+ All Categories
Home > Documents > IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i...

IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i...

Date post: 01-Apr-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
51
Il UNITED REPUBLIC OF TANZANIA IATIONAL DEVELOPMENT AGENCY DANIDA 824 TZ.IR 85 IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS HYDROLOGY - LOW FLOW GAUGINGS 1984 CARL BRO COWiCONSULT KAMPSAX - KRLJGER «CCKK
Transcript
Page 1: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IlUNITED REPUBLIC OF TANZANIA

IATIONAL DEVELOPMENT AGENCY DANIDA

824TZ.IR 85

IMPLEMENTATION OFWATER MASTER PLANS FORIRINGA, RUVUMA AND MBEYA REGIONS

HYDROLOGY - LOW FLOW GAUGINGS 1984

CARL BRO • COWiCONSULT • KAMPSAX - KRLJGER «CCKK

Page 2: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IUNITED REPUBLIC OF TANZANIADANISH INTERNATIONAL DEVELOPMENT AGENCY DANIDA

IMPLEMENTATION OFWATER MASTER PLANS FORIRINGA, RUVUMA AND MBEYA REGIONS

HYDROLOGY - LOW FLOW GAUGINGS 1984

! T. i1 -:i- i u / O

L.G:

0

LIBRARY, INTERNA n:-NA-,.

-; j )] G.-.f. 1 4 1 / 1 4

CARL BRO • COWICONSULT • KAMPSAX - KRLJGER «CCKK

Page 3: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

III

LOW FLOW STUDIES IN IRINGA, MBEYA AND RUVUMA REGIONS, TANZANIA

III

IIIIIIIIIIIIII

TABLE OF CONTENTSPage

1. INTRODUCTION 1

2. DESCRIPTION OF FIELD WORK 2m 2.1 Low Flow Measurements 2

2.2 Network Station Visits 3

3. DATA ANALYSES 4

4. VILLAGE WATER DEMAND VERSUS AVAILABILITY 16

5. CORRELATION ANALYSIS 29

6. CONCLUSION AND RECOMMENDATIONS 32

APPENDIX 1

Page 4: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

I

IIIIIIIIIIIIIIIIIII

1. INTRODUCTION

The aim of the low flow study is to provide the best possible estimates

of the 10-year minimum flows at the selected sources of the village

water supply schemes. Such estimates will form the basis for the final

design of the individual water supplies and for additional source

investigations where selected sources do not have sufficient yields.

The low flow measurement programme was conducted during the months of

September, October and November 1984. Two measurements were made at

most of the selected sites with approximately one month lag-time

between them. At some sites it was not possible to make the second

measurement owing to unsually early and heavy rainfall.

The sources, at which the flows were measured, were selected according

to the procedure outlined in the Working Paper "Minimum Flow Assessment

at Village Level", September 1984, Appendix 1 of this report.

Questionnaires were filled in for each of the measured sites, and the

analyses and conclusions from these are detailed in this report.

In addition, a correlation analysis of annual minimum discharges at the

permanent hydrological stations in the same areas has been performed.

The field work in the three regions of Tanzania was carried out in

close cooperation with the respective MAJI officers who provided help-

ful and capable field teams.

Page 5: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

2. DESCRIPTION OF FIELD WORK

The data needed for the low flow study necessitated two different field

activities, a) low flow measurements at 132 sources for future water

supplies, and b) evaluation of the permanent hydrological network rele-

vant for the study within the project area.

2.1 Low Flow Measurements

Two field teams in each region were in charge of conducting discharge

measurements at pre-selected sites, see Appendix 1 "Working Paper,

September 1984 for list of villages. Each team was equipped with a

Landrover and put in charge of half the number of districts in their

region.

The field teams visited between one and three sites a day and made

discharge measurements by pygmy current meter on large and fairly large

streams, by V-notch on smaller streams and by bucket on very small

streams. The results were entered in a questionnaire where also

answers to questions about the stream and the village were noted.

These questionnaires have formed the basis for the following analyses.

The field teams and their work was checked at random times by the

hydrologists and they have proven to be of very high quality.

The measurements were conducted at the end of the dry season in order

to measure the baseflow (groundwater flow) unaffected by rainfall.

The measurements were made with a timelag of approximately one month to

enable calculation of the rate of depletion by means of which the

absolute low flow of 1984 is estimated.

At some sites it was only possible to make one measurement and at other

sites the second measurement had been affected by rain.

Two sites were not visited at all, and no estimates of low flow will be

made at these sites.

Page 6: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIII1IIIIIIIIII

2.2 Network Station Visits

The estimated low flow will be related to the lowest flow obtained in

1984 from the permanent hydrological network stations. To this end,

visits to a number of gauging stations were necessary to have a picture

of the reliability of the data collected from these.

10-year minimum flows have been calculated for 12 stations during the

Water Mater Flan of Iringa, Mbeya and Ruvuma, see Table 1, and these

flows will be used in the following analyses. Nine of the above

mentioned twelve stations were visited by the hydrologist and one of

the remaining three stations was closed because of road construction.

Altogether 19 of the most reliable stations in the network were visited

in order to assess the reliability of the data - and out of these 18

stations were found to be in a satisfactory condition.

The water levels from a number of stations have been collected and

converted to discharges of which the lowest for each station is found.

The ratio of the minimum flow of 1984 and the 10-year minimum will

then be used to scale the minimum flow of the measured streams in order

to find its 10-year minimum.

Table 1 - 10-year minimum flows at selected hydrological stations

Station River Areakm*

10-year minimuml/s/km* 1/s

1KA 22

1KA 37A

1KA 32A

IRC 8A

3A 8

IRC 5A

1KA 7A

IRC 3A

3B 15

1RB 2

1KB 19

1KB 18B

IRC 2A

Mtitu

Lukosi

Lt Ruaha

Kiwira

Myovisi

Kiwira

Chimala

Mbaka

Mtembwa

Ruhuhu

Hagafiro

Ruhudji

Kiwira

445

2890

759

655

152

217

167

645

8000

2220

153

410

1660

2.5

2.8

0.3

8.3

1.6

9.5

1.0

3.9

0.01

6.67

3.5

3.5

5.4

1,130

8,092

228

5,436

243

2,062

167

2,540

80

14,830

536

1,435

8,964

Page 7: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

3. DATA ANALYSES

The questionnaires from each of the selected water supply sources have

been analysed and a recession constant calculated, where possible. The

recession constants are calculated using the equation

Q2 - Ql x .

where

Ql is the discharge at the time ti

0.2 is the discharge at the time t2

k is the recession constant varying for each catchment

The recession constants for the selected water supply sources are shown

in Table 2.

The lowest discharge for 1984 for 11 out of the 12 selected hydrologi-

cal stations plus that of station 1KB 18B was found. The number of

days (t2 - ti) from the latest low flow measurement (Qj) to the lowest

discharge at the nearest hydrological station was then found and used

in the above equation to find Q2 (the absolute lowest flow for 1984 at

the sources).

The station 1KB 18B was selected as the closest station to station

1KB 19, which has a calculated 10-year minimum, but has been closed

because of the Makambako to Songea road construction. The 10-year

minimum of 1KB 18B has been estimated by multiplying the 10-year mini-

mum specific yield of 1KB 19 by the catchment area of 1KB 18B. The

10-year minima are shown in Table 1.

At each hydrological station the ratio of the 10-year minimum

(QlO-year min' a n d t n e lowest 1984 discharge (Qnin 1984) is found and

used to scale the calculated 1984 minima of the sources (qm£n 1984)

near to it, in order to estimate their 10-year minima (qio-year

Page 8: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIII

II

II1

IIII

III

Table 2 - Recession constants

Villagename

Iringa

Ismani Group

Tungamalenga

Nyamahana

Ilula

Tanangozi

Magubike

Ikungve

Mfukulembe

Idonda

Ilula Itunda

Image

Mtitu

Mafuruto

Ibwnu

Mufindi

Maduma *

Mbalamaziwa

Nyakipanbo

Igomaa

Kiliminzowo

Wambi

Siombe

Ujindile

Boimanda

Usalule

Horonga

Makete

Bulongva

Lupalilo

Ikonda

Macamba

Iwawa

Kisinga

Ihanga

Ukwama

Masisewe

Mbalatse

Igolwa

Ukange

12

l2

12

Date

84.10.03.84.09.24.

84.10.02.

84.10.02.

84.09.26.

84.09.28.34.09.23.

84.10.01.

84.10.04.

34.10.05.

84.10.09.

