1
Indian regulations in
Electrical Safety
P.LahiriBARC
2
Indian regulations.
• Indian Electricity Act-1910.
• Indian Electricity (Supply) Act- 1948.
• Indian Electricity Regulatory Commission Act-1998.
• The Electricity Act –2003.
• Indian Electricity Rules- 1956.
Repealed under section 185 of Electricity act -2003
3
• Make generation, transmission, distribution and utilization of electricity as safe as possible.
• Identification of different categories of agencies.
• Remove ambiguities from existing qualitative guidelines and pronounce precise quantitative technical requirement with respect to safety.
Objectives of regulations
4
Categories of agencies
• Supplier of electricity.
• Consumer of electricity.
• Electrical inspector.
• Electrical contractor and supervisors.
• Authorized persons.
5
Hazards of electricity• Electric shock:- Current flows through body or part of body
when two surfaces having electrical potential difference is touched resulting in burn, disability or even death.
• Flashover:-Sudden collapse of electric field by having a conducting path between two electrical potential different surfaces resulting in burn, fire.
• Blast:-Failure of dielectric medium between two electrical potential different surfaces resulting in projectile, mechanical force, fire or burn.
• Heat:-Caused by loose connection in the circuit, overheating of insulation/ conductor due to overload or prolonged short circuit current etc. resulting in fire, burn.
6
Quantitative effect of electric current (up to 3sec.) on human (source Daziel)
Effect mA
d.c a.c
60Hz 10kHz
M F M F M F
Perception threshold 5.2 3.5 1.1 0.7 12 8
Shock but not painful 9 6 1.8 1.2 17 11
Muscular control lost, breathing difficulty.
90 60 23 15 94 63
Ventricular fibrillation 500 500 100 100
7
Flash and flame burnThermal burns, Current flows typically external, Damage to skin
8
Electric shock and flash burn
9
EXPLOSION
Occurrence of blast
10
Classification of rated voltage as per IE rule
250V
650V
Low Voltage (LV)
Medium Voltage (MV)
High Voltage (HV)
Extra High Voltage (EHV)
33kV
Above 33kV
11
Authorization• Avoid chaos
• Fixing up of responsibility
• Ensures expertise
• Authorization.• Electrical isolation.
• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.
• Earthing.
• Reporting accidents.
12
Authorization ruleRequirement Applicable for Rule
Work to be executed by licensed electrical contractor.
All new, addition, alteration jobs having electrical scope except minor jobs.
45-(1), (3)
Safety officer to be authorized by owner with approval of electrical inspector.
Electrical installation with more than 250kW connected load
3, 4, 5, 6
Prior approval from electrical inspector to work
Any electrical work on live apparatus/ line
36 (2)
13
Authorization cntd.
Qualifications rule
Agency Minimum qualification
Rule
Authorized O & M person for generating station of capacity above 100MW and sub-stations of 132kV and above.
Second class diploma in mechanical or electrical engineering & training from CEA approved institute.
3 (2A)
Assistants to above ITI & training from CEA approved institute
3 (2A)
14
Electrical isolation.
• Quick de-energization
• Ensure de-energization while on work
• Authorization.
• Electrical isolation.• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.
• Earthing.
• Reporting accidents.
15
Electrical isolation(Rule)
Rating of service connection Isolation device
Rule
CB SFU*
LV, MV service connection 50-(b) (i) (ii)
upto 1000kVA at 11kV
Above 1000kVA at 11kV upto 2500kVA at 33kV Above 2500kVA at 33kV Any rating beyond 33kV
16
LV,MV
17
11k,33k
or
18
>33k
19
Electrical isolation device for transformers (Rule)
Rating of transformer Isolation device RulePri: Sec:
CB SFU* CB SFU*
Upto 630kVA and primary side less than HV
50-(b) (i) (ii)
upto 630kVA and primary side HV and above.
630kVA to 1000kVA irrespective of primary voltage
Above 1000kVA irrespective of primary voltage
20
Above 1000kVA
21
Primary HV
22
630kVA
23
Identification & display
• Electricity is invisible:-– Various current carrying portions– Different circuits/ phases/ a.c/ d.c. etc.– Different voltages LV,HV,MV etc– Power flow directions. – ON/OFF positions and direction of
operation of SFUs/CBs/Isolators.– Source locations of PCCs/ MCCs and
load locations of each feeders of MCCs– Danger notices.
• Authorization.
• Electrical isolation.
• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.
• Earthing.
