+ All Categories
Home > Documents > indr.orgindr.org/wp-content/uploads/2013/11/418-Yudongxia-Reservoir-and-N… · i Contents...

indr.orgindr.org/wp-content/uploads/2013/11/418-Yudongxia-Reservoir-and-N… · i Contents...

Date post: 21-Sep-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
184
Resettlement Plan September 2012 PRC: Guiyang Integrated Water Resources Management (Sector) Project Updated Resettlement Plan for Yudongxia Reservoir Core Subproject Prepared by the Guiyang municipal government for the Asian Development Bank.
Transcript
  • Resettlement Plan September 2012

    PRC: Guiyang Integrated Water Resources Management (Sector) Project Updated Resettlement Plan for Yudongxia Reservoir Core Subproject Prepared by the Guiyang municipal government for the Asian Development Bank.

  • CURRENCY EQUIVALENTS (as of 18 September 2012)

    Currency unit – yuan (CNY)

    CNY1.00 = $0.1581

    $1.00 = CNY6.3245

    NOTE (i) The fiscal year (FY) of the Government of the People’s Republic of China and its

    agencies ends on 31 December. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY2011 ends on 31 December 2011.

    (ii) In this report, "$" refers to US dollars. This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

  • Resettlement Plan for the Yudongxia Reservoir and No.2 Dongjiao Waterworks

    Subproject (Updated)

    Guiyang ADB Project Management Office

    Guiyang Zhushui Water Resources Industrial Development Co.,

    Ltd.

    October 2011

    ADB-funded Guiyang Integrated Water Resources Management (Sector) Project

  • i

    Contents

    ABBREVIATIONS……………………………………………………………………………..….vi

    NOTES TO THIS UPDATE……………………………………………………………………..vii

    LETTER OF COMMITMENT………………………………………………………………….…x

    EXECUTIVE SUMMARY…………………………………………………….………………….xi

    1. OVERVIEW OF THE SUBPROJECT ..................................................................... 1

    1.1. Background ................................................................................................. 1

    1.2 Brief Introduction ......................................................................................... 2

    1.2.1. Project Components ........................................................................................... 2

    1.2.2. Range of Land Acquisition and House Demolition and Brief Introduction of

    Impacts……. ................................................................................................................... …3

    1.2.3. Socioeconomic Benefits of the Subproject ......................................................... 4

    1.2.4. Resettlement Cost Estimate ............................................................................... 4

    1.2.5. Project and Resettlement Implementation Plan ................................................. 4

    2. RANGE OF PROJECT AREA AND SOCIOECONOMIC PROFILE ....................... 7

    2.1. Measures to Avoid or Minimize Land Acquisition and House Demolition .. 7

    2.1.1. Principles for Project Design and Site Selection ................................................ 7

    2.1.2. Scheme Comparison of the Subproject .............................................................. 7

    2.2. Range of Survey for Land Acquisition and House Demolition Impacts .... 10

    2.3. Socioeconomic Profile of Affected City and District (County) .................. 11

    2.3.1. Socioeconomic Profile of Affected City (Prefecture) .......................................... 11

    2.3.2. Socioeconomic Profile of Affected District (County) ......................................... 12

    2.4. Socioeconomic Profile of Affected Towns ................................................. 13

    2.5. Socioeconomic Profile of Affected Villages .............................................. 14

    3. PROJECT IMPACTS ............................................................................................. 16

    3.1. Project Impacts Identification .................................................................... 16

    3.2. Methods for Project Impacts Survey (physical indicators) ....................... 16

    3.2.1. Land Survey ...................................................................................................... 16

    3.2.2. Survey of Population and Houses .................................................................... 16

    3.2.3. Survey of Special Items .................................................................................... 17

    3.2.4. Verification of Survey Results ........................................................................... 17

    3.3. Project Impacts and Impact Level Analysis .............................................. 17

    3.3.1. Permanent Acquisition of Collective Land and Impacts Analysis ..................... 17

    3.3.2. Temporary Land Occupation ............................................................................. 25

    3.3.3. Demolition of Residential Houses, Attached Facilities and Impact Analysis .... 27

    3.3.4. Impacts Analysis for Demolition of Non-residential Houses ............................. 28

    3.3.5. Situation of Affected People and Socioeconomic Profile .................................. 29

    3.4. Ethnic Minorities........................................................................................ 31

    3.5. Basic Conditions Survey for Vulnerable Groups ...................................... 32

    3.6. Women Gender Analysis .......................................................................... 33

    3.7. Scattered Trees and Tombs ...................................................................... 34

    3.8. Infrastructure and Special Facilities .......................................................... 35

  • ii

    3.9. Mineral Resources and Cultural Relics .................................................... 38

    3.10. Other Impacts ........................................................................................... 38

    4. LEGAL FRAMEWORK AND POLICIES ................................................................ 40

    4.1. Applicable Laws, Regulations & Policies for Resettlement ...................... 40

    4.2. ADB Policies ............................................................................................. 41

    4.3. China’s Laws and Regulations ................................................................. 42

    4.3.1. Relevant Stipulations for Land Acquisition ........................................................ 42

    4.4. Principles and Eligibility for Compensation of the Subproject .................. 47

    4.4.1. Compensation Principles .................................................................................. 47

    4.4.2. Eligibility for Compensation and Beneficiaries .................................................. 47

    4.5. Compensation Rates of the Subproject .................................................... 48

    4.5.1. Compensation Rates for Requisition of Collective Land .................................. 48

    4.5.2. Compensation Rates for Temporary Land Occupation ..................................... 48

    4.5.3. Compensation Rates for Residential Houses ................................................... 48

    4.5.4. Compensation Rates for Non-residential Houses ............................................ 49

    4.5.5. Compensation Rates for Land Attachments and Special Facilities .................. 50

    4.5.6. Post-resettlement Support ................................................................................ 51

    4.5.7. Other Costs and Taxes ..................................................................................... 51

    4.5.8. Vulnerable groups ............................................................................................. 52 4.6. Entitlement Matrix ..................................................................................... 53

    5. RESETTLEMENT MEASURES ............................................................................ 58

    5.1. Objectives of Resettlement ....................................................................... 58

    5.2. Principles for Resettlement and Rehabilitation ......................................... 58

    5.3. Resettlement Rehabilitation Plan ............................................................. 59

    5.3.1. Rehabilitation Plan for Slightly Affected Villages and Groups .......................... 59

    5.3.2. Rehabilitation Plan for Seriously Affected Villages and Groups ....................... 59

    5.4. Rehabilitation Program for Affected Enterprise ........................................ 70

    5.5. Training for APs ........................................................................................ 71

    5.6. Protection of Women’s Rights and Interests ............................................ 71

    5.7. Minority Development ............................................................................... 72

    5.8. Assistance Measures for Vulnerable Groups ........................................... 72

    5.9. Recovery of the Temporarily Occupied Land ........................................... 73

    5.10. Recovery of Infrastructure and Land Attachments ................................... 73

    5.10.1. Reconstruction of Irrigation Pumping Stations .................................................. 73

    5.10.2. Traffic Recovery Measures ............................................................................... 75

    5.11. Subsequent Support Measures ................................................................ 75

    5.12. Social Preparation Plan ............................................................................ 75

    6. INSTITUTIONAL ORGANIZATIONS AND RESPONSIBILITIES .......................... 78

    6.1. Management Agencies for Resettlement Implementation........................ 78

    6.1.1. Institutional Setup ............................................................................................. 78

    6.1.2. Responsibilities of Agencies ............................................................................. 78

    6.2. Staffing and Equipment of Resettlement Management Agencies ............ 81

    6.2.1. Staffing .............................................................................................................. 81

  • iii

    6.2.2. Equipment ......................................................................................................... 81

    6.3. Training Program ...................................................................................... 81

    6.3.1. Training Program for Resettlement Management Staff .................................... 81

    6.3.2. Measures for Improving Resettlement Agencies .............................................. 82

    7. PUBLIC PARTICIPATION AND GRIEVANCE REDRESS .................................... 83

    7.1. Public Participation ................................................................................... 83

    7.1.1. Public Participation at the Project Preparation Stage ....................................... 83

    7.1.2. Public Participation Plan ................................................................................... 84

    7.2. Grievance Redress Procedure ................................................................. 85

    8. RESETTLEMENT BUDGET ................................................................................. 87

    8.1. Resettlement Budget ................................................................................ 87

    8.2. Annual Investment Plan ............................................................................ 92

    8.3. Management and Disbursement of Resettlement Funds ......................... 92

    9. RESETTLEMENT IMPLEMENTATION PLAN ...................................................... 94

    9.1. Principles for Resettlement Implementation ............................................. 94

    9.2. Implementation Schedule for Resettlement ............................................. 94

    10. MONITORING AND EVALUATION ....................................................................... 98

    10.1. Internal monitoring .................................................................................... 98

    10.1.1. Purpose ............................................................................................................. 98

