Date post: | 07-Apr-2018 |
Category: |
Documents |
Upload: | nguyen-tuan-anh |
View: | 224 times |
Download: | 0 times |
of 25
8/3/2019 IMCA-RiskGuideline_2
1/25
----------------------- Page 1-----------------------
AB
Identifying and Assessing Riskin Construction Contracts
An IMCA Discussion Document
International MarineContractors Association
www.imca-int.com July 2006
----------------------- Page 2-----------------------
AB
The International Marine Contractors Association(IMCA) is the international trade associationrepresenting offshore, marine and underwaterengineering companies.
IMCA promotes improvements in quality, health, safety,environmental and technical standards through the publicationof information notes, codes of practice and by otherappropriate means.
There are two core activities that relate to all members: Competence & Training Safety, Environment & Legislation
The Association is organised through four distinct divisions,each covering a specific area of members interests: Diving,Marine, Offshore Survey, Remote Systems & ROV.
There are also five regional sections which facilitate work onissues affecting members in their local geographic area Asia-Pacific, Central & North America, Europe & Africa, MiddleEast & India and South America.
IMCA Risk Discussion Document
This document was prepared for IMCA by its ContractsWorkgroup, under the direction of the Overall ManagementCommittee and IMCA Council.
www.imca-int.com/contracts
The information contained herein is given for guidance only and endeavours to
reflect best industry practice. For the avoidance of doubt no legal liability shallattach to any guidance and/or recommendation and/or statement herein contained
.
----------------------- Page 3-----------------------
8/3/2019 IMCA-RiskGuideline_2
2/25
Identifying and Assessing Risk in Construction ContractsAn IMCA Discussion Docume
nt
July 2006
1 Introduction ........................................................................................................... 1
2 This Document ...................................................................................................... 3
2.1 Risk ....................................................................................................................................................................... 3
2.2 Contracting .............................................................................................................................
............................ 3
2.3 Profitability .......................................................................................................................................................... 4
2.4 Risk Management ............................................................................................................................................... 4
2.5 Where Does Control of Risk Lie? ................................................................................................................. 4
2.6 Risk Identification............................................................................................................................................... 5
2.7 Target Audience for this Document.............................................................................................................. 6
2.8 Main Risk Areas .................................................................................................................................................. 6
3 Contractual Risks ................................................................................................... 8
Appendices
1 Risk Areas ............................................................................................................. 11
Performance Risks ........................................................................................................................................................ 12
Financial Risks ................................................................................................................................................................ 14
8/3/2019 IMCA-RiskGuideline_2
3/25
Political Risks ................................................................................................................................................................. 15
Technical Risks .....................................................................................................................................
......................... 16
Geographical Risks ....................................................................................................................................................... 17
Operator Risks.............................................................................................................................................................. 18
2 IMCA Competition Law Guidelines .................................................................. 19
----------------------- Page 4-----------------------
----------------------- Page 5-----------------------
1 Introduction
The handling of risk in construction contracts varies considerably.This depends on the nature and location of
the work, the operator and contractor involved and the prevailing contracting climate. Each of these variesover time and there are also outside influences such as banks, governments and t
he insurance market.
In recent years, operators and contractors have remarked thatthe balance and handling of risks in somecontracts was not ideal and this document aims to promote dialogue between all parties to try to improve thissituation.
IMCA is an international trade association representing offshore, marine and underwater engineeringcompanies. IMCA members are upstream contractors ingeneral, but several of them are integratedcontractors completing downstream projects as well, so the intent of this document is to cover oil and gascontracting in general.
IMCA is widely recognised for collecting good practice from several parties andpublishing generic guidelines ofrelevance throughout the industry and around the world on many
issues relating to performance in theindustry on, for example, safety, the environment and other aspects.
Amongst IMCAs objectives are to:
strive for the highest possible standards with a balance of risk and cost;
achieve equitable contracting regimes; and
8/3/2019 IMCA-RiskGuideline_2
4/25
promote co-operation across the industry.
In publishing this document, IMCA believes it will serve the long-term interestsof all participants in the oil andgas industry and promote dialogue between the parties about risk in pursuit of the above objectives. This, inturn, will improve relations, increase efficiency and reduce overall costs.
