Ill delmarva power ® An Exelon Company SUPPLIER COORDINATION TARIFF PAGE FOR DPL -MARYLAND CURRENT UPDATE Internet update on or before: August 15, 2017 Tariff changes effective: September 1, 2017 Reason for the Tariff Changes: Schedule 3 Case/Order No. Reference(s): Schedule 3 of the POR Leaf Nos. changed in this update: Schedule 3. pnj LAST UPDATE Internet update on or before: December 1, 2016 Tariff changes effective: Schedule 3, Purchase of Receivables effective June 1, 2016. Reason for the Tariff Change: To update Purchase of Receivables in Schedule 3. Case/Order No. Reference(s): Approved at November 30, 2016 Administrative Meeting. Leaf Nos. changed in this update: Schedule 3. lec
Transcript
Page 1: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

Ill delmarva ~ powerreg

An Exelon Company

SUPPLIER COORDINATION TARIFF PAGE FOR DPL -MARYLAND CURRENT UPDATE

Internet update on or before August 15 2017

Tariff changes effective September 1 2017

Reason for the Tariff Changes Schedule 3

CaseOrder No Reference(s) Schedule 3 of the POR

Leaf Nos changed in this update Schedule 3

pnj

LAST UPDATE Internet update on or before December 1 2016

Tariff changes effective Schedule 3 Purchase of Receivables effective June 1 2016

Reason for the Tariff Change To update Purchase of Receivables in Schedule 3

CaseOrder No Reference(s) Approved at November 30 2016 Administrative Meeting

Leaf Nos changed in this update Schedule 3 lec

lJ delmava ia powerreg

An Exelon Company

MD Electric Supplier Tariff - PSC MD No 10

DELMARVA POWER amp LIGHT COMPANY

MARYLAND ELECTRICITY SUPPLIER COORDINATION

TARIFF

TABLE OF CONTENTS 10 DEFINITIONSEXPLANATIONS OF ABBREVIATIONS 1

20 GENERAL TERMS AND CONDITIONS 5 21 Scope and Purpose 5 22 Electricity Supplierrsquos Responsibilities to Customers 5 23 Tariff to Govern 5 24 Recourse to the Commission 5 25 FERC Jurisdiction 5 26 Electricity Supplier Obligations 5 27 Electricity Supplier and Company Obligations 6 28 Control Area Services and Obligations 6 29 Communications and Data Exchange 6

291 Electronic Data Interchange 6 210 Record Retention 6 211 Characteristics of Service 6 212 Net Energy Metering6a

30 UTILIZATION OF SCHEDULING COORDINATORS 7 31 Participation Through a Scheduling Coordinator 7 32 Designation of a Scheduling Coordinator 7 33 Change of Scheduling Coordinator 7 34 Load Scheduling Through a Scheduling Coordinator 8 35 Primary Obligations of Electricity Supplier 8

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES 9 41 Application Process to Company 9

411 Completed Package 9 412 Notice of Incomplete Package for Tariff Service 9 413 Review of Completed Package 9 414 Grounds for Rejecting a Package 10 415 Conditional Acceptance of Package 10

42 Commencement of UtilitySupplier Services 10 43 Notice of Electricity Supplier Discontinuance to the Company 10 44 Termination of UtilitySupplier Services 10

441 Supplier Cessation of or Withdrawal from Participation 10 442 Default by the Electricity Supplier 11

45 Effect of Termination 11 46 Survival of Obligations 11

50 CREDITWORTHINESS 11 51 Purpose and Intent 11 52 Finding of Creditworthiness 11 53 Credit Amount 11 54 Change in Financial Status 12 55 Failure to Maintain Creditworthy Status 12 56 No Endorsement of Electricity Supplier 12

Approved by Letter Order dated August 1 2017 Effective September 1 2017

60 NONCOMPLIANCE AND DEFAULT 13 61 Definition of Noncompliance 13 62 Events of Noncompliance 13 63 Supplier Default 13 64 Cure and Default 13

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW 14 71 Pre-enrollment Information 14

711 Manner of Request 14 712 Customer Information 14

7121 Historical Interval Data 14 72 Procedure to Formalize Selection of Electricity Supplier 14

721 Authorization Record14a 722 Enrollment by an Electricity Supplier14a 723 Enrollment Processing by the Company14a 724 Notice of Enrollment14a

73 Change of Electricity Supplier14a 74 Assignment of Contract 14b 75 Electricity Supplier Drop Processing by the Company 14b 76 Customer Cancellation Request 14b

761 Non-Residential Customer Cancellation 14b 77 Transaction Error Handling 14b

771 Incumbent Supplier-Identified Erroneous Transactions 14b 772 Electronic Cancel Transactions Received Later Than Five Days 14b

78 Customer Designation to Control 15 79 Customer Termination of Service at Existing Account 15 710 Supplier Discontinuance of Service 15 711 Effective Date of Discontinuance 15 712 Customer Number Change 15 713 Full Requirements Service Provision 15

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS 16 81 The Companyrsquos Role 16 82 Load Profiles 16 83 Use of Historical Load Information for Forecasting Customer Load

Obligations 16 84 Rounding to Whole Megawatts 16 85 System Losses 16 86 Unaccounted for EnergyResidual Load 17 87 No Warranty 17

ii

Approved by Letter Order dated August 1 2017 Effective September 1 2017

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES 17 91 Capacity 17

911 Customer Specific 17 912 Daily Electricity Supplier Obligation 17

92 Transmission 17 921 Customer Specific 17 922 Daily Electricity Supplier Obligation 17

93 Load Forecasting 18 94 Load Scheduling 18 95 The Day-After Settlement 18

951 Estimate Customer Consumptionhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip18 9511 Hourly Metered Customers 18 9512 Monthly Metered Customers 18 9513 Apply Losses 18 9514 Aggregate Profiles 18 9515 Allocate Unaccounted for Energy (Residual) 18

952 Submit Estimated Load Obligations Data to PJM 19 953 Financial Settlement and Billing 19

96 The ldquo60-Dayrdquo SettlementConsumption Energy Imbalance 19 961 Meter Data Collection 19 962 Monthly Metered Customers 19 963 Determine Consumption Energy Imbalances 19

9631 Apply Losses 19 9632 Aggregate Profiles 19 9633 Allocate Unaccounted for Energy (Residual) 20 9634 Calculate Consumption Energy Imbalances 20

964 Submit Reconciliation Data to PJM 20 965 Financial Settlement and Billing 20

97 Settlement Beyond ldquo60 Daysrdquo 20 98 Settlement Calculations 20

100 ACTIVE LOAD MANAGEMENT 20 101 Demand Side Management (DSM) 20 102 DSM Operation 20 103 Ownership Maintenance and Operation of DSM Devices 20

iii Approved by Letter Order dated August 1 2017 Effective September 1 2017

110 ELECTRICITY SUPPLIER CHARGES BILLING AND PAYMENT 21 111 Charges for UtilitySupplier Services 21 112 Electricity Supplier Payment of Obligations to the Company 21

1121 Billing Procedure 21 1122 Billing Correction and Estimated Billing 21 1123 Manner of Payment 22 1124 Late Fee for Unpaid Balances 22 1125 Net Billing between the Company and Electricity Supplier 22 1126 Billing Disputes 22

113 Billing for Electricity Supplierrsquos Obligations to Other Parties 22

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION 23 121 Billing Services Selection and Change 23

1211 Billing Service Options 23 1212 Notification of Billing Option Change 23 1213 Change of Billing Options Offered 23

122 Meter Reading Information 23 1221 Estimated Meter Read 23 1222 Meter Read Data 23

123 Separate (Dual) Billing 23 1231 Customer Billing Complaints 23

124 Company Consolidated Billing23a 1241 Billing Format ndash Bill Ready23a 1242 Purchase of Electricity Supplier Receivables 23a

12421 Payment Posting 23b 1243 Billing and Payment Data Access 23b 1244 Bill Due Date 23b 1245 Utility Responsibilities in the event of Supplier Default 23b

125 Electricity Supplier Consolidated Billing 23c 126 Billing and Payment Programs 23c

1261 Budget Billing Plan23c 1262 Direct Debit Plan23c

127 Taxes 23c 1271 Company Tax Responsibilities 23c 1272 Supplier Tax Responsibilities 23c 1273 Tax Exemptions 23c

iiia

Approved by Letter Order dated August 1 2017 Effective September 1 2017

130 COMPANY-SUPPLIED METERING SERVICES 24 131 Meters 24 132 Reading 24 133 Non-standard Meteringhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip25 134 Meter Testing 25

140 NON-UTILITY SUPPLIED METERING SERVICES 25

141 Advanced Metering 25

150 SYSTEM OPERATION 26 151 Curtailment 26 152 Reasonable Efforts 26 153 PJM Requirements 26

160 CONFIDENTIALITY OF INFORMATION 26 161 Generally 26 162 Customer-Specific Information 26

170 DISPUTE RESOLUTION 27 171 Informal Resolution of Disputes 27 172 Recourse 27

180 FORCE MAJEURE 27

190 REGULATORY AUTHORIZATIONS AND JURISDICTION 27 191 Compliance with Applicable Legal Authorities 27 192 Change in Applicable Legal Authorities 28

200 LIMITATION OF LIABILITY 28 201 General Limitation of Liability 28 202 Limitation of Liability for Service Interruptions and Variations 28 203 Additional Limitations of Liability in Connection with Competitive

Power Supply 28

210 MISCELLANEOUS PROVISIONS 29 211 Notices 29 212 No Prejudice of Rights 29 213 Fluctuations 29 214 Interruptible Service 29 215 Customer Curtailment by Supplier 29

iv

Approved by Letter Order dated August 1 2017 Effective September 1 2017

10 DEFINITIONSEXPLANATION OF ABBREVIATIONS

Account - An account for a Customer is one metered or unmetered rate or service classification and is identified by a Company designated Contract Account ID or Service Number

Appropriate Similar Day ndash hourly forecasted load based on a comparable weekday month and season

Assignment of Contract ndash an assignment or transfer of a customer service id from one Supplier to another

Advanced Metering - metering equipment that provides for the monitoring andor recording of electric consumption data to enable remote interrogation to collect interval measurement of energy and Demand

Ancillary Services ndash services that are necessary for the transmission and distribution of electricity from supply sources to loads and for maintaining reliable operation of the transmission and distribution system

Bankruptcy - includes but not limited to the appointment of a receiver liquidator or trustee of the Electricity Supplier or a decree by a court adjudging the Electricity Supplier bankrupt or insolvent or sequestering any substantial part of its property or a petition to declare bankruptcy or to reorganize the Electricity Supplier

Business Day ndash any day on which the Companyrsquos and PJMrsquos Corporate offices are open for business

Charge ndash any fee that is billable by the Company to the Electricity Supplier under this Tariff including any fee(s) for UtilitySupplier Services

Commission ndash the Public Service Commission of Maryland

Company - also known as the Electricity Distribution Company or Delmarva Power amp Light Company

Companyrsquos System ndash the transmission subtransmission and Distribution Facilities owned operated and maintained by the Company or its agent

Competitive Power Supply ndash unbundled energy capacity transmission andor Ancillary Services provided by an Electricity Supplier to Customers except that Competitive Power Supply does not include such services provided to Customers by the Company in the provision of Standard Offer Service

Control Area Operator ndash PJM Interconnection LLC or successor organization

Coordinated Electricity Supplier ndash an Electricity Supplier that has appointed a Scheduling Coordinator as its designated agent for the purpose of submitting energy schedules to the PJM Office of Interconnection

Credit Amount ndash an amount equal to the greater of $25000 or the sum of two months of a) Projected Customer payments to the Electricity Supplier for the Companys services if the Electricity Supplier provides consolidated billing and b) Electricity Supplier payments for supplier services provided by the Company

1 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Credit Resources ndash financial resources including but not limited to investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or cash deposit in the Credit Amount

Creditworthy ndash a creditworthy Electricity Supplier meets the Companyrsquos credit standards and pays the Companys billed charges when due

Customer ndash any person partnership association corporation or governmental agency or other entity or its duly authorized representative receiving Competitive Power Supply from an Electricity Supplier Also called a Business Partner

Delivery Service ndash the provision of electric distribution and other services provided by the Company to a Customer who has exercised its right and buys all of its electric supply services (ie capacity energy fuel Transmission and Ancillary Services) for an Account from an Electric Supplier other than the Company

Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts

Demand Response Program ndash is a voluntary PJM program that compensates end-use (retail) customers for reducing their electricity use (load) when requested by PJM during periods of high power prices or when the reliability of the gird is threatened These customers receive payments from PJM members called Curtailment Service Providers

Distribution Facilities ndash electric facilities owned by the Company that operate at voltages of 34500 volts or less and that are used to deliver electricity to Customers up through and including the point of physical connection with electric facilities owned by the Customer

Electricity Supplier or ldquoSupplierrdquo ndash a supplier of electricity that has been certified or licensed by the Commission to sell electricity to Customers within the State of Maryland For the purpose of this document the Company is not an Electricity Supplier in the provision of Standard Offer Service An Electricity Supplier sells electricity to Customers utilizing the Transmission andor Distribution Facilities of the Company

Electricity Supplier Representative ndash any officer director employee consultant contractor or other agent or representative of the Electricity Supplier who has the authority to bind Electricity Supplier

Electric Supply amp Delivery Service - the provision of electric distribution and other services provided by the Company to a Customer who buys all of its electric supply services (ie capacity energy Transmission and Ancillary Services) for an Account from the Company Electric Supply amp Delivery Service includes Delivery Service Transmission Service and Standard Offer Service or Hourly Priced Service and associated charges

Electronic Data Interchange (EDI) ndash the computer to computer exchange of business documents in conformance with ANSI X12 standards also known as Electronic Transactions

2 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Emergency ndash a condition or situation which the Company or PJM deems in its reasonable judgment imminently likely to endanger life or property or affect or impair or imminently will affect or impair the Companyrsquos electrical system or the electric system of others to which the Companyrsquos electrical system is directly or indirectly connected Such a condition or situation includes but is not limited to potential overloading of the Companyrsquos transmission andor distribution circuits PJM minimum generation (ldquolight loadrdquo) conditions unusual operating conditions on either the Companyrsquos or the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplier without jeopardizing the Companyrsquos electric system or the electrical systems of others to which the Companyrsquos electrical system is directly or indirectly interconnected

FERC ndash the Federal Energy Regulatory Commission

Force Majeure ndash an event of Force Majeure shall be as defined in Section 180

Full Requirements Service Provision ndash a provision that requires that an Electricity Supplier be the sole source of electricity supply supporting 100 of its customersrsquo purchased supply needs

Interval Metering ndash metering equipment that supplies hourly or sub-hourly kwh and kwd readings

Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts

Kilowatt-hour or kWh ndash 1000 watts for one (1) hour or 1000 watt-hours

Load Serving Entity or ldquoLSErdquo ndash a PJM tariff term referring to an entity that has been granted the authority or has an obligation pursuant to State or local law regulation or franchise to sell electric energy to end-users within the PJM control area

Locational Marginal Price or ldquoLMPrdquo ndash the hourly integrated marginal price to serve load at individual locations throughout PJM calculated by the PJM OI as specified in the PJM Tariff

Megawatt or MW - one thousand kilowatts

Meter Read Date ndash the date on which the Company schedules a meter to be read for purposes of producing a Customer bill in accordance with the regularly scheduled billing cycles of the Company

Non-standard Metering - Metering requested by a Supplier that captures information beyond the minimum components required by the Customerrsquos prevailing retail service tariff andor requires a reading methodology or schedule that varies from Standard Metering services

PJM ndash PJM Interconnection LLC or successor organization with a similar function

PJM Control Area ndash the area encompassing electric systems recognized by the North American Electric Reliability Council as the ldquoPJM Control Areardquo

3 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

PJM OI ndash the PJM Office of Interconnection the system operator for the PJM Control Area or any successor organization with a similar function

PJM Tariff ndash the PJM Open Access Transmission Tariff on file with the FERC and which sets forth the rates terms and conditions of transmission service over transmission facilities located in the PJM Control Area

3a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 2: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

lJ delmava ia powerreg

An Exelon Company

MD Electric Supplier Tariff - PSC MD No 10

DELMARVA POWER amp LIGHT COMPANY

MARYLAND ELECTRICITY SUPPLIER COORDINATION

TARIFF

TABLE OF CONTENTS 10 DEFINITIONSEXPLANATIONS OF ABBREVIATIONS 1

20 GENERAL TERMS AND CONDITIONS 5 21 Scope and Purpose 5 22 Electricity Supplierrsquos Responsibilities to Customers 5 23 Tariff to Govern 5 24 Recourse to the Commission 5 25 FERC Jurisdiction 5 26 Electricity Supplier Obligations 5 27 Electricity Supplier and Company Obligations 6 28 Control Area Services and Obligations 6 29 Communications and Data Exchange 6

291 Electronic Data Interchange 6 210 Record Retention 6 211 Characteristics of Service 6 212 Net Energy Metering6a

30 UTILIZATION OF SCHEDULING COORDINATORS 7 31 Participation Through a Scheduling Coordinator 7 32 Designation of a Scheduling Coordinator 7 33 Change of Scheduling Coordinator 7 34 Load Scheduling Through a Scheduling Coordinator 8 35 Primary Obligations of Electricity Supplier 8

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES 9 41 Application Process to Company 9

411 Completed Package 9 412 Notice of Incomplete Package for Tariff Service 9 413 Review of Completed Package 9 414 Grounds for Rejecting a Package 10 415 Conditional Acceptance of Package 10

42 Commencement of UtilitySupplier Services 10 43 Notice of Electricity Supplier Discontinuance to the Company 10 44 Termination of UtilitySupplier Services 10

441 Supplier Cessation of or Withdrawal from Participation 10 442 Default by the Electricity Supplier 11

45 Effect of Termination 11 46 Survival of Obligations 11

50 CREDITWORTHINESS 11 51 Purpose and Intent 11 52 Finding of Creditworthiness 11 53 Credit Amount 11 54 Change in Financial Status 12 55 Failure to Maintain Creditworthy Status 12 56 No Endorsement of Electricity Supplier 12

Approved by Letter Order dated August 1 2017 Effective September 1 2017

60 NONCOMPLIANCE AND DEFAULT 13 61 Definition of Noncompliance 13 62 Events of Noncompliance 13 63 Supplier Default 13 64 Cure and Default 13

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW 14 71 Pre-enrollment Information 14

711 Manner of Request 14 712 Customer Information 14

7121 Historical Interval Data 14 72 Procedure to Formalize Selection of Electricity Supplier 14

721 Authorization Record14a 722 Enrollment by an Electricity Supplier14a 723 Enrollment Processing by the Company14a 724 Notice of Enrollment14a

73 Change of Electricity Supplier14a 74 Assignment of Contract 14b 75 Electricity Supplier Drop Processing by the Company 14b 76 Customer Cancellation Request 14b

761 Non-Residential Customer Cancellation 14b 77 Transaction Error Handling 14b

771 Incumbent Supplier-Identified Erroneous Transactions 14b 772 Electronic Cancel Transactions Received Later Than Five Days 14b

78 Customer Designation to Control 15 79 Customer Termination of Service at Existing Account 15 710 Supplier Discontinuance of Service 15 711 Effective Date of Discontinuance 15 712 Customer Number Change 15 713 Full Requirements Service Provision 15

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS 16 81 The Companyrsquos Role 16 82 Load Profiles 16 83 Use of Historical Load Information for Forecasting Customer Load

Obligations 16 84 Rounding to Whole Megawatts 16 85 System Losses 16 86 Unaccounted for EnergyResidual Load 17 87 No Warranty 17

ii

Approved by Letter Order dated August 1 2017 Effective September 1 2017

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES 17 91 Capacity 17

911 Customer Specific 17 912 Daily Electricity Supplier Obligation 17

92 Transmission 17 921 Customer Specific 17 922 Daily Electricity Supplier Obligation 17

93 Load Forecasting 18 94 Load Scheduling 18 95 The Day-After Settlement 18

951 Estimate Customer Consumptionhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip18 9511 Hourly Metered Customers 18 9512 Monthly Metered Customers 18 9513 Apply Losses 18 9514 Aggregate Profiles 18 9515 Allocate Unaccounted for Energy (Residual) 18

952 Submit Estimated Load Obligations Data to PJM 19 953 Financial Settlement and Billing 19

96 The ldquo60-Dayrdquo SettlementConsumption Energy Imbalance 19 961 Meter Data Collection 19 962 Monthly Metered Customers 19 963 Determine Consumption Energy Imbalances 19

9631 Apply Losses 19 9632 Aggregate Profiles 19 9633 Allocate Unaccounted for Energy (Residual) 20 9634 Calculate Consumption Energy Imbalances 20

964 Submit Reconciliation Data to PJM 20 965 Financial Settlement and Billing 20

97 Settlement Beyond ldquo60 Daysrdquo 20 98 Settlement Calculations 20

100 ACTIVE LOAD MANAGEMENT 20 101 Demand Side Management (DSM) 20 102 DSM Operation 20 103 Ownership Maintenance and Operation of DSM Devices 20

iii Approved by Letter Order dated August 1 2017 Effective September 1 2017

110 ELECTRICITY SUPPLIER CHARGES BILLING AND PAYMENT 21 111 Charges for UtilitySupplier Services 21 112 Electricity Supplier Payment of Obligations to the Company 21

