February 2011
INDONESIA’S POWER SECTOR: SECTORAL
EMISSIONS PROFILE AND MITIGATION
OPPORTUNITIES
CE
NT
ER
F
OR
C
LE
AN
A
IR
P
OL
IC
Y
Di
al
og
ue
.
In
si
gh
t.
So
lu
ti
on
s
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 2 12/20/2011
ACKNOWLEDGMENTS
This report was prepared by Nitin Zamre and Rashika Agrawal of ICF International and Thomas
Polzin and Anmol Vanamali from the Center for Clean Air Policy. The authors also thank the
main sponsor of this report, the Center for Clean Air Policy (CCAP), and especially Matthew
Ogonowski and Ned Helme. The authors would also like to thank Pelangi Indonesia for their
valuable input throughout the process.
The authors would like to thank Jos Wheatley and Sarah Love of the UK Department for
International Development (DFID) for their generous financial support for the project. The
authors would also like to thank Agus Purnomo from DNPI for his support for this project. For
avoidance of any doubt and for the purpose of clarity, the authors would like to state that this
report is based on an independent study. The contents of the report reflect the views of the
authors and not necessarily the views of the UK or Indonesian governments.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 3 12/20/2011
Table of Contents
I. Electricity Sector Overview ...........................................................................................5
I.A. Summary ..........................................................................................................................9 I.A.1. Total Output/Production ................................................................................................9 I.A.2. Revenues, share of GDP ...............................................................................................10 I.A.3. Role of power sector in overall economy ....................................................................11
I.B. Quantitative and Qualitative Characterization of Sector .................................11 I.C. Ownership patterns of the sector.....................................................................12
II. Emissions overview of the sector .................................................................................14 II.A. Background and Discussion of Emissions: Sources, Drivers, and Trends ......14 II.B. Historical annual CO2 emissions from power sector ........................................15
III. Background Assumptions for Sector Analysis ...........................................................17 III.A. Fuel Prices & Emission Factors .......................................................................17 III.B. New Capacity .....................................................................................................17
III.C. Policies included ................................................................................................19 III.D. Demand ..............................................................................................................19
III.E. Reserve Margin Requirements ........................................................................19 III.F. Transmission .....................................................................................................20
IV. Description of analytical model and methodology used ....................................21
V. Baseline (Business as Usual) scenario for the electricity sector ................................22 V.A. Production/output .................................................................................................22
V.B. Annual GHG Emissions .......................................................................................25 V.C. Energy intensity and CO2 intensity .....................................................................27
VI. GHG Mitigation Options and Costs ............................................................................29 VI.A. Selection criteria for consideration of mitigation options .................................29
VI.B. Overview of each mitigation option considered .................................................29
VII. Analysis of GHG Mitigation Scenarios .......................................................................34 VII.A. Mitigation Scenario in 2020 .................................................................................34
VII.B. Mitigation Scenarios in 2030 ................................................................................40 VII.C. Demand Side Management Measures .................................................................45
VII.D. Summary of Mitigation Scenarios Analysis .......................................................46 VIII. Cost Summary .......................................................................................................48
IX. Results Comparison ..............................................................................................50 IX.A. Indonesian Climate Change Sectoral Roadmap by BAPPENAS .....................50 IX.B. Indonesia’s Greenhouse Gas Abatement Cost Curve by DNPI .......................51 X. Conclusions and Next Steps .................................................................................53
APPENDIX 1 .............................................................................................................................55 APPENDIX 2 .............................................................................................................................58 APPENDIX 3 .............................................................................................................................59
APPENDIX 4 .............................................................................................................................60 APPENDIX 5 .............................................................................................................................60 APPENDIX 6 .............................................................................................................................61 APPENDIX 7 .............................................................................................................................63 APPENDIX 8 .............................................................................................................................64 APPENDIX 9 .............................................................................................................................65
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 4 12/20/2011
APPENDIX 10 ...........................................................................................................................66 Applications of the IPM®...................................................................................................66 IPM® Modelling Approach ...............................................................................................67
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 5 12/20/2011
I. Executive Summary
I.A. Introduction
Of the 17,000 islands that constitute the archipelagic nation of Indonesia, only two, Java and
Sumatra, account for 90% of the electricity demand. Electricity consumption in Indonesia has
grown at an average rate of 9% from 1990 to 2005 and at 6% from 2001 onwards. As shown in
the table majority of Indonesia’s electricity is generated using fossil fuels.
Capacity Type
Capacity (GW)
Generation (TWh)
CO2 Emissions
(Million Metric Tons)
Average Efficiency (%)
Average CO2 Intensity (Metric
Ton/TWh)
Coal 8 56 51 34% 0.91
Gas 7 26 12 40% 0.46
Oil 11 29 21 31% 0.73
Hydro 4 11 - - -
Geothermal 1 3 0 - -
Total 30 125 84 - -
The Government of Indonesia has taken a series of progressive and regressive steps which have
hitherto ensured government control of the electricity sector. Two-thirds of the generating
capacity is owned by PLN, the stated-owned utility and there is an acute need of private
investment. The power sector in Indonesia faces issues such as government regulated electricity
tariffs which do not reflect the actual cost of supply, lack of investment supporting policies with
a well defined criteria for financial investments, lack of regulation on fuel costs for captive plants
and IPPs which have led to low participation of private sector in the power sector. Emissions
from power sector emissions have grown historically at an average rate of 6% per annum since
1990 reaching to a level of approximately 85 MtCO2 in 2005.
I.B. Analysis
I.B.1. Methodology
The study was conducted in three phases viz (1) Estimate emission upto 2030 under BAU
scenario (2) Estimate impact of a range of carbon prices on emissions from the electricity sector
and (3) Analyze effectiveness of other mitigation policies in comparison with various carbon
price scenarios. These analysis was performed using IPM, a proprietary cost-optimization
developed by ICF International that specifically designed to analyze effects of policy choices on
electricity networks by taking into account assumptions on growth, demand and supply patterns,
commodity price assumptions and policy choices (such as a carbon taxes). This report lays down
details of the first and second phases.
I.B.2. BAU Projections
Installed capacity is expected to grow to 243 GW by 2030 with coal-based generation accounting
for more than half of it.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 6 12/20/2011
Installed Capacity under BAU
Year
Annual Installed Capacity (GW)
Coal Natural Gas Oil Nuclear Hydro (>10MW) Other* Total
Sub-Critical Super-Critical
2005 8 - 7 11 0 4 1 30
2010 12 1 9 11 0 4 1 38
2015 21 5 15 13 0 5 5 64
2020 24 19 24 18 0 6 9 99
2025 29 41 39 28 0 6 10 153
2030 37 79 64 44 0 7 12 243
Installed Renewable Capacity under BAU
Year Annual Installed Capacity (GW)
Small Hydro (<10MW) Geothermal Biomass Total
2005 0.1 0.8 0.0 0.9
2010 0.1 1.1 0.0 1.2
2015 0.2 5.3 0.1 5.6
2020 0.2 8.9 0.2 9.3
2025 0.2 10.1 0.3 10.6
2030 0.2 11.3 0.4 11.9
The electricity sector of Indonesia has been growing at a rate of 9% from 1990 to 2005. GHG
emissions in the electricity sector were approximately 83 MtCO2 in 2005. As per this study’s
projections, GHG emissions under a BAU scenario reached 268 MtCO2 by 2020 with a CAGR
of 7%, while reaches 688 MtCO2 by 2030, with a CAGR of 13%. After calculating baseline
emissions, our study studied the impact on the electricity system of a carbon tax ranging from
10$/tCO2 to $90/tCO2. These scenarios were analyzed with the help of a proprietary cost
optimization model developed by our partner consultants ICF International. The The mitigation
options considered reflect options that the Indonesian government have with a new carbon price.
Different options could evolve based on different carbon prices as reflected in our analysis. For
the purposes of our analysis we focused on 2020 and 2030 as our target years to be able to
directly compare to existing analysis as well as to Indonesia’s climate targets.
I.B.3 GHG Mitigation Options
In this paper, step-by-step analysis was done by imposing a carbon cost on the business as usual
(BAU) case, starting at $10/tCO2 and increasing it by $10/ tCO2 in successive iterations. In every
stage, the changes related to capacity mix, generation mix, emissions level and investment
requirements over BAU were noted. Imposition of carbon cost on the system (in BAU scenario)
would in-effect prompt changes viz. retirement of inefficient capacity, conversion of existing
inefficient plants to more efficient plants, preference of more efficient or gas based capacity as a
resort for system expansion and increase in proportion of renewable energy in the generation
mix. However, different combinations of these changes would occur at different carbon costs.
I.C. Overview of Results
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 7 12/20/2011
I.C.1. Analysis of GHG Mitigation Scenarios
The findings for the variouis mitigation scnarios for the years 2020 and 2030 are illustrated
though an (a) emissions profile (b) installed capacity (c) generation mix and (d) resulting
emissions reduction compared to BAU at a range of carbon prices (0-$80/tCO2)
In 2020, the abatement potential observed under a carbon price of $80/tCO2 32 MtCO2 without
DSM and 54 MtCO2 with DSM. In 2030, the abatement potential observed under a carbon price
of $80/tCO2 is 115 MtCO2 without DSM and 218 MtCO2 with DSM. The reduction in
emissions are due to changes in the system generation mix brought upon by imposing a carbon
price which simultaneiously penalizes dirtier sources (e.g. sub-critical coal) while incentivizing
cleaner sources (e.g. geothermal). The majority of the emissions reductions from the BAU are
achieved through introduction of cleaner sources such as Biomass, IGCC, Nuclear, Hydro, and
Geothermal in varying proportions that replace dirtier srouces uch as Gas, Coal (sub and super-
critical) and Oil.
I.C.2. Summary of Results
Emissions from the power sector are expected to increase to 268 MtCO2 by 2020, and under the
mitigation scenarios, Indonesia has the maximum potential to abate approximately 54MtCO2 in
2020 at a carbon price of $80/tCO2, which contributes to approximately 7% of the total emission
targets of 26% announced by the Indonesian Government. Of this total abatement, contribution
from DSM towards emission reduction can be significant: up to 20 MtCO2 in 2020. By 2030, the
maximum abatement that can be achieved by Indonesia is approximately 200 MtCO2 and of
which 50% can be achieved through DSM programs under our assumptions. Under the Dynamic
MACC analysis, assuming all else is constant, the choice of generation mix depends on two
primary external variables – carbon price and the time period under consideration. The higher the
carbon price, the more incentive to introduce cleaner technologies in order to displace dirtier
ones and the longer the time period, the higher the ability of clean projects to earn their returns
and hence prove more profitable than dirtier ones.
Indonesian policymakers should accordingly focus on implementing mitigation measures with a
longer time frame in mind and an incentive mechanism (imposing a carbon price on emissions is
one method that we consider) that financially incentivizes clean energy technology while
simultaneously penalizes polluting ones.
I.C.3. Conclusion
This analysis suggests that the power sector can contribute to emissions reductions of around 54
MtCO2 and 219 MtCO2 by 2020 and 2030 respectively. While our study suggests that there is a
large potential to reduce electricity demand by increasing the potential of energy efficient
technologies (or DSM), the supply side analysis done in this report demonstrates that the
imposition of a carbon price will also be successful in reducing emissions and making the
generation mix cleaner.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 8 12/20/2011
A mitigation potential of 32 MtCO2 and 115 MtCO2 exists by years 2020 and 2030
respecectively (not considering reduced demand from DSM) at a carbon price of $80/tCO2. A
high carbon price scenario may not be feasible in the short –to-medium term, but policy-makers
have a range of domestic policy options that could to lead to the replacement of dirty/inefficient
sources of energy to cleaner ones.
The mitigation analysis presented in this paper is designed for policymakers and industry alike to
evaluate possible implications of different mitigation scenarios. A broad range of carbon price
and integrated demand side management scenarios are presented so that the optimal mitigation
policies and actions can be realized. Policymakers should view this analysis as a resource to
determine whether their public policy decisions can be viewed as effective and efficient. Industry
can subsequently view the analysis to determine what effect public policy decisions will have on
the generation and capacity mix of Indonesia and invest accordingly
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 9 12/20/2011
I. Electricity Sector Overview
I.A. Summary
I.A.1. Total Output/Production
The archipelagic geography has outlined the electricity sector in Indonesia. More than 17,000
islands constitute this country and all but two are electrically isolated. Only 5 islands are densely
populated viz. Java, Sumatra, Kalimantan, Sulawesi and Irian Jaya with a majority of electricity
demand centers residing in Java and Sumatra. Together, they account for 90% of the total
electricity demand in Indonesia.
Historically, most of the isolated and off-grid systems relied on oil-based power plants,
especially diesel plants and some oil-steam plants. Furthermore, outside of the Java-Bali system
oil plants were used extensively. The main reason for this has been the availability of oil fuels
and ease of oil fuels transportation across islands, and even into remote areas.
Table 1: Indonesia's Electric Power Output
Installed Capacity1 (GW) Power Generation
2 (TWh)
1992 11 42
1993 14 47
1994 14 51
1995 15 59
1996 16 67
1997 19 77
1998 21 78
1999 21 85
2000 21 93
2001 21 102
2002 21 108
2003 21 113
2004 21 120
2005 23 127 1
Installed capacity of PLN Plants 2
Electricity produced from power plants of PLN and the power purchased by PLN
Source: Indonesia Energy Outlook & Statistics 2006
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 10 12/20/2011
Figure 1: Development of Indonesia's Power System
Historically, the growth of Indonesia’s power sector has been very sluggish. As shown in Table 1
over 1992-2005, the PLN’s installed capacity has grown at a Compound Annual Growth Rate
(CAGR) of 6% with almost negligible change in installed capacity over 1998-2004. Similarly, the
total electricity supplied by PLN has grown at a CAGR of 9% over 1992-2005 with average
growth of 6% since 2001.