    10.1.2. Organization and Staff ...................................................................................... 98

    10.1.3. Scope of Internal Monitoring ............................................................................. 98

    10.1.4. Internal Monitoring Reporting ........................................................................... 98

    10.2. External monitoring ................................................................................... 99

    10.2.1. Scope and Methods of External Monitoring ...................................................... 99

    10.2.2. External Monitoring Reporting ........................................................................ 100

    10.3. Resettlement Post-evaluation ................................................................. 100

    APPENDIX 1 LOCATION MAP OF THE SUBPROJECT IN GUIYANG MUNICIPALITY

    …………………………………………………………………………………………A1-1

    APPENDIX 2 MAPS ...................................................................................................... A2-1

    APPENDIX 3 ORDER TO CEASE CONSTRUCTION (29AUGUST 2008) .................. A3-1

    APPENDIX 4 ESTIMATED UNIT COST OF HOUSE RECONSTRUCTION ................ A4-1

    APPENDIX 5 MINUTES OF PUBLIC PARTICIPATION MEETINGS ............................ A5-1

    APPENDIX 6 TERMS OF REFERENCE FOR EXTERNAL MONITORING AND

    EVALUATION ................................................................................................................. A6-1

    APPENDIX 7 DETAILED RESETTLEMENT COST TABLES ....................................... A7-1

    APPENDIX 8 GENDER ANALYSIS ............................................................................... A8-1

    APPENDIX 9 UPDATED RESETTLEMENT INFORMATION BOOKLET (RIB) ............ A9-1

  • iv

    List of Tables

    Table A Update of the Former RP…………………………………………………………..………viii

    Table 1-1 Summary of Project Components .............................................................................. 2

    Table 1-2 Summary of Major Resettlement Impacts of the Subproject ..................................... 3

    Table 1-3 Plan for Examination and Approval of Project and Resettlement Plan ..................... 6

    Table 2-1 Scheme Comparison for Dam Site Selection ............................................................ 8

    Table 2-2 Inundation Indicators for Different Water Storage Levels at Lower Dam Site ........... 8

    Table 2-3 Comparison of Proposed Sites for Waterworks ......................................................... 9

    Table 2-4 Summary of Impacts of Land Acquisition and House Demolition in Terms of

    Administrative Division ...................................................................................................... 11

    Table 2-5 Socioeconomic Conditions of Affected Cities, and Counties ................................... 13

    Table 2-6 Economic Situation of Towns Affected by Land Acquisition and House Demolition 14

    Table 2-7 Economic Situation of Villages and Groups Affected by Land Acquisition and House

    Demolition ........................................................................................................................ 14

    Table 3-1 Summary of Permanent Acquisition of Collective Land by the Subproject ............. 18

    Table 3-2 Impact Analysis for Land Acquisition in Terms of Village Groups ............................ 22

    Table 3-3 Impact Analysis for Land Acquisition in Terms of AHs ............................................. 23

    Table 3-4 Summary of Temporary Land Occupation of the Subproject ................................... 26

    Table 3-5 Summary of Demolition of Houses and Attachments by the Subproject ................. 27

    Table 3-6 Summary of Living Conditions of the Households Affected by House Demolition .. 28

    Table 3-7 Summary of Demolition of Non-Residential Houses by the Subproject ................ 299

    Table 3-8 Summary of Population Directly Affected by the Subproject ................................... 29

    Table 3-9 Summary of Income and Expenditure of Households by the Subproject ................ 31

    Table 3-10 Summary of Impacts on Ethnic Minorities by the Subproject ................................ 32

    Table 3-11 Summary of Impacts on Vulnerable Groups .......................................................... 32

    Table 3-12 Summary of Scattered Trees and Tombs Affected by the Subproject ................... 36

    Table 3-13 Summary of Infrastructure and Special Facilities Affected .................................... 37

    Table 4-1 Relevant Policies on Land Acquisition and House Demolition and Their Application

    ......................................................................................................................................... 44

    Table 4-2 Resettlement Principles of the Subproject............................................................... 47

    Table 4-3 Eligibility for Compensation ..................................................................................... 47

    Table 4-4 Compensation Rates for Land Acquisition............................................................... 48

    Table 4-5 Compensation Rates for Temporary Land Occupation ........................................... 48

    Table 4-6 Compensation Rates for Demolition of Residential Houses .................................... 49

    Table 4-7 Compensation Rates for Demolition of Non-residential Houses ............................. 49

    Table 4-8 Compensation Rates for Land Attachments and Special Facilities Affected by the

    Subproject ........................................................................................................................ 50

    Table 4-9 Population Covered by Post-resettlement Support ................................................. 51

    Table 4-10 Compensation Rates for Other Costs .................................................................... 51

    Table 4-11 Entitlement Matrix .................................................................................................. 54

    Table 5-1 Production Rehabilitation Plan for Slightly Affected Villages ................................... 59

    Table 5-2 Summary of Income Restoration Measures of Mitangjing Group ............................ 61

    Table 5-3 Summary of Expected Income Restoration for Mitangjing Group ........................... 61

  • v

    Table 5-4 Balance Sheet for Income Restoration Measures of Mitangjing Group .................. 61

    Table 5-5 Summary of Key Technical Indicators of the Resettlement site of Mitangjing Group

    ......................................................................................................................................... 62

    Table 5-6 Balance Sheet for House Reconstruction Funds of Mitangjing Group .................... 63

    Table 5-7 Infrastructure Construction and Investment of Mitangjing Group ............................ 64

    Table 5-8 Summary of Income Restoration Measures of Xiaoyan Group ............................... 66

    Table 5-9 Summary of Expected Income Restoration for Xiaoyan Group............................... 66

    Table 5-10 Balance Sheet for Income Restoration Measures of Xiaoyan Group .................... 67

    Table 5-11 Summary of Key Technical Indicators of the Resettlement site of Xiaoyan Group 67

    Table 5-12 Balance Sheet for House Reconstruction Funds of Xiaoyan Group ..................... 68

    Table 5-13 Infrastructure Construction and Investment of Xiaoyan Group ............................. 69

    Table 5-14 Schedule of Training for APs ................................................................................. 71

    Table 5-15 Restoration Measures for Irrigation Pumping Stations .......................................... 74

    Table 6-1 Staffing of Resettlement Agencies ........................................................................... 81

    Table 6-2 Schedule for Resettlement Implementation Training ............................................... 82

    Table 7-1 Key Public Participation Activities during Project Preparation ................................. 83

    Table 7-2 Public Participation Plan .......................................................................................... 84

    Table 8-1 Resettlement Cost Estimate (by Component) ......................................................... 88

    Table 8-2 Resettlement Cost Estimate (by District/County) .................................................... 89

    Table 8-3 Resettlement Investment Plan ................................................................................. 92

    Table 9-1 Resettlement Implementation Schedule .................................................................. 95

    Table 10-1 Progress Report on Land Acquisition and Resettlement ....................................... 99

    Table 10-2 Execution Progress of Funds Utilization ................................................................ 99

    Table 10-3 Reporting Schedule for Resettlement Monitoring and Evaluation ....................... 100

    List of Figures

    Figure 3-1 Land to Be Acquired for the Subproject ................................................................. 21

    Figure 3-2 Residential Houses to Be Demolished for the Subproject ..................................... 28

    Figure 3-3 Schematic Map of Division of Water Sources Protection Zones ........................... 38

    Figure 5-1 Schematic Map of the Resettlement Site of Mitangjing Group .............................. 63

    Figure 5-2 Schematic Map of the Resettlement Site of Xiaoyan Group .................................. 68

    Figure 5-3 Yudongxia Downstream ......................................................................................... 71

    Figure 6-1 Resettlement Management Organization .............................................................. 78

    Figure 7-1 Public Participation and Consultation .................................................................... 84

    Figure 7-2 Appeal Procedure for APs ...................................................................................... 86

  • vi

    ABBREVIATIONS

    AAOV - Average Annual Output Value ADB - Asian Development Bank AH - Affected Household AP - Affected Person DMS - Detailed Measurement Survey EMDPAP - Ethnic Minority Development Plan GMG - Guiyang Municipal Government

    GSDRI - Guizhou Water Resources and Hydropower Survey, Design and Research Institute

    GZWRID - Guiyang Zhushui Water Resources Industrial Development Co., Ltd.

    M&E - Monitoring and evaluation MLS - Minimum Living Security PMO - Project Management Office PRC - People’s Republic of China RP - Resettlement Plan

    Units

    Currency unit = Yuan (CNY) 1.00 yuan = $0.15 1 hectare = 15 mu

  • vii

    Notes to this Update At the technical assistance stage of the Subproject, the Guiyang PMO prepared

    the Resettlement Plan for the Yudongxia Reservoir and No.2 Dongjiao Waterworks

    Subproject (the ―former RP‖) according to the Feasibility Study Report for the

    Subproject and ADB’s social safeguard policies.

    On March 8, 2010, the Guizhou Provincial Development and Reform

    Commission, and the Water Resources Department of Guizhou Province issued the

    Reply on the Preliminary Design of the Yudongxia Reservoir and No.2 Dongjiao

    Waterworks Subproject (GPDRC [2010] No.319). From July 2010 to October 2011,

    with the support of the affected county and township governments, villages and APs,

    and the design agency, Guiyang Zhushui Water Resources Industrial Development

    Co., Ltd. (GZWRID) completed the review of resettlement impacts, detailed

    measurement survey and the assessment on the compensation policies and rates,

    and resettlement programs of the Subproject. The former RP has been updated

    according to the Project Agreement with ADB dated June 17, 2010.