• Reporting accidents.
24
Identification & display (Rule)
Requirement Applicable for Rule
Display of danger notice.
Electrical installation rated MV and above.
35
Visual identification by distinct colour.
All conductors connected to earthing system
32(1)
Visual distinction of circuits, voltages, feeders etc.
All electrical installation 41
25
Restriction of access
• Thwart accidental or unauthorized access:-
• Authorization.
• Electrical isolation.
• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.
• Earthing.
• Reporting accidents.
26
Restriction of access (Rule)
Requirement Applicable for Rule
Metallic covering which is electrically and mechanically continuous
All live conductors for indoor installations.
51(1)(a)
Metallic fencing of height not less than 1.8M.
Out door sub-station. 68(b)
27
Inspection testing & maintenance
• Ensure adequacy of safety related parameter:
• Maintaining safety related parameter within limit.
• Authorization.
• Electrical isolation.
• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.
• Earthing.
• Reporting accidents.
28
Commissioning inspection (Rule)
Type of Installation
Type of test (Rule do not specify) interpreted.
Inspecting authority
Any installation upto MV (not generating plant)
Visual inspection.
Insulation resistance.
High voltage.
Earth resistance.
Any functional requirement.
Supplier.
Generating plant of capacity less than 10kW
Same as above Owner
29
Commissioning inspection (Rule) cntd.
Type of Installation
Type of test (Rule do not specify) interpreted.
Inspecting authority
Generating plant of capacity more than 10kW
Depending upon voltage level as desired by Electrical Inspector
Electrical Inspector.
HV or EHV installation
Visual inspection, insulation resistance, high voltage, earth resistance, functional tests and test as desired by Electrical Inspector.
Electrical Inspector.
30
Periodic inspection (Rule)Type of test Maximum
time interval.Record keeping duration
Test by inspector 5 years Not specified
Earth resistance for LV and MV installation
2 years 2 years.
Earth resistance for HV and EHV installation
1 year 2 year
Fire extinguishers 1 year Not specified
31
Preparedness.
• Mitigate the effect of fast acting electrical disaster
• Ensure correct course of action
• Authorization.
• Electrical isolation.
• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.
• Earthing.
• Reporting accidents.
32
Preparedness (Rule)Essential Applicable for Rule
First-aid box, Restoration chart, Fire buckets
Every generating station, enclosed sub-station and enclosed switch station
43(2), 44(1), 43(1)
Two or more gas masks
1.Generating station with capacity of 5MW and above
2.Enclosed sub-station with transformation capacity of 5 MVA and above
43(3)
33
Preparedness (Rule)cntd.
Essential Applicable for Rule
Artificial respirator
Every manned high voltage or extra-high voltage generating station, sub-station or switch station
44(4)
Trained personnel for providing artificial respiration.
All attended generating station and sub-station.
44(3)
34
Possibility of success of artificial respiration
source Edition Electric Institute resuscitation manual
35
Other hazard precaution.
• Reduce potential initiating events of accident
• Authorization.
• Electrical isolation.
• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.
• Earthing.
• Reporting accidents.
36
Other hazard precaution.(Rule)
Situation Safety measure RuleElectrical installation in explosive atmosphere
Explosion proof/ dust tight depending upon the hazardous zone as per IS5571
51(d)
Multistoried building with height more than 15M.
1. Power cable ducts shall not be used for other services
2. Power cable ducts shall have fire barrier at each floor crossing
50A-(4)
37
Other hazard precaution.(Rule)cntd..
Situation Safety measure RuleElectrical installation with more than 2000litres of oil
1.Baffle wall of 4hr fire rating between single phase banks and on consumer premise.
2.Oil soak pit for full quantity of oil
64(2)-(e)
Electrical installation with more than 9000litres of oil
1.Measures mentioned above.
2.Fire extinguisher.
3.Oil draining arrangement.
64-(2)(e)
38
Other hazard precaution.(Rule)cntd..
Situation Safety measure Rule
Substation and switch station in the basement
1.Entrance shall have 2hr fire rating fire resistance door
2.A curb at entrance to trap oil flow.
3.Direct access to transformer from outside
4.Transformer protection by automatic HVWSp/ CO2/ BCF/ BTM/ N2 injection and drain.
64-(2) (f)-(ii)
39
Other hazard precaution.(Rule) cntd..
Location based on oil inventoryTotal oil quantity in litre (includes transformer and other apparatus)
Location Rule
Indoor Out-doorIndl: building Res:/ com:
bldg. Any floor of
1st
Bs.Gr. Fl.