I.A.2. Revenues, share of GDP
While the economy has grown at an average rate of 6% per annum over the last 5 years (2005-
2009), the revenue generated from power sector has grown at an average rate of 10%1. However,
the percent share contribution of power sector to the national economy has been consistent over
the same period at an average 1% per annum. In 2009, the power sector contribution to the total
GDP of $5,613 Billion (at current price) was merely $1 Billion2.
This dismal contribution of power sector to the national economy can be attributed to the
inability of the government to reflect the real cost of electricity generation in the consumer
power tariffs in Indonesia. The Indonesian government, which decides the power tariffs in
Indonesia, has failed to revise the tariffs since 2003 due to strong public agitation against tariff
hikes.
The Presidential Decree No. 104, 2003 was the last decree passed for power tariff revision in
Indonesia. The decree created a uniform tariff structure in all regions of the country with the
tariff divided among various consumer categories.
1 Statistics from Bank of Indonesia, March 2010
2 Statistics from Bank of Indonesia, March 2010
0
5
10
15
20
25
1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005
(GW
)
0
20
40
60
80
100
120
140
(TW
h)
Installed Capacity of PLN Power Plants (GW)
Electricity produced by PLN's Power Plants and Power purchased by PLN (TWh)
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 11 12/20/2011
I.A.3. Role of power sector in overall economy
The electricity consumption in Indonesia has grown at an average rate of 9% from 1990 to
20053. Although the industrial sector has dominated the electricity consumption among the
different consumer categories, its share in the total electricity consumption has dropped from
56% in 1990 to 41% in 2005. Over the same period, the share of residential consumption has
increased from 29% to 37% mainly due to increase in electrification ratio and extremely slow
pace of increasing electricity tariffs. Also, the electricity consumption of commercial consumer
has increased from 15% to 22% over 1990-2005 while the transportation sector has had a
consistent level of electricity consumption. Figure 2 illustrates the electricity consumption
pattern of different consumer categories over time.
Figure 2: Electricity Consumption by Sector
I.B. Quantitative and Qualitative Characterization of Sector
By the end of 2005, 53% of installed capacity was based on oil and gas. Despite being one of the
largest net exporters of coal in the world, coal supported only 33% capacity in Indonesia. Also,
hydro supported 12% of installed capacity while the rest was based on geothermal and biomass
resources, which are abundantly available in Indonesia.
Table 2 below provides details of Indonesia installed capacity in 2005 across various fuels, while
Figure 3 lays out the age characterization of the installed capacity. As can be observed most of
the plants in Indonesia are old and falls in the 5-20 years age category.
Table 2: Breakdown of facilities by fuel type, 2005
Capacity Type
Capacity (GW)
Generation (TWh)
CO2 Emissions
(Million Metric Tons)
Average Efficiency (%)
Average CO2 Intensity (Metric
Ton/TWh)
Coal 8 56 51 34% 0.91
Gas 7 26 12 40% 0.46
Oil 11 29 21 31% 0.73
3 Indonesia Energy Outlook and Statistics, 2006
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 12 12/20/2011
Capacity Type
Capacity (GW)
Generation (TWh)
CO2 Emissions
(Million Metric Tons)
Average Efficiency (%)
Average CO2 Intensity (Metric
Ton/TWh)
Hydro 4 11 - - -
Geothermal 1 3 0 - -
Total 30 125 84 - -
Source: PLN Statistics, ICF Research on Captive Plants
Note: Data on 2005 Installed capacity in Indonesia includes 7GW of existing captive capacity
Figure 3: Age Characterization of Installed Capacity (2008)
I.C. Ownership patterns of the sector
The national government of Indonesia has been responsible for the development and
administration of electricity sector for the last half century4. The state-owned electric utility PT
PLN, through its subsidiaries, carries out the functions of generation, transmission and
distribution of electricity in Indonesia. It operates nearly two-third of country’s generating
capacity while the rest is owned by IPPs and captive power producers.
Captive capacity, which totals 6,560 MW, has been installed by industries that do not have an
easy access to the PLN’s distribution grid or that provide backup for PLN’s service5.
Approximately, 60% of the captive capacity is based on diesel while the rest comes from
cogeneration. Of the total captive capacity in Indonesia, approximately 4,000 MW capacity
provides backup to PLN services6. However, there are other reports
7 which state the total captive
capacity to be much higher than 6.5 GW. Since the details of the additional capacity are not
accessible the same has not been considered in this analysis.
4 http://pdf.wri.org/powerpolitics_chap5.pdf
5 http://pdf.wri.org/powerpolitics_chap5.pdf
6 PLN
7 Electric Power Sector in Indonesia, U.S. Commercial Service, CS Jakarta, 11/8/2005
0
1
2
3
4
5
6
7
8
9
< 5 Years 5-9 Years 10-14
Years
15-19
Years
20-24
Years
25-29
Years
30-34
Years
35-39
Years
> 40 Years
Insta
lle
d C
ap
acity (
GW
)
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 13 12/20/2011
The Electricity Law, passed in 1985, encouraged the participation of private enterprises in power
sector without promoting competition in electricity business. It provided opportunity to the
private companies to participate in power sector by operating power plants for sale of electricity
to PLN only. However, the law came into effect when the necessary accompanying regulations
were promulgated through the Presidential Decree No. 37 in 1992, which invited the private
sector investors for operating large scale Independent Power Plants (IPPs) for sale of electricity
to PLN. This led to nearly 25 IPPs entering the power system, from 1994-1997.
In September 2002, Indonesia enacted Law No. 20 to transform the monopolistic structure of the
power sector into a limited competitive market within a five-year time frame. It emphasized the
efficient, transparent and competitive provision of electricity supply along with providing equal
treatment to all market players including PLN. It encouraged the establishment of an independent
market regulator and market operator.
However, the government later revoked the Law 20/2002 stating that electricity is a ―wealth for
the people‖ should be under full control of the State and hence, should be viewed as integrated
business rather than being unbundled. The annulment of this law drove the power sector’s re-
structuring process back to the starting point.
These drastic changes in the government policies for the sector restructuring provided an
uncertain environment for the investors which led to miniscule capacity additions during this
period. In order to re-instate confidence in electricity business, the government issued
Regulations No.3/2005 to address general planning on power requirement, role of private players
in power sector, priority for renewable energy sources and the pricing policy. The new
regulations establish the National Electricity General Plan under the auspices of the Government
of Indonesia along with the development of yearly Electrical Power Supply Plan by PLN and
approved by MEMR. It established that the electricity prices and the permits to conduct
electricity business for public use have to be issued by the government.
Despite these efforts, many problems remain. The power sector in Indonesia faces issues such as
government regulated electricity tariffs which do not reflect the actual cost of supply, lack of
investment supporting policies with a well defined criteria for financial investments, lack of
regulation on fuel costs for captive plants and IPPs which have led to low participation of private
sector in the power sector. At present, there are nearly 35 IPPs in Indonesia, operating only 12%
of the total installed capacity in Indonesia (2,588 MW).
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 14 12/20/2011
II. Emissions overview of the sector
II.A. Background and Discussion of Emissions: Sources, Drivers, and Trends
Historically, Indonesia was one of the largest oil producers. After reaching their peak production
in 1991, oil reserves started declining and in 2005, Indonesia became a net oil importer.
However, the dependency on oil for the country’s energy needs has not reduced. The continued
dependency on oil for power generation is due to the oil price subsidies provided by the
government, which encourage economic inefficiencies. Indonesia oil subsidies are amongst the
largest in the world amounting to almost 3% of Indonesia’s GDP and 30% of the government.8
The high prices and extreme volatility in international oil prices over the last few years has
increased the subsidy burden on the Government exchequer. In order to mitigate this exposure
and reduce the dependency on imported fuel, the government initiated fast track programs to
promote other fuels (coal, gas and renewables) in the capacity mix, and is also encouraging a
switch from oil based capacity to gas or coal based capacity.
Coal is Indonesia’s largest fossil fuel resource. Indonesia’s coal reserves are fairly well
distributed along the islands of Sumatra, Kalimantan, Sulawesi and Papua. Of the total estimated
coal reserves of 90.45 billion tons, Indonesia has mineable coal reserves of around 18.71 billion
tons. The quality of coal varies and mostly consists of lignite (24.4%), sub-bituminous (61.45%),
bituminous (13.02%) and little amount of anthracite. The calorific value of Indonesian coal
ranges between 5,000-7,000 kcal/kg.
The average growth rate of coal production in Indonesia over 2000-2005 was 14% per annum
and most of this growth was export-oriented owing to the high international coal prices. The
share of coal exports from total production during this period has been in excess of 70%. Of the
total domestic consumption during 2000-2005, the coal consumption in electricity sector has
remained rather flat owing to little coal based capacity additions. However, the coal consumption
for the electricity sector is becoming increasingly more important with the decrease in oil and
gas reserves and increasing power demand. To address these issues, the Indonesian government
through Law Number 4 of 2009 concerning Mineral and Coal Mining in Indonesia, aims to curb
the excessive coal exports and make it available for domestic consumption. This would help
achieve the targeted coal capacity planned under first and second 10,000 MW crash programs.
The story with natural gas is very similar. Despite having one of the highest natural gas reserves
in the world, the domestic gas consumption is among the lowest. The main obstacle to rapid
development and to expanded utilization of gas has been Indonesia’s energy pricing policy and
gas development issues both in upstream and downstream infrastructure.
For the last two years, export of oil and gas has contributed approximately 22-25% to the
national current account. Any expansion in the domestic use of gas would reduce export
revenues and, hence, does not feature prominently in national energy plans9. However, since a
large number of liquefied natural gas export contracts will end in 2010, leaving the total gas
8 http://www.southsearepublic.org/article/268/read/indonesian_oil_subsidies, October 2005
9 Indonesia Country Report, USAID ASIA, June 2007
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 15 12/20/2011
volume available of approximately 9.5 million ton per annum for new sales agreement, it is
expected that the domestic usage of gas will increase and the same is reflected through increased
gas generation in PLN’s plans till 2018. The prospects of gas contracts being renewed are little
as the government plans to phase out the existing oil price subsidies and rationalize energy
prices. This would encourage the promotion of domestic gas use and reduce reliance on oil fuels.
Indonesia exports almost half of its gas production to the Asia-Pacific region10
. With falling oil
production and rising international prices, Indonesia has been encouraging greater use of
domestic gas. But this requires a major investment in setting up the infrastructure for gas as more
than 70% of Indonesia’s gas fields are located off-shore.
Historically, PLN has faced problems to secure gas supply from the existing gas infrastructures.
To address this problem to some extent, PLN, in their Rencana Usaha Penyediaan Tenaga
Listrik (RUPTL), mention that they will use gas from LNG to power their 750 MW combined-
cycle in West Java. An LNG receiving terminal will be built in the province of Banten in West
Java. Using LNG will give PLN more flexibility in gas supply. Nevertheless, the source of LNG
is still unclear. Some of the expected sources of LNG are: Tangguh LNG plant in West Papua,
existing Bontang LNG plant in East Kalimantan and the newly planned Donggi LNG plant in
Central Sulawesi.
The volume of natural gas available for domestic use in Indonesia in the future is uncertain. For
the purpose of this analysis, we therefore assume the ratio of gas generation in the supply mix to
remain similar to the ratio of gas generation in PLN RUPTL’s supply mix forecast until 2018.
Beyond that year, proportion of gas based generation is assumed to remain constant till 2030.
Overall, fossil fuels have been dominating the fuel mix in Indonesia’s power sector despite
abundantly available renewable energy sources. Oil has been the mainstay of power sector.
Existence of a price subsidy for oil without any subsidy for gas makes the latter an expensive
fuel option thus causing its low consumption despite being more environmental friendly.
Although the share of coal in the generation mix has been limited historically, the 10,000 MW
Fast Track program would increase the use of coal and hence the carbon emissions in coming
years.
II.B. Historical annual CO2 emissions from power sector
Emissions from power sector emissions have grown historically at an average rate of 6% per
annum since 1990 reaching to a level of approximately 85 MtCO2 in 2005. Concerns over rising
GHG emissions and climate change have caused Indonesia to set a target of a 26% reduction to
the country’s overall GHG emissions by 2020.
10
Paper, ―On Prospects on Sustainable Energy Sources for Power Generation in Indonesia‖, Department of Energy
and Environment, Sweden
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 16 12/20/2011
Figure 4: Historical CO2 Emissions Trend from Power Sector
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 17 12/20/2011
III. Background Assumptions for Sector Analysis
III.A. Fuel Prices & Emission Factors
Table 3: Fuel Price Assumptions
The fuel prices considered for BAU analysis are as
per ICF’s forecast of international prices for coal and
oil, and the gas prices are based on the existing long
term gas supply contracts for domestic gas supply in
Indonesia. The domestic gas market is subsidized and
the existing gas supply contracts are priced in the
range of 3-4$/MMBTU. As the international oil and
gas prices are increasing there is pressure in the
domestic market for the increase in gas prices in the
future. The fuel price assumptions are listed in Table
3 and further detailed in Appendix 6
The emission factors considered for BAU analysis are
as per 2006 IPCC Guidelines for National
Greenhouse Gas Inventories as shown in Appendix 7.