    This update involves resettlement impacts, compensation and resettlement

    policies, socioeconomic conditions, and resettlement budget and resettlement

    implementation plan, covering all chapters of the former RP. See Table A.

  • viii

    Table A Update of the Former RP

    No. Updated item Former RP Updated RP Remarks

    1 Project design

    The components include reservoir (incl.

    the dam), No.2 Dongjiao Waterworks and

    its water distribution network, with normal

    pool level of 1,075m, total storage

    capacity of 18.2 million m³, annual water

    supply capacity of 31.8 million m³ and

    maximum dam height of 71.5m.

    The components include reservoir (incl. the

    dam), No.2 Dongjiao Waterworks and its water

    distribution network, with normal pool level of

    1,075m, total storage capacity of 18.6 million

    m³, annual water supply capacity of 30 million

    m³ and maximum dam height of 72m.

    No major change, just more precise

    2 Range and impacts

    of land acquisition

    11 villages and 16 village groups of 5

    townships in Wudang District of Guiyang

    Municpality and Longli County of Qiannan

    Prefecture

    10 villages and 19 village groups of 5 townships

    (Pianpo Xiang, Dongfeng Town, Xintian Office,

    Yongle Xiang and Xingshi Town) in 2 districts

    (Wudang and Nanming Districts) of Guiyang

    Municpality and Longli County of Qiannan

    Prefecture

    Guiyang Municipality was re-zoned

    administratively in 2008.

    3 Resettlement

    impacts

    (1) 1,311 persons will be affected directly

    by land acquisition and house demolition;

    one non-residential house (Yudongxia

    Company) with 26 persons will be

    affected; 173 persons will be affected

    temporarily; (2) 3,128.71 mu of land will

    be acquired permanently, including 944.49

    mu of cultivated land; 119.1 mu of land will

    be occupied temporarily, including 35.52

    mu of cultivated land; (3) residential

    houses of 8626.56 m2 will be demolished;

    (4) non-residential houses of 4,132.4 m2

    (1) 1,620 persons will be affected directly by

    land acquisition and house demolition; one

    enterprise (Yudongxia Company) with 26

    persons will be affected; 207 persons will be

    affected temporarily; (2) 2,344.94 mu of land

    will be acquired permanently, including 1,366

    mu of cultivated land; 116.34 mu of land will be

    occupied temporarily; (3) residential houses of

    26,889.92 m2 will be demolished; (4) non-

    residential houses of 3,633.11 m2

    Compared to the former RP, (1) the

    population affected directly by land

    acquisition and house demolition has

    increased by 309; (2) permanently

    acquired land area has been reduced

    by 783.77 mu; (3) the demolition area

    of residential houses has increased

    by 18,263.36 m2, mainly because the

    housing conditions of the affected

    villages improved from 2006 to 20081;

    (4) the demolition area of non-

    residential houses has been reduced

    by 499.29 m2

    4 Compensation rates

    for land acquisition

    Compensation rates vary with land type,

    and range from 3,903 yuan/mu (unused

    Wudang District: Xintian Office— cultivated land

    99,000 yuan/mu, non-cultivated land 39600

    According to the new policy of

    Guiyang Municipality in 2009, the

    1 The cut-off date is 29 August 2008.

  • ix

    No. Updated item Former RP Updated RP Remarks

    land) to 30,719 yuan/mu (irrigated land) yuan/mu; Dongfeng Town—cultivated land

    75,000 yuan/mu, non-cultivated land 30,000

    yuan/mu, Pianpo Xiang— cultivated land

    53,200 yuan/mu, non-cultivated land 21,280

    yuan/mu; Nanming District: Yongle Xiang—

    cultivated land 75,000 yuan/mu, non-cultivated

    land 30,000 yuan/mu; Longli County—cultivated

    land 34,500 yuan/mu, woodland 19,260

    yuan/mu

    compensation rates for land

    acquisition have improved greatly.

    5 Compensation rates

    for house demolition

    The compensation rates for residential

    houses are 388 yuan/m2 for masonry

    concrete structure, 304 yuan/m2 for

    masonry timber structure, 238 yuan/m2 for

    timber structure and 74 yuan/m2 for

    auxiliary houses; the compensation rates

    for non-residential houses are 426

    yuan/m2 for masonry concrete structure,

    332 yuan/m2 for masonry timber structure,

    253 yuan/m2 for timber structure and 74

    yuan/m2 for auxiliary houses.

    The compensation rates for residential houses

    are 706 yuan/m2 for masonry concrete

    structure, 577 yuan/m2 for masonry timber

    structure and 410 yuan/m2 for timber structure;

    the compensation rates for non-residential

    houses are 479 yuan/m2 for masonry concrete

    structure, 406 yuan/m2 masonry timber

    structure and 334 yuan/m2 for timber structure

    Similar to the compensation rates for

    land acquisition, the compensation

    rates for house demolition have also

    improved.

    6

    Resettlement

    program for house

    demolition

    Central resettlement for Mitangjing Group

    of Ganjing Village and Xiaoyan Group of

    Dayan Village

    Central resettlement for Mitangjing Group of

    Ganjing Village, and Xiaoyan Shangjie and

    Xiaoyan Xiajie Groups of Dayan Village

    Little variation from the former RP

    7 Financial budget

    Based on prices in December 2005, the

    total resettlement costs of Subproject are

    88,117,500 yuan.

    Based on prices in Q3 2011, the total

    resettlement costs of Subproject are

    356,370,900 yuan.

    The resettlement costs have

    increased by 268.25 million yuan,

    mainly because the compensation

    rates have improved greatly.

    8 Implementation

    schedule

    House demolition and resettlement will

    begin in February 2007 and end in

    January 2009.

    House demolition and resettlement will begin in

    December 2011 and end in May 2013.

  • x

  • xi

    Executive Summary The Guiyang Yudongxia Reservoir and No.2 Dongjiao Waterworks Subproject is

    one of the core subprojects of the Guiyang Integrated Water Resources Management

    Project financed by ADB. It is a water resources project that focuses on water supply.

    The major task of the Subproject is to satisfy the domestic and industrial water

    demands of the eastern part and the Xintian area of Guiyang Municipality. The major

    components include reservoir multi-purpose engineering and the supporting pipeline

    network of waterworks, covering reservoir construction (incl. the dam), No.2 Dongjiao

    Waterworks and its water distribution network. The Guiyang Municipal Water

    Resources Bureau (PMO) is the implementing agency for the Subproject. This

    Subproject will be started in December 2011 and completed by May 2013 for

    commissioning.

    The major impacts caused by the Subproject include permanent land acquisition,

    temporary land occupation and house demolition. According to the survey of project

    impacts, land acquisition and house demolition of the Subproject will affect 5

    townships (Pianpo Xiang, Dongfeng Town, Xintian Office, Yongle Xiang and Xingshi

    Town), 10 villages and 19 village groups in 3 districts / counties (Wudang District,

    Nanming District and Longli County) of Guiyang Municipality and Qiannan Prefecture.

    The total population directly affected by land acquisition and house demolition of the

    Subproject is 1,646, including (i) 385 households with 1,328 persons only affected by

    land acquisition; (ii) 71 households with 292 persons affected both by land acquisition

    and house demolition; and (iii) one non-residential house (Yudongxia Company) with

    26 persons. The total population temporarily affected by the Subproject is 207. In the

    Subproject, the permanent land acquisition will be 2,344.94 mu, including 1,366 mu

    of cultivated land; the temporary land occupation will be 116.34 mu; the total area of

    house demolition will be 26,889.92 m² for residential houses and 3,633.11 m² of non-

    residential houses. In addition, the Subproject will also affect 8.25 km of tractor road,

    3 power substations, 5 pumping stations, 26.022 km of canals, 14 pedestrian bridges,

    20 spill-weir dams and a 10 kVA high-tension line.

    To avoid or minimize negative impacts of land acquisition, adequate consultation

    was conducted on the potential site of the Subproject, the village groups affected by

    reservoir inundation and resettlement at the stage of feasibility study and preliminary

    design. An optimum option was selected through comparison.

    This Resettlement Plan (RP) is based on the Land Administration Law of the

    PRC (2004), Decision of the State Council on Deepening the Reform and Rigidly

    Enforcing Land Administration (SC [2004] No.28), the applicable policies of Guizhou

    Province and Guiyang Municipality, and ADB’s social safeguard policies. According to

    the above policies, and in consultation with local governments and affected persons,

    the resettlement principles of the Subproject are: (1) Involuntary resettlement should

    be avoided where feasible; (2) The affected persons are granted compensation and

    rights that can at least maintain or even improve their livelihoods in the absence of

    the project; (3) The affected persons are given compensation and assistance in

    resettlement whether legal title is available or not before the cut-off date; (4) The

  • xii

    economic compensation shall ensure that everyone will at least maintain their

    standard of living after resettlement; (5) If the land available to everyone is insufficient

    to maintain his/her livelihood, replacement in cash or in kind and other income-

    generating activities are provided for the lost land; (6) The affected persons fully

    understand their entitlements, the method and standard of compensation, the

    livelihood and income restoration plan, and the project schedule, and participate in

    the implementation of the Resettlement Plan; (7) No land should be acquired before

    the affected persons are satisfied with the compensation and resettlement (plan); (8)

    The executing agency and an independent agency / third party should monitor the

    compensation, relocation and resettlement operations; (9) The vulnerable groups

    (including women) are provided special assistance or treatment so that they lead a

    better life, and all affected persons should have an opportunity to benefit from the

    project; and (10) The resettlement costs are sufficient to cover all affected aspects.