The document is not intended to represent an exhaustive analysis of all risks which are covered by contracts inthe oil and gas industry. It is a short discussion document intended to highlight issues. The subject is huge andthere exists already a vast knowledge base about risk and risk management in the public arena, published byacademics and the industry with input from operators and contractors. In addition, each operator andcontractor probably has its own department responsible for this subject and its own strategy, perhaps in aformalised document and approach. This document is not in
tended to replace this regime; rather, it isintended to supplement it.
Each contract, project and client/contractor relationship isunique. This document does not present apreconceived single solution or recommendation for or against contract styles such as EPIC (engineering,procurement, installation and construction) or lump sum. It aimsat commenting on some of the issues thatmay need to be addressed in various contracting situations.
This document is about:
identifying risk;
identifying the financial consequences of the risk becoming a reality;
helping the contracting parties to achieve their appropriate risk balance;
trying to avoid parties accepting risks they dont understand; and
dealing with unknown risks.
The document can be used by operators and contractors to identify areas where risk may threaten theintegrity of a contract. Parties to a contract often do not realize that theperson who manages the risk under acontract may not necessarily be the person who carries the financial consequences of the risk becoming areality. The risks should be allocated to the party best to assume the risk.
This document does not contain contractual clauses and does not form a standardcontract. It is published asan aide for operators and contractors alongside their in-house risk approaches.
A trade association cannotmake compliance with its publications mandatory and remain within the bounds ofcompetition law. IMCA
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
8/3/2019 IMCA-RiskGuideline_2
5/25
IMCA Risk Discussion Document1
----------------------- Page 6-----------------------
recognises the requirements of competition law and these are reflected in the IMCA Competition Law Policy
which is reproduced in Appendix 2.
The document has been developed by the IMCA Contracts Workgroup in conjunction with other IMCAmembers who also contributed to the development of the related
document IMCA Contracting Principles.IMCA documents often evolve and any reader is welcome to provide suggestions foradditions. This documentshould generally be considered to be work in progress. It is intendedas a document to help dialogue betweenthe parties to understand, mitigate and manage risk appropriately to the benefitof all the parties. Its aims are
to:
improve dialogue;
improve risk apportionment and understanding in contracts and projects;
improve efficiency and project delivery;
improve operator/contractor relations;
save money;
avoid litigation;
increase opportunities;
facilitate the development of alternative solutions; and
sustain the industry.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
2IMCA Risk Discussion Document
----------------------- Page 7-----------------------
2 This Document
2.1 Risk
Risk is sometimes poorly understood by the main contracting parties and also those outside.
The effect of this is a danger:
to operators, in that they embark upon or frame a development uninfo
rmed of some of the risksinvolved;
8/3/2019 IMCA-RiskGuideline_2
6/25
to contractors, that they adopt risk that they donot understand and lose money, perhaps
becoming bankrupt, thus reducing the global pool of contractorscapable of doing work;
to both parties, that if the risk is poorly understood and allocated, it is likely to be incorrectly
assessed, mitigated, insured and managed, resulting in poor project delivery;
to those further down the supply chain, that if the two main playerscannot deal with risks well
themselves, sub-contractors are likely to manage this poorly too;
to those outside (such as banks, national oil companies, etc.), thatthey will take poorly informed
decisions that make the risk environment worse;
to all parties, in that a lack of understanding of risk leads to inefficiency where each pays more andmakes less out of the venture.
2.2 Contracting
During the contracting process:
1 an operator wants to achieve a goal;
2 the operator does not want to take the risk of doing the work itself. This could be for a variety
of reasons: it does not have the skill, personnel, equipment, ti
me, desire, etc.;
3 contractors offer to do the work on the operators behalf. Why? The contractors are
established to have the skill, personnel, equipment, time, desire etc.;
4 however, the capability of the bidding contractors varies.They may all be able to complete the
work, but some can accept more of the risks than others.This depends on their skill, personnel,
equipment, time, desire etc., as well as their risk acceptance profile. These behaviours may be
amongst the distinguishing factors between bidders to help decide who is awarded the work, but
all parties need to understand the risks which they are accepting and know how the contract is
dealing with them. An operators best interests are not necessarily served by contractors
competing on criteria such as acceptance of excessive risk.