III.B. New Capacity
To cater to the rapid increase in electricity demand,
the government designed the first crash program to
establish new coal based electricity generation with a
total capacity of 10,000 MW. Of the 10,000 MW coal
capacity 1,885 MW would use super critical
technology while the rest would use sub-critical
technology. As per PT PLN’s Business Plan for Electricity Supply, the total 10,000 MW coal
capacity is scheduled for commissioning by 2011. However, looking at the progress in achieving
the above said targets it looks highly unlikely that these targets would be realized; and hence for
our analysis, we have staggered the addition of 10,000 MW of coal build up to 2013 as shown in
Appendix 4. Also, 7,500 MW capacity under this plan is scheduled to cater Java-Bali region (Of
7,500 MW in Java-Bali, 1,885 MW would be super-critical coal plants and the rest would be
sub-critical coal plants) while 2,500 MW capacity would serve regions outside Java-Bali region 11
(the entire 2,500 MW would be sub-critical coal capacity).
The Presidential Decree No.5, 2006 identifies renewable energy as one of the primary energy
resources in Indonesia and mandates its use for electricity generation for on-grid and off-grid
applications. To achieve the targets set in National Energy Policy for renewable energy gestation
by 2025, the government designed the second crash program whose administrative process is
scheduled to be completed during the period 2009-2014. The program commits another 10,000
11
PLN Annual Report, 2008
Year HSD Coal Gas
USD/Barrel USD/tCO2 USD/MMBtu
2008 45.0 98.0 4.0
2009 48.6 89.3 4.2
2010 58.8 83.7 4.5
2011 63.9 80.2 4.7
2012 66.6 79.6 5.0
2013 68.7 78.8 5.3
2014 70.6 77.9 6.0
2015 72.7 77.2 6.0
2016 74.2 77.1 6.0
2017 75.3 77.1 6.0
2018 75.3 77.1 6.0
2019 75.3 77.1 6.0
2020 75.3 77.1 6.0
2021 75.3 77.1 6.0
2022 75.3 77.1 6.0
2023 75.3 77.1 6.0
2024 75.3 77.1 6.0
2025 75.3 77.1 6.0
2026 75.3 77.1 6.0
2027 75.3 77.1 6.0
2028 75.3 77.1 6.0
2029 75.3 77.0 6.0
2030 75.3 77.0 6.0
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 18 12/20/2011
MW to Indonesia’s electricity system through 60% renewable (48% geothermal and 12% hydro),
26% coal (all sub critical coal capacity) and 14% gas based capacity. In our analysis, we assume
that the entire 10,000 MW under second crash program shall enter the system over 2014-2020 as
shown in Appendix 4.
The development of nuclear power plants (NPP) in Indonesia is still unclear although there has
been some previous planning. The blueprint estimates the uranium resources at 24,000 tons
mostly in Central Kalimantan. The proven reserves are estimated at 4,600 tons, with most of the
reserves categorized as low grade ores. These deposits are not sufficient even to run a 4 GW NPP
for 10 years and hence, in the long-run, Indonesia will have to depend on imported uranium,
possibly from Australia. In terms of waste management, it is still unclear where the waste will be
stored. The National Energy Management (2006-2025) blueprint outlays a plan of building 4
GW of nuclear capacity over 2016-2024 but the inconclusive political environment has caused
uncertainty about the time frame of nuclear gestation in Indonesia. ICF assumes no nuclear
capacity to enter the Indonesia’s power system under the business as usual scenario.
The total geothermal potential in Indonesia is estimated at 27 GW as shown in Appendix 5.
However, until 2005, the total installed capacity of geothermal was around 815 MW. The
significantly low investments in geothermal capacity can be attributed to the ambiguity in the
law for geothermal capacity development. The law mandates geothermal projects to be
developed as ―Total Projects‖12
but does not, by itself, facilitate the development of such
projects. As per the MEMR’s Road Map of Development of Geothermal, the target of
geothermal utilization for electricity is 9,500 MW in the year 2025. Taking this forward, ICF
analysis has assumed the total geothermal capacity of 11 GW by 2030.
Among the other renewable resources, Indonesia has a rich potential of hydro and biomass. The
National Energy Management (2006-2025) blueprint estimates the total large hydro potential at
75 GW, small hydro potential at 450MW and biomass potential at 50 GW. ICF assumes a yearly
addition of 100 MW hydro plant throughout the analysis period while 100 MW biomass
additions every 5 years starting 2015, primarily to cater to the rural demand. Biomass in
Indonesia is available mainly from solid waste, rice residue, rubber wood, sugar residues and
palm oil residues. For our analysis, we assume the biomass generation to be based on solid
waste.
Appendix 7 shows the cost and performance data for various electricity generation technologies
considered in the analysis. The parameters for different new technologies likely to enter the
power system are different for Java-Bali region and for the regions outside Java-Bali due to the
capacity size required to meet the demand in various regions.
12
Total Projects are those where the upstream (involving generation of steam, its treatment and delivery) and the
downstream (generation of electricity) of the electricity generation process are handled by the same company.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 19 12/20/2011
III.C. Policies included
The Indonesian energy sector is in the early stages of transformation. The reform process was
initiated by Electricity Law 20/2002 from the year 2002. Table 4 details the policies that have
been considered for the BAU analysis.
Table 4: Policies considered for BAU Analysis
Policy Date Details
Indonesia’s National Climate Change Action Plan
2007 Guideline for all sectors for an integrated effort to tackle climate change
Presidential Regulation No.5 on National Energy Policy
2006 Sets energy mix composition to be achieved in 2025
Presidential Regulation No. 71 2006 Mandates the implementation of 10,000MW Fast Track Program to build coal plants; Mandates the implementation of second 10,000MW Fast Track Program with thrust on renewable energy sources
Blueprint of National Energy Implementation Program 2005-2025
2005 Describes measures for energy supply security, road maps for various sectors and programs to phase out subsidies and improve energy efficiency
Presidential Instruction No.10 2005 Describes the energy efficiency programs in Indonesia
Ministerial Regulations No.31 2005 Guidelines for implementing Energy Efficiency Programs
MEMR Regulation 8 2005 Seeks to attract private investments in oil and gas explorations
Green Energy Policy, MEMR Decree No.2
2004 Highlights renewable energy potential in Indonesia
Law No.27 on Geothermal Power 2003 Provides certainty of law to geothermal industry; Defines rules for exploration and development under competitive bidding
National Energy Conservation Plan
2002 Details the opportunities to save energy in various sectors
Oil and gas Law No.22 2001 Stipulates transparency in the downstream oil and gas operations; bases pricing mechanism on market prices; provides investors equal regulatory and legal treatment
PROPENAS Law 2001 Reduces burden of energy subsidies on state budget; increases prices of energy
III.D. Demand
The demand forecasts by the Ministry of Energy & Mineral Resources and PLN assume
considerably different growth rates. The Ministry of Energy and Mineral Resource’s (MEMR)
RUKN projections assume the energy demand to grow at a 9.98% (2008-2050) compounded
average growth rate (CAGR) while PLN’s RUPTL assumes a CAGR of 9.3% (2008-2020). ICF
assumed the growth rates under the MEMR’s projections and applied the same to the actual
demand in 2007. The demand forecasts by MEMR, PLN and the one used in this analysis are
shown in Appendix 1.
III.E. Reserve Margin Requirements
The measure of available capacity above the requirements to meet standard peak demand levels
is called the reserve margin. This measures the ability of an oil or gas producer to generate more
energy than the usual system demand. The existing reserve margins of 15~ 25% in Indonesia are
high relative to international standards (typically 10~20%). This is due to different types (based
on total installed capacity in the system, rather than basing it on actual available capacity) of
accounting for reserves.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 20 12/20/2011
For the long term planning, MEMR’s assumption of 30% reserve margin requirement for West
Java while 40% reserve margin requirement for other regions are based on total installed
capacity. However, for our analysis we have based our reserve margin requirements on the
available capacity as shown in Appendix 2. West Java is the only region with a reserve margin of
less than 25% at approximately 15%. These numbers are not expected to change through 2030
for all regions.
III.F. Transmission
PLN’s existing transmission network has an inter-island link only between Java and Bali while
all other islands have isolated power systems. A 3,000 MW transmission line between West Java
and Sumatra is expected to be fully operational from 201813
.
The study does not include any inter island links except the existing Java-Bali link and the
proposed 3,000MW West Java-Sumatra link as per PLN’s inter-island transmission connectivity
plan. No other transmission capacity has been considered in the study.
The T&D losses assumed in our study are based on the losses considered by the MEMR for their
demand estimates. As listed in Appendix 3 these losses decline sufficiently over time leaving no
scope for any further improvement under mitigation scenarios.
13
RUPTL, PT PLN
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 21 12/20/2011
IV. Description of analytical model and methodology used
The criterion of optimization that the model makes use of is the minimization of the system’s
total cost, so that the alternatives for power generation are chosen in the order of the lowest cost.
It is important to emphasize that, besides the capital and operation costs, the Model allows to
incorporate additional ―penalty‖ costs for the alternatives, such as environmental and social
costs.
Additionally, the cost and the performance characteristics (efficiency and capacity factor) of the
technological alternatives for electricity supply are also inputs for the Model. These data are used
together with the fuel price data for the economic competition of the alternatives whenever the
addition of capacity is necessary.
ICF has used Indonesia - Integrated Planning Model (I-IPM®) is a dynamic linear programming
model that generates optimal decisions using perfect foresight. It determines the least-cost
method of meeting energy demands and peak energy requirements over a specified period (e.g.
2005 to 2030). In its solution, the model considers a number of key operating or regulatory
constraints (e.g. emission limits, transmission capabilities, renewable generation requirements,
fuel market constraints) that are placed on the power and fuel markets. In particular, the model is
well-suited to consider complex treatment of emission regulations involving trading, banking,
and progressive flow control of emission allowances, as well as traditional command-and-control
emission policies. A detailed description of IPM® is given in Appendix 9.
ICF has been using Indonesia - Integrated Planning Model (I-IPM®) since 2003. Over the course
of last 5 years ICF has been engaged by various private sector utilities to prepare complete
market assessments and dispatch analyses to assess the developments on existing as well as new
power installations, with a view to determine the size of the gas-to-power markets in Indonesia.
The work has involved developing Indonesia’s power sector modeling database as well as full
short and long-term dispatch analyses including detailed forecasts on capacity additions, forward
prices, fuel consumption, generation and CO2 emissions.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 22 12/20/2011
V. Baseline (Business as Usual) scenario for the electricity sector
V.A. Production/output
Table 5 below shows the growth in installed capacity from 2005 to 2030 under the Business As
Usual (BAU) scenario, clearly illustrating a nearly fourfold increase in the oil based capacity in
the system over 2010-2030. This increase in oil-based capacity is to meet the super peak load of
the system which persists for very few hours, which is also reflected by very little generation
(Table 8) from this huge oil capacity addition.
Table 5: Installed Capacity under BAU
Year
Annual Installed Capacity (GW)
Coal Natural Gas Oil Nuclear Hydro (>10MW) Other* Total
Sub-Critical Super-Critical
2005 8 - 7 11 0 4 1 30
2010 12 1 9 11 0 4 1 38
2015 21 5 15 13 0 5 5 64
2020 24 19 24 18 0 6 9 99
2025 29 41 39 28 0 6 10 153
2030 37 79 64 44 0 7 12 243
*Other includes small hydro, geothermal and biomass
Note: Data on 2005 Installed capacity in Indonesia includes 7GW of existing captive capacity
Table 6: Installed Renewable Capacity under BAU
Year Annual Installed Capacity (GW)
Small Hydro (<10MW) Geothermal Biomass Total
2005 0.1 0.8 0.0 0.9
2010 0.1 1.1 0.0 1.2
2015 0.2 5.3 0.1 5.6
2020 0.2 8.9 0.2 9.3
2025 0.2 10.1 0.3 10.6
2030 0.2 11.3 0.4 11.9
Table 7: Power Generation under BAU
Year
Annual Power Generation (TWh)
Coal Natural Gas Oil Nuclear Hydro Other* Total
Sub-Critical Super-Critical
2005 56 0 26 29 0 11 3 125
2010 88 5 38 29 0 12 5 177
2015 146 38 45 2 0 14 29 273
2020 160 138 64 2 0 18 47 428
2025 188 304 102 2 0 20 62 678
2030 237 577 162 4 0 21 78 1080
*Other includes small hydro, geothermal and biomass
Figure 5 and
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 23 12/20/2011
Figure 6 below show the change in capacity and generation mix over 2015 to 2030 under the
BAU. Figures clearly demonstrate the continued dominance of coal in the power sector. The
share of coal under the BAU in the capacity mix increases from 41% in 2015 to 48% in 2030,
while increases from 67% to 75% in the generation mix during the same time horizon.
Figure 5: Capacity Mix under BAU
2020 2030
Biomass0%
Gas15%
Coal76%
Oil0%
Nuclear0%
Hydro2%
Geothermal7%
Biomass0%
Gas26%
Coal48%
Oil18%
Nuclear0%
Hydro3%
Geothermal5%
Biomass Gas Coal Oil Nuclear Hydro Geothermal
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 24 12/20/2011
Figure 6: Generation Mix under BAU
2020 2030
Under the BAU, approximately 18 GW of renewable power is realized of which approximately
11 GW is geothermal capacity. Figure 7 provide details of capacity additions of different
renewable capacity.