    All APs have been informed of the major information of the Resettlement Plan in

    various means, such as meetings, interviewing, village group discussions, public

    consultation, and community consultation, etc. Through these activities, all APs can

    participate in project preparation, which likewise give full consideration of their

    demands in the resettlement plan. The Guiyang PMO will be responsible for the

    monitoring, follow-up consultation and grievance redress for the implementation of

    this RP. The means for accepting complaints and grievances have been clearly

    described in this RP.

    As for permanent land acquisition, the compensation rates shall follow the Notice

    of GMG on the Promulgation and Implementation of Uniform AAOVs and Location-

    based Compensation Rates for Land Acquisition (GMG [2009] No.99): Wudang

    District: Xintian Office—cultivated land 99,000 yuan/mu, non-cultivated land 39600

    yuan/mu; Dongfeng Town—cultivated land 75,000 yuan/mu, non-cultivated land

    30,000 yuan/mu, Pianpo Xiang—cultivated land 53,200 yuan/mu, non-cultivated land

    21,280 yuan/mu; Nanming District: Yongle Xiang—cultivated land 75,000 yuan/mu,

    non-cultivated land 30,000 yuan/mu; Longli County—cultivated land 34,500 yuan/mu,

    woodland 19,260 yuan/mu.

    The compensation rate for temporary land occupation is based on Document

    GMG [2009] No.86 of GMG, 30,000 yuan/mu for Nanming District and for 21,600

    yuan/mu for Wudang District.

    The compensation rates for demolition of residential houses are 706 yuan/m2 for

    masonry concrete structure, 577 yuan/m2 for masonry timber structure and 410

    yuan/m2 for timber structure; the compensation rates for non-residential houses are

    479 yuan/m2 for masonry concrete structure, 406 yuan/m2 for masonry timber

    structure and 334 yuan/m2 for timber structure. In addition, the households affected

    by house demolition will receive compensation fees for infrastructure and other

    subsidies.

    A post-resettlement support fund will be established to support the APs at 600

    yuan/year per capita for 20 years.

    The income restoration measures for the displaced people will include cash

  • xiii

    compensation, industrial structural adjustment, priority in getting jobs from the project

    construction, etc. After discussion with the affected towns, villages and APs, 80% of

    the land compensation fees and all resettlement subsidies shall be directly paid to

    the AHs who will reinvest them on the structural plantation adjustment on the

    remaining land or on other non-agricultural trades. In addition, during the construction

    period, the Subproject will generate a demand of 350 persons/day of unskilled jobs

    that shall be given to the affected laborers with priority (minimum 30% women). The

    Guiyang PMO will arrange a special fund of 165,000 yuan to provide technical

    training for the affected laborers (incl. 50% of women at minimum). Such technical

    trainings will be conducted by the PMO jointly with agricultural and social security

    departments. Further, the Guiyang PMO jointly with civil administration department

    will also establish 93,000 yuan support funds for vulnerable groups to assist the

    affected vulnerable groups. The ethnic minorities shall enjoy the same entitlements

    as the Han People in the aspects of land acquisition, house demolition and

    resettlement.

    House demolition of this Subproject will mainly affect Mitangjing Group of

    Ganjing Village and Xiaoyan Group of Dayan Village. The former plans to re-

    construct their houses all together in the open places of the previous village nearby

    the proposed reservoir, while the latter plans to re-build their houses all together in

    the open places of the existing village near Tousong Road. In this regard, in

    combination with the construction planning for new rural area of all towns,

    construction of the basic facilities such as water supply, electricity supply and road

    shall be financed by the government, while the rural households will build their

    residences on the planned homesteads according to their individual requirements.

    Based on the implementation schedule of the Subproject, land acquisition,

    compensation and resettlement shall be started in early 2012 and completed by May

    2013. In order for the effective implementation of the RP, in addition to the internal

    monitoring, the external monitoring on semi-annual basis shall be conducted by an

    independent agency. The total costs for resettlement of the Subproject will be

    356,370,900 yuan (approximately accounting for 57% of the total project costs),

    covering land acquisition (occupation) compensation fees, house demolition

    compensation, reconstruction of infrastructure, related taxes and charges, and

    contingencies as well.

  • 1

    1. OVERVIEW OF THE SUBPROJECT

    1.1. Background

    The Yudongxia Reservoir and No.2 Dongjiao Waterworks Subproject is one of

    the core subprojects of Guiyang Integrated Water Resources Management Project

    financed by ADB. Yudongxia Damsite is located in Toubao Village of Dongfeng Town

    of Wudang District of Guiyang Municipality, being on Yudonghe River – a secondary

    tributary of Nanminghe River which is the source River of Qingshuihe River of

    Wujiang River System of Changjiang River Catchments. It is 3km from Dongfeng

    Town of Wudang District of Guiyang Municipality, 8km from Xintianzhai Town (where

    government of Wudang District is situated), 18km from the city proper of Guiyang

    Municipality. At same time of retaining the functions of irrigation and supplying

    drinking water as a small-sized reservoir, the range of water supply of the reservoir

    will cover eastern part and Xintian area of the urban areas. The proposed No.2

    Dongjiao Waterworks located on the flank hillside of the right mountain chain of the

    Yudongxia Reservoir damsite shall be constructed in Toubao Village being at the

    elevation of 1,038-1,026m and 600m away from the village road of Toubao Village.

    Guiyang Municipality is located in the watershed headpool area between the

    Wujiang River System of Changjiang River Catchments and the Hongshuihe River

    System of the Pearl River Catchments where characterized by distinct karst

    development. The ground water -retaining capacity is poor and the ecological

    environment is fragile. Most of the rivers within this area belong to the headstreams

    of the end tributaries which have small catchments areas, short distances and limited

    quantity of water resources. In the urban area, there are only one large-sized (II)

    reservoir (Baihuahu) and three medium-sized reservoirs (A’ha, Huaxi and

    Songboshan). What’s more is that the spatio-temporal distribution of water resources

    of Guiyang Municipality is seriously unbalanced, resulting in a shortage in utilizable

    water resources. With the rapid population growth and economic development of

    Guiyang Municipality, the water demand will increase gradually and thus enlarging

    the disparities between supply and demand. Water shortage will become the

    bottleneck that hinders the sustainable development of this area.

    In May 1998, the Guizhou Water Resources and Hydropower Survey, Design

    and Research Institute (hereinafter referred to as the ―GSDRI‖) was entrusted by

    GMG to undertake the planning for flood control, water supply and river course water

    environment integrated treatment for Guiyang Municipality. As a result, the Report on

    Planning of Flood Control, Water Supply and River course Water Environment

    Integrated Treatment for Urban Area of Guiyang Municipality was completed and

    approved by GMG through Document ZFT [1999] No.1. In this report, the planned

    water supply scheme for the urban area of Guiyang Municipality was ―existing water

    sources + west suburb + nearby planned water sources + Sancha River water

    diversion‖, proposing the Subproject as one of the key water sources supplying water

    to the urban area. It was also proposed to construct No.2 Dongjiao Waterworks of

  • 2

    100,000t/d to satisfy the meet and industrial water demands of the eastern part and

    the Xintian area.

    1.2. Brief Introduction

    1.2.1. Project Components The Subproject is a project of water resources focusing on water supply bearing

    the task of satisfying the domestic and industrial water demands in the eastern part

    and Xintian area of Guiyang Municipality. The components of the Subproject include

    dam and reservoir works (incl. pivot), No.2 Dongjiao Waterworks, pipeline network,

    access roads, etc. as shown in Table 1-1. The schematic map of the components of

    the Subproject is shown in Appendix 1.

    Table 1-1 Summary of Project Components

    Component Brief Description Major Impacts

    Reservoi

    r

    Reservoir

    area

    Located in Toubao Village, Dongfeng Town,

    Wudang District, with normal pool level of

    1,075m, total storage capacity of 18.6 million

    m³, annual water supply capacity of 30 million

    m³ and maximum dam height of 72m (incl.

    foundation)

    Wudang District of

    Guiyang Municipality

    and Longli County of

    Qiannan Prefecture, with

    2,127.88 mu of

    permanent land

    acquisition, including

    1,201.16 mu of

    cultivated land.

    Damsite

    area

    Located in Toubao Village of Dongfeng Town.

    Major structures include: concrete double-arch

    dam, crest spillway, dam-body bottom

    emptying outlet, dam-body water intake point

    and water-diversion tunnel

    Wudang District of

    Guiyang Municipality,

    with 45.85 mu of

    permanent land

    acquisition and 116.34

    mu of temporary land

    occupation.