Other floors
No oil. 64 (2)2000 or less
2000 to 9000 9000 or more
40
Protection & interlocks.
• Avoid human errors
• Authorization.
• Electrical isolation.
• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.
• Earthing.
• Reporting accidents.
41
Transformer protectionRating Mandatory relay
protectionRemark
Less than 630kVA and primary side less than HV
No relay based protection is mandatory
Not specified
Less than 630kVA and primary side more than HV
Over current/ short circuit relay etc for secondary CB.
Not specified but implied by R50(b)(ii)
630kVA to 1000kVA
Over current/ short circuit relay etc for secondary CB.
Not specified but implied by R50(b)(ii)
42
Transformer protection
cntd..
Rating Mandatory relay protection
Remark
1000kVA to 10MVA
1. Bucholz
2. Winding temp:
3. Oil temp:
R64(2)
More than 10MVA 1. Bucholz
2. Winding temp:
3. Oil temp:
4. Differential
R64(2)
43
HV & EHV installations interlocksSituation Preventive interlock Rule
Isolator and CB in series
Isolator operation not allowed when CB is closed.
64 (A) (1)
Earthing switch and isolator
Earthing switch can not be closed when isolator is closed
Two or more incomer feeders to a bus bar but not intended for parallel operation
Only one feeder can be switched on at a time
44
HV & EHV installations interlockscntd..
Situation Preventive interlock Rule
Two or more transformers in parallel
Secondary CB trips if primary of that transformer trips.
64 (A) (1)
Doors or gates give access to live parts
Doors can not be opened when any part is live.
Neutral switching device between neutral and earthing is used for generator
GCB can not be closed when neutral breaker is open.
45
HV & EHV installations protectionProtection against.
Type of relay Mandatory for Rule
Over current. Over current/ short circuit relay.
Any Equip., cable supply line etc.
64A (2)
Rising touch potential.
Earth leakage/ earth fault.
Generator rated over 100kVA
Internal fault. Differential relay Generator rated over 1MVA Bus bars rated over 200kV
Switching over voltage/ lightning
Lightning arrestor Overhead line terminations
92(1)
46
Other protectionsProtection for.
Type of relay Mandatory for Rule
Human safety.
ELCB/ RCCB/ etc.
Any installation having connected load more than 5kW at MV or above
61A
DC earthing. Over current relay between earthed middle conductor and earth.
DC three wire system
61 (1) (d) (i)
47
mSec
50H a.c current (rms mA)
Zone 1- Usually no reaction, Zone 2 – Reaction may occur but usually no patho- psychological dangerous effect, Zone 3- No risk of fibrillation, Zone 4- Fibrillation possible (50% probability), Zone 5- Unsafe or fibrillation
Time/ Current for a.c 50Hz
48
Clearances (physical spacing)
• Minimum air insulation clearance.
• Minimum space to work.
• Minimum space for escape.
• Authorization.
• Electrical isolation.
• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.• Earthing.
• Reporting accidents.
49
Clearances for bare conductor other than overhead lines(Rule)
Voltage Section clearance (outdoor) in m.m.
Ground clearance (outdoor) in m.m
Rule
Upto 11kV 2600 2750
64
33kV 2800 3700
66kV 3000 4000
220kV 4300 5500
400kV 6500 8000
50
Clearance above ground of overhead lines across/ along a street (Rule)
Condition System voltage Clearance in mm
Rule
Across LV, MV 5800
77
HV 6100
AlongLV, MV 5500
HV 5800
Any where else
LV, MV, HV (upto11kV)
4600
HV(above 11kV) 5200
Every where EHV
5200 + 300 for every 33kV but not less than 6100
51
Clearance of overhead lines from building(Rule)
Condition System voltage Minimum clearance in mm
Vertical
(IE R 79)
LV, MV 2500
HV 3700
EHV 3700 + 300 for every 33kV
Horizontal
(IE R 80)
LV, MV 1200
HV upto 11kV 1200
HV above 11kV
2000
EHV 2000 + 300 for every 33kV
52
SECTION CLEARANCE
SC
Section clearance
SC
53
GC
GROUND CLEARANCE
GROUND LEVEL
Ground clearance
Height of tall man’s raised finger tip with raised hand-2.5m
54
Earthing system.
• Limit touch potential• Limit step potential• Safe predefined passage for
fault current• Facilitate detection of
incipient fault• Reduce neutral shifting
• Authorization.
