+ All Categories
Home > Documents > In-Situ MVA of CO Sequestration Using Smart Field Technology Library/events/2013/carbon...

In-Situ MVA of CO Sequestration Using Smart Field Technology Library/events/2013/carbon...

Date post: 03-Jul-2018
Category:
Upload: dinhxuyen
View: 212 times
Download: 0 times
Share this document with a friend
43
In-Situ MVA of CO 2 Sequestration Using Smart Field Technology FE - 0001163 Shahab D. Mohaghegh Petroleum Engineering & Analytics Research Lab (PEARL) West Virginia University U.S. Department of Energy National Energy Technology Laboratory Carbon Storage R&D Project Review Meeting Developing the Technologies and Infrastructure for CCS August 20-22, 2013
Transcript

In-Situ MVA of CO2 Sequestration Using Smart

Field Technology FE - 0001163

Shahab D. Mohaghegh Petroleum Engineering & Analytics Research Lab (PEARL)

West Virginia University U.S. Department of Energy

National Energy Technology Laboratory Carbon Storage R&D Project Review Meeting

Developing the Technologies and Infrastructure for CCS August 20-22, 2013

2

Presentation Outline

• Introduction • Reservoir Simulation Model • Intelligent Leakage Detection System (ILDS) • Accomplishments • Summary

Objective • Develop an in-situ CO2 leak detection technology based on

the concept of Smart Fields. – Using real-time pressure data from permanent downhole gauges to

estimate the location and the rate of CO2 leakage.

CO2 Leakage(X,Y,Q) Artificial

Intelligence & Data Mining

Industrial Advisory Committee (IAC)

• Project goes through continuous peer-review by an Industrial Review Committee.

• Meetings:

– November 6th 2009 : • Conference call • Site selection criteria

– November 17th 2009: • A meeting during the Regional Carbon Sequestration Partnership Meeting in Pittsburgh • Selection of a suitable CO2 sequestration site

– November 18th 2011: • Reporting the modeling process to IAC

– February 16th 2012: • Reporting the modeling process to NETL/DOE

– April 18th 2013: • Reporting project’s progress to NETL/DOE

Name Affiliation Neeraj Gupta Battelle Dwight Peters Schlumberger George Koperna ARI Grant Bromhal DOE-NETL Richard Winschel CONSOL

Background

Citronelle

Injected Fluid: Carbone Dioxide Depth of Injection Well:11,800ft Depths & Geological Name of Interval: 9,400-10500 ft (Paluxy Formation)

Injection Volumes: 500 ton/day(9.48 Bcf/day) Injection Duration: 3 Years(2012-2015)

Geological Model 3 Cross Sections Sand Layers-D-9-7 Grid Thickness

Porosity from 40 Well Logs Permeability Realizations

Reservoir Simulation Model

7

17 Layers( 10 Injection Layers) 51 Simulation Layers Porosity Distribution from 40 Well Logs Permeability Distribution: Conductive 1,147,500 Grid Blocks

Plume extension: 500 years after injection ends.

Plume extension is shown

only for the blocks with

CO2

Impact of Trapping Mechanism

8

Srg = 0.30 Srg = 0.29

Srg = 0.26

Srg = 0.11

Residually Trapped CO2 vs. Time

Impact of Trapping Mechanism

9

Dissolved CO2 vs. Time

Srg = 0.30

Srg = 0.29

Srg = 0.26

Srg = 0.11

Impact of Trapping Mechanism

10

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Cardium #1 Cardium #2 VikingSandstone

Nisku #2

Mineral Trapping 0.000% 0.000% 0.000% 0.000%Structural Trapping 17.101% 55.176% 33.482% 80.237%Solubility trapping 28.250% 10.238% 28.064% 9.254%Resiudual traping 54.649% 34.586% 38.455% 10.510%

Con

trib

utio

n Pe

rcen

tage

, %

Trapping Mechanism Contribution to the Storage

Process (After 500 years)

Srg = 0.30 Srg = 0.11

Total CO2 Injected (MMCF) 15,045 Total CO2 Injected (TONS) 550,596

Seal Quality

11

Realization Thickness (ft) Permeability (Darcy)

1 150 10^-3 2 150 10^-5 3 150 10^-7 4 200 10^-3 5 200 10^-5 6 200 10^-7 7 250 10^-3 8 250 10^-5 9 250 10^-7

150 ft < h < 250 ft 10-3

darcy < k < 10-7 darcy

Basal Shale

Danztler Sand

Two additional geological layers where included in the model corresponding to the Washita-Fredericksburg interval (on top of the Paluxy formation):

• Basal Shale (Seal) • Danztler Sand (Aquifer)

Seal Quality

12

Grid refinement of the basal shale simulation layers: Grid was refined vertically into 75 to 125 simulation layers to generate grid-blocks with thickness of 2 ft.