    No.2

    Dongjiao

    Waterwo

    rks

    Plant

    area

    With 100,000t/d of water-supply capacity,

    servicing Xintianzhai, Dongfeng Town and

    Luowan area. The waterworks is located in

    Toubao village of Dongfeng town, 500m south

    of the entrance of the Yudongxia Scenic spot.

    The elevation is 1,031-1,035m.

    Wudang District of

    Guiyang Municipality,

    with 70.30 mu of

    permanent collective

    land acquisition, all

    being cultivated land

    Pipeline

    network

    The water distribution pipeline network adopts

    head-tank control for water supply. After being

    treated in Toubao waterworks, the incoming

    water from Yudongxia reservoir will be

    pumped respectively into the head tanks of

    Gouchang of Xintianzhai, Dongfeng of

    Dongfeng Town and Luowan of Luowan area,

    from which, the water will be distributed further

    to the connecting point of the urban pipeline

    networks or the places of concentrated water

    users. In terms of distance: waterworks to

    clean water tank of Gouchang: 8.21 km;

    waterworks to clean water tank of Dongfeng:

    6.59 km; waterworks to clean water tank of

    Wudang District of

    Guiyang Municipality,

    with 10.18 mu of

    permanent collective

    land acquisition (by 3

    head-tanks), including

    3.813 mu of cultivated

    land

  • 3

    Component Brief Description Major Impacts Luowan: 3.28 km, totally 18.08 km.

    Access roads

    1) Access road connecting the waterworks

    and the highway; 2) road connecting the

    damsite and the water works

    Wudang District of

    Guiyang Municipality,

    with 90.72 mu of

    permanent collective

    land acquisition

    (cultivated land)

    1.2.2. Range of Land Acquisition and House Demolition and Brief Introduction of Impacts

    The range of impacts caused by the land acquisition and house demolition of the

    Subproject will cover the land-use areas by the reservoir (incl. the reservoir area and

    the damsite area), No.2 Dongjiao Waterworks, pipeline network, access roads, etc.

    All the places that are seriously affected by the land acquisition and project

    construction to the extent that the production and livelihood of the local people are

    affected shall belong to the impacted areas of the Subproject.

    At the present stage, the impacts of land acquisition and house demolition of the

    Subproject are determined on the basis of the recommended scheme in the

    feasibility study report and the approved Preliminary Design. The detailed

    measurement survey was completed in Oct 2011.

    Land acquisition and house demolition of the Subproject will affect 5 townships,

    10 villages and 19 village groups in 3 districts / counties (Wudang District, Nanming

    District and Longli County) of Guiyang Municipality and Qiannan Prefecture. The total

    population directly affected by land acquisition and house demolition of the

    Subproject is 1,646. In the Subproject, the permanent land acquisition will be

    2,344.94 mu, including 1,366 mu of cultivated land; the temporary land occupation

    will be 116.34 mu; the total area of house demolition will be 26,889.92 m² for

    residential houses and 3,633.11 m² of non-residential houses. The major impacts are

    summarized in Table 1-2.

    Table 1-2 Summary of Major Resettlement Impacts of the Subproject

    Municipality / prefecture Guiyang Municipality Qiannan

    Prefecture Total

    District / county Wudang

    District

    Nanming

    District

    Longli

    County

    Township 3 1 1 5

    Villages 7 2 1 10

    Village groups 12 5 2 19

    Acquisition of

    collective land

    (mu)

    Total 460.11 1471.18 413.65 2344.94

    Where: cultivated land 230.6 857.36 278.04 1366

    Temporary land

    occupation (mu)

    Total 78.68 37.66 0 116.34

    Where: cultivated land 0 31.09 0 31.09

    House

    demolition (m²)

    Residential houses 2216.63 8019.67 16653.62 26889.92

    Non-residential houses 94.45 15 0 109.45

    Directly affected

    population

    Households affected by

    land acquisition 212 140 33 385

    Population affected by 790 429 109 1328

  • 4

    Municipality / prefecture Guiyang Municipality Qiannan

    Prefecture Total

    District / county Wudang

    District

    Nanming

    District

    Longli

    County

    land acquisition

    Households affected by

    both land acquisition

    and house demolition

    8 31 32 71

    Population affected by

    both land acquisition

    and house demolition

    27 129 136 292

    Enterprises 1 0 0 1

    Population 26 0 0 26

    Subtotal of directly impacted population 843 558 245 1646

    Temporarily

    affected

    population

    Households 0 60 0 60

    Population 0 207 0 207

    1.2.3. Socioeconomic Benefits of the Subproject The design normal pool level of Yudongxia Reservoir is 1,075m, with total

    storage capacity of 18.60 million m³ and annual water supply capacity of 30 million

    m3. The Subproject will bring about the following socioeconomic benefits: (i) Project

    implementation will greatly improve the water supply environment and ensure the

    water supply security of Wudang District of Guiyang Municipality. (ii) According to the

    section plan of Xintian area and the master plan of Dongfeng Town, the benefited

    population will be 182,000 people. (iii) The subproject will supply 62,600 m³/d of

    water for industrial demand, 2,730 m³/d for public building requirement, 11,720 m³/d

    for fire-prevention purpose and 5,860 m³/d for road-cleaning and green space

    watering.

    1.2.4. Resettlement Cost Estimate According to the Feasibility Study Report for the Yudongxia Reservoir

    Subproject of Guiyang Municipality prepared by the GSDRI, the total investment in

    the Subproject is 620.682 million yuan, including 361,852,100 yuan for land

    acquisition and resettlement that accounts for 57% of the total investment.

    1.2.5. Project and Resettlement Implementation Plan In order to manage water resources in an effective, systematic and unified

    manner, the GSDRI was entrusted by GMG to plan the integrated utilization and

    development of water resources for Guiyang Municipality, and completed the Report

    on the Planning of Integrated Utilization and Development of Water Resources of

    Guiyang Municipality in early 2006, which proposed the Subproject as a water supply

    project for the urban area of Guiyang Municipality to be developed with priority.

    In June 2007, the State Development and Reform Commission approved the

    construction of the Subproject with the Reply on the Proposal for the Guiyang

    Integrated Water Resources Development, and Water and Soil Conservation Project

    (DRCRC [2007] No.1408).

  • 5

    Afterwards, the GSDRI completed the Feasibility Study Report for the Yudongxia

    Reservoir and No.2 Dongjiao Waterworks Subproject (draft for review). On June 2,

    the Guizhou Provincial Development and Reform Commission issued the Reply on

    the Feasibility Study Report for the Yudongxia Reservoir and No.2 Dongjiao

    Waterworks Subproject (GPDRC RC [2009] No.1057).

    On March 8, 2010, the Guizhou Provincial Development and Reform

    Commission, and the Water Resources Department of Guizhou Province issued the

    Reply on the Preliminary Design of the Yudongxia Reservoir and No.2 Dongjiao

    Waterworks Subproject (GPDRC [2010] No.319).

    Matters related to land acquisition and resettlement have also been subject to

    review and approval.

    In March 2008, the GSDRI was appointed by GZWRID to prepare a report on

    land acquisition and resettlement for the Subproject.

    On August 26, 2008, the Guizhou Provincial Government approved the order to

    cease construction for the construction and inundation areas of the Subproject with

    Document GPG Office Letter [2008] No.55, and this date was the cut-off date of the

    Subproject.

    After the cut-off date was announced, GZWRID and the GSDRI conducted a

    detailed measurement survey (DMS) of resettlement impacts, policies and programs

    together with the affected county/district and township governments, and completed

    the Report on Land Acquisition and Resettlement Planning for the Yudongxia

    Reservoir and No.2 Dongjiao Waterworks Subproject in October 2009, which was

    approved by the Resettlement Bureau for Water Resources and Hydropower Projects

    of Guizhou Province on December 18, 2009. On March 4, 2009, the Land and

    Resources Department of Guizhou Province issued the Reply on the Pre-

    examination of the Land Used for the Yudongxia Reservoir and No.2 Dongjiao

    Waterworks Subproject (GPLRD LPE [2009] No.19), approving the land pre-

    examination in principle.

    After the Preliminary Design of the Subproject was approved in March 2010, the

    check of DMS and the report on resettlement implementation planning were

    completed with the support of the affected county and township governments,

    villages and APs from July 2010 to Oct 2011.

    On September 28, 2011, the Land and Resources Department of Guizhou

    Province submitted to the Examination Report on the Land Used for the Yudongxia

    Reservoir and No.2 Dongjiao Waterworks Subproject (GPLRD LUP [2011] No.393) to

    the Ministry of Land and Resources. See Table 1-3.