84.09.26.

84.09.29.

84.11.07.

34.10.06.

84.10.29.

84.10.03.

84.09.27.

34.09.26.

34.10.09.

84.09.25.

84.09.29.

84.09.28.

84.09.29.

84.10.01.

84.10.17.

84.10.16.

84.10.01.

84.10.13.

84.10.16.34.10.02.

34.10.01.

84.10.15.

84.10.02.

34.10.02.

84.10.13.

84.10.15.

84.10.13.

1stmaasurem.

L/S-

88.0

7.7

204.0

159.0

19.2

19.18.2

34.7

0.62

1.98

6.05

10.2

23.0

190.1

5.5

8.4

0.35

168.2

53.4

5.2

8.2

156.0

9.9

16.9

1.8

0.31

4.5

0.75.4

10.7

2.9

1.5

0.35

0.65

0.14

1.37

Date

84.10.29.84.10.26.

84.10.31.

84.11.05.

84.10.27.

84.11.02.84.11.02.

84.11.05.

84.11.06.

84.11.01.

84.10.30.

84.10.27.

84.11.03.

84.10.29.

84.10.29.

34.10.29.

"84.10.27.

84.10.30.

84.10.31.

84.10.30.

84.11.02.

84.11.05.

85.11.05

34.11.04.

84.11.07.

84.11.06.34.11.06.

84.11.05.

84.11.04.

34.11.04.

84.11.03.

84.11.02.

84.11.03.

84.11.03.

2ndmeasurem.L/S

31.28.5

110.6

155.0

13.7

18.88.1

32.3

0.26

1.95

10.85

4.36

40.6

7.9

0.33

106.4

41.4

2.65

7.2

154.0

16.2

38.7

1.5

0.25

3.3

1.954.64

10.7

2.2

1.7

0.16

0.7

0.22

1.16'

RecessionConstantdays-1

0.0031

0.0202

0.0007

0.0105

0.00040.0002

0.0019

0.0252

0.0005

0.0262

0.0021

0.0013

0.0216

0.0077

0.0206

0.0042

0.0004

0.0092

0.0061

0.0165

0.0044

0.0131

0.0234

0.0075

Remarks

never dries

never dries

never dries

never dries

discharge toolarge to measure

never dries

dry

never dries

never dries

never dries

never dries

never dries

never dries

never dries

i Source has not been measured

Page 9: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIII1III1IIIIIIIII

Table 2 - Continued

Villagename

Ludewa

Mawengi

Itundu

Madunda

Madilu

Lugarawa

Luilo

Mboil

Mbozi Uest

Myovisi

Vwawa

Kacete

Ihanda

Isandula

Senjele

Heiya

Vwawa Township

Ileje

Iioko

Sheyo

I tale

Mbeya

Ilongo

Mbuyuni

Utengule

Ikhoho

Ihombe

Uyole

Iwindi

Isuto

Itimba

Rujewa

Ijumbi

Isangala

12

12

12

12

12

123

12

Date

84.10.19.

84.10.17.84.10.17.

84.10.19.84.10.17.

84.10.15.84.1L.12.

84.10.15.

84.10.22.84.10.22.

84.10.05.

34.10.10.

84.10.07.

34.10.04.

84.10.09.

84.10.06.84.10.06.

84.10.01.

84.10.11.

84.10.11.

84.10.14.

84.1071*3 :

84.10.12.84.10.12.84.10.12.

84.10.20.

84.10.20.

84.10.21.

84.10.22.

84.09.28.

84.10.22.

84.09.28.34.09.28.

84.10.18.

84.10.19.

84.10.21.

84.10.26.

34.10.18.

Iscmeasures.

L/S

1.8

0.70.22

0.500.46

0.370.17

0.43

0.601.6

834.0

24.5

10.8

5.6

0.4

1.7212.2

80.2

168.0

13.5

13.6

6.0

13.512.2

168.0

100.0

592.0

134.0

22.8

13.5

6.3

24.945.1

9.6

83.0

2810.0

27.0

Data

84.11.15.

84.11.13.84.11.13.

84.11.15.84.11.15.

84.11.12.

84.11.12.

84.11.14.84.U.14.

84.11.02.

84.11.01.

84.U.01.

84.11.OS.

84.11.03.84.11.03.

84.10.30.

84.11.08.

84.U.13.

84.U.16.

84.11.13.

84.11.10.

84.10.30.

84.11.11.

34.10.30.84.10.30.

84.11.10.

84.11.15.

34.11.12.

2ndmeasurem.

L/S

1.6

0.70.16

0.550.38

0.41

0.41

0.151.48

503.0

22.95

9.5

7.6

1.6626.8

77.7

180.0

29.5

177.0

905.0

118.0

12.1

11.9

5.7

27.852.0

68.8

2514.0

30.3

RecessionConstantdays"1

0.0037

0.0113

0.0063

0

0.05610.0034

0.0173

0.0029

0.0050

0.0013

0.0011

Village posi-tion tfrong, allvillages onwatershed

0.0183

0.0312

0.0039

0.0053

0.0081

0.0043

Remarks

never dries

never dries

never driesnever dries

never dries

never dries

other sourceshould be found

never dries

never drit»

never dries

never dries

never drit*

never driesnever driesnever dries

never dries

never dries

never driesnever dries

never dries

never dries

new sourceshould be foundsource runs dry

Page 10: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIII1III1I1IIIIIII

Table 2 - Continued

Villagename

Chunya

Mtanila

Ngvala

Mkwajuni/Mwambani

Maleza

NamkuXwe

Ifyenkenya

Rungwe

Nsigara

Kasiabone

N'daga

Kanyelele

Mgopyolo

Lyenje

Ndicu

Kyela

Ngana

Ngamanga

Sinyang»

Songea

Libango

Namabcngo

Mpitimbi

Muhukuru

Magagura 12

Ngahokora

Matimira

Nakahuga

Paramiho *

Lipokel»

Mbiagawhalule

Limamu

Haaga

Mlilayoyo

Mbimbi

Kilangalanga

Nguindé

«dvema

Namatuhi

Njalaoataca

Namangol»

Lilondo 1I

Dace

84.10.17.

84.10.19.

84.10.22.

84.10.20.

84.10.26.

84.10.24.

84.10.09.

84.10.10.

84.09.29.

84.10.09.

84.10.11.

84.10.11.

84.10.08.

84.10.04.

84.10.06.

84.10.08.

84.10.19.

84.11.29.

84.10.14.

84.10.14.

84.10.11.84.10.11.

84.10.10.

84.10.04.

84.10.05.

84.10.09.

84.10.12.

84.10.17.

84.11.01.

84.10.05.

84,10.16.

84.10.17.

34.10.16.

84.10.06.

84.10.13.

84.10.17.

84.10.18.

34.10.11.84.10.11.

1stmaasurem.

L/S

16.3

2.77

0.96

638.6

9.24

769.0

3.3

5.0

13.7

0.065

3.35

32.1

164.0

16.5

24.9

4.25

0.46

0.76

0.100.04

0.13

1.7

0.21

0.31

0.12

7.9

5.4

0.6

0.45

0.43

0.2

0.13

1.5

2.6

1.21

0.480.69

•Dace

84.11.13.

84.11.19.

84.11.17.

84.11.15.

84.11.05.

84.11.05.

84.10.31.

84.11.07.

84.11.08.

84.11.07.

84.11.07.

34.11.03.

84.11.05.

84.11.03.

84.11.27.

84.11.06.84.11.06.

84.11.07.

84.11.OS.

84.11.27.

84.11.07.

84.11.28.

84.11.30.

84.11.29.

84.11.28.

84.11.29.

84.11.29.

84.11.28.

2ndmass urea.

L/S

9.2

2.4

0.86

1557.0

9.4

320.0

2.05

3.2

22.8

0.05

2.34

30.9

80.0

9.8

31.6

0.300.05

0.08

0.19

0.25

0.07

3.2

0.33

0.58

1.0

0.2

4.1

1.11

RecessionConstantdays-1

0.0218

0.00S3

0.0038

0.0332

0.0140

0.0154

0.0093

0.0115

0.0012

0.0229

0.0193

0.0158

0.0032

0.0043

0.0182

0.0212

0.0106

0.0021

Remarks

dry

dry

never dries

never dries

never dries

never dries

never dries

never dries

never dries

never driesnever dries

never dries

runs dry

never dries

never drie*

never dries

never dries

never dries

never dries

never driesnever dries

X Source has not been measured

Page 11: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIII11IIIIIII1I1III

Table 2 - Continued.