1121 Billing Procedure 21 1122 Billing Correction and Estimated Billing 21 1123 Manner of Payment 22 1124 Late Fee for Unpaid Balances 22 1125 Net Billing between the Company and Electricity Supplier 22 1126 Billing Disputes 22

113 Billing for Electricity Supplierrsquos Obligations to Other Parties 22

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION 23 121 Billing Services Selection and Change 23

1211 Billing Service Options 23 1212 Notification of Billing Option Change 23 1213 Change of Billing Options Offered 23

122 Meter Reading Information 23 1221 Estimated Meter Read 23 1222 Meter Read Data 23

123 Separate (Dual) Billing 23 1231 Customer Billing Complaints 23

124 Company Consolidated Billing23a 1241 Billing Format ndash Bill Ready23a 1242 Purchase of Electricity Supplier Receivables 23a

12421 Payment Posting 23b 1243 Billing and Payment Data Access 23b 1244 Bill Due Date 23b 1245 Utility Responsibilities in the event of Supplier Default 23b

125 Electricity Supplier Consolidated Billing 23c 126 Billing and Payment Programs 23c

1261 Budget Billing Plan23c 1262 Direct Debit Plan23c

127 Taxes 23c 1271 Company Tax Responsibilities 23c 1272 Supplier Tax Responsibilities 23c 1273 Tax Exemptions 23c

iiia

Approved by Letter Order dated August 1 2017 Effective September 1 2017

130 COMPANY-SUPPLIED METERING SERVICES 24 131 Meters 24 132 Reading 24 133 Non-standard Meteringhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip25 134 Meter Testing 25

140 NON-UTILITY SUPPLIED METERING SERVICES 25

141 Advanced Metering 25

150 SYSTEM OPERATION 26 151 Curtailment 26 152 Reasonable Efforts 26 153 PJM Requirements 26

160 CONFIDENTIALITY OF INFORMATION 26 161 Generally 26 162 Customer-Specific Information 26

170 DISPUTE RESOLUTION 27 171 Informal Resolution of Disputes 27 172 Recourse 27

180 FORCE MAJEURE 27

190 REGULATORY AUTHORIZATIONS AND JURISDICTION 27 191 Compliance with Applicable Legal Authorities 27 192 Change in Applicable Legal Authorities 28

200 LIMITATION OF LIABILITY 28 201 General Limitation of Liability 28 202 Limitation of Liability for Service Interruptions and Variations 28 203 Additional Limitations of Liability in Connection with Competitive

Power Supply 28

210 MISCELLANEOUS PROVISIONS 29 211 Notices 29 212 No Prejudice of Rights 29 213 Fluctuations 29 214 Interruptible Service 29 215 Customer Curtailment by Supplier 29

iv

Approved by Letter Order dated August 1 2017 Effective September 1 2017

10 DEFINITIONSEXPLANATION OF ABBREVIATIONS

Account - An account for a Customer is one metered or unmetered rate or service classification and is identified by a Company designated Contract Account ID or Service Number

Appropriate Similar Day ndash hourly forecasted load based on a comparable weekday month and season

Assignment of Contract ndash an assignment or transfer of a customer service id from one Supplier to another

Advanced Metering - metering equipment that provides for the monitoring andor recording of electric consumption data to enable remote interrogation to collect interval measurement of energy and Demand

Ancillary Services ndash services that are necessary for the transmission and distribution of electricity from supply sources to loads and for maintaining reliable operation of the transmission and distribution system

Bankruptcy - includes but not limited to the appointment of a receiver liquidator or trustee of the Electricity Supplier or a decree by a court adjudging the Electricity Supplier bankrupt or insolvent or sequestering any substantial part of its property or a petition to declare bankruptcy or to reorganize the Electricity Supplier

Business Day ndash any day on which the Companyrsquos and PJMrsquos Corporate offices are open for business

Charge ndash any fee that is billable by the Company to the Electricity Supplier under this Tariff including any fee(s) for UtilitySupplier Services

Commission ndash the Public Service Commission of Maryland

Company - also known as the Electricity Distribution Company or Delmarva Power amp Light Company

Companyrsquos System ndash the transmission subtransmission and Distribution Facilities owned operated and maintained by the Company or its agent

Competitive Power Supply ndash unbundled energy capacity transmission andor Ancillary Services provided by an Electricity Supplier to Customers except that Competitive Power Supply does not include such services provided to Customers by the Company in the provision of Standard Offer Service

Control Area Operator ndash PJM Interconnection LLC or successor organization

Coordinated Electricity Supplier ndash an Electricity Supplier that has appointed a Scheduling Coordinator as its designated agent for the purpose of submitting energy schedules to the PJM Office of Interconnection

Credit Amount ndash an amount equal to the greater of $25000 or the sum of two months of a) Projected Customer payments to the Electricity Supplier for the Companys services if the Electricity Supplier provides consolidated billing and b) Electricity Supplier payments for supplier services provided by the Company

1 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Credit Resources ndash financial resources including but not limited to investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or cash deposit in the Credit Amount

Creditworthy ndash a creditworthy Electricity Supplier meets the Companyrsquos credit standards and pays the Companys billed charges when due

Customer ndash any person partnership association corporation or governmental agency or other entity or its duly authorized representative receiving Competitive Power Supply from an Electricity Supplier Also called a Business Partner

Delivery Service ndash the provision of electric distribution and other services provided by the Company to a Customer who has exercised its right and buys all of its electric supply services (ie capacity energy fuel Transmission and Ancillary Services) for an Account from an Electric Supplier other than the Company

Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts

Demand Response Program ndash is a voluntary PJM program that compensates end-use (retail) customers for reducing their electricity use (load) when requested by PJM during periods of high power prices or when the reliability of the gird is threatened These customers receive payments from PJM members called Curtailment Service Providers

Distribution Facilities ndash electric facilities owned by the Company that operate at voltages of 34500 volts or less and that are used to deliver electricity to Customers up through and including the point of physical connection with electric facilities owned by the Customer

Electricity Supplier or ldquoSupplierrdquo ndash a supplier of electricity that has been certified or licensed by the Commission to sell electricity to Customers within the State of Maryland For the purpose of this document the Company is not an Electricity Supplier in the provision of Standard Offer Service An Electricity Supplier sells electricity to Customers utilizing the Transmission andor Distribution Facilities of the Company

Electricity Supplier Representative ndash any officer director employee consultant contractor or other agent or representative of the Electricity Supplier who has the authority to bind Electricity Supplier

Electric Supply amp Delivery Service - the provision of electric distribution and other services provided by the Company to a Customer who buys all of its electric supply services (ie capacity energy Transmission and Ancillary Services) for an Account from the Company Electric Supply amp Delivery Service includes Delivery Service Transmission Service and Standard Offer Service or Hourly Priced Service and associated charges

Electronic Data Interchange (EDI) ndash the computer to computer exchange of business documents in conformance with ANSI X12 standards also known as Electronic Transactions

2 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Emergency ndash a condition or situation which the Company or PJM deems in its reasonable judgment imminently likely to endanger life or property or affect or impair or imminently will affect or impair the Companyrsquos electrical system or the electric system of others to which the Companyrsquos electrical system is directly or indirectly connected Such a condition or situation includes but is not limited to potential overloading of the Companyrsquos transmission andor distribution circuits PJM minimum generation (ldquolight loadrdquo) conditions unusual operating conditions on either the Companyrsquos or the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplier without jeopardizing the Companyrsquos electric system or the electrical systems of others to which the Companyrsquos electrical system is directly or indirectly interconnected

FERC ndash the Federal Energy Regulatory Commission

Force Majeure ndash an event of Force Majeure shall be as defined in Section 180

Full Requirements Service Provision ndash a provision that requires that an Electricity Supplier be the sole source of electricity supply supporting 100 of its customersrsquo purchased supply needs

Interval Metering ndash metering equipment that supplies hourly or sub-hourly kwh and kwd readings

Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts

Kilowatt-hour or kWh ndash 1000 watts for one (1) hour or 1000 watt-hours

Load Serving Entity or ldquoLSErdquo ndash a PJM tariff term referring to an entity that has been granted the authority or has an obligation pursuant to State or local law regulation or franchise to sell electric energy to end-users within the PJM control area

Locational Marginal Price or ldquoLMPrdquo ndash the hourly integrated marginal price to serve load at individual locations throughout PJM calculated by the PJM OI as specified in the PJM Tariff

Megawatt or MW - one thousand kilowatts

Meter Read Date ndash the date on which the Company schedules a meter to be read for purposes of producing a Customer bill in accordance with the regularly scheduled billing cycles of the Company

Non-standard Metering - Metering requested by a Supplier that captures information beyond the minimum components required by the Customerrsquos prevailing retail service tariff andor requires a reading methodology or schedule that varies from Standard Metering services

PJM ndash PJM Interconnection LLC or successor organization with a similar function

PJM Control Area ndash the area encompassing electric systems recognized by the North American Electric Reliability Council as the ldquoPJM Control Areardquo

3 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

PJM OI ndash the PJM Office of Interconnection the system operator for the PJM Control Area or any successor organization with a similar function

PJM Tariff ndash the PJM Open Access Transmission Tariff on file with the FERC and which sets forth the rates terms and conditions of transmission service over transmission facilities located in the PJM Control Area

3a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 3: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

TABLE OF CONTENTS 10 DEFINITIONSEXPLANATIONS OF ABBREVIATIONS 1

20 GENERAL TERMS AND CONDITIONS 5 21 Scope and Purpose 5 22 Electricity Supplierrsquos Responsibilities to Customers 5 23 Tariff to Govern 5 24 Recourse to the Commission 5 25 FERC Jurisdiction 5 26 Electricity Supplier Obligations 5 27 Electricity Supplier and Company Obligations 6 28 Control Area Services and Obligations 6 29 Communications and Data Exchange 6

291 Electronic Data Interchange 6 210 Record Retention 6 211 Characteristics of Service 6 212 Net Energy Metering6a

30 UTILIZATION OF SCHEDULING COORDINATORS 7 31 Participation Through a Scheduling Coordinator 7 32 Designation of a Scheduling Coordinator 7 33 Change of Scheduling Coordinator 7 34 Load Scheduling Through a Scheduling Coordinator 8 35 Primary Obligations of Electricity Supplier 8

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES 9 41 Application Process to Company 9

411 Completed Package 9 412 Notice of Incomplete Package for Tariff Service 9 413 Review of Completed Package 9 414 Grounds for Rejecting a Package 10 415 Conditional Acceptance of Package 10

42 Commencement of UtilitySupplier Services 10 43 Notice of Electricity Supplier Discontinuance to the Company 10 44 Termination of UtilitySupplier Services 10

441 Supplier Cessation of or Withdrawal from Participation 10 442 Default by the Electricity Supplier 11

45 Effect of Termination 11 46 Survival of Obligations 11

50 CREDITWORTHINESS 11 51 Purpose and Intent 11 52 Finding of Creditworthiness 11 53 Credit Amount 11 54 Change in Financial Status 12 55 Failure to Maintain Creditworthy Status 12 56 No Endorsement of Electricity Supplier 12

Approved by Letter Order dated August 1 2017 Effective September 1 2017

60 NONCOMPLIANCE AND DEFAULT 13 61 Definition of Noncompliance 13 62 Events of Noncompliance 13 63 Supplier Default 13 64 Cure and Default 13

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW 14 71 Pre-enrollment Information 14

711 Manner of Request 14 712 Customer Information 14

7121 Historical Interval Data 14 72 Procedure to Formalize Selection of Electricity Supplier 14

721 Authorization Record14a 722 Enrollment by an Electricity Supplier14a 723 Enrollment Processing by the Company14a 724 Notice of Enrollment14a

73 Change of Electricity Supplier14a 74 Assignment of Contract 14b 75 Electricity Supplier Drop Processing by the Company 14b 76 Customer Cancellation Request 14b

761 Non-Residential Customer Cancellation 14b 77 Transaction Error Handling 14b

771 Incumbent Supplier-Identified Erroneous Transactions 14b 772 Electronic Cancel Transactions Received Later Than Five Days 14b

78 Customer Designation to Control 15 79 Customer Termination of Service at Existing Account 15 710 Supplier Discontinuance of Service 15 711 Effective Date of Discontinuance 15 712 Customer Number Change 15 713 Full Requirements Service Provision 15

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS 16 81 The Companyrsquos Role 16 82 Load Profiles 16 83 Use of Historical Load Information for Forecasting Customer Load

Obligations 16 84 Rounding to Whole Megawatts 16 85 System Losses 16 86 Unaccounted for EnergyResidual Load 17 87 No Warranty 17

ii

Approved by Letter Order dated August 1 2017 Effective September 1 2017

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES 17 91 Capacity 17

911 Customer Specific 17 912 Daily Electricity Supplier Obligation 17

92 Transmission 17 921 Customer Specific 17 922 Daily Electricity Supplier Obligation 17

93 Load Forecasting 18 94 Load Scheduling 18 95 The Day-After Settlement 18

951 Estimate Customer Consumptionhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip18 9511 Hourly Metered Customers 18 9512 Monthly Metered Customers 18 9513 Apply Losses 18 9514 Aggregate Profiles 18 9515 Allocate Unaccounted for Energy (Residual) 18

952 Submit Estimated Load Obligations Data to PJM 19 953 Financial Settlement and Billing 19

96 The ldquo60-Dayrdquo SettlementConsumption Energy Imbalance 19 961 Meter Data Collection 19 962 Monthly Metered Customers 19 963 Determine Consumption Energy Imbalances 19

9631 Apply Losses 19 9632 Aggregate Profiles 19 9633 Allocate Unaccounted for Energy (Residual) 20 9634 Calculate Consumption Energy Imbalances 20

964 Submit Reconciliation Data to PJM 20 965 Financial Settlement and Billing 20

97 Settlement Beyond ldquo60 Daysrdquo 20 98 Settlement Calculations 20

100 ACTIVE LOAD MANAGEMENT 20 101 Demand Side Management (DSM) 20 102 DSM Operation 20 103 Ownership Maintenance and Operation of DSM Devices 20

iii Approved by Letter Order dated August 1 2017 Effective September 1 2017

110 ELECTRICITY SUPPLIER CHARGES BILLING AND PAYMENT 21 111 Charges for UtilitySupplier Services 21 112 Electricity Supplier Payment of Obligations to the Company 21

1121 Billing Procedure 21 1122 Billing Correction and Estimated Billing 21 1123 Manner of Payment 22 1124 Late Fee for Unpaid Balances 22 1125 Net Billing between the Company and Electricity Supplier 22 1126 Billing Disputes 22

113 Billing for Electricity Supplierrsquos Obligations to Other Parties 22

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION 23 121 Billing Services Selection and Change 23

1211 Billing Service Options 23 1212 Notification of Billing Option Change 23 1213 Change of Billing Options Offered 23

122 Meter Reading Information 23 1221 Estimated Meter Read 23 1222 Meter Read Data 23

123 Separate (Dual) Billing 23 1231 Customer Billing Complaints 23

124 Company Consolidated Billing23a 1241 Billing Format ndash Bill Ready23a 1242 Purchase of Electricity Supplier Receivables 23a

12421 Payment Posting 23b 1243 Billing and Payment Data Access 23b 1244 Bill Due Date 23b 1245 Utility Responsibilities in the event of Supplier Default 23b

125 Electricity Supplier Consolidated Billing 23c 126 Billing and Payment Programs 23c

1261 Budget Billing Plan23c 1262 Direct Debit Plan23c

127 Taxes 23c 1271 Company Tax Responsibilities 23c 1272 Supplier Tax Responsibilities 23c 1273 Tax Exemptions 23c

iiia

Approved by Letter Order dated August 1 2017 Effective September 1 2017

130 COMPANY-SUPPLIED METERING SERVICES 24 131 Meters 24 132 Reading 24 133 Non-standard Meteringhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip25 134 Meter Testing 25

140 NON-UTILITY SUPPLIED METERING SERVICES 25

141 Advanced Metering 25

150 SYSTEM OPERATION 26 151 Curtailment 26 152 Reasonable Efforts 26 153 PJM Requirements 26

160 CONFIDENTIALITY OF INFORMATION 26 161 Generally 26 162 Customer-Specific Information 26

170 DISPUTE RESOLUTION 27 171 Informal Resolution of Disputes 27 172 Recourse 27

180 FORCE MAJEURE 27

190 REGULATORY AUTHORIZATIONS AND JURISDICTION 27 191 Compliance with Applicable Legal Authorities 27 192 Change in Applicable Legal Authorities 28

200 LIMITATION OF LIABILITY 28 201 General Limitation of Liability 28 202 Limitation of Liability for Service Interruptions and Variations 28 203 Additional Limitations of Liability in Connection with Competitive

Power Supply 28

210 MISCELLANEOUS PROVISIONS 29 211 Notices 29 212 No Prejudice of Rights 29 213 Fluctuations 29 214 Interruptible Service 29 215 Customer Curtailment by Supplier 29

iv

Approved by Letter Order dated August 1 2017 Effective September 1 2017

10 DEFINITIONSEXPLANATION OF ABBREVIATIONS

Account - An account for a Customer is one metered or unmetered rate or service classification and is identified by a Company designated Contract Account ID or Service Number

Appropriate Similar Day ndash hourly forecasted load based on a comparable weekday month and season

Assignment of Contract ndash an assignment or transfer of a customer service id from one Supplier to another

Advanced Metering - metering equipment that provides for the monitoring andor recording of electric consumption data to enable remote interrogation to collect interval measurement of energy and Demand

Ancillary Services ndash services that are necessary for the transmission and distribution of electricity from supply sources to loads and for maintaining reliable operation of the transmission and distribution system

Bankruptcy - includes but not limited to the appointment of a receiver liquidator or trustee of the Electricity Supplier or a decree by a court adjudging the Electricity Supplier bankrupt or insolvent or sequestering any substantial part of its property or a petition to declare bankruptcy or to reorganize the Electricity Supplier

Business Day ndash any day on which the Companyrsquos and PJMrsquos Corporate offices are open for business

Charge ndash any fee that is billable by the Company to the Electricity Supplier under this Tariff including any fee(s) for UtilitySupplier Services

Commission ndash the Public Service Commission of Maryland

Company - also known as the Electricity Distribution Company or Delmarva Power amp Light Company

Companyrsquos System ndash the transmission subtransmission and Distribution Facilities owned operated and maintained by the Company or its agent

Competitive Power Supply ndash unbundled energy capacity transmission andor Ancillary Services provided by an Electricity Supplier to Customers except that Competitive Power Supply does not include such services provided to Customers by the Company in the provision of Standard Offer Service

Control Area Operator ndash PJM Interconnection LLC or successor organization

Coordinated Electricity Supplier ndash an Electricity Supplier that has appointed a Scheduling Coordinator as its designated agent for the purpose of submitting energy schedules to the PJM Office of Interconnection

Credit Amount ndash an amount equal to the greater of $25000 or the sum of two months of a) Projected Customer payments to the Electricity Supplier for the Companys services if the Electricity Supplier provides consolidated billing and b) Electricity Supplier payments for supplier services provided by the Company

1 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Credit Resources ndash financial resources including but not limited to investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or cash deposit in the Credit Amount

Creditworthy ndash a creditworthy Electricity Supplier meets the Companyrsquos credit standards and pays the Companys billed charges when due

Customer ndash any person partnership association corporation or governmental agency or other entity or its duly authorized representative receiving Competitive Power Supply from an Electricity Supplier Also called a Business Partner

Delivery Service ndash the provision of electric distribution and other services provided by the Company to a Customer who has exercised its right and buys all of its electric supply services (ie capacity energy fuel Transmission and Ancillary Services) for an Account from an Electric Supplier other than the Company

Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts

Demand Response Program ndash is a voluntary PJM program that compensates end-use (retail) customers for reducing their electricity use (load) when requested by PJM during periods of high power prices or when the reliability of the gird is threatened These customers receive payments from PJM members called Curtailment Service Providers

Distribution Facilities ndash electric facilities owned by the Company that operate at voltages of 34500 volts or less and that are used to deliver electricity to Customers up through and including the point of physical connection with electric facilities owned by the Customer

Electricity Supplier or ldquoSupplierrdquo ndash a supplier of electricity that has been certified or licensed by the Commission to sell electricity to Customers within the State of Maryland For the purpose of this document the Company is not an Electricity Supplier in the provision of Standard Offer Service An Electricity Supplier sells electricity to Customers utilizing the Transmission andor Distribution Facilities of the Company

Electricity Supplier Representative ndash any officer director employee consultant contractor or other agent or representative of the Electricity Supplier who has the authority to bind Electricity Supplier

Electric Supply amp Delivery Service - the provision of electric distribution and other services provided by the Company to a Customer who buys all of its electric supply services (ie capacity energy Transmission and Ancillary Services) for an Account from the Company Electric Supply amp Delivery Service includes Delivery Service Transmission Service and Standard Offer Service or Hourly Priced Service and associated charges

Electronic Data Interchange (EDI) ndash the computer to computer exchange of business documents in conformance with ANSI X12 standards also known as Electronic Transactions

2 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Emergency ndash a condition or situation which the Company or PJM deems in its reasonable judgment imminently likely to endanger life or property or affect or impair or imminently will affect or impair the Companyrsquos electrical system or the electric system of others to which the Companyrsquos electrical system is directly or indirectly connected Such a condition or situation includes but is not limited to potential overloading of the Companyrsquos transmission andor distribution circuits PJM minimum generation (ldquolight loadrdquo) conditions unusual operating conditions on either the Companyrsquos or the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplier without jeopardizing the Companyrsquos electric system or the electrical systems of others to which the Companyrsquos electrical system is directly or indirectly interconnected