  • 6

    Table 1-3 Plan for Examination and Approval of Project and Resettlement Plan

    Item

    Domestic

    Prepared by Time of

    submission Reviewed by

    Time of approval /

    implementation

    Land pre-

    examination GZWRID Jan. 2009

    Land and Resources Dept.

    of Guizhou Province Mar. 2009

    Land application

    GZWRID / Land and

    Resources Dept. of

    Guizhou Province

    Sep. 2011 Ministry of Land and

    Resources Aug. 2012

    Feasibility study

    report GSDRI / GZWRID Mar. 2009

    Guizhou Provincial

    Government Jun. 2009

    Preliminary design GSDRI / GZWRID Dec. 2009

    Guizhou Provincial

    Development and Reform

    Commission

    Mar. 2010

    RP for domestic

    approval GSDRI / GZWRID Mar. 2009

    Resettlement Bureau for

    Water Resources and

    Hydropower Projects of

    Guizhou Province

    Dec. 2009

    Updated RP for

    ADB approval GSDRI / GZWRID Feb. 2012 ADB Mar. 2012

    Based on the present progress of the Subproject, the updated RP was submitted

    to ADB in February 2012. After ADB review and concurrence, resettlement will be

    implemented from March 2012 to May 2013.

  • 7

    2. RANGE OF PROJECT AREA AND SOCIOECONOMIC

    PROFILE

    2.1. Measures to Avoid or Minimize Land Acquisition and House Demolition

    2.1.1. Principles for Project Design and Site Selection Resettlement impacts have been considered at the design stage to minimize

    such impacts. The main principles are as follows:

    Avoiding any settlement that may restrict reservoir size

    Avoiding or minimizing occupation of existing and planned residential areas

    (urban and rural)

    Avoiding or minimizing occupation of high-quality farmland and pasture land

    Gaining access to the proposed construction sites through existing state

    and local roads

    Avoiding or minimizing occupation of environmentally sensitive areas

    Selecting a resettlement community in line with the local development plan

    2.1.2. Scheme Comparison of the Subproject In order to minimize the land acquisition and resettlement, the GSDRI has

    conducted strict scheme comparison and optimization2, of which, land acquisition is

    one of the most important indicators. Under the premises of ensuring the water-

    supply scope and the functions, the GSDRI has undertaken strict scheme verification

    and comparison for the dam site, reservoir inundation level, waterworks site and

    water distribution pipeline network.

    (1) Determination of the dam site and inundation level

    The inundation indicators for all dam -site schemes of the reservoir are based on

    the 1:10,000 topographic map of project feasibility study stage. In the stage of

    feasibility study, the dam-site selection was made after comparing the No.1 and No.2

    upper dam sties and the lower dam site. The lower dam site was recommended after

    comparison. In terms of resettlement impacts and water-supply indicators, there are

    not any big differences between the two options of lower and upper sites in

    resettlement impacts. However, the annual water-supply volume at 95% reliability is

    31.80 million m3 in the lower dam site, which is higher than those of the two upper

    dam sites, indicating better water-supply indicator. The comparison of dam site

    schemes is shown in Table 2-1.

    2 Under China’s project preparation procedures, scheme comparison is conducted at the feasibility study

    stage, and will be further demonstrated at the preliminary design stage. Therefore, the section in the

    former RP is used here.

  • 8

    Table 2-1 Scheme Comparison for Dam Site Selection

    Item Unit No.1 Upper Dam Site

    No.2 Upper Dam Site

    Lower dam site

    Normal pool level m 1075 1075 1075

    Dead water level m 1037 1035 1035

    Key inundation indicators

    Arable land mu 720 720

    House demolition

    M2 22660 22660

    APs / 785 785

    Scenic spot / 1 2

    Resettlement investment

    0,000 yuan

    6195.13 6551.19

    Corresponding normal storage capacity

    0,000 m3 1450 1610 1680

    Dead storage capacity 0,000 m3 70 75 87

    Regulated storage capacity 0,000 m3 1380 1535 1593

    Regulating structures Annual

    regulation Annual

    regulation Annual

    regulation

    Annual water supply at 95% 0,000 m3 2900 3110 3180

    In order to determine the optimal inundation line, as for the recommended dam

    site scheme (lower dam site), four different water levels respectively 1,070m, 1,075m,

    1,080m and 1,085m were used for comparison as shown in Table 2-2. From the

    analysis of all inundation indicators, when the water storage level is higher than

    1,075m, the values of inundation indicators increase greatly. In contrast, the water

    supply indicators for 1,070m storage level are inferior to that of 1,075m. Therefore,

    the 1,075m storage level is recommended as the normal storage level.

    Table 2-2 Inundation Indicators for Different Water Storage Levels at Lower Dam Site

    Item Unit Lower dam site

    Normal pool level m 1070 1075 1080 1085

    Key in

    un

    datio

    n

    ind

    icato

    rs

    Arable land mu 596 720 1045 1311

    Irrigated mu 550 660 946 1170

    Non-irrigated mu 46 60 99 141

    Woodland mu 120 180 220 390

    Shrub forest mu 617 788 1235 1583

    APs / 648 785 1136 1425

    Existing scenic spot

    / 2 2 2 2

    In sum, considering the inundation indicators and water supply indicators of the

    Subproject, in this stage, the scheme of lower dam site with 1,075m of normal pool

    level was recommended.

    (2) Selection of the site for waterworks

    The dead water level of Yudongxia Reservoir is 1,035m. Taking into

    consideration of the head loss, the level of incoming water of the waterworks can be

    computed. After fixing the points on the contour maps of 1:10,000, the professional

    staffs of all subjects were organized to visit and investigate the sites. In the initial

    stage, several sites were proposed (5 sites at the very beginning). After consultation

    with the Wudang District Water Resources Bureau, Construction Bureau, Planning

    Bureau, Land and Resources Bureau, as well as the government of Dongfeng Town

  • 9

    and Gaoxin Office of Xintian area, two sites, namely the Toubao and Dongfeng sites,

    were finally proposed for comparison. See Table 2-3.

    Table 2-3 Comparison of Proposed Sites for Waterworks

    Toubao Site Dongfeng Site

    Pros

    (1) Near to water sources of Yudongxia

    reservoir, and thus water delivery pipelines are

    easy to arrange.

    (2) The proposed site is situated on wasteland,

    waste hill and some non-capital farmland, and

    thus indicating low land acquisition costs.

    (3) No buildings are found within the proposed

    site, and thus without house demolition.

    (4) No mines or enterprises are found nearby

    the proposed site, and thus the construction is

    simple and will not be affected by the

    neighboring environment.

    (5) The geological conditions of the proposed

    site are suitable for construction of

    waterworks.

    (1) Near to the highway, indicating

    convenient transportation.

    (2) Short distance of water distribution

    pipeline system, and thus requiring less

    investment.

    (3) Wastewater produced by the

    waterworks can be directly discharged into

    river after treatment.

    (4) The landform of the proposed site

    shapes rectangle with open views, and

    thus the construction arrangement is easy.

    (5) The geological conditions of the

    proposed site are suitable for construction

    of waterworks.

    Cons

    (1) Far from the highway, requiring additional

    construction of about 1000m of access road.

    (2) Big volume of earthworks, especially high-

    slope treatment engineering.

    (3) The water distribution pipeline network is

    long, requiring more engineering investments.

    (4) The wastewater produced by the

    waterworks needs to be diverted to the river

    700m away.

    (5) Waterworks may produce negative impacts

    on the agricultural irrigation canals located on

    the foot of the hill.

    (6) The proposed site is relatively narrow.

    (1) The proposed site is situated on

    wasteland and farmland, indicating high

    costs for land acquisition.

    (2) Big volume of earthworks, especially

    high-slope treatment engineering.

    (3) Long distance of water distribution

    pipeline system, and thus requiring big

    investment.

    (4) Over 10 households in the

    construction area need to be relocated.

    (5) There are one paper mill and several

    processing factories nearby the proposed site,

    and thus the waterworks will be affected

    greatly by the neighboring environment.

    After comprehensive comparison, it can be seen that (i) Toubao site, where

    without polluting enterprises nearby, is near to the reservoir that can help to greatly

    reduce the earthwork of pipeline construction and the investment on pipe materials;

    and (ii) There are many enterprises nearby Dongfeng site, failing to satisfy the width

    of sanitary protection zone. Therefore, from the perspective of environment, Toubao

    site is recommended as the site for the waterworks.

    (3) Distribution of pipelines

    Land inundation cannot be avoided in reservoir construction. However, the

    amount of land occupation for construction sites and water distribution pipeline

    network can be reduced through optimization of construction methods. Such will also

    help to minimize the negative impacts caused by land acquisition and house

    demolition.

    In the arrangement of water distribution pipelines, the Subproject will follow the

    following principles: (a) The construction of water distribution pipelines must try to

  • 10

    minimize the length, avoid big undulation, reduce earthworks, minimize occupation of

    farmland, avoid occupation of fertile land and complete the engineering at the most

    economical costs; (b) The orientation and position of the pipelines must conform to

    the planning for urban and enterprise development, and the construction must be

    conducted at the utmost along the existing roads or planned roads for the purpose of

    convenient construction and maintenance; (c) Water distribution pipelines must try to

    avoid penetrating river valleys, mountain ridges, key railways and flood passages, as

    well as avoid the places with high-corrosive soils and where landslides, land

    collapses, mud and stone flow may easily occur; (d) The water distribution pipelines

    must make full use of the water head, especially giving priority to gravity flow where

    applicable; and (e) The selection of water distribution pipelines must take into

    account of the compatibility with long-term plan and the in-phase implementation.

