K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
IN THE NAME OF ALMIGHTY ALLAH, THE MOST BENEFICENT, THE MOST MERCIFUL
GREEN LINE BUS RAPID TRANSIT SYSTEM
(Updated as of 16th August, 2016)
(From KESC Power House Surjani Town To Municipal Park + CBD Extension M.A. Jinnah Road)
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
GROWTH IN URBAN TRANSPORT DEMAND
POPULATION INCREASES
BIRTH RATES
MIGRATION
GEOGRAPHICAL DECONCENTRATION
AVAILABILITY OF MOTORIZED TRANSPORT
INCREASES IN HOUSE HOLD INCOME
INCREASES IN COMMMERCIAL AND INDUSTRIAL ACTIVITY
Karachi and Urban Resilience
• Karachi has emerged as a resilient city by responding toeconomic, social and environmental change(s)
• Challenges to Urban Development:– Population
– Lack of Integrated Planning
– Non Inclusive Growth
– Pollution
– Encroachment
– Enforcement
– Irregular Development
• Karachi needs investment and in a coordinated fashion
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
1982 TRANSPORT COMMISSION (Justice Ajmal Mian)
COMMITTEE NO.1 SHORT TERM AND LONG TERM
COMMITTEE NO.2 TRAFFIC SAFETY AND PREVENTION
SPECIAL COMMITTEE CONSTITUTION OF METROPOLITAN
TRANSPORT AUTHORITY
TRANSPORT PLANS
KARACHI TRANSPORT (MERZ RENDELL) 1951 – 52
KDA MASTER PLAN 1974 – 1985
RAPID TRANSIT CELL MASS TRANSIT SYSTEM PLAN 1977
COMMISSION OF ENQUIRY IN KARACHI AFFAIRS (MASOOD UZ ZAMAN) 1985
KARACHI MASS TRANSIT PLAN 1990
KARACHI MASTER PLAN 2020 2005
KARACHI TRANSPORT IMPROVEMENT PLAN 2013
Background
6
• 4.5% composition of Public Transport Vehicles carry 42% of Total Persons Traveling in the City.
• Private Cars which is 36.5% of Total Vehicular Traffic carries only 21% of Persons. Showing Lesser Average Vehicle Occupancy.
• The above leads to the conclusion that there is still deficiency of Public Transport availability on all Major Routes in the city.
34.3
25.1 24.6 24.123.5
22.922
20.820.2
18.8
0
5
10
15
20
25
30
35
40
Popula
tion (
Millions)
Karachi Now
Karachi in 2030
• 4.5% composition of
Public Transport
Vehicles carry 42% of Total Passengers
• Private Cars are36.5% of
Total Vehicular Traffic carries
only 21% Passengers.
Mansehra Colony
Tower
Mauripur
Gulbai
Shershah
Board Office
Municipal Park
Regal Chowk
Model Colony
Numaish
NaganChowrangi
UNIVERSITY ROAD
UNIVERSITY ROAD
Planned BRTS Corridors - KTIP(Karachi Transportation Improvement Project)
Mansehra Colony
SingerChowrangi
MaymarMore
Tower
Mauripur
Gulbai
Shershah
Nishan-e-HaiderChowk
Board Office
Surjani
Municipal Park
Regal Chowk
Model Colony
Numaish
NaganChowrangi
Yellow Line GoS - Public Private Partnership ModelBid Submitted by Dec 18, 2014Construction may start by Jan,2016
Blue Line By a Private DeveloperIn Detail Design StageConstruction may start by 2016
Red Line Under discussion with ADB
Green Line 21.7 km to be executed by KIDCL under Ministry of Communication, Government of Pakistan
Orange Line To be executed byGovernment of Sind
M10 / RCDHighway Junction
Green line Blue line Red line Yellow line
Merging Point
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
• Execution: Karachi Infrastructure Development Company Ltd. (KIDCL)
• Project Scope Construction of GLBRTS Corridor along with Stations and Depot (Infrastructure)
• Project Start KESC Power House, Surjani Town.