FERC ndash the Federal Energy Regulatory Commission

Force Majeure ndash an event of Force Majeure shall be as defined in Section 180

Full Requirements Service Provision ndash a provision that requires that an Electricity Supplier be the sole source of electricity supply supporting 100 of its customersrsquo purchased supply needs

Interval Metering ndash metering equipment that supplies hourly or sub-hourly kwh and kwd readings

Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts

Kilowatt-hour or kWh ndash 1000 watts for one (1) hour or 1000 watt-hours

Load Serving Entity or ldquoLSErdquo ndash a PJM tariff term referring to an entity that has been granted the authority or has an obligation pursuant to State or local law regulation or franchise to sell electric energy to end-users within the PJM control area

Locational Marginal Price or ldquoLMPrdquo ndash the hourly integrated marginal price to serve load at individual locations throughout PJM calculated by the PJM OI as specified in the PJM Tariff

Megawatt or MW - one thousand kilowatts

Meter Read Date ndash the date on which the Company schedules a meter to be read for purposes of producing a Customer bill in accordance with the regularly scheduled billing cycles of the Company

Non-standard Metering - Metering requested by a Supplier that captures information beyond the minimum components required by the Customerrsquos prevailing retail service tariff andor requires a reading methodology or schedule that varies from Standard Metering services

PJM ndash PJM Interconnection LLC or successor organization with a similar function

PJM Control Area ndash the area encompassing electric systems recognized by the North American Electric Reliability Council as the ldquoPJM Control Areardquo

3 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

PJM OI ndash the PJM Office of Interconnection the system operator for the PJM Control Area or any successor organization with a similar function

PJM Tariff ndash the PJM Open Access Transmission Tariff on file with the FERC and which sets forth the rates terms and conditions of transmission service over transmission facilities located in the PJM Control Area

3a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 4: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

60 NONCOMPLIANCE AND DEFAULT 13 61 Definition of Noncompliance 13 62 Events of Noncompliance 13 63 Supplier Default 13 64 Cure and Default 13

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW 14 71 Pre-enrollment Information 14

711 Manner of Request 14 712 Customer Information 14

7121 Historical Interval Data 14 72 Procedure to Formalize Selection of Electricity Supplier 14

721 Authorization Record14a 722 Enrollment by an Electricity Supplier14a 723 Enrollment Processing by the Company14a 724 Notice of Enrollment14a

73 Change of Electricity Supplier14a 74 Assignment of Contract 14b 75 Electricity Supplier Drop Processing by the Company 14b 76 Customer Cancellation Request 14b

761 Non-Residential Customer Cancellation 14b 77 Transaction Error Handling 14b

771 Incumbent Supplier-Identified Erroneous Transactions 14b 772 Electronic Cancel Transactions Received Later Than Five Days 14b

78 Customer Designation to Control 15 79 Customer Termination of Service at Existing Account 15 710 Supplier Discontinuance of Service 15 711 Effective Date of Discontinuance 15 712 Customer Number Change 15 713 Full Requirements Service Provision 15

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS 16 81 The Companyrsquos Role 16 82 Load Profiles 16 83 Use of Historical Load Information for Forecasting Customer Load

Obligations 16 84 Rounding to Whole Megawatts 16 85 System Losses 16 86 Unaccounted for EnergyResidual Load 17 87 No Warranty 17

ii

Approved by Letter Order dated August 1 2017 Effective September 1 2017

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES 17 91 Capacity 17

911 Customer Specific 17 912 Daily Electricity Supplier Obligation 17

92 Transmission 17 921 Customer Specific 17 922 Daily Electricity Supplier Obligation 17

93 Load Forecasting 18 94 Load Scheduling 18 95 The Day-After Settlement 18

951 Estimate Customer Consumptionhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip18 9511 Hourly Metered Customers 18 9512 Monthly Metered Customers 18 9513 Apply Losses 18 9514 Aggregate Profiles 18 9515 Allocate Unaccounted for Energy (Residual) 18

952 Submit Estimated Load Obligations Data to PJM 19 953 Financial Settlement and Billing 19

96 The ldquo60-Dayrdquo SettlementConsumption Energy Imbalance 19 961 Meter Data Collection 19 962 Monthly Metered Customers 19 963 Determine Consumption Energy Imbalances 19

9631 Apply Losses 19 9632 Aggregate Profiles 19 9633 Allocate Unaccounted for Energy (Residual) 20 9634 Calculate Consumption Energy Imbalances 20

964 Submit Reconciliation Data to PJM 20 965 Financial Settlement and Billing 20

97 Settlement Beyond ldquo60 Daysrdquo 20 98 Settlement Calculations 20

100 ACTIVE LOAD MANAGEMENT 20 101 Demand Side Management (DSM) 20 102 DSM Operation 20 103 Ownership Maintenance and Operation of DSM Devices 20

iii Approved by Letter Order dated August 1 2017 Effective September 1 2017

110 ELECTRICITY SUPPLIER CHARGES BILLING AND PAYMENT 21 111 Charges for UtilitySupplier Services 21 112 Electricity Supplier Payment of Obligations to the Company 21

1121 Billing Procedure 21 1122 Billing Correction and Estimated Billing 21 1123 Manner of Payment 22 1124 Late Fee for Unpaid Balances 22 1125 Net Billing between the Company and Electricity Supplier 22 1126 Billing Disputes 22

113 Billing for Electricity Supplierrsquos Obligations to Other Parties 22

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION 23 121 Billing Services Selection and Change 23

1211 Billing Service Options 23 1212 Notification of Billing Option Change 23 1213 Change of Billing Options Offered 23

122 Meter Reading Information 23 1221 Estimated Meter Read 23 1222 Meter Read Data 23

123 Separate (Dual) Billing 23 1231 Customer Billing Complaints 23

124 Company Consolidated Billing23a 1241 Billing Format ndash Bill Ready23a 1242 Purchase of Electricity Supplier Receivables 23a

12421 Payment Posting 23b 1243 Billing and Payment Data Access 23b 1244 Bill Due Date 23b 1245 Utility Responsibilities in the event of Supplier Default 23b

125 Electricity Supplier Consolidated Billing 23c 126 Billing and Payment Programs 23c

1261 Budget Billing Plan23c 1262 Direct Debit Plan23c

127 Taxes 23c 1271 Company Tax Responsibilities 23c 1272 Supplier Tax Responsibilities 23c 1273 Tax Exemptions 23c

iiia

Approved by Letter Order dated August 1 2017 Effective September 1 2017

130 COMPANY-SUPPLIED METERING SERVICES 24 131 Meters 24 132 Reading 24 133 Non-standard Meteringhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip25 134 Meter Testing 25

140 NON-UTILITY SUPPLIED METERING SERVICES 25

141 Advanced Metering 25

150 SYSTEM OPERATION 26 151 Curtailment 26 152 Reasonable Efforts 26 153 PJM Requirements 26

160 CONFIDENTIALITY OF INFORMATION 26 161 Generally 26 162 Customer-Specific Information 26

170 DISPUTE RESOLUTION 27 171 Informal Resolution of Disputes 27 172 Recourse 27

180 FORCE MAJEURE 27

190 REGULATORY AUTHORIZATIONS AND JURISDICTION 27 191 Compliance with Applicable Legal Authorities 27 192 Change in Applicable Legal Authorities 28

200 LIMITATION OF LIABILITY 28 201 General Limitation of Liability 28 202 Limitation of Liability for Service Interruptions and Variations 28 203 Additional Limitations of Liability in Connection with Competitive

Power Supply 28

210 MISCELLANEOUS PROVISIONS 29 211 Notices 29 212 No Prejudice of Rights 29 213 Fluctuations 29 214 Interruptible Service 29 215 Customer Curtailment by Supplier 29

iv

Approved by Letter Order dated August 1 2017 Effective September 1 2017

10 DEFINITIONSEXPLANATION OF ABBREVIATIONS

Account - An account for a Customer is one metered or unmetered rate or service classification and is identified by a Company designated Contract Account ID or Service Number

Appropriate Similar Day ndash hourly forecasted load based on a comparable weekday month and season

Assignment of Contract ndash an assignment or transfer of a customer service id from one Supplier to another

Advanced Metering - metering equipment that provides for the monitoring andor recording of electric consumption data to enable remote interrogation to collect interval measurement of energy and Demand

Ancillary Services ndash services that are necessary for the transmission and distribution of electricity from supply sources to loads and for maintaining reliable operation of the transmission and distribution system

Bankruptcy - includes but not limited to the appointment of a receiver liquidator or trustee of the Electricity Supplier or a decree by a court adjudging the Electricity Supplier bankrupt or insolvent or sequestering any substantial part of its property or a petition to declare bankruptcy or to reorganize the Electricity Supplier

Business Day ndash any day on which the Companyrsquos and PJMrsquos Corporate offices are open for business

Charge ndash any fee that is billable by the Company to the Electricity Supplier under this Tariff including any fee(s) for UtilitySupplier Services

Commission ndash the Public Service Commission of Maryland

Company - also known as the Electricity Distribution Company or Delmarva Power amp Light Company

Companyrsquos System ndash the transmission subtransmission and Distribution Facilities owned operated and maintained by the Company or its agent

Competitive Power Supply ndash unbundled energy capacity transmission andor Ancillary Services provided by an Electricity Supplier to Customers except that Competitive Power Supply does not include such services provided to Customers by the Company in the provision of Standard Offer Service

Control Area Operator ndash PJM Interconnection LLC or successor organization

Coordinated Electricity Supplier ndash an Electricity Supplier that has appointed a Scheduling Coordinator as its designated agent for the purpose of submitting energy schedules to the PJM Office of Interconnection

Credit Amount ndash an amount equal to the greater of $25000 or the sum of two months of a) Projected Customer payments to the Electricity Supplier for the Companys services if the Electricity Supplier provides consolidated billing and b) Electricity Supplier payments for supplier services provided by the Company

1 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Credit Resources ndash financial resources including but not limited to investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or cash deposit in the Credit Amount

Creditworthy ndash a creditworthy Electricity Supplier meets the Companyrsquos credit standards and pays the Companys billed charges when due

Customer ndash any person partnership association corporation or governmental agency or other entity or its duly authorized representative receiving Competitive Power Supply from an Electricity Supplier Also called a Business Partner

Delivery Service ndash the provision of electric distribution and other services provided by the Company to a Customer who has exercised its right and buys all of its electric supply services (ie capacity energy fuel Transmission and Ancillary Services) for an Account from an Electric Supplier other than the Company

Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts

Demand Response Program ndash is a voluntary PJM program that compensates end-use (retail) customers for reducing their electricity use (load) when requested by PJM during periods of high power prices or when the reliability of the gird is threatened These customers receive payments from PJM members called Curtailment Service Providers

Distribution Facilities ndash electric facilities owned by the Company that operate at voltages of 34500 volts or less and that are used to deliver electricity to Customers up through and including the point of physical connection with electric facilities owned by the Customer

Electricity Supplier or ldquoSupplierrdquo ndash a supplier of electricity that has been certified or licensed by the Commission to sell electricity to Customers within the State of Maryland For the purpose of this document the Company is not an Electricity Supplier in the provision of Standard Offer Service An Electricity Supplier sells electricity to Customers utilizing the Transmission andor Distribution Facilities of the Company

Electricity Supplier Representative ndash any officer director employee consultant contractor or other agent or representative of the Electricity Supplier who has the authority to bind Electricity Supplier

Electric Supply amp Delivery Service - the provision of electric distribution and other services provided by the Company to a Customer who buys all of its electric supply services (ie capacity energy Transmission and Ancillary Services) for an Account from the Company Electric Supply amp Delivery Service includes Delivery Service Transmission Service and Standard Offer Service or Hourly Priced Service and associated charges

Electronic Data Interchange (EDI) ndash the computer to computer exchange of business documents in conformance with ANSI X12 standards also known as Electronic Transactions

2 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Emergency ndash a condition or situation which the Company or PJM deems in its reasonable judgment imminently likely to endanger life or property or affect or impair or imminently will affect or impair the Companyrsquos electrical system or the electric system of others to which the Companyrsquos electrical system is directly or indirectly connected Such a condition or situation includes but is not limited to potential overloading of the Companyrsquos transmission andor distribution circuits PJM minimum generation (ldquolight loadrdquo) conditions unusual operating conditions on either the Companyrsquos or the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplier without jeopardizing the Companyrsquos electric system or the electrical systems of others to which the Companyrsquos electrical system is directly or indirectly interconnected

FERC ndash the Federal Energy Regulatory Commission

Force Majeure ndash an event of Force Majeure shall be as defined in Section 180

Full Requirements Service Provision ndash a provision that requires that an Electricity Supplier be the sole source of electricity supply supporting 100 of its customersrsquo purchased supply needs

Interval Metering ndash metering equipment that supplies hourly or sub-hourly kwh and kwd readings

Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts

Kilowatt-hour or kWh ndash 1000 watts for one (1) hour or 1000 watt-hours

Load Serving Entity or ldquoLSErdquo ndash a PJM tariff term referring to an entity that has been granted the authority or has an obligation pursuant to State or local law regulation or franchise to sell electric energy to end-users within the PJM control area

Locational Marginal Price or ldquoLMPrdquo ndash the hourly integrated marginal price to serve load at individual locations throughout PJM calculated by the PJM OI as specified in the PJM Tariff

Megawatt or MW - one thousand kilowatts

Meter Read Date ndash the date on which the Company schedules a meter to be read for purposes of producing a Customer bill in accordance with the regularly scheduled billing cycles of the Company

Non-standard Metering - Metering requested by a Supplier that captures information beyond the minimum components required by the Customerrsquos prevailing retail service tariff andor requires a reading methodology or schedule that varies from Standard Metering services

PJM ndash PJM Interconnection LLC or successor organization with a similar function

PJM Control Area ndash the area encompassing electric systems recognized by the North American Electric Reliability Council as the ldquoPJM Control Areardquo

3 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

PJM OI ndash the PJM Office of Interconnection the system operator for the PJM Control Area or any successor organization with a similar function

PJM Tariff ndash the PJM Open Access Transmission Tariff on file with the FERC and which sets forth the rates terms and conditions of transmission service over transmission facilities located in the PJM Control Area

3a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 5: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES 17 91 Capacity 17

911 Customer Specific 17 912 Daily Electricity Supplier Obligation 17

92 Transmission 17 921 Customer Specific 17 922 Daily Electricity Supplier Obligation 17

93 Load Forecasting 18 94 Load Scheduling 18 95 The Day-After Settlement 18

951 Estimate Customer Consumptionhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip18 9511 Hourly Metered Customers 18 9512 Monthly Metered Customers 18 9513 Apply Losses 18 9514 Aggregate Profiles 18 9515 Allocate Unaccounted for Energy (Residual) 18

952 Submit Estimated Load Obligations Data to PJM 19 953 Financial Settlement and Billing 19

96 The ldquo60-Dayrdquo SettlementConsumption Energy Imbalance 19 961 Meter Data Collection 19 962 Monthly Metered Customers 19 963 Determine Consumption Energy Imbalances 19

9631 Apply Losses 19 9632 Aggregate Profiles 19 9633 Allocate Unaccounted for Energy (Residual) 20 9634 Calculate Consumption Energy Imbalances 20

964 Submit Reconciliation Data to PJM 20 965 Financial Settlement and Billing 20

97 Settlement Beyond ldquo60 Daysrdquo 20 98 Settlement Calculations 20

100 ACTIVE LOAD MANAGEMENT 20 101 Demand Side Management (DSM) 20 102 DSM Operation 20 103 Ownership Maintenance and Operation of DSM Devices 20

iii Approved by Letter Order dated August 1 2017 Effective September 1 2017

110 ELECTRICITY SUPPLIER CHARGES BILLING AND PAYMENT 21 111 Charges for UtilitySupplier Services 21 112 Electricity Supplier Payment of Obligations to the Company 21

1121 Billing Procedure 21 1122 Billing Correction and Estimated Billing 21 1123 Manner of Payment 22 1124 Late Fee for Unpaid Balances 22 1125 Net Billing between the Company and Electricity Supplier 22 1126 Billing Disputes 22

113 Billing for Electricity Supplierrsquos Obligations to Other Parties 22

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION 23 121 Billing Services Selection and Change 23

1211 Billing Service Options 23 1212 Notification of Billing Option Change 23 1213 Change of Billing Options Offered 23

122 Meter Reading Information 23 1221 Estimated Meter Read 23 1222 Meter Read Data 23

123 Separate (Dual) Billing 23 1231 Customer Billing Complaints 23

124 Company Consolidated Billing23a 1241 Billing Format ndash Bill Ready23a 1242 Purchase of Electricity Supplier Receivables 23a

12421 Payment Posting 23b 1243 Billing and Payment Data Access 23b 1244 Bill Due Date 23b 1245 Utility Responsibilities in the event of Supplier Default 23b

125 Electricity Supplier Consolidated Billing 23c 126 Billing and Payment Programs 23c

1261 Budget Billing Plan23c 1262 Direct Debit Plan23c

127 Taxes 23c 1271 Company Tax Responsibilities 23c 1272 Supplier Tax Responsibilities 23c 1273 Tax Exemptions 23c

iiia

Approved by Letter Order dated August 1 2017 Effective September 1 2017

130 COMPANY-SUPPLIED METERING SERVICES 24 131 Meters 24 132 Reading 24 133 Non-standard Meteringhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip25 134 Meter Testing 25

140 NON-UTILITY SUPPLIED METERING SERVICES 25

141 Advanced Metering 25

150 SYSTEM OPERATION 26 151 Curtailment 26 152 Reasonable Efforts 26 153 PJM Requirements 26

160 CONFIDENTIALITY OF INFORMATION 26 161 Generally 26 162 Customer-Specific Information 26

170 DISPUTE RESOLUTION 27 171 Informal Resolution of Disputes 27 172 Recourse 27

180 FORCE MAJEURE 27

190 REGULATORY AUTHORIZATIONS AND JURISDICTION 27 191 Compliance with Applicable Legal Authorities 27 192 Change in Applicable Legal Authorities 28

200 LIMITATION OF LIABILITY 28 201 General Limitation of Liability 28 202 Limitation of Liability for Service Interruptions and Variations 28 203 Additional Limitations of Liability in Connection with Competitive

Power Supply 28

210 MISCELLANEOUS PROVISIONS 29 211 Notices 29 212 No Prejudice of Rights 29 213 Fluctuations 29 214 Interruptible Service 29 215 Customer Curtailment by Supplier 29

iv

Approved by Letter Order dated August 1 2017 Effective September 1 2017

10 DEFINITIONSEXPLANATION OF ABBREVIATIONS

Account - An account for a Customer is one metered or unmetered rate or service classification and is identified by a Company designated Contract Account ID or Service Number

Appropriate Similar Day ndash hourly forecasted load based on a comparable weekday month and season

Assignment of Contract ndash an assignment or transfer of a customer service id from one Supplier to another

Advanced Metering - metering equipment that provides for the monitoring andor recording of electric consumption data to enable remote interrogation to collect interval measurement of energy and Demand

Ancillary Services ndash services that are necessary for the transmission and distribution of electricity from supply sources to loads and for maintaining reliable operation of the transmission and distribution system

Bankruptcy - includes but not limited to the appointment of a receiver liquidator or trustee of the Electricity Supplier or a decree by a court adjudging the Electricity Supplier bankrupt or insolvent or sequestering any substantial part of its property or a petition to declare bankruptcy or to reorganize the Electricity Supplier

Business Day ndash any day on which the Companyrsquos and PJMrsquos Corporate offices are open for business

Charge ndash any fee that is billable by the Company to the Electricity Supplier under this Tariff including any fee(s) for UtilitySupplier Services

Commission ndash the Public Service Commission of Maryland

Company - also known as the Electricity Distribution Company or Delmarva Power amp Light Company

Companyrsquos System ndash the transmission subtransmission and Distribution Facilities owned operated and maintained by the Company or its agent

Competitive Power Supply ndash unbundled energy capacity transmission andor Ancillary Services provided by an Electricity Supplier to Customers except that Competitive Power Supply does not include such services provided to Customers by the Company in the provision of Standard Offer Service

Control Area Operator ndash PJM Interconnection LLC or successor organization

Coordinated Electricity Supplier ndash an Electricity Supplier that has appointed a Scheduling Coordinator as its designated agent for the purpose of submitting energy schedules to the PJM Office of Interconnection

Credit Amount ndash an amount equal to the greater of $25000 or the sum of two months of a) Projected Customer payments to the Electricity Supplier for the Companys services if the Electricity Supplier provides consolidated billing and b) Electricity Supplier payments for supplier services provided by the Company

1 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Credit Resources ndash financial resources including but not limited to investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or cash deposit in the Credit Amount

Creditworthy ndash a creditworthy Electricity Supplier meets the Companyrsquos credit standards and pays the Companys billed charges when due

Customer ndash any person partnership association corporation or governmental agency or other entity or its duly authorized representative receiving Competitive Power Supply from an Electricity Supplier Also called a Business Partner

Delivery Service ndash the provision of electric distribution and other services provided by the Company to a Customer who has exercised its right and buys all of its electric supply services (ie capacity energy fuel Transmission and Ancillary Services) for an Account from an Electric Supplier other than the Company

Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts

Demand Response Program ndash is a voluntary PJM program that compensates end-use (retail) customers for reducing their electricity use (load) when requested by PJM during periods of high power prices or when the reliability of the gird is threatened These customers receive payments from PJM members called Curtailment Service Providers

Distribution Facilities ndash electric facilities owned by the Company that operate at voltages of 34500 volts or less and that are used to deliver electricity to Customers up through and including the point of physical connection with electric facilities owned by the Customer

Electricity Supplier or ldquoSupplierrdquo ndash a supplier of electricity that has been certified or licensed by the Commission to sell electricity to Customers within the State of Maryland For the purpose of this document the Company is not an Electricity Supplier in the provision of Standard Offer Service An Electricity Supplier sells electricity to Customers utilizing the Transmission andor Distribution Facilities of the Company

Electricity Supplier Representative ndash any officer director employee consultant contractor or other agent or representative of the Electricity Supplier who has the authority to bind Electricity Supplier

Electric Supply amp Delivery Service - the provision of electric distribution and other services provided by the Company to a Customer who buys all of its electric supply services (ie capacity energy Transmission and Ancillary Services) for an Account from the Company Electric Supply amp Delivery Service includes Delivery Service Transmission Service and Standard Offer Service or Hourly Priced Service and associated charges

Electronic Data Interchange (EDI) ndash the computer to computer exchange of business documents in conformance with ANSI X12 standards also known as Electronic Transactions

2 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Emergency ndash a condition or situation which the Company or PJM deems in its reasonable judgment imminently likely to endanger life or property or affect or impair or imminently will affect or impair the Companyrsquos electrical system or the electric system of others to which the Companyrsquos electrical system is directly or indirectly connected Such a condition or situation includes but is not limited to potential overloading of the Companyrsquos transmission andor distribution circuits PJM minimum generation (ldquolight loadrdquo) conditions unusual operating conditions on either the Companyrsquos or the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplier without jeopardizing the Companyrsquos electric system or the electrical systems of others to which the Companyrsquos electrical system is directly or indirectly interconnected

FERC ndash the Federal Energy Regulatory Commission

Force Majeure ndash an event of Force Majeure shall be as defined in Section 180

Full Requirements Service Provision ndash a provision that requires that an Electricity Supplier be the sole source of electricity supply supporting 100 of its customersrsquo purchased supply needs

Interval Metering ndash metering equipment that supplies hourly or sub-hourly kwh and kwd readings

Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts

Kilowatt-hour or kWh ndash 1000 watts for one (1) hour or 1000 watt-hours

Load Serving Entity or ldquoLSErdquo ndash a PJM tariff term referring to an entity that has been granted the authority or has an obligation pursuant to State or local law regulation or franchise to sell electric energy to end-users within the PJM control area

Locational Marginal Price or ldquoLMPrdquo ndash the hourly integrated marginal price to serve load at individual locations throughout PJM calculated by the PJM OI as specified in the PJM Tariff

Megawatt or MW - one thousand kilowatts

Meter Read Date ndash the date on which the Company schedules a meter to be read for purposes of producing a Customer bill in accordance with the regularly scheduled billing cycles of the Company

Non-standard Metering - Metering requested by a Supplier that captures information beyond the minimum components required by the Customerrsquos prevailing retail service tariff andor requires a reading methodology or schedule that varies from Standard Metering services

PJM ndash PJM Interconnection LLC or successor organization with a similar function

PJM Control Area ndash the area encompassing electric systems recognized by the North American Electric Reliability Council as the ldquoPJM Control Areardquo

3 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

PJM OI ndash the PJM Office of Interconnection the system operator for the PJM Control Area or any successor organization with a similar function

PJM Tariff ndash the PJM Open Access Transmission Tariff on file with the FERC and which sets forth the rates terms and conditions of transmission service over transmission facilities located in the PJM Control Area

3a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 6: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

110 ELECTRICITY SUPPLIER CHARGES BILLING AND PAYMENT 21 111 Charges for UtilitySupplier Services 21 112 Electricity Supplier Payment of Obligations to the Company 21

1121 Billing Procedure 21 1122 Billing Correction and Estimated Billing 21 1123 Manner of Payment 22 1124 Late Fee for Unpaid Balances 22 1125 Net Billing between the Company and Electricity Supplier 22 1126 Billing Disputes 22

113 Billing for Electricity Supplierrsquos Obligations to Other Parties 22

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION 23 121 Billing Services Selection and Change 23

1211 Billing Service Options 23 1212 Notification of Billing Option Change 23 1213 Change of Billing Options Offered 23

122 Meter Reading Information 23 1221 Estimated Meter Read 23 1222 Meter Read Data 23

123 Separate (Dual) Billing 23 1231 Customer Billing Complaints 23

124 Company Consolidated Billing23a 1241 Billing Format ndash Bill Ready23a 1242 Purchase of Electricity Supplier Receivables 23a

12421 Payment Posting 23b 1243 Billing and Payment Data Access 23b 1244 Bill Due Date 23b 1245 Utility Responsibilities in the event of Supplier Default 23b

125 Electricity Supplier Consolidated Billing 23c 126 Billing and Payment Programs 23c

1261 Budget Billing Plan23c 1262 Direct Debit Plan23c

127 Taxes 23c 1271 Company Tax Responsibilities 23c 1272 Supplier Tax Responsibilities 23c 1273 Tax Exemptions 23c

iiia

Approved by Letter Order dated August 1 2017 Effective September 1 2017

130 COMPANY-SUPPLIED METERING SERVICES 24 131 Meters 24 132 Reading 24 133 Non-standard Meteringhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip25 134 Meter Testing 25

140 NON-UTILITY SUPPLIED METERING SERVICES 25

141 Advanced Metering 25

150 SYSTEM OPERATION 26 151 Curtailment 26 152 Reasonable Efforts 26 153 PJM Requirements 26

160 CONFIDENTIALITY OF INFORMATION 26 161 Generally 26 162 Customer-Specific Information 26

170 DISPUTE RESOLUTION 27 171 Informal Resolution of Disputes 27 172 Recourse 27

180 FORCE MAJEURE 27

190 REGULATORY AUTHORIZATIONS AND JURISDICTION 27 191 Compliance with Applicable Legal Authorities 27 192 Change in Applicable Legal Authorities 28

200 LIMITATION OF LIABILITY 28 201 General Limitation of Liability 28 202 Limitation of Liability for Service Interruptions and Variations 28 203 Additional Limitations of Liability in Connection with Competitive

Power Supply 28

210 MISCELLANEOUS PROVISIONS 29 211 Notices 29 212 No Prejudice of Rights 29 213 Fluctuations 29 214 Interruptible Service 29 215 Customer Curtailment by Supplier 29

iv

Approved by Letter Order dated August 1 2017 Effective September 1 2017

10 DEFINITIONSEXPLANATION OF ABBREVIATIONS

Account - An account for a Customer is one metered or unmetered rate or service classification and is identified by a Company designated Contract Account ID or Service Number

Appropriate Similar Day ndash hourly forecasted load based on a comparable weekday month and season

Assignment of Contract ndash an assignment or transfer of a customer service id from one Supplier to another

Advanced Metering - metering equipment that provides for the monitoring andor recording of electric consumption data to enable remote interrogation to collect interval measurement of energy and Demand

Ancillary Services ndash services that are necessary for the transmission and distribution of electricity from supply sources to loads and for maintaining reliable operation of the transmission and distribution system

Bankruptcy - includes but not limited to the appointment of a receiver liquidator or trustee of the Electricity Supplier or a decree by a court adjudging the Electricity Supplier bankrupt or insolvent or sequestering any substantial part of its property or a petition to declare bankruptcy or to reorganize the Electricity Supplier

Business Day ndash any day on which the Companyrsquos and PJMrsquos Corporate offices are open for business

Charge ndash any fee that is billable by the Company to the Electricity Supplier under this Tariff including any fee(s) for UtilitySupplier Services

Commission ndash the Public Service Commission of Maryland

Company - also known as the Electricity Distribution Company or Delmarva Power amp Light Company

Companyrsquos System ndash the transmission subtransmission and Distribution Facilities owned operated and maintained by the Company or its agent

Competitive Power Supply ndash unbundled energy capacity transmission andor Ancillary Services provided by an Electricity Supplier to Customers except that Competitive Power Supply does not include such services provided to Customers by the Company in the provision of Standard Offer Service

Control Area Operator ndash PJM Interconnection LLC or successor organization

Coordinated Electricity Supplier ndash an Electricity Supplier that has appointed a Scheduling Coordinator as its designated agent for the purpose of submitting energy schedules to the PJM Office of Interconnection

Credit Amount ndash an amount equal to the greater of $25000 or the sum of two months of a) Projected Customer payments to the Electricity Supplier for the Companys services if the Electricity Supplier provides consolidated billing and b) Electricity Supplier payments for supplier services provided by the Company

1 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Credit Resources ndash financial resources including but not limited to investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or cash deposit in the Credit Amount

Creditworthy ndash a creditworthy Electricity Supplier meets the Companyrsquos credit standards and pays the Companys billed charges when due

Customer ndash any person partnership association corporation or governmental agency or other entity or its duly authorized representative receiving Competitive Power Supply from an Electricity Supplier Also called a Business Partner

Delivery Service ndash the provision of electric distribution and other services provided by the Company to a Customer who has exercised its right and buys all of its electric supply services (ie capacity energy fuel Transmission and Ancillary Services) for an Account from an Electric Supplier other than the Company

Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts

Demand Response Program ndash is a voluntary PJM program that compensates end-use (retail) customers for reducing their electricity use (load) when requested by PJM during periods of high power prices or when the reliability of the gird is threatened These customers receive payments from PJM members called Curtailment Service Providers

Distribution Facilities ndash electric facilities owned by the Company that operate at voltages of 34500 volts or less and that are used to deliver electricity to Customers up through and including the point of physical connection with electric facilities owned by the Customer

Electricity Supplier or ldquoSupplierrdquo ndash a supplier of electricity that has been certified or licensed by the Commission to sell electricity to Customers within the State of Maryland For the purpose of this document the Company is not an Electricity Supplier in the provision of Standard Offer Service An Electricity Supplier sells electricity to Customers utilizing the Transmission andor Distribution Facilities of the Company

Electricity Supplier Representative ndash any officer director employee consultant contractor or other agent or representative of the Electricity Supplier who has the authority to bind Electricity Supplier

Electric Supply amp Delivery Service - the provision of electric distribution and other services provided by the Company to a Customer who buys all of its electric supply services (ie capacity energy Transmission and Ancillary Services) for an Account from the Company Electric Supply amp Delivery Service includes Delivery Service Transmission Service and Standard Offer Service or Hourly Priced Service and associated charges

Electronic Data Interchange (EDI) ndash the computer to computer exchange of business documents in conformance with ANSI X12 standards also known as Electronic Transactions

2 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Emergency ndash a condition or situation which the Company or PJM deems in its reasonable judgment imminently likely to endanger life or property or affect or impair or imminently will affect or impair the Companyrsquos electrical system or the electric system of others to which the Companyrsquos electrical system is directly or indirectly connected Such a condition or situation includes but is not limited to potential overloading of the Companyrsquos transmission andor distribution circuits PJM minimum generation (ldquolight loadrdquo) conditions unusual operating conditions on either the Companyrsquos or the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplier without jeopardizing the Companyrsquos electric system or the electrical systems of others to which the Companyrsquos electrical system is directly or indirectly interconnected

FERC ndash the Federal Energy Regulatory Commission

Force Majeure ndash an event of Force Majeure shall be as defined in Section 180

Full Requirements Service Provision ndash a provision that requires that an Electricity Supplier be the sole source of electricity supply supporting 100 of its customersrsquo purchased supply needs

Interval Metering ndash metering equipment that supplies hourly or sub-hourly kwh and kwd readings

Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts

Kilowatt-hour or kWh ndash 1000 watts for one (1) hour or 1000 watt-hours

Load Serving Entity or ldquoLSErdquo ndash a PJM tariff term referring to an entity that has been granted the authority or has an obligation pursuant to State or local law regulation or franchise to sell electric energy to end-users within the PJM control area

Locational Marginal Price or ldquoLMPrdquo ndash the hourly integrated marginal price to serve load at individual locations throughout PJM calculated by the PJM OI as specified in the PJM Tariff

Megawatt or MW - one thousand kilowatts

Meter Read Date ndash the date on which the Company schedules a meter to be read for purposes of producing a Customer bill in accordance with the regularly scheduled billing cycles of the Company

Non-standard Metering - Metering requested by a Supplier that captures information beyond the minimum components required by the Customerrsquos prevailing retail service tariff andor requires a reading methodology or schedule that varies from Standard Metering services

PJM ndash PJM Interconnection LLC or successor organization with a similar function

PJM Control Area ndash the area encompassing electric systems recognized by the North American Electric Reliability Council as the ldquoPJM Control Areardquo

3 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

PJM OI ndash the PJM Office of Interconnection the system operator for the PJM Control Area or any successor organization with a similar function

PJM Tariff ndash the PJM Open Access Transmission Tariff on file with the FERC and which sets forth the rates terms and conditions of transmission service over transmission facilities located in the PJM Control Area

3a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 7: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

130 COMPANY-SUPPLIED METERING SERVICES 24 131 Meters 24 132 Reading 24 133 Non-standard Meteringhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip25 134 Meter Testing 25

140 NON-UTILITY SUPPLIED METERING SERVICES 25

141 Advanced Metering 25

150 SYSTEM OPERATION 26 151 Curtailment 26 152 Reasonable Efforts 26 153 PJM Requirements 26

160 CONFIDENTIALITY OF INFORMATION 26 161 Generally 26 162 Customer-Specific Information 26

170 DISPUTE RESOLUTION 27 171 Informal Resolution of Disputes 27 172 Recourse 27

180 FORCE MAJEURE 27

190 REGULATORY AUTHORIZATIONS AND JURISDICTION 27 191 Compliance with Applicable Legal Authorities 27 192 Change in Applicable Legal Authorities 28

200 LIMITATION OF LIABILITY 28 201 General Limitation of Liability 28 202 Limitation of Liability for Service Interruptions and Variations 28 203 Additional Limitations of Liability in Connection with Competitive

Power Supply 28

210 MISCELLANEOUS PROVISIONS 29 211 Notices 29 212 No Prejudice of Rights 29 213 Fluctuations 29 214 Interruptible Service 29 215 Customer Curtailment by Supplier 29

iv

Approved by Letter Order dated August 1 2017 Effective September 1 2017

10 DEFINITIONSEXPLANATION OF ABBREVIATIONS

Account - An account for a Customer is one metered or unmetered rate or service classification and is identified by a Company designated Contract Account ID or Service Number

Appropriate Similar Day ndash hourly forecasted load based on a comparable weekday month and season

Assignment of Contract ndash an assignment or transfer of a customer service id from one Supplier to another

Advanced Metering - metering equipment that provides for the monitoring andor recording of electric consumption data to enable remote interrogation to collect interval measurement of energy and Demand

Ancillary Services ndash services that are necessary for the transmission and distribution of electricity from supply sources to loads and for maintaining reliable operation of the transmission and distribution system

Bankruptcy - includes but not limited to the appointment of a receiver liquidator or trustee of the Electricity Supplier or a decree by a court adjudging the Electricity Supplier bankrupt or insolvent or sequestering any substantial part of its property or a petition to declare bankruptcy or to reorganize the Electricity Supplier

Business Day ndash any day on which the Companyrsquos and PJMrsquos Corporate offices are open for business

Charge ndash any fee that is billable by the Company to the Electricity Supplier under this Tariff including any fee(s) for UtilitySupplier Services

Commission ndash the Public Service Commission of Maryland

Company - also known as the Electricity Distribution Company or Delmarva Power amp Light Company

Companyrsquos System ndash the transmission subtransmission and Distribution Facilities owned operated and maintained by the Company or its agent

Competitive Power Supply ndash unbundled energy capacity transmission andor Ancillary Services provided by an Electricity Supplier to Customers except that Competitive Power Supply does not include such services provided to Customers by the Company in the provision of Standard Offer Service

Control Area Operator ndash PJM Interconnection LLC or successor organization

Coordinated Electricity Supplier ndash an Electricity Supplier that has appointed a Scheduling Coordinator as its designated agent for the purpose of submitting energy schedules to the PJM Office of Interconnection

Credit Amount ndash an amount equal to the greater of $25000 or the sum of two months of a) Projected Customer payments to the Electricity Supplier for the Companys services if the Electricity Supplier provides consolidated billing and b) Electricity Supplier payments for supplier services provided by the Company

1 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Credit Resources ndash financial resources including but not limited to investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or cash deposit in the Credit Amount

Creditworthy ndash a creditworthy Electricity Supplier meets the Companyrsquos credit standards and pays the Companys billed charges when due

Customer ndash any person partnership association corporation or governmental agency or other entity or its duly authorized representative receiving Competitive Power Supply from an Electricity Supplier Also called a Business Partner

Delivery Service ndash the provision of electric distribution and other services provided by the Company to a Customer who has exercised its right and buys all of its electric supply services (ie capacity energy fuel Transmission and Ancillary Services) for an Account from an Electric Supplier other than the Company

Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts

Demand Response Program ndash is a voluntary PJM program that compensates end-use (retail) customers for reducing their electricity use (load) when requested by PJM during periods of high power prices or when the reliability of the gird is threatened These customers receive payments from PJM members called Curtailment Service Providers

Distribution Facilities ndash electric facilities owned by the Company that operate at voltages of 34500 volts or less and that are used to deliver electricity to Customers up through and including the point of physical connection with electric facilities owned by the Customer

Electricity Supplier or ldquoSupplierrdquo ndash a supplier of electricity that has been certified or licensed by the Commission to sell electricity to Customers within the State of Maryland For the purpose of this document the Company is not an Electricity Supplier in the provision of Standard Offer Service An Electricity Supplier sells electricity to Customers utilizing the Transmission andor Distribution Facilities of the Company

Electricity Supplier Representative ndash any officer director employee consultant contractor or other agent or representative of the Electricity Supplier who has the authority to bind Electricity Supplier

Electric Supply amp Delivery Service - the provision of electric distribution and other services provided by the Company to a Customer who buys all of its electric supply services (ie capacity energy Transmission and Ancillary Services) for an Account from the Company Electric Supply amp Delivery Service includes Delivery Service Transmission Service and Standard Offer Service or Hourly Priced Service and associated charges

Electronic Data Interchange (EDI) ndash the computer to computer exchange of business documents in conformance with ANSI X12 standards also known as Electronic Transactions

2 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Emergency ndash a condition or situation which the Company or PJM deems in its reasonable judgment imminently likely to endanger life or property or affect or impair or imminently will affect or impair the Companyrsquos electrical system or the electric system of others to which the Companyrsquos electrical system is directly or indirectly connected Such a condition or situation includes but is not limited to potential overloading of the Companyrsquos transmission andor distribution circuits PJM minimum generation (ldquolight loadrdquo) conditions unusual operating conditions on either the Companyrsquos or the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplier without jeopardizing the Companyrsquos electric system or the electrical systems of others to which the Companyrsquos electrical system is directly or indirectly interconnected

FERC ndash the Federal Energy Regulatory Commission

Force Majeure ndash an event of Force Majeure shall be as defined in Section 180

Full Requirements Service Provision ndash a provision that requires that an Electricity Supplier be the sole source of electricity supply supporting 100 of its customersrsquo purchased supply needs

Interval Metering ndash metering equipment that supplies hourly or sub-hourly kwh and kwd readings

Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts

Kilowatt-hour or kWh ndash 1000 watts for one (1) hour or 1000 watt-hours

Load Serving Entity or ldquoLSErdquo ndash a PJM tariff term referring to an entity that has been granted the authority or has an obligation pursuant to State or local law regulation or franchise to sell electric energy to end-users within the PJM control area

Locational Marginal Price or ldquoLMPrdquo ndash the hourly integrated marginal price to serve load at individual locations throughout PJM calculated by the PJM OI as specified in the PJM Tariff

Megawatt or MW - one thousand kilowatts

Meter Read Date ndash the date on which the Company schedules a meter to be read for purposes of producing a Customer bill in accordance with the regularly scheduled billing cycles of the Company

Non-standard Metering - Metering requested by a Supplier that captures information beyond the minimum components required by the Customerrsquos prevailing retail service tariff andor requires a reading methodology or schedule that varies from Standard Metering services

PJM ndash PJM Interconnection LLC or successor organization with a similar function

PJM Control Area ndash the area encompassing electric systems recognized by the North American Electric Reliability Council as the ldquoPJM Control Areardquo

3 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

PJM OI ndash the PJM Office of Interconnection the system operator for the PJM Control Area or any successor organization with a similar function

PJM Tariff ndash the PJM Open Access Transmission Tariff on file with the FERC and which sets forth the rates terms and conditions of transmission service over transmission facilities located in the PJM Control Area

3a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 8: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

10 DEFINITIONSEXPLANATION OF ABBREVIATIONS

Account - An account for a Customer is one metered or unmetered rate or service classification and is identified by a Company designated Contract Account ID or Service Number

Appropriate Similar Day ndash hourly forecasted load based on a comparable weekday month and season

Assignment of Contract ndash an assignment or transfer of a customer service id from one Supplier to another

Advanced Metering - metering equipment that provides for the monitoring andor recording of electric consumption data to enable remote interrogation to collect interval measurement of energy and Demand