Biomass0%
Gas15%
Coal70%
Oil0%
Nuclear0%
Hydro4%
Geothermal11%
Biomass0%
Gas15%
Coal76%
Oil0%
Nuclear0%
Hydro2%
Geothermal7%
Biomass Gas Coal Oil Nuclear Hydro Geothermal
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 25 12/20/2011
Figure 7: Renewable capacity additions under BAU by 2030
V.B. Annual GHG Emissions
CO2 emissions were approximately 83 MtCO2 in 2005. Under BAU the emissions reaches 268
MtCO2 by 2020 with a CAGR of 7%, while reaches 688 MtCO2 by 2030, with a CAGR of 13%.
Major contributor of emissions is coal followed by gas. Table 8 provides the emission details
from each capacity types while
Figure 8 pictorially shows the increasing emissions level from 2015 to 2030. Table 8: CO2 Emissions
Year
CO2 Emissions (MmtCO2) Coal
Natural Gas Oil Other Total Sub-Critical Super-Critical
2005 49 0 17 16 0 83
2010 79 3 16 23 0 122
2015 132 26 18 2 0 178
2020 146 94 26 1 1 268
2025 173 209 41 2 1 427
2030 221 396 66 3 2 688
815
3,520
57
920
4054,800
1,200
4,800
400
1,700
0
2000
4000
6000
8000
10000
12000
Geothermal Biomass Large Hydro Small Hydro
R
e
l
i
z
a
b
l
e
R
e
n
e
w
a
b
l
e
P
o
t
e
n
t
i
a
l
(
M
W)
Total Installed Capacity till 2005 Except Captive Captive Capacity till 2005Firm Capacity First Crash ProgramSecond Crash Program Additional Builds considered in BAU
11 GW
0.4 GW
6.8 GW
0.067 GW
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 26 12/20/2011
Figure 8: CO2 Emissions under BAU
178
268
427
688
0
100
200
300
400
500
600
700
800
900
2010 2015 2020 2025 2030 2035
CO2 Emissions (MtCO2)
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 27 12/20/2011
V.C. Energy intensity and CO2 intensity
Energy intensity of the power sector under the BAU improves from the level of 10 PJ/TWh to 8
PJ/TWh, while CO2 intensity improves from 0.66 to 0.64 MtCO2/MWh.
Figure 9: Energy and CO2 Intensity
0.6
0.61
0.62
0.63
0.64
0.65
0.66
0.67
0.68
0.69
0.7
0
2
4
6
8
10
12
2005 2010 2015 2020 2025 2030
Energy and CO2 Intensity
Energy Intensity (PJ/TWh) CO2 Intensity (MtCO2/ MWh)
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 28 12/20/2011
Figure 10: CO2 Intensity by Fuel Type (MtCO2/MWh)
Thus concludes our BAU analysis for the electricity sector in Indonesia. We will now explore the
effects of different carbon prices on the emissions of the power sector.
0.660.69
0.65 0.63 0.63 0.64
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
2005 2010 2015 2020 2025 2030
CO2 Intensity by Fuel Type (Mt CO2 / MWh)
Sub-Critical Coal Super-CriticalCOal Natural Gas Oil Average All Fuels
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 29 12/20/2011
VI. GHG Mitigation Options and Costs
Once the baseline emissions were projected, mitigation options were allowed in the modelling
system and the power system of Indonesia was again simulated to analyze its response to carbon
costs. The mitigation options reflect options that the Indonesian government have with a new
carbon price. Different options could evolve based on different carbon prices as reflected in our
analysis. For the purposes of our analysis we focused on 2020 and 2030 as our target years to be
able to directly compare to existing analysis as well as to Indonesia’s climate targets.
Step-by-step analysis was done by imposing a carbon cost on the business as usual (BAU) case,
starting at $10/tCO2 and increasing it by $10/ tCO2 in successive iterations. In every stage, the
changes related to capacity mix, generation mix, emissions level and investment requirements
over BAU were noted. Similarly, for modelling negative cost options, for each of the DSM
programs – viz. General Lighting (DSM GL), Street Lightning & Ballasts (DSM SLBL)14
,
Chillers (DSM CH), Air conditions (DSM AC), Refrigerators (DSM RF) and Televisions (DSM
TV) the associated costs and the demand reduction were computed and modelled on BAU
considering all the of them are implemented.
Imposition of carbon cost on the system (in BAU scenario) would in-effect prompt changes viz.
retirement of inefficient capacity, conversion of existing inefficient plants to more efficient
plants, preference of more efficient or gas based capacity as a resort for system expansion and
increase in proportion of renewable energy in the generation mix. However, different
combinations of these changes would occur at different carbon costs.
VI.A. Selection criteria for consideration of mitigation options
The GHG abatement options suggested here are important for the electricity sector, and are
consistent with the sectoral development goals and relevant policies by the government of
Indonesia. They have significant emissions reduction potential and their implementation is
feasible.
VI.B. Overview of each mitigation option considered
Demand Side Management
The National Energy Conservation Master Plan (2005)—RIKEN (Rencana Induk Konservasi
Energi Nasional) states that Indonesia’s goal is to decrease energy intensity by around 1% per
year on average until 2025. In affect various energy saving Demand Side Management (DMS)
measures are planned to be implemented in Indonesia. This analysis includes mainly energy
efficiency improvements occurring in the residential and commercial sectors including
installation of efficient lighting (viz. CFL or General Lighting (GL), Ballasts and Street
Lighting), efficient space cooling systems (viz. Chillers and Air-conditioning) and efficient
appliances (viz. Televisions15 and Refrigerators). Implementation of efficient TVs is not a
negative cost option and hence are not been considered as a DSM option. Under the BAU
14
As the individual energy savings from Street lightning and Ballasts were not significant the two measures are
implemented together to study the impact. 15
Implementation of efficient TV’s is not a negative cost option and hence not been presented in the results.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 30 12/20/2011
Scenario - each category assumes technology penetration in 2005 remains constant until 2030.
Table 9 provides the details on the efficient technology penetration in 2005. While in the DSM
cases i.e. the Conservation Scenario – Technology penetration for each category increases
incrementally by 1% every year from 2010 to 2030. The actual BAU may be such that the
technology penetration increases at a steady rate, if not at 1% each year. In that case our analysis
would have over-estimated the impact of energy efficiency in the residential and commercial
sectors. However, this information is not easy to ascertain and certainly beyond the scope of this
project’s mandate.
The limitations and implications of the above methodology will be explored in another report
that will form part of this project.
Appendix 9 details the yearly energy saving and the investment requirement of various DSM
activities.
Table 9: Penetration of efficient technology in 2005
Technology Penetration of efficient technology in 2005
Lighting
General lighting 10% - 30%
Ballasts 9% - 10%
Street Lighting 40%
Space Cooling
Air-conditioning 10% - 20%
Chillers 5%
Efficient Appliances
Refrigerators 10% - 20%
Televisions 5% - 15%
Solar
Being a tropical country, Indonesia is bestowed with enormous solar potential with the maximum
potential in the Sulawesi, Maluku and Nusa islands. However, due to considerable capital cost
for solar technology and lack of local manufacturing industry for technology components, solar
has not found its place in the plausible mitigation options for Indonesia in our study.
Nonetheless, modular installations of solar PV provide for meeting the off-grid energy demand
on a larg0065 scale.
Geothermal power
Geothermal is not an intermittent resource and can provide a reliable electricity production.
Typical geothermal plants in Indonesia have a capacity factor of more than 90% which
outperforms other conventional power plants.
As shown in Appendix 5, the total geothermal potential in Indonesia is estimated at 27 GW and
is predominantly available in Sumatra and Java regions. However, given the unavailability of
adequate transmission evacuation facilities available near geothermal sites and environmental
barriers associated with geothermal site gestation, only 15GW potential can be exploited for
electricity generation. The analysis assumes 11GW geothermal capacity to enter the system
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 31 12/20/2011
under BAU (as discussed earlier) and a possibility of additional 4GW to enter under mitigation
scenario.
Hydro power
As discussed earlier, Indonesia has huge large hydro potential. Most of the potential in Java Bali
region has already been exploited. The water level of rivers in Java-Bali region has receded due
to deforestation which prevents further expansion of large hydro power in this region. However,
there is large untapped potential in regions outside Java-Bali16
.
With the proven advantages like low maintenance cost, high reliability, efficiency and
availability; hydro power has disadvantages related to deforestation and population
rehabilitation. Due to this, the entire 75GW of large hydro potential cannot be exploited for
electricity generation. This analysis assumes only 5GW of large hydro potential to enter the
system under mitigation scenario.
Micro, mini and small hydro are mature technologies in Indonesia. Even though the total
potential for these options is as small as 500 MW, small hydro plants prove beneficial for
providing electricity to rural communities.
Biomass power
The total biomass potential in Indonesia is estimated at 50GW. The majority of this potential is
scattered over Kalimantan, Sumatra, Papua and Sulawesi. However, the total potential of
biomass energy for electricity generation assumed under mitigation scenarios is around 15GW
and is mostly available outside Java.
Various technologies available in Indonesia to produce electricity from biomass energy are:
• Biomass combustion power – This technology is in a mature stage and is widely used to
produce electricity from agro-waste, forest products and municipal waste.
• Biomass combined heat and power (CHP) – Here, a boiler is used to produce both heat and
electricity which improves the overall system efficiency to as much as 85%.
• Biomass co-firing - Co-firing increases the efficiency of the energy conversion to about 30%-
38% which is much higher than that in biomass combustion plant (typically about 15% to
20%).
• Biomass integrated gasification combined cycle (BIGCC) - Gasification is the main alternative
to combustion for electricity generation. There are many examples of biomass gasification
projects in the R&D stage, although the only technologies commercially deployed are CFB
(Circulating Fluidised Bed) atmospheric pressure.
Wind
Indonesia does not have either on-shore or off-shore wind potential. Although, the National
Blueprint for Energy shows large wind potential, but due to poor wind speeds, these sites cannot
be exploited for electricity generation. For the purpose of this analysis, no wind potential (in
both, BAU and mitigation scenario) is assumed.
16
Paper, ―On Prospects of Sustainable Energy Sources for Power Generation in Indonesia”, Department of Energy
and Environment, Sweden
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 32 12/20/2011
Nuclear
As the development of nuclear capacity in Indonesia is highly dependent on the government’s
decision, ICF assumes that under mitigation scenarios, the total nuclear potential of 4 GW (in
line with the National Energy Management blueprint) can enter the system beyond 2025.
IGCC
An IGCC plant is a combination of both combined cycle and gasification plant. The coal is
gasified into synthetic gas (syngas), which is then used as fuel for electricity generation in a
combined cycle operation. The operation of the IGCC plant can be summarized as:
1. The feedstock (coal in this case) is gasified in an air or oxygen blown gasifier at high
temperature and pressure.
2. This gasification results in the production of synthetic gas (syngas) which is made up of
carbon monoxide and hydrogen; this syngas is then combusted in a gas turbine.
3. The hot exhaust gases from the gas turbine are used to produce steam to drive a steam
turbine.
Hence power is produced both from the gas and the steam turbines. In an IGCC installation,
typically 60-70% of the power comes from the gas turbine.17
IGCC plants offer the benefits of low emissions, low water use, low carbon dioxide emissions,
high efficiency, ability to use various fuels depending on the gasifiers used (coal, refinery
residues, biomass), and also production of by-products like chemicals, synthetic fuels, fertilizers
and hydrogen. Estimated efficiency for IGCC plants is assumed to 40%.
Since the technology is not too technically advanced, there is still time for it to be commercially
viable. So in the mitigation scenario, we assume that IGCC can be a possibility for Indonesia
after 2020.
IGCC-CCS
Gasification carried out in the IGCC process is also the baseline technology for carbon capture
and sequestration (CCS). CCS consists of the separation of CO2 from energy-related sources, its
transportation to a storage location and long-term isolation from the atmosphere. To facilitate
carbon transportation and storage, CO2 is typically compressed to a high density when it is
captured.
One of the key benefits of CCS technology is that when it is used with Enhanced oil recovery
(EOR), or with coal bed methane, it leads to the maximum extraction of those resources as well.
In Indonesia, Java-Bali and Sumatra are the demand centric regions. Hence, given the size and
costs associated with IGCC-CCS plants, this technology would mainly be developed to cater to
demand in these regions. However, due to space constraints in Java-Bali, there are two
possibilities for developing IGCC-CCS for this region: first, develop the IGCC plant in Java-Bali
and lay a transportation line for carbon storage in a nearby island or second, build the IGCC-
17
http://www.worldenergy.org/documents/scenariosgeneration.pdf
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 33 12/20/2011
CCS plant in some other island and lay transmission line for power evacuation to Java-Bali
region. Based on the storage capacity available IGCC-CCS options for the analysis are
considered viable only in Kalimantan and Sumatra with a potential of approximately 2 GW.
Like IGCC, the IGCC-CCS technology is also in pilot stage and is yet to be commercially
available. Hence, IGCC-CCS also is considered to be an option after 2020, under mitigation
scenario.
