1
IN THE HIGH COURT OF KARNTAKA AT BANGALORE
DATED THIS THE 5th DAY OF NOVEMBER 2012
PRESENT
THE HON’BLE MR.VIKRAMAJIT SEN, CHIEF JUSTICE
AND
THE HON’BLE MRS. JUSTICE B.V. NAGARATHNA
WRIT APPEAL NO.3932/2004 (GM-MMS)
BETWEEN:
T.R. Narayanaswamy, S/o. T.K. Ramanatha Iyer, Aged about 66 years, No.226, C.V. Raman Avenue, Rajmahal Vilas,
Bangalore. : Appellant (By Shri. H. Srinivas Rao, Advocate) AND: 1. The State of Karnataka,
By its Secretary –II, Department of Commerce and Industries, M.S. Building, K.R. Circle, Bangalore.
2. The Director,
Department of Mines and Geology, Khanija Bhavan, Race Course Road, Bangalore. : Respondents
(By Shri. R.G. Kolle, Addl., Government Advocate for R-1 & 2)
R
2
This Writ Appeal is filed under Section-4 of the Karnataka
High Court Act praying to set aside the order passed in Writ
Petition No.117/2003 dated 23rd July 2004 and to direct the
respondent No.1 to consider the Appellant’s application dated
12.02.2002 for renewal, read with the direction of this Court in
W.P.No.42001/1995.
This Writ Appeal having been heard and reserved for
pronouncement of judgment, this day, the Chief Justice
pronounced the following :
JUDGMENT
Vikramajit Sen, C.J.
In this Appeal the Appellant has called in question the legal
correctness of the decision dated 23.07.2004 of the learned
Single Judge in Writ Petition No.117/2003. The facts germane
to the controversy are not in dispute. On 15.03.1982 a Quarry
Lease pertaining to Survey No.421 of Maralabbe Kuppe village of
Kanakapura taluk, Bangalore Rural District, Karnataka,
admeasuring 54 acres came to be granted in favour of the
Petitioner/Appellant for a period of ten years. It was renewed
thereafter for another tranche of ten years. Accordingly, the
tenure of the lease was to terminate by efflux of time on
15.03.2002. The Appellant, as per Rule 9(2) of the Karnataka
3
Minor Mineral Concession Rules, 1994 [hereafter referred to as
‘KMMCR 1994’] applied within the prescribed time, on
12.02.2002, for the renewal thereof. Rule 9 (2A) of KMMCR
1994, inserted with effect from 17.07.1997, ordains that where a
renewal application has been filed within the prescribed time the
lease shall be deemed to have been extended till such time as the
Government passes the requisite Orders; there is no automatic
renewal of the subject Lease postulated in the Rules.
Eventually on 21.11.2002 the Respondents accorded a renewal of
the lease, however restricting it to an extent of 10 acres only as
against the erstwhile 54 acres. This decision was predicated on
Rule 15 of the KMMCR 1994 on the ground that the Appellant
did not possess an “100% export oriented granite cutting and
polishing small scale industrial unit” as contemplated under
Rule 15 of the KMMCR 1994. It was this Order which came to
be impugned by way of the subject Writ Petition. The impugned
Order categorically claims support for the view of another learned
Judge taken in W.P. No.42001/1995 which was also filed by the
petitioner herein; it was allowed on 28.08.2000, remitting the
4
matter back for reconsideration in accordance with law viz., by
means of a reasoned and speaking order.
2. Principally two arguments have been raised before us.
Firstly, that it is The Granite Conservation and Development
Rules, 1999 [‘GCDR 1999’ for brevity] (a Parliamentary as also be
a later enactment renders the KMMCR 1994 ineffectual).
Secondly, that the factual matrix of the case in hand concerned
the 'renewal' in contradistinction to the 'grant' of a quarry lease
and therefore, the terms of the original lease particularly with
reference to the extent of land could not have been altered by the
respondents.
3. The relevant Rules of the KMMCR 1994 are
reproduced for facility of reference:
“9. Application for grant or renewal of a
quarrying lease –
x x x x
9(2) - An application for renewal of a
quarrying lease to quarry specified minor
mineral belonging to the State Government
which has not been notified under Rule 8-B
shall be in FORM-R and shall be made to the
5
Director at least twelve months before the expiry
of the lease. The application shall be
accompanied by a fee of rupees two thousand in
the form of a treasury challan under the
specified Head of account together with the
difference of amount of security deposit, if any,
to be paid by the lessee at the prevailing rates
in the form of treasury challan and a certificate
issued by the Competent Authority for having
cleared the arrears, if any, in respect of any
lease held by him as on the date of making
application for renewal..