Seal Quality

13

0

50

100

150

200

250

1 2 3 4 5 6 7 8 9

Dep

th o

f inv

asio

n (ft

)

Realizations

Depth of invasion of CO2 within the Basal Shale (all realizations)

Realization Thickness (ft) Permeability (Darcy)

1 150 10^-3 2 150 10^-5 3 150 10^-7 4 200 10^-3 5 200 10^-5 6 200 10^-7 7 250 10^-3 8 250 10^-5 9 250 10^-7

150 ft < h < 250 ft 10-3

darcy < k < 10-7 darcy

Seal Quality

14

Conductive Seal 150 md-ft< k*h< 250 md-ft

Tight Seal 1.5 md-ft< k*h< 2.5 md-ft

Very Tight Seal 0.015 md-ft< k*h< 0.025 md-ft

Seal Quality

15

Pressure gain – all scenarios Seal Conductivity

Scenario Permeability of the Confining Unit (md)

K*h range of the confining unit (md-ft)

Conductive 1 150 250 Tight 0.01 1.5 2.5

Very Tight 0.0001 0.015 0.025

0

20

40

60

80

100

120

140

ConductiveTight

Very Tight

Ave

rage

Pre

ssur

e ga

in (p

si)

Scenario

Pressure Gain vs Scenario

0.43 % and 3.18% of the initial average reservoir

pressure

Pressure Gain = Avg. P @ 500 years – Initial Avg. P

D--7

1,259,000 1,261,000 1,263,000 1,265,000 1,267,000 1,269,000 1,271,000 1,273,000

1,259,000 1,261,000 1,263,000 1,265,000 1,267,000 1,269,000 1,271,000 1,273,000

11,271,00011,273,000

11,275,00011,277,000

11,279,00011,281,000

11,283,000

11,2

73,0

0011

,275

,000

11,2

77,0

0011

,279

,000

11,2

81,0

0011

,283

,000

0.00 0.25 0.50 0.75 1.00

0.00 0.50 1.00 km

3.15 miles

3.15 miles

Impact of Boundary Conditions

16

Pressure Behavior in Observation Well(D-9-8)

1

2

3

1 2 3 4

4

Post Injection Site Care (PISC)

17

Yearly Pressure Difference distribution Threshold Verification

1 ye

ar p

ost-

inje

ctio

n

2 ye

ar p

ost-

inje

ctio

n

Sensitivity Analysis

18

Reservoir Pressure @ Observation Well

• Kv/Kh • Maximum Residual

Gas Saturation • Brine Density • Brine Compressibility • Boundary Condition

Permeability Relative permeability

CO2 Plume Extension

History Matching

19

D-4-13 and/or D-4-14In-zone monitoringAbove-zone monitoringFluid sampling

D-9-11Neutron Logging

Primary Injector (D-9-7#2)Injection surveysPressureSeismicGroundwater

Backup Injector(D-9-9#2)Neutron loggingSeismicGroundwater

Characterization Well (D-9-8#2)Neutron loggingPressureFluid samplingSeismicDistributed Temperature

Model Plume Extent

Injection Data PDG Data

4365

4375

4385

4395

4405

4415

4425

4435

4445

4455

4465

8/17/2012 9/6/2012 9/26/2012 10/16/2012 11/5/2012 11/25/2012 12/15/2012 1/4/2013 1/24/2013 2/13/2013

Pres

sure

Psi

Date

PDG(5109) PDG(5108)

History Matching

20

17 Layers( 10 Injection Layers) 51 Simulation Layers Porosity Distribution from 40 Well Logs Permeability: 460md 125*125*51 (800000) Grid Blocks (∆x = ∆y =133.3 ft) Relative Perm: Mississippi Test site (sg=7.5%)

Operational Constraints (actual rate +Max 6300 psi) Ρbrine = 62 lb/ft3 Cbrine = 3x10-6 (1/psi) at 14.7 psi Preference = 4393psi at 4015 ft. Kv = 0.1Kh

History Matching

21

Matching Parameter Absolute Permeability Brine Density Reference Pressure Transmissibility Multiplier Reservoir Boundary Relative Permeability

CO2 Leakage Modeling

22

CO2 Leakage Modeling

23

CO2 Leakage Modeling

24

00.10.20.30.40.50.60.70.80.9

0 500 1000 1500 2000 2500

∆P(P

si)