Ancillary Services ndash services that are necessary for the transmission and distribution of electricity from supply sources to loads and for maintaining reliable operation of the transmission and distribution system

Bankruptcy - includes but not limited to the appointment of a receiver liquidator or trustee of the Electricity Supplier or a decree by a court adjudging the Electricity Supplier bankrupt or insolvent or sequestering any substantial part of its property or a petition to declare bankruptcy or to reorganize the Electricity Supplier

Business Day ndash any day on which the Companyrsquos and PJMrsquos Corporate offices are open for business

Charge ndash any fee that is billable by the Company to the Electricity Supplier under this Tariff including any fee(s) for UtilitySupplier Services

Commission ndash the Public Service Commission of Maryland

Company - also known as the Electricity Distribution Company or Delmarva Power amp Light Company

Companyrsquos System ndash the transmission subtransmission and Distribution Facilities owned operated and maintained by the Company or its agent

Competitive Power Supply ndash unbundled energy capacity transmission andor Ancillary Services provided by an Electricity Supplier to Customers except that Competitive Power Supply does not include such services provided to Customers by the Company in the provision of Standard Offer Service

Control Area Operator ndash PJM Interconnection LLC or successor organization

Coordinated Electricity Supplier ndash an Electricity Supplier that has appointed a Scheduling Coordinator as its designated agent for the purpose of submitting energy schedules to the PJM Office of Interconnection

Credit Amount ndash an amount equal to the greater of $25000 or the sum of two months of a) Projected Customer payments to the Electricity Supplier for the Companys services if the Electricity Supplier provides consolidated billing and b) Electricity Supplier payments for supplier services provided by the Company

1 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Credit Resources ndash financial resources including but not limited to investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or cash deposit in the Credit Amount

Creditworthy ndash a creditworthy Electricity Supplier meets the Companyrsquos credit standards and pays the Companys billed charges when due

Customer ndash any person partnership association corporation or governmental agency or other entity or its duly authorized representative receiving Competitive Power Supply from an Electricity Supplier Also called a Business Partner

Delivery Service ndash the provision of electric distribution and other services provided by the Company to a Customer who has exercised its right and buys all of its electric supply services (ie capacity energy fuel Transmission and Ancillary Services) for an Account from an Electric Supplier other than the Company

Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts

Demand Response Program ndash is a voluntary PJM program that compensates end-use (retail) customers for reducing their electricity use (load) when requested by PJM during periods of high power prices or when the reliability of the gird is threatened These customers receive payments from PJM members called Curtailment Service Providers

Distribution Facilities ndash electric facilities owned by the Company that operate at voltages of 34500 volts or less and that are used to deliver electricity to Customers up through and including the point of physical connection with electric facilities owned by the Customer

Electricity Supplier or ldquoSupplierrdquo ndash a supplier of electricity that has been certified or licensed by the Commission to sell electricity to Customers within the State of Maryland For the purpose of this document the Company is not an Electricity Supplier in the provision of Standard Offer Service An Electricity Supplier sells electricity to Customers utilizing the Transmission andor Distribution Facilities of the Company

Electricity Supplier Representative ndash any officer director employee consultant contractor or other agent or representative of the Electricity Supplier who has the authority to bind Electricity Supplier

Electric Supply amp Delivery Service - the provision of electric distribution and other services provided by the Company to a Customer who buys all of its electric supply services (ie capacity energy Transmission and Ancillary Services) for an Account from the Company Electric Supply amp Delivery Service includes Delivery Service Transmission Service and Standard Offer Service or Hourly Priced Service and associated charges

Electronic Data Interchange (EDI) ndash the computer to computer exchange of business documents in conformance with ANSI X12 standards also known as Electronic Transactions

2 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Emergency ndash a condition or situation which the Company or PJM deems in its reasonable judgment imminently likely to endanger life or property or affect or impair or imminently will affect or impair the Companyrsquos electrical system or the electric system of others to which the Companyrsquos electrical system is directly or indirectly connected Such a condition or situation includes but is not limited to potential overloading of the Companyrsquos transmission andor distribution circuits PJM minimum generation (ldquolight loadrdquo) conditions unusual operating conditions on either the Companyrsquos or the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplier without jeopardizing the Companyrsquos electric system or the electrical systems of others to which the Companyrsquos electrical system is directly or indirectly interconnected

FERC ndash the Federal Energy Regulatory Commission

Force Majeure ndash an event of Force Majeure shall be as defined in Section 180

Full Requirements Service Provision ndash a provision that requires that an Electricity Supplier be the sole source of electricity supply supporting 100 of its customersrsquo purchased supply needs

Interval Metering ndash metering equipment that supplies hourly or sub-hourly kwh and kwd readings

Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts

Kilowatt-hour or kWh ndash 1000 watts for one (1) hour or 1000 watt-hours

Load Serving Entity or ldquoLSErdquo ndash a PJM tariff term referring to an entity that has been granted the authority or has an obligation pursuant to State or local law regulation or franchise to sell electric energy to end-users within the PJM control area

Locational Marginal Price or ldquoLMPrdquo ndash the hourly integrated marginal price to serve load at individual locations throughout PJM calculated by the PJM OI as specified in the PJM Tariff

Megawatt or MW - one thousand kilowatts

Meter Read Date ndash the date on which the Company schedules a meter to be read for purposes of producing a Customer bill in accordance with the regularly scheduled billing cycles of the Company

Non-standard Metering - Metering requested by a Supplier that captures information beyond the minimum components required by the Customerrsquos prevailing retail service tariff andor requires a reading methodology or schedule that varies from Standard Metering services

PJM ndash PJM Interconnection LLC or successor organization with a similar function

PJM Control Area ndash the area encompassing electric systems recognized by the North American Electric Reliability Council as the ldquoPJM Control Areardquo

3 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

PJM OI ndash the PJM Office of Interconnection the system operator for the PJM Control Area or any successor organization with a similar function

PJM Tariff ndash the PJM Open Access Transmission Tariff on file with the FERC and which sets forth the rates terms and conditions of transmission service over transmission facilities located in the PJM Control Area

3a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 9: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

Credit Resources ndash financial resources including but not limited to investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or cash deposit in the Credit Amount

Creditworthy ndash a creditworthy Electricity Supplier meets the Companyrsquos credit standards and pays the Companys billed charges when due

Customer ndash any person partnership association corporation or governmental agency or other entity or its duly authorized representative receiving Competitive Power Supply from an Electricity Supplier Also called a Business Partner

Delivery Service ndash the provision of electric distribution and other services provided by the Company to a Customer who has exercised its right and buys all of its electric supply services (ie capacity energy fuel Transmission and Ancillary Services) for an Account from an Electric Supplier other than the Company

Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts

Demand Response Program ndash is a voluntary PJM program that compensates end-use (retail) customers for reducing their electricity use (load) when requested by PJM during periods of high power prices or when the reliability of the gird is threatened These customers receive payments from PJM members called Curtailment Service Providers

Distribution Facilities ndash electric facilities owned by the Company that operate at voltages of 34500 volts or less and that are used to deliver electricity to Customers up through and including the point of physical connection with electric facilities owned by the Customer

Electricity Supplier or ldquoSupplierrdquo ndash a supplier of electricity that has been certified or licensed by the Commission to sell electricity to Customers within the State of Maryland For the purpose of this document the Company is not an Electricity Supplier in the provision of Standard Offer Service An Electricity Supplier sells electricity to Customers utilizing the Transmission andor Distribution Facilities of the Company

Electricity Supplier Representative ndash any officer director employee consultant contractor or other agent or representative of the Electricity Supplier who has the authority to bind Electricity Supplier

Electric Supply amp Delivery Service - the provision of electric distribution and other services provided by the Company to a Customer who buys all of its electric supply services (ie capacity energy Transmission and Ancillary Services) for an Account from the Company Electric Supply amp Delivery Service includes Delivery Service Transmission Service and Standard Offer Service or Hourly Priced Service and associated charges

Electronic Data Interchange (EDI) ndash the computer to computer exchange of business documents in conformance with ANSI X12 standards also known as Electronic Transactions

2 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Emergency ndash a condition or situation which the Company or PJM deems in its reasonable judgment imminently likely to endanger life or property or affect or impair or imminently will affect or impair the Companyrsquos electrical system or the electric system of others to which the Companyrsquos electrical system is directly or indirectly connected Such a condition or situation includes but is not limited to potential overloading of the Companyrsquos transmission andor distribution circuits PJM minimum generation (ldquolight loadrdquo) conditions unusual operating conditions on either the Companyrsquos or the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplier without jeopardizing the Companyrsquos electric system or the electrical systems of others to which the Companyrsquos electrical system is directly or indirectly interconnected

FERC ndash the Federal Energy Regulatory Commission

Force Majeure ndash an event of Force Majeure shall be as defined in Section 180

Full Requirements Service Provision ndash a provision that requires that an Electricity Supplier be the sole source of electricity supply supporting 100 of its customersrsquo purchased supply needs

Interval Metering ndash metering equipment that supplies hourly or sub-hourly kwh and kwd readings

Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts

Kilowatt-hour or kWh ndash 1000 watts for one (1) hour or 1000 watt-hours

Load Serving Entity or ldquoLSErdquo ndash a PJM tariff term referring to an entity that has been granted the authority or has an obligation pursuant to State or local law regulation or franchise to sell electric energy to end-users within the PJM control area

Locational Marginal Price or ldquoLMPrdquo ndash the hourly integrated marginal price to serve load at individual locations throughout PJM calculated by the PJM OI as specified in the PJM Tariff

Megawatt or MW - one thousand kilowatts

Meter Read Date ndash the date on which the Company schedules a meter to be read for purposes of producing a Customer bill in accordance with the regularly scheduled billing cycles of the Company

Non-standard Metering - Metering requested by a Supplier that captures information beyond the minimum components required by the Customerrsquos prevailing retail service tariff andor requires a reading methodology or schedule that varies from Standard Metering services

PJM ndash PJM Interconnection LLC or successor organization with a similar function

PJM Control Area ndash the area encompassing electric systems recognized by the North American Electric Reliability Council as the ldquoPJM Control Areardquo

3 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

PJM OI ndash the PJM Office of Interconnection the system operator for the PJM Control Area or any successor organization with a similar function

PJM Tariff ndash the PJM Open Access Transmission Tariff on file with the FERC and which sets forth the rates terms and conditions of transmission service over transmission facilities located in the PJM Control Area

3a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 10: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

Emergency ndash a condition or situation which the Company or PJM deems in its reasonable judgment imminently likely to endanger life or property or affect or impair or imminently will affect or impair the Companyrsquos electrical system or the electric system of others to which the Companyrsquos electrical system is directly or indirectly connected Such a condition or situation includes but is not limited to potential overloading of the Companyrsquos transmission andor distribution circuits PJM minimum generation (ldquolight loadrdquo) conditions unusual operating conditions on either the Companyrsquos or the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplierrsquos electrical system or conditions such that the Company is unable to accept energy from the Electricity Supplier without jeopardizing the Companyrsquos electric system or the electrical systems of others to which the Companyrsquos electrical system is directly or indirectly interconnected

FERC ndash the Federal Energy Regulatory Commission

Force Majeure ndash an event of Force Majeure shall be as defined in Section 180

Full Requirements Service Provision ndash a provision that requires that an Electricity Supplier be the sole source of electricity supply supporting 100 of its customersrsquo purchased supply needs

Interval Metering ndash metering equipment that supplies hourly or sub-hourly kwh and kwd readings

Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts

Kilowatt-hour or kWh ndash 1000 watts for one (1) hour or 1000 watt-hours

Load Serving Entity or ldquoLSErdquo ndash a PJM tariff term referring to an entity that has been granted the authority or has an obligation pursuant to State or local law regulation or franchise to sell electric energy to end-users within the PJM control area

Locational Marginal Price or ldquoLMPrdquo ndash the hourly integrated marginal price to serve load at individual locations throughout PJM calculated by the PJM OI as specified in the PJM Tariff

Megawatt or MW - one thousand kilowatts

Meter Read Date ndash the date on which the Company schedules a meter to be read for purposes of producing a Customer bill in accordance with the regularly scheduled billing cycles of the Company

Non-standard Metering - Metering requested by a Supplier that captures information beyond the minimum components required by the Customerrsquos prevailing retail service tariff andor requires a reading methodology or schedule that varies from Standard Metering services

PJM ndash PJM Interconnection LLC or successor organization with a similar function

PJM Control Area ndash the area encompassing electric systems recognized by the North American Electric Reliability Council as the ldquoPJM Control Areardquo

3 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

PJM OI ndash the PJM Office of Interconnection the system operator for the PJM Control Area or any successor organization with a similar function

PJM Tariff ndash the PJM Open Access Transmission Tariff on file with the FERC and which sets forth the rates terms and conditions of transmission service over transmission facilities located in the PJM Control Area

3a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 11: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

PJM OI ndash the PJM Office of Interconnection the system operator for the PJM Control Area or any successor organization with a similar function

PJM Tariff ndash the PJM Open Access Transmission Tariff on file with the FERC and which sets forth the rates terms and conditions of transmission service over transmission facilities located in the PJM Control Area

3a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 12: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

Premise ndash one contiguous property or site which normally has one delivery point of service and one or more metered or unmetered service classes that when totaled equal the entire electricity used at that one Premise or site Each Premise shall have only one Electricity Supplier providing the electric supply requirements for that one Premise Multiple Premises or sites under the same name are considered multiple Customers

Scheduling Coordinator ndash an entity recognized by the PJM OI and qualified to act on behalf of the Electricity Supplier in taking such actions with PJM as are necessary in order for Electricity Supplierrsquos obligations as defined in this Tariff to be met including the submission of energy schedules to the PJM OI and that either is (1) a member of the PJM Interconnection LLC or (2) is the agent for scheduling purposes of one or more Electricity Suppliers that are members of the PJM Interconnection LLC

Service Territory ndash the geographic areas of the State of Maryland in which the Company has an electric distribution franchise to serve electric Customers

Standard Metering Services ndash the capture by metering equipment of the minimum billing components required by the Customerrsquos prevailing retail service tariff that is read on scheduled meter reading dates in order to enable a bill to be created in accordance with the regularly scheduled billing cycle

Standard Offer Service ndash electricity service which the Company must offer to its eligible customers who do not otherwise receive electricity from an Electricity Supplier

Supplier Average Generation Rate ndash the simple average generation or commodity portion of the Supplier rate which does not include the transmission portion of the rate which the Supplier charged an individual Customer for a 12 month period or for the portion of a 12 month period that they served an individual Customer

Supplier Responsibilities - those actions to be taken by a Supplier that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Competitive Electric Supply to serve Customers located within the Companys Service Territory (including load forecasting certain scheduling-related functions and reconciliation) and any other activity necessary either with PJM or otherwise for the Supplier to provide Competitive Electric Supply

Transmission Service - Transmission Services for the delivery of power in and through Delmarvas service territory are to be provided under the PJM Open Access Transmission Tariff on file with the FERC and as amended from time-to-time or successor tariff The facilities providing Transmission Service that are both subject to the PJM Open Access Transmission Tariff and are owned by the Company are those that operate at voltages of above 34500 volts

Undisputed Charges ndash charges for UtilitySupplier Services for which Electricity Supplier has not invoked the dispute resolution provisions of Section 17 of the Tariff

Unforced Capacity - is as defined within the PJM Reliability Assurance Agreement in effect as of November 1999 and as may be modified from time to time

UtilitySupplier Services - those services that permit the type of interface and coordination between Electricity Suppliers and the Company in connection with the delivery of Energy Supply to serve Customers located within the Companyrsquos Service Territory including reconciliation functions and those services provided by the Company to the Supplier as identified in this Tariff or as otherwise necessary for the Supplier to provide Competitive Electric Supply to its Customers A list of such UtilitySupplier Services and the schedule of charges for same is contained in this Tariff at Schedule 1

4 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 13: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

20 GENERAL TERMS AND CONDITIONS 21 Scope and Purpose This Tariff and any related executed agreements set forth the basic requirements for interaction and coordination between the Company as the Local Distribution Company (Company) and each Electric Supplier necessary for ensuring the delivery of Competitive Power Supply

22 Electricity Supplierrsquos Responsibilities to Customers The Electricity Supplier shall be solely responsible for having all necessary and appropriate contractual or other arrangements with its Customers consistent with Commission rules and regulations and with this Tariff The Company shall not be responsible for monitoring reviewing or enforcing such contracts or arrangements

23 Tariff to Govern This Tariff and any related executed agreements set forth the basic requirements for business interactions and coordination between the Company and Electricity Suppliers necessary for ensuring the delivery of Competitive Power Supply from Electricity Suppliers to their Customers via the Companyrsquos System

24 Recourse to the Commission Nothing in this Tariff shall restrict the rights of any party to file a complaint with the Commission

25 FERC Jurisdiction The inclusion of FERC-jurisdictional matters within the scope of this Tariff is intended solely for informational purposes and is not intended to accord any jurisdictional authority over such matters to the Commission If anything stated herein is found by the FERC to conflict with or to be inconsistent with any provision of the Federal Power Act (FPA) or any rule regulation order or determination of the FERC under the FPA the applicable FERC rule regulation order or determination of the FPA shall control To the extent required under any provision of the FPA or any rule regulation order or determination of the FERC under the FPA the Company shall secure from time to time all appropriate orders approvals and determinations from the FERC necessary to support this Tariff

26 Electricity Supplier Obligations Unless otherwise indicated an Electricity Supplier will be required to

a) Obtain a license and any other necessary approvals from the Commission and any other appropriate Maryland State agencies and local governments for participation in the Maryland retail energy market

b) Execute all appropriate Control Area Operator applications and agreements c) Submit a completed Application Package (See Section 41) d) Satisfy the creditworthiness standards of the Company pursuant to Section 5 e) Demonstrate prior to Customer enrollment via EDI that it is equipped with the

communication capabilities necessary to comply with Electronic Data Interchange (EDI) testing requirements as approved by the Commission and

f) Pay all present or future federal state municipal or other taxes imposed by any taxing authority for sale of Competitive Power Supply to retail Customers under this Tariff The Electricity Supplier shall collect and remit all such taxes to the applicable taxing authority to the extent required or permitted by law If any transaction is exempt from the payment of any such taxes the Electricity Supplier will if requested provide the Company with valid tax exemption certificates Should the Company be required to remit any such taxes directly to any applicable taxing authority other than taxes previously collected by the Company directly from the Electricity Supplierrsquos Customers the Electricity Supplier indemnifies the Company and will pay to the Company all such tax amounts upon demand 5

Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 14: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

g) Provide the Company notification regarding its door to door activity no later than the morning of the day the sales and marketing activities begin The notification shall include the Suppliers name the beginning and ending date(s) of the marketing activities and the zip codes(s)

27 Electricity Supplier and Company Obligations The Company shall provide Electricity Suppliers with services as necessary for the delivery of energy to serve retail access load located within the Companys Service Territory The Company and Electricity Supplier will cooperate in order to ensure delivery of energy to Customers The Electricity Supplier and the Company shall exchange all data materials or other information that is specified in this Tariff in accordance with Commission standards and that may otherwise be reasonably required by the Electricity Supplier or the Company in connection with their obligations under this Tariff subject to the confidentiality provisions in Section 16

28 Control Area Services and Obligations The Electricity Supplier is responsible for procuring those services provided by the PJM OI that are necessary for the delivery of Competitive Power Supply to its Customers In addition the Electricity Supplier must satisfy all obligations that are imposed on a Load Serving Entity (LSEs) in the PJM The Electricity Supplier must make all necessary arrangements for scheduling the delivery of energy through the PJM OI The Company and the Electricity Supplier shall coordinate with the PJM OI to determine the magnitude and location of the Electricity Suppliers actual or projected load as required by the PJM OI for the purpose of calculating the appropriate firm transmission service reservation unforced capacity obligation or other requirements under the PJM Tariff the PJM Reliability Assurance Agreement or the tariff or similarly applicable agreements of any other applicable Control Area Operator

The Electricity Supplier shall meet all applicable reliability standards established by the Mid-Atlantic Area Council of the North American Electric Reliability Council or its successor PJM or its successor the FERC the Commission or any other State regional federal or industry body with authority to establish reliability standards

29 Communications and Data Exchange Electronic information exchange between the Electricity Supplier and the Company under this Tariff shall employ an Electricity Supplier identification number in accordance with Commission standards In addition the Company may also assign to the Electricity Supplier identification codes that may be required by PJM in connection with the submission andor confirmation of load schedules for serving load in the Companys service territory

291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate standards To the extent the Commission has not established EDI standards the Company and the Electricity Supplier shall exchange information and data in formats agreed to by the Company and Electricity Supplier The Electricity Supplier and Company shall follow Commission approved EDI testing requirements and implementation guidelines

210 Record Retention The Electricity Supplier and the Company shall comply with all applicable laws rules and regulations for record retention as they are and may from time to time be modified including but not limited to those issued by the Commission and FERC

6 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 15: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

211 Characteristics of Service The delivery service specified and furnished by the Company shall consist of sixty (60) hertz single phase or three phase alternating current at one standard primary or secondary voltage The type of service (number of phases and voltages) available varies with location and load Voltage delivered to the customersrsquo facilities normally will be maintained within the limits prescribed by the regulations of the Commission except under Emergency conditions andor conditions beyond the reasonable control of the Company