A large number of contracts are completed under the lump sum/turnkey regime. The reason for this
is that the operator wants to know at the outset what the budget andschedule is and then should be
required to have no management or other role during the project.It relies on a well-defined scope of
work and a competent contractor. The intent is tha
8/3/2019 IMCA-RiskGuideline_2
7/25
t the operators define what they want, thecontractor builds it and hands it over in working condition to the op
erator who inserts the key, turnsit on and then owns and operates a successful facility. T
his idyllic model is easily spoiled by variousfrequently seen events:
1 the scope is not well-defined at the outset;
2 the contractor under-performs;
3 during the project, the operator interferes with: the scope, or the management, etc.;
4 unforeseen events.
It is not possible to have a lump sum without theturnkey element the two are inseparable.
The contractor cannot estimate the costs and run his
own project whilst maintaining budget andschedule control if the operator interferes. The upstream anddownstream construction industry has
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
IMCA Risk Discussion Document3
----------------------- Page 8-----------------------
not always been as successful at leaving the contractor to deliver lu
mp sum turnkey facilities as, forexample, the ship building industry.
Contractors are not bankers or underwriters. The risks of funding projects, changes in foreign
exchange rates and insuring projects should be understood and taken by the most appropriate party.
The operator may be better placed.
One of the aims of this document is to avoid erosion of the profit margin through incorrect
understanding and apportionment of risk.
2.3 Profitability
Contractors generally aim to make a certain percentage profit margin.The industry has reported that
profit margins have been low or negative for several contractors on several projects in recent years.
Some contractors have accumulated several loss making projects such that their whole annual result
has been negative and this viability-threatening situation for several contractors has been one of the
drivers for this document. A number of operators have commented on this unsatisfactory state of
affairs as well.
Clearly, features in the commercial process such as competitive biddi
8/3/2019 IMCA-RiskGuideline_2
8/25
ng impact on profit margins, butthis model has served the industry well. During difficult co
mmercial times, contractors are presentedwith the difficulty of bidding too high and missing the award.
If this occurs, their expensive facilities(offices, workforce, fabrication yards and vessels) will be
idle. If there is a large incentive to keep
these facilities active (at almost any cost) then bids can be submitted too low with no (or negative)
profit margin in desperation to win work. The work is later completed at a loss and the situation can
only get worse for all parties. This situation is unsustainable.
Nearly all of the risks discussed in this document have the capacity of eroding profit margin and
moving the project from a profit making into a loss-making venture.
In the hypothetical case of a contractor with a project target profitmargin of 5%, it should be noted
that it takes only a small swing in the contract price of 5% to erode100% of its margin. Further,it should be noted that the contractor only has recourse to the proje
ct duration (a few years at most)to achieve its return. The producing life of the facility that t
he contract was put in place to deliverclearly has a longer time for the operator to break even plus the opp
ortunity to charge more highly ifnecessary/appropriate/possible for its products later in the facilitys
life. Of course, a 5% swing in thecontract price for the operator is simply 5%, not 100% of his profit.
2.4 Risk Management
Risk management is the process by which the likelihood of risk occurring or its impact on a project is
reduced. It has five steps:
1 Identify the potential sources of risk on the project.
2 Determine their individual impact and select those with a significant impact for full analysis.
3 Assess the overall impact of significant risk.
4 Determine how the likelihood or impact of risk can be reduced.
5 Develop and implement a plan for controlling the risks and achieving the reductions.
2.5 Where Does Control of Risk Lie?
One way of classifying the risk is by identifying where control of the risk lies. This may change during
the life of the project.
The publication of this document by IMCA is intended to assist and promote i
ndustry dialogue and efficiency and its adoption is not mandatory.
4
8/3/2019 IMCA-RiskGuideline_2
9/25
IMCA Risk Discussion Document
----------------------- Page 9-----------------------
There are five classifications of risk according to where control lies:
1 External: Unpredictable
These are risks beyond the control of the individual or operator and are totally
unpredictable. They arise from external influences such asthird parties, acts of god, etc.
2 External: Predictable but Uncertain
These risks are also beyond the control of individuals or companies. They are expected, but
to what extent? There is usually data to determine a n
orm or average, but the actual impactcan be above or below this norm. Bad weather is an example.
