IM and IM-DF connection test status
Test Setup @ Waseda
DATA from QUEST
Readout by I2C
JTAG for DF
JTAG for IM
Status : Test @ FNAL (IM and DF with DF mini backplane)• IM worked on DF. Low speed data transfer test was succeeded.• Required data transfer speed (DDR200 MHz) was not stable due to the IM power generator
problem. Test @ Waseda (IM and DF with DF mini backplane)• After replacement of power generator, required speed (DDR 200 MHz) was accomplished
with channel delay. • Now we are testing the data flow around IM (i.e. QUEST->IM->DF test) with pseudo data.
Plan :Test @ waseda• Finish IM data flow test in Nov.• New IMx10 (power gen replaced and
minor change) available at Dec.• Final IM data flow test with new IM
and new FW in Dec.Test @ CERN ( IM and DF with ATCA)• IM data flow will be tested with DF
on ATCA , with pseudo data(Lab4) and read ROD data (P1) in Jan and Feb.
Some Picture Full IM mounted DF
IMx4 DF in ATCA (not tested)