Super-critical plants
Supercritical units operate at higher temperatures and pressures than sub-critical units; the higher
pressure increases turbine efficiency and power output, thereby leading to lesser coal usage for
production of same amount of electricity. Hence, building super-critical coal plants in lieu of
sub-critical coal plants can reduce the coal usage and therefore, abate carbon emissions.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 34 12/20/2011
VII. Analysis of GHG Mitigation Scenarios
Based on the assumptions listed in Section VI, the emissions from the electricity sector in
Indonesia were projected for the years 2020 and 2030. A significant result from these projections
analysis is the representation of the abatement potential in the electricity sector using Marginal
Abatement Cost Curve (MACC) methodology. Simplistically, the MACC relates the cost per
additional unit of emissions reductions to the total quantity of reductions.
One of the more widely recognized and used MACC models is the step curve or ―Static MACC‖
which provides information regarding the abatement potential of various technologies/mitigation
options at a particular cost step. However, in the real world setting, the abatement potential of a
mitigation option/technology depends not only on abatement cost, but also on the system
dynamics and limitations at that particular cost step. This multi-dimensional relationship is
captured through the use of ICF International’s proprietary cost optimization model IPM (refer
Appendix 10) and we refer to the resulting MACC as the Dynamic MACC. The Dynamic
MACCs for Indonesia were compiled by recording the changes in system emissions level for
every $10/tCO2 increase in the carbon cost over the BAU for the positive cost curve, while
recorded for reduction in demand level over BAU for the negative cost curve. For each carbon
cost-point, the Dynamic MACC also shows the changes in capacity and changes in generation
mix over BAU.
In the sections below we discuss our findings for the years 2020 and 2030 by discussing, in the
said order, the (a) the emissions profile (b) installed capacity (c) generation mix and (d) resulting
emissions reduction compared to BAU at a range of carbon prices (0 - $80/tCO2). Although the
results of this analysis are in the form of Dynamic MACCs, we have also represented them in the
form of Static MACCs in order to help gauge the value added by this analysis and to help in
comparisons with other studies as well. As one will observe, the implications from the Dynamic
MACC are far greater than the Static MACC. For instance while the Static MACC gives us an
idea of the abatement potential of various technologies at a certain carbon price, the Dynamic
MACCs show us the system changes over a range of carbon prices, thereby enabling the reader
to visualize the implications of a range of carbon price levels on the electricity system and the
emissions resulting from it. Dynamic MACCs guide the power sector planners in developing
long term investment strategies to select among the variety of efficiency and generation options.
Considering that the aim of this study is to enable Indonesian stakeholders in making public
policy choices in a real-world setting, we chose to focus our analysis on the implications of the
Dynamic MACCs. We will further use this analysis to compare effectiveness of other policy
mechanisms such as clean coal incentives in another report under this project.
VII.A. Mitigation Scenario in 2020
In 2020, the abatement potential observed under a carbon price of $80/tCO2 is 32 MtCO2 and 54
MtCO2 without DSM and with DSM respectively. The difference in emissions under the various
carbon price scenarios compared to BAU can be seen in Table 14.
At $80/tCO2 cost total abatement potential is approximately 50 MT, Figure 13
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 35 12/20/2011
Table 10: Emissions by Fuel type in 2020 Source of
Emissions (MtCO2) BAU CP30 CP50 CP80 DSM30ALL DSM50ALL DSM80ALL
Oil 1 1 1 1 1 0 1
Coal 241 231 223 201 209 198 180
Gas 27 27 30 34 27 31 34
Hydro 0 0 0 0 0 0 0
Geothermal 0 0 0 0 0 0 0
Total 268 260 254 236 237 230 214
The reduction in emissions observed in Table 10 are due to changes in the system generation mix
that are brought upon by imposing a carbon price which simultaneously penalizes dirtier sources
(e.g. sub-critical coal) while incentivizing cleaner sources (E.g. geothermal).
The system changes in installed capacity mix and generation mix under various carbon prices
scenarios can be observed in Tables 11 and 12 respectively.
Table 11: Changes in Capacity Proportion by different technology types in 2020
Changes in the System
Capacity Mix (GW) CP30 CP50 CP80 DSM30ALL DSM50ALL DSM80ALL
Abatement Potential (MtCO2) 9 14 32 31 38 54
Biomass 0 1 5 0 2 5
Gas -4 -4 -4 -5 -4 -5
Coal Sub Critical -1 -3 -4 -2 -4 -4
Coal Super Critical 6 8 11 2 4 7
IGCC 0 0 0 0 0 0
Oil 0 -1 -5 -2 -4 -7
Nuclear 0 0 0 0 0 0
Hydro 0 0 2 0 0 2
Geothermal 0 0 0 0 0 0
Total 0 1 5 -7 -5 -2
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 36 12/20/2011
Table 12: Changes in Generation Proportion by different technology types in 2020
Changes in the System
Generation Mix (TWh) CP30 CP50 CP80 DSM30ALL DSM50ALL DSM80ALL
Abatement Potential (MtCO2) 9 14 32 31 38 54
Biomass 0 4 17 0 8 17
Gas 0 0 0 0 0 0
Coal Sub Critical -40 -61 -101 -43 -68 -102
Coal Super Critical 39 56 75 11 29 47
IGCC 0 0 0 0 0 0
Oil 0 -1 1 -1 -1 0
Nuclear 0 0 0 0 0 0
Hydro 1 1 7 1 1 7
Geothermal 0 0 0 -1 -1 -1
Total 0 0 0 -32 -32 -32
The Dynamic MACCs representing the abatement potential associated with resulting changes in
capacity and generation mix can be seen in Figures 11 and 12 respectively. As can be observed
from the Dynamic MACCs the majority of emissions reductions from BAU are achieved through
Supercritical, Biomass-CHP and Large hydro displacing sub-critical coal and contributes
towards total abatement of approximately 38 MtCO2 at a carbon price of $80/tCO2. DSM
measures are excluded from this particular analysis because the model assumes an optimum mix
of generation sources to meet a particular level of energy demand. Hence, energy efficiency
measures which inherently mean reduction of demand are calculated separately and the Dynamic
MACC is run for the resulting reduced demand. This issue will be further explored in a separate
paper on energy efficiency which forms part of the project. However as it can be seen from
Tables 10-12, we have calculated the impact of DSM on three carbon price scenarios and the
resulting abatement potential reflect the increase in emissions reduction from energy demand
reduction.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 37 12/20/2011
Figure 11: MAC Curve 2020 - Capacity Changes (GW)
4
6
910
14
23
30
32 33
-20
-10
0
10
20
30
40
CP10 CP20 CP30 CP40 CP50 CP60 CP70 CP80 CP90
Ch
ange
s in
Cap
acit
y M
ix (
GW
)
Hydro
Nuclear
Oil
IGCC
Coal Super Critical
Coal Sub Critical
Gas
Biomass
Geothermal
Abatement Potential (MtCO2)
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 38 12/20/2011
Figure 12: MAC Curve 2020 - Generation Changes (TWh)
-150
-100
-50
0
50
100
150
CP10 CP20 CP30 CP40 CP50 CP60 CP70 CP80 CP90
Ch
ange
s in
Ge
ne
rati
on
Mix
(TW
h)
Geothermal
Hydro
Nuclear
Oil
IGCC
Coal Super Critical
Coal Sub Critical
Gas
Biomass
Abatement Potential (MtCO2)
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 39 12/20/2011
As mentioned in the introduction to this section, the Dynamic MACC results were converted into
Static MACC representation for ease of comparison. The methodology used to create this Static
MACC was to average out the cost levels at which a particular technology enters into the system
and the resulting emission reduction from BAU in order to represent total abatement potential at
a single cost.
Figure 13: 2020 MAC Curve at 80$/ tCO2Abatement Cost
-45
-2
39
64
-60
-40
-20
0
20
40
60
80
0 10 20 30 40 50
Ab
ate
me
nt
Co
st (
$/t
on
)
Abatement Potential (MT CO2)
DSM Coal Super Critical Small Hydro Biomass-CHP Large Hydro
81
DSM Super Critical
Coal
Small
HydroBiomass -
CHP
Large
Hydro
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 40 12/20/2011
VII.B. Mitigation Scenarios in 2030
In 2030, the abatement potential observed under a carbon price of $80/tCO2 is 115MtCO2 and
218 MtCO2 without DSM and with DSM respectively. The difference in emissions under the
various carbon price scenarios compared to BAU can be seen in Table 13.
Table 13: Emissions by Fuel type in 2030
Emissions
(MtCO2) BAU CP30 CP50 CP80 DSM30ALL DSM50ALL DSM80ALL
Oil 3 3 3 3 3 3 3
Coal 617 587 511 488 484 410 386
Gas 68 73 83 83 71 81 81
Hydro 0 0 0 0 0 0 0
Geothermal 0 0 0 0 0 0 0
Total 688 664 598 573 558 494 470
The reduction in emissions observed in Table 13 are due to changes in the system generation mix
that are brought upon by imposing a carbon price which simultaneously penalizes dirtier sources
(e.g. sub-critical coal) while incentivizing cleaner sources (E.g. geothermal).
Table 14: Changes in Capacity Proportion by different technology types in 2030
Changes in the System
Capacity Mix (GW) CP30 CP50 CP80 DSM30ALL DSM50ALL DSM80ALL
Abatement Potential (MtCO2) 25 91 115 131 194 219
Biomass 5 16 16 4 16 16
Gas -4 -4 -6 -11 -11 -13
Coal Sub Critical -5 -17 -18 -8 -18 -18
Coal Super Critical 6 7 6 -10 -13 -12
IGCC 0 2 5 0 1 2
Oil 0 -3 -6 -5 -8 -11
Nuclear 0 4 4 0 4 4
Hydro 1 1 6 1 1 6
Geothermal 0 4 4 0 4 4
Total 4 9 12 -31 -24 -22
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 41 12/20/2011
Table 15: Changes in Generation Proportion by different technology types in 2030
Changes in the System
Generation Mix (TWh) CP30 CP50 CP80 DSM30ALL DSM50ALL DSM80ALL
Abatement Potential (MtCO2) 25 91 115 131 194 219
Biomass 18 52 51 13 50 49
Gas 0 0 0 0 0 0
Coal Sub Critical -58 -147 -178 -85 -152 -181
Coal Super Critical 36 34 33 -77 -98 -91
IGCC 0 13 30 0 4 13
Oil 0 0 -1 -1 -1 -1
Nuclear 0 32 32 0 32 32
Hydro 3 3 18 3 3 18
Geothermal 0 15 15 -3 12 12
Total 0 0 0 -150 -150 -150
As one can observe from the Dynamic MACCs shown in Figures 14 and 15, the emissions
reductions vis-à-vis BAU is achieved through introduction of cleaner sources such as Biomass,
IGCC, Nuclear, Hydro and Geothermal in varying proportions that replace dirtier sources such as
Gas, coal (sub and super-critical) and Oil. Please note that one of the significant results under the
2030 $80/tCO2 carbon price scenario is that over the long run cleaner sources such as Biomass
and Geothermal become much more viable than relatively clean sources such as super-critical
coal.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 42 12/20/2011
Figure 14: MAC Curve 2030 – Capacity Changes (GW)
-110
-90
-70
-50
-30
-10
10
30
50
70
90
110
130
-40
-30
-20
-10
0
10
20
30
40
50
CP10 CP20 CP30 CP40 CP50 CP60 CP70 CP80 CP90
Ab
ate
me
nt
Po
ten
tial
(M
tCO
2)
Ch
ange
s in
Cap
acit
y M
ix (
GW
)
Biomass Gas Coal Sub Critical
Coal Super Critical IGCC Oil
Nuclear Hydro Geothermal
Abatement Potential (MtCO2)
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 43 12/20/2011
Figure 15: MAC Curve 2030 - Generation Changes (TWh)
-250
-200
-150
-100
-50
0
50
100
150
200
250
CP10 CP20 CP30 CP40 CP50 CP60 CP70 CP80 CP90
Ch
ange
s in
Ge
ne
rati
on
Mix
(TW
h)
Geothermal
Hydro
Nuclear
Oil
IGCC
Coal Super Critical
Coal Sub Critical
Gas
Biomass
Abatement Potential (MtCO2)
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 44 12/20/2011
As with the earlier section, the Dynamic MACC results for 2030 were converted into Static
MACCs for ease of comparison. The methodology used to create this Static MACC was to
average out the cost levels at which a particular technology enters into the system and the
resulting emission reduction from BAU in order to represent total abatement potential at a single
cost. On comparison with the Static MACC for 2020, one can observe that by 2030 a larger
proportion of clean technologies is feasible because of the ability to earn returns over a longer
period of time.
Figure 16: 2030 MAC Curve at 80$/tCO2 Abatement Cost
Table 16: 2030 - Abatement potential and Cost for Different Mitigation Options
Mitigation Options Abatement Cost ($ /tCO2) Abatement Potential (MtCO2)
DSM -44 104
Coal Super Critical -6.9 5
Geothermal 16.3 14
Nuclear 24.7 29
IGCC 33.4 7
Small Hydro 37.7 2
Biomass-Gasification 52.4 25
IGCC-CCS 64.4 9
Biomass-CHP 76.3 9
Large Hydro 79.2 14
-44
0 0
-70
16
0
25
0
33
38
0
0
52
0
79
-60
-40
-20
0
20
40
60
80
0 20 40 60 80 100 120 140 160 180 200
Ab
ate
me
nt
Co
st (
$/t
on
)
Abatement Potential (MT CO2)
DSM Coal Super Critical Geothermal Nuclear IGCC Small Hydro Biomass-Gasification Biomass-CHP IGCC-CCS Large Hydro
DSMSuper Critical
Coal
Geothermal
Nuclear
IGCC
Small Hydro
Biomass -
Gasification
Biomass -
CHP
Large
Hydro
58
64
IGCC-CCS
219
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 45 12/20/2011
VII.C. Demand Side Management Measures
If demand reduction measures are implemented along with the 30$/tCO2 marginal carbon cost,
additional reduction in emissions can be achieved. Under such scenarios Indonesian power sector
can contribute towards 3.9% to 4.6% of the total emission reduction targets of 2020.