3 Internal: Technical
These are risks arising directly from the technology of the project work, of the design,
construction or operation of the facility.
4 Internal: Non-Technical
These are within the control of individuals or the operator
and usually arise from a failure ofa project team to achieve its expected performance.
They may result in schedule delays, costover-runs or an interruption to cash flow.
5 Legal: Civil and Criminal
Risks under civil law can arise from contractual arrangements, patent rights etc. Risks under
criminal law can arise under statute, e.g. the UK Health &Safety at Work Act.
2.6 Risk Identification
2.6.1 Timing of Risk Identification
Risks need to be identified early enough to do something about them. Project risks should be
considered from the earliest conceptual stage. For example, risks from environmental
loading are key drivers in choice of conceptual design and so are considered on day one.
This document indicates that risks should beconsidered throughout the process from
conceptual screening through more detailed front end engine
ering and design (FEED), the bidprocess, award and project execution. A risk
inventory can run through from phase to
8/3/2019 IMCA-RiskGuideline_2
10/25
phase, so nothing is lost between phases when the contracting parties may change. It can
continue right through into the production phase where it may have an influence on
maintenance, for example.
The key message is that the earlier the risk is identified
the better.
2.6.2 Who Retains the Risk?
After the risks are identified, it is critical to see whichparties retain this risk in practice and
through the contract clauses. Limiting values and circumstances may need to be defined.
2.6.3 Risk Importance
A conventional risk analysis can be used to rank the import
ance of the risks in descendingorder from: High risk + high value, through high risk +low value or low risk + high value, to
low risk + low value.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
IMCA Risk Discussion Document5
----------------------- Page 10-----------------------
2.7 Target Audience for this Document
The target audience for this document is:
Operators: Operator during conceptual development, bidding, construction Operator during production Partners
Contractors: Prime contractors Sub-contractors Vendors
Others: Finance community Host governments/national oil companies Insurance market/brokers.
The key targets are the operators and prime contractors during conceptual development, bidding and
construction. The other stakeholders in the list can influence therisks and their allocation and need
to be aware of the issues.
2.8 Main Risk Areas
The main areas of risk in these contracts are:
8/3/2019 IMCA-RiskGuideline_2
11/25
Contractual
Performance
Financial
Political
Technical
Geographical
Operator
Contractual risks may include:
Operator group and contractor group property and personnel
Project works (including both operator and contractor supplied items)
Pollution
Third parties
Consequential losses
Warranty obligations
Unlimited liability/damages at large
Insurance cover
Force majeure and suspension
Delay
Variation orders
Free access to worksite
Intellectual property rights
Termination by operator for convenience
Operators obligation to pay contractor.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
6IMCA Risk Discussion Document
----------------------- Page 11-----------------------
Performance risks may include:
Scope, nature and duration of work
8/3/2019 IMCA-RiskGuideline_2
12/25
Schedule interactions
Size
Safety and environmental performance
Weather
Soil and foundations
External influences
Operator and influences at time of bid.
Financial risks may include:
Profitability
Value of contract (size)
Balance sheet debt
Off-balance sheet debt
Level of exposure
Foreign currency exposure
Terms of payment
Operator creditworthiness
Insurance.
Political risks may include:
Interference
Disturbance
Confidentiality
Permits and licences.
Technical risks may include:
FEED quality
New technology
Weather
Soil and foundations.
Geographical risks may include:
Location of the work
Operator risks may include:
8/3/2019 IMCA-RiskGuideline_2
13/25
Operator areas of influence
Insurance
Problems which impact the operator and can impact the contractor.
There will always be overlaps between these areas. The
contractual risks are a function of thewording of the contract whereas the other risks evolve from elsewhere
but the contract will be usedwhere necessary to deal with them. For this reason th
e contractual risks are explored in slightlygreater detail in section 3 below, whereas the other topics are explor
ed in Appendix 1.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
IMCA Risk Discussion Document
7
----------------------- Page 12-----------------------
3 Contractual Risks
C.1 Operator group and contractor group property and personnel
The contract should define the costs of loss of or damage to the parties respective groups property
and personnel of whatsoever nature, irrespective of cause (includingnegligence).