    Construction access road and sites are also optimized to adopt wasteland for the

    purpose of avoiding farmland occupation. At the same time, according to the

    construction schedule, the APs whose land will be acquired (occupied) must be

    informed in advance so that they can minimize their losses.

    2.2. Range of Survey for Land Acquisition and House Demolition Impacts

    The range of impacts caused by land acquisition and house demolition includes

    the inundation area, reservoir damsite area, waterworks area and the supporting

    pipeline area, as shown in Appendix 2.

    The inundation treatment range includes the reservoir inundation area and the

    places of inundation, bank collapse, landslide and other affected places that are

    caused the impounding of the reservoir. According to the requirements of the Design

    Code for Land Acquisition and Resettlement for Water Conservancy and Power

    Engineering (SL 290-2003), the following range is specified for inundation treatment

    for the Subproject.

    (1) Land acquisition line: The line for acquisition of cultivated land and orchard

    land shall consider the design flood backwater line after 20 years of silt accumulation.

    In the front section of the dam where backwater is not obvious, due to the impacts of

    wave-rising, the line shall consider an additional 0.5m to the normal pool level of

    1,075m for the sake of safety. The line for acquisition of woodland, grassland and

    other types of land shall be the normal pool level of 1,075m.

    (2) Population migration line: The line for population migration shall consider the

    design flood backwater line after 20 years of silt accumulation. In the front section of

    the dam where backwater is not obvious, due to the impacts of wave-rising, the line

    shall consider an additional 1m to the normal pool level of 1,075m for the sake of

    safety.

    (3) Inundation line for special facilities: to be determined by reference to the

    standard for each type of special facilities and the corresponding flood standard

    (4) The land acquisition ranges for the damsite area, the waterworks and the

    pipelines will be determined based on the overall hydrotechnic and construction

    layout.

  • 11

    According to the above ranges, land acquisition and house demolition of the

    Subproject will cover the 5 townships, 10 villages and 19 village groups of Wudang

    and Nanming Districts of Guiyang Municipality and Longli County of Qiannan

    Prefecture, as shown in Table 2-4.

    Table 2-4 Summary of Impacts of Land Acquisition and House Demolition in Terms

    of Administrative Division

    Component Prefecture /

    municipality

    District /

    county Township Village Group

    Reservoir

    Guiyang

    Municipality

    Nanming

    District

    Yongle

    Xiang

    Ganjing Mitangjing

    Shitang Heping, Liuping, Xiaoshan,

    Yaoping

    Wudang

    District

    Pianpo

    Xiang Pianpo Shaoshang, Xinzhai

    Dongfeng

    Town Toubao /

    Qiannan

    Prefecture

    Longli

    County

    Xingshi

    Town Dayan

    Xiaoyan Shangjie, Xiaoyan

    Xiajie

    Damsite Guiyang

    Municipality

    Wudang

    District

    Dongfeng

    Town

    Housuo /

    Toubao /

    Waterworks Guiyang

    Municipality

    Wudang

    District

    Dongfeng

    Town

    Housuo Guanshan

    Toubao No.6

    Zhuchang /

    Pipelines Guiyang

    Municipality

    Wudang

    District

    Dongfeng

    Town

    Wudang No.2, No.6, No.9

    Luowan No.5

    Xintian

    Town Xintian /

    Access

    roads

    Guiyang

    Municipality

    Wudang

    District

    Dongfeng

    Town

    Toubao No.7, No.1, No.2, No.5

    Zhuchang /

    2.3. Socioeconomic Profile of Affected City and District (County)

    The Subproject affects Wudang and Nanming Districts of Guiyang Municipality

    and Longli County of Qiannan Prefecture.

    2.3.1. Socioeconomic Profile of Affected City (Prefecture) Guiyang Municipality is located in central Guizhou Province, and is the capital

    city of Guizhou Province, an important integrated industrial base, and a hub of

    commercial and tourist services in southwestern China. Guiyang governs 6 districts

    (Yunyan, Nanming, Xiaohe, Huaxi, Wudang and Baiyun), one city (Qingzhen) and 3

    counties (Kaiyang, Xifeng and Xiuwen). At the end of 2010, Guiyang had a

    population of 4.325 million, including an agricultural population of 2.946 million, an

    cultivated area of 4.109 million mu, and a GDP of 112.182 billion yuan, in which the

    GDP of primary industries was 5.71 billion yuan, that of secondary industries 45.695

    billion yuan and that of tertiary industries 60.776 billion yuan. Fiscal revenue was

    30.464 billion yuan, the per capita net income of farmers was 5,976 yuan, and the

    per capita disposable income of urban residents was 16,579 yuan.

    Qiannan Buyi-Miao Autonomous Prefecture is located in central southern

  • 12

    Guizhou and on the golden corridor of southwestern China open to the sea, and is a

    place inhabited by many ethnic groups. The prefecture governs two county-level

    cities (Duyun and Fuquan), 10 counties (Guiding, Libo, Dushan, Weng’an, Pingtang,

    Huishui, Longli, Luodian, Dushan and Changshun), and Sandu Shui Autonomous

    County. The prefecture has a total administrative area of 26,195 km². At the end of

    2010, the total population was 3.9043 million, including an agricultural population of

    3,416,200, a non-agricultural population of 488,100 and a minority population of

    2.1747 million. In 2010, the prefecture’s cultivated land area was 2.79 million mu,

    GDP 35.6 billion yuan, fiscal revenue 5.446 billion yuan, per capita net income for

    farmers 3,760 yuan, and per capita disposable income of urban residents was 11,192

    yuan.

    2.3.2. Socioeconomic Profile of Affected District (County) Wudang District is located in the southeast of Guiyang Municipality, and is one

    of the nine district-level units of Guiyang Municipality. The district governs 12

    townships and 121 villages, with a population of 291,200, including an agricultural

    population of 200,200 and a nonagricultural population of 91,000, a land area of

    964.9 km2, a population density of 303.3 persons/km2, an cultivated area of 144,600

    mu, a per capita cultivated area of 0.72 mu, a gross industrial output value of 5.986

    billion yuan, a gross agricultural output value of 859 million yuan, local fiscal revenue

    of 4,523,200 yuan, a gross grain output of 64,900 tons, a per capita grain output of

    324 kg and farmers’ per capita net income of 5,505 yuan.

    Nanming District is one of the central urban districts of Guiyang Municipality, and

    governs 4 townships and 29 villages, with a population of 600,400, including an

    agricultural population of 22,300 and a nonagricultural population of 578,100, a land

    area of 209.34 km2, a population density of 3,285.6 persons/km2, an cultivated area

    of 15,100 mu, a per capita cultivated area of 0.02 mu, a gross industrial output value

    of 14.905 billion yuan, a gross agricultural output value of 189 million yuan, local

    fiscal revenue of 227,879,000 yuan, a gross grain output of 4,300 tons, a per capita

    grain output of 18 kg and farmers’ per capita net income of 6,603 yuan.

    Longli County, Qiannan Prefecture is located in central Guizhou, bordering

    Guiding County on the east, Huishui County on the south, Huaxi District, Guiyang

    Municipality on the west, and Wudang District and Kaiyang County, Guiyang

    Municipality on the north. The county governs 8 townships and 6 towns with 159

    villages, with a population of 210,400, including an agricultural population of 189,000

    and a nonagricultural population of 21,400, a land area of 152.1 km2, a population

    density of 138.3 persons/km2, an cultivated area of 162,900 mu, a per capita

    cultivated area of 0.86 mu, a gross industrial output value of 1.549 billion yuan, a

    gross agricultural output value of 215 million yuan, local fiscal revenue of 52.22

    million yuan, a gross grain output of 75,000 tons, a per capita grain output of 398 kg

    and farmers’ per capita net income of 3,933 yuan. See Table 2-5.

  • 13

    Table 2-5 Socioeconomic Conditions of Affected Cities, and Counties

    Item Unit Wudang

    District

    Nanming

    District

    Longli

    County

    Number of townships / 12 4 14

    Number of villages / 121 29 159

    Population 0,000 29.12 60.04 21.04

    Agricultural population 0,000 20.02 2.23 18.90

    Nonagricultural population 0,000 9.10 57.81 2.14

    Land area km2 964.9 209.34 1521

    Population density /km2 303.3 3285.6 138.3

    Arable area 0,000 mu 14.46 1.51 16.29

    Per capita cultivated area mu 0.72 0.02 0.86

    Gross industrial output value 00m yuan 59.86 149.05 15.49

    Gross agricultural output value 00m yuan 8.59 1.89 2.15

    Local fiscal revenue 0,000 yuan 45232 227879 5222

    Gross grain output 0,000 tons 6.49 0.43 7.50

    Per capita grain output kg 324 18 398

    Per capita net income of farmers yuan 5505 6603 3933

    Source: 2010 Guiyang Statistical Yearbook

    2.4. Socioeconomic Profile of Affected Towns

    The Subproject involves 5 townships, including 3 townships (Xintian Town,

    Dongfeng Town and Pianpo Xiang) in Wudang District, Guiyang Municipality, Yongle

    Xiang in Nanming District, Guiyang Municipality, and Xingshi town in Longli County of

    Qiannan Prefecture.