Figure 17-19 below illustrates the changes over BAU in generation mix (TWh) with DSM under
different carbon cost for 2020 & 2030. The graph represents the penetration of super critical
technology, hydro and Biomass under each of the scenarios in 2020 while penetration of
Nuclear, Geothermal and IGCC by 2030.
Figure 17: 2020 Changes in Generation Mix with DSM under various Carbon Cost
Figure 18: 2030 Changes in Generation Mix with DSM under various Carbon Cost
-120
-100
-80
-60
-40
-20
0
20
40
60
80
100
DSM+30$ DSM+50$ DSM+80$
Ch
ange
in G
en
era
tio
n M
ix (
TWh
)
Geothermal
Hydro
Nuclear
Oil
IGCC
Coal Super Critical
Coal Sub Critical
Gas
Biomass
-300
-250
-200
-150
-100
-50
0
50
100
150
DSM+30$ DSM+50$ DSM+80$
Ch
ange
in G
en
era
tio
n M
ix (
TWh
)
Geothermal
Hydro
Nuclear
Oil
IGCC
Coal Super Critical
Coal Sub Critical
Gas
Biomass
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 46 12/20/2011
As would be expected, implementation of demand side management measures are the most cost
effective options for reducing the emissions from the power sector (Figure 19).
Figure 19: Total Abatement Potential with and without DSM
VII.D. Summary of Mitigation Scenarios Analysis
Emissions from the power sector are expected to increase to 268 MtCO2 by 2020, and under the
mitigation scenarios, Indonesia has the maximum potential to abate approximately 54MtCO2 in
2020 at a carbon price of $80/tCO2, which contributes to approximately 7% of the total emission
targets of 26% announced by the Indonesian Government. Of this total abatement, contribution
from DSM towards emission reduction can be significant: up to 20 MtCO2 in 2020.
Further by 2030, the maximum abatement that can be achieved by Indonesia is approximately
200 MtCO2 and of which 50% can be achieved through DSM programs under our assumptions.
Thus the important takeaways from this section of the report are the fact that the results under the
Dynamic MACC analysis assuming all else is constant, the choice of generation mix depends on
two primary external variables – carbon price and the time period under consideration. The
higher the carbon price, the more incentive to introduce cleaner technologies in order to displace
dirtier ones and the longer the time period, the higher the ability of clean projects to earn their
returns and hence prove more profitable than dirtier ones.
Indonesian policymakers should accordingly focus on implementing mitigation measures with a
longer time frame in mind and an incentive mechanism (imposing a carbon price on emissions is
9
31 25
131
14
38
91
194
3254
115
219
0
50
100
150
200
250
Without DSM With DSM Without DSM With DSM
2020 2030
Ab
ate
me
nt
Po
ten
tia
l (M
T C
o2
)
CP30 CP50 CP80
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 47 12/20/2011
one method that we consider) that financially incentivizes clean energy technology while
simultaneously penalizes polluting ones.
This analysis will be helpful in informing policymakers the expected emissions from imposing a
range of carbon prices. Policymakers may also choose to increase the impact of carbon pricing
by changing some of the BAU conditions such as removing oil subsidies, creating subsidies for
clean coal technology, removing implementation barriers to geothermal (thereby creating a larger
pool of exploitable resource). Such changes in domestic policy will change the equation in favor
of cleaner technologies, and hence the overall effect of carbon prices will be significantly larger.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 48 12/20/2011
VIII. Cost Summary
The Total Annual Resource Cost shows total System Cost under BAU and at specific carbon
prices ($30, $50, $80) as well as those carbon prices with all DSM options enacted. System Cost
includes fixed and variable cost of operations, fuel cost, capital cost, and any DSM investment
necessary. With DSM options enacted, all carbon price scenarios are less expensive when
compared to BAU. Tables 17-18 below show the Total Annual Resource cost in 2020 and 2030.
Figures 20-21 show incremental system costs as well as abatement potential without DSM
options. The optimal incremental savings is carbon price $30/tCO2 with energy efficiency
measures enacted in 2020 and 2030. With energy efficiency measures and investment cost
accounted for, these options would mitigate 31 MtCO2 and 131 MtCO2 in 2020 and 2030,
respectively. This would also save $1297 Mm and $5252 Mm respectively.
Table 17 Total Annual Resource Cost 2020
Total Annual Resource Cost
(MmUS$) BAU CP30 CP50 CP80 DSM30ALL DSM50ALL DSM80ALL
Variable O&M 1,089 1,066 1,065 1,033 994 990 958
Fixed O&M 3,132 3,184 3,226 3,440 2,999 3,067 3,255
Fuel 12,465 12,163 11,996 11,257 11,261 10,974 10,341
Capital 6,300 6,690 7,069 8,777 5,644 6,211 7,745
Total 22985.2 23103.8 23355.7 24507 20897.7 21242.2 22299
Table 18 Total Annual Resource Cost 2030
Total Annual Resource Cost
(MmUS$) BAU CP30 CP50 CP80 DSM30ALL DSM50ALL DSM80ALL
Variable O&M 2,812 2,761 2,819 2,776 2,376 2,415 2,361
Fixed O&M 6,923 7,118 7,680 7,915 6,203 6,787 7,020
Fuel 29,682 28,906 26,729 25,994 25054.5 22905.4 22264.9
Capital 27,484 28,726 33,078 35,699 23,324 27,607 30,101
Total 66,901 67,510 70,306 72,382 56,958 59,714 61,747
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 49 12/20/2011
Figure 20 Incremental System Cost 2020
Figure 21 Incremental System Cost 2030
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 50 12/20/2011
IX. Results Comparison
IX.A. Indonesian Climate Change Sectoral Roadmap by BAPPENAS
In December 2007 Bappenas (National Development Planning Agency) published a document
titled "National Development Planning: Indonesia Responses to Climate Change", that has been
revised in July 200818
. The document is intended to strengthen and reinforce the RPJMN
(National Medium-Term Development Plan) 2004-2009 as well as to include inputs for the
preparation of RPJMN 2010-2014 in the context of integrating climate change. The Indonesian
Climate Change Sectoral Roadmap (ICCSR) is meant to provide inputs for the 5 year RPJMN
(2010-2014), laying particular emphasis on the challenges emerging in the forestry, energy,
industry, agriculture, transportation, coastal area, water, waste and health sectors. In this, several
goals are set out with regards to both adaptation and mitigation of climate change. The most
important goal is that emissions from greenhouse gases will decrease by 26% from total
projected BAU emissions in 2020.
Within the power sector in Indonesia, the BAU scenario projects future level of emissions
against which reduction by project activity might be determined. Without policy or regulatory
intervention, the government of Indonesia predicts that emissions would increase 189% from 83
MtCO2 in 2009 to 236 MtCO2 in 2020. This compares quite closely with ICF’s result of
emissions rising under BAU up to 268 MtCO2 in 2020.
According to the analysis, using the current trend of introduction of renewable technologies
(mainly geothermal) 18 MtCO2were reduced by 2020. Constraints for some technologies was set
according to the resource limit and geographical limit. New technologies, including speculative
technologies improving emissions from coal and gas were added to the base case scenario. These
technologies include both retrofitting as well as carbon capture technology.
Four likely and speculative new technologies using coal and gas were added to the base- case
scenario for application within the life time considered in the model. Retrofitting is also included
as well as CCS and other variants of carbon capture technology. Carbon reductions from these
technologies are estimated at 40.2 MtCO2, of 17% or total emission by 2020, with an abatement
cost of $23.44/tCO2. These new technologies when combined with a 4 GW Nuclear Plant and
introduction of carbon capture technology achieve reductions or 62.4 MtCO2, or 26.4% of total
emissions by 2020, with abatement costs of $33.74/tCO2.
Finally, carbon prices were imposed in the model. Values of 25 USD and $50/tCO2were imposed
for both the base case scenario and total carbon emission cap with new technologies. In the year
2020, at $25/tCO2 emissions reduced by 88.4 MtCO2 (37.4%), while at $50/tCO2 will result in
reduction by 129.7 MtCO2 (53.8%).
The BAPPENAS analysis does not include a wide range of policy options. This analysis also
uses technology as the base for achieving reductions instead of the effects of a carbon price.
Unfortunately, this methodology does not consider the effect or benefit of energy efficiency
measures. Reduction in projected demand would also decrease the efficacy of certain
technologies that are introduced to the system.
18
Bappenas, 2009 ―Indonesia Climate Change Sectoral Roadmap‖
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 51 12/20/2011
IX.B. Indonesia’s Greenhouse Gas Abatement Cost Curve by DNPI
To coordinate climate change-related activities within Indonesia, in July 2008 President
Yudhoyono established the Dewan Nasional Perubahan Iklim (DNPI) or National Council on
Climate Change. The Council is specifically tasked with the role of convening different
stakeholders in Indonesia to create consensus around the opportunities and challenges related to
climate change. To that effect, the DN PI has commissioned a study on GHG Abatement Cost
Curve analysis to provide a quantitative basis for a national discussion on the opportunities for
reducing GHG emissions in Indonesia consistent with national development goals. The global
greenhouse gas abatement ―cost curve‖ developed by global consultancy McKinsey & Company
summarizes the technical potential to reduce emissions of greenhouse gases at a cost of up to 80
USD per tCO2e of avoided emissions. The cost curve shows the range of emission reduction
actions that are possible with technologies that either are available today or are highly likely to
be available by 2030.19
As stated before in the comparison between static and dynamic cost curves, step curves such as
those shown in the DNPI study tells the reader that what abatement potential is achievable at a
particular carbon price, while our analysis goes a step further and demonstrates emissions
reductions resulting from the installed capacity and generation mix at a carbon price range given
the system dynamics of the Indonesian electricity sector. From a policymaker’s perspective the
Static MACC presented in the DNPI study, though helpful, lays out the mitigation potential
simplistically without considering the systemic limitations and dynamics of the Indonesian
electricity sector. Hence, comparison with the DNPI study would mean extrapolating results
from our Dynamic MACC analysis and representing it in the form of a static MACC as shown in
figures 13 and 16 in an earlier section.
The cost curve analysis in the DNPI study presents abatement opportunities that would be
available at an abatement cost ceiling of $80/tCO2 in 2030. The DNPI study estimates installing
an additional 27 GW of hydro capacity by 2030 which represents an abatement potential of 65
MtCO2e at a negative abatement cost of -7/tCO2e. This is the most significant difference from
our study as we project a maximum of 18 GW additional capacity added at a carbon price of
$80/tCO2, which represents an abatement potential of 15 MtCO2. Similarly, the DNPI study
projects Biomass power plants as the second largest abatement opportunity at 64 MtCO2e
reductions. Our analysis projects that up to 16 GW of biomass capacity could be added to the
installed capacity mix by 2030 at a carbon price of $80/tCO2 which represents an abatement
potential of 34 MtCO2. The DNPI study assumes an additional 6 GW of Geothermal capacity
into the electricity mix, while CCAP assumes a maximum of 4 GW added Geothermal capacity
by 2030.
The DNPI study projects that DSM options have an abatement potential of 47 MtCO2e, while our
projections measure it to be 104 MtCO2. The limitations of our DSM figures have been
explained in an earlier section and should be viewed in such light while making comparisons. At
19
DNPI 2010, ―Indonesia’s Greenhouse Gas Abatement Curve‖
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 52 12/20/2011
the point of writing this report, the authors were not able to obtain the assumptions behind the
DNPI study’s methodology of estimating the DSM potential in Indonesia.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 53 12/20/2011
X. Conclusions and Next Steps
Emissions from the power sector in Indonesia are set to increase to approximately 268 MtCO2 in
2020 and 688 MtCO2 by 2030 in a BAU context. Our analysis suggests that the power sector can
contribute to emissions reduction of around 54 MtCO2 and 219 MtCO2 by 2020 and 2030
respectively. Considering that the Indonesian Govt. has a self-imposed emissions reduction
target of 26% by 2020, which amounts to around 658 MtCO2 (assuming that total emissions are
2.530 GtCO2 as per the DNPI report), the power sector could contribute up to 8.2% of necessary
emissions reduction.
Broadly, emissions from the electricity sector can be reduced by reducing demand and reducing
carbon content of the electricity generated. Our study suggests that there is a large potential to
reduce electricity demand by increasing the potential of energy efficient technologies (or DSM).
DSM measures can provide emission reductions of approximately 20 MtCO2 in 2020 and 100
MtCO2 in 2030. However, distinguishing the rate of adoption of these energy efficient
technologies under BAU and mitigation scenarios is a highly complex exercise that is influenced
by many unquantifiable variables such as social trends and pricing of green products. Hence,
while we recommend increasing the rate of adoption of energy efficient appliances and
technology, we would like to focus on the results relating to making the supply side options
cleaner.
Regarding the supply side analysis, it is obvious from the modeling exercise carried out in this
report that the imposition of carbon price will be successful in making the generation mix
cleaner. A mitigation potential of 32 MtCO2 and 115 MtCO2 exists by years 2020 and 2030
respectively (not considering reduced demand from DSM) at a carbon price of $80/ tCO2.