C.2 Project works (including both operator- and contractor-supplied items)
The contract should define the responsibility for loss of or damage to the project works if such loss or
damage is caused by an act or omission on the part of the contractorgroup whilst the project works
are in the care, custody and control of the contractor group.
C.3 Pollution
The contract should define the responsibility for theeffects of pollution and contamination of
whatever kind emanating from the contractor groupsspread and onshore facilities, operators
facilities, the work and the facilities of others (third parties).
C.4 Third parties
The contract should define the legal liability for third parties losses caused by each, including in
circumstances where a contractor is required to perform work in an area of close proximity to any
existing facilities.
C.5 Consequential losses
The contract should define the indemnities for eac
8/3/2019 IMCA-RiskGuideline_2
14/25
h partys groups respective indirect orconsequential losses howsoever caused or arising (including negligenc
e) whether or not foreseeableat the date of the contract.
C.6 Warranty obligations
Warranty obligations and defective performance liabilities (includingpost termination for default) and
all other implied liabilities should be expressed inthe contract in terms of magnitude, time and
remedy.
C.7 Unlimited liability/damages at large
The contract should define or limit the contractor groups total cumulative liability under the contract
and at law, in order to enable him to assess his overall exposure resulting from, for example, liability
for delay, damage, rework, re-performance and/or replacement and default (whether or not suchactions are carried out by a third party).
C.8 Insurance cover
The full details of the insurance policy terms, conditions, limits and exclusions (and any alterations)
should be available to all parties and define the cover available ornot for the project.
C.9 Force majeure and suspension
In the event that the contractor is prevented from performing the work due to force majeure or
suspension by the operator, the contract should definewhether the contractor has the right to
remove any vessel from site once a maximum period agreed in the contract has been exceeded.
C.10 Delay
The contractors liability for delay and liquidated damages should be defined and should be the
operators sole financial remedy under both the contract and at law.
C.11 Variation orders
The contract should define the contractors obligations to perform theoperator instructed variation
orders taking account of contractors other existing commitments, any change to the risk profile of
the workplace and a mutually agreed adjustment to price and schedulewhere appropriate.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
8IMCA Risk Discussion Document
8/3/2019 IMCA-RiskGuideline_2
15/25
----------------------- Page 13-----------------------
C.12 Access to worksite
The contract should define the access to the work site and remedies in the event of delay or
additional costs incurred as a result of restricted access to the wor
k site by the operator or any party(other than a member of the contractor group), including intervention
by an action group whether ornot such intervention is defined as force majeure.
C.13 Intellectual property rights
Intellectual property rights (IP) in terms of the party who developedthose IP before or during the
project should be clearly identified.
C.14 Termination by operator for convenience
Should the operator terminate the whole or part of the work for its convenience then the contract
should define the entitlement to payment for all workperformed, materials including cancellation
costs relating thereto and all vessel and equipment costs and termination fee.
C.15 Operators obligation to pay contractor
Payment by the operator to the contractor is a material term of the contract and time critical.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
IMCA Risk Discussion Document9
----------------------- Page 14-----------------------
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
10IMCA Risk Discussion Document
----------------------- Page 15-----------------------
Appendix 1
Risk Areas
The main areas of risk in these contracts are:
Contractual (C) (this is discussed in section 3 above)
The following areas of risk are discussed in this appendix below:
Performance (PE)
8/3/2019 IMCA-RiskGuideline_2
16/25
Financial (F)
Political (PO)
Technical (T)
Geographical (G)
Operator (O)
The risks are grouped, numbered and annotated as shown in the brackets above forease of cross reference.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
IMCA Risk Discussion Document11
----------------------- Page 16-----------------------
Performance Risks
PE.1 Scope, nature and duration of the work
The scope and nature of work should be defined inthe contract. The contractor should have
sufficient time and information to assimilate the detail in the bid phase. Particular difficulty occurs with
contracts where:
there is insufficient time or information available to understand thedetail;
the information is insufficiently developed at bid stage (poor FEED see T.1);
the project depends on the contractor developing a new solution during the project for which he
cannot quantify the resources (groundbreaking projects see T.2);
the information available is wrong;
the bid scope is outside the knowledge of the operator and/or bidder (eg very large turnkey
projects).
