Date post: | 20-Jan-2016 |
Category: |
Documents |
Upload: | erika-short |
View: | 221 times |
Download: | 1 times |
BAW1-2, Technical Address 1
ILC-BAW1Interim Summary and Further Plan
Akira Yamamoto, Marc Ross and Nick Walker
GDE Project Managers
Reported at BAW1, held at KEK, Sept. 9, 2010
10-9-9, A. Yamamoto
BAW1-2, Technical Address 2
The 1st BAW Announcement http://ilcagenda.linearcollider.org/conferenceDisplay.py?confId=4593
10-9-9, A. Yamamoto
10-9-9, A. Yamamoto BAW1-2, Technical Address 3
SB2009 Themes
N Walker
10-9-9, A. Yamamoto BAW1-2, Technical Address 4
Updated ILC R&D / Design Plan
Major TDP Goals:• ILC design evolved for
cost / performance optimization
• Complete crucial demonstration and risk-mitigating R&D
• Updated VALUE estimate and schedule
• Project Implementation Plan
Release 5Aug. 2010
10-9-9, A. Yamamoto BAW1-2, Technical Address 5
Baseline Assessment Workshops• Face to face meetings• Open to all stakeholders• Plenary
TLCC Process
• Open plenary meeting• Two-days per theme• Two themes per workshop
– Two four-day workshops
• Participation (mandatory)– PM (chair)– ADI team / TAG leaders
• Agenda organised by relevant TAG leaders– Physics & Detector Representatives– External experts
• Achieve primary TLCC goals– In an open discussion environment
• Prepare recommendation
5
10-9-9, A. Yamamoto BAW1-2, Technical Address 6
Baseline Assessment WorkShops
When Where What
WAB 1 Sept. 7-10, 2010
KEK 1. Accelerating Gradient2. Single Tunnel (HLRF)
WAB 2 Jan 18-21, 2011
SLAC 3. Reduced RF power4. e+ source location
Baseline Assessment Workshops• Face to face meetings• Open to all stakeholders• Plenary
BAW1-2, Technical Address 7
Time-Table / Agenda (Sept. 7)updated: August 27
Day Am/pm Subject Chair/presenter
9/7 Single Tunnel ML Design and HLRF -1 S. Fukuda / C. Nantista
9:0 0 90 min
Opening and Introduction- Opening address- Report from AAP- BAW1 objectives and goals
Chair: S. Yamaguchi- A. Suzuki (KEK-DG)- E. Elsen- A. Yamamoto (GDE-PM)
10:45 90 min
Single tunnel CF design and HLRF design- Single tunnel CF design status (1 hour)- General HLRF design in SB2009 (30 min)
Chair: T. Shidara- A. Enomoto - S. Fukuda
13:30120 min
HLRF KCS-KCS design and R&D status (45 min)-Demonstration of feasibility (45 min)
Chair: S. Fukuda- C. Nantista - C. Adolphsen
15:45105 min
HLRF – EU XFEL and RDR - Introduction (20 min)- Experience from XFEL (1 hour)- RDR configuration (as backup) (10 min)- Discussion (15 min)
Chair: N. Walker-M. Ross -W. Bialowons - S. Fukuda - ALL
10-9-9, A. Yamamoto
BAW1-2, Technical Address 8
Time-Table / Agenda (Sept. 8)Day Am/pm Subject Convener/presenter
9/8 Single Tunnel ML Design and HLRF -2 S. Fukuda / C. Nantista
9:00 DRFS -DRFS design and R&D status-Installation strategy-(1 hour total)
Chair: C. Nantista- S. Fukuda - S. Fukuda
10:45 HLRF and LLRF-LLRF requirements/issues for KCS 30-LLRF requirements/issues for DRFS 30-Requirements from Beam Dynamics 30
Chair: T. Shidara- C. Adolphsen - S. Michizono - K. Kubo
13:30 Operational consideration- Sorting cavities in relation with HLRF 30- Gradient and RF Power Overhead 30
Chair: C. Adolphsen- S. Noguchi- J. Cawardine
15:45 Discussions and Recommendations- General discussions and questions- Summary and recommendations
Chair: A. Yamamoto- TBD- ALL
10-9-9, A. Yamamoto
BAW1-2, Technical Address 9
Single Tunnel Proposal: intro 1
• The proposal to go to a single tunnel solution for the Main Linac technical systems remains essential that outlined in the SB2009 report.