    Xintian town is located in the center of Wudang District, with a total population of

    24,440 and a gross output value of 161.416 million yuan, including 11.44 million yuan

    in agricultural output value, 140.586 million yuan in industrial output value, and 9.39

    yuan million in tertiary output value. The average per capita net income for rural

    farmers is 5,125 yuan.

    Dongfeng Town is located in the east of Wudang District, with a total population

    of 23,432 and a gross output value of 286.293 million yuan, including 80.41 million

    yuan in agricultural output value, 195.133 million yuan in industrial output value, and

    10.75 million yuan in tertiary output value. The average per capita net income for

    rural farmers is 4,900 yuan.

    Pianpo town is located in the northeast of Wudang District, with a total

    population of 1681 and a gross output value of 10.0171 million yuan, including 8.58

    million yuan in agricultural output value, 0.2671 million yuan in industrial output value,

    and 1.17 million yuan in tertiary output value. The average per capita net income for

    rural farmers is 4,300 yuan.

    Yongle Town is located in the southeast of Wudang District, with a total

    population of 12819 and a gross output value of 80.14 million yuan, including 62.86

    million yuan in agricultural output value, 11.313 million yuan in industrial output value,

    and 5.97 million yuan in tertiary output value. The average per capita net income for

  • 14

    rural farmers is 4,015 yuan.

    Xingshi town is located in the southwest of Longli county, with a total population

    of 15099 and a gross output value of 43.275 million yuan, including 33.47 million

    yuan in agricultural output value, 6.285 million yuan in industrial output value, and

    3.52 million yuan in tertiary output value. The average per capita net income for rural

    farmers is 4,010 yuan. The socioeconomic conditions of the affected villages are

    detailed in Table 2-6.

    Table 2-6 Economic Situation of Towns Affected by Land Acquisition and House

    Demolition

    Indicator Unit Xintian

    Town

    Dongfeng

    Town

    Yongle

    Xiang

    Pianpo

    Xiang

    Xingshi

    Town

    # of households / 8395 8237 3791 534 4198

    Population / 24440 25182 13655 1843 14829

    Where: men / 13140 17467 6904 889 7601

    Agricultural population

    / 3885 4202 6850 1796 7228

    Arable area mu 1140 807 11557 2040 13500

    GDP 0,000 yuan 16141.6 151641 23662.318 3057 14347.2

    Where: agriculture 0,000 yuan 1144 12190 12351.65 2401 8489.2

    Industry 0,000 yuan 14058.6 132630 3325.94 26.71 5506

    Tertiary industries 0,000 yuan 939 6821 7984.728 656 352

    Per capita net

    income of farmers

    yuan/

    person 5125 7557 7667 7310 4010

    Source: County/District statistics, 2010

    2.5. Socioeconomic Profile of Affected Villages

    Among the 10 villages and 16 village groups affected by the Subproject, the

    average population per household is 3.3-4.9 persons, and the average per capita

    cultivated area is 1.0-3.9 mu. Average per capita income varies greatly, ranging from

    3,980 yuan to 5,840 yuan. There are almost no industrial enterprises in the affected

    villages. These villages engage mainly in agricultural production, with major crops of

    paddy rice, corn, rapeseed, etc. Other kinds of economic crops such as peach tree

    and vegetables are also grown. See Table 2-7.

    Table 2-7 Economic Situation of Villages and Groups Affected by Land Acquisition

    and House Demolition, 2010

    Township Affected

    Village

    Affected

    Group

    # of

    households Population

    Arable

    area

    (mu)

    Per capita

    cultivated

    area (mu)

    Per capita

    net income

    of farmers

    (yuan)

    Dongfeng

    Town

    Toubao

    Total 524 1932 4211.75 2.18 5120

    No.7 52 198 392.05 1.98 5010

    No.1 58 217 440.5 2.03 4990

    No.2 62 223 566.39 2.54 5120

    No.5 67 254 602.01 2.37 5000

    No.6 135 489 826.41 1.69 5120

    Housuo Total 365 1346 3149.65 2.34 5820

    Guanshan 62 231 637.57 2.76 5150

  • 15

    Township Affected

    Village

    Affected

    Group

    # of

    households Population

    Arable

    area

    (mu)

    Per capita

    cultivated

    area (mu)

    Per capita

    net income

    of farmers

    (yuan)

    Luowan Total 384 1416 2676.21 1.89 4465

    No.5 54 179 413.5 2.31 4335

    Zhuchang Total 257 948 1763.28 1.86 4800

    Wudang

    Total 329 1213 2632.21 2.17 4659

    No.2 120 246 566.39 2.30 4580

    No.6 72 220 452 2.05 4300

    No.9 81 231 460 1.99 4100

    Yongle

    Xiang

    Ganjing

    Total 487 1796 4220.62 2.35 4116

    Mitangjing 81 289 965.18 3.34 4187

    Shitang

    Total 452 1667 4467.55 2.68 4100

    Heping 68 238 749.68 3.15 4200

    Liuping 72 257 675.93 2.63 4250

    Xiaoshan 69 248 704.3 2.84 4069

    Yaoping 75 251 650.11 2.59 3980

    Xintian

    Town Xintian Total 215 1038 1598.52 1.54 5250

    Xingshi

    Town

    Dayan

    Total 283 1258 3585.29 2.85 4200

    Xiaoyan

    Shangjie 38 140 490.14 3.50 4150

    Xiaoyan Xiajie 36 125 333.52 2.67 4150

    Pianpo

    Xiang

    Pianpo

    Total 458 1409 3254.9 2.31 4561

    Shaoshang 145 352 442.51 1.26 4821

    Xinzhai 213 489 521.85 1.07 4765

  • 16

    3. PROJECT IMPACTS

    3.1. Project Impacts Identification

    According to the analysis of the impacts survey, project impacts include the

    following five types:

    (1) Land losses caused by land acquisition or occupation;

    (2) Impacts caused by demolition of residential houses and attached facilities;

    (3) Impacts caused by demolition of non-dwelling buildings;

    (4) Losses of special facilities and infrastructure;

    (5) Other impacts (water source protection area, downstream irrigation area, etc.)

    3.2. Methods for Project Impacts Survey (physical indicators)

    On March 8, 2010, the Guizhou Provincial Development and Reform

    Commission, and the Water Resources Department of Guizhou Province issued the

    Reply on the Preliminary Design of the Yudongxia Reservoir and No.2 Dongjiao

    Waterworks Subproject (GPDRC [2010] No.319). From July 2010 to October 2011,

    with the support of the affected county and township governments, villages and APs,

    and the design agency, GZWRID completed the detailed measurement survey of

    resettlement impacts.

    3.2.1. Land Survey Land survey adopted electronic plane table for block graphs mapping at the

    scale of 1:1000. The households and the officials from village groups, villages, towns

    and counties verified the boundaries on site, while land and forest administration

    departments and the professionals of the GSDRI verified the categories of lands. At

    the same time, the survey group conducted on-site measurement. Computation,

    statistics and summarizing of the inundated area were conducted by computers

    according to different household and different administrative jurisdiction. The

    computed results were ratified by household, group, village, town and county level by

    level. The unit of calculating land area is standard ―mu‖.

    3.2.2. Survey of Population and Houses The survey on the construction area, waterworks and pipelines was conducted

    as per the land acquisition lines. During the survey, a measured 1:1,000 topographic

    map was used for level control, and the surveyors and the local officials were present

    at sites and made records of the results for every household according to the

    designated range and in combination with the examination of household registry. The

    statistics of the floorage area of buildings and the number of attached facilities

    adopted the method of on-site measurement household by household. The private

    properties of the APs were disclosed to the public for the purpose of public

    supervision during DMS before final statistical announcement.

  • 17

    3.2.3. Survey of Special Items The surveys of special items were based on the data below inundation line

    provided by the respective competent departments. In this connection, site

    verifications were conducted after filling the forms for survey.

    3.2.4. Verification of Survey Results The survey results were verified level by level verification. The private indices

    involving individual farmer’s households were signed or sealed by individual

    households to show their acknowledgements. The collectively-owned indices were

    signed and sealed by the property-holding units. The indices of village groups were

    signed and sealed by the representatives or officials of the village and groups to

    show their acceptance. The village-level indices were verified by the officials of the

    villages or towns through signing and sealing. The town-level indices were signed

    and sealed by the representatives of the towns and counties, and verified by the

    government. The category and quantity of the inundated lands must be also

    approved by the county-level land and resources, and forestry departments.

    3.3. Project Impacts and Impact Level Analysis

    3.3.1. Permanent Acquisition of Collective Land and Impacts Analysis

    A. Permanent acquisition of collective land The Subproject involves 10 villages and 19 village groups in 5 townships in

    Wudang and Nanming Districts of Guiyang Municipality and Longli County of

    Qiannan Prefecture. 2,344.94 mu of collective land will be acquired, including 1,366

    mu of cultivated land3 (58.3%).

    By component, the reservoir will inundate 2,127.88 mu of land, accounting for

    90.7%, including 1,201.16 mu of cultivated land; the damsite will occupy 45.85 mu of

    collective land permanently, accounting for 2.0%; the waterworks and its water

    distribution net


Recommended