The operator also has to perform in order for the contractor to perform. This issue is discussed
further under O.3.
If there is a danger of any of these risks occurring, the contract should define how the parties will deal
with the situation.
PE.2 Schedule interactions
The parties should understand the schedule and what happens if the sch
8/3/2019 IMCA-RiskGuideline_2
17/25
edule changes. The effect ofschedule changes which are operator initiated (change of
scope, delivery of information/materials/components/approvals/permits etc, variation orders) and contractor ini
tiated (delay) should be definedin the contract. This includes interaction with long lead time items.
PE.3 Size
The probability of a problem described in items PE.1 and 2 in this performance risk register occurring
is increased on large projects.
PE.4 Safety and environmental performance
The contractor is expected to complete the workwith certain operator/own/industry safety
performance targets. If these targets are not achieved there wil
l probably be other knock-on effectson the project performance. Any targets, other than the contractors own ones, should be defined in
the contract such that there are no surprises.
PE.5 Weather
Weather risk needs to be assessed on a case-by-case basis.For example, some vessels are able to
accept a different level of weather risk than others.This may be a competitive edge issue if
contractors have, for example, larger equipment which can operate in worse weather conditions. But
for each contractor there will be a limit, beyond which the responsibility for weather risk should be
identified.
PE.6 Soil and foundations
The soil and foundations (site conditions) risk is generally borne bythe operator. This follows the
principle that the risk cannot be fully measured bythe contractor prior to the commencement of
work and so unknown costs could be out of proportion to the contractorsreward.
PE.7 External influences
Many of the risks discussed in this document may be outside the control of the contractor. Such risks
may prevent the contractor performing and include:
Access (see C.12);
Interfaces with operator and interfaces with other contractors;
Political risks (see PO.1-4);
Risks of interference and disturbance (see PO.1 and PO.2).
The publication of this document by IMCA is intended to assist and promote i
8/3/2019 IMCA-RiskGuideline_2
18/25
ndustry dialogue and efficiency and its adoption is not mandatory.
12IMCA Risk Discussion Document
----------------------- Page 17-----------------------
PE.8 Operator and influences at time of bid
If there is incomplete information at the time of bid, it will impactnegatively on the performance of
the contractor. If the contract is re-bid or negotiated over anextended period before award, both
the operator and contractor may have a lack of continuity in the bidprocess and amongst personnel.
Both can impact negatively on contractor performance.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
IMCA Risk Discussion Document13
----------------------- Page 18-----------------------
Financial Risks
F.1 Profitability
Contractors generally aim to make a certain percentageprofit margin. This is the most critical
outcome of the contracting process for the contractor.
At the end of the contract the contractoronly has the financial result. By comparison, the operator acquire
s an asset with a lifetime expectationof positive returns and with some element of control over these retur
ns.
F.2 Value of contract (size)
See PE.3.
F.3 Balance sheet debt
The terms of payment and any deposits, performancebonds, bank guarantees, and parent co
guarantees etc should be understood.
F.4 Off-balance sheet debt
The terms of payment and any deposits, performancebonds, bank guarantees, and parent co
guarantees etc should be understood.
F.5 Level of exposure
See F.2. This is related to size but also to payment method, cash fl
ow, etc
F.6 Foreign currency exposure
8/3/2019 IMCA-RiskGuideline_2
19/25
Many contracts are in countries which are not the home country of the contractor. In addition,
components, supplies and sub-contractors can also come from further countries. These facts can
combine to mean that the contractor could have acurrency exchange risk for the project.
The operator is often better placed to cope with this risk. This is because:
the materials etc which are paid for with foreign currencies may have been designated by the
operator;
the operator is probably operating in the local country of the work (which the contractor may
not be) and so will be set up to deal with its currency;
the operator (generally being a larger capitalised comp
any) can get better currency terms andperhaps has access to the host government to negotiate terms.
Swings of a few percent are regular and should be considered in the light of F.1 above.
F.7 Terms of payment
The payment terms should reflect the progress of the work and be cashneutral. It is noted that host
governments in some overseas projects are obstacles in this area and it is clearly an operator matter
to address this with the relevant government. See F.3 and F.4 above.
