+ All Categories
Home > Documents > Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003...

Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003...

Date post: 08-Oct-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
42
Final Report, July 2008 Carbon Capture Technology Options and Costs Jared Ciferno Office of Systems, Analysis and Planning Indiana Carbon Capture & Sequestration Summit September 3-4, 2008 Indianapolis, Indiana
Transcript
Page 1: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

Final Report, July 2008

Carbon Capture Technology Options and CostsJared CifernoOffice of Systems, Analysis and Planning

Indiana Carbon Capture & Sequestration Summit

September 3-4, 2008Indianapolis, Indiana

Page 2: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

2

• New Coal-fired Power Plants– IGCC Pre-combustion CO2 Capture– PC Post-combustion CO2 Capture

• Existing Pulverized Coal Power Plants– Post-combustion CO2 Capture

Topics

CO2 Capture Applied To……..

Presenter
Presentation Notes
Focus will be on CO2—Plants designed to meet all other criteria pollutant environmental emission targets.
Page 3: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

3

National Energy Technology Laboratory

•Only DOE national lab dedicated to fossil energy – Fossil fuels provide 85% of U.S. energy supply

•One lab, five locations, one management structure•1,200 Federal and support-contractor employees•Research spans fundamental science to technology demonstrations

West VirginiaPennsylvaniaOklahoma

Alaska

Oregon

Page 4: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

4

Large Proportion of Total Coal-fired CO2 From Existing Plants

0

500

1,000

1,500

2,000

2,500

3,000

3,500

1995 2000 2005 2010 2015 2020 2025 2030

Unscrubbed Steam

Scrubbed Steam

New Steam

IGCC

Existing units 90.1% of cumulative

coal-fired CO2 2007-2030

(74.6% of year 2030 coal-fired

CO2)

Tons

(mill

ions

) CO

2Coal-fired Generation CO2 Forecast

AEO’07 Reference Case

Page 5: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

5

Time to Commercialization

Amine solvents

Physical solvents

Cryogenic oxygen

Advancedphysical solvents

Advancedamine solvents

Ammonia

PBI membranes

Solid sorbents

Membrane systems

ITMs

Ionic liquids

MOFs

Enzymatic membranes

CAR process

Chemicallooping

OTM boiler

Biologicalprocesses

Cos

t Red

uctio

n B

enef

it

Present 5+ years 10+ years 15+ years 20+ years

Post-combustion

Pre-combustion

Oxycombustion

CO2 Capture Technology Options

Presenter
Presentation Notes
This slide illustrates how the Sequestration Program Capture projects cover technologies that will take some time to develop to commercial status but should have substantial cost reduction benfits. Technologies being pursued that have longer times to commercialization have a potential for higher cost reductions. COST REDUCTION BENEFIT: ZONE 1 is equivalent to 30-90% increase in COE. ZONE 2 is a ~20% improvement in cost at ~25-70% increase in COE. ZONE 3 is a ~40% improvement in cost at ~15-40% increase in COE. ZONE 4 is a ~70% reduction in cost at 5-13% increase in COE. ZONE 5 is a 90+% reduction in cost. TIME TO COMMERCIALIZATION: ZONE 1: Current Commercial Technologies (Amine Solvents…) PRESENT This technology exists commercially although it has not been deployed at the scale required for most medium sized (~400 MW) CO2 capture applications. ZONE 2: Near-Term Technologies (Advanced Physical Solvents…) 1-3 years These technologies are similar to the “Current Commercial Technology” but which include advances in chemicals or process optimizations. ZONE 3: Mid-Term Technologies (PBI Membranes…) 2-6 years These technologies have been demonstrated at the lab or small pilot scale. ZONE 4: Long-Term Technologies (Ionic Liquids…) 4-8 years These are newly developed technologies that show great promise but generally have not been developed into a specific technology for CO2 capture or beyond the lab/conceptual scale. ZONE 5: Next Generation Power Plants/CO2 Removal Plants (Chemical Looping…) 5-12 years
Page 6: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

6

Power Plant Cost Trends

• Power plant construction costs have risen at rates greater than that of inflation in past few years

