We respect, care and deliver
Introducing 14 Shaft Impala
• 14 Shaft is one of the “Big 5” shafts
• 2 x Sections:• Upper Section
Conventional• Decline Section B&P and
conventional
• Daily tons planned at 7 275 per shift (BP16)
• Conventional UG2 : 31% • Conventional Mer : 34% • Bord & Pillar (Hybrid ):35%
• 36 Half levels mining
We respect, care and deliver
14 Shaft Impala Infrastructure
15 LEVEL
16 LEVEL
17 LEVEL
18 LEVEL
19 LEVEL
20 LEVEL
21 LEVEL
22 LEVEL
23 LEVEL
24 LEVEL
25 LEVEL
26 LEVEL
27 LEVEL
28 LEVEL
We respect, care and deliver
Mining Methods
• Conventional narrow reef mining:
• 65% of the Weighline tons are mined conventional, both Merensky and UG2.
• Two shifts, day and night.
• Scraper cleaning on night shift.
• Support, drilling and charging up on dayshift.
• Predominantly conventional double sided breast mining.
• Footwall drives, 18m - 24m below reef.
• Rse/Wze connections, 180m and 250m apart.
• Panel Face length varies between 15m – 30m.
• Panels are separated by 6 x 3m grid pillars with 2m ventilation holings.
• Stoping widths, 1.1m - 1.3m .
• Stoping team size: 13 people at work.
We respect, care and deliver
Mining Methods ( Continue )
• Bord and Pillar Hybrid mining:
• 7 x 7 meter, bord and pillar.
• It contributes 35% of the weighline tons, only Merensky tons.
• Two shifts, day and nightshift.
• LHD cleaning on nightshift and tipping on follow-on strike belts.
• Making safe, handheld pneumatic drilling of faces, roof support with bolters and charging up, on dayshift.
• 1 x blast per bord in a 24 hour cycle. (2 x 8 hour shifts and re-entry period)
• Each dayshift team consist of 5 team members, excluding the Miner and nightshift.
• Average stoping width 1.9m
We respect, care and deliver
Surface
14 Shaft 14A Shaft 14B Shaft
IMPALA PLATINUM - NO.14 SHAFTGeneral Ventilation Layout - Existing System
21 Level
27 Level
28 Level
560 kg/s[23.2 m/s ]
515 kg/s[ 10.5 m/s ]
370 kg/s[ 12.4 m/s]
26 Level
25 Level
24 Level
22 Level
23 Level
355 kg/s[ 17.8 m/s ]
Level Distance Below Collar
Surface 0.0 m
15 Level -620.3 m
16 Level -675.3 m
17 Level -730.3 m
18 Level -785.3 m
19 Level -840.3 m
20 Level -895.3 m
21 Level -950.3 m
22 Level -1005.3 m
23 Level -1060.3 m
24 Level -1103.3 m
25 Level -1164.3 m
26 Level -1199.3 m
27 Level -1235.3 m
28 Level -1290.3 m
19 Level
17 Level
15 Level
16 Level
18 Level
14 Vent Shaft
We respect, care and deliver
Merensky Fire Detection Heads
CO
COCO
COCO
COCOCO
COCO CO
COCO
COCO
14V Shaft
2 x 1050KW Fans343m3/s
14 Shaft
14MW Plant458m3/s
14A Shaft
2 x 2.2MW Fans512m3/s
14B Shaft
12MW Plant387m3/s
Merensky Reef Horison CO and Smoke Detectors
We respect, care and deliver
q
Conveyor Fire Detection Heads
T1
T2
T3
T4
C1
C2
C3
C4
C4 tail
23 Decline RAW
23 TM3 RAWCOCO
COCO
CO
CO CO
CO
CO
COCO
CO
CO CO
CO
14A Shaft
2 x 2.2MW Fans512m3/s
14B Shaft
12MW Plant387m3/s
Conveyor Decline CO and Smoke Detectors
We respect, care and deliver
Description of Accident
• On Friday, 22 January 2016 at approximately 17H02 the CO detection head at themain dip conveyor tail end failed to safe (200 ppm) and lost communication.
• This activated the fire suppression systems on the belt and alarmed at the ShaftControl Room and Central Control Room.
• From here onwards a number of CO detection heads alarmed which activated the firesuppression systems on the belt installation and alarmed in the Shaft Control Roomand Central Control Room.
• At approximately 17H27, the 23 RAW CO detection head alarmed in Shaft ControlRoom, Central Control Room and also in the Banksman’s cabin.
• The centralised blasting commenced from the control room at approximately 18H05although all the fire detection heads had not cleared.
• The three hour re-entry period expired at 21:05 and despite the fact that three of thefire detection heads in the lower section was in alarm, the night shift was lowered tothe top section at 21:18.
We respect, care and deliver
Description of Accident
• 144 employees proceeded underground to the top section of the mine.