• The primary motivation was and remains a reduction in project cost due to the removal of the service tunnel for the Main Linac.
• The original proposal was based on the adoption of two novel schemes for the HLRF:– KCS– DRFS
• KCS has been identified as a preferred solutions for ‘flat land’ sites where surface access (buildings) is not restricted
• DRFS has been identified as being preferred solutions for mountainous region where surface access (buildings) is severely limited.
• Having both R&D programmes in parallel can be considered as risk-mitigation against one or other of them failiing.
• It is acknowledged that both these schemes require R&D– Programmes are detailed in the R&D Plan Release 5
• At the time of submission in December 2009, the two primary obstacles to adoption of a single tunnel were identified as
– Safety egress– Operations & Availability10-9-9, A. Yamamoto
BAW1-2, Technical Address 10
Single Tunnel Proposal: intro 2• Both these issues were addressed during the 2009 and the
successful results reported in the SB2009 proposal.– The conclusions of these studies were later accepted by both AAP
and PAC• The remaining identified issues were with the technical
feasibility and cost of the HLRF solutions upon which the single-tunnel proposal was based.
• Two components to successful adoption were identified– Definition of acceptance criteria for TD Phase R&D for successful
demonstration of one or more of the novel proposed schemes– Inclusion in the designs of a risk-mitigation strategy, whereby a fall-
back to the RDR HLRF Technical Solution (in a single-tunnel) could be adopted, should the associated R&D not be considered successful.
• The remainder of these slides deals with these two additional points
10-9-9, A. Yamamoto
BAW1-2, Technical Address 11
RDR HLRF Tech. Solution 1• Two scenarios have been cursorily studied for support of an RDR-like HLRF solution in a
single-tunnel1. 10MW MBK + (Marx) Modulator in the tunnel2. XFEL-like solution with modulators (low-voltage) accessible in cryo refrigeration
builds/caverns, with long pulsed cables feeding 10MW MBKs (via a pulse transformer) in the tunnel.
• Both are considered technically feasible.
• For 1, early investigations show the tunnel diameter would need to increase to 6.5m– This represents an estimated 10% increase in cost/unit tunnel length (~0.5% TPC)
considered acceptable.– Current availability* simulations (cf SB2009 proposal) suggest an additional ~5%
linac overhead (~2.5% TPC)• For 2:
– additional space for modulators in halls/caverns is required.– Cost of 3000 km of pulsed cable will be required.– Re-design of tunnel cross-section needed to accommodate cables.– Current availability* simulations (cf SB2009 proposal) suggest an additional ~2.5%
linac overhead (~1.3% TPC)
* see later comments on availability10-9-9, A. Yamamoto
BAW1-2, Technical Address 12
RDR HLRF Tech. Solution 2• It is proposed that these RDR-like single-tunnel
solutions be carried forward in parallel, to enough detail to support a cost estimate (incremental)
• This estimate – together with the scope of the necessary re-design work to adopt one of the scenarios, will be factored into the TDR Risk Assessment
• The main R&D and AD&I effort will continue to pursue the preferred baseline solutions for KCS and DRFS.
