Implementation of Construction Project with Detailed Contract Documents Soe Minn Sett Myanmar Transitional Platform 1 March 2014 UMFCCI, Yangon
Transcript
Page 1: Implementation of construction project with detailed contract documents r1

Implementation ofConstruction Project with

Detailed Contract Documents

Soe Minn SettMyanmar Transitional Platform1 March 2014

UMFCCI, Yangon

Page 2: Implementation of construction project with detailed contract documents r1

Key Team Player in following airport projects:-Changi Airport (Singapore)Sembawang Airbase (Singapore)Seletar Airport (Singapore)New Phu Quoc International Project (Vietnam)Can Tho International Airport (Vietnam)Buon Ma Thout Airport (Vietnam)Benazir Bhutto International Airport (Islamabad, Pakistan)Naypyitaw Airport (Myanmar)Melbourne Airport (Australia)Hambantota International Airport (Sri Lanka)

Soe Minn SettB.E (Civil), M.Sc (Transportation Engineering)

Page 3: Implementation of construction project with detailed contract documents r1

3

1) LEGAL FRAME WORK

2) FORM OF CONTRACT

3) RESULT OF DETAILED CONTRACT

DOCUMENTS

CONTENT

Myanmar Transitional Platform

Page 4: Implementation of construction project with detailed contract documents r1

4

Ref: Imperial Gazetteer of India, v. 9, p. 213.

LEGAL FRAME WORK

BRITISH BURMA MUNICIPAL ACT, 1874

BURMA MUNICIPAL ACT, 1884

Ref: “A Collection of The Acts published by the Governor General of India in Council in the year 1885”

Myanmar Transitional Platform

Page 5: Implementation of construction project with detailed contract documents r1

5

LEGAL FRAME WORK

Rangoon City Municipal Act (1922)

Rangoon City Municipal Act (1956)

Myanmar Transitional Platform

Page 6: Implementation of construction project with detailed contract documents r1

6

Yangon City Development CommitteeLEGAL FRAME WORK

Myanmar Transitional Platform

Page 7: Implementation of construction project with detailed contract documents r1

7

CURRENT PRACTICE

City Development Committee

Myanmar Transitional Platform

Page 8: Implementation of construction project with detailed contract documents r1

8

CURRENT PRACTICE

Ministry of Construction

Myanmar Transitional Platform

Page 9: Implementation of construction project with detailed contract documents r1

9

Contract LawLEGAL FRAME WORK

- Myanmar Contract Act, 1872

(formerly known as “Indian Contract Act”)

- Sale of Goods Act, 1930Same as Australian, English, Hong Kong and Singapore law.

three major differences:

(i) Consideration may be given by a person who is not a person to the

contract;

(ii) Past consideration (that is, payment/performance prior to entering into the

contract) is valid consideration

(iii) Consideration is not presumed in the case of a contract under seal.

Myanmar Transitional Platform

Page 10: Implementation of construction project with detailed contract documents r1

10

LEGAL FRAME WORK

Typical Contract Agreement Document (Private Sector Project)

-Contract agreements were drafted on Stamp paper and signed by both parties.

-May witness by Lawyers

-Mentioned payment term

-General description of project deliverable (Eg. 8 stories R.C building, 20’ x 50’ Warehouse Steel Structure building etc)SPECIME

N

Myanmar Transitional Platform

Page 11: Implementation of construction project with detailed contract documents r1

11

LEGAL FRAME WORK

SPECIMEN

SPECIMEN

Typical Contract Agreement Document (Private Sector Project)

SPECIMEN

Myanmar Transitional Platform

Page 12: Implementation of construction project with detailed contract documents r1

12

LEGAL FRAME WORK

SPECIMEN

Typical Contract Agreement Document (Government Sector Project)

Myanmar Transitional Platform

Page 13: Implementation of construction project with detailed contract documents r1

13

LEGAL FRAME WORK

Myanmar Transitional Platform

Photo Courtesy : Swe Oo’s Facebook PUBLIC share

Page 14: Implementation of construction project with detailed contract documents r1

14

FORM OF CONTRACT

PRINCIPAL STAGES OF CONSTRUCTION PROCESS

14

Project Brief

Decision to Build

Evaluation &

AwardCompletion & Maintenance

Design Drawing

sTender Documentation-Conditions of Contract-Drawings-BQs-Specifications

Tender Invitation

Construction Works

Letter of Intent/Awar

d

Contract Documents

Myanmar Transitional Platform

Page 15: Implementation of construction project with detailed contract documents r1

15

FORM OF CONTRACT

Standard form of Contract Documents

1. Articles of Agreement

2. Conditions of Contract (regulate to practice)

3. Plans and Drawings

4. Bill of Quantities

5. Specification (recommend to practice)

Myanmar Transitional Platform

Page 16: Implementation of construction project with detailed contract documents r1