• Why?– Global demand for electricity infrastructure-related

items – High fuel and labor prices– High raw material prices

• Expected to worsen

Page 7: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

7

80

100

120

140

160

180

200

2000 2001 2002 2003 2004 2005 2006 2007 Q32007

Q12008

Year

Cos

t Ind

ex (2

000

= 10

0)

CERA Power Capital Cost Index (PCCI)

> 80% Increase in Power Plant Capital Cost in past 8 years

Source: http://www.ihsindexes.com/*Excludes Nuclear

Presenter
Presentation Notes
The IHS/CERA Power Capital Costs Index (PCCI) Leveraging CERA's Index + Scenarios methodology, the PCCI tracks and forecasts the costs associated with the construction of a portfolio of 30 different power generation plants in North America. The PCCI is a work product of the Capital Costs Analysis Forum for Power (CCAF-P), a research project managed by CERA.
Page 8: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

8

New IGCCWith and Without CO2 Capture

Page 9: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

9

New IGCC Power PlantNo CO2 Capture

Process Design1:Plant: 2 gasifiers, 2 Comb. Turbine,

1 Steam TurbinePower: ~600 - 650 MWOxygen: 95% O2 via cryogenic ASUTurbines: Advanced F-Class Turbine Steam: 1800psig/1050°F/1050°F

TPD: Short Ton per DayTPY: Short Ton per Year (at 80% Capacity Factor)

1See Appendix for further design conditions: Coal type, Plant Location,Financial Criteria, etc.

References: Cost and Performance Baseline for Fossil Energy Power Plants--Volume 1 Bituminous Coal to Electricity, U.S. Department of Energy/National Energy Technology Laboratory, Final Report, May 2007

Presenter
Presentation Notes
Key points: No Air Extraction from Combustion Turbine to ASU - gas turbine vendor performance estimate shows no air extraction possible with H2-rich syngas. Steam lower steam conditions – gas turbine vendor states H2-rich syngas requires lower firing temperature, and thus lower exhaust temperature. This is due to materials concerns resulting from the high water-content in the combustion products. The lower GT exhaust temperature limits the steam temperature. Three Additional Processes CO2 Pressure Loss Thermal Efficiency Loss *Syngas Cooling
Page 10: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

10

New IGCC Power PlantWith SelexolTM CO2 Scrubbing

IGCC CO2 Capture Advantages:1. High PCO22. Low Volume Syngas Stream

SelexolTM CO2 Capture Advantages:1. Physical Liquid Sorbent2. Highly selective for H2S and CO23. CO2 is produced at “some” pressure4. 30+ years of commercial operation (55

worldwide plants)TPD: Short Ton per DayTPY: Short Ton per Year (at 80% Capacity Factor)

1See Appendix for further design conditions: Coal type, Plant Location,Financial Criteria, etc.

References: Cost and Performance Baseline for Fossil Energy Power Plants--Volume 1 Bituminous Coal to Electricity, U.S. Department of Energy/National Energy Technology Laboratory, Final Report, May 2007

Presenter
Presentation Notes
Key points: No Air Extraction from Combustion Turbine to ASU - gas turbine vendor performance estimate shows no air extraction possible with H2-rich syngas. Steam lower steam conditions – gas turbine vendor states H2-rich syngas requires lower firing temperature, and thus lower exhaust temperature. This is due to materials concerns resulting from the high water-content in the combustion products. The lower GT exhaust temperature limits the steam temperature. Three Additional Processes CO2 Pressure Loss Thermal Efficiency Loss *Syngas Cooling Requires Gas Cooling (to ~100oF) and Reheating (to ~500oF) CO2 regenerated at low pressure
Page 11: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

11

0

5

10

15

20

25

30

35

40

45

50

Existing PC New IGCC 40% CO2Capture

60% CO2Capture

70% CO2Capture

90% CO2Capture

Net

Effi

cien

cy (%

HH

V)

35%

39%

36%25 - 35%

34%32%

New IGCC Efficiency

Without CO2 Capture With CO2 Capture

CO2 Capture ’s New IGCC net efficiency by 3 to 8% pts.