Villagename

Mbinga

I, undo

Mango

Ngindo

Liteabo

Ndumbi

(Cindimba chini

Kindimba juu

Linda

Kihangi

Silo

Wuklro

Maheng*

Hyangayanga

Miyao

Sepukila

Malindindo

MikaUnga

Mpepai

Mbaaba bay

Mapilipili Liwihi

Nangombo

Tunduru

Mateoanga

Nandembo

Machemba

Naluwale

Asani

Kindamba

Mi»yaje

Njanga

Ma rumba

Dace

84.11.14.

84.11.14.

84.11.15.

B4.10.17.

84.11.12.

34.10.13.

84.10.13.

84.10.22.

84.10.22.

84.10.24.

34.10.17.

84.10.17.

84.10.20.

84.10.25.

84.10.18.

84.10.16.

84.10.16.

84.10*. 21.

84.10.26.

84.10.24.

84.10.26.

84.10.30.

84.10.28.

84.10.27.

84.10.27.

34.10.23.

84.10.30.

84.10.24.

84.10.25.

84.10.25.

1stmeasures».

L/S

7.2

3.3

444.0

6.9

0.07

2.7

0.5

1.3

0.09

0.32

1.7

0.43

1.1

13.3

0.07

4.4

6.7

537.0

0.006

S65.O

6.6

2.1

2.1

3.7

17.9

4.5

1.1

32.3

0.35

Dace

84.11.20.

84.11.08.

84.11.08.

84.11.26.

84.11.26.

84.11.26.

84.11.20.

84.11.20.

84.11.21.

84.11.21.

84.11.21.

84.11.16.

84.11.26.

84.11.16.

84.11.26.

84.11.13.

84.11.12.

84.11.13.

84.11.08.

84.11.27.

84.11.10.

84.11.10.

84.11.10.

2ndmaasuram.

L/S

6.5

2.2

0.26

2.2

0.06

0.30

1.48

0.10

20.4

3.9

8.0

3210.0

0.002

693.0

6.3

0.21

1.7

2.314.6

2.2

1.3

34.5

0.33

SecessionConstantdays"'-

0.0015

*

0.0081

0.0216

0.0112

0.0020

0.0044

0.0420

0.0031

0.0318

0.0015

0.1272

0.0122

0.0275

0.0121

0.0243

0.0035

Remarks

never dries

never dries

never dries

never dries

never dries

never dries

never dries

never dries

never dries

spring sourcesupply out oforder

never dries

never drie*

never dries

Page 12: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

II1I1I1IIII1I1IIIIIII

The equation is shown below, and the calculated 10-year minima for the

sources are shown in Table 3.

- QlO-minq 10-year min " <lmin 1984 (r )

^min 1984

For the sources at which only one measurement is valid a recession

constant of 0.0300 has been selected with which to calculate the mini-

mum flow of 1984. This recession constant has been selected on the

safe side in order not to calculate too large a low flow. The calcul-

ated low flow has then been scaled with the ratio of the nearest hydro-

station, see equation above*.

Page 13: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

I 10

II

1IIIIIII1IIIIIII

Table 3 10-year minimum flows

VillageName

Iringa

Ismani

Tungamalenga

Nyamahana

Ilula

Tanangozi

Magubike

Ikungwe

Mfukulembe

Idonda

Ilula Itunda

Image

Mtitu

Ibumu

Mufindi

Maduma

Mbalamaziwa

Nyakipambo

Igomaa

Kiliminzowo

Wambi

Njombe

Ujindile

Boimanda

Usalule

Moronga

12

12

Ql

L/S

81.27.7

110.6

155.0

13.7

18.88.1

32.3

0.26

1.95

6.05

4.36

28.0

190.1

5.5

7.9

0.33

106.4

41.4 .

2.65

7.2

154.0

9.9

RecessionConstant

k

0.00310.0300

0.0202

0.0007

0.0105

0.00040.0002

0.0019

0.0252

0.0005

0.0300

0.0262

0.0300

. 0.0300

0.0-300

0.0021

0.0018

0.0216

0.0077

0.0206

0.0042

0.0004

0.0300

Time lag

t

3030

3

10

19

1313

10

9

14

35

19

47

47

16

17

17

17

19

16

15

16

46

Q min 198A

L/S

743.1

104.1

154

11.2

18.78.0

31.7

0.21

1.94

2.12

2.65

6.8

46.4

3.4

7.6

0.32

0.0

73.7

35.8

1.91

6.76

153.0

2.5

10-yearminimum

L/S

34.7

46.9

69.3

5.0

12.0

14.3

0.1

0.9

1.0

1.2

3.1

20.9

1.5

3.4

0.14

0

33.2

16.1

0.9

3.0

68.9

1.1

Page 14: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIII1III1IIIII

11

Table 3 Continued

VillageName

Makete

Bulongwa

Lupalilo

Ikonda

Matamba

Iwawa

Kisinga

Ihanga

Ukwaroa

Masisiwe

Mbalatse

Igolwa

Ukange

Ludewa

Mawengi

Itundu

Madunda

Madilu

Lugarawa

Luilo

Mbozi

Mbozi West

Myovisi

Vwawa

12

12

12

12

12

Vwawa Township

Katete

Ihanda

Isandula 12

Ql

L/S

16.9

1.5

0.25

3.3

0.74.64

10.7

2.2

1.7

0.16

0.65

0.14

1.16

1.6

0.70.22

0.500.38

0.370.17

0.41

0.151.48

503.0

24.5

9.5

13.5

5.6

0.4

1.6612.2

RecessionConstant

k

0.0300

0.0092

0.0061

0.0165

0.03000.0044

0.0300

0.0131

0.0300

0.0234

0.0300

0.0300

0.0075

0.0037

0.03000.0300

0.03000.0063

0.03000.0300

0.0300

0.05610.0034

0.0173

0.0300

0.0300

0.0300

0.0300

0.0300

0.03000.0300

Time lag

t

30

10

11

8

309

10

11

11

12

13

12

12

0

22

00

33

3

11

6

7

10

6

13

8

1111

Q min 1984

L/S

6.9

1.4

0.23

2.9

0.34.46

7.93

1.9

1.22

0.12

0.44

0.1

1.06

1.6

0.660.21

0.88

0.49

0.37

0.141.47

453-

19.9

7.0

11.3

3.8

0.3

1.28.8

10-yearminimumL/S

3.1

0.6

0.1

1.3

2.1

3.6

0.9

0.6

0.1

0.2

0.1

0.5

0.7

0.4

0.4

0.2

0.2

0.7

453

19.9

7.0

11.3

3.8

0.3

1.28.8

Page 15: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

111I1II1111I111I11111

Table 3 Continued

VillageName

Mbozi

Senjele

Hezya

Ileje

Isoko

Sheyo

Itale 123

Mbeya

Ilongo

Mbuyuni

Utengule

Ikhoho

Ihotnbe

Uyole

Iwindi 12

Isuto

Itimba

Ru j ewa

I^umbi

Isangala

Chunya

Mtanila

Ngwala

Mkwa j uni /Mwam.