• In order to reduce the number of scenarios to be developed, we propose to phase out one of these RDR-like options within the next six-months
* see later comments on availability10-9-9, A. Yamamoto
BAW1-2, Technical Address 13
Time-Table / Agenda (Sept. 9)Day Am/pm Subject Convener/presenter
9/9 Cavity: Gradient R&D and ML Cavity Gradient R. Geng/A. Yamamoto
9:00 Introduction and Current Status- Technical address for the 2nd part of WS - Overview from RDR to R&D Plan 5 - Progress of cavity gradient data-base/yield
Chair: M. Ross- A. Yamamoto- R. Geng - C. Ginsburg
10:45 R&D Status and further R&D specification- Fabrication, testing, & acceptance for XFEL/HG - R&D expected in cooperation w/ vendors - R&D w/ a pilot plant w/ vendor participation
Chair: K. Yokoya- E. Elsen- M. Champion - H. Hayano
13:30 Short-tem R&D and Specification- Field emission and R&D strategy- Gradient, Spread, Q0, Radiation: R&D specification, standardization
Chair: C. Pagani- H. Hayano - R. Geng
15:45 Long-term R&D ACD subjects and goals - Seamless/hydro-forming, Large Grain, Cavity shape variation, VEP, Thin Film, - Further R&D toward TEV/ML - Discussions for Cavity R&D and Recommendations
Chair: A. Yamamoto- R. Rongli to lead discussions
10-9-9, A. Yamamoto
BAW1-2, Technical Address 14
Time-Table / Agenda (Sept. 10)Day Am/pm Subject Convener/presenter
9/10 ILC accelerator gradient and operational margin A. Yamamoto andJ. Kerby
9:00 Gradients from VTS to Operation- Introduction: Overview on ILC gradient specification at each testing / operation step - Terminology definition - Operational results from VT/HTS/CM tests in data base- Operational results from STF VT/CM tests at KEK
Chair: H. HayanoA. Yamamoto
M. Ross-C. Ginsburg - E. Kako
10:30 Operational margin- Lorentz Force Detuning and Effects on op. margin- Comments from LLRF and Beam Dynamics- Acceerator Operation gradient margin
Chair: N. Toge- E. Kako - (K. Kubo/C. Michizono) - N. Walker
13:30 Cost Impacts- Reminder on cost effects- List of systems / technical components affected by gradient specification change- A plan to prepare for communication w/ industries
Chair: N. Walker- P. Garbincius- J. Kerby
- A. Yamamoto
15:30 General Discussion and recommendation- General discussions- Summary and recommendations
Chair: A. Yamamoto- All
10-9-9, A. Yamamoto
Discussion Topics: Accelerating Gradient1st BAW, KEK, Sept. 9-10, 2010
• Gradient Improvement Studies: (Convener: Rongli Geng/A. Yamamoto) – Material/fabrication, surface processing, instrumentation and repair– Strategy to overcome ‘quench’, and ‘field emission’ and to maintain moderate cryogenic
load,– Strategy to define and specify ‘Emitted Radiation’, (Radiation that may result in
increased cryogenic-load and usable gradient limitations), – Improvement of gradient and achievement of adequate yield,
• Strategy for Accelerating Gradient in the ILC: (Convener: Akira Yamamoto) – Overview and scope of ‘production yield’ progress and expectations for TDP, including
acceptable spread of the gradient needed to achieve the specified average gradient,– Specifications of Gradient, Q0, and Emitted Radiation in vertical test, including the
spread and yield,– Specifications of Gradient, Cryogenic-load and Radiation, including the gradient spread
and operational margin with nominal controls, in cryomodule test,– Specifications of Gradient, Cryogenic-load and Radiation, including the gradient spread
and the operational margin with nominal controls in beam acceleration test,– Impact on other accelerator systems: CFS, HLRF, LLRF, Cryogenics, and overall costs.10-9-9, A. Yamamoto 15BAW1-2, Technical Address
Global Plan for SCRF R&D
Year 07 2008 2009 2010 2011 2012
Phase TDP-1 TDP-2
Cavity Gradient in v. testto reach 35 MV/m
ProcessYield 50%
ProductionYield 90%
Cavity-string to reach 31.5 MV/m, with one-cryomodule
Global effort for string assembly and test(DESY, FNAL, INFN, KEK)
System Test with beamacceleration
FLASH (DESY) , NML (FNAL) STF2 (KEK, extend beyond 2012)
Preparation for Industrialization
Production Technology R&D
10-9-9, A. Yamamoto 16BAW1-2, Technical Address
BAW1-2, Technical Address 17
Cavity Gradient Yield as of June, 20102nd-pass cavity yield at >25 MV/m is (70 +- 9) %
improved to (74 +- 8) % >35 MV/m is (48 +- 10) %
improved to (56 +- 10) %LCWS2010
10-9-9, A. Yamamoto
BAW1-2, Technical Address 18
Gradient Improvement PlanBased on Recent Understanding due to Globally Coordinated S0 Program
• Highest priority is to push yield up near 20 MV/m – the yield drop due to local (geometrical) defects near equator weld.