However, one should note that a high carbon price scenario such as this is not feasible either
domestically or internationally in the short-to-medium term. Hence, in order to achieve any
significant reduction, policy makers need to do more in order to shift the economics towards
cleaner sources and away from dirty/inefficient ones. While this paper only delves into carbon
pricing as a market-based policy mechanism, there is a whole range of domestic policies that the
Indonesian Govt. could enact in order to tilt the balance.
This paper is one in a series of papers from CCAP regarding the Indonesian power sector. A
paper on the Demand Side Measurement analysis will focus on the limitations and implications
of relying on these measures to achieve national emission reduction targets. A paper on Clean
Coal Policy analysis will focus on possible outcomes if the Indonesian government focuses
primarily on reducing the country’s emissions from coal based power generation. Following
these CCAP will release an analysis of international policy and financing implications of
Indonesian climate goals. This will be the final paper, tying together international processes and
Indonesian climate action.
Finally, the mitigation analysis presented in this paper is designed for policymakers and industry
alike to evaluate possible implications of different mitigation scenarios. A broad range of carbon
price and integrated demand side management scenarios are presented so that the optimal
mitigation policies and actions can be realized. Policymakers should view this analysis as a
resource to determine whether their public policy decisions can be viewed as effective and
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
Center for Clean Air Policy 54 12/20/2011
efficient. Industry can subsequently view the analysis to determine what effect public policy
decisions will have on the generation and capacity mix of Indonesia and invest accordingly.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
55 12/20/2011
APPENDIX 1
MEMR’s Energy and Peak Demand Forecast
Region Energy Demand (GWh)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Java-Bali 122,894 133,996 146,305 159,968 175,074 191,794 210,317 230,855 253,382 278,267
Sumatra 17,694 19,017 20,447 22,051 23,797 25,693 27,754 29,994 32,487 35,219
Kalimantan 5,188 5,628 6,079 6,563 7,074 7,622 8,211 8,846 9,559 10,336
Sulawesi 4,581 4,873 5,196 5,553 5,943 6,365 6,823 7,318 7,862 8,453
Nusa 960 1,029 1,104 1,188 1,281 1,381 1,493 1,609 1,742 1,882
Maluku 456 491 527 571 615 662 713 763 820 880
Papua 667 739 807 873 938 1,002 1,066 1,130 1,195 1,261
Region
Energy Demand (GWh)
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Java-Bali 305,775 336,215 369,930 407,305 448,766 494,792 546,423 603,853 667,767 738,933
Sumatra 38,216 41,507 45,123 49,103 53,490 58,333 63,747 69,751 76,418 84,281
Kalimantan 11,185 12,116 13,137 14,259 15,494 16,863 18,384 20,072 21,951 24,046
Sulawesi 9,099 9,795 10,553 11,370 12,257 13,213 14,250 15,371 16,583 17,897
Nusa 2,037 2,205 2,385 2,581 2,791 3,020 3,265 3,532 3,818 4,128
Maluku 942 1,007 1,074 1,145 1,218 1,295 1,375 1,459 1,546 1,640
Papua 1,329 1,400 1,473 155 1,625 1,706 1,789 1,876 1,966 206
Region Peak Demand (MW)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Java-Bali 19,389 21,141 23,084 2,524 27,624 30,264 33,188 3,643 39,986 43,914
Sumatra 3,316 3,564 3,832 4,133 4,460 4,816 5,202 5,622 6,090 6,602
Kalimantan 1,001 1,085 1,170 1,263 1,362 1,468 1,582 1,704 1,841 1,993
Sulawesi 977 1,039 1,108 1,184 1,267 1,353 1,455 1,561 1,677 1,803
Nusa 220 237 254 274 294 317 343 370 400 432
Maluku 93 100 108 116 126 135 145 156 167 180
Papua 137 151 165 179 192 205 218 231 245 258
Region
Peak Demand (MW)
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Java-Bali 48,257 52,364 57,617 63,441 69,901 77,073 85,115 94,061 104,016 115,102
Sumatra 7,164 7,657 8,325 9,059 9,868 10,762 11,761 12,869 14,099 15,549
Kalimantan 2,157 2,299 1,488 1,591 686 734 787 842 901 964
Sulawesi 1,941 2,053 2,211 2,383 2,568 2,770 2,987 2,176 2,340 2,517
Nusa 468 497 538 581 628 679 735 795 859 928
Maluku 192 202 215 229 244 260 276 292 310 329
Papua 272 282 296 311 327 343 360 377 396 414
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
56 12/20/2011
PLN’s Energy and Peak Demand Forecast
Region
Energy Demand (GWh)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Java-Bali 112,659 119,706 131,821 145,139 159,840 176,006 192,980 211,512 231,527 251,967 275,179
Sumatra 17,966 19,472 21,190 23,050 25,093 27,366 29,851 32,578 35,514 38,741 42,257
Kalimantan 4,908 5,400 5,980 6,607 7,278 8,022 8,825 9,713 10,701 11,771 12,902
Sulawesi 4,628 5,146 5,720 6,385 7,124 7,946 8,861 9,877 11,009 12,266 13,665
Nusa 1,055 1,168 1,360 1,557 1,719 1,887 2,072 2,274 2,495 2,732 2,972
Maluku 463 512 564 618 674 735 799 868 941 1,018 1,101
Papua 619 674 728 787 848 917 991 1,073 1,161 1,257 1,368
Region
Peak Demand (MW)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Java-Bali 17,627 18,854 20,900 23,012 25,343 27,906 30,597 33,535 36,708 39,949 43,629
Sumatra 3,262 3,521 3,817 4,133 4,480 4,863 5,283 5,741 6,232 6,773 7,358
Kalimantan 914 999 1,101 1,210 1,327 1,455 1,592 1,743 1,911 2,094 2,291
Sulawesi 883 982 1,089 1,212 1,347 1,497 1,663 1,847 2,050 2,275 2,525
Nusa 228 256 298 332 357 385 416 448 484 523 566
Maluku 106 117 129 141 153 166 180 194 209 225 243
Papua 132 143 154 166 178 192 207 223 241 260 282
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
57 12/20/2011
ICF’s Energy and Peak Demand Forecast
Region
Energy Demand (GWh)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Java-Bali 107,420 117,803 129,222 141,781 155,593 170,783 187,490 205,864 226,071 248,295 272,737
Sumatra 26,304 27,916 29,690 31,640 33,785 36,144 38,738 41,591 44,729 48,180 51,976
Kalimantan 9,068 9,498 9,972 10,492 11,065 11,694 12,387 13,148 13,986 14,907 15,920
Sulawesi 4,367 4,803 5,282 5,809 6,389 7,027 7,728 8,499 9,348 10,281 11,307
Nusa 1,222 1,319 1,426 1,544 1,673 1,815 1,972 2,144 2,333 2,541 2,770
Maluku 427 470 516 568 625 687 756 831 914 1,005 1,105
Papua 585 644 708 778 856 942 1,036 1,139 1,253 1,378 1,515
Region
Energy Demand (GWh)
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Java-Bali 299,619 329,183 361,698 397,458 436,786 480,040 527,610 579,928 637,467 700,748 770,345 846,888
Sumatra 56,150 60,741 65,790 71,343 77,451 84,167 91,555 99,679 108,614 118,441 129,249 141,135
Kalimantan 17,034 18,259 19,607 21,089 22,719 24,512 26,483 28,652 31,037 33,659 36,544 39,716
Sulawesi 12,435 13,676 15,041 16,542 18,193 20,008 22,005 24,201 26,617 29,273 32,194 35,407
Nusa 3,021 3,298 3,602 3,937 4,305 4,710 5,156 5,645 6,184 6,776 7,428 8,144
Maluku 1,216 1,337 1,471 1,617 1,779 1,956 2,151 2,366 2,602 2,862 3,148 3,462
Papua 1,666 1,832 2,015 2,216 2,438 2,681 2,949 3,243 3,566 3,922 4,314 4,744
Region
Peak Demand (MW)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Java-Bali 18,262 20,046 22,009 24,168 26,541 29,152 32,024 35,182 38,655 42,475 46,676
Sumatra 4,353 4,687 5,055 5,460 5,905 6,395 6,933 7,525 8,177 8,893 9,681
Kalimantan 1,374 1,461 1,557 1,662 1,778 1,906 2,046 2,200 2,370 2,556 2,762
Sulawesi 899 989 1,088 1,197 1,316 1,447 1,592 1,751 1,925 2,117 2,329
Nusa 217 236 258 281 306 334 365 399 437 478 523
Maluku 94 104 114 125 138 152 167 183 202 222 244
Papua 138 152 167 184 202 222 244 269 296 325 358
Region
Peak Demand (MW)
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Java-Bali 51,296 56,379 61,967 68,113 74,873 82,307 90,484 99,477 109,366 120,243 132,205 145,362
Sumatra 10,547 11,500 12,548 13,700 14,968 16,362 17,895 19,581 21,435 23,474 25,717 28,184
Kalimantan 2,987 3,236 3,509 3,809 4,139 4,502 4,902 5,341 5,824 6,355 6,940 7,582
Sulawesi 2,561 2,817 3,098 3,407 3,747 4,121 4,532 4,985 5,482 6,029 6,631 7,293
Nusa 572 627 687 753 826 906 994 1,091 1,197 1,314 1,442 1,584
Maluku 268 295 325 357 393 432 475 522 575 632 695 764
Papua 393 433 476 523 575 633 696 765 842 926 1,018 1,120
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
58 12/20/2011
APPENDIX 2
MEMR’s Reserve Margin
Region Reserve Margin (%)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
West Java 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15%
Central Java 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
East Java + Bali 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Sumatera 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Kalimantan 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Sulawesi 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Nusa 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Papua 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Maluku 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Region Reserve Margin (%)
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
West Java 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15%
Central Java 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
East Java + Bali 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Sumatera 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Kalimantan 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Sulawesi 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Nusa 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Papua 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
Maluku 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25% 25%
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
59 12/20/2011
APPENDIX 3
T&D Losses
Region
T&D Losses (%)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Java-Bali 9.5 9.4 9.3 9.2 9.1 9.0 8.9 8.8 8.7 8.6 8.5
Sumatra 11.5 11.4 11.3 11.2 11.1 11.0 10.9 10.8 10.7 10.6 10.5
Kalimantan 11.8 11.7 11.6 11.5 11.4 11.3 11.2 11.1 11.0 10.9 10.8
Sulawesi 11.5 11.4 11.3 11.2 11.1 11.0 10.9 10.8 10.7 10.6 10.5
Nusa 7.5 7.4 7.3 7.2 7.1 7.0 7.0 7.0 7.0 7.0 7.0
Maluku 8.0 7.9 7.8 7.7 7.6 7.5 7.5 7.5 7.5 7.5 7.5
Papua 10.0 9.9 9.8 9.7 9.6 9.5 9.4 9.3 9.2 9.1 9.0
Region
T&D Losses (%)
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Java-Bali 8.4 8.3 8.2 8.1 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0
Sumatra 10.4 10.3 10.2 10.1 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
Kalimantan 10.7 10.6 10.5 10.4 10.3 10.3 10.3 10.2 10.2 10.2 10.2 10.2
Sulawesi 10.5 10.4 10.4 10.3 10.3 10.2 10.2 10.1 10.1 10.1 10.1 10.1
Nusa 7.0 7.0 7.0 7.0 7.0 7.0 7.0 7.0 7.0 7.0 7.0 7.0
Maluku 7.5 7.5 7.5 7.5 7.5 7.5 7.5 7.5 7.5 7.5 7.5 7.5
Papua 9.0 9.0 9.0 9.0 9.0 9.0 9.0 9.0 9.0 9.0 9.0 9.0
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
60 12/20/2011
APPENDIX 4
Capacity under First 10,000MW Crash Program as assumed in ICF Modeling
Year Capacity in Java (MW) Capacity Outside Java (MW)
2009 1,500 400
2010 1,500 400
2011 1,500 400
2012 1,500 400
2013 1,500 400
Total 7,500 2,000
Progress of Plants planned under First 10,000MW Crash Program
Power Plant Capacity (MW) Progress till 2009
PLTU Labuan 2 x 315 COD
PLTU Rembang 2 x 315 COD
PLTU Indramayu 3 x 330 COD in 2010
PLTU Suralaya 1 x 625 80%
PLTU Paiton 1 x 660 73%
PLTU Pacitan 2 x 315 72%
PLTU Pelabuhan Ratu 3 x 350 42%
PLTU Teluk Naga 3 x 315 50%
PLTU Tanjung Awar-awar 2 X 350 8%
PLTU Kendari 2 x 10 52%
PLTU Ende 2 x 7 64%
Capacity under Second 10,000MW Crash Program as assumed in ICF Modeling Capacity
Type Region 2014 2015 2016 2017 2018 2019
Coal Java - - - - - -
Outside Java 200 200 200 200 200 200
Gas Java 300 300 300 - - -
Outside Java 600 600 500 - - -
Geothermal Java - - 500 - 400 -
Outside Java - - 250 250 - -
Hydro Java 400 400 400 400 - -
Outside Java 800 800 800 800 - -
APPENDIX 5
Geothermal Resource Potential in Indonesia
Location Resources (MWe)
Speculative Hypothetic Probable Possible Proven
Sumatera 5,275 2,194 5,555 15 380
Jawa 2,235 1,446 3,175 885 1,815
Bali-Nusa Tenggara 360 359 943 - 14
Sulawesi 925 12 865 150 78
Maluku 400 37 297 - -
Kalimatan 45 - - - -
Papua 50 - - - -
Total 9,290 4,048 10,835 1,050 2,287
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
61 12/20/2011
APPENDIX 6
ICF's Fuel Price Assumptions
Year HSD Coal Gas
USD/Barrel USD/Ton USD/MMBtu
2008 45.0 98.0 4.0
2009 48.6 89.3 4.2
2010 58.8 83.7 4.5
2011 63.9 80.2 4.7
2012 66.6 79.6 5.0
2013 68.7 78.8 5.3
2014 70.6 77.9 6.0
2015 72.7 77.2 6.0
2016 74.2 77.1 6.0
2017 75.3 77.1 6.0
2018 75.3 77.1 6.0
2019 75.3 77.1 6.0
2020 75.3 77.1 6.0
2021 75.3 77.1 6.0
2022 75.3 77.1 6.0
2023 75.3 77.1 6.0