• Project End M.A Jinnah Road
• PC -I Approved by ECNEC @ Rs. 16,085.1 M
under the Prime Minister’s Initiaitive.
• Consultant M/s. EA Consulting (Pvt.) Ltd.
• Vetting Consultant: M/s. Exponent Engineering (Pvt) Ltd.
• IITS Consultant: M/s. BLIC GmBH Germany, EA & DCC JV
Board of Directors, KIDCL
• Secretary Communications…. Chairman BOD• Secretary Finance, GoP• Secretary Planning, GoP• Chief Secretary Sindh• Additional Secretary, PM’s Office• Mr. Arif Hassan, Sr. Architect / Urban Planner• Chief Executive Officer, KIDCL• Lt. Gen (R) Shahid Niaz;• Mr. Sarosh Lodhi, Dean Civil & Architecture NED; • Commissioner Karachi; • Secretary Transport, GoS; and• Dr. Noman Ahmed, Chairman Arch. & Town Planning, NED
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
Objectives of Green Line
• To provide reliable, safe, affordable, high quality and fast BRT BusService,
• To Improve the quality of life of commuters in Karachi,
• To improve the quality of public transport system in Karachi,
• To provide infrastructure that allows buses to ply in an efficientmanner with exclusive right-of-way for a significant portion oftheir route length, and
• Reduce passengers’ travel time, and
• Encourage mode shift from private use of vehicles to Publictransport mode.
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
Peak throughput (passengers/hr/direction) 12,000
System passenger-trips per day 300,000
Highest peak hour boarding & alighting at a single station 4,500
Highest full-day boarding at a single station 50,000
Location of busway lanes Centre of Roadway
Number of BRT stations 25
Number of corridors 1
Number of BRT terminals 2
Number of BRT depot 1
Total length of dedicated busway (Up to Municipal Park) 21.7 km
Length including mixed traffic portions 0 km
Average distance between stations 800 m
Signal Priority or Grade Separation at Interchange Grade Separation
Salient Features Green Line BRTS
Municipal Park
Radio Pakistan
Garden Sqaure
Taj Medical Complex
KGA Ground
West of Quaid-e-Azam
Gurumandir
Lasbela Chowk
No. 1 Chowrangi
Model ParkBaqai Hospital
Public Park
Board Office
KDA Chowrangi
Hydari Market
Five Star Chowrangi
Jummah Bazar
Sakhi Hassan Chowrangi
Erum Shopping Emporium
BRT GREEN LINE
Corridor Length 21.70 km Elevated 11.70 kmAt grade 10.00 kmNo. of Stations: 25 Nos
Project Start
Congested Corridor
Nagan Chowrangi
UP Mor Intersection
Road 2400
Power House Chowrangi
Road 4200
Two Minute Chowrangi
Surjani Chowrangi
KDA Chowrangi Surjani Town
KESC Power House
Karimi Chowrangi
Legend At Grade Elevated Station
CONTRACT PACKAGE# KAR/BRTS/GL/01
LOCATION FROM NAZIMABAD CHOWRANGI TO GURU MANDIR
CONTRACTOR CRFG-MATRACON JOINT VENTURE
CONTRACT VALUE 1845.43 MILLION
DATE OF START JANUARY 28TH 2016
PROJECT LENGTHELEVATED
RAMP AT GRADE
2510 M562 M374 M
NO. OF STATIONS (CIVIL WORKS ONLY)
4 NOS
TOTAL COMPLETED REMAINING REMARKS
PILE LOAD TEST 02 DONE 0 Completed
PILES 436 349 87 IN PROGRESS
PILES CAP 86 52 34 IN PROGRESS