– Fab. QA/QC– Mechanical polish prior to heavy EP– Post-VT local targeted repair– Seamless cavity– Large-grain mat. From ingot slicing– Fine grain mat. Optimization
• Also high priority is to suppress field emission at high gradient (up to 42 MV/m) – and quantify its effect on cryogenic loss and dark current.
Eliminate Local defect(geo.) near equator weld
Remove local defect (comp.)and field emitter
10-9-9, A. Yamamoto
BAW1-2, Technical Address 19
R&D Milestone in RDRrevised in Rel-5
Stage Subjects Milestones to be achieved Year
S0 9-cell cavity
35 MV/m, max., at Q0 ≥ 8E9, with a production yield of 50% in TDP1, and 90% in TDP2 1), 2)
2010/
2012
S1 Cavity-string 31.5 MV/m, in average, at Q0 ≥ 1E10, in one cryomodule, including a global effort 2010
S2Cryomodule-string
31.5 MV/m, in average, with full-beam loading and acceleration 2012
10-9-9, A. Yamamoto
ILC Accelerator, Operational Gradient
• Strategy for Average Accelerating Gradient in the ILC operation:– Overview and scope of 'production yield' progress and expectations for TDP,
• including acceptable spread of the gradient needed to achieve the specified average gradient,
– Cavity• Gradient, Q0, and Emitted Radiation in vertical test, including the spread and yield,
– Cryomodule• Gradient, Cryogenic-load and Radiation, including the gradient spread and
operational margin with nominal controls,– ILC Accelerator
• Gradient, Cryogenic-load and Radiation, including the gradient spread and the operational margin with nominal controls
– Strategy for tuning and control, • including feedback, control of ‘Lorentz force detuning’, tolerances and availability
margin,– Impact on other accelerator systems: CFS, HLRF, LLRF, Cryogenics, and overall costs.
10-9-9, A. Yamamoto 20BAW1-2, Technical Address
BAW1-2, Technical Address 21
A possible balance inILC ML Accelerator Cavity Specification
10-9-9, A. Yamamoto
Single 9-cell cavity gradient
String Cavity gradient in cryomodule w/o
beam
String cryomodule gradient in accelerator
with beam35 MV/m, on average w/ spread above a threshold
33 MV/m, on average(or to be further
optimized)
31.5 MV/m, on average(or to be further
optimized)
BAW1-2, Technical Address 22
ILC SCRF Cavity Specification and relationship to the R&D Programs
Cost-relevant design parameter(s) for TDR
Currently proposed specification
Relevant R&D programme
Comment
Mass production distribution (models)
S0 cost optimisation will require a model for the yield curves based on the S0 R&D results
Average gradient 35 MV/m S0 primary cost driver
Gradient spread ±20% (28-42 MV/m) S0/S1/S2 cost-optimisation and performance balance
Average performance in a cryomodule (margin)
5%**
(33 MV/m average)
S1
total of 10% specified in RDR, but distribution not given (assumed equally split here)
Allowed operational gradient overhead for RF control (full beam-loading)
5%**
(31.5 MV/m average)
S2 (S1*)
Required RF power overhead for control
10% S2 (S1*)
10-9-9, A. Yamamoto
•Important input will also be gained from S1 program•** as a starting point for the discussions
BAW at KEK 2010.9.8, S.Noguchi 24
Quench GradientFeed-back Limit
Feed-back
Time
Gradient
Highest Gradient OperationFrom S. Nogichi
Operating Gradient
One Cavity – One Klystron
Best Configuration
Beam Timing
BAW1-2, Technical Address 26
Higher Gradient Operation with Better Electric Power Efficiency Small Tuning Range & Less DLD Effect
Cavity Groupingwith Over-Coupling
10-9-9, A. Yamamoto
BAW1-2, Technical Address 27
How should we do for Degraded Cavity ?
To Save other Good Cavities, We should have Tunability for RF Power & Coupling.
