State of Israel Ministry of Energy and Water

Natural Gas Authority

Industrial Gas Installation Directive

(IGID)

Prepared for Natural Gas Authority Qiryat Hamada 6 POB 45140 Jerusalem 90451 Prepared by Parsons Brinckerhoff Beit Bareket 1 Airport City POB 1032 Airport City 70100 Israel www.pbworld.com

Page 2: Industrial Gas Installation Directive (IGID)

Revision # Date Reason for change

0 1.2.09 Initial draft

1 2.3.09 Review with comments

2 22.3.09 Review with comments

3 6.4.09 submitted to NGA

4 19.11.09 submitted to NGA

5 08.08.10 Add'l comments in section 1.4, 6 & 7- 31792

II

Page 3: Industrial Gas Installation Directive (IGID)

Table of Contents Table Of Contents...................................................................................................................... 3

Abbreviation List 4

Abbreviation List 5

SECTION 1.0 GENERAL ...................................................................................................... 6

SECTION 2.0 TABA ............................................................................................................ 9

SECTION 3.0 DESIGN OF THE SYSTEM .......................................................................... 10

3.1 Schedule 10

3.2 Detailed Design 10

3.3 Provision of the Package 13

3.4 The NGA Review Process 14

SECTION 4.0 PROCUREMENT ............................................................................................ 15

4.1 Manufacturing of the System 15

4.2 Lawful code 15

4.3 Certificates 15

4.4 Traceability 15

4.5 Material Specification 16

SECTION 5.0 CONSTRUCTION ............................................................................................. 18

5.1 Construction of the system 18

5.2 NGA Supervision 21

5.3Notification to the NGA 21

5.4 Testing and Commissioning 21

5.4 Testing and Commissioning 22

SECTION 6.0 REQUEST FOR GASSING UP .............................................................. 24

6.1Request Requirements 24

6.2NGA Review 25

6.3Provision of Gassing up permit 25

SECTION 7.0 OPERATIONS AND EMERGENCY ..................................................... 26

7.1 Procedure Details 26

7.2Construction Completion Certificate 27

Page 4: Industrial Gas Installation Directive (IGID)

7.3 System Completion Approval 29

SECTION 8.0 PROVISION OF AS BUILT DOCUMENTATION ................................... 31

8.1As built Documentation Provision 31

SECTION 9.0 FINAL COMPLETION APPROVAL ......................................................... 32

SECTION 10.0 HEALTH SAFETY AND ENVIRONMENT PLAN ................................. 33

10.1General safety 33

10.2Adherence to Procedures 33

10.3HSE Objectives 33

10.4Training and Material Maintenance 34

10.5Safety Management System 34

10.6Items to be Addressed in HSE Procedures 35

10.7Environmental Responsibility 36

10.8Incident reporting 36

10.9Hazard Identification Study (HAZID) 37

SECTION 11.0 QA/QC SYSTEM QUALITY ASSURANCE AND CONTROL PLAN .... 38

SECTION 12.0 INSPECTION AND MAINTENANCE PROGRAM ............................... 39

Page 5: Industrial Gas Installation Directive (IGID)

Abbreviation List

ABD - As Built Documentation

AGI - Above ground installation

ALARP - As Low As Reasonably Possible

CA - Certifying Authority

CAR - Corrective action report

CP - Cathodic Protection

CTOD - Crack Tip Opening Displacement

EMP - Environmental Management Plan

HAZ - Heat Affected Zone

HAZID - Hazard Identification Study

HAZOP - Hazard & Operability

HSE - Health, Safety & Environment

IGID - Industrial Gas Installation Directive

NCR - Non conformance report

NDT - Non Destructive Testing

NGA - Natural Gas Authority- Israel

OPM - Operating Manual

Owner - Owner may be owner and/or operator

P&ID - Process and instrumentation diagram

PFD - Process flow diagram

(W)PQR - (welding) Procedure qualification record

QA/QC - Quality Assurance / Quality Control

QP - Quality Plan

SCADA - Supervisory Control And Data Acquisition

SMS - Safety Management System

TABA - City Wide Outline Plan for Natural Gas

WPS - Welding procedure specification

V

Page 6: Industrial Gas Installation Directive (IGID)

SECTION 1.0 GENERAL 1.1 This document shall be known as the Industrial Gas Installation Directive,

hereinafter entitled the IGID.

1.2 The IGID shall be supplementary to the City Wide Outline Plan for Natural

Gas, (TABA) the Natural Gas Law, Safety Decree and other relevant TABA’s,

and shall be read in conjunction with them.

1.3 The TABA shall be in place and sanctioned independent of the IGID. The

IGID provides more detailed specification of some of the requested

information necessary to obtain NGA approval for the design, fabrication,

installation and operation of Industrial Gas Installation system.

1.4 The standard relevant for the IGID is the EN 15001 (series) or the ASME

B31.3. (latest editions)

1.5 In case of conflict, the City Wide Outline Plan for Natural Gas (TABA) the

Natural Gas Law and/or Safety Decree shall govern over the IGID.