Maleza

Namkukwe

Ifyenkenya

Qi

L/S

77.7

168.0

13.6

6.0

13.512.2

168.0

100-0

592.0

118.0

12.1

11.9

5.7

24.945.1

9.6

68.8

2514.0

27.0

9.2

2.4

0.86

638.6

RecessionConstant

k

0.0300

0.0300

0.0300

0.0300

0.03000.03000.0300

0.0300

0.0300

0.0184

0.0312

0.0039

0.0053

0.03000.0300

0.0300

0.0081

0.0043

0.0300

0.0218

0.0053

0.0038

0.0300

Time lag

t

16

6

52

53

545454

33

33

8

13

1919

0

18

26

18

12

14

15

Q min 1984

L/S ,

48.1

140.3

2.86

1.22

2.672.4133.25

37.16

220

102

8.3

11.9

5.7

14.125.5

9.6

68.8

2327

12.4

0

0.0

6.2

2.3

0.82

0.0

407

12

10-yearminimum

L/S

48.1

140.3

2.6

1.1

2.52.230.6

• - —

18.6

110

51

4.1

11.9

5.7

39.6

9.6

68.8

1573

6.2

0

0

4.7

1.7

0.6

0

100

Page 16: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

13

1

III

Table 3 Continued

Village Ql Recession Time lag Q min 1984 "10-yearName Constant minimum

L/S k t L/S L/S

Rungwe

Nsigara 9-24

Kasiabone 320.0 0.0332 30

Ndaga 2.05 0.0140 0

Kanyelele 3.2 0.0154 29

Ngopyolo 13.7

Lyenje 0.05 0.0093 33

Nditu 2.34 0.0115 29

Kyela

Ngana 30.9 0.0012 0

Ngamanga 80.0 0.0229 0

Sinyanga 9.8 0.0193 0

Songea

Libango 24.9 0.0063 27

Namabengo 4.25 0.0300 9

Mpitimbi 0.46 0.0300 31

Muhukuru 0.76 0.0300 31

Magagura 1 0.10 0.0300 35

2 0.04 0.0300 35

Ngahokora 0.08 0.0158 36

Matimira . 1.7 0.0300 41

Nakahuga 0.19 0.0032 40

Feramiho

Lipokela 0.25 0.0043 11

Mbingamhalule 0.07 0.0182 8

Limamu 3.2 0.0212 0

Lilondo 1 0.48 0.0300 35

2 0.69 0.0300 35

Hanga 5.4 0.0300 15

Mlilayoyo 0.33 0.0106 0

Mbirabi 0.45 0.0300 30

Kilangalanga 0.43 0.0300 28

Ngwinde 0.20 0.0300 0

9.2118.2

2.05

2.1

13.7

0.037

1.7

30.9

80.0

9.8

21.0

3.24

0.2

0.3

0.10.01

0.5

0.1

0.24

0.05

3.2

0.160.23

3.44

0.33

0.25

0.25

0.20

8.3108.4

1.85

1.9

12.3

0.034

1.6

13

35

..1.0

18.9

2.9

0.2

0.3

0.1

0.1

0.5

0.1

0.2

0.1

2.9

0.4

3.1

0.3

0.2

0.2

0.2

Page 17: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

III1IIIIIIIIIIIIIIIII

14

Table 3 Continued

VillageName

Songea

Mdwema

Namatuhi

Njalamatata

Namanguli

Mbinga

Lundo

Mango

Ngindo

Litembo

Ndumbi

Kindimba chini

Kindimba juu

Linda

Kihangi

Silo

Wukiro

Mahenge

Myangayanga

Miyao

Sepukila

Malindindo

Mikalanga

Mpepai

Mbamba Bay

Mapipili Liwihi

Nangombo

Tunduru

Matemanga

Nandembo

Machemba

Naluwale

Ql

L/S

0.13

1.5

2.6

1.11

7.2

3.3

444.0

6.5

0.07

2.2

0.26

1.3

0.06

0.30

1.48

0.10

1.1

13.3

0.07

3.9

6.7

537.0

0.002

565.0

6.3

0.21

1.7

2.3

RecessionConstant

k

0.0300

0.0300

0.0300

0.0021

0.0300

0.0300

0.0300

0.0015

0.0300

0.0081

0.0216

0.0300

0.0112

0.0020

0.0044

0.0420'

0.0300

0.0300

0.0300

0.0031

0.0300

0.0300

0.0318

0.0300

0.0015

0.1272

0.0122

0.0275

Time lag

t

40

32

28

0

0

0

0

0

0

7

7

23

0

0

0

0

25

20

28

0

30

20

0

20

0

2

3

2

Q min 1984

L/S

0.1

0.57

1.12

1.11

7.2

3.3

444.0

6.5

0.07

2.1

0.22

0.65

0.06

0.30

1.48

0.10

0.5

7.30.03

3.9

2.7

295

U .UUZ

310

6.3

0.2

1.64

2.2

"10-yearminimum

L/S

1 0.1

0.5

1.0

1.1

6.5

3.0

400

5.9

0.1

2.1

0.6

0.1

0.30

1.3

0.1

0.4

6.6

0.1

3.5

2.5

265

n iU. I

280

5.7

0.2

1.5

2.0

Page 18: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

111111111111111111111

Table 3

VillageName

Tunduru

Amani

Kindamba

Misyaje

Nj enga

Marumba

-

Continued

Ql

L/S

14.6

2.2

1.1

32.3

0.33

RecessionConstant

k

0.0121

0.0243

0.0300

0.0300

0.0035

Time lag

t

7

0

20

20

5

Q min 1984

L/S

13.4

2.2

0.6

17.7

0.32

15

-10-yearminimumL/S

12.1

2.0

0.5

16.0

0.3

Page 19: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

16

4. VILLAGE WATER DEMAND VERSUS AVAILABILITY

The village water demand has been calculated during Che Water Master

Plan of Iringa, Mbeya and Ruvuma for each water supply scheme and has

been based on the expected population in the year 2006, multiplied by

the amount of water needed per capita per day. Some of the future

populations seem to have been estimted rather too high, especially for

the arid ares, and it may be advisable to look into this matter. The

populations in question are marked by an asterix in Table 4.

Below is a list of water demands versus availability - from which it

can be seen that 49% of the village water supply schemes measured will

have sufficient water in the year 2006.

In 51% of the schemes the water available is less than what will be

needed, and in these schemes it is very important to locate other

sources with large enough minimum flows, either to supply all the water

needed, or at least enough to supplement the proposed source. Should

this not be possible, then an alternative solution, i.e. shallow wells,

must be considered.

At some sites it has been difficult to measure the water available,

either because of seepage over a large area, or because of water

collects underground, resulting in little or no surface flow. There-

fore, some of the measurements do not reflect the actual amount of

water available. A brief description of each site at which there was a

deficit is therefore needed.

Iringa Region, Iringa District

I lu 1 axj3r oup_ :

Additional sources may be needed to supply the proposed amount of

water. Reconnaissance will be needed.

Ikungwei_Single:

Several streams run through the village, and intakes could be

constructed on one or more of these streams. Measurements on these

streams will determine how many intakes are necessary.

Page 20: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

17

Ilula_ItundaA_Single

The measurements were made 100 m upstream of the intake structure, but

even so, it is necessary to provide additional water, which may be

found in nearby streams.

Imagex_Grou2

Since only one measurement was valid here it is difficult to say if the

the amount of water available is too small. Additional measurements

are necessary here.

MtituA_Groug

There may be enough water available here, but since only one measure-

ment is valid it is difficult to say. Additional measurements are

needed to ascertain the quantities of water.

Iringa Region, Mufindi District

Additional sources are necessary in order to supply the needed amount

of water.

This group scheme consists of Nyakipambo, Mtambula and Ihegele vil-

lages, which in the Water Master Plan were single schemes. It would be

an idea either to go back to the original proposal, or to make an addi-

tional intake on Msolwa river if enough water is available here.

A new source has to be found here as the proposed source runs dry.

Several rivers run parallel to the proposed source, and intakes could

be constructed on these when measurements have shown if there is enough

water.

Iringa Region, Njombe District

It is possible that enough water is available here, but as there is

only one valid measurement it is difficult to estimate an exact 10-year

minimum*

Page 21: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

18

Iringa Region, Makete District

At all these villages there may be enough water available, but because

only one valid measurement is available it is difficult to be certain,

and additional measurements are recommended.

Several sources run parallel to the proposed source so that intakes

could be established on one or more of these, if additional measure-

ments prove the necessity.

Ikondai_Single

Additional intakes should be possible on sources either parallel to the

proposed village or southeast of the village.

Matamba^Groujj

Additional sources are available in the vicinity to augment the supply

of the existing, but measurements should be made before selecting the

source or sources.

Several additional sources are available in or near the village, but

it may be a problem to get enough head as the village is situated on

the watersheds.

IgolwaA_Single

This village is also located on the watershed so, even though there are

plenty of sources in the vicinity, there is a problem of enough head.

Iringa Region, Ludewa District

MawengiA_Single

Additional sources are needed to supply the necessary amount of water.

A reconnaissance must be made to find a suitable supply.

Page 22: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

19

Itundui_Groug

Only the proposed sources were measured, therefore it is very likely

that the three existing intakes can supply the remaining water, only

measurements here can ascertain this.

An additional source should be found in order to supply adequate

amounts of water.

This village is situated on the watershed, so even though plenty of

sources are available, not enough head can be found.

Several additional sources are available here so that intakes on one or

more of them could solve the problems of too little water.

The potential intake sites should be measured and if enough water is

available they should be developed to supplement the proposed sites.

Mbeya Region, Mbeya District

The proposed source runs dry here, therefore another source should be

found if possible, otherwise alternative supply must be sought.

Mbeya Region, Mbozi District

If enough head is available the proposed intake may be moved downstream

to the confluence of the tributary from the south, but measurements

should be made beforehand to make sure this is a viable solution.

