INDUCTION PACK 2
(I) The Funding Agreement(II) Managing the Project Stages
2
Project Preparation: Three Step Process
Project Verification Step Status Quo Step Pre-Appraisal /
Business Case StepBusiness Plan
Step
THE NDPG PROJECT STAGES
Implementa-tion Step
Immediate Interventions
Exit Step
3
Introduce Municipalities to NDPG
MUNICIPALITY AND TREASURY SIGN FUNDING AGREEMENT (FA) AND PRELIMINARY SCHEDULES
NDP Unit makes call for projects
Municipality prepare project application (may be assisted by consultants) Submit application to NDP Unit
NDP Unit receives application:•Records receipt , Allocates to a PD, First round assessment
NDP Unit prepares shortlist of projects for verification
NDP Unit undertakes Verification Process:•Site / municipal visits, Complete Verification Report
Final short list for submission to Review Committee / Reference Group
Reference Group recommendations & Report to DDG with funding envelope recommendations
Funding envelope approved by Treasury
Induction workshop by Treasury in the Municipality
Notify Municipality of award
Support Bundles Contents
* Support Bundle A1•Toolkit 1: Grant overview•Toolkit 2: Grant details•Toolkit 3: Guidelines for registration•Toolkit 4: Registration form•Toolkit 5: Building the Business Case
** Support Bundle A2•Funding Agreement (FA)•Schedules
4
THE FUNDING AGREEMENTTHE FUNDING AGREEMENTExtracts to note:
Clause 4.2.20: the municipality is responsible for managing performance of the consultants
“ Enter into all contracts with the Consultant and/or Contractor as required to complete the Project, and shall be
responsible for the management of the performance of the Consultant and/or Contractor in accordance with the contract
and for the management of the Project as a whole in accordance with all applicable National Treasury Regulations and
related National Treasury Guidelines and municipal supply chain management legislation and policy.
Clause 4.2.21: the municipality is responsible for ensuring that the required project management capacity is in
place at all times.
“Maintain an appointed Project Manager at all times”
Clause 5.1: although a funding envelope is potentially available, the NT in the yearly gazette stipulates the actual
yearly allocation
“The National Treasury shall allocate to this Project, on the terms and conditions set forth in this Agreement, amounts for
Technical Assistance and/or Capital Grant Funds, not exceeding the amounts stipulated in the Schedules, and/or as may
be revised and agreed to in writing by the National Treasury.
Clause 5.9 and 5.10: causes for suspension and or withdrawal of funds:
“ Should the Municipality not provide progress reports, financial reconciliation reports, bank statements and updated cash
flow projections on a monthly basis, as required by the National Treasury, and should the Municipality submit for payment
an invoice of the Consultant in respect of Technical Assistance Funding, or request a drawn-down in terms of the Capital
Grant transfer to the Municipality, more than one calendar month from the date of such invoice or request for draw-down,
projected by the most recent Milestone Payment Schedule, the National Treasury shall be entitled to withhold payment of
further transfers until such time as all required reports are submitted. All costs arising from such delayed payments shall be
for the account of the Municipality. 5.10 Should the Municipality not meet the agreed milestones on a monthly basis, as
required for Technical Assistance or quarterly, as required for the Capital Grant, the National Treasury shall be entitled to
withhold or delay payment of further invoices and/or transfers, in whole or in part, until such time as milestones are met. All
costs arising from such delayed payments and/or transfers shall be for the account of the Municipality.
5
THE FUNDING AGREEMENT SCHEDULESTHE FUNDING AGREEMENT SCHEDULES1 General Project Description Yes…ensure you fill in details of the NDPG project manager AND
specifics about the project as per your application + the verification report + information from your award letter.
2 Overall Project Costs Yes. Must reflect the actual and indicative contributions of municipal, other public and private partners.
3 Milestone Payment Schedule Yes at least for year 1
4 Authorization by the Municipality Yes, signed by the MM (as Accounting Officer)…name and signature
5 Council Resolution supporting NDPG Application Yes
6 Special Conditions No
7 NDPG Award Letter from National Treasury Yes
8 Any pertinent delegations approved by the Municipality in terms of this project, e.g. payment requests signed off by NDPG Coordinator, or by NDPG Project Manager, any related delegations and evidence thereof, etc.