References: Cost and Performance Baseline for Fossil Energy Power Plants--Volume 1 Bituminous Coal to Electricity, U.S. Department of Energy/National Energy Technology Laboratory, Final Report, May 2007

Evaluation of Alternate Water Gas Shift Configurations for IGCC Systems, Draft Internal Report,, December 2007

Presenter
Presentation Notes
Bituminous Baseline Costs reported in December 2006$ and Oxycombustion costs reported in January 2007$ and both are considered equivalent.
Page 12: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

12

0

2

4

6

8

10

12

Existing PC New IGCC 40% CO2Capture

60% CO2Capture

70% CO2Capture

90% CO2Capture

Cos

t of E

lect

ricity

(cen

ts/k

wh)

New IGCC Cost of Electricity

Without CO2 Capture

New IGCC with CO2 Capture ’s Existing PC COE by ~ 5X

To Match CA Proposed 1,100 lb/MWh

To Match New NGCC 800 lb/MWh

References: Cost and Performance Baseline for Fossil Energy Power Plants--Volume 1 Bituminous Coal to Electricity, U.S. Department of Energy/National Energy Technology Laboratory, Final Report, May 2007

Evaluation of Alternate Water Gas Shift Configurations for IGCC Systems, Draft Internal Report,, December 2007

Presenter
Presentation Notes
Bituminous Baseline Costs reported in December 2006$ and Oxycombustion costs reported in January 2007$ and both are considered equivalent.
Page 13: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

13

New Pulverized CoalWith and Without CO2 Capture

Page 14: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

14

New Supercritical PC Power PlantNo CO2 Capture

Process Design:Steam: 3500 psig/1110°F/1150°FNOx: LNB, OFA and SCRSOx: Wet limestone FGDPM: Baghouse

CO2 Capture Challenges:Low Pressure: 14.8Low Concentration: 13% volume

Reference: Pulverized Coal Oxycombustion Power Plants—Volume 1 Bituminous Coal to Electricity, U.S. Department of Energy/National Energy Technology Laboratory, Revision 2 Final Report, August 2008

TPD: Short Ton per DayTPY: Short Ton per Year

Page 15: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

15

PC Boiler(With SCR)

Sulfur Removal

ParticulateRemoval

Ash

Coal6,800 TPD

STEAMCYCLE

CO2 CaptureProcess*

ID Fan

Air

CO22,215 psia

661 MWgross550 MWnet

CO2Comp.

Flue Gas

CO2 To Storage14,600 TPD

4,260,000 TPY

Low Pressure Steam

Optional Bypass(<90% Capture)

Process Design:CO2 Capture: 30-90%, compressed to 2,215 psiaBalance of Plant: Oversized to maintain 550 MW net

New Supercritical PC Power PlantAmine Scrubbing CO2 Capture

Reference: Pulverized Coal Oxycombustion Power Plants—Volume 1 Bituminous Coal to Electricity, U.S. Department of Energy/National Energy Technology Laboratory, Revision 2 Final Report, August 2008

TPD: Short Ton per DayTPY: Short Ton per Year

*CO2 Capture Process Flow Diagram in Appendix

Presenter
Presentation Notes
Supercritical Boiler: Once-through, spiral-wound, Benson-boiler, wall-fired, balanced draft, water cooled, dry bottom. Includes superheater, reheater, economizer and air heater. NOx Control: Fitted with low-NOx burners and OFA
Page 16: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

16

Advantages1. Proven Technology Remove CO2

and H2S from NG2. Chemical solvent High loadings at

low CO2 partial pressure3. Relatively cheap chemical ($2-3/lb)4. Small scale commercial experience

Disadvantages1. High heat of reaction high

regeneration energy required

2. Easily degraded by SOx, NOx, PM

3. Post-combustion capture (for food grade CO2) is limited and currently at small scale (<200 TPD)

1. Developed in 1930– Triethanolamine (TEA), first commercially available, used in gas

treating (H2S and CO2 removal)– TEA replaced by amine mixtures (MEA, DEA, MDEA) in the 1950’s

2. 2005—Various proprietary formulations offered by: Fluor Daniel, Dow Chemical, UOP/Union Carbide, Huntsman Corp., BASF, EXXON, MHI, Coastal and others.