Page 23: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

20

Mbeya Region, Chunya District

Mtanila^Groug

The proposed year 2006 population seems unrealistic, it is doubtful

that the soil can support such a population expansion. The source runs

dry so that additional sources must be found or shallow wells proposed.

Mwambani/MkwajuniA_Single

Additional sources are needed if the future population has to be

supplied. The population increase does seem unrealistic.

The population increase seems somewhat unrealistic in such a dry area,

but possibly additional sources could be found.

NamkukweA_Single

Additional sources are necessary here as the proposed source runs dry,

shallow wells may be a possibility.

Mbeya Region, Rungwe District

This is a spring source and very difficult to measure accurately.

Seepage around the source was noticed, therefore it is possible that

enough water is available. Additional measurements downstream may give

better results.

Additional intakes will be necessary if the proposed supply shall be

met, and several sources flowing parallel to the proposed source could

supply the required water. Measurements of the amounts will determine

the number of necessary additional intakes.

Page 24: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

21

Ruvuma Region, Songea District

The water available is sufficient at present, but cannot supply a

future larger population. However, there are several streams to the

west and south of the village which could supply the required water,

and additional intakes could be constructed there.

Mgitimbix_Grou£

Hpitimbi already has a source that supplies part of the group. Only

one intake was measured although there are two; therefore the yield

should be higher. The measurements are very difficult to perform as

the water is collected by infiltration wells. The supply here is con

sidered sufficient.

Muhukurux_Grou£

It is necessary to locate an additional source here as the supply is

inadequate.

The measurements seem to have been made on another source than the one

proposed. The proposed source could later be developed to supplement

the one MAJI has selected.

This source was measured close to its spring source. The intake could

be moved downstream and then possibly supply the whole village.

The intake site here is very wet but difficult to measure. If the

amount of water proves to be too small there will be several

possibilities of additional sources nearby; however, they will

probably be too low for gravity schemes.

Nakahuga^S ing 1 e

Several additional sources exist to supplment the proposed source but

measurements must take place in order to select the best suited.

Page 25: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

22

Peramihoi_Grou2

It was not possible to perform any measurements here as the water is

collected by infiltration galleries» but there seems to be a sufficient

supply.

There is an existing bamboo scheme here, which could be supplemented by

other sources.

The intake could be moved some distance downhill, but will probably

have to be supplemented by other sources.

There are probably no additional sources, therefore other alternatives

must be considered if the proposed amount of water shall be supplied.

The measurements made here are not exact as the area is very swampy,

and therefore the discharge is very difficult to measure. The amount

of water available is considered sufficient.

Additional sources have to be found and measured as the proposed source

cannot meet the demand.

This is a Danida scheme built on MAJI recommendation. In order to

supply the future demand an additional source will have to be found.

The area is very swampy and therefore very difficult to measure, but

the available supply seems to be sufficient.

The measurement here seems unrealistic, and the source ought to yield

more. Additional measurements are recommended.

Page 26: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIII1IIIIIIIIIiIIII

23

Mbinga District

In the mountainous regions of Mbinga District the population tends to

be very scattered within the villages' and to a large extent to inhabit

the watershed areas. As such, it is very difficult to find sources

that originate from higher elevations than the habitation. The area is

supplied by water through thousands of small streams, all perennial and

all with small yields near their spring source. In fact, most houses

have their own little furrow that leads water past their house. It is

therefore a diffcult task to better their supply through one intake, as

parts of the village will always be situated too high for such a

supply. A solution, however, would be to construct several small

intakes and thereby supply the whole village. Villages with such pro-

blems are Linda, Kihangi Manuka, Silo, Wukiro, Mahenge, Myangayanga,

Sepukila and Mapipili Liwihi.

NdumbiA_Single

Plenty of additional sources exist so that adequate water supply should

not be a problem. Measurements should be made before selecting an

additional source.

Measurements are very difficult here as water is collected in an

infiltration well, but the amount is considered sufficient.

Tunduru District

Measurements are difficult here as the intake is situated in a pond.

The supply should be adequate.

An additional source should be found, or an alternative supply

considered for both these supplies.

Page 27: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIII1IIIIIIIIIIIIII

24

Table 4 - Water demand and availability

Village/Group

Iringa District

Ismani Group

Tungamalenga Group

Nyamahana Group

Ilula Group

Tanangozi Group

Magubike Group

Ikungwe, Single

Mfukulembe, Single

Idonda, Single

Ilula Itunda, Single

Image Group

Mafuluto, Single

Mtitu Group

Ibumu

Mufindi District

Maduma, Single

Mbalamaziwa Group

Ihegele

Nyakipambo Group

Mtambula

Igomaa, Single

Kilindnzowo, Single

Wambi Group

Njombe District

Ujindile, Single

Boimanda, Single

Usalule Group

Moronga Group

Makete District

Bulongwa Group

Present/futurepopulation

28,014/42,432

4,529/13,587

4,132/13,830

16,211/40,245

20,615/28,830

5,325/10,465

1,443/ 1,905

1,352/ 1,785

1,334/ 2,588

4,244/ 9,209

8,708/21,989

826/ 2,478

64,782/99,860

1,725/ 3,470

2,912/ 5,824

7,419/14,910

1,295/ 2,590

1,082/ 2,835

2,506/ 5,012

1,291/ 3,382

1,144/ 3,016

13,626/28,245

1,834/ 2,764

541/ 1,278

89,501/195,602

14,962/24,113

17,498/25,481

Waterdemandxa /day

1,051

388

336

1,002

865

259

47

44

64

230

547

61

2,480

86

145

368

259

84

75

949

69

31

5,209

598

629

Wateravailability

m^/day2-year min.

665

14

160

413

2,781

451

18

146

413

Wateravailability

m^/day10-year min.

2.998

4,052

5,988

432

1,037

1,236

9

78

86

104

268

1,000

1,806

130

293

12

0

2,868

1,391

78

259

5,953

95

268

Page 28: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

25

Table 4 (cont'd)

Village/Group

Makete District

Lupalilo Group

Ikonda, Single

Matamba Group

Iwawa Group

Kisinga, Single

Xhanga, Single

Ukwama, Single

Masisiwe, Single

Mbalatse, Single

Igolwa, Single

Ukange, Single

Ludewa District

Mawengi, Single

Itundu Group

Madunda, Single

Madilu, Single

Lugarawa, Single

Luilo Group

Mbozi District

Mbosi West Group

Myovisi Group

Vwawa Group

Katete, Single «

Ihanda, Single

Isandula, Single

Senjele, Single

Hezya, Single

Ileje District

Isoko Group

Itale, Single

Present/futurepopulation

Waterdemandm3/day

Wateravailability

mVday2-year min.

Wateravailability

m^/day10-year min.

S

3.306/ 5.290

888/ 1.420

7.001/10.100

5.779/ 9.245

855/ 1.368

1.290/ 1.457

1.327/ 2.672

900/ 1.359

1.744/ 1.970

1,570/ 1.805

1,316/ 1.842

2.371/ 5.572

3.958/ 9.301

1.485/ 3.490

2.504/ 5.884

5.705/13.407

11.198/27.654

28.056/97.669

10.682/23.362

18.037/31.601

2.110/ 8.060

2.959/ 6.421

2.441/ 5.757

2.867/ 6.221

2:436/ 5.286

5.140/ 9.012

3.187/ 6.690

13135

250

273

34

36

66

33

49

45

46

139

232

87

147

355

689

2.432

580

1.042

201

160

143

155

132

224

167

80

14

172

278

80

14

26

14

66

92

54

54

26

26

97

40

347

52

9

112

181

311

78

52

9

17

9

43

60

35

35

17

17

63

6.912

1.719

1.581

328

26

864

4.156

12.122

225

3.050

Page 29: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

1III1IIII

IIIIIIIIIII

26

Table 4 (cont'd)

Village/Group

Ileje District

Sheyo, Single

Mbeya District

Ilongo Group

Mbuyuni Group

Utengule Group

Ikhoho, Single

Ihombe Group

Uyole Group

Iwindi Group

Isuto Group

Itimba, Single

Rujewa Group

Ijumbi Group

Isangala Group

Chunya District

Htanila Group

Ngwala, Single

Mkwajuni, Single

Mwambani, Single

Maleza, Single S

Namkukwe, Single

Ifyenkenya Group

Rungwe District

Nsigara Group

Kasiabone, Single

Ndaga Group

Kanyelele Group

Ngopyolo Group

Lyenje, Single

Nditu, Single

Present/futurepopulation

.....

