Improving Worker Safety
Working in Bangladesh After
Rana Plaza
Aidan Madden 11th November 2016 ARUP
Rana Plaza
Collapse on 24th April 2013 1129 deaths
Asia
6
Rana Plaza
9
courts
Report, Review & Briefing
Colour Coded Overall Assessment
Red Close factory building (or significant parts) immediately.
Amber Immediate Action required locally.
Yellow Action required within 6 weeks.
Green Action required within 6 months and longer term actions
(maintenance).
Tafop Apparels Ltd. Block-A, Plot 1, 2, 3A, BSCIC I/A, Sagorika Road, Chittagong
(22.3560E, 91.7714N) 08 June 2014
Structural Inspection Report
Observations & Actions Authors:
Bernard FitzPatrick/Billy Allen
Reviewed by: John Flaherty Approved by: Aidan Madden
Category Amber Revision: Issue 01 Date: 17th June 2014
DEA
Action in 6
Months:
[PERCENT
AGE]
Action in 6
Weeks:
[PERCENT
AGE]
Immediate
Actions:
46%
Closure: 1%