Industrial Commission Update
June 20, 2019
Justin J. KringstadGeological Engineer
Director
North Dakota Pipeline Authority
2
Statewide Initial Oil Production Rates – 24hr
JJ Kringstad - North Dakota Pipeline Authority 2
3
Bakken/Three Forks Initial Production Rate: 24hr
JJ Kringstad - North Dakota Pipeline Authority 3
4
4,000+ BOPD 24hr Initial Production Rates
JJ Kringstad - North Dakota Pipeline Authority 4
5
Statewide Gas Performance
JJ Kringstad - North Dakota Pipeline Authority 5Average BKN/TF Well Performance Statewide
~12% Improvement
Over 2017
6
Statewide Initial Gas Production Rate: 24hr
JJ Kringstad - North Dakota Pipeline Authority 6
Bakken and Three Forks Gas Performance
JJ Kringstad - North Dakota Pipeline Authority 7
8JJ Kringstad - North Dakota Pipeline Authority 8
Top 20 IP Rates (Oil)
9JJ Kringstad - North Dakota Pipeline Authority 9
Top 20 IP Rates (Oil)
10JJ Kringstad - North Dakota Pipeline Authority 10
Top 20 IP Rates (Oil)
11JJ Kringstad - North Dakota Pipeline Authority 11
Top 20 IP Rates (Oil)
12JJ Kringstad - North Dakota Pipeline Authority 12
Top 20 IP Rates (Oil)
*Month “0” is a partial month with daily production calculated using “Days on production”. Months 1+ use calendar days to calculate daily rate.
13JJ Kringstad - North Dakota Pipeline Authority 13
Top 20 IP Rates (Oil)Electrical Submersible Pump (ESP) Timeline
14JJ Kringstad - North Dakota Pipeline Authority 14
Impact of ESP on Production ProfilesWell: SIBYL USA 44-19TFH (Mountrail County)
*Month “0” is a partial month with daily production calculated using “Days on production”. Months 1+ use calendar days to calculate daily rate.
15JJ Kringstad - North Dakota Pipeline Authority 15
Impact of ESP on Production ProfilesAdditional Examples
*Month “0” is a partial month with daily production calculated using “Days on production”. Months 1+ use calendar days to calculate daily rate.
Well File: 32012 Well File: 33942
16JJ Kringstad - North Dakota Pipeline Authority 16
High Initial Production (IP) Scenarios
“Typical” type curve used as a
comparison example for how
high IP wells may perform
over time.
In this example, the entire
production curve over time is
uplifted relative to a “typical”
well. Well economics and
EUR are both improved.
In this example, only the early
life of the well is higher
relative to a “typical” well.
Early well economics improve,
but uncertainty exists if EUR
will improve or suffer with the
high IP rate.
In this example, the early life
of the well is higher relative to
a “typical” well. Early well
economics improve along with
an incremental EUR
improvement.
17JJ Kringstad - North Dakota Pipeline Authority 17
Oil IP Bin Comparison
*Month “0” is a partial month with daily production calculated using “Days on production”. Months 1+ use calendar days to calculate daily rate.
18JJ Kringstad - North Dakota Pipeline Authority 18
Oil IP Bin Comparison
19JJ Kringstad - North Dakota Pipeline Authority 19
Oil IP Bin Comparison – “Clean”
20JJ Kringstad - North Dakota Pipeline Authority 20
Oil IP Bin Comparison – “Clean”
21JJ Kringstad - North Dakota Pipeline Authority 21
Economic Incentive to Higher IP RatesExample: Payout Period Using $7 million well cost
22JJ Kringstad - North Dakota Pipeline Authority 22
Economic Incentive to Higher IP RatesExample: Rate of Return Using $7 million well cost
23JJ Kringstad - North Dakota Pipeline Authority 23
Economic Incentive to Higher IP RatesExample: Breakeven Pricing Using $7 million well cost
Cushing $56.74
Brent $64.23WTI + $7.49
Crude Oil Prices – June 20, 2019
24JJ Kringstad - North Dakota Pipeline Authority
Pricing Data: Bloomberg &
CME (LLS-Argus)Houston WTIWTI + $6.81
JJ Kringstad - North Dakota Pipeline Authority 24
North Dakota Oil Pricing
2525JJ Kringstad - North Dakota Pipeline Authority 25
US Crude Oil Storage Volumes and Spot Prices
2626JJ Kringstad - North Dakota Pipeline AuthorityJJ Kringstad - North Dakota Pipeline Authority 26
EIA Forecasted Oil Price
2727JJ Kringstad - North Dakota Pipeline Authority 27
2828JJ Kringstad - North Dakota Pipeline Authority 28
North Dakota Oil Production Forecast Assumes Current Technology – Enhanced Oil Recovery Not Included
2929JJ Kringstad - North Dakota Pipeline Authority 29
Major Oil Transmission Systems
Williston Basin Oil Production & Export Capacity, BOPDAssumes Current Technology – Enhanced Oil Recovery Not Included
Production forecast is for visual demonstration purposes only and should
not be considered accurate for any near or long term planning.