1.632/ 3.084

14.027/46.244

11.009/36.485

7.703/30.658

1.262/ 1.767

4.555/ 6.211

9.618/13.271

13.191/18.256

8.342/11.250

1.605/ 2.188

20.981/86.470

4.843/19.730

3.485/ 5.151

7.007/34.964

. 1.039/ 2.881

5.032/ 15.126

2.199/ 6.597

3.680/11.040

4.342/10.464

2.900/ 3.354

1.232/ 1.626

6.273/10.532

4.730/ 5.020

6.797/ 8.973

1.058/ 1.442

2.400/ 3.168

Waterdemandm^/day

77

1.152

907

766

44

144

332

422

279

54

2.779

522

128

874

72

377

164

275

260

83

24

269

125

224

36

79

Wateravailability

mVday2-year min.

226

80

245

5

Wateravailability

m^/day10-year min.

95

1.607

9.504

4.406

354

1.028

492

3.421

829

5.944

201.053

536

0

0

406

147

52

0

8.640

717

9.366

159

164

1.063

3

138

Page 30: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIII1II1IIII1IIIIII

27

Table 4 (cont'd)

Village/Group

Kyela District

Ngana Group

Ngamanga Group

Sinyanga Group

Songea District

Libango Group

Namabengo Group

Mpitimbi Group

Muhukuru Group

Magagura, Single

Ngahokora, Single

Matimira, Single

Peramiho Group

Lipokela Group

Mbingamhalule, Single

Limamu, Single

Lilondo., Single

Hanga, Single

Mlilayoyo, Single

Mbimbi, Single

Ngwinde, Single

Mdwemba, Single

Namatuhi, Single

Njalamatata Group

Namangole Group

Kilangalanga, Single

Nakahuga, Single

Mbinga District

Lundo Group

Mango Group

Ngindo, Single

Litembo, Single

Present/futurepopulation

25.127/34.740

12.747/19.3367.325/10.314

12.863/22.730

5.368/13.130

4.167/10.430

6.192/14.8602.531/ 6.190

1.629/ 3.9902.591/ 6.560

4.555/ 6.882

2.402/ 7.162

2.180/ 5.700

2.035/ 5.3301.747/ 4.280

2.426/ 6.1401.032/ 2.520

1.379/ 3.2001.039/ 2.750

719/ 1.8801.331/ 3.260

7.679/18.780

3.649/ 9.1201.370/ 3.3501.527/ 3.740

2.721/ 3.7755.474/ 8.300

573/ 1.925

2.784/ 6.640

WaterdemandnrVday

861

479

255

566

327

260

370

154

99

163

149

117

142

133

106

153

62

79

68

46

81

467

227

83

93

93

206

48

165

Wateravailabili ty

m-Vday2-year min.

386

26

40

14

14

66

26

14

54

40

26

26

14

66

132

146

26

14

Wateravailabili ty

m^/day10-year min.

1.1233.024

346

1.633

251

17

26

9

9

43

17

9

268

35

268

26

17

17

9

43

86

95

17

9

562

259

34.560

510

Page 31: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

1IIIIIIIIII1I1III1III

28

Table 4 Ccont'd)

Village/Group

Mbinga District

Ndumbi, Single

Kindimba chini/juu,S in g te

Linda, Single

Kihangi Mahuka, Single

Silo, Single

Wukiro, Single

Mahenge, Single

Myangayanga Group

Miyao Group

Sepukila, Single

Malindindo, Single

Mikalanga, Single

Mpepai, Single

Mbanba Bay Group

Mapipili Liwihi, Single

Nangombo, Single

Tunduru District

Matemanga Group

Nandembo, Single

Machemba Group

Naluwale Group

Amani Group

Kindamba, Single

Misyaje, Single

Njenga, Single

Ma rumba Group

Present/futurepopulation

2.518/

1.721/

2.044/

1.607/

2.256/

2.720/

1.579/

3.700

3.320

5.212

4.100

4.855

6.490

3.770

6.595/15.960

4.364/11.570

1.569/

2.053/

2.294/

3.000/

5.742/

2.455/

1.770/

4.625/

2.873/

3.938/

1.415/

3.781/

560/

1.183/

1.625/

4.020/

3.190

5.235

5.850

7.150

8.620

6.260

2,650

8.100

6.790

6.970

2.560

9.380

1.000

2.700

3.900

8.139

Waterdemandm^/day

92

82

130

102

121

162

94

397

288_

79

130

146

178

214

156

66

200

169

172

63

232

24

67

97

202

Wateravailability

m^/day2-year min.

14

80

14

42

172

14

54

14

11

26

200

67

40

Wateravailability

nH/day10-year min.

9

181

52

9

27

112

9

35

570

9

302

216

22.896

9

24.192

492

17

130

173

1.045

173

43

1.382

26

Page 32: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIII1IIIIIIIIIII

5.

WA32Anwnarg*

29

CORRELATION ANALYSES

In areas with similar hydrological and geological charactistics the

annual minimum flows from the hydromet stations have been correlated.

Within a selected area a period was chosen in which all stations had

flow data, the annual minima were then found, and correlation between

pairs of stations conducted as shown below.

1KA2A

mV* r.O,7S1 r-OTtt

1KA2MV

1KA21*nf/%

Figure 1 - Correlation of annual minimum flows for hydromet.

stations on Lt Ruaha upstream of Iringa

Correlation between the following stations during the period 1958-79

were performed.

Table 5 - Correlation coefficients of annual minimum flows at hydromet.

stations on Lt Ruaha river upstream of Iringa

1KA 22 1KA 39A 1KA 2A 1KA 32A

1KA 21A

1KA 22

1KA 39A

1KA 2A

0,564 0,781

0,734

- •

-

0,763

0,840

0,888—

0,731

0,610

0,921

0,840

Page 33: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

1II11IIII1I11IIIIIIII

30

N

Figure 2 - Hydromet. station on Lt Ruaha river system upstream of

Iringa

Table 6 - Correlation coefficients of annual minimum flows at hydromet,

stations in the Rungwe, Kyela area

IRC 5A IRC 3A IRC 2A

IRC 8A

IRC 5A

IRC 3A

0,692 0,090

0,239-

0,456

0,209

0,517

Table 7 - Correlation coefficients of annual minimum flows at hydromet,

stations in the Mbeya, Myovisi area

3A 14A 3A 6 3A 7A

3A 8

3 A 14A

3A 6

0.01 0.65

0.07

0.41

0.10

0.43

Page 34: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIfIIII1IIIIIIIII

31

The recession constants of a river have in earlier studies, i.e. the

Water Master Plan of Iringa, Mbeya and Ruvuma shown to vary little from

year to year.

The analogue assumption would then be that the average recession

constant at a homogenous area varies little from year to year. If this

could be verified by spotchecks during a couple of dry seasons it would

be possible to make only one gauging at the ungauged village sources,

and with the date of the gauging and the date of the absolute minimum

flow at a nearby hydrostation the minimum flow that year could be

calculated, and hence the 10-year minimum of that particular village

source. A greater number of village sources within such areas could be

analysed every season by this method.

Correlation analyses have been conducted in the Rungwe, Kyela area,

the Myovisi, Mbeya area and Little Ruaha upstream of Iringa. It has

not been possible to identify any other areas in which such correlation

would be possible, since in all other areas the topographical and

hydrological characteristics vary greatly.

The Rungwe, Kyela area does not seem to have a very good correlation

- as shown in Table 6 - nor does the Myovisi, Mbeya area as seen from

Table 7; however, the Little Ruaha area upstream of Iringa shows very

good correlation.

In the Lt. Ruaha area only a few of the sources need to be measured;

it can therefore not be recommended that average recession constants be

used in any of the areas of the three regions.

Page 35: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIII1IIIIIIIIII

32

CONCLUSIONS AND RECOMMENDATIONS

A number of sources, as seen from Table 4, cannot provide the water

which will be needed in the year 2006, and at many locations new or

additional sources have to be found. In Mbeya 8 sources do not provide

enough water, in Iringa 26 and in Ruvuma 33 sources have too small

yields.

This is based on the comparison of the projected water demand in the

year 2006 and the minimum flow statistically expected to occur once in

10 years. It is however important to consider that both a projected

demand and the 10-year minimum flow are parameters which may have a

considerable inherent uncertainty.