Time(hour)

Leaking Well(D-9-2) Leakage rate = 30MSC/day

Observation Well

Pressure Behavior @ Observation Well

AI Model Development

25

00.10.20.30.40.50.60.70.80.9

0 500 1000 1500 2000 2500

∆P(

Psi)

Time(hour)

-Leakage Rate -Leakage Location(X,Y)

Descriptive Statistics Mean 0.091 Standard Error 0.0047 Median 0.092 Mode 0 Standard Deviation 0.062 Sample Variance 0.0038 Kurtosis -1.31 Skewness 0.029 Range 0.195 Minimum 0 Maximum 0.195 Sum 15.38 Count 168

Data Summarization

AI Model Development

26

Leakage Rate

Mcf/day

15

20

25

30

35

40

45

50

55

60

65

70

75

80

85

90

95

100

105

110

Leakage Location(X) Leakage Location(Y)

Leak

age

Rat

e

Hou

rly

Pres

sure

on

e w

eek

afte

r Lea

kage

(168

dat

a po

ints

fo

r eac

h le

akag

e ra

te)

Leakage Locations

Output Input

Validation – Blind Runs

27

Leakage Rate

Mcf/day 26 52

88

11276000

11276500

11277000

11277500

11278000

11278500

11279000

11279500

1268500 1269000 1269500 1270000 1270500

Lati

tude

(Y)

Longtitude(X)

Actual Leakage Location

Neural Network PredictionLeakage

Location(X) Actual

Leakage Location(X)

N.N

Leakage Location(Y)

Actual

Leakage Location(X)

N.N Run 1 1268902.53 1268903.05 11277566.74 11277569.97 2 1268902.53 1268902.78 11277566.74 11277565.13 3 1268902.53 1268902.55 11277566.74 11277567.57 4 1270359.37 1270359.03 11279158.24 11279157.46 5 1270359.37 1270359.11 11279158.24 11279157.51 6 1270359.37 1270359.17 11279158.24 11279157.44 7 1270184.29 1270184.53 11276221.98 11276223.47 8 1270184.29 1270185.16 11276221.98 11276224.14 9 1270184.29 1270183.81 11276221.98 11276222.66

Nine new leakage Scenarios

Validation – Blind Runs

28

0

20

40

60

80

100

120

1 2 3 4 5 6 7 8 9

26

52

88

41

77

103

33

61

94

24.8

51.5

88.6

43.5

78.0

101.5

33.8

62.3

22.3Le

ak

ag

e R

ate

(MS

cf/

da

y)

Run

Actual Rate ILDS Prediction

ILDS Leakage Rate Prediction

PDGs at Citronelle Site

29

D-4-13 and/or D-4-14In-zone monitoringAbove-zone monitoringFluid sampling

D-9-11Neutron Logging

Primary Injector (D-9-7#2)Injection surveysPressureSeismicGroundwater

Backup Injector(D-9-9#2)Neutron loggingSeismicGroundwater

Characterization Well (D-9-8#2)Neutron loggingPressureFluid samplingSeismicDistributed Temperature

Model Plume Extent

Ref: ARI

Noise Analysis - PDGs

30

𝑁𝑁𝑁𝑁 = 𝑃𝑃𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 − 𝑃𝑃𝑓𝑓𝑓𝑓𝑎𝑎𝑎𝑎𝑓𝑓𝑓𝑓 → 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 𝐿𝐿𝑁𝑁𝐿𝐿𝑁𝑁𝐿𝐿 =1

𝑛𝑛 − 1�𝑁𝑁𝑓𝑓2𝑛𝑛

𝑓𝑓=1

1/2

Noise Level = 0.08 Psi Distribution = Normal (Gaussian)

De-noising Process

31

Training with De-Noised Data

32

Leakage Location(X) Leakage Location(Y)

Leakage Rate

33

0

0.2

0.4

0.6

0.8

1

0 1000 2000 3000

∆P(

Psi)

Time(hour)

0

0.2

0.4

0.6

0.8

1

0 500 1000 1500 2000 2500

∆P

(Psi

)

Time(hour)

De-noising

Summarization

Descriptive Statistics Mean 0.091532 Kurtosis -1.31344 Standard Error 0.004755 Skewness 0.029047 Median 0.091797 Range 0.194824 Mode 0 Minimum 0 Standard Deviation 0.061636 Maximum 0.194824