(2A) If an application for renewal of a
quarrying lease made within the time referred to
in sub-rule (2) is not disposed of by the State
Government before the date of expiry of the
lease, the period of that lease shall be deemed
to have been extended by a further period till
the State Government passes orders thereon.
x x x x
11. Grant or renewal of quarrying lease:-
(1) There shall be a Committee to make
recommendations for grant or renewal of a
quarrying lease under this rule. …...
xxx
6
(3) On receipt of applications from the
Director, the committee shall having regard to
the priorities under rule 12, and the guidelines
issued by the State Government, if any,
consider such applications and make
recommendations to the Government.
Provided that the Committee shall not
consider such applications in respect of any
area, which is notified under rule 8B after the
receipt of the application on or before the date
of consideration and all such application shall
be liable to be return to the applicants and
security deposit and fee paid, if any, may be
refunded.
xxx
12. Priorities:- (1) Selection from amongst the
applicants for grant of quarrying lease under
this chapter shall normally be made in the
following order of preference, namely:-
(i) a Corporation or undertaking owned or
controlled by the State or Central
Government and Joint Sector projects with
such Government Corporations or
Undertakings;
7
(ii) persons who have already established
hundred per cent export oriented units for
cutting and polishing of granites in the
State;
(iii) Persons who have already established a
small scale Industrial unit for cutting and
polishing of granites in the State;
(iv) Persons who hold a valid licence for
establishment of a granite cutting and
polishing unit within the State for the
purpose of hundred per cent export and
persons who hold a permanent Registration
Certificate for establishment of a Small
Scale Industrial Unit in the State;
(v) a society registered under the Karnataka
Co-operative Societies Act,1959, and the
members of which belong to the Scheduled
Castes & Scheduled Tribes;
(vi) a Society registered under the Karnataka
Co-operative Societies Act,1959, and the
members of which belong to economically
weaker sections of the Society and who are
also stone quarry workers by tradition;
(vii) all others:
8
(2) In case of applicants falling under clause
(iv) of this rule 12 who require specified minor
mineral for their proposed industry they shall
set up industry in accordance with their
industrial program within a period of twenty
four months from the date of execution of lease
deed and shall keep the Director informed of the
progress made every six months from the date
of execution of lease deed. On setting up of
industry the lessees shall inform the fact in
writing to the Director failing which the lease
shall be deemed to have been terminated on the
expiry of the said period of twenty four months.
Where the lessees are unable to set up industry
within the said period for reasons beyond their
control they may submit before the expiry of the
said period an application to the Director
explaining the reasons for the same together
with affidavits. The Director shall forward such
applications to the State Government and it
may on being satisfied that such failure in
setting up the industry was due to reasons
beyond the control of the lessee, extend the
period of such lease by one more year either
prospectively or retrospectively.
x x x
9
14. Disposal of application for grant or renewal
of lease:-
(1) Application for grant or renewal of lease
shall be disposed-
(i) in the case of an existing industry
within a period of One hundred and
eighty days from the date of receipt of
application failing which the
applicants shall be informed of the
reasons for delay within fifteen days
after the expiry of the disposal
period.
(ii) in all other cases within a period of
four months from the date of receipt
of applications failing which the
applicants shall be informed of the
delay within fifteen days after the
expiry of the disposal period.
15. Maximum area of Quarrying lease to be
granted:-
(1) Total area of one or more quarry leases to
quarry specified minor minerals shall not
exceed;
(i) fifty acres in case of an existing hundred
percent export oriented granite cutting and
10
polishing unit in the State, falling under
clause (ii) of sub-rule (1) of rule of 12;
(ii) forty acres in case of other granite cutting
and polishing units in the State, falling
under clause (iii) (iv) and (v) of Sub-rule (1)
of rule 12;
(iii) ten acres in all other cases, falling under
clause (iv),(v),(vi) and (vii) of sub-rule (1) of
rule 12.
xxx xxx
x x x
57. Application of these rules for renewal:-
Where a quarrying lease or any other right for
quarrying a minor mineral has been granted
before the commencement of these rules is
renewed after such commencement, these rules
shall apply in relation to such renewal of a
quarrying lease or licence granted after such
commencement”.