212 Net Energy Metering 2121 Net Energy Metering Payment A Customer receiving electricity from an Electricity Supplier and participating in Rider ldquoANEMrdquo ndash Pilot Aggregate Net Energy Metering - of Delmarvarsquos Maryland Electric Tariff who has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year will be provided a net metering payment as outlined in the Rider

No later than March 31 of each year the Company will contact the Electricity Supplier of record for all Customers who have accrued or appear to be close to accruing net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year Within 15 calendar days of receipt of such list each Electricity Supplier of record will provide the Company with the Supplier Average Generation Rate that they charged each Customer for the prior 12 months or for the portion of the prior 12 months that they served each Customer The Company will notify each Electricity Supplier of record of any additional Customers that have accrued net excess generation for the 12-month period ending with the billing cycle that is complete immediately prior to the end of April of that year subsequent to the March 31 notification Within seven calendar days of receipt each Electricity Supplier of record will provide the Company the Supplier Average Generation Rate that they charged each additional Customer for the prior twelve months or for the portion of the prior 12 months that they served each Customer The Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 is the only rate that will be used to calculate the credit to the Customer for the entire 12-month period If the Electricity Supplier of record does not provide rate information within the specified time period the calculation of the credit to the Customer will use the rate paid to the Companyrsquos SOS Customers as a proxy for developing the net excess generation credit

If a Customer discontinues service prior to the billing cycle that is complete immediately prior to the end of April of that year and has accrued cumulate net excess generation the Company will notify the Electricity Supplier of record as of the last date of service The Electricity Supplier will provide within seven calendar days the Supplier Average Generation Rate that they charged the Customer for months that they served the Customer since the billing cycle that was completed immediately prior to the end of April of the previous year

If a Customer correctly disputes the Electricity Supplier of recordrsquos rate or their failure to provide the rate the Electricity Supplier will address the complaint with the Customer The Electricity Supplier will indemnify the Company for any additional costs incurred by the Company which are caused by the Electricity Supplier of recordrsquos rate not being provided in accordance with this Tariff or the Electricity Supplierrsquos failure to provide their rate These costs include but are not limited to overpayment by the Company to the Customer legal fees incurred by the Company carrying costs paid by the Company to the Customer and carrying costs incurred by the Company

6a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 16: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

2122 Net Metering Aggregation Pilot Effective April 1 2012 the Companyrsquos Net Metering Aggregation Pilot will be available to Customers who are provided Competitive Power Supply by an Electricity Supplier All of the terms and conditions associated with the Net Metering Aggregation Pilot as described in Rider ANEM All Customers participating in the Net Metering Aggregation Pilot must be served by the same Electricity Supplier and use Dual Billing

The Company will provide the Electricity Supplier meter read data for each aggregated account in accordance with Section 12 of this Tariff Within five business days after the Meter Read Date the Company will provide the Electricity Supplier with the following information about the eligible customer-generator in a format agreed upon between the Company and Electricity Supplier

1 Account number ndash eligible ldquohostrdquo account 2 Account number(s) ndash aggregated accounts 3 Start meter reading date 4 Stop meter reading date 5 Start index 6 Stop index 7 kWh consumed or generated

If the aggregated group has accrued net excess generation for the 12-month period that ends with the billing cycle that is complete immediately prior to the end of April of each year then the eligible ldquohostrdquo account of the aggregation group will be provided a net metering payment at the Supplier Average Generation Rate provided by the Electricity Supplier of record as of March 31 The net metering credit will be calculated for the entire group as outlined in Section 2121 of this Tariff The total amount of the payment will be provided to the eligible ldquohostrdquo account

6b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 17: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

30 UTILIZATION OF SCHEDULING COORDINATORS 31 Participation Through a Scheduling Coordinator An Electricity Supplier is responsible for performing the responsibilities and obligations provided in this Tariff but may elect to perform certain functions through a Scheduling Coordinator To the extent an Electricity Supplier so elects it becomes a Coordinated Electricity Supplier A Coordinated Electricity Supplier may retain up to ten Scheduling Coordinators with the Company at any time More than ten Scheduling Coordinators may be allowed if mutually agreed upon by the Electricity Supplier and the Company An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator for all the Electricity Supplierrsquos responsibilities including Unforced capacity obligation import capability load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator is responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier If there are multiple Scheduling Coordinators each shall be responsible for meeting all of the requirements of PJM which may be necessary in order to carry out its responsibilities for that portion of the Coordinated Electricity Suppliers load that is attributable to such Scheduling Coordinator There shall not be multiple Scheduling Coordinators where one such Coordinator performs certain functions and another Coordinator performs certain other functions relative to the same customers or load

An Electricity Supplier may become a Coordinated Electricity Supplier by entering into a business arrangement with another Electricity Supplier or other entity that will act as a Scheduling Coordinator A Coordinated Electricity Supplier must enter into this business arrangement with a Scheduling Coordinator(s) for all the Electricity Supplierrsquos responsibilities including unforced capacity obligation transmission obligation import capability load forecasting load scheduling and reconciliation rights and responsibilities The Scheduling Coordinator or multiple Scheduling Coordinators acting together are responsible for meeting all of the requirements of PJM which may be necessary in order to carry out itstheir responsibilities All actions of the Scheduling Coordinator on behalf of the Electricity Supplier are binding on and attributable to the Electricity Supplier

32 Designation of a Scheduling Coordinator To designate a Scheduling Coordinator the Electricity Supplier must provide the Company with a completed Scheduling Coordinator Designation Form fully executed by both the Electricity Supplier and the Scheduling Coordinator The Scheduling Coordinator Designation Form is not intended to supplant or replace any agency contract between the Electricity Supplier and a Scheduling Coordinator

33 Change of Scheduling Coordinator The Electricity Supplier shall notify the Company in writing if it changes Scheduling Coordinators or ceases to be a Coordinated Electricity Supplier or ceases to provide scheduling coordination on its own behalf and said notice shall specify the effective month of the change or termination The effective day of the change or termination shall be the first day of the month indicated in the notification letter If notification is received by the Company less than 10 Business Days before the first day of that month the effective day of the change shall be the first day of the subsequent month The Company will provide confirmation of receipt of change of Scheduling Coordinator to the Electricity Supplier within 2 Business Days of receipt of such notice In the event the

7 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 18: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

Electricity Supplier ceases using a Scheduling Coordinator the Electricity Supplier shall immediately assume the direct performance of all Electricity Supplier Responsibilities under this Tariff

34 Load Scheduling Through a Scheduling Coordinator Coordinated Electricity Suppliers cannot submit individual load schedules to the PJM OI nor can Coordinated Electricity Suppliers propose scheduling changes on an individual basis Rather the Scheduling Coordinator is responsible for submitting all schedules and changes thereto on behalf of itself as well as its Coordinated Electricity Suppliers

35 Primary Obligations of Electricity Supplier Notwithstanding any designation of a Scheduling Coordinator the Electricity Supplier remains responsible for fulfilling all of its obligations and requirements under this Tariff

8 Approved at the MD PSC Administrative Meeting on September 21 2011 and Effective September 26 2011

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 19: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

40 COMMENCEMENT AND TERMINATION OF UTILITYSUPPLIER SERVICES

41 Application Process to Company An Electricity Supplier seeking to sell electricity in the Companyrsquos service territory must deliver a completed Electricity Supplier Application Package (Registration) to the Company as directed through the Online Registration System

411 Completed Registration A completed Registration for services under this Tariff consists of the following

a) A completed registration contract fully executed by an Electricity Supplier Representative

b) A completed EDI Trading Partner Agreement (optional)

c) A Supplier Coordination Agreement fully executed by an Electricity Supplier Representative

d) Written evidence that the Electricity Supplier is a member in good standing and is a signatory to applicable PJM agreements either directly or through a Scheduling Coordinator

e) A completed Credit Application fully executed by an Electricity Supplier Representative

f) Proof that the Electricity Supplier has obtained a license from the Commission and any other governmental approvals required for participation in customer choice in Maryland and

g) Any registration or processing fee set forth in Schedule 1

412 Notice of Incomplete Registration for Tariff Service In the event an Electricity Supplier submits an incomplete Registration the Company will provide written notice to the Electricity Supplier of the Applicationrsquos deficiency within 10 Business Days of the date of final submission of the Registration Application An incomplete Registration shall not be processed until it is completed and delivered to the Company

413 Review of a Completed Registration Following receipt of a completed Registration Application the Company shall review the Registration and conduct a credit review The Company shall conduct its review and notify the Supplier of acceptance or rejection within 30 days of receipt of the completed Registration or within a timeframe mutually agreed to by the Company and Supplier

9 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 20: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

For approved applications the Company shall execute the necessary agreements and return executed copies to the Electricity Supplier Upon rejection of any application the Company shall provide the affected Electricity Supplier with written or electronic notice of rejection and shall state the basis for the rejection When the basis for the rejection is for credit reasons a copy of the notice shall be provided to the Commission

414 Grounds for Rejecting a Registration The Company may reject any Registration under this Tariff on any of the following grounds

a) An Electricity Supplier or an affiliate thereof has undisputed outstanding debts to the Company arising from its previous receipt of services from the Company under this Tariff

b) The Electricity Supplier has failed to satisfy the Companyrsquos credit requirements or

c) The Electricity Supplier has failed to deliver to the Company a completed Registration within 30 days of written notice of the Registrationrsquos deficiency

415 Conditional Acceptance of Registration Where grounds for rejection of an Application Registration exist due to outstanding and undisputed debts owed to the Company by an Electricity Supplier or an affiliate thereof the Company may offer the affected Electricity Supplier a conditional acceptance if the Electricity Supplier pays such debts before it receives UtilitySupplier Services If the Electricity Supplier rejects the Companyrsquos offer of conditional acceptance under this Section then its Application Registration for UtilitySupplier Services will be deemed rejected

42 Commencement of UtilitySupplier Services UtilitySupplier Services under this Tariff shall commence within 15 days after the execution by all parties of the Supplier Coordination Agreement provided that all of the information necessary for the Company to provide services has been provided to the Company and any conditions have been satisfied by the Electricity Supplier

43 Notice of Electricity Supplier Discontinuance to the Company The Electricity Supplier shall provide to the Company the same notice of discontinuance or cessation of business that the Supplier is required to provide the Commission pursuant to Commission regulations and procedures

44 Termination of UtilitySupplier Services UtilitySupplier Services under this Tariff will or may be terminated as follows

441 Supplier Cessation of or Withdrawal from Participation In the event the Electricity Supplier ceases to participate or otherwise withdraws from the provision of Competitive Power Supply to Customers in the Companyrsquos Service Territory the Supplier Coordination Agreement between the Electricity Supplier and the Company shall terminate 30 days following the date on which the Electricity Supplier ceases to supply any customers in the Companyrsquos Service Territory

10 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 21: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

442 Default by the Electricity Supplier In the event of Default by the Electricity Supplier pursuant to Section 60 of this Tariff the Company may terminate the Supplier Coordination Agreement between the Electricity Supplier and the Company by providing written notice to the Electricity Supplier in Default without prejudice to any remedies available to the Party not in Default by reason of the Default

45 Effect of Termination Upon termination of Coordination Service the Electricity Supplier shall not be authorized to provide Competitive Power Supply to the Companyrsquos System Any Customers of the Electricity Supplier shall either select a new Electricity Supplier or shall be provided Standard Offer Service in accordance with the Companyrsquos Tariff The Electricity Supplier may thereafter provide Competitive Power Supply to the Companyrsquos System only upon satisfaction of the provisions herein for obtaining UtilitySupplier Services and Company approval of a new application

46 Survival of Obligations Termination of Coordination Service for any reason shall not relieve either the Company or the Electricity Supplier of any obligation accrued or accruing prior to the termination

50 CREDITWORTHINESS

51 Purpose and Intent The Electricity Supplier must satisfy the Companyrsquos creditworthiness standards These standards must be scaleable and will take into consideration the scope of operations of each Electricity Supplier The primary scaling criterion is the projected total monies due the Company from the Electricity Supplier The purpose of the Companyrsquos credit review will be to provide reasonable and satisfactory assurance of the following

bull The Supplierrsquos ability to pay applicable Credit Amount Supplier Coordination Fees andor any applicable penalties included in this Tariff

bull The Supplierrsquos ability to process and remit applicable customer payments due the Company if the Electricity Supplier will be performing Consolidated Billing or

bull Any other charges fees or penalties authorized by the Commission and payable to the Company

52 Finding of Creditworthiness The Company will apply on a non-discriminatory basis reasonable financial evaluation standards to assess and examine the Electricity Supplierrsquos financial condition The Electricity Supplier shall demonstrate that it has sufficient Credit Resources to satisfy the Companyrsquos financial evaluation standards

53 Credit Amount The Electricity Supplier will supply all information requested by the Company necessary to establish the requested Credit Amount The Company may require the Electricity Supplier to provide either the Credit Amount or an alternate Credit Amount applicable to the Electricity Supplier The Company will periodically review the Credit Amount and related credit terms Following such review the Company may revise the required Electricity Supplierrsquos Credit Resources The Electricity Supplier shall at all times satisfy requests for Credit Resources and shall periodically but no less frequently than quarterly provide updated information to the Company to reflect any changes in financial and business status on a confidential basis and promptly notify the Company in writing of any such changes On an ongoing basis the Electricity Supplier must at all times maintain Credit Resources that are consistent as determined by the Company with its obligations to the Company

Filed with MPSC on January 9 2001 11

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 22: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

54 Change in Financial Status The Electricity Supplier shall promptly inform the Company of any facts that would cause a change in the Credit Resources applicable to the Electricity Supplier Failure to satisfy on an ongoing basis any of the requirements set forth in this Section including failure to provide additional credit funds when requested by the Company if any such failure is not cured within 10 Business Days from receipt of written notice thereof will constitute an Event of Default

55 Failure to Maintain Creditworthy Status Should an Electricity Supplier fail to maintain Creditworthy status the Company may require the Electricity Supplier to provide additional Credit Resources including but not limited to an investment-grade bond rating a guarantee from a parent entity with an investment-grade bond rating surety bond andor a letter of credit or deposit in the Credit Amount

56 No Endorsement of Electricity Supplier By determining that the Electricity Supplier is Creditworthy under this Tariff the Company makes no express or implied warranties or guarantees of any kind with respect to the financial or operational qualifications of such Electricity Supplier

12 Filed with MPSC on January 9 2001

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 23: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

60 NONCOMPLIANCE AND DEFAULT

61 Definition of Noncompliance The Company or the Electricity Supplier shall be deemed to be in noncompliance of this Tariff upon its failure to observe any material term or condition of this Tariff

62 Events of Noncompliance Noncompliance of this Tariff shall include but is not limited to the following

a) Failure of Electricity Supplier to maintain credit standards noted in the Creditworthiness Section of this Tariff

b) Electricity Supplierrsquos or Companys failure to make payment of any Undisputed Charges for Electricity UtilitySupplier Services in the time prescribed

c) Electricity Supplier or Company Bankruptcy

d) A written admission by the Electricity Supplier of its inability to pay its debts generally as they become due or the electricity Supplierrsquos consent to the appointment of a receiver trustee or liquidator of it or of all or any part of its property or

e) Breach of the Supplier Coordination Agreement

63 Supplier Default An Electricity Supplier is considered a defaulted supplier if it is unable to deliver electricity because

a) The Commission revokes or suspends the Electricity Supplierrsquos retail electricity license or

b) The Electricity Supplier is unable to transact sales through the regional transmission organization designated for Maryland by the Federal Energy Regulatory Commission

64 Cure and Default If either the Company or the Electricity Supplier fails to comply with its obligations under the Tariff (hereinafter the Noncompliant Party) the other party shall provide written notice to the Noncompliant Party describing such noncompliance in reasonable detail and demanding its cure The Noncompliant Party shall be deemed to be in default (Default) of its obligations under this Tariff if (i) it fails to cure its noncompliance within ten Business Days after its receipt of such notice or (ii) the noncompliance cannot be cured within such period and the Noncompliant Party does not commence action to cure the noncompliance within such period and thereafter diligently pursue such action to completion In the case of the Electricity Supplierrsquos failure to maintain its status as a Commission-licensed Electricity Supplier or the Electricity Supplierrsquos failure to meet its PJM obligations either directly or through a Scheduling Coordinator or Electricity Supplierrsquos Bankruptcy no notice shall be required or opportunity to cure permitted

13

Filed with MPSC on November 2 2009 and Effective on October 7 2009

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 24: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

70 CUSTOMER ENROLLMENT AND INFORMATION PROCESS FLOW

71 Pre-enrollment Information Prior to requesting pre-enrollment Customer information from the Company an Electricity Supplier shall notify the Customer of its intention to initiate such a request and obtain the Customers Consent for release of such information The Electricity Supplier notice shall specify the customer information to be requested from the Company as listed in Section 712 The Electricity Supplier is required to maintain a record of a Customers Consent for a period of not less than 180 days from its expiration subject to audit by the Commission

711 Manner of Request Electricity Suppliers are required to request pre-enrollment information from the Company as specified in Section 291

712 Customer Information Electricity Supplier requests for Customer information received via EDI transaction will include the following information

i Account name ii Billing address iii Service address iv Service Account number v Voltage level vi Rate code vii Load profile viii Meter number ix Meter type x Multiple meter indicator xi Peak load contribution xii Billed demand xiii Monthly historical demand for the previous 12 months xiv Monthly historical consumption for the previous 12 months

7121 Historical Interval Data Transmittal of historical interval meter data for the previous 12 months is provided via EDI request

72 Procedure to Formalize Selection of Electricity Supplier In order to initiate a Competitive Power Supply the Electricity Supplier will obtain appropriate authorization from the Customer or from the person authorized to act on the Customers behalf indicating the Customers choice of the Electricity Supplier in accordance with the rules and regulations of the Commission The Electricity Supplier must notify its customers that by signing up for Competitive Power Supply with the Electricity Supplier the Customer is consenting to the disclosure by the Company to the Electricity Supplier of certain basic information about the Customer At a minimum the notice shall inform the Customer that the following information will be disclosed the Customers Company account number data about meter readings rate class and electric usage the Customers name and address(es) whether the Customer is participating in the Companyrsquos Energy For Tomorrow program or as otherwise may be consistent with Commission rulings

14 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 25: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

721 Authorization Record It is the Electricity Suppliers responsibility to maintain records of the Customers authorization in the event of a dispute in order to provide documented evidence of authorization to the Company or the Commission The authorization shall include the Customerrsquos acknowledgement that the Customer has received the notice as described in Section 72

722 Enrollment by an Electricity Supplier The Electricity Supplier shall provide an electronic file to the Company containing information in accordance with this Tariff or the procedures established by the Commission or by mutual agreement of the Electricity Supplier and Company Upon receipt of the electronic file from the Electricity Supplier the Company will confirm receipt of the file Within 1 Business Day of receipt of the electronic file the Company will validate the records contained in the file and will provide an electronic validation including appropriate control totals such as number of records received and the reason for any rejections (eg invalid account number) and any information the Electricity Supplier can use to identify rejected records

723 Enrollment Processing by the Company The Company will process enrollment transactions in accordance with this Tariff and applicable Commission rules and regulations The last enrollment transactions received at days end will be effective three business days after receipt of the electronic transaction All electronic transactions associated with enrollment processing must be performed in accordance with this Tariff and applicable Commission data exchange standards rules and regulations

724 Notice of Enrollment The Company and the Electricity Supplier will provide written notice of enrollment to the Customer entering into a service agreement with the Electricity Supplier For customers this notification will occur within one business day after the Electricity Supplier receives the Companyrsquos enrollment response

73 Change of Electricity Supplier If a Customer contacts a new Electricity Supplier to request a change of Electricity Supplier and the new Electricity Supplier agrees to serve the Customer the Customers new Electricity Supplier shall obtain appropriate authorization from the Customer or person authorized to act on the Customers behalf indicating the Customers choice of Electricity Supplier and shall thereupon follow the same procedures for enrollment of Electricity Supplier as for the initial Competitive Power Supply designated in Section 72 Once the process is complete the Company will notify the Customers current Electricity Supplier by electronic transaction that the Customer has elected to terminate service from that Electricity Supplier

14a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 26: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

74 Electricity Supplier Drop Processing by the Company The Company will process valid drop transactions in accordance with this Tariff and applicable Commission rules and regulations A drop transaction received by the Company will be effective three business days after receipt of the new enrollmentdrop electronic transaction The Company will assign a customer who has been dropped by a supplier and not enrolled by a supplier to Standard Offer Service

75 Assignment of Contract At least 30 days prior to the effective date of any assignment or transfer of a customerrsquos contract from one Supplier to another the Suppliers shall jointly provide written notice to the Customers of the Supplier the Commission the Company and the Office of the Peoplersquos Counsel of the assignment of transfer In addition the Supplier receiving the transferred Customers must also contact the Company to coordinate the transfer of the Customerrsquos contact and submit a valid enrollment transaction for each Customer The Company will not render a notice of enrollment to the Customer

76 Customer Cancellation Request On request of a Customer to cancel supply service with the Electricity Supplier an Electricity Supplier shall process the Customers Cancellation Request for electric service within two Business Days after receipt of the Cancellation Request

761 Customer Cancellation Customers should first attempt to cancel service through contact with its Electricity Supplier After the third business day following a Customer request for an Electricity Supplier to cancel supply service the Customer may contact the Company to verify that a cancellation request has been processed by the company If the Company has not received a cancellation request from the Electricity Supplier and the Customer requests cancellation of supplier service the Company shall process a cancellation and return the Customer to Standard Offer Service The drop will be effective three business days after the cancelation was performed by the Company