F.8 Operator creditworthiness
Some operators are now smaller companies than the main contractors.Understanding whether the
operator has the financial backing to continue to pay the contractoris important. For some overseas
projects the parent operator may have sufficient creditworthiness butthe project may be operated via
a separate subsidiary with smaller credit.
F.9 Insurance
See C.8. The financial integrity/security of the underwriters is critical.
F.10 Materials
The implications of material cost fluctuation, e.g. fuel or steel prices, should be understood by both
parties.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
14IMCA Risk Discussion Document
8/3/2019 IMCA-RiskGuideline_2
20/25
----------------------- Page 19-----------------------
Political Risks
PO.1 Interference
PO.1.1 Before award Some host governments in
terfere with the normal business process(operator/contractor relationship) by insisting on c
ertain contract styles. These include EPICcontracts, lump sum bids, specific contract and
payment terms, local content and locallegislation/standards. This can add considerable uncertainty and
risk to bids. Host governments canfrustrate the award process as well, making the
cost of bidding higher (due to protractednegotiations), the risk of interference with other projects for the c
ontractor higher, the prospect offrustrated bidding (a bid submitted which costs money to prepare and
where eventually no award ismade), and stimulating general negative effects on contractor cash flow. The contractor has little
opportunity to influence these aspects which should be clarified in the bid stage and the operator is
generally better placed to influence these aspects positively.
PO.1.2 During contract The same broad points as in PO.1.1 apply.In addition, the host government
may delay payment, change laws and taxes, change local standards, andinterfere with local content or,
be a cause of delay where local content is late or of unacceptable quality. The contractor has little
opportunity to influence these aspects which should beclarified in the bid and the operator is
generally better placed to influence this positively.
PO.2 Disturbance
The contractor needs a secure environment to completehis work on site. Local disturbance can
negatively influence schedule. The operator has the best opportunity to influence local stability and
provide security to the contractors workforce and spread. Similarly, the operator has the best
opportunity to influence the completion of local work and ensure no interruption to the supply of
materials, personnel and third party provided items tothe contractor. The parties should work
together with other operators in the region, host governments and security personnel to aim at
secure working. Again, the contractor has little opportunity to influence these aspects which should
be clarified in the bid and the operator is generally better placed to influence this positively.
PO.3 Confidentiality
There is a risk that confidentiality may be breached which is a political risk. The contractor has little
opportunity to influence this so it should be clarified in the bid an
8/3/2019 IMCA-RiskGuideline_2
21/25
d the operator is generally betterplaced to influence this positively.
PO.4 Permits and licences
Permits and licences may not be issued in time bythe authorities, or may be required by the
authorities at a time when they cannot be procured by the contractor.The operator is usually closer
to the authorities and may be better placed to influence the issue ofpermits and licences.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
IMCA Risk Discussion Document15
----------------------- Page 20-----------------------
Technical Risks
T.1 FEED quality
The contractor may be asked to bid on the basis that he has studied the FEED (front end engineering
design) and accepted it. There may be insufficient time to complete this study in full depth in the bid
period. FEED may have errors and in a complex bidthese may be impossible to find. It is also
inequitable to ask the bidders (effectively) to be theauditors of the FEED which is, in part, what
occurs in a bid where the contractor is asked to accept the FEED.The risk of FEED being inaccurate
needs to be understood and the possible effects of this clarified.This process often needs only to bedone once with the successful bidder, not with all bidders.
T.2 New technology
In ground-breaking projects the bidder may be asked to carry out designs and activities during the
project that have not been completed before. The biddermay be unable to envisage that a piece of
technology will be unsuccessful. Both parties should understand this situation and work towards
understanding the risks, their implications and the costs of solutions. Then the risks should be
apportioned.
T.3 Weather
See PE.5.