The projections of population figures are based on generalized assump-

tions about growth rates which may or may not apply to the particular

village. The 10-year minimum flow is based on various assumptions

about similarity between the behaviour of the stream under investiga-

tion and a larger stream in the vicinity. Thus, we recommend that the

following considerations are applied before rejecting a source not

meeting the demand criteria of year 2006.

- Has the past trends in the village development confirmed the earlier

population projections?

- What is the consequence of rejecting a source, that is, can

additional or alternative sources be developed and at which cost?

- If the 10-year criterion is not met, does the source meet a 5-year

criterion or a 2-year criterion, see Table 8), and what are the

consequences in terms of reduced availability of water for the

villager. Can such a reduction be considered acceptable when com-

pared to the cost of developing either an alternative source or an

additional source. This question also relates to the problem of

whether a traditional source may be acceptable during a period of

deficiency.

Page 36: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

III1IIIIIIII1I

33

IIIIII

Table 8 - Villages with too little water in the year 2006

2-year minimum 10-year minimum

Iringa 21 26

Mbeya 8 8

Ruvuma 29 33

Of the 132 measured sources 67 have shown not to have sufficient water

for the future populations in the year 2006. It is therefore highly

recommended that another low flow programme be conducted during the dry

season of 1985. This low flow programme should cover 26 sources In

Iringa Region, 8 sources in Mbeya Region and 33 sources in Ruvuma

Region as recommended in Chapter 4, and should start early September in

order to be completed before the rains start. A proposed time-schedule

is shown below in Fig. 3.

The sources where not enough water was available can be grouped into

two categories:

Category 1: Sources with insufficient water based on two measurements

in 1984.

Category 2: Sources with insufficient water based on one measurement

in 1984 and an assumed recession constant (safe side).

The recommended low flow programme for 1985 would then comprise two

programmes:

*

Programme for category 1: Measurements at additional/alternative

sources

Programme for category 2: Measurements at proposed sources to verify

the minimum flow and if necessary

measurements at additional/alternative

sources.

The village water supply sources under programme 2 are not considered

to be many.

Page 37: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

WORKING PAPER

MINIMUM FLOW ASSESSMENT

AT VILLAGE LEVEL

SEPTEMBER 1984

DANIDA - CCKK

Page 38: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

WORKING PAPER

MINIMUM FLOW ASSESSMENT AT VILLAGE LEVEL

1. INTRODUCTION

During the Water Master Plan, hydrological investigations were aimedat two different main goals. These were t

to establish the regional hydrological regimecomprising precipitation, evaporation, runoffand the distribution of these parameters in timeand space.

to establish estimates for minimum flow at sourcesnear the villages to suit the planning of thewater supply schemes.

The estimates of minimum flows had to be based on single measurementscarried out during village visits* These were then compared on aregional basis and included in the planning procedure*

It was, however, clear that before actual construction should takeplace there would bê a number of cases where the accuracy of theplanning estimates would not be sufficient and where additional sourceinvestigations would have to be made.

The aim of the present working paper is thus to outline the principlesfor selection of village sources for additional measurements, to presentthe selcted villages and to describe the method of measurement and analysis.

2. SELECTION OF SOURCES FOR ADDITIONAL MEASUREMENTS

2.1 Hydrological zoning

The water master plan results comprised I.a.a map of hydrological zones from which a firstestimate of 10 - year TMtrftmim flows can becalculated for small catchments. (Drg. No. 6Box II 10-year minimum runoff in 1/s/knr). Ingeneral these zones and derived estimates wouldbe more reliable as regards zone 3 and 4 thanas regards zone 1 and 2*

Screening from a purely hydrological point of viewhas thus been performed In the following ways

- if village source yields inzone 1 or 2 are below4 times the estimated demand these sources areincluded in the preliminary list of village sourcesfor additional measurements.

Page 39: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

if village source yields in zone 3 or 4 are below 2 timesthe estimated demand these sources are included in thepreliminary list of village sources for additional measurements.

2.2 Construction Programme

The three year rolling construction programme Has been studiedand all included schemes with surface water sources has beenselected for additional measurements unless a relatively largestream with well established dry-season flow is the source.

2.3 Priority Programme

The priority programme of 633 villages has been considered.No single village Is included for additional source assessmentunless it is included in the priority programme. In the sameway, no group scheme has been included for additional measurementunless it comprises a reasonable number of priority schemes. •

2.4 Scheme Type

Villages for which conventional pumping has been the only feasiblesolution Indicated in the Master Plan have not been included, asthe implementation of such schemes will be defered to some futuredate.

2.5 Results of screening procedure

The results in terms of village sources to be assessed in moredetail are given as a list ( Appendix 2.1, 2.2 and 2.3 )•The number of villages /group schemes are as follows :

No. of schemes for additional measurements

IRINGA 41

RUVUMA 52MBEYA 39

TOTAL 132

Page 40: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

3. MEASUREMENTS OF DISCHARGE

3.1 Equipment

The measurements of discharge will all be carried out at relativelysmall streams* Three types of equipment are envisaged to besufficient for these measurements which are expected mainly to bein the range of 1 - 50 1/s. The field teams will be equipped with:

t- V-notch (90°)

calibrated bucket and stopwatch

- micro-propeller (OTT-meter)

The V-notch is .manufactured for the purpose, buckets calibratedand the micropropellers are available at the regional hydrologicaloffices to «here they were handed over by the end of the MasterPlan Phase.

3.2 Staffing

The central Maji authorities (Mr. W. Balai le ) hâve been informedabout the programming of the activities and have in turn requestedthe regional hydrologists'.to make available two field teams ineach region. The activities of these field teams will be supervisedby the CCKK-hydrologist. Instructions and a form to be filled infor each source have been prepared ( see Appendix 3.1).

4. PRINCIPLES OF ANALYSIS

4.1 General

The basic idea is to carry out two spot measurements at each sourcewith a time lag of approximately one month. During the dry season,when no rain occurs, the flows will represent a baseflow originatingfrom the groundwater.

The two measurements will give information on the rate of depletionof the ground, -water reservoir. Based on information from permanent Ma.stations, the depletion curve can be extended and a 10-year minimumflow estimate arrived at*

Page 41: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

4.2 Recession curve

When a groundwater reservoir is the only source of a stream,which will be the case at the end of the dry. season, thedischarge will decrease exponentially» Thus, the process canbe described by the equation

Q2 = Qx x e •Wt2"tl)> where

Q, is discharge at the time t.

Q. is discharge at the time t.

k is a constant varying from catchment to catchment

The constant k can thus be calculated from two measurements ofdischarge spaced in time such as to give a reasonable accuracy.

If the time of the annual minimum flow can be estimated, then thesame equation can be applied to yield the annual minimum. Thisminimum flow can then be scaled to give the 10-year minimum flowwhen compared to the hydrological regime of an adjacent Maji-station with a long record.

5. D M a COLLECTION AND ANALYSIS

5.1 Spot Measurements

The spot measurements are carried out at all selected villagescheme sources. These sources appear as a result of the screeningprocedure and are given in Appendix 2.1, 2.2 and 2-3- The timelag between the two measurements will be approximately one monthand the measurement form (Appendix 3.1) will be filled in.In addition to the measurements, questions will be. asked at thelocal level regarding the reliability of the particular stream(is it ever running dry, how often etc ).

5.2 Majl-station minimum flow

By the end of the dry season data on the lowest recorded level(time and gauge height) at the permanent hydro-stations in thearea shall be collected. These levels shall be conv-erted to dis-charges using the available rating curves and the 1984 minimumflow is arrived at for the hydrostations. This flow is thencompared with the 10-y ear minimum at the sane station and theratio Is calculated.

Page 42: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

DISTRICT

MAKETE

ir

IT

1!

Il

fl

LUDEWA

if

iit

VILLAGE/GROUP

Klsinga,single,

Ihanga, single

Ukwama, single

Masisiwe, single

Mbalatse single

Igolwa, single

Ukange, single

Mawengi,single

Itundu Group

Madunda, single

Madilu, single

Lugarawa, single

Lullo Group

R£G.NO.