• Electrical isolation.
• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.
• Earthing.• Reporting accidents.
F
E
Et
E/X CURVE
Es
Earth Mat
X
1M 0.5M
Step & Touch potential
56
Earthing (Rule)Requirement Applicable for RuleEarthing terminal by Supplier.
LV consumer 33
Separate earthing terminal by supplier and consumer.
MV and above 33
Minimum two independent and redundant path with two earth electrode.
Earthing network for equipment, system. R61(2),
R61(3), R51(1)(b), R67(1)
All metallic part not intended to serve as conductor shall be earthed.
All electrical apparatus
Grounding of neutral. a.c electrical power supply system more than 125V
61(1)(a), 64(3)
57
Reporting of accidents
• Reporting for analysis.
• Fast reporting prevents suppression of facts.
• Authorization.
• Electrical isolation.
• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.
• Earthing.
• Reporting accidents.
58
Reporting of accidents (Rule)Type of accident Report
formatMaximum period for reporting
Rule
Fatal involving loss or injury
Telegraphic
and
24hours44A
Written 48hours
Failure of transformer or reactor above 20MVA
Written 48hours 65(8)
59
Conclusion
• Regulations can induce more concern.• Regulations can not rule out accidents by themselves• Every concerned individuals should handle electricity in
safe manner• Do not try to find out loopholes of regulation to limit our
responsibility.• Try to adopt a proactive approach by understanding the
intentions of the regulation authors.• In case of doubt ask electrical inspector or Central
Electricity Authority.
60
61
Clearance across the road
62
Clearance along the road
63
Clearance anywhere else
64
Clearance from building
Vertical clearance
Horizontal clearance
65
Fl-1
Fl-4
Fl-2
Electrical service shaft
Fire barrier
Cables
Fire barrier in cable duct
66
Ground clearance for bare conductor other than overhead lines(Rule)
Voltage Clearance in mm Outdoor
Upto 11kV
2750
33kV 3700
66kV 4000
220kV 5500
400kV 8000
Height of tall man’s raised finger tip with raised hand-2.5m
67
Phase to Phase(Rule)
Voltage Clearance in mm Outdoor
Ph~Ph Ph~E Sec: Ground
11kV 460
33kV 915
66kV 1220
220kV 3350
400kV 4000
68
Phase to earth(Rule)
Voltage Clearance in mm Outdoor
11kV 305
33kV 610
66kV 750
220kV 1675
400kV 3500
69
ClearancesIt denotes the minimum distance in air between two potentially different points (this includes earthed/ ground surfaces) to avoid flashover during normal and transient over voltage.
Phase to earthMinimum distance between live conducting parts and neighboring earthed parts.
Phase to earth
70
ClearancesIt denotes the minimum distance in air between two potentially different points (this includes earthed/ ground surfaces) to avoid flashover during normal and transient over voltage.
Phase to earth Phase to PhaseMinimum distance between live parts of different phases.
Phase to phase
71
ClearancesIt denotes the minimum distance in air between two potentially different points (this includes earthed/ ground surfaces) to avoid flashover during normal and transient over voltage.
Phase to earth
Phase to PhaseIsolating clearanceMinimum distance between two sides of an open isolator
Isolating clearance
72
ClearancesIt denotes the minimum distance in air between two potentially different points (this includes earthed/ ground surfaces) to avoid flashover during normal and transient over voltage.
Section clearanceMinimum distance between maintenance zone and nearest live part plus one stretched arm length of a person
Phase to earth
Phase to Phase
Isolating clearance
Section clearance
73
ClearancesIt denotes the minimum distance in air between two potentially different points (this includes earthed/ ground surfaces) to avoid flashover during normal and transient over voltage.
Ground clearanceMinimum distance between lowest point of support insulator and ground
Phase to earth
Phase to Phase
Isolating clearance
Section clearance
Ground clearance
74
CLEARANCES IN OUTDOOR
PH-TO PH
STRUCTURE
PHASETO EARTH
GANTRY
TOWER
Phase to earth & phase to phase clearance
P-E rule P-P rule
75
Isolating clearance
Isolating clearance
76
77
Safety provisions in IE Rules• Authorization.
• Electrical isolation.
• Identification & display.
• Restriction of access.
• Inspection, testing etc.
• Preparedness for adversity.
• Other hazard precaution.
• Protection & interlocks.
• Clearances.
• Earthing.
• Reporting accidents.
78