T.4 Soil and foundations
See PE.6.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
8/3/2019 IMCA-RiskGuideline_2
22/25
16IMCA Risk Discussion Document
----------------------- Page 21-----------------------
Geographical Risks
G.1 Location of the work
The geographical location will determine the magnitude of weather, political and operator risks. Most
of these issues are discussed under Political Risks above and include: politics; stability and changes to law/tax; local legislation/standards; governing law; security of vessels and personnel; material supply interruption;
hindrance to mobilisation of spread; interruption to supplies for spread; hindrance to movement of personnel (crew change); late delivery of the work from or by third parties; project logistics; quality of operator supplied materials; permits and licences.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
IMCA Risk Discussion Document17
----------------------- Page 22-----------------------
Operator Risks
O.1 Operator areas of influence
The paragraphs above discuss operator risks and the operators influenceon:
the bid; award schedule; intellectual property; credit worthiness; interference; supervision; approval regime and timing; timely provision of information; local content; logistics; contracting regime; FEED quality; scope of work clarity; cash flow for project work and variation orders; permits and licences.
O.2 Insurance
If the operator decides to self insure all or part of the project the
8/3/2019 IMCA-RiskGuideline_2
23/25
re is sometimes no policy wording.Without it, there is a risk that a claim will lead to dispute rather t
han payment. In the case of a claim,the contractor has recourse only to the operator (who
may be claim averse) rather than to aninsurer, who recognises that paying claims is an integral part of his
business. This can lead to souring
of the contract relationship. If recourse is to the project manager, whose job is to keep the project
within budget (and whose bonus may depend on it) the claim handling may be particularly complicated
and the project manager may not be well versed in claims handling which is a discipline that insurers
particularly retain. An insurance wording should exist and be available for all parties. See also C.8.
O.3 Problems which impact the operator and can impact the contractor
Some project problems impact the operator. If these
occur, an operator problem should not bepassed on to the contractor. However, such problems often impact the contractors performance,
despite being outside his control. Examples are late deliveryof third party materials or information,
poor quality third party materials, poor quality information, late approval, late delivery or deficiencies
in permits and licences, late payment and poor interfaces. Each of these eventualities should be
understood by the parties.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
18IMCA Risk Discussion Document
----------------------- Page 23-----------------------
Appendix 2
IMCA Competition Law Guidelines
Introduction
These guidelines are compiled for members in accordance with the Associations constitution. They will becirculated to all members.
Policy
The Association, its regional sections and all committeeswill comply with all applicable
competition law (competition, antitrust and similar laws) including those of theUnited States ofAmerica, the European Union, the United Kingdom and other countries in which theAssociation
is active.
All meetings will start with this as agenda item 1.
8/3/2019 IMCA-RiskGuideline_2
24/25
General
1. The Constitution and section objectives are written to comply with competition law.2. Membership is open to all companies active in the offshore, marine or underwater engineering industries.
Any action in rejecting a membership application or currentmember is reviewed for compliance withcompetition law.
3. The Association has a formal document retention and disposal policy.4. The Association has a formal complaints procedure
Rules for Meetings
Members should comply with the following guidelines when meeting:
1. Agendas of all meetings should be reviewed for compliance with competitionlaw.
2. Items not on the agenda will not be allowed if they raise issues which violate competition law.3. All participants have the right to question any topic or discussion that might violate competition law. Any
participant has the right to state their objection and leave a meeting if they feel that any topic or discussion
violates competition law.4. Minutes of all meetings should be accurate and should not be doctored or incomplete.5. Minutes of all meetings should be reviewed for compliance with competition law. Minutes should also
include statements to show compliance with competition law.6. All meetings should be scheduled and no unscheduled, informal, ad-hoc or si
de sessions should be held.
The following guidelines should be adhered to by all members during any meetings:
1. Do not discuss current or future prices.2. Do not discuss what is a fair profit level.3. Do not discuss an increase or decrease in price.4. Do not discuss standardising or stabilising prices.5. Do not discuss pricing procedures.6. Do not discuss cash discounts.7. Do not discuss credit terms.8. Do not discuss controlling sales.9. Do not discuss allocating markets.10. Do not complain to a competitor that its prices constitute unfair trade practices.11. Do not discuss refusing to deal with a company because of its pricing or distribution policies.12. Do not attend unscheduled, informal, ad-hoc or side sessions.
Conclusion
Trade associations can be targets for government agencies patrolling and enforcing compliance withcompetition law. By conducting its business openly and avoiding e
ven the appearance that it is engaging inactivity that might seem to have an effect on prices or competition, the Association and members can protect
8/3/2019 IMCA-RiskGuideline_2
25/25
themselves from charges of violations of competition law.
The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.
IMCA Risk Discussion Document19