2024 75.3 77.1 6.0
2025 75.3 77.1 6.0
2026 75.3 77.1 6.0
2027 75.3 77.1 6.0
2028 75.3 77.1 6.0
2029 75.3 77.0 6.0
2030 75.3 77.0 6.0 Prices in Real2008$
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
62 12/20/2011
PLN’s Fuel Price Assumptions
Year HSD Coal Gas
USD/Barrel USD/Ton USD/MMBtu
2008 140.0 90.0 6.0
2009 140.0 90.0 6.0
2010 140.0 90.0 6.0
2011 140.0 90.0 6.0
2012 140.0 90.0 6.0
2013 140.0 90.0 6.0
2014 140.0 90.0 6.0
2015 140.0 90.0 6.0
2016 140.0 90.0 6.0
2017 140.0 90.0 6.0
2018 140.0 90.0 6.0
2019 140.0 90.0 6.0
2020 140.0 90.0 6.0
2021 140.0 90.0 6.0
2022 140.0 90.0 6.0
2023 140.0 90.0 6.0
2024 140.0 90.0 6.0
2025 140.0 90.0 6.0
2026 140.0 90.0 6.0
2027 140.0 90.0 6.0
2028 140.0 90.0 6.0
2029 140.0 90.0 6.0
2030 140.0 90.0 6.0
Prices in Real2008$
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
63 12/20/2011
APPENDIX 7 Cost and Performance Data for NEW Electricity Generation Technologies
Technology Fuel Unit Size (MW)
Efficiency1
(%)
Maximum Capacity Factor
2
(%)
FOM Cost
3
(US $/kW-year)*
VOM Cost
4
(US $/MWh)*
Investment Cost
5 (US
$/kW)*
Construction Time
6 (Year)
Java Bali Region
Super Critical Coal
Coal 660 45 85 29.16 1.60 1,400 4
Sub Critical Coal
Coal 250 36 85 29.16 1.60 1,190 4
Combined Cycle
Natural gas 330 49 90 22.00 1.96 930 3
Combustion Turbine
Oil 50 25 100 22.00 1.96 550 3
IGCC Coal 600 40 95 31.77 1.60 1,800 4
IGCC-CCS Coal 600 32 95 31.77 1.60 3,100
Nuclear Uranium 1000 - 90 76.27 0.94 4,000 7
Geothermal Geothermal 50 - 95 50.00 8.00 2,800 3
Biomass (Combustion Power)
Biomass 20 15 50 38.22 0.71 $1,700 in 2020
2
Biomass (CHP)
Biomass 20 45 50 38.22 0.71 $1,550 in 2020
2
Biomass (Gasification)
Biomass 20 75 50 38.22 0.71 $2,100 in 2020
2
Large Hydro Hydro >10 - Monthly Profile
53.33 - 3,000 5
Small Hydro Hydro <10 - Monthly Profile
53.33 - 2,000 4
Outside Java Bali Region
Super Critical Coal
Coal 660 45 85 29.16 1.60 1,600 4
Sub Critical Coal – Sumatra
Coal 250 32 85 29.16 1.60 1,300 4
Sub Critical Coal – Kalimantan
Coal 65 30 85 29.16 1.60 1,300 4
Sub Critical Coal – Nusa
Coal 50 30 85 29.16 1.60 1,300 4
IGCC Coal 600 40 95 31.77 1.60 1,800 4
IGCC - CCS Coal 600 32 95 31.77 1.60 3,100 4
Combined Cycle
Natural gas 150 36 90 22 1.96 1,000 3
Combustion Turbine
Oil 50 24 100 22 1.96 600 3
Geothermal Geothermal 10-55
- 95 50 1.00 2,00 3
Biomass (Combustion Power)
Biomass 20 15 50 38.22 0.71 $1,700 in 2020
2
Biomass (CHP)
Biomass 20 45 50 38.22 0.71 $1,550 in 2020
2
Biomass (Gasification)
Biomass 20 75 50 38.22 0.71 $2,100 in 2020
2
Large Hydro Hydro >10 - Monthly Profile
53.33 - 3,000 5
Small Hydro Hydro <10 - Monthly Profile
53.33 - 2,000 4
Source: 1 and 5 – RUPTL, PLN except for Biomass and Geothermal
2, 3,4 and 6 – ICF Assumptions
Note: All cost numbers are US $2008
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
64 12/20/2011
APPENDIX 8
Emission Factors from IPCC tables for stationary combustion in the energy sector
Fuel
CO2 Content N2O Content
kg/TJ on a Net Calorific Basis
Anthracite 98,300 1.5
Lignite 101,000 1.5
Sub-Bituminous 94,600 1.5
Bituminous 94,600 1.5
Natural Gas 56,100 0.1
Oil 77,400 0.6
Distillate 77,400 0.6
Landfill Gas 54,600 0.1
Biomass 54,600 0.1
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
65 12/20/2011
APPENDIX 9
Energy savings and investment cost for various Demand Side Management Activities
GWH Mn USD GWH Mn USD GWH Mn USD GWH Mn USD GWH Mn USD GWH Mn USD
Energy Savings Investment Cost Energy Savings Investment Cost Energy Savings Investment Cost Energy Savings Investment Cost Energy Savings Investment Cost Energy Savings Investment Cost
2010 0 0 0 0 0 0 0 0 0 0 0 0
2011 295 11 25 7 43 3 92 28 822 85 182 66
2012 644 9 54 9 94 3 200 33 1791 100 396 78
2013 1053 7 88 10 154 4 327 39 2928 117 647 91
2014 1530 5 128 10 224 4 476 45 4256 137 941 107
2015 2085 3 175 10 305 5 648 53 5799 159 1282 124
2016 2727 14 229 9 399 8 848 61 7585 184 1677 143
2017 3468 26 291 9 508 12 1078 71 9645 213 2132 165
2018 4320 41 362 8 633 16 1343 81 12015 245 2656 190
2019 5297 59 444 7 776 21 1647 93 14734 281 3257 218
2020 6415 79 538 6 940 27 1995 107 17844 321 3945 250
2021 7692 103 645 5 1127 34 2392 122 21395 367 4730 285
2022 9146 130 766 3 1340 42 2844 139 25441 418 5624 325
2023 10800 162 905 1 1582 51 3358 158 30041 475 6641 369
2024 12678 197 1062 -1 1857 61 3942 179 35264 539 7795 419
2025 14806 238 1241 5 2168 73 4604 203 41183 611 9104 475
2026 17215 285 1443 13 2521 87 5353 258 47882 776 10585 625
2027 19937 338 1671 22 2920 102 6199 321 55453 966 12259 827
2028 23009 399 1928 32 3370 119 7155 393 64000 1184 14148 1061
2029 26474 468 2219 44 3877 138 8232 476 73635 1434 16278 13292030 30375 545 2545 58 4448 160 9445 570 84486 1719 18677 1639
RefrigeratorsYears General Lighting Ballasts Street Lighting Air-Conditioning Chillers
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
66 12/20/2011
APPENDIX 10
Integrated Planning Model (IPM®) is a linear programming formulation that selects investment
options and dispatches generating and load management resources to meet overall electric
demand today and over the chosen planning horizon. System dispatch - determining the proper
and most efficient use of the existing and new resources available to utilities and their customers
- is optimized given the security requirements, resource mix, unit operating characteristics, fuel
and other costs including environmental costs, and transmission possibilities. Although the
solution is arrived at simultaneously, conceptually it is easier to think of the model carrying out a
series of tasks.
As a forward-looking model, the IPM® can easily tackle the complex task of determining the
most efficient capacity adjustment path. Because the model solves for all years simultaneously, it
will select the most appropriate solution to ensure that system security is not compromised (e.g.
build new base-load or peaking units, retrofit or repower existing units), select units that should
be retired or mothballed, and identify the timing of such events. Capacity prices are one of the
results from this optimization process. Investment decisions are selected by the model by taking
into account system security requirements, forecasts of customer demand for electricity,
realization of electricity prices across the year, the cost and performance characteristics of
available options, technical characteristics of existing power plant units and a host of other
factors. By using this degree of foresight, the model replicates the approach used by power plant
developers, regulatory personnel, and energy users when reviewing investment options.
Applications of the IPM®
Its linear programming structure makes the IPM®
particularly well suited for a variety of
applications such as assessing planning strategies or regulatory policy options. Among the types
of analyses that can be conducted with the IPM® are:
Power price forecasts. The IPM® can be used to predict wholesale power, renewables
obligation certificates prices or the value of emission permits using scenarios developed
through the IPM® database interface.
Strategic planning. The IPM® can be used to assess the costs and risks associated with
alternative utility and consumer resource planning strategies as characterized by the
portfolio of options included in the input data base.
Analysis of uncertainty. The efficiency of the model's computational algorithms allows
it to be used with various techniques for analyzing the potential impacts of uncertain
future conditions (e.g. load growth, fuel prices, environmental regulations, costs and
performance of resource options) and the risks associated with alternative planning
strategies. Alternative approaches that have been used for analyzing uncertainty with the
IPM® include sensitivity analysis, decision analysis, and modelling uncertainty
endogenously by incorporating specific factors that are uncertain and the associated
probabilities for different values or expectations for these factors directly into the linear
programming structure.
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
67 12/20/2011
Optimization of operations under system-wide constraints. Various approaches can be
evaluated for meeting environmental constraints (e.g. limits on hourly, daily, or annual
emissions), fuel use constraints (e.g. optimum allocation of limited fuel supplies to
alternative plants), load management constraints (e.g. dispatch of directly controlled
loads given limits on the availability and scheduling of service interruptions), and other
operational constraints (e.g. "must-run" considerations and "area-protection" concerns).
The model can also address optimum usage of pumped storage facilities and economic
or long-term contracted power purchases from neighboring regions.
Assessing the effect of multi-pollutant policies. The environmental modelling
capabilities are extremely sophisticated, developed as they have been with a view to
support the US EPA’s federal emission control programmes since the 1980s. Whether
estimating the marginal abatement costs of NOx, SO2, or CO2, or establishing the
optimal operating and investment regime in the face of multi-pollutant regulations, the
IPM allows the user to compare alternative investment programmes thus minimizing the
possibility of stranding investments and preparing the client to respond pro-actively to
evolving environmental regulation.
Options assessment. The IPM® can be used to "screen" alternative resource options and
option combinations based upon their relative costs and potential earnings. By defining
all plausible alternatives, the model will suggest the optimal timing for different actions
on the basis that all market participants are seeking to maximize profits.
Estimation of avoided costs. Shadow prices from the linear programming solution can
be used to determine avoided costs by season or time-of-day for pricing purchases from
qualifying facilities, independent power producers, or economy and/or firm power
purchases from other utilities. Shadow prices also can be used to assess the economic
value of relaxing a constraint (e.g. what is the marginal cost of emissions reductions for
the utility?), to conduct marginal cost studies, and to determine the cost reductions of
alternative options in order for these options to be competitive with those options
selected by the model or the "preferred" options. This greatly enhances the capability to
use the model and its outputs as a screening tool.
Integrated resource planning. The IPM® can be used to perform least-cost planning
studies that simultaneously optimise demand-side options (load management and
conservation), fuel supply, non-utility supply, renewable options and traditional utility
supply-side options. The model has been licensed to Red Eléctrica de España (REE) and
Polskie Sieci Elektroenergetyczne (PSE), system operators in Spain and Poland
respectively, who use it to prepare inputs into their national energy plans. We have also
licensed the software to a number of private sector clients.
Detailed modelling of dispatch. The IPM®’s dispatch algorithms are very accurate and
have been benchmarked against detailed utility dispatch models. This includes the
ability to optimise the allocation of capacity across energy, reserve and capacity markets.
We are also adept at using this in combination with other industry standard models such
as GE MAPS and PowerWorld.
IPM® Modelling Approach
DRAFT Report for Developing Country Project: Mobilizing Sectoral Mitigation Actions in
Indonesia – Power Sector
68 12/20/2011
The IPM® uses a linear optimization to simultaneously solve for power plant dispatch and fuel
use, capacity expansion, environmental retrofitting, modernization/re-powering, inter-regional
transmission, electric energy and capacity prices, and emissions costs. The model accurately
captures the unique performance characteristics and limitations of conventional and
unconventional generation technologies including gas and steam turbines, combined cycle, co-
generation, nuclear, hydro, wind, solar, and other renewables. Energy efficiency and demand
side management programs are properly evaluated in an integrated framework with other
resource options recognizing their limited capacity value and non-dispatchable characteristics.
The IPM® is also a dynamic model that optimizes capacity decisions over the entire planning
period simultaneously.