Sample Variance 0.003799 Sum 15.37744

Leakage Location

Leakage Rate

Noisy Pressure Data

The Interface Development

35

Accomplishments to Date

• Geological model was developed. • Reservoir Simulation Model was developed. • Impact of Relative Perms of Trapping Mechanism was

determined • Seal Quality and Integrity was studied • Sensitivity analysis was performed • Reservoir Simulation Model was history matched • Intelligent Leakage Detection System (ILDS) was designed

and developed. – Initial Design – Validated for Simple Reservoir System – Validated for Simple Leakage System

• High Frequency data was cleansed and summarized • ILDS interface was developed

Summary

• Key Findings: - Location and amount of CO2 leakage can be detected and quantified, rather quickly, using continuous monitoring of the reservoir pressure. - Pattern recognition capabilities of Artificial Intelligence and Data Mining may be used as a powerful deconvolution tool.

– Lessons Learned(proof of concept): - Development of an Intelligent Leakage Detection System (ILDS) is initiated for detection and quantification of CO2 leakage.

– Future Plans: - Increase the robustness of ILDS by: + Using history matched model + Examining impact of different boundary conditions, + Including more sources of leakage(like Cap rock Leakage) + Examining detection of simultaneous multiple leakages.

Bibliography List peer reviewed publications generated from

project per the format of the examples below • Journal, one author:

– Gaus, I., 2010, Role and impact of CO2-rock interactions during CO2 storage in sedimentary rocks: International Journal of Greenhouse Gas Control, v. 4, p. 73-89, available at: XXXXXXX.com.

• Journal, multiple authors: – MacQuarrie, K., and Mayer, K.U., 2005, Reactive transport modeling in fractured

rock: A state-of-the-science review. Earth Science Reviews, v. 72, p. 189-227, available at: XXXXXXX.com.

• Publication: – Bethke, C.M., 1996, Geochemical reaction modeling, concepts and applications: New

York, Oxford University Press, 397 p.

38

Appendix Benefit to the Program

• Program goals : – Develop technologies to demonstrate that 99 percent

of injected CO2 remains in the injection zones.

• Benefits statement: – This project is developing the next generation of

intelligent software that takes maximum advantage of the data collected using “Smart Fields” technology to continuously and autonomously monitor and verify CO2 sequestration in geologic formations. This technology will accommodate in-situ detection and quantification of CO2 leakage in the reservoir.

Appendix Project Overview:

Goals and Objectives • Goals and objectives in the Statement of Project:

– This project proposes developing an in-situ CO2 Monitoring and Verification technology based on the concept of “Smart Fields”. This technology will identify the approximate location and amount of the CO2 leakage in the reservoir in a timely manner so action can be taken and ensure that 99 percent of the injected CO2 remains in the injection zone.

– Success Criteria and Decision Points:

– There are a total of 10 milestones (and 4 sub-Milestone) in this project. – Decision points come at the end of quarters 4 (Milestone 2.2) and 15

(Milestone 6). At the decision points a “go” or “no go” decision on the continuation of the project is made based on the accomplishments of the project up to that point.

Appendix Organization Chart

Main Contributors (Research & Development): Alireza Haghighat, Alireza Shahkarami, Daniel Moreno, Najmeh Borzoui, and Yasaman Khazaeni. Full Time Research Associate: Vida Gholami,

Appendix Gantt Chart

Q1 Q2 Q3 Q4 Q5 Q6 Q7 Q8 Q9 Q10 Q11 Q12 Q13 Q14 Q15 Q16Program Management Task OneSite Selection Task Two

2.12.22.3

Base Model Development Task Three3.13.23.33.43.53.6

Sensitivity Analysis Task Four4.14.24.3

CO2 Leakage Modeling Task Five5.15.25.35.4

High Frequency Data Handling Task Six6.16.26.3

Pattern Recognition Analysis Task Seven7.17.27.37.47.57.6

Application to Homogeneous Reservoir Task Eight

History Matching Task Nine9.19.29.3

Application to Heterogeneous Reservoir Task Ten

Interface Development Task Eleven

Budjet Period 1 Budget Period 2Task Title

Project Tasks

Task 1: Program Management and Reporting Task 2: Site Selection Subtask 2.1: Establishing the Industrial Review Committee Subtask 2.2: Developing Site Selection Criteria Task 3: Reservoir Data Collection and Base Reservoir Model Construction Subtask 3.1: Selection of Reservoir Modeling Software

Task 2: Site Selection Subtask 2.3: Selecting a Site Task 3: Reservoir Data Collection and Base Reservoir Model Construction Subtask 3.2: Collect data

Task 3: Reservoir Data Collection and Base Reservoir Model Construction Subtask 3.3: Use Collected Data to Develop a Geological Model Subtask 3.4: Assessing the need for Up-scaling the Geological Model

Task 3: Reservoir Data Collection and Base Reservoir Model Construction Subtask 3.5: Import the Geological Model into the Flow Model Subtask 3.6: Flow Model Testing

Task 4: Sensitivity Analysis of the Reservoir Simulation Model Subtask 4.1: Building multiple heterogeneous porosity maps based on logs from existing wells in the formation. Subtask 4.2: Defining different Porosity Permeability correlations and building different geological realizations of the reservoir. Subtask 4.3: Comparing different realizations of the reservoir and ranking them based on injectivity.