PIER SHAFT 82 10 72 IN PROGRESS
GIRDER 206 7 199 IN PROGRESS
ABUTMENTS 4 1 POUR 3 IN PROGRESS
CONTRACT PACKAGE# KAR/BRTS/GL/02
LOCATIONFROM NAGAN CHOWRANGI TO NAZIMABAD
CHOWRANGI
CONTRACTOR M/S. CH. A. LATIF & SONS PVT. LIMITED
CONTRACT VALUE 1084.717 MILLION
DATE OF START MARCH 25TH 2016
PROJECT LENGTHELEVATED
RAMPAT GRADE
930 M1023 M5797 M
NO. OF STATIONS (CIVIL WORKS ONLY)
7 NOS
TOTAL COMPLETED REMAINING REMARKS
PILE LOAD TEST 03 3 0 DONE
PILES 160 160 0 DONE
PILES CAP 34 34 0 IN PROGRESS
PIER SHAFT 28 21 7 IN PROGRESS
ABUTMENT 6 4 2 IN PROGRESS
TRANSOMS 28 8 20 IN PROGRESS
GIRDER FORM WORK IS IN PROGRESS
CONTRACT PACKAGE# KAR/BRTS/GL/03
LOCATION CONSTRUCTION OF BOARD OFFICE INTERCHANGE
CONTRACTOR M/S AGHA CONSTRUCTION COMPANY
CONTRACT VALUE 785.867 MILLION
DATE OF START MARCH 5TH , 2016
PROJECT LENGTHELEVATED
RAMP314.25 M
625 M
NO. OF STATIONS (CIVIL WORKS ONLY) NONE
TOTAL COMPLETED REMAINING REMARKS
PILE LOAD TEST 01 DONE 0 Completed
PILES 128 118 10 IN PROGRESS
PILES CAP 17 13 4 IN PROGRESS
PIER SHAFT &TRANSOM
24 14 10 IN PROGRESS
ABUTMENTS 3 3 0 Completed
GIRDER CAST IN PLACE
CONTRACT PACKAGE# KAR/BRTS/GL/UT-01
LOCATIONCONSTRUCTION OF WATER TRUNK (DIA1200MM
FROM NAGAN CHOWRANGI TO SAKHI HASAN & RELOCATION OF PUMPING STATION NEAR KDA CHOWRANGI.
CONTRACTOR M/S. MUHAMMAD HASNI BUILDER
CONTRACT VALUE 145.70 MILLION
DATE OF START DECEMBER 03RD 2015
PROJECT LENGTH 2100 M
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
• Gate and visual inspection area
• Administrative Office for the concessioner operators
• Re-fueling area
• Vehicle washing and cleaning area
• Major repairs
• Minor repairs and Maintenance
• BRT vehicle parking
• Private vehicle parking
• Other
- Tire Storage Space of 5m x 10m
- Security office
- Pray Room
- Napping Room
- Canteen
Functions of Depot
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
ITS
• ITS Objectives– Maximize commuter transit
– Provide secure reliable & cost effective BRT
– How ITS makes it possible• Minimize passenger on/off boarding time
• Maximize vehicle and personnel efficiency
• Provides electronic tools for revenue generation
• Enable real-time monitoring & operational control
• Minimize revenue leakages / malpractices
• Security tools for surveillance and rapid response
29
Integrated Intelligent Transportation System
All Lines (KTIP)
Feasibility & Technical
Study
Development of RFP:
(Green & Orange)
a) Technical Documents
b) BOQs
c) Specifications
d) Cost Estimates e) Concessions
Procurement of IITS
Design-Built Vendor
Data Communication
Highway
AVM / Fleet
Management
Central Command &
Control
Automatic Fare
Collection (AFC)
Passenger Information
System
Security & Surveillance
Bus Depot and Bus
Docking System Energy Management
Assist Green & Orange
Lines during Civil
Infrastructure
Financial Integration
Legal Integration
and Enabling Laws
Supervision
Services
Environment & Landscape
• EIA approved from SEPA in November 2015, prior toconstruction phase.