1.6 The general objective of the IGID is to present instructions and guidelines

required by the Natural Gas Authority (NGA) to the supplier, Owner or

Operator (herein, owner) of an Industrial Gas Installation system, with the

intention of assisting the applicant obtaining required, necessary permits.

1.7 The IGID is applicable to the planning, designing, fabrication, constructing,

operating and maintaining of an Industrial Gas Installation system and does

not address local and regional permitting.

1.8 Owner shall be in full compliance with the IGID. When in full compliance with

the requirements of the IGID and all other specific requirements made by the

NGA, the NGA will submit written confirmation of compliance to the required

Regional Planning Committee.

1.9 Once written confirmation has been submitted by the NGA to the Regional

Planning Authorities, the owner may continue to apply for the required

building permits ( בנייה יהיתר ).

6

Page 7: Industrial Gas Installation Directive (IGID)

1.10 Owner’s compliance with the IGID shall be verified with the NGA through the

ongoing process, as described below. Only upon completion of this process

will written approval be submitted, as described in section 1.8.

1.11 Owner shall bear all costs associated with Owner’s compliance with the IGID

and application for permits. The NGA shall not bear any commercial or other

responsibility related to Owner’s successful or unsuccessful compliance with

the IGID and application for permits.

1.12 The NGA shall be the custodian of the IGID. The Owner shall be obliged to

obtain the latest version of the IGID inclusive of all its supplements,

addendum, etc., from the NGA

1.13 The purpose of the IGID is to create conditions for the safe and efficient

development and use of an Industrial Gas Installation system in accordance

with Israeli governmental law and policy.

1.14 Before Owner can install and subsequently operate an Industrial Gas

Installation system, the Owner shall apply for a permit and such permit shall

be granted before commencement of any installation related activity. The

IGID provides guidelines and instructions for Owner to follow in his application

procedure for an installation and operating permit.

It shall be emphasized that the owner bears the sole responsibility for the safe

construction, operation and maintenance of the distribution system and shall

implement the required procedures, means and methods assuring that the

system integrity is maintained throughout its design and operational life.

1.15 Exemptions to the IGID may be granted by the NGA only upon written request

by Owner and subject to agreed restrictions and conditions. Such agreed

exemption shall carry NGA signature. Exemptions to the IGID shall be

considered on a case-by-case basis and a given exemption can be withdrawn

if:

1.15.1 the data furnished by Owner to obtain it appear to be incorrect

or incomplete to the extent that the exemption would not have

Page 8: Industrial Gas Installation Directive (IGID)

been granted if the actual data had been known at the time the

decision was made.

1.15.2 the circumstances on the basis of which it was granted have

changed to the extent that the exemption would not have been

granted if the altered circumstances had existed at the time the

decision was made.

1.15.3 It cannot be maintained in case a safety hazard develops out

of it.

1.15.4 It appears that one or more conditions, under which it was

granted, are not complied with.

7

Page 9: Industrial Gas Installation Directive (IGID)

SECTION 2.0 TABA

2.1 The design, procurement, construction and operations of the system shall

fully comply with the relevant TABA instructions.

2.2 The owner shall verify if more than one TABA is applicable to the segment.

2.3 The designer shall provide a statement in the design package (as described

below) that the design conforms to the TABA.

2.3.1 Should this not be the case, the designer shall list the non conformities.

2.4 A detailed risk assessment shall be carried out on each Above ground

installation (AGI) in addition to the risk assessment carried out during the

TABA stage.

9

Page 10: Industrial Gas Installation Directive (IGID)

SECTION 3.0 DESIGN OF THE SYSTEM

3.1 Schedule

3.1.1 As an essential part of the preparation of the design, the Owner shall prepare

a detailed schedule providing data on all aspects of the planned project

development including but not limited to design, procurement, manufacturing,

fabrication, installation, testing and commissioning aspects. This data shall

include:

� description of all key activities in logical sequence

� early and late start of these activities

� early and late completion of these activities

� scheduled or available float in all activities

� interfaces with third parties

� milestones

� target dates for getting permits

� contingencies and mitigation measures in case of conflicts

3.1.2 This schedule shall take into account the review process of the NGA, as

described below. This schedule shall be submitted to the NGA periodically

during the life of the project.

3.1.3 This planning stage shall be accompanied by a revision track record, that

provides information, background of schedule changes and mitigation

measures in case schedule changes might create conflicts.

3.2 Detailed Design

3.2.1 The Design shall make reference to the relevant TABA and shall

provide more detailed information complementary to the requested

information therein.

3.2.2 The design shall provide a complete and comprehensive summary of

all design related data and criteria applicable to the proposed

Industrial Gas Installation system such as:

10

Page 11: Industrial Gas Installation Directive (IGID)

� Reference to the design code stated in section 1.4,

guidelines, technical specifications and all addenda to

these

� Relevant engineering decisions, their rationality, choice of

design related parameters and any other variables having

impact on the design.