• After the instruction was issued to withdraw all employees from underground, 140employees were safely evacuated and 4 employees were overcome by noxious gases.
• The emergency control room was established at 22:55
• The fire is the subject of an enquiry in terms of the MHSA and cannot comment on thecause of the fire and any related matter.
We respect, care and deliver
q
Settlers
14A Ventilation Shaft
14 B Shaft
CO21 Level
CO SM CO SM
CO SM CO SM
CO SM CO SM
CO SM
CO SM CO SM
CO SM
CO SM
CO
Total Underground Power Failure occurred at 02:29
We respect, care and deliver
Conveyors schematic
Level
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Tipping on C4
Tipping on C3
14# Surface
COB
(46 m)COC
(46m)
C1 (194 m)
C2 (410 m)
C3 (950 m)
C4 (980 m)
T1 (110 m)
T2 (110 m)
T3 (110 m)
T4 (110 m)
Total Conveyor Lenght: 3 066 m
Belts on Dip: 2 626 mBelts on Strike: 440 m
We respect, care and deliver
Physical Damage
• On 22 January 2016 a fire started in the conveyor decline in the vicinity of T4 on C4 conveyor and burnt up and down the excavation.
• The conveyor excavation extend from 21 Level through to below 28 Level –3 076 m of excavation.
• The excavation was originally supported with grouted rebar tendons and expanda bolts as well as 50 mm fibre-crete lining – heat caused failure of expanda bolts and expansion cracks in lining
• The conveyor excavation houses the conveyor structure (1 350 mm steelcord belt), the diesel mono rail system (DMTS)and all services e.g. fibre optic, control and LT cables and piping (water, compressed air)
• The complete conveyor up to 150m from the tail-end of C4 belt was damaged (all belt destroyed and structure deformed)
• All services were damaged (burst pipes, electrical and instrumentation cables destroyed)
• Two monorail units damaged and rails distorted in some areas
We respect, care and deliver
Access Safety
• Risk assessment conducted on safe making process– Make safe from level into conveyor excavation– Barring only to be done from the top down– From scaffold - dress and waterjet loose rocks – Progress scaffold 2.5 metres– Bar and sound till solid from scaffold – waterjet clean– Replace failed and protruding bolts – Do coring of shotcrete lining for test– Perform pull test on bolts and replace where required– Do full cover shotcrete
• Risks identified– Falling objects/rocks– Falling from height– Dust– Live electricity– Heavy equipment handling(motors, gearboxes, pipes, conveyor belt, pulleys)
We respect, care and deliver
Labour Strategy
Before fire After fire
Total Employees 4156 2989
Total Vertical 1586 1980
Total Decline 2209 669
Teams 85 63
Tonnes 7275t 3210t
We respect, care and deliver
Scope of this Project
Rehabilitation and reconstruction of the No 14 shaft decline conveyor and services broadly comprising:
• Rehabilitation of the conveyor decline primary and secondary
support.
• Rehabilitation of cable, fibre and piping in the conveyor decline
• Installation and commissioning of the service DMTS.
• Stripping, removal and reconstruction of the burnt C0B, C0C, C1,
C2, C3 and C4 conveyor belts
We respect, care and deliver
Progress on Decline Rehabilitation
• 1824 metres made safe
• 1318 metres shotcreted
• 1040 metres cleaned
• 1062 metres structural steelwork completed
We respect, care and deliver
Current Progress
• T1 conveyor completed.
• Temporary “relay” pumping system installed and commissioned to
accommodate water from waterjets.
• Second Diesel Shunting trolley delivered and commissioned underground.
• Redesigns for C3 transfer box, C2/C1 transfer box, C0c and C0b pendula's.
• C3 conveyor currently 53% complete.
• Gearboxes and Motors for C3 refurbished and delivered.
• All C3 bearings replaced.
• Lagging - 7/15 pulleys for C3 completed.
We respect, care and deliver
Opportunities Identified
• More access points for safe making.
• Appears that only 60% of steelwork need replacement.
• Refurbishment of long lead items e.g. motors, gearboxes, VSD panels,
transformers will reduce lead times.
• Additional DMTS shunter will alleviate logistic delays and assist with
handling of heavy components – approved by insurance
• Pulley bearing replacement and lagging will be done in situ.
• Two steel work erectors will work concurrently on stripping/replacement.
We respect, care and deliver
Project – Milestones
Key MilestoneDue Date
Completion Application Approved Commission C3 Commission C0C Commission C0B Commission C4 Commission C2 Commission C1
March 2016 24th Oct 2016 13th Dec 2016 14th Dec 2016 13th Feb 2017 17th Feb 2017 10th Mar 2017
We respect, care and deliver
Interim Measures
• Commission C3 during October 2016.• Discharge through temporary orepass to level – capacity
approximately 1300tonnes/day• Tram to shaft orepasses• Will allow 24 level to start up
– B&P : 17 Stoping and 9 Development teams– Conventional : 5 Stoping teams