Alkanolamines for Acid Gas Removal

Page 17: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

17

Amine Scrubbing ExperienceFluor Econamine FGSM Commercial Plants (2004)

Source: Improvement in Power Generation With Post-Combustion Capture of CO2, IEA GHG Report Number PH4/33, November 2004

Page 18: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

18

0

5

10

15

20

25

30

35

40

45

50

Existing New 30% CO2Capture

50% CO2Capture

70% CO2Capture

90% CO2Capture

Net

Effi

cien

cy (%

HH

V)

33%

39%

35%

25 - 35%

31%28%

New PC Efficiency

Without CO2 Capture With CO2 Capture

CO2 Capture ’s New PC net efficiency by 4 to 12% pts.

References: Pulverized Coal Oxycombustion Power Plants—Volume 1 Bituminous Coal to Electricity, U.S. Department of Energy/National Energy Technology Laboratory, Revision 2 Final Report, August 2008

Integrated Environmental Control Model 2008

Presenter
Presentation Notes
Bituminous Baseline Costs reported in December 2006$ and Oxycombustion costs reported in January 2007$ and both are considered equivalent.
Page 19: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

19

0

2

4

6

8

10

12

Existing New 30% CO2Capture

50% CO2Capture

70% CO2Capture

90% CO2Capture

Cos

t of E

lect

ricity

(cen

ts/k

wh)

New PC Cost of Electricity

Without CO2 Capture With CO2 Capture

References: Pulverized Coal Oxycombustion Power Plants—Volume 1 Bituminous Coal to Electricity, U.S. Department of Energy/National Energy Technology Laboratory, Revision 2 Final Report, August 2008

Integrated Environmental Control Model 2008

CO2 Capture ’s Existing COE by ~ 4 — 5X

To Match CA Proposed 1,100 lb/MWh

To Match New NGCC 800 lb/MWh ~ 65% Capture

Presenter
Presentation Notes
Bituminous Baseline Costs reported in December 2006$ and Oxycombustion costs reported in January 2007$ and both are considered equivalent.
Page 20: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

20

Existing Pulverized CoalWith CO2 Capture

Page 21: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

21

Key Challenges to PC CO2 Retrofits1. Space limitations — acres needed for current scrubbing2. Major equipment modifications3. Regeneration steam availability — can steam turbine operate

at part load using current scrubbing technology?4. Sulfur — additional deep sulfur removal required using

current CO2 scrubbing technology 5. Make-up power — satisfy need to maintain baseload output6. *Water availability7. *Local storage availability (saline formation, EOR)8. *Scheduling outages for CO2 retrofits9. *Post-retrofit dispatch implications due to increase in COE10. *Retrofit triggering New Source Review11. *Proposed legislation

*Analyses on these topics is currently in progress at NETL, beyond the scope of today’s presentation

Presenter
Presentation Notes
Main driver is the Global Climate Change Initiative
Page 22: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

22

Case Study: AEP Conesville Unit #5• Total 6 units = 2,080 MWe• Unit #5:

– Subcritical steam cycle (2400psia/1005oF/1005oF)*– Constructed in 1976– 463 MW gross (~430 MW net)– ESP and Wet lime FGD (95% removal efficiency, 104 ppmv)

Ultimate Analysis (wt.%) As Rec’d

Moisture 10.1

Carbon 63.2

Hydrogen 4.3

Nitrogen 1.3

Sulfur 2.7

Ash 11.3

Oxygen 7.1

HHV (Btu/lb) 11,293

Mid-western bituminous coal

Reference: CO2 Capture From Existing Coal-Fired Power Plants, U.S. Department of Energy/National Energy Technology Laboratory, Revised Final Report, November 2007

Presenter
Presentation Notes
*subcritical conditions represent the most common steam cycle operating conditions for the existing US fleet of utility scale power generation systems (pg 8) 1. 5 elevations of tangentially fired coal burners Balanced draft mode with slight negative furnace pressure ‘Conventional Arch’ type design (see figure 2-2) Mid-western bituminous coal
Page 23: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

