

  • 8/11/2019 IJEPES-D-13-01721

    19/23

  • 8/11/2019 IJEPES-D-13-01721

    20/23

    19

    [20] T. T. H. Pham, Y. Bsanger, and N. Hadjsaid, New challenges inpower system

    restoration with large scale of dispersed generation insertion, IEEE Trans. Power Syst.,

    24 (1) (Feb. 2009) 398406.

    [21] V. Kumar, R. H. C. Kumar, I. Gupta, and H. O. Gupta, DG integrated approach for

    service restoration under cold load pickup,IEEE Trans. Power Del., 25 (1) (Jan. 2010)

    398406.

    [22] P.M. De Oliveira-De Jesus, M.A. Alvarez, J.M. Yusta, " Distribution power flow method

    based on a real quasi-symmetric matrix" ELSEVIER, Electric Power Systems Research,

    95 (2013) 148-159.

    [23] Radial distribution test feeders.

    Table 1: Restoration Results for Modified IEEE 13-Node Network.

    casefault

    location

    switch operation to fault

    isolation

    switches operation to

    SR

    runtime

    (S)

    1 4-10 4-10, 10-11 6-11 0.35

    2 2-3 2-3, 3-4 6-11, 9-12,4-10 0.52

    3 4-12 4-12, 12-14, 12-13 5-14 0.3

    4 1-8 1-8, 8-9 9-12 0.39

    Table 2: Restoration Results for Modified IEEE 37-Node Network.

    casefault

    location

    switch operation to fault

    isolation

    switches operation to

    SR

    runtime

    (S)

    1 2-26 2-26, 26-27 36-27 0.45

    2 27-30 27-30, 30-31, 30-33 26-35 0.43

    3 2-23 2-23, 23-24, 23-25 20-25 0.35

    4 3-4 3-4, 4-5 27-36, 22-16, 7-8 1.12

    5 5-6 5-6, 6-14, 6-7 22-16, 36-12, 9-10 0.96

    6 7-8 7-8, 8-9, 8-15 36-12, 22-16 0.86

    7 3-19 3-19, 19-20 25-20 0.52

  • 8/11/2019 IJEPES-D-13-01721

    21/23

    20

    Fig.1. A 16-bus distribution network

    .

    Fig. 2. Example of graph-based method.

  • 8/11/2019 IJEPES-D-13-01721

    22/23

    21

    Fig.3. The branch and node numbering of a radial distribution network.

    Fig.4. modified IEEE 13-node network.

    Fig.5. modified IEEE 37-node network.

  • 8/11/2019 IJEPES-D-13-01721

    23/23

    22

    Fig.6. voltage after restoration for modified IEEE 13-node network.

    Fig.7. voltage after restoration for modified IEEE 37-node network.


Recommended