77 Transaction Error Handling An Electricity Supplier shall notify the Company of an enrollment or drop error via EDI cancel transaction no later than two business days after the enrollment or drop transaction is initiated by the Electricity Supplier The Company shall process the cancel transaction and return the Customer to the Customers enrollment state before the erroneous transaction

771 Incumbent Supplier-Identified Erroneous Transactions If an erroneous transaction is identified by the incumbent Electricity Supplier the incumbent Electricity Supplier shall upon verifiable consent of the Customer cancel the pending Enrollment by notifying the Company by an EDI cancel transaction within 24 hours of the Customers Consent and not later than two days after the erroneous enrollment or drop transaction is received by the Company Initiation of the EDI cancel transaction by the incumbent Electricity Supplier without the verifiable Customer consent is considered an unauthorized enrollment of the Customer with the incumbent Supplier

772 Electronic Cancel Transactions Received Later Than Two Business Days EDI cancel transactions received from the incumbent Electricity Supplier later than two business days after the erroneous enrollment or drop transaction is received by the Company will be rejected

14b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 27: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

78 Customer Designation to Control Electricity Supplier acknowledges and agrees that the Company will give effect to all Customer requests to change to a new Electricity Supplier and consequently the most recent Customer designation of an Electricity Supplier for which the procedures under Section 73 have been completed will be given effect by the Company Except as otherwise provided in this Tariff the Company shall remove a customer from supplier services only if directed by the supplier subject to applicable bankruptcy law

79 Customer Termination of Service at Existing Account If there is a discontinuance of Delivery Service to a Customer at a particular Premise for any reason and such discontinuance extends beyond five calendar days the Company will notify the current Electricity Supplier of the Customers discontinuance of service for the Account at the Customers location If the discontinuance is due to a Customer moving to another Premise within the Companys service territory and if available the Company will provide the Electricity Supplier that served the Customer at the old location with the Customers new mailing address or forwarding address Any request for service at a new location must follow the procedures described in section 72 If the Company is not contacted by a selected Supplier in accordance with the procedure outlined in section 72 or section 73 the Company will provide the Customer with Electric Supply amp Delivery Service at the new location

710 Supplier Discontinuance of Service When initiating the discontinuance of service to Customers the Electricity Supplier must comply with the notification requirements of the Maryland Public Service Commission and submit a valid lsquodroprsquo transaction to the Company three days prior to the date the customer is to be discontinued

711 Effective Date of Discontinuance Any discontinuance except those under Section 78 will take effect in accordance with the provisions of this Tariff that govern a retail Customerrsquos changes of Electricity Supplier

712 Customer Number Change If the Company elects to change the account number for a Customer receiving Competitive Power Supply service from the Electricity Supplier the Company will notify the Electricity Supplier of the change in account number at the same Customer location via electronic file

713 Full Requirements Service Provision The Electricity Supplier shall agree to supply full requirements service for each of its Customers at each Customer Account enrolled Partial requirements or split load service will not be supported

15 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 28: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

80 GENERAL LOAD OBLIGATION ALLOCATION METHODS

81 The Companyrsquos Role The Company shall allocate hourly energy and daily capacity and transmission peak load contribution in accordance with the currently-effective PJM FERC and Commission rules regulations practices and procedures and as detailed in the Companys then-applicable Operating Manual Procedures for Determining Peak Load Contribution for Capacity and Transmission Service and Total Hourly Energy Obligation (the Operating Manual) The Company will submit these values electronically to PJM following the PJM published guidelines as may be changed from time to time These values will also be made available to the Electricity Supplier The Company shall provide to the Electricity Supplier customer usage data that will allow the Electricity Supplier to bill customers in a timely manner for capacity and energy that is consistent with the load obligation assigned to the Electricity Supplier

82 Load Profiles For Accounts which do not have Interval Metering the Company will provide load profiles for various classes from the Companyrsquos load research The load profiling methodology may be updated on a periodic basis throughout the duration of the Agreement subject to Public Service Commission approval All load profiles and procedures necessary to apply them to the energy capacity and transmission allocations will be made available to the Electricity Supplier

83 Use of Historical Load Information for Forecasting Customer Load Obligations The Company will provide historical Customer usage data for interval and non-interval metered Customers in accordance with Commission regulations and applicable Tariff provisions

84 Rounding to Whole Megawatts So long as the PJM OI or its successor requires the scheduling and delivery of energy only in whole MW the Company will round each Electricity Supplierrsquos aggregate load value for each hour to a whole MW value for PJMs interchange accounting purposes

85 System Losses For purposes of the Electricity Supplierrsquos load calculations the applicable system losses shall be calculated by multiplying hourly kWh sales delivered to Customer(s) served at specified voltage levels by the applicable system loss factor The applicable system loss factors are attached hereto as Schedule 2 and are subject to change from time to time to reflect changes in system losses or any separate charges on transmission customers that PJM may impose or change for the level of transmission line losses that is included in these factors Any amendments to these loss factors will be filed with the Commission and the FERC if required provided to the Electricity Supplier and become effective 30 days after filing unless otherwise ordered by the Commission or the FERC The Company will file any such revision and propose that it become effective concurrently with any change in or imposition of separate PJM line loss charges The Company will make a good faith effort to advise the Electricity Supplier of any change in these loss factors more than thirty (30) days in advance of a change when warranted

16 Revision Filed with MPSC on January 30 2009 and Effective February 18 2009

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 29: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

86 Unaccounted For EnergyResidual Load For purposes of allocating energy capacity and transmission obligations the Company will adhere to the philosophy that ldquothe sum of the parts must equal the wholerdquo on a non-discriminatory basis For energy allocation all Customer loads will be summed (after grossing up for System Losses as described in Section 85) and compared to the PJM metered zonal hourly energy The hourly residual or mismatch will be allocated back to all LSEs in a nondiscriminatory manner

87 No Warranty Although the information provided under Articles 8 and 9 shall be accurate and correct to the best of the Companyrsquos knowledge and belief for its originally-intended purposes the Company makes no warranties as to the accuracy or usefulness of the information and takes no responsibility for the Supplierrsquos use of the information and the Electricity Supplier makes no warranties hereunder regarding any such information or its use

90 LOAD RECONCILIATION CAPACITY AND TRANSMISSION ACCOUNTING PROCESSES

91 Capacity The PJM Reliability Assurance Agreement (RAA) establishes the Unforced Capacity Obligation of Load Serving Entities in PJM for the purpose of ensuring the adequacy of supply during peak load periods PJMrsquos implementation of the RAA places certain obligations on the Company to calculate and report system peak load contribution data for each Customer attributable to the Electricity Supplier

911 Customer Specific ndash In accordance with the PJM RAA and PJM rules and procedures the Company will calculate a system peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

912 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the system peak load contributions for all Customers served by the Electricity Supplier

92 Transmission The PJM Open Access Transmission Tariff (OATT) establishes the Network Service Transmission Obligation of Load Serving Entities in PJM PJMrsquos implementation of the OATT places certain obligations on the Company to calculate and report zonal peak load contribution data for each Customer attributable to the Electricity Supplier

921 Customer Specific ndash In accordance with the PJM OATT and PJM rules and procedures the Company will calculate a zonal peak load contribution ldquotagrdquo for each Customer Such calculation will be updated from time to time in accordance with PJM rules and procedures All calculation methods and results will be made available to the Electricity Supplier

922 Daily Electricity Supplier Obligation ndash The Company will report to PJM according to PJM procedures the sum of the zonal peak load contribution for each Customer served by the Electricity Supplier

17 Filed with MPSC on January 9 2001

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 30: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

93 Load Forecasting The Company is not obligated to provide load-forecasting services The Electricity Supplier is responsible for forecasting its Customer load obligations

94 Load Scheduling The Electricity Supplier is responsible for fulfilling its load obligations directly with PJM

95 The Day-After Settlement The Day-After Settlement occurs after the day of dispatch PJM will perform the first portion of settlement as part of its wholesale accounting procedures by comparing the Electricity Supplierrsquos supply schedule to the load responsibility (See 956) submitted by the Company In the Day-After Settlement PJM will bill or credit Electricity Supplier for the difference each hour between (i) any hourly energy amounts actually supplied by the Electric Service Provider and (ii) the hourly load responsibility of the Electricity Supplier The difference will be billed or credited to Electricity Supplier at PJMrsquos LMPs For the Day After Settlement actual system loads will be known Also actual system weather will be known and will be used to update Customer load profiles for monthly-metered load profile classes The Day-After Settlement will be based upon estimates of Customer consumption

951 Estimate Customer Consumption The Company will estimate hourly Customer consumption quantities as follows

9511 Hourly Metered Customers If available actual data from interval-metered Customers will be collected by the Company and will be used for energy reconciliation If not available usage will be estimated

9512 Monthly Metered Customers The class average load profile will be determined in accordance with the load profiling methodology The class average profile will be scaled according to each Customerrsquos historical consumption factor

9513 Apply Losses The Customers estimated usage by hour from Section 9511 will be multiplied by the appropriate loss factor respective to Customer class per Section 85 to determine the Customers estimated gross usage by hour

9514 Aggregate Profiles The gross hourly estimated usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

9515 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

18 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 31: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

952 Submit Estimated Load Obligation Data to PJM The Company will compute and submit to PJM the complete hourly estimated load obligation data quantities for each day Such PJM data submittals will be in accordance with PJM accounting deadlines as outlined in the PJM Operating Agreement

953 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

96 The ldquo60 Dayrdquo SettlementConsumption Energy Imbalance The second portion of the settlement process occurs after all actual monthly and interval energy usage data has been processed for the day in question (approximately 45-60 days later) Consumption Energy Imbalance service accounts for mismatches between the Day-After Load Estimation for the Electricity Supplier and the energy that was actually used by its Customers Given the absence of universal real-time metering the calculation of Consumption Energy Imbalance quantities must typically occur after the monthly reading or monthly estimation of Customers meters

961 Meter Data Collection Meter data collected by the Company shall be utilized to calculate the quantity of energy actually consumed by an Electricity Supplierrsquos Customers for a particular period Such collection shall occur at the time of a Customerrsquos monthly meter reading

962 Monthly Metered Customers Data from monthly-metered Customers is collected in subsets corresponding to Customer billing cycles (billing routes) which close on different days of the month The Company shall convert such meter data including estimates for Customers to the equivalent hourly usage Load profile class load curves will be scaled to metered usage to derive an estimate for the hour-by-hour usage

963 Determine Consumption Energy Imbalances The Company will determine hourly Consumption Energy Imbalance quantities at a minimum on a calendar month basis in conjunction with PJMrsquos billing schedule

9631 Apply Losses The monthly-metered Customers estimated usage by hour and the interval metered Customerrsquos hourly usage will be multiplied by the appropriate loss factor respective to Customer class to determine the Customers gross usage by hour

9632 Aggregate Profiles The gross hourly usage quantity for each Customer will be aggregated by the Company to arrive at a total gross Customer usage quantity by hour for each Electricity Supplier

19 Filed with MPSC on January 9 2001

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 32: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

9633 Allocate Unaccounted for Energy (Residual) The gross hourly loads for the Electricity Suppliers and the Company will be compared to the aggregate PJM zonal load for the Companyrsquos zone Any differences will be allocated to the Electricity Supplier and the Companyrsquos loads on a non-discriminatory basis in accordance with Section 86

9634 Calculate Consumption Energy Imbalances Hourly Consumption Energy Imbalances are calculated respective to each Electricity Supplierrsquos Estimated Day-After Settlement Load Obligations

964 Submit Reconciliation Data to PJM After a calendar month becomes fully metered the Company will compute and submit to PJM the complete hourly Consumption Energy Imbalance quantities for that calendar month Such PJM data submittals will be in accordance with PJM accounting deadlines and the timing of such submittals may change from time to time

96 5 Financial Settlement and Billing The Company and the Electricity Supplier will rely on PJM to perform calculations to determine the monetary value of reconciliation quantities and to bill andor credit the Electricity Suppliers and the Company for oversupplies and undersupplies at an hourly price through the PJM grid accounting system Oversupplies and undersupplies will be calculated as determined by PJM

97 Settlement Beyond ldquo60 Daysrdquo Subsequent to the ldquo60 Day Settlementrdquo PJMrsquos monthly bills to the Company and Supplier shall be subject to adjustment for any errors in arithmetic computation meter readings or other errors as agreed upon by the Company and the Supplier

98 Settlement Calculations Settlement calculations will be provided upon request

100 ACTIVE LOAD MANAGEMENT

101 Demand Side Management (DSM) The Company shall continue to offer voluntary DSM programs to its distribution customers The Company will continue to receive all PJM capacity benefits from the operation of these programs

102 DSM Operation The Company shall have the right to operate its DSM programs in response to PJM requests or whenever the Company determines it to be appropriate or necessary

103 Ownership Maintenance and Operation of DSM Devices The Company will continue to own operate and maintain all DSM equipment hardware and software that it has paid for and installed

20 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 33: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

110 UTILITYSUPPLIER CHARGES BILLING AND PAYMENT

111 Charges for UtilitySupplier Services The Electricity Supplier agrees to pay all charges for UtilitySupplier Services provided by the Company as set forth in Schedule 1 of this Tariff

112 Electricity Supplier Payment of Obligations to the Company The Electricity Supplier shall pay for all UtilitySupplier Services or any other charge it incurs hereunder in accordance with the following provisions

1121 Billing Procedure Each month the Company shall submit an invoice to the Electricity Supplier for all charges for UtilitySupplier Services provided under this Tariff and the Supplier Coordination Agreement The invoice may be transmitted to the Electricity Supplier by any reasonable method as agreed to between the Electricity Supplier and the Company The Electricity Supplier shall make payment for Charges incurred on or before the due date that shall appear on the bill This date shall be determined by the Company and shall not be less than 15 days from the date of transmittal of the bill

1122 Billing Corrections and Estimated Billings Notwithstanding anything stated herein bills shall be subject to adjustment for any errors in arithmetic computation meter readings estimating or other errors as set forth in the Companyrsquos Tariff from the date of such original monthly billing

21 Revision Filed with MPSC on July 31 2002 and Effective August 1 2002

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 34: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

1123 Manner of Payment The Electricity Supplier shall make payments of funds payable to the Company by electronic payment to a bank designated by the Company If disputes arise regarding the Electricity Supplierrsquos bill the Electricity Supplier must pay the undisputed portion of disputed bills under investigation by the due date shown on the bill

1124 Late Fee for Unpaid Balances If payment is made to the Company after the due date shown on the bill interest will be added to the unpaid balance until the entire bill is paid at the rate of 15 per month for two months At the end of the second nominal billing interval an additional charge to be made equal to 2 of any portion of the original amount which remains unpaid at the time The total of these charges may not exceed 5

1125 Net Billing between the Company and Electricity Supplier The Parties agree that the Company may as part of the routine billing and payment process between the Company and Electricity Supplier ldquonetrsquo or offset any and all amounts which may be due and owing by the Electricity Supplier to the Company against any and all amounts which may be due and owning by the Company to the Electricity Supplier Upon mutual agreement of the Parties other charges and transactions may also be net or offset as part of the routine billing and payment process between the Company and the Electricity Supplier

1126 Billing Disputes In the event the Electricity Supplier fails to make payment on or before the due date because of a billing dispute between the Company and the Electricity Supplier the Company will continue to provide UtilitySupplier Services under this Tariff and the Supplier Coordination Agreement as long as the Electricity Supplier (1) continues to make all payments not in dispute and (2) pays into an escrow account the portion of the invoice in dispute pending resolution of the dispute If the dispute cannot be resolved the Company may terminate the Supplier Coordination Agreement and retain the amount in escrow (including interest) The Company shall notify the Electricity Supplier in writing of its intent to do so The Electricity Supplier may within 30 days file a complaint with the Commission in which case the Company will continue to provide UtilitySupplier Services until final disposition of the complaint

113 Billing for Electricity Supplierrsquos Obligations to Other Parties The Company will assume no responsibility for invoicing or billing of services between the Electricity Supplier and PJM the Electricity Supplier and any energy source or a Scheduling Coordinator and any Coordinated Electricity Suppliers

22 Revision Filed with MPSC on December 31 2005 and Effective January 15 2006

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 35: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

120 RETAIL CUSTOMER BILLING AND PAYMENT COLLECTION

121 Billing Services Selection and Change The Customer has the option to choose whether the Company or the Electricity Supplier will render a consolidated bill (including Company and Electricity Supplier charges) or whether to have separate bills from the Company and the Electricity Supplier The Electricity Supplier shall notify the Company of the Customerrsquos choice of billing service option when notifying the Company of the Customerrsquos enrollment

1211 Billing Service Options Customers will have the opportunity to choose from the following billing service options

(a) Separate (Dual) Electric CompanyElectricity Supplier Billing (b) Electric Company Consolidated Billing - Bill Ready Option (c) Electricity Supplier Consolidated Billing - Bill Ready Option ndash This option is not

available at this time please see Section 125

1212 Notification of Billing Option Change If the billing option for a Customer changes after initial enrollment the Electricity Supplier must notify the Company of the change prior to five calendar days before the scheduled meter reading date and the change will be effective the last meter reading date before we received the change

1213 Change of Billing Options Offered An Electricity Supplier who adds or deletes a billing option that it offered when UtilitySupplier Services are initiated pursuant to this Tariff shall provide 60 calendar-days notice prior to implementing the additiondeletion to its affected customers the Company the Maryland Public Service Commission Staff the Office of Peoplersquos Counsel

122 Meter Reading Information The Company will read the Customersrsquo meters in accordance with its customary practices

1221 Estimated Meter Read In the event an actual meter reading cannot be obtained the Company shall estimate the Customerrsquos consumption for billing purposes for the applicable period in accordance with Commission approved procedures

1222 Meter Read Data The Company will normally provide the Electricity Supplier with actual or estimated meter read data within 3 days of the Meter Read Date

123 Separate (Dual) Billing If the Customer chooses to use Dual Billing the Company and the Electricity Supplier will separately send their bills directly to the Customer The Company will render its bills consistent with its standard billing practices

1231 Customer Billing Complaints The Company shall process all complaints and customer services regarding the bill rendered by the Company in accordance with applicable regulations and performance specifications The Electricity Supplier shall process all complaints and customer services regarding the bill rendered by the Electricity Supplier in accordance with applicable regulations and performance specifications

23 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 36: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

124 Company Consolidated Billing The Company shall render a single consolidated bill with Customer charges for both the Company and the Electricity Supplier separately stated

1241 Billing Format ndash Bill Ready If the Company renders a consolidated bill the Supplier must transmit its billing information to the Company in a bill ready format and in accordance with the billing practices and EDI standards accepted by the Commission

a The Supplier must calculate and send its Customersrsquo charges to the Company within 3 Business Days of receipt of the meter read data If the Electricity Supplier fails to transmit its Customersrsquo information to the Company in the required timeframe the Company will not render a consolidated bill

b The Company will not be liable for the Electricity Supplierrsquos charges or losses damages or consequential damages associated with the Electricity Supplierrsquos Customers not being billed for the Electricity Supplierrsquos charges for that period

c The Electricity Supplier is responsible for the bill content transmitted to the Company

1242 Purchase of Electricity Supplier Receivables When an Electricity Supplier elects to use Company Consolidated Billing the Company will purchase the Electricity Supplierrsquos receivables pursuant to Commission rules and regulations and any other provisions of this Tariff

(a) All electricity charges resulting from the Supplier provision of Competitive Power Supply for Customers billed using Company Consolidated Billing will be purchased The Company will not purchase receivables associated with non-commodity charges or early termination fees (ETF)

(b) In the event a Customer is converted from Electric Company Consolidated Billing to Separate (Dual) Billing Supplier and Company will each be responsible for its own receivables effective as of the start of Dual Billing

(c) The Company will pay all undisputed charges to the Electricity Supplier by the 5th day from due date noted on the consolidated bill in accordance with Schedule 3 of this Tariff

(d) The Company will make payments of funds payable to the Electricity Supplier via electronic payment with remittance advice to a bank designated by the Electricity Supplier Wire transfer of funds will be made per relevant Commission orders unless other terms are mutually agreed upon

(e) Purchased Electricity Supplier receivables will be treated the same manner as Company charges pursuant to applicable Tariffs

23a Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 37: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

(f) In the event a Customer disputes an Electricity Supplierrsquos charges and notifies the Company the Company can withhold the disputed amount from that Electricity Supplier until such time that the Company is notified that the dispute has been resolved

(g) If the Electricity Supplierrsquos Customer is on a budget or levelized payment plan the Company shall only be obligated to purchase each month the amount of the monthly installment under the budget or levelized payment plan

(h) The Company may add to or deduct from any payments due to Electricity Suppliers amounts that may result from reconciliations adjustments or recalculations of estimated readings cancel and rebills or any applicable billing adjustment

(i) The Company shall also purchase account receivables of electricity based on estimated bill The Company will not purchase accounts receivables incurred prior to the Suppliers election to use Company consolidated billing for that Customer

1243 Billing and Payment Data Access The Company and the Electricity Supplier shall transmit consumption billing and related data to each other using electronic transaction for the purpose of Company consolidated billing

(a) The Company shall remit supplier revenue and billing data to the supplier by electronic means