16

Common Standard Form of Condition of Contract Joint Contracts Tribunal (JCT)

International Federation of Consulting Engineers (FIDIC)

NEC Engineering and Construction Contract (NEC)

Singapore Institute of Architect (SIA)

Association of Consultant Architects (ACA)

Public Sector Standard Conditions of Contract for Construction Works (PSSCOC)

Master Format (Construction Specification Institute, CSI)

FORM OF CONTRACT

Myanmar Transitional Platform

Page 17: Implementation of construction project with detailed contract documents r1

17

Common Standard Form of Condition of Contract

FORM OF CONTRACT

Myanmar Transitional Platform

Page 18: Implementation of construction project with detailed contract documents r1

18

Common Standard Form of Condition of Contract

FORM OF CONTRACT

Page 19: Implementation of construction project with detailed contract documents r1

19

Common Standard Form of Condition of Contract

FORM OF CONTRACT

Myanmar Transitional Platform

Page 20: Implementation of construction project with detailed contract documents r1

20

Common Standard Form of Condition of Contract

FORM OF CONTRACT

Myanmar Transitional Platform

Page 21: Implementation of construction project with detailed contract documents r1

21

Common Standard Form of Condition of Contract

FORM OF CONTRACT

Myanmar Transitional Platform

Page 22: Implementation of construction project with detailed contract documents r1

22

PSSCOCPublic Sector Standard Conditions of Contract for Construction Works

1. Definitions and Interpretation

2 . Superintending Officer and

Superintending Officer's Representative

3. Contract Documents

4. General Obligations of the Contractor

5. Sub-Surface and Ground Conditions

6. Permanent Works Designed by the

Contractor

7. Notices and Fees

8. Setting Out

9. Programme for the Works

10. Quality in Construction

11. Administration

12. Possession of Site And

Commencement Of Works

13. Suspension

14. Time for Completion

15. Expediting Progress of Works

16. Liquidated Damages

17. Substantial Completion

18. Defects

19. Variations to the Works

20. Valuation of Variations

21. Measurement

22. Claims for Loss and Expense

23. Procedure for Claims

24. Construction Equipment

Temporary Works Materials and

Goods

25. General Responsibilities

26. Indemnity Provisions

27. Insurance for Personal Injury, Work

Injury Compensation and Property

Damage

28. Insurance of the Works

29. Damage to Property of Employer or

Government

30. Assignment and Subcontracting

31. Termination by The Employer

32. Progress Payments and Final Account

33. Fluctuations

34. Final Completion Certificate

35. Settlement of Disputes

36. Recovery by the Employer

37. Governing Law & Notices

FORM OF CONTRACT

Myanmar Transitional Platform

Page 23: Implementation of construction project with detailed contract documents r1

23

Technical SpecificationSpecifications

FORM OF CONTRACT

Myanmar Transitional Platform

Page 24: Implementation of construction project with detailed contract documents r1

24

Technical SpecificationSpecifications

FORM OF CONTRACT

Myanmar Transitional Platform

Page 25: Implementation of construction project with detailed contract documents r1

25

SpecificationsSpecification Format

- National Building Specification Format (UK Based System)

- Master Format (Construction Specification Institute, CSI)

(US Based System)

- PWD/CPG General Specification

FORM OF CONTRACT

Myanmar Transitional Platform

Page 26: Implementation of construction project with detailed contract documents r1

26

SpecificationsParticular Requirement

FORM OF CONTRACT

NBS Master Format

Myanmar Transitional Platform

Page 27: Implementation of construction project with detailed contract documents r1

27

Technical SpecificationSpecifications

FORM OF CONTRACT

NBS Master Format

Myanmar Transitional Platform

Page 28: Implementation of construction project with detailed contract documents r1

28

Publish Standard Condition of Contract by relevant Authorities

(for Public and Private Sectors)

Regulate to practice the published Standard Condition of Contract

Practice to include Detailed Specification(Consultants, License Engineers, Professional Engineers)

RECOMMENDATION

Myanmar Transitional Platform

Page 29: Implementation of construction project with detailed contract documents r1

29

Clear understanding of respective responsible of each party

(Benefit to both Employer and Employee)

Prevent ambiguity and un-necessary Arbitration at Court (lost time and money)

Property is “General Public Investment”(Contribute GDP)

Preparation for “Next Generation of Construction Industrial”

(Set up the industrial practice and standard to prevent from Nasty International Contractor who want to take advantages on lack of industrialise inexperience)

RESULT OF PRACTICING DETAILED CONTRACT DOCUMENT

Myanmar Transitional Platform

Page 30: Implementation of construction project with detailed contract documents r1

30

Thank You

Soe Min SettEmail : [email protected]