No BUT….. We prefer that the MM delegates the NDPG programme management responsibilities here. Full name and signature of MM and delegated official.
MAIN AGREEMENT IS STANDARD. SCHEDULES ARE ORGANIC…CAN BE CHANGED BUT ONLY IF SIGNED BY THE SAME PARTIES WHO SIGNED THE FA…THE MM AND THE CD NDPG
6
Project Preparation: Three Step Process
Status Quo Step Pre-Appraisal / Business Case Step
Business Plan Step
A. YOU HAVE RECEIVED YOUR AWARD LETTERB. YOU HAVE SIGNED THE FA C. YOU KNOW WHAT YOUR GAZETTED ALLOCATIONS ARE:
WHAT THEN ARE THE SUGGESTED PROCESS STEPS FOR MANAGING THE PROJECT PREPARATION PROCESS ?
Implementation Step
Exit Step
7
MANAGING THE PROJECT CYCLE: GUIDELINES ON % SPLIT MANAGING THE PROJECT CYCLE: GUIDELINES ON % SPLIT OF ALLOCATIONS OVER PROJECT LIFE CYCLEOF ALLOCATIONS OVER PROJECT LIFE CYCLE
TECHNICAL ASSISTANCE OUTPUTS
20%
10%
10%
25%
30%
5%
NDPG PROGRAMME MANAGEMENT& COORDINATION
TOWNSHIP REGENERATIONSTRATEGY AND IMPLEMENTATIONPLAN
REVIEW OF PROGRAMME ANDPROJECT STATUS QUO
PRE-FEASIBILITY & DETAILEDINVESTIGATIONS
BUSINESS PLANS
EXIT PLANS & M&E
CAPITAL GRANT OUTPUTS
18%
1%
80%
1%
DETAILED DESIGNS
CONSTRUCTION SUPERVISION
CAPITAL FOR CONSTRUCTION
O&M
8
EXAMPLE OF MANAGING THE PROJECT CYCLE: GUIDE TO % EXAMPLE OF MANAGING THE PROJECT CYCLE: GUIDE TO % ALLOCATION SPLITALLOCATION SPLIT
Case Study: Municipality x received an NDPG award letter stating that they have been awarded a TA envelope of R12m and R150m for CG. The Municipal project manager now draws up an indicative project plan to start the process of contracting external and internal support for the planning and implementation process. A very indicative idea of how the R12m TA and R150m CG could be utilized:
1. Programme Management & Coordination: overall management of the NDPG award from status quo step to exit and review.
(ONLY IF NEEDED!)
(i) If consultant: max 1% of R162m, to be paid from TA if consultant. (20% of TA = R2.4m).(ii) If a municipal official on contract: to be paid from CG
2. Status Quo Review: programme and project level assessment Approx 10% of TA = R1.2m
3. Feasibilities and other technical or sectoral studies Approx 25% of TA = R3m
4. Business Plans Approx. 30% of TA = R3.6m
5. Exit Reviews, Assessments Approx 5% of TA = R600.000
6. Township Renewal Strategy Approx 10% of TA = R 1.2m
7. Detailed design work to build asset funded by the capital Approx 18% of the CG envelope of R150m = R27m
8. Capital for construction Approx 80% of R150 CG amount = R120m
9. Outsourced Construction Management Approx 1% of R150m CG = R1.5m
10. Kick-start operating funding (BIDs, ops, etc.), if needed Approx 1% of R150m CG = R1.5m
9
PSC agrees Terms of Reference (ToR) for the Overall Status Quo analysis and report
Municipality may appoint consultants (using TA Grant) to prepare Overall Status Quo report
Municipality nominates a Project Steering Committee (PSC) that reports to a Portfolio Head (MMC)
Draft programme Status Quo report with priorities and phasing of projects and input to Township Regeneration Strategy
Final Status Quo report(s) approved by PSC (Overall and Project – and contains scoping of Pre-Appraisal Step)
Workshop on Overall Status Quo report with priorities with PSC and NDP Unit. NDP Unit and PSC to formally minute the decision
Project Status Quo report(s) prepared for priority project(s) including draft revised schedules and Council resolutions
NDP Unit receives Final Status Quo report and reviews it
Final Status Quo Report is approved by the Municipal Council and resolution approved
Treasury signs new / revised schedules
Project baseline 1 established on Treasury Portfolio data base
Amended schedules (V2)
STRAGIEC REVIEW BY THE NDPG UNIT
CONTRACTUAL APPROVAL BY
THE NDPG UNIT
PARALLEL DEVELOPMENT OF A
TOWNSHIP REGENERATION STRATEGY AND