Task 5: Simulating CO2 Leakage and Realistic Downhole Pressure Data Subtask 5.1: Simulation of CO2 Leakage

August 22, 2013

Task 5: Simulating CO2 Leakage and Realistic Downhole Pressure Data Subtask 5.2:High Frequency Data Streams Generation Task 6: Developing Techniques for Handling High Frequency Data Subtask 6.1: Processing of High Frequency Data Streams – Data Cleansing

Task 5: Simulating CO2 Leakage and Realistic Downhole Pressure Data Subtask 5.3:Transmission of Data from Modeled Pressure Gauges Task 7: Performing Pattern Recognition Analysis Subtask 7.1: Key Performance Indicators Using Fuzzy Set Theory

Task 5: Simulating CO2 Leakage and Realistic Downhole Pressure Data Subtask 5.4:Emulation of Field Data Using Data Stream Distortion Task 7: Performing Pattern Recognition Analysis Subtask 7.2: Data Partitioning for Neural Network Modeling

Task 6: Developing Techniques for Handling High Frequency Data Subtask 6.2: Processing of High Frequency Data Streams – Data Summarization

Task 6: Developing Techniques for Handling High Frequency Data

Subtask 6.3: Preparation of High Frequency Data for Pattern Recognition

Task 7: Performing Pattern Recognition Analysis

Subtask 7.4: Subtask 7.3: Neural Network Architecture Design

Task 8: Testing and Validation of CO2 Leak Detection in a Homogeneous Reservoir

Task 7: Performing Pattern Recognition Analysis

Subtask 7.4: Neural Network Training and Calibration Subtask 7.5: Neural Network Validation Subtask 7.6: Neural Network Model Analysis

Task 9: Integrating CO2 Injection and History Matching the Model

Subtask 9.2: In Situ CO2 Behavior Validation Subtask 9.3: Model Integrity Verification

Milestone Timelines Milestone log

Title Description Related task or subtask Completion Date

Budget Period 1

Milestone 1.1 Advisory Board Meeting Advisory board should get together for a meeting (or conference call) to select a site for the project. Subtask 2.1 End of First Quarter

Milestone 1.2 Site Selection A site must be selected for the project. Subtask 2.2, 2.3 End of Second Quarter

Milestone 2.1 Data collection Completion of geologic and production data collection Subtask 3.2 End of Third Quarter

Milestone 2.2 Completion of geological model Completion of geologic/geo-cellular model Subtask 3.3 End of Fourth Quarter

Milestone 2.3 Completion of the base model Completion and testing the base flow model Subtask 3.6 End of Fifth Quarter

Milestone 3 Sensitivity Analysis Completion of the sensitivity analysis on the reservoir model Subtask 4.3 End of Sixth Quarter

Budget Period 2 Milestone 4.1 CO2 Leakage Modeling Model realistic CO2 leakage from the formation Subtask 5.1 End of Eighth Quarter

Milestone 4.2 Downhole pressure modeling Model realistic real-time downhole pressure measurements. Subtask 5.2, 5.3, 5.4 End of Eleventh Quarter

Milestone 5 Handling High Frequency Data Developing techniques for handling high frequency data Subtask 6.1, 6.2, 6.3 End of Thirteenth Quarter

Milestone 6 Pattern recognition Completing pattern recognition analysis Subtask 7.1, 7.2, 7.3, 7.4, 7.5, 7.6 End of Fifteenth Quarter

Milestone 7 Application to Homogeneous system Completing of analysis and application to Homogeneous system Task 8 End of Fifteenth Quarter

Milestone 8 CO2 Injection Modeling Completion of modeling the CO2 injection. Subtask 9.3 End of Fifteenth Quarter

Milestone 9 Application to Heterogeneous system Completing of analysis and application to Heterogeneous system Task 10 End of Sixteenth Quarter

Milestone 10 Build Program Interface Completion of Software Package Task 11 End of Sixteenth Quarter


Recommended