4. The GCDR 1999 has been formulated by the Central
Government in exercise of the powers conferred by Section 18 of
the MMDR Act 1957. In the event of any irreconcilable
differences between the two pandects of Rules, the Central Rules
which are also later in time would prevail. There can be no cavil
however that subsequent legislation or formulations of Rules and
11
Regulations will not automatically repeal or annul all that is then
in existence. It is for the Courts to peruse the two pandects in
an endeavor to give effect to both in so far as that may be
possible. This position stands clarified, although arguably it
need not have been so done, by Rule 52 of GCDR 1999. Under
these circumstances, we need not discuss in detail the exposition
of the law enunciated by the Constitution Bench titled Ishwari
Khetan Sugar Mills Vs. State of Uttar Pradesh, AIR 1980 SC
1955 : (1980) 4 SCC 136 as well as the series of other
pronouncements to the same effect. The relevant Rules of the
GCDR 1999 are also reproduced for facility of reference.
“6. Period for which leases may be granted
or renewed –
(1) The maximum period for which a lease
may be granted shall not exceed thirty
years:
Provided that the minimum period
for which any such lease may be granted
shall not be less than twenty years.
(2) A lease may be renewed for a period not
exceeding twenty years.
(3) Notwithstanding anything contained in
sub-rule (2), if the State Government is of
12
the opinion that in the interest of
development of granite it is necessary to
do so, it may, for reasons to be recorded,
authorize the renewal of a lease for a
further period or periods not exceeding
twenty years in each case.
7. Minimum and maximum area for grant of a
mining lease:-
(1) The minimum area that may be granted
or renewed under a lease for ensuring
mining activities to optimum depth shall
not be less than one hectare.
(2) The maximum area that may be granted
under a mining lease shall not exceed
fifty hectares:
Provided that the State Government, if it is
satisfied on the basis of proposed production level,
geological or topographical conditions, may for the
reasons to be recorded in writing, grant or renew a
lease over an area more than the maximum area or
less than the minimum area specified under this
rule.
52. Applicability of the provisions of Minor
Miner Concession Rules framed by the State
Government.
13
The provisions of the Minor Mineral
Concession Rules or any other rules framed by the
State Government under Section 15 of the Act shall
be applicable to granite quarry leases to the extent
they are not repugnant to or inconsistent with
these rules”.
5. Rule 15 of the KMMCR 1994 (supra) stipulates that
the maximum area that can be granted for a quarry lease cannot
exceed 50 acres in case of an existing hundred percent export
oriented granite cutting and polishing unit; and 40 acres in case
of other granite cutting and polishing units (see supra). Since
the petitioner does not fall in either, it is entitled only to ten
acres. On the other hand, Rule 7 of the GCDR 1999 ordains that
the minimum area shall not be less than one hectare and the
maximum area shall not exceed 50 hectares; the proviso
thereto, however, should not be overlooked as it vests informed
discretion on the State Government to breach both the maximum
and minimum areas. We must immediately note that in the
case in hand, this discretion has obviously not been even
exercised since the impugned Order dated 21.11.2002 does not
even attempt to articulate any reason for the Respondent-State
14
Government to have transgressed the aforementioned
parameters. As is known, an acre of land is equal to 4840
square yards (4047 square meters) whereas one hectare is
equivalent to 100 ares or 10000 square meters or 2.471 acres.
Even though the renewal of the Appellant’s quarry lease has been
confined only to ten acres by the respondent, it is nonetheless
more than one hectare which is the minimum area prescribed by
the Rule 7(1) of the GCDR 1999. Even without taking recourse
to the discretion of the State Government preserved by the
proviso, the reduction of area does not infringe or violate either
the GCDR 1999 or the KMMCR 1994. Therefore, the challenge to
the area/extent of the land as contained in the renewed lease
does not have any substance as it is well within the
postulation/parameter of both the enactments mentioned above.
The decision of the Constitution Bench of the Apex Court is
rendered in respect of the facts of that case. There is no
repugnancy in the two pandects. Arguably, it would have arisen
had the area covered by the renewed lease fallen short of one
hectare i.e., less than 2.47 acres. Even in such a situation, had
valid and articulated reasons been disclosed by the State
15
Government justifying going below one hectare, advantage of the
proviso to Rule 7 of the GCDR 1999 could have been availed.
6. It seems to us that both the State and the Central Rules
can coexist and in fact tend to prescribe similar principles and
endeavour to achieve common objectives. The preamble of GCDR
1999 clarifies that its intendment is “for conservation and
systematic development and scientific mining to conserve the
granite resources and to prescribe a uniform framework with
regard to systematic and scientific exploitation of granite
throughout the country. . .”. Therefore, both GCDR 1999 as well
as KMMC 1994 can coexist since their provisions are not
repugnant or incompatible to each other. So far as the present
factual matrix is concerned, the problem would have become
acutely manifest had the grant or renewal pertained to an area
which was less than 2.4 acres. It should be kept in perspective
that since granite is a minor mineral, by virtue of Section 14 of
the MMDR Act 1957 the postulations contained in Sections 5 to
13 thereof would not be applicable.