• Independent Monitoring Consultant for HSE & EIACompliance
• Landscape Consultant – Transplantation & CompensatoryPlantation (7,321 being removed / 19,500 Re-planted)
• Coordination with KMC and DMCs, Commissioner & DCOffices
LANDSAPE STRATEGY
BRT ROUTE IS LOCATED ALONG THE MEDIAN FROM GURUMANDIR TO POWERHOUSE , 22 KM
• 7321 TREES ARE TO BE REMOVED• 6521 PODOCARPUS SPECIES• 800 TREES TO BE TRANSPLANTED• 19500 NEW TREES TO BE
PLANTED AS COMPENSATORY PLANTING
• NEW TREES WILL BE ENVIROMENT FRIENDLY
• FOR THE FIRST TIME IN ANY MASS TRANSPORT SYSTEM IN PAKISTAN TRANSPLANTATION OF TREES OF THIS SCALE IS GOING TO TAKE PLACE
SITE PLAN BRT ROUTE
TRANSPLANTATION DEMO
LIGNUM VITAE
AZADIRACHTA INDICA
4.TRANSPLANTED
2.PRUNE,SECURE AND LIFT1. ISOLATE ROOTBALL
3.TRANSPORT TO NEW SITE
TRANSPLANTED
PROPOSED TREES
ALLISTONIA SCHOLARIS
CASSIA FISTULA CRATEVA RELIGIOSA
LIGNUM VITAE
DELONIX REGIA
ADDITION OF LOCAL TREES WILL REVIVE THE STREET CHARACTER THAT WAS ONCE PREVALENT IN KARACHI
AZADIRACHTA INDICA
GOALS AND OBJECTIVES• USE SHELTER DESIGN TO ENHANCE VISIBILITY OF THE SERVICE
• PROVIDE CONSISTENCY (IN MATERIALS, COLORS AND DESIGN) WITH OTHERSITE ELEMENTS, INCLUDING LIGHTING, RAILINGS, SIGNAGE, FURNITURE ETC.
• ENSURE SAFE ACCESSIBILITY FOR ALL, INCLUDING PEOPLE WITH DISABILITY & SENIOR CITIZENS
• PROVIDE PASSENGERS WITH INFORMATION, INCLUDING SIGNAGE, WAY FINDING & REAL-TIME ARRIVAL INFORMATION
• ENABLE PRECISE BERTHING AT DESIGNATED STOPPING POINTS
• ENABLE PASSENGERS TO BOARD THROUGH MULTIPLE DOORS
• ENABLE LEVEL BOARDING BY MATCHING PLATFORM HEIGHT WITH VEHICLE FLOOR HEIGHT AND USING PRECISION DOCKING
• MATERIALS AND COMPONENTS MUST BE EASY TO MAINTAIN, REPAIR AND REFURBISH; BE PROVEN VANDAL-RESISTANT;
GL-02 AT GRADE STATIONS; (Station Count = 07)
STATION TYPES
• STATION IS AT GRADE IN THE CENTRE OF THE CARRIAGE WAY
• PEDESTRIAN BRIDGE CONNECTS BRT USERS TO THE STATION• STATIONS LOCATED BETWEEN NAGAN CHOWRANGI AND NAZIMABAD CHOWRANGI
GL-04 ELEVATED STATIONS; (Station Count = 10)
• STATIONS ARE ELEVATED AND ON THE SIDE OF THE BUS CARRIAGE WAY• PEDESTRIAN BRIDGE CONNECTS BRT USERS TO THE STATION• STATIONS LOCATED BETWEEN KESC POWER HOUSE AND NAGAN CHOWRANGI
TYPICAL STATIONS
STATION TYPES – TOTAL 21 STATIONS (18.4Kms Corridor)
GL-01 ELEVATED STATIONS; (Station Count = 04)
• STATIONS ARE ELEVATED AND ON THE SIDE OF THE BUS CARRIAGE WAY• PEDESTRIAN BRIDGE CONNECTS BRT USERS TO THE STATION• STATIONS LOCATED BETWEEN NAZIMABAD CHOWRANGI TO GURU MANDIR