+ All Categories
Home > Documents > Improving LIGO’s stability and sensitivity: commissioning examples

Improving LIGO’s stability and sensitivity: commissioning examples

Date post: 19-Mar-2016
Category:
Upload: ezhno
View: 24 times
Download: 0 times
Share this document with a friend
Description:
Improving LIGO’s stability and sensitivity: commissioning examples. August 24, 2004 Michael Landry LIGO Hanford Observatory. Recent commissioning efforts. Reliability & Stability Seismic retrofit at LLO: Hydraulic External Pre-Isolator (HEPI) Sensitivity - PowerPoint PPT Presentation
20
G040423-00-D Improving LIGO’s stability and sensitivity: commissioning examples August 24, 2004 Michael Landry LIGO Hanford Observatory
Transcript
Page 1: Improving LIGO’s stability and sensitivity: commissioning examples

G040423-00-D

Improving LIGO’s stability and sensitivity: commissioning examples

August 24, 2004Michael Landry

LIGO Hanford Observatory

Page 2: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 2G040423-00-D

Recent commissioning efforts

Reliability & Stability Seismic retrofit at LLO: Hydraulic External Pre-Isolator

(HEPI) Sensitivity

Operate at high power: achieve designed optical gain Laser power increase Thermal compensation system (TCS)

Page 3: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 3G040423-00-D

Daily Variability of Seismic Noise

PRE-ISOLATOR

REQUIREMENT

(95% of the time)

Livingston

Hanford

RMS motion in 1-3 Hz band

Dis

plac

emen

t (m

)

daynight

Page 4: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 4G040423-00-D

Hydraulic External Pre-Isolation:HEPI at LLO

Page 5: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 5G040423-00-D

Page 6: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 6G040423-00-D

X-arm length disturbance on a noisy afternoon

Page 7: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 7G040423-00-D

HEPI summary

Remaining tasks Complete commissioning of final six chambers Sensor and whitening filter optimization Scripting, safeties, man-machine interface software

Summary All hardware installed Crucial one-arm test completed successfully LIGO will soon have two sites capable of night and day operation

with reasonable duty cycle Pre-Isolator is first Advanced LIGO subsystem shown to work at

required specification at observatory setting

Page 8: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 8G040423-00-D

LHO 4k noise history

(science design)

Page 9: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 9G040423-00-D

S1 Noise Component Analysis, LLO 4k

G020482-00-D 5Rana Adhikari noise analysis

S1

Page 10: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 10G040423-00-D

Estimated Noise Limits for S2(as planned in October 2002)

S1S2(expected)

Page 11: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 11G040423-00-D

LHO 4k noise history

S1S2S3

(science design)

Page 12: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 12G040423-00-D

What is shot noise?

Laser light comes in discrete packets of photons Stastical fluctuation in detected photons appears as

length noise in an interferometer; Poisson statistics of light arrival times at the gravity-wave port photodiodes

Strain noise decreases with the square-root of laser power

Page 13: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 13G040423-00-D

What can we do about shot noise?

Increase laser power Lasers refurbishing, now running at ~8W

Approximately 4W incident on interferometers Input optics-train modified and aligned for better throughput Additional photodiodes added to gravity-wave port Additional power produces “thermal lensing” in interferometer

optics necessitates Thermal Compensation System (TCS)

Ensure other high-frequency noise sources are reduced accordingly E.g. “oscillator phase noise”

Page 14: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 14G040423-00-D

Thermal CompensationSystem (TCS)

Over-heat Correction

Inhomogeneous Correction

Under-heat Correction

CO2 Laser

?

ZnSe Viewport Over-heat pattern

Inner radius = 4cm Outer radius =11cm

Require TCS to match input beam to the mode supported in arm cavities

All systems installed

ITM

Page 15: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 15G040423-00-D

Two CO2 lasers installed on H1

To input test mass (ITM) High Reflectivity surface

Page 16: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 16G040423-00-D

TCS on the power recycled Michelson: beam images at gravity-wave port

No Heating 30 mW 60 mW 90 mW

120 mW 150 mW 180 mW Input beam

Best match

Page 17: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 17G040423-00-D

High-frequency noise improvements

Recent high-frequency noise improvement by factor of 2-4

Thermal compensation required to support this gain in sensitivity (otherwise thermal lensing would limit such gains)

Page 18: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 18G040423-00-D

Parallel efforts

Many other key commissioning efforts underway, including Control of angular degrees-of-freedom (d.o.f.)

All 14 angular d.o.f. controlled on Hanford 4km interferometer Input pointing into the interferometers controlled

Acoustic mitigation Reducing control noise from other feedback systems in the

interferometers

Page 19: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 19G040423-00-D

2Q

Time Line

19993Q 4Q

Now

First Science Data

Inauguration

20001Q 2Q 3Q 4Q

20011Q 2Q 3Q 4Q

20021Q 2Q 3Q 4Q

20031Q 3Q 4Q

E1Engineering

E2 E3 E4 E5 E6E7 E8 E9

S1Science

S2 S3

First Lock Full Lock all IFO

Runs

2Q1Q 3Q 4Q

2004

S4(expected)

Page 20: Improving LIGO’s stability and sensitivity: commissioning examples

LIGO I 20G040423-00-D

Looking ahead Livingston 4km interferometer:

Finish Hydraulic external pre-Isolator (HEPI) Get good spectrum back Implement improvements from LHO 4km interferometer

Hanford 4km interferometer: High power operations “output mode cleaner” test version 2 New frequency and intensity stablization, “common mode” boards, non-

resonant sideband photodiodes on interferometer reflected output port Optimize dewhitening for new low-noise digital-to-analog converters

Hanford 2km interferometer: Implement improvements from the Hanford 4km interferometer

Expect 4-6 week science run beginning Jan 2005 On track to reach design sensitivity and begin an extended

science run summer 2005


Recommended