16
7. We shall now consider the second argument placed by
the learned counsel for the appellant. As has already been
narrated above, the first renewal was granted on 10.10.1994 with
effect from 15.03.1992 for a period of ten years. The second
renewal was applied for by the appellant on 12.02.2002, by
which time the KMMCR 1994 had come into operation having
been published in the Karnataka Gazette Extraordinary, dated
28.05.1994. It must immediately be observed that to accord a
renewed term, the KMMCR 1994 also governed the first renewal
since the decision was taken five months later, but since this
question has not been argued by either side, we shall not dwell
on it any further. Indubitably, by virtue of Rule 57 of KMMCR
1994, the respondents were obliged to apply them atleast when
the second renewal had been asked for. Furthermore, after
08.07.1999, Rule 16 contains an embargo against granting a
quarry lease for a period in excess of twenty years, which period
has been crossed on 15.03.2002 so far as the present case is
concerned, if the KMMCR 1994 are adverted to. However, unlike
the case of the extent of land which can be granted for a quarry
lease, there is variance between the State and Central Rules so
17
far as the tenure thereof is concerned, as the GCDR 1999
prescribes a maximum of thirty years and a minimum of twenty
years tenure for a lease. In addition, a renewal is postulated for
a period not exceeding twenty years, and the third sub-rule
enables further renewals if so justified in writing by the State
Government, in the event it is of the persuasion that the opinion
that these renewals would be in the interest of the development
of the granite industry. With regard to the tenure of a granite
quarry lease the KMMCR 1994 must give way to the GCDR 1999.
It was this dialectic which prevailed on us to hold so, in
W.P.Nos.16107-108/2012 disposed of on 17.09.2012.
8. Another significant difference between KMMCR 1994
and the GCDR 1999 concerns the initial grant of a quarry lease.
Rule 12 of the KMMCR 1994 contains an enumeration of
priorities which would prevail on the State to grant a quarry
lease to an applicant. The learned Single Judge in the impugned
Order has held that “the petitioner’s application for renewal of
lease requires to be considered on the basis of the priorities in
Rule 12. If that be so, the application of Rule 15 fixing the
ceiling on the area of quarrying lease cannot be restricted to
18
applications for grant of quarrying lease, but, is applicable also
to applications for renewal.” Contrary to the submissions
made by the learned counsel for the Appellant/Petitioner there is
little in substance or no difference between the ‘grant’ and
‘renewal’ of the lease. The argument of learned counsel for the
appellant before us appears to be somewhat different. It is
contended that the renewal cannot bring into existence fresh or
altered covenants except those pertaining to the tenure or
periodicity of the lease. We are not persuaded by this
argument. In Delhi Development Authority Vs. Durga Chand
Kaushish (1973) 2 SCC 825 their Lordships have clarified that –
“a renewal of lease is really grant of a fresh lease. It is called a
‘renewal’ simply because it postulates the existence of a prior
lease which generally provides for renewal as of right. In all
other respects, it is really a fresh lease.” In that case a lease
was admittedly for a period of 90 years, and an
increase/enhancement of rent prior to the expiry of its tenure or
during its tenure was held to be impermissible since no covenant
in the lease envisaged such an action. Even though the factual
matrix of the two cases are different, the foregoing enunciation of
19
the law by the Apex Court is relevant and must be applied. In the
present case, we shall abjure from pronouncement as to whether
the priorities contained in Rule 12 of the KMMCR 1994 would
once again have to be kept in perspective even at the time of its
renewal, as this aspect does not arise for our determination.
However, it appears to us that on the coming into effect of the
GCDR 1999, Rule 12 of the KMMCR 1994 has been rendered
otiose. If Rule 12 is not applicable to ‘grant of leases’ then it
could be argued that having regard to 1999 Rules, Rule 15 is
also not applicable to grant of lease as the extent is dependent on
nature of unit specified in Rule 12. It could further be argued
that if Rule 12 is not applicable to “renewal of leases” then
automatically Rule 15 also would not apply with regard to
renewal of leases. Therefore, the argument could be that if Rule
12 is not applicable for grant or renewal of leases, then Rule 15
also would not be applicable. In other words Rules 12 and 15
would not be applicable for renewal of a lease but we do not say
anything regarding their applicability for grant of a lease. They
also do not refer to “renewal of a lease” but only “grant of a lease”
20
unlike other provisions such as Rules 8, 9, 11, 14, 16, 18 which
refer to both expressions.