(b) The Supplier shall have access to customer billing and payment information from the Company for the supplierrsquos presently enrolled customers at no cost beyond the tariffed rate

(c) The Company shall provide the Supplier with the same electronic access to customer bill information that it provides to the customer

1244 Bill Due Date For consolidated billing options the Electricity Supplier must adopt the same bill due date as the Company Most bill due dates will be in accordance with the Companyrsquos published bill schedule

1245 Utility Responsibilities in the event of Supplier Default A defaulted Electricity Supplier as defined in Section 63 using Electricity Company consolidated billing services remains obligated to provide the Electricity Company with information necessary to allow the Electricity Company to continue consolidated billing through the conclusion of the billing cycle in which the default occurred The defaulted Electricity Supplier is prohibited from issuing bills to persons who were customers at the time of the default unless specifically authorized by the Commission

(a) A request to authorize an Electricity Supplier to bill directly may be made to the Commission by the Company or the applicable Electricity Supplier

(b) The defaulted Electricity Supplier and the Company shall continue to abide by the Supplier Coordination Agreement

23b Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 38: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

125 Electricity Supplier Consolidated Billing The issues of the supplierrsquos qualifications to provide a consolidated billing service and their ability to purchase Company receivables have not been determined Should any Electricity Supplier elect to provide Electricity Supplier Consolidated Billing the Commission has determined that the issues of purchase of receivables and the qualifications of the Electricity Supplier to provide consolidated billing must be considered prior to any Electricity Supplier Consolidated Billing being implemented

126 Billing and Payment Programs The Company has the following programs that may impact Customer bills

1261 Budget Billing Plan The Company will continue to offer the Budget Billing Plan for its charges Customers seeking to enroll in or terminate from the Budget Billing Plan must do so by contacting the Company If a Customer is enrolled in the Companyrsquos Budget Billing Plan and switches to an Electricity Supplier the Company will perform a final budget reconciliation to remove the commodity charges from the budget bill amount The Companyrsquos portion of the budget bill amount will be based solely on its regulated charges and at the Companyrsquos discretion may include amounts required to true-up (or settle) any excessive accumulated deviation from the budget plan Such true-up may occur immediately or during the Companyrsquos regular budget review periods The Company will make budget billing available for Supplier charges If the Supplier elects to include a budget amount on the Companyrsquos consolidated bill the Supplier must provide budget billing information in a manner consistent with current regulations and EDI standards to be included on the consolidated bill

1262 Direct Debit Plan and Auto Pay The Company will continue to offer the Direct Debit and Auto Pay programs for all charges billed on a Company rendered bill Customers seeking to enroll in or terminate from these programs must do so by contacting the Company

127 Taxes In accordance with Commission procedures the entity that originates the charge is responsible for and shall remit and file taxes applicable to its charges

1271 Company Tax Responsibilities The Company is responsible for calculation collection and remittance of gross receipts taxes franchise tax on delivery service and State and local energy taxes assessed on delivery service or other products and services provided by the Company

1272 Supplier Tax Responsibilities The Electricity Supplier is responsible for calculation collection if applicable and remittance of State and sales taxes assessed on all products and services provided by the Electricity Supplier

1273 Tax Exemptions Where Customers are exempt from taxes it is the responsibility of both the Company and the Electricity Supplier to separately procure any required tax exemption certificates from the Customer

23c Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 39: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

130 COMPANY-SUPPLIED METERING SERVICES

131 Meters The Company shall provide Standard Metering Services and Company-owned Electric Metering Equipment in accordance with the Companyrsquos prevailing retail service tariff on file with the Commission as said tariff may be revised by the Company from time to time This section shall not apply to the extent Article 14 applies

132 Reading This section shall not apply to the extent Article 14 applies All Customers shall have their electric energy deliveries metered and read in accordance with applicable Commission regulations and Company procedures Electricity Supplier shall pay all charges associated with special meter reads which shall be made only for data collection and informational purposes and not for purposes of determining a date for the switching of a Customer to Competitive Power Supply

24 Revision Filed with MPSC on May 17 2004 and Effective June 1 2004

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 40: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

133 Non-standard Metering This section shall not apply to the extent Article 14 applies The Company shall own and install equipment for any Electricity Supplier requesting Company owned Non-standard Metering The Electricity Supplier shall pay all costs associated with the removal and testing of any existing electric metering equipment the installation and testing of the Non-standard Metering equipment and all incremental costs of Non-standard Metering services above those charges that the Company has included in its tariffs for standard metering The Non-standard Metering will be used for determining loads starting with the first Meter Read Date following the installation The Company shall provide but the Electricity Supplier shall pay for the installation operation and maintenance of the required compatible communicationtelephone link in order to transmit the metered information to the Company As long as it does not interfere with the Companys operations the Electricity Supplier may opt to install their own communication link for their own interrogation purposes with such link being to separate equipment that would read translate andor store data provided by a pulse-initiator that is attached to the meter In addition at the Electricity Supplierrsquos request and with written authorization from the Customer the Company will provide if feasible on-site pulse outputs through an isolation relay or similar equipment at the Electricity Supplierrsquos expense based on the Companyrsquos actual time and material costs that will allow the Electricity Supplier near real-time access to energy consumption data Any meter installed and owned by the Company shall be used for billing capacity obligation determination transmission obligation determination and energy reconciliation All meters used for billing whether required by the Company or requested by the Electricity Supplier will be maintained and tested by the Company in accordance with Commission regulations Additional metering services requested by the Electricity Supplier or the Customer and approved by the Company will be provided at charges as provided by the Company

134 Meter Testing In addition to any meter testing that is performed in compliance with Commission regulations upon the Electricity Supplierrsquos written request which shall include the Customers authorization to pull the meter for testing the Company will test designated electric meter(s) used for billing In the event a test requested by the Electricity Supplier establishes that a Company-owned electric meter is registering inaccurately by more than the applicable Commission tolerances and requirements as may be revised by the Commission from time to time the costs of said tests shall be borne by the Company Any Company-owned electric meter found to be inaccurate by more than the applicable Commission tolerances and requirements or is otherwise found to be defective shall be adjusted repaired or replaced at the sole cost and expense of the Company The cost of testing a meter at the request of the Electricity Supplier which is determined to be operating within applicable Commission tolerances and requirements and not found to be defective will be borne by the Electricity Supplier The Electricity Supplier shall pay the costs set forth in this Tariff for such testing

140 NON-UTILITY-SUPPLIED METERING SERVICES

141 Availability With written authorization from the Customer an Electricity Supplier may request and pay for non-utility owned metering for their Customer under the provisions as stated under the Metering and Meter Reading ldquoMMRrdquo Rider of the Companyrsquos retail tariff

25 Approved at the MD PSC Administrative Meeting on December 21 2016 and Effective December 26 2016

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 41: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

150 SYSTEM OPERATION

151 Curtailment The Company shall have the right to curtail interrupt or reduce the Electricity Supplierrsquos supply of electric energy and the right to disconnect the Electricity Supplierrsquos Customers whenever the Company determines or when the Company is directed by PJM that such a disconnection curtailment interruption or reduction is necessary to facilitate construction installation maintenance repair replacement or inspection of any of the Companyrsquos facilities to maintain the safety and reliability of the Companyrsquos electrical system as directed by governmental authorities or due to Emergencies forced outages potential overloading of the Companyrsquos transmission andor distribution circuits or Force Majeure Any other provisions of this Tariff that may seem to contradict this right shall be subordinated to this right Curtailments andor disconnects will be carried out in a nondiscriminatory manner with respect to a Customerrsquos Electricity Supplier

152 Reasonable Efforts The Company shall use reasonable efforts to minimize any scheduled curtailment interruption or reduction to the extent practicable under the circumstances provide the Electricity Supplier with prior notification of any such curtailment interruption or reduction to the extent practicable and resume service as promptly as practicable following elimination of the condition causing the disconnection curtailment interruption or reduction

153 PJM Requirements The Electricity Supplier acknowledges and agrees that it will cooperate with the Company so that the Company will be in compliance with all PJM Emergency Operations Procedures as defined in the PJM Operating Manual which include but are not limited to those procedures pertaining to minimum and maximum generation emergencies and measures requiring involuntary Customer participation such as supply voltage reduction or full interruption of Customer load by either manual or automatic means

160 CONFIDENTIALITY OF INFORMATION

161 Generally All information made available by the Company to the Electricity Supplier in connection with the provision of UtilitySupplier Services including but not limited to rate class load profile data and information regarding computer or communications systems owned or leased by the Company shall be used only for the purposes of receiving UtilitySupplier Services and providing Competitive Power Supply under this Tariff to Customers in the Companyrsquos service territory An Electricity Supplier shall not disclose such information to third parties without the Companyrsquos prior authorization andor consent

162 Customer-Specific Information The Company will not provide to the Electricity Supplier Customer-specific information without the Customerrsquos written consent except for information as allowed by the Commission for bill collection or credit rating reporting purposes or pursuant to Section 71 and 72 of this tariff The Electricity Supplier shall keep all such Customer-specific information supplied by the Company confidential unless the Electricity Supplier has the Customers written authorization to do otherwise

26 Revision Filed with MPSC on Revision Filed with MPSC on December 11 2008 and Effective on December 15 2008

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 42: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

170 DISPUTE RESOLUTION

171 Informal Resolution of Disputes The Company and Supplier shall use good faith efforts to informally resolve all disputes arising out of the implementation of this Tariff the provisions of the UtilitySupplier Services andor carrying out of Supplier Responsibilities

172 Recourse Complaints or disputes that are not satisfactorily resolved between the parties may be filed with

Executive Secretary Office of External Relations Maryland Public Service Commission or Maryland Public Service Commission 6 St Paul Street 6 St Paul Street Baltimore Maryland 21202 Baltimore Maryland 21202

(410) ndash767-8028 1-800-492-0474

180 FORCE MAJEURE Neither the Company nor the Electricity Supplier shall be considered to be in default in the performance of its obligations under this Tariff except obligations to make payments to the extent that performance of any such obligation is prevented or delayed by any cause existing or future which is beyond the reasonable control of and not the result of the fault or negligence of the affected party including but not limited to strike lockout or other labor difficulty acts of the other party or its agentscontractors riot civil insurrection war (whether or not declared) fire flood earthquake unusually severe weather government orders preventing performance or materially adversely affecting the affected party acts of God and other causes of a similar nature (a ldquoForce Majeure Eventrdquo) If a party is prevented or delayed in the performance of any such obligation by a Force Majeure Event such party shall immediately provide notice to the other party of the circumstances preventing or delaying performance and the expected duration thereof Such notice shall be confirmed in writing as soon as reasonably possible The party so affected by a Force Majeure Event shall endeavor to the extent reasonable to remove the obstacles which prevent performance and shall resume performance of its obligations as soon as reasonably practicable The settlement of strikes and labor disturbances shall be wholly within the discretion of the party experiencing that difficulty Economic hardship of either party shall not constitute a Force Majeure Event under this Tariff Computer problems shall not constitute a Force Majeure Event under this Tariff

190 REGULATORY AUTHORIZATIONS AND JURISDICTION

191 Compliance with Applicable Legal Authorities The Company and the Electricity Supplier are subject to and shall comply with all existing or future applicable federal state and local laws all existing or future Commission orders or regulations or other duly authorized actions of governmental authorities having jurisdiction over such matters Company will not violate directly or indirectly or become a party to a violation of any applicable federal state or local statute

27 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 43: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

regulation rule or order in order to provide service to Electricity Supplier The Companyrsquos obligation to provide service is subject to the condition that all requisite governmental and regulatory approvals for the provision of such service will have been obtained and will be maintained in force during such period of service The Electricity Supplier acknowledges and agrees that the Company may need to act in response to governmental or civil authority directives which may affect Customer load The Electricity Supplier agrees to cooperate with the Company in order to comply with said directives

192 Change in Applicable Legal Authorities This Tariff is subject to change in the future to reflect any FERC-required changes in the pricing mechanism structure andor operations of PJM or successor entity and to reflect any relevant changes required by the Commission or other Maryland State agency having jurisdiction or by virtue of any federal or state law or regulation and such changes shall be deemed to be binding upon the parties except where the right to terminate is exercised in accordance with the terms of this Tariff

200 LIMITATION OF LIABILITY

201 General Limitation Of Liability The Company shall have no duty or liability with respect to Competitive Power Supply before it is delivered by an Electricity Supplier to the Companyrsquos distribution system The Company shall have the same duty for distribution service to Customers receiving Competitive Power Supply as to those receiving electric energy and capacity from the Company In no event shall either party be liable to the other for any consequential indirect or special damages suffered by the other party arising from activities conducted pursuant to this Tariff or related Agreements

202 Limitation Of Liability For Service Interruptions And Variations The Company does not guarantee continuous regular and uninterrupted supply of service The Company may interrupt or limit the supply of service on a non-discriminatory basis with respect to suppliers for the purpose of making repairs changes or improvements in any part of its system for the general good of the service or the safety of the public or for the purpose of preventing or limiting any actual or threatened instability or disturbance of the system The Company is not liable for any loss costs damages or expense to the Electricity Supplier as a result of such interruptions or limitations of supply or for any other reasons beyond the Companys control The Company also is not liable for any loss costs damages or expense to the Electricity Supplier by failure to supply or by interruption reversal reduction surge or fluctuation in supply caused by events beyond the control of the Company or any cause except gross negligence or willful misconduct of the Company

203 Additional Limitations Of Liability In Connection With Competitive Power Supply Other than its duty to deliver Competitive Power Supply subject to the provisions of this Tariff the Company shall have no duty or liability to the Electricity Supplier providing Competitive Power Supply arising out of or related to a contract or other relationship between the Electricity Supplier and a Customer of the Electricity Supplier The Company shall implement Customer selection of the Electricity Supplier consistent with Commission rules and regulations and shall have no liability to the Electricity Supplier arising out of or related to switching or not switching Electricity Suppliers except in the event of gross negligence or willful misconduct of the Company

28 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 44: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

210 MISCELLANEOUS PROVISIONS

211 Notices All filings pertinent to this tariff should be made to

Executive Secretary Maryland Public Service Commission 6 St Paul Street Baltimore MD 21202

212 No Prejudice of Rights The failure of either party to insist on any one or more instances upon strict performance of any provisions of this Tariff or to take advantage of any of its rights hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any such right or any other right hereunder which shall remain in full force and effect

213 Fluctuations Electric delivery service must not be used by the Customer in such a manner as to cause unusual fluctuations or disturbances in the Companyrsquos delivery system Should such fluctuation or disturbance be caused by the Customer the Company may discontinue service to the Customer causing the fluctuation or disturbance or require the Customer to modify their installation andor install approved controlling devices The Electric Supplier hereby recognizes the potential for service discontinuance under this provision and waives any claim for lost profits or similar damages relating to such discontinuance

Where the use of current is intermittent or subject to violent fluctuation the Company reserves the right to base the measured Demand applicable to a Suppliers capacity obligation upon a five (5) minute period or to add to the measured Demand as determined under the measured Demand provision of the applicable Service Classification an amount equal to sixty-five percent (65) of the rated capacity in kilowatts of apparatus having fluctuating or intermittent current requirements

214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from their Supplier

215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW

29 Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 45: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

SCHEDULE 1 ndash PROCESSING FEES AND CHARGES

Company Charges (to Supplier)

1) Administrative and Processing Fee for administrative simplicity charged based on $20 per bill issued by Delmarva that

contains charges of the Electricity Supplier

2) Unscheduled Meter Read a) Non-interval $2500 per meter read

b) Interval Actual Cost (based on time and material) per meter read with a cap of $10000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

This special meter reading service shall be for data collection or informational purposes only Such special meter reading service shall not be used to expedite a Customerrsquos switch to an Electricity Supplier or to return to the Companyrsquos electric supply services Nor shall this service be used to change the Customerrsquos regular scheduled billing unless it is agreed to by the Company at the Companyrsquos sole discretion and at the Electricity Supplierrsquos additional expense

3) Meter Testing (requires Customer authorization) a) Non-interval $3000 per meter test

b) Interval Actual Cost (based on time and material) per meter test with a cap of $50000

(Provisions exist to permit upon mutual agreement a third party to provide this service at Suppliers expense)

4) Meter Exchange of Non-Utility Owned Meter Actual Cost (based on time and material) per meter

Supplier Charges (to Company)

Consolidated Billing Charge None

Revision Filed with MPSC on April 4 2002 and Effective April 1 2002

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 46: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

SCHEDULE 2 ndash SYSTEM LOSS FACTORS

Energy Loss Factors (used for hourly energy settlement)

Service Type Loss Factor Secondary 107438 Primary 104532 Transmission 102861

Demand Loss Factors (used for annual PLC calculations)

Service Type Loss Factor Secondary 107820 Primary 105669 Transmission 103193

Secondary Service - Single phase or three phase circuits carrying a nominal voltage of 480 volts or less between any two conductors

Primary Service - Single phase or three phase circuits carrying a nominal voltage of 2400 volts to 34500 volts between any two conductors

Transmission Service - Single phase or three phase circuits carrying a nominal voltage in excess of 34500 volts between any two conductors

Approved and Effective June 1 2014

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 47: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

SCHEDULE 3 - DISCOUNT RATE FOR PURCHASE OF RECEIVABLES PROGRAM ndash DELMARVA MARYLAND

1) The initial (unadjusted) Discount Rate for Residential Service Customers served under Schedules R R-TOU-ND and DPL Maryland Electric and Non-Residential Customers Type I and Type II served under Schedules SGS-S GS-SH GS-WH ORL TN and OL and SGS-S LGS-S and GS-P respectively and Hourly Priced Customers served under schedules LGS-S GS-P and GS-T of the Retail Electric Service Tariff is calculated as follows

a) The Uncollectible Expense Component percent is calculated by dividing the Electric Supplier uncollectible expense associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule The Late Payment Revenue percent is calculated by dividing the Electric Supplier Late Payment Revenue associated with each rate schedule by the electricity revenues billed for all Electricity Suppliers for that rate schedule

b) The Program Development and Operation Cost Expense Component percent is calculated by amortizing the estimated programming testing and other information technology costs directly associated with COMAR 2053 over a two year period The annual amortization cost by type is divided by the estimated number of choice accounts to derive at an annual cost per customer The estimated kWh by type are multiplied by the supply rate for that type to calculate the annual supply revenue The Program Development and Operation Cost Component percent is derived by dividing the annual cost per customer by the annual supply revenue per customer

c) The Risk Component percent is set to zero at this time d) The initial Discount Rate is derived by adding the net

Uncollectible Expense Component (a) the Program Development and Operation Cost Component (b) and the Risk Component (c)

2) The Reconciliation Component is calculated on the Imbalance separately for residential and non-residential customers Imbalances are recorded in a balancing segment regulatory asset or regulatory liability and represent the differences between cumulative costs eligible for recovery and discount amounts for purchased receivables During its disposition an Imbalance earns interest at the same rate as is paid on customer deposits pursuant to Sections 20300104 and 20300204 of the Code of Maryland Regulations as determined annually by the Public Service Commission Such rate is adjusted for taxes when the Imbalance represents an under-collection of costs to the Company

Approved by Letter Order dated August 1 2017 Effective September 1 2017

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES
Page 48: Ill delmarva power® · 2.1 Scope and Purpose ... 9.5.1.5 Allocate Unaccounted for Energy (Residual)..... 18 9.5.2 Submit Estimated ... 20.0: LIMITATION OF LIABILITY ..... 28 20.1

The Reconciliation Component rate is calculated by dividing the Imbalance including interest earned or owed separately for residential and non-residential customers by the estimated electricity revenues billed for all Electricity Suppliers for those rate schedules

3) If there are unrecovered costs associated with the purchase of eligible Electricity Supplier receivables and an insufficient number of Electricity Suppliers are using Company consolidated billing to support the recovery of those costs the Company is permitted to impose a charge on Electricity Suppliers to recover such costs

4) The Discount Rate (after the first year of service) is derived by updating the initial rate calculated above and adding the Reconciliation component

5) The Discount Rate is as follows

Rate Schedule Discount Rate Residential ndash Schedules R amp R-TOU-ND 17078 Type I ndash Schedule SGS-S GS-SH GS-WH TN ORL amp OR 00000 Type II ndash Schedules SGS-S LGS-S amp GS-P 00000 Hourly Priced Customers ndash Schedules LGS-S GS-P amp GS-T 00000

Approved by Letter Order dated August 1 2017 Effective September 1 2017

  • MD Electric Supplier Tariff - PSC MD No 10
  • DELMARVA POWER amp LIGHT COMPANY
  • MARYLAND
  • ELECTRICITY SUPPLIER COORDINATION TARIFF
    • TABLE OF CONTENTS
      • Demand ndash the rate of use of energy during a specified time interval expressed in kilowatts
      • Kilowatt or kW - unit of measurement of useful power equivalent to 1000 watts
        • 291 Electronic Data Interchange (EDI) To the extent the Commission has established EDI or other standards for communications and data exchange the Company and the Electricity Supplier shall employ those standards or mutually agreeable alternate
          • 214 Interruptible Service Interruptible services provided by Suppliers to Customers with loads in excess of 1 MW must be reported to the Electric Delivery Service provider within 17 calendar-days of the Customerrsquos signing up for the service from
          • 215 Customer Curtailment by Supplier The Supplier will notify the Company at least twenty minutes in advance of requesting a Customer to curtail load that is in excess of 1 MW
          • SCHEDULE 1 ndash PROCESSING FEES AND CHARGES