23

Existing PC Plant CO2 Capture ModificationsConesville Unit #5

Reference: CO2 Capture From Existing Coal-Fired Power Plants, U.S. Department of Energy/National Energy Technology Laboratory, Revised Final Report, November 2007

Presenter
Presentation Notes
Operation and performance of the existing boiler, air heater and ESP does not change Steam cycle configuration and performance does change The FGD system is modified to meet <10 ppmv SO2 CO2 is compressed to 2,200psi
Page 24: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

24

0

5

10

15

20

25

30

35

40

ConesvilleUnit #5

30% CO2Capture

50% CO2Capture

70% CO2Capture

90% CO2Capture

Net

Effi

cien

cy (%

HH

V)

29%

32%

35%

27%

24%

Existing PC EfficiencySame trend as “New Plant”

With

out C

O2

Cap

ture

CO2 Capture ’s net efficiency by 3 to 11% pts.

Reference: CO2 Capture From Existing Coal-Fired Power Plants, U.S. Department of Energy/National Energy Technology Laboratory, Revised Final Report, November 2007

Presenter
Presentation Notes
Bituminous Baseline Costs reported in December 2006$ and Oxycombustion costs reported in January 2007$ and both are considered equivalent.
Page 25: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

25

Existing PC Base Load Output ImpactPost CO2 Retrofit Losses to Grid

0

50

100

150

200

250

300

350

400

450

500

Conesville Unit #5 30% Capture 50% Capture 70% Capture 90% Capture

Net

Out

put (

MW

)

303 MW

333 MW

363 MW

392 MW

434MW 131 MW30% Loss

101 MW23% Loss

71 MW16% Loss

42 MW10% Loss

Reference: CO2 Capture From Existing Coal-Fired Power Plants, U.S. Department of Energy/National Energy Technology Laboratory, Revised Final Report, November 2007

With

out C

O2

Cap

ture

Page 26: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

26

0

2

4

6

8

10

12

ConesvilleUnit #5

New PC 30% CO2Capture

50% CO2Capture

70% CO2Capture

90% CO2Capture

Cos

t of E

lect

ricity

(cen

ts/k

wh)

Existing PC Cost of ElectricityExisting Fleet Retrofit Advantage!

No Capture

References: Pulverized Coal Oxycombustion Power Plants—Volume 1 Bituminous Coal to Electricity, U.S. Department of Energy/National Energy Technology Laboratory, Revision 2 Final Report, August 2008

Integrated Environmental Control Model 2008

Retrofit an Existing PC Plant up to ~40% CO2 capture will have lower

COE than New PC Plant w/o Capture

Make-up power = 6.5 cents/kWh Make-up power = 12 cents/kWh

Presenter
Presentation Notes
Bituminous Baseline Costs reported in December 2006$ and Oxycombustion costs reported in January 2007$ and both are considered equivalent.
Page 27: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

27

Summary Results Comparison

Page 28: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

28

0

5

10

15

20

25

30

35

40

45

50

Existing PC New SCPC New IGCC Existing Plant New SCPC New IGCC

Net

Effi

cien

cy (%

HH

V)

39%

28%

32%

39%

25%

25-35%

Power Plant Efficiency SummaryWith 90% CO2 Capture

No CO2 Capture 90% CO2 Capture

Presenter
Presentation Notes
Bituminous Baseline Costs reported in December 2006$ and Oxycombustion costs reported in January 2007$ and both are considered equivalent.
Page 29: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

29

0

2

4

6

8

10

12

14

Existing PC New PC New IGCC Existing PC New SCPC New IGCC

Cost

of E

lect

ricity

(cen

ts/k

Wh)

Cost of Electricity SummaryWith 90% CO2 Capture

No CO2 Capture 90% CO2 Capture

’s Existing COE by ~ 3 — 4X

’s Existing COE by ~ 5X

Presenter
Presentation Notes
Bituminous Baseline Costs reported in December 2006$ and Oxycombustion costs reported in January 2007$ and both are considered equivalent.
Page 30: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

30

CO2 Capture Summary1. New Integrated Gasification Combined Cycle

• For a 600 MW plant, @90% Capture 13,000 TPD or 3.6MM TPY removed• One current state-of-the-art technology option is SelexolTM