9. On the other hand, it could also be interpreted that
Rule 15 would apply to all renewals of leases subsequent to the
enforcement of the KMMCR 1994, though the initial lease was
prior to 1994, even though the word “renewal” is not found in
Rule 15. We say so because renewal of a lease is in substance
grant of a fresh lease. But Rule 12 cannot be applied to a
renewal of lease granted prior to 1994. Rule 12 cannot be
applied for considering a renewal of a lease granted prior to
KMMCR 1994 as the word ‘renewal’ would then lose its
contextual meaning having regard to priorities for grant of lease
stated in Rule 12. On the other hand, in respect of a lease
granted after the enforcement of KMMCR 1994 both Rules 12
and 15 would apply for grant of lease. With regard to renewal of
a lease, depending on the nature of the unit at the time of
renewal, Rule 15 is applicable but not Rule 12. We say this
because the GCDR 1999 prescribe the grant of a prospecting
licence prior to the execution of a quarry lease. The
comprehensive preferences put into place by Rule 12 have
21
escaped the postulation of the GCDR 1999 either in respect of
grant of a prospecting licence or of a quarrying lease, and this
being so it seems to us that Rule 12 prioritization would apply
mutatis mutandis to the grant of prospecting licence, as that is
the threshold or springboard for the grant of quarry leases or
prospecting licences. As is apparent, it is an arduous task that
the Court has to perform an ironing out the creases of the statute
or Rules and Regulations when they appear to collide with or
confront each other; the Court will always endeavour to apply
the rationale of both unless it becomes impossible to do so.
10. Since the renewal tantamounts to a fresh grant,
irrespective of the time of grant i.e., when with respect to a grant
made prior to KMMCR Rules, the State Government is duly
empowered to consider the extent of land which it finds
expedient to convey to any applicant such as the
Petitioner/Appellant having regard to the statutory provisions
relating to renewal of a lease. Unlike in the case of the tenure of
the lease, both the GCDR 1999 and KMMCR 1994 can coexist so
far as the extent of land sought to be given on lease is concerned.
We do not find any infraction of any law or of any Rules in the
22
decision of the State Government to reduce the area of the leased
land from 54 acres to 10 acres, as contained in the impugned
Order. Both the GCDR 1999 and KMMCR 1994 accord
preference to parties who have already invested or are willing to
invest moneys for the “Conservation and Systematic
Development of the Scientific Mining to conserve, the granite
resources”. So far as the petitioner is concerned, it is not his
case that he is entitled to 50 acres, possibly because he has not
set up hundred percent export oriented granite cutting and
polishing unit. It is also not his case that he is entitled to 40
acres because he has established a granite cutting and polishing
unit. Therefore, in our opinion, the grant of a lease for 10 acres
as against erstwhile 54 acres is totally justified and reasonable.
It is ubiquitously believed in the trade or market that Indian
granite is of high quality; pink granite available in Karnataka is
amongst the best and therefore is must sought after. A person
who is not willing to or has neglected to plough in requisite
investment, in the ultimate analysis, deprives others from
engaging the enterprise to the optimum; and prevents the State
from generating/recoverable maximum returns. Our attention
23
has been drawn to the exposition of law in Maya Mathew Vs.
State of Kerala (2010) 4 SCC 498. The GCDR 1999 partake of
the nature of a special enactment when compared to KMMCR
1994 which are general inasmuch as they apply to all minor
minerals. But in addition, the GCDR 1999 are also subsequent
or later in time, and therefore its provisions must prevail over the
earlier KMMCR 1994. Our analysis respects and implements
these well entrenched principles of statutory interpretation.
11. We are now in a piquant position since the impugned
order of the Government has been quashed in the impugned
decision of the learned Single Judge but it is not the State of
Karnataka which has come up in appeal. Therefore, in the
absence of an appeal, the impugned decision would have to be
reconsidered by the Government in the light of our observations
made above. The prayer in the Appeal is for setting aside the
finding of the learned Single Judge declaring that Rule 15 of the
KMMCR 1994 has application to the ‘renewal of Quarry Lease’ in
the Order dated 23.07.2004 which, because of our analysis, we
do not find to be legally acceptable. We also do not find any
error in the impugned order of the State Government in applying
24
Rule 15 of KMMCR 1994 and accordingly dismiss the Appeal, but
with no order as to the costs.
Sd/- CHIEF JUSTICE
Sd/- JUDGE
Vr/Sk/-