303

324

195

325

. 319

196

320

95

1 - 5 6

94

96

_ 108

1 - 5 8

HYDROZONE

3

4

4

3-4

3

4

i*

4

4

4

4

4

1

R E M A R K S

3 year plan

2 intakes

Total No. of Schemes

Page 43: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

RUVUMA REGION APPENDIX NO. 2 . 2 HYDRO MEASUREMENTS

DISTRICT

SONGEAit

M

II

Tt

M

It

II

tt

tt

tt

tt

tt

tt

tt

tf

It

Itn

•1

ii

it

MB ING Att

tt

M

it

tt

it

M

ti

it

M

VILLAGE/GROUP

Libango Group

Namabengo Group

Mpitimbi Group

MuhukurU Group

Magagura, single

Ngahokora, single

Matimira, single

Nakahuga, single

Peramino Group

Lipokela Group

Mbinganfaalule, single

Limamu, single

Lilondo, single

Hanga, single

Mlilayoyo, single

Mbimbi» single

Namangole Group

Kilangalanga, single

Ngvinde, singleMawama, singleNamatuhi, sinale

Njalamatata GroupLundo Group

Mango Group

Ngindo, single

Litembo, single

Ndumbi, single

Kindinba Chini/Juu

Linda,* single

Kihangi Mahuka

Silo, single

Wukiro, single

Mahenge, single

REG. NO.

R - 3

R - 6

R - 14

R -. 16

133

134

66

120

R - 8

R - 12

131

96

93

77

79

101

R - 10

271

'7°g141154

R - 11R - 25

R - 21

167

193

186

188

202

227

203

197

303

HDROLZONE

2

2 «•

2 - 3

2

2

2

2

3

. 3

3

3

2

4

3

3

2

2

2

2323

2

2

2

2

2

22

2

2

2

R E M A R K S

3 year plan

tt

tt

tt

tt

tt

2 intakes

3 year planif

tt

it

2 intakes

Page 44: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIII1IIII1II1IIIII

DISTRICT

M3INGAft

it

rt

i t

i t

it» •

ii

TUNDURUtt

«i

tt

ti

tt

tt

n

n -

VILLAGE/GROUP

Myangayanga Group

Miya« Group

Sepukila, single

Malindindo, single

Mikalanga, single

Mpepai, single

Mbamba Bay, GroupManipili Liwihi,singl<

Nanaanoo smaieMatemanga Group

Nandembo single

Machemba Group

Naluwal» Group

Atoani Group

Kindamba single

Misyaje single

Njenga single

Marumba Group

REG. NO"!'' ,

R - 19

R - 23

243

21"5

214 ,

244

R - 28: 225

162R - 31

40

R - 34

R - 35

R - 38

802

254

8

R - 40

.HYDROZONE

2

2

2

2

2

2

222

1

1

1

1

1

1

1

1

1

R E M A R K S

3 year p lan

tt

H

" 2 intakes

3 year plani?

#

Total No. of Schemes : 52

Page 45: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

APPENDIX 2.3 MEASUREMENTS

DISTRICT*

MBOZI

ILEJE

MBEYA

Rural

CHUNYA

RUNGWE

VILLAGE

Mbozi West, Group

Myovisi Group

Vwawa group

Katete, single

Ihanda, single

Isandula, single

Senjele, single

Hezva, single

Isoko, group

Itale, single

Sheyo single

Ilongo group

Mbuyuni group

Utengule group

Ikhoho, single

THfTfWV» _ tWTTllTO" • • • • • r 3 ™ w J.

Oyole group

Iwindi group

Isuto group

Itiiriba single

Rujewa group

rjumbi groupIsangala group

Mtanila group

Mgwala single

Mkwajuni single

rtijantoani single

Maleza single

Namlcukwe single

Nsigara group

rîasiabone, single

Mdaga group

Kanyelele group

REG.NO.

M - 34

M - 39

M - 42

503

435

481

380

373

M - 72

27

37

M - 7

M - 4

M - 6

146

M - 10

M - 13

M - 22

M - 26

106

M - 3

M - 8

M - 23

M - 30

514

9

11

855

14

M - 58

367

M - 45

M - 56

HXDROZONE

1

1

1

1

1

1

1

3

4

4

4

2

2

1

1

1

2

2

3

1

1

2

2-3

1

1

1

1

1

1

4

4

3

4

R E M A R K 3

2 Intakes

3 year plan

4 intakes

Hydrant

3 year plan

3 year plan

3 year plan

3 year plan.

3 year plan Hydrarn

Cunt'd...

Page 46: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

4BEYA REGION ( C o n t ' d . . . ) APPENDIX 2 . 3 HYDRO MEASUREMENTS

DISTRICT*

BENGWE

KXELA

" m T O T

Ngopyolo group

Lyenje single

Nditu single

Hgana group

Ngamanga group

Sinyanga group

REG.NO.

M - 65

•308

321

M - 70

M - 67

M - 68

HYDROZONE

4

4

4

4

4

4

R E M A R K S

TOTAL No. of Schemes: 39

Page 47: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

C C R K

2.

3.

LOW FLOW MEASUREMENT PROGRAMME '

1. VILLAGE

Name >•

Region

District

Single Scheme Planned •

Group Scheme Planned • Reference

SOURCE

Name

Spring Source

Stream

Measurement at

D

D

• Intake site as shown on Village Sketch

D Other site, describe location

••••»••*•**«*•*< >•*•••***•••***•*«•*••*•****••##***<

MEASUREMENT

Date of Visit 19 ...

Method Ï V-notch Q Bucket • oct-aeter

V-notchî Head measured in notch (h..) .•*.*...-....... cmLength top of weir to water level (left) (1.) cmLength top of weir to water level (right) (tj) cm

Bucket : Volume of bucket(V) litres

Time to fill bucket ( O seconds

Time to fill bucket (t«) seconds

Average time (t ) seconds

Ott-meter: Use Maji standard form to fill in and calculate discharge

Page 48: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

'RELIABILITY OF MEASUREMENT

V-notch : Is all water passing the V-notch or is it bypassed;

de scribe ..*•••..••••••r •

Has V-notch been placed horizontally describe any

deviation •.*••

Bucket : Is bucket well calibrated

Is all flowing water collected describe

OTT-Meter ; How many verticals in cross-section has been measured

•••••••••*•••••*>•>>••••••••>*•••>••••••••••••*••#••••

Which heights over river bed has been used for measuring

Q 0.6 Q 0.2/0.8

Describe Site:

Bed : O Rocky

• Stones, boulders

Q gravel

D sand

• silt/clay

Bank : D no vegetation

D some vegetation

• vegetation inteferes with measurement

Page 49: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

I1

5. SOURCE RELIABILITY ( INTERVIEW )• • ' • . -

« Is there a flow at the source all year round

Has anybody experienced the source being dry

IHow often does the source dry up v G twice a yearI

IIII

DD

aa,

yes

no

yes

no

D once a year

O once in two years

D less than once in 2 years

D many people

D only few

• How many people collects water from

* the stream Q the whole village

I• If the source runs dry where is water then collected

6. DISCHARGE CALCULATION

I V-notch : Calculate H • I,- (1« + Ij)/^ » .................. cm

From Table 1 find Q " m 1/s

Bucket : Calculate Q = V/t » 1/s

• Ott-mftter : Calculate Q from standardMaji calculation form

Field Team Leader Signature Date

Page 50: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

DEFINITION SKETCH

* ,

on.

NOTE : y MUST BE > 5 CM.

Page 51: IMPLEMENTATION OF WATER MASTER PLANS FOR IRINGA, RUVUMA AND MBEYA REGIONS · 2014. 3. 7. · i united republic of tanzania danish international development agencdanida y implementation

IIIIIIIIIIIIIIIIIIIII

COWIconsult(TANZANIA)

Consulting Engineers and Planners Ltd.

TABLE 1 !

Discharge in 1/s for 90° V-notch

(Head H in cm ) Q = 0.0 148 x H2'48

Headcm

1.02.0

.. 3.04.0

5.0•5

6.0.5

7.0.5

8.0.5

9.0.5

10.0•5

11.0.5

12.0.5

13.0.5

14.0.5

15.0 •.5

16.0.5

17.0.5

13.0.5

DischargeI/a

0.0150.082

0.220.46

0.80- 1.01

1.261.54

1.852.19

2.562.99

3.443.93

4.475.04

5.666.32.

7.027.77

8.569.40

10.311.2

12.213.3

14.315.5

16,717.9.

19.220.6

Head,cm

19.0 '.5

20.0.5

21.0.5

22.0.5

23.0.5

24.0•5

25.0•5

26.0.5

27.0.3 — -

28.0•5

29.0.5

30.0.5

31.0•5

32.0.5

33.0.5

34.0•5

Discharge1/s

21.923.4

24.926.5

28.129.8

•• 31.633.4

35.337.2

39.241.2

43.445.5

47.850.1

52.554.9

57.460.0

62.765.3

68.271.0

73.976.9

30.083.1

36.389.6

92.996.4


Recommended