• CO2 Capture “Parasitic Load” ’s net efficiency by 3 - 8% points• Cost of electricity 4 - 5X Existing average pulverized coal fleet cost

2. New Pulverized Coal• For a 600 MW plant, @90% Capture 15,000 TPD or 4.3MM TPY removed• Current SOA technology is amine-based scrubbing (Econamine, KS-1)• CO2 Capture “Parasitic Load” ’s net efficiency by 4 - 12% points• Cost of electricity 4 - 5X Existing average pulverized coal fleet cost

3. Existing Pulverized Coal • NETL Existing PC Study Concluded that major no technical barriers exist with

retrofitting with amine-based CO2 capture from 30% to 90% removal• CO2 Capture “Parasitic Load” net efficiency by 3 - 11% points• Existing PC plant will lose ~120 MW to grid! (532 MWe 413 MWe)

4. Water usage • Existing PC by 40% • New PC >> IGCC

*Depending on the cost of Make-up-power

Page 31: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

31

Appendix

Page 32: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

32

Design Basis: Bituminous Coal Type

Illinois #6 Coal Ultimate Analysis (weight %)As Rec’d Dry

Moisture 11.12 0Carbon 63.75 71.72

Hydrogen 4.50 5.06Nitrogen 1.25 1.41Chlorine 0.29 0.33

Sulfur 2.51 2.82Ash 9.70 10.91

Oxygen (by difference) 6.88 7.75100.0 100.0

HHV (Btu/lb) 11,666 13,126

Presenter
Presentation Notes
Recent data from the Henry Hub Spot Price index indicate a natural gas price in the $8.80/MMBtu range. This will have a tremendous affect on our results, since it is ~50% higher than our cost. We should perform a sensitivity analysis of fuel price (including coal) vs. LCOE
Page 33: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

33

IGCC Environmental Targets

Pollutant Environmental Target NSPS Limit1 Control

Technology

NOx 15 ppmv (dry) @15% O2

1.0 lb/MWh(0.117 lb/MMBtu)

LNB and syngas nitrogen dilution

SO2 0.0128 lb/MMBtu1.4 lb/MWh

(0.163 lb/MMBtu)Sulfinol (NC)Selexol (CC)

PM 0.0071 lb/MMBtu 0.015 lb/MMBtu Quench, water scrubber

Hg >90% Removal20x10-6 lb/MWh

(2.3 lb/TBtu)Carbon Bed

NSPS: New Source Performance StandardsNC: No CO2 Capture CC: CO2 Capture Case

Based on EPRI’s CoalFleet for Tomorrow Initiative design basis

1Value in parenthesis is calculated based on a heat rate of 8,570 Btu/kWh from the non-capture IGCC case

Page 34: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

34

New Pulverized Coal Environmental Targets

Pollutant Environmental Target NSPS Limit Control

Technology

NOx 0.07 lb/MMBtu1.0 lb/MWh

(0.111 lb/MMBtu)LNB, OFA, SCR

SO2 0.119 lb/MMBtu1.4 lb/MWh

(0.156 lb/MMBtu)Wet Limestone

Scrubber

PM 0.015 lb/MMBtu 0.015 lb/MMBtu Fabric Filter

Hg 0.70 lb/TBtu20x10-6 lb/MWh

(2.2 lb/TBtu)Co-benefit

capture

NSPS: New Source Performance StandardsLNB: Low NOx BurnersOFA: Over-fired airSCR: Selective Catalytic Reduction

Based on BACT analysis, exceeding new NSPS requirements

Page 35: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

35

Total Plant Cost

•Includes– Equipment

• Initial chemicals and catalyst loadings

– Materials– Labor

• Direct and Indirect– Engineering and

Construction Management

– Project and Process Contingencies

•Excludes– Owner’s costs

• Land, licensing and permitting, AFUDC

– Escalation to period of performance

– Taxes (except payroll)– Site specific

considerations– Labor incentives in

excess of 5 day/10 hour work week

– EPC premiums

Page 36: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

36

0

500

1,000

1,500

2,000

2,500

3,000

3,500

Supercritical Ultra-supercritical

Supercritical Ultra-supercritical

Tota

l Pla

nt C

ost (

$/kW

) 2,810

1,643

2,855

1,579

New PC Capital Cost

Without CO2 Capture With 90% CO2 Capture

Reference: Pulverized Coal Oxycombustion Power Plants—Volume 1 Bituminous Coal to Electricity, U.S. Department of Energy/National Energy Technology Laboratory, Revision 2 Final Report, August 2008