10-9-9, A. Yamamoto
Summary from S. Michizono
28BAW1-2, Technical Address
(1) LLRF overhead ~5%(2) Cavity gradient tilt (repetitive) ~5%(3) Pulse-to-pulse gradient fluctuation ~1%rms
RDR DRFS (PkQl) DRFS(Cavity grouping)
Operation gradient Max. 33 MV/m Average 31.5 MV/m Max. 38 MV/m
RF source 10 MW 800 kW
Waveguide loss 8% power 2% power 2% power
Static loss (Ql, Pk) 2% power 2% power 2% power
Kly Hv ripple 2.5% power 2.5% power 2.5% power
Microphonics 2% power 2% power 2% power
Reflection 0% power 14% power 0% power
Other LLRF margin 10% power 10% power 5%~10% power
Ql tolerance 3% (2) 3% (2)
Pk tolerance 0.2dB (2) 0.2dB (2)
Detuning tolerance 15Hz rms(3) 20Hz rms (3)
Beam current offset 2% rms (3)
RF p
ower
Tole
ranc
e
We have to examine these numbers experimentally. Tolerance should be discussed with cavity and HLRF group. If the tolerance is smaller, better gradient tilt would be possible.10-9-9, A. Yamamoto
Quench limits and operating gradients for 1.3GeV (FLASH ACC4-7)from J. Carwardine
20.9 MV/m 23.7 MV/m 24.8 MV/m 27.5 MV/m
Avg Emax:31.4 MV/m
Avg Emax:28.6 MV/m
Avg Emax:27.9 MV/m
Avg Emax:23 MV/m
ACC67ACC45
29BAW1-2, Technical Address10-9-9, A. Yamamoto
Ideally, all cavities reach their respective quench limits at the same forward power
25.7 MV/m 28.5 MV/m
4.6 MW klystron power (est.) 5.5 MW klystron power (est.)
23.0 MV/m 26.1 MV/m
ACC6 C2 will quench first (artifact of RF distribution
forward power ratios)
Reality: errors in power ratios due to manufacturing tolerances of rf attenuators(In this case: tolerances are of the order +/-0.1dB)
Avg Emax:31.4 MV/m
Avg Emax:28.6 MV/m
Avg Emax:27.9 MV/m
Avg Emax:23 MV/m
30BAW1-2, Technical Address10-9-9, A. Yamamoto
BAW1-2, Technical Address 31
Subjects to be further studied in TDP-2
• Further Studied in TDP-2– How wide cavity gradient spread may be
acceptable in balance of HLRF power source capacity and efficiency?
– How large operational margin required and adequate in cryomodule and accelerator operation?
10-9-9, A. Yamamoto
BAW1-2, Technical Address
Discussionstoward consensus/recommendation
• Observation– Challenging operational margin in accelerator operation to be reliable enough
for sufficient availability for physics run.
• Our Strategy Proposed– Make our best effort with forward looking position to realize the accelerator
operational gradient to be 31.5 MV/m, as proposed in RDR, (and) on average with reasonable gradient spread,
– Keep cost containment concept resulting in the ML tunnel length fixed and not to expand,
– Prepare for the industrialization including cost and quality control.
– Ask physics/detector groups to share our observation and forward looking strategy
10-9-9, A. Yamamoto 32
BAW1-2, Technical Address 33
Summary - 1BAW1 Objectives and Goals
• Assess technical proposal in SB2009• Confirm R&D Plan required and Goal in TDP-2• Discuss Impact across system interfaces, cost,
and schedule, • Discuss toward consensus in GDE and
Physics/Detector groups to prepare for TLCC.
10-9-9, A. Yamamoto
BAW1-2, Technical Address 34
Summary – 2Tasks in each day/session
Date Main Theme Tasks
Sept. 7 IntroductionKCS: Design and R&DRDR: Technical
Make the workshop tasks clearProcess for the reality including costFeasibility as a backup solution
Sept. 8 DRFS: Design and R&DLLRF/ControlDiscussions
Process for the reality including costR&F operation margin for cavity/acceleratorRecommendation
Sept. 9 Cavity Gradient R&DDiscussions
Strategy for cavity gradient improvementShort-term and long-term strategy to be clear
Sept. 10 ML Accelerator GradienDiscussions
Accelerator gradient including spreadAppropriate balance of gradient in cavity/cryomodule/ML-accelerator, Adequate/required/acceptable gradient margin in accelerator operationRecommendation
10-9-9, A. Yamamoto