3131JJ Kringstad - North Dakota Pipeline AuthorityJJ Kringstad - North Dakota Pipeline Authority 31
Exact DAPL Expansion Timeline(s) Unavailable
32JJ Kringstad - North Dakota Pipeline AuthorityJJ Kringstad - North Dakota Pipeline Authority 32
Upcoming or
Recent Plant
Expansion
WBI Transmission
Andeavor
Major Gas Pipeline and Processing Infrastructure
WBI Energy – North Bakken Expansion Project
JJ Kringstad - North Dakota Pipeline Authority 33
Project Highlights
• 67 Miles - 20” Pipeline
• 19 Miles - 12” Pipeline
• $220+ Million
• 250,000 MCFD Capacity (expandable)
• Expandable to 375,000 MCFD
• End of 2021 Proposed Completion
• Residue Gas Service From North of
Lake Sakakawea to Northern Border
Pipeline in McKenzie County
WBI Energy – North
Bakken Expansion Project
JJ Kringstad - North Dakota Pipeline Authority 34
Project Highlights
• 67 Miles - 20” Pipeline
• 19 Miles - 12” Pipeline
• $220+ Million
• 250,000 MCFD Capacity (expandable)
• Expandable to 375,000 MCFD
• End of 2021 Proposed Completion
• Residue Gas Service From North of
Lake Sakakawea to Northern Border
Pipeline in McKenzie County
JJ Kringstad - North Dakota Pipeline Authority 35
Northern Border Pipeline
*Data Source: Northern Border IPS
• 42” Pipeline
• Carries Canadian (Port of Morgan) and Domestic Gas
• Receives Gas From ND Plants, WBI Transmission Interconnections, and WY Pipelines (Bison & Grasslands)
• Midcontinent Deliveries
JJ Kringstad - North Dakota Pipeline Authority
Simplified Example NB CalculationsConclusion: IF no other gas export options open and all other deliveries on other pipelines stay static, ND
gas production could increase 0.82-1.12 BCFD (from April-19) before Northern Border is 100% Bakken
production. BTU management becomes increasingly important for Bakken residue gas.
36
Northern Border Proposed Expansion Options
JJ Kringstad - North Dakota Pipeline Authority 37
Two Proposed Options:
Stateline/Watford City to Ventura
-580 Mdth Incremental (~525 MMCFD)
-Phase 1: Q3 2021
-Phase 2: Q4 2023
Stateline/Watford City to Cheyenne
-430 Mdth Incremental (~390 MMCFD)
-Phase 1: Q3 2021
-Phase 2: Q4 2022
Simplified Example NB CalculationsConclusion: IF no other gas export options open and all other deliveries on other pipelines stay static, ND
gas production could increase 0.82-1.12 BCFD (from April-19) before Northern Border is 100% Bakken
production. BTU management becomes increasingly important for Bakken residue gas.
• Gas Plants With C2+ Capture
~1,010+ BTU Residue Gas
• Gas Plants With C3+ Capture
~1,150+ BTU Residue Gas
JJ Kringstad - North Dakota Pipeline Authority 38
Bakken Natural Gas Infrastructure
3939JJ Kringstad - North Dakota Pipeline Authority 39
Regional NGL Infrastructure
Kinder
JJ Kringstad - North Dakota Pipeline Authority 40
North Dakota Captured* NGL’s
4141JJ Kringstad - North Dakota Pipeline Authority 41*Non-flared NGL’s & Assumes 10 GPM
NGL Pipeline Takeaway Options
42
4242JJ Kringstad - North Dakota Pipeline Authority 42
ONEOK Elk Creek NGL Pipeline
Project Highlights
• 900 Miles - 20” Pipeline
• $1.4 Billion
• 240,000 BPD Capacity
• Expandable to 400,000
BPD
• End of 2019 Proposed
Completion
• Y-Grade Transportation
JJ Kringstad - North Dakota Pipeline Authority 43
Justin J. Kringstad, DirectorNorth Dakota Pipeline Authority
600 E. Boulevard Ave. Dept. 405Bismarck, ND 58505-0840
Phone: (701)220-6227Fax: (701)328-2820
E-mail: [email protected]
Websites: www.pipeline.nd.gov
www.northdakotapipelines.com
Contact Information
JJ Kringstad - North Dakota Pipeline Authority 44