CO2 Capture ’s TPC by ~$1,300/kW

Presenter
Presentation Notes
Bituminous Baseline Costs reported in December 2006$ and Oxycombustion costs reported in January 2007$ and both are considered equivalent.
Page 37: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

37

IGCC Total Plant Cost Summary

Without CO2 Capture With CO2 Capture

CO2 Capture ’s TPC by ~$580-690/kW

Tota

l Pla

nt C

ost (

$/kW

)

Note: See Appendix for Total Plant Cost Line Items Included and Excluded

Presenter
Presentation Notes
Notes: CO2 Capture increases TPC between $580-700/kW
Page 38: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

38

Economic AssumptionsFinancial Structure

Type of Security % of Total

Current (Nominal)

Dollar Cost

Weighted Current

(Nominal) Cost

After Tax Weighted Cost

of CapitalLow Risk

Debt 50 9% 4.5% 2.79%Equity 50 12% 6% 6%

11% 8.79%High Risk

Debt 45 11% 4.95% 3.07%Equity 55 12% 6.6% 6.6%

11.55% 9.67%

High Risk Low RiskCapital Charge Factor 0.175 0.164

Coal Levilization Factor 1.1439 1.1485General O&M Levelization Factor 1.1607 1.1660

Page 39: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

39

Economic AssumptionsParameter Assumptions

Parameter Value

Income Tax Rate38% Effective (34% Federal, 6% State less 1% Property and 1% Insurance)

Repayment Term of Debt 15 years

Grace Period on Debt Repayment 0 years

Debt Reserve Fund None

Depreciation 20 years, 150% Declining Balance

Working Capital Zero for all parameters

Plant Economic Life 30 years

Investment Tax Credit 0%

Tax Holiday 0 years

Start-up Costs (% EPC) 2%

All other additional costs ($) 0

EPC escalation 0%

Duration of Construction 3 years

Page 40: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

40

CO2 Mitigation Costs

CO2 Avoided (COEcapture – COEbase)

(Emissionsbase – Emissionscapture)

CO2 Captured(COEcapture – COEbase)

(CO2 Removed)0 0.2 0.4 0.6 0.8 1

CapturePlant

ReferencePlant

tonne CO2/kWh

CO2 Avoided

CO2 Captured

Page 41: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

41

CO2 Capture Process

Presenter
Presentation Notes
Structured packing Advantages *Very low pressure drop (minimize fan horsepower) *High contact efficiency/low packing height *Good tolerance for maldistribution in a large tower *Smallest possible tower diameter
Page 42: Indiana Carbon Capture & Sequestration Summit · 7. 80 100 120 140 160 180 200 2000 2001 2002 2003 2004 2005 2006 2007 Q3 2007 Q1 2008. Year Cost Index (2000 = 100) CERA Power Capital

42

SelexolTM Scrubbing

To ClausH2S/CO2

Steam 120 MMBtu/hr

Stage 1H2S Absorber(2 Columns)

H2S Concentrator

N2 PurgeH2S/CO2 Acid Gas Stripper

Makeup60 gpd

MP Flash

LP Flash

Stage 2CO2 Absorber(4 Columns)

17% total CO297 Mol % CO2

35% total CO299 Mol % CO2

HP Flash

To TurbineFuel Gas6 MMscfd

95oF/495 psia

H2S/CO2 RichShifted Syngas100oF/500 psia

Lean Selexol10,000 gpm

CO2 Rich

CO2 Rich Selexol

10,000 gpm

Semi-Lean Selexol50,000 gpm

Reabsorber

13% total CO278 Mol% CO2

35% total CO278 Mol % CO2

300 psia

160 psia

50 psia

400 psia


Recommended