IMPLEMENTATION PLAN CAN COMMENCE HERE
10
Pre- Appraisal Report
Draft Report with implications for project scope and concept
Consultants appointed and / or briefed on PA step by Municipality
Phase 1: Consultants undertake project appraisals:•Technical (land, planning, geotechnical, environmental, infrastructure)•Economic and Social (economic profile, socio-economic data, potential for leveraging economic investment
Phase 2: Impact assessment (based on technical, social, economic studies from above)•Technical impacts and risks•Economic impacts and risks•Social impacts and risks
Revise the project conceptPrepare final Pre Appraisal report•Revised project scope•Impact assessment•Indicative project budget and work plan•Summary of TR Strategy and implications of project for TRP and vice versaScope the needs of the Business Plan stepInclude revised schedules and milestone payment schedule
Submit final report to Municipal Council for information
Submit PA report to NDP Unit
Include summary of the TR Strategy and indicate alignment of project to the Strategy
Workshop to discuss findings with PSC and Treasury officials, include TRS
Treasury and Municipality sign revised schedules
SRATEGIC REVIEW BY THE NDPG
CONTRACTUAL APPROVAL
Amended schedules (V3)
11
Appoint consultants to prepare Business Plan / extend appointment
Technical viability Institutional arrangements Financial viability
Implementation Plan
Draft Business Plan with draft revised Schedules
Financial Plan
In line with funding envelope Not in line with funding envelope then apply for Exception
Municipal Council resolution and Municipal Council approved Business Plan and schedules
Business Plan and schedules to NDP Unit for approvalTreasury approved Business Plan and endorse schedules
Capital Grant award to Municipality
Quarterly disbursements of CG to Municipality
Treasury sends Municipality letter with conditions and amendments to schedules
Treasury monitoring of project progress
Partnership / Leverage Plan
Workshop with PSC and Treasury and TRP consultants and officials to discuss draft Business Plan and revised draft schedules and alignment with TRP
Include summary of TRP and ensure projects aligned with TRP
CONTRACTUAL APPROVAL BY NDPG:
CAPITAL GRANT TOTAL AMOUNT IS CONFIRMED
CONTRACUAL REVIEW BY NDPG
STRATEGIC REVIEW BY NDPG
Risk Management PlanOngoing Management / Exit Strategy Plan
Municipality revised BP and schedules
12
PSC and NDPG PD’s resolve procurement of resources for the implementation of the Business Plan
Municipality mobilises the professional team (new / existing) for implementation
Procurement of contractors / extend appointment of professional team to undertake final design
Municipality approves final design and NDP Unit provides inputs, if necessary
Project implementation / construction
Implementation team commissions detailed design
Final design for implementation
Achieve milestone payment pointsTreasury Implementation review / inspection (quality assurance)Begin consideration of exit requirementsComplete projectProject Handover
Submit project close out report with all support documentation to MunicipalitySubmit draft Exit Strategy to NDP Unit and Municipality
NDPG Disburse payment to Municipality
NDP Unit confirms close out report submitted
NDP Unit considers draft Exit Strategy
CONTRACTUAL REVIEW
CONTRACTUAL REVIEW
CONTRACTUAL APPROVAL
CONTRACTUAL REVIEW
13
NDP Unit undertakes project inspection / review
Municipality ensures necessary management and maintenance requirements are in place (financial / budgetary and human capacity)
Municipality and NDP Unit exit workshopMunicipality and NDP Unit review Exit Strategy
Municipality approves final Exit StrategyNDP Unit receives copy
NDP Unit updates project data on their systems as status complete