� Software used for design and analyses

� Decisive design factors derived from the route survey,

environmental, corrosion and protection philosophy,

specific operating criteria, required lifetime for the pipeline,

etc.

3.2.3 The design shall provide specific details about project specific design

factors, waivers and deviations to the code, etc., all to be agreed

between Owner and NGA and such agreement shall be in writing and

signed by both parties.

3.2.4 This design should include a description and drawing that shows the

boundary limits of this project. These boundary limits should note the

upstream provider as well as the downstream owner. (as applicable)

3.2.5 The scope of the NGA review takes into consideration the upstream

boundary limits from the NG provider up to the first valve in the skid

into the turbine/ heater/ or other facility. Therefore, it is considered that

this valve is the downstream boundary limit and therefore shall not be

included in the design package.

3.2.6 The design shall be carried out by a recognized, competent, design

firm to assure its robustness.

3.2.7 To support the design, Owner shall conduct a detailed route survey of

the proposed system, on both sides of the theoretical centerline of the

pipeline corridor as well as around any above ground system facility,

(e.g. block valve station, PRMS, etc.) which shall provide the following

data along the route:

11

Page 12: Industrial Gas Installation Directive (IGID)

� Surface topography

� Location of any infrastrastructure facilities, infrastructure

lines, (ie High Voltage cables, below ground pipelines)

buildings, above and under ground structures, etc.

� Land use limitations (as per TABA)

3.2.8 The data obtained from this survey shall be evaluated and utilized in

the decision making regarding optimization of the proposed pipeline

route and be taken into consideration for the pipeline design,

particularly taking into account possible hazards to the NG pipe due to

the surrounding areas.

3.2.9 The detailed design shall include the following items that firmly

establish the system parameters, installation and operating criteria and

limitations:

� Overall design philosophy and statements of code approval

� Design pressures

� Design temperature

� Flows

� Velocities

� P&IDs

� PFDs

� Outside diameter

� Wall thickness

� Material grade (composition, choice of material)

� Design drawings

� Hazardous area drawings

� HAZID

� HAZOP

� Corrosion protection measures. (corrosion coating, CP,

impressed current)

� Stability measures (weight coating, burial, backfill)

12

Page 13: Industrial Gas Installation Directive (IGID)

� Geotechnical report

� risk assessment

� Environmental report

� Protection measures (burial, backfill, concrete coating,

saddles)

� Installation criteria and limitations i.e. allowable stress level

and stress control during all phases of the pipeline

installation activities

� Electrical design

� Instrumentation design

� Operating criteria and limitations such as gas flow, operating

pressure, surge pressure, minimum and maximum

throughput

� System layout inclusive protection system against over

pressurization

� Stress analysis

� Connection to the SCADA system

� Supervision plan

3.2.10 The detailed design package shall be signed and approved by the

designers and the owner/operator.

3.2.11 The designer shall provide a statement that approves that the design

meets the requirements of the design code as found in section 1.4 as

well as the relevant TABA's.

3.2.12 The Owner shall provide a statement approving the above as well and

stating his readiness to own and / or operate this line in a safe manner

3.3 Provision of the Package

3.3.1 The owner shall provide the NGA with three color copies of the design

packages as well as three CDs that include all documents found in the

hard copies.

13

Page 14: Industrial Gas Installation Directive (IGID)

3.4 The NGA Review Process

3.4.1 The NGA shall review the design for content and shall be allowed to

reject the design out of hand, should the package quality not meet the

required high standards.

� In the event that the package is rejected as such, the owner

shall have the right to reissue the package upon revision as

described above. This reissuance shall include a specific table

of changes made to the package that will assure that the

package is robust. This revised package shall also be

approved by a second, experienced independent design firm.

3.4.2 Upon initial acceptance of the design package, the NGA shall carry out

a design review and issue an approval or design comments. These

design comments will be provided in a tabular format to the owner for

response.

3.4.3 Responses to these comments shall be provided to NGA within the

table format to assure tracking of the comments. Revised

documentation shall be provided in the format as described above.

3.4.4 The tracking of this design review stage shall be carried out strictly

through the table and therefore, it is advised that a highly detailed

response be provided within the table along with a specific mention of

the location of the document within the revised package.

3.4.5 Upon conclusion of the review, a revised design package shall be

provided (if applicable) as per the method described above.

3.4.6 The final design package shall be signed and approved by the

designer.

3.4.7 The NGA shall provide the design approval for this package upon

completion of this review as well as other requirements of the NGA

described elsewhere.

14

Page 15: Industrial Gas Installation Directive (IGID)

SECTION 4.0 PROCUREMENT 4.1 Manufacturing of the System

4.1.1 Based on the approved design package, the owner shall begin to

carry out the procurement process.

4.1.2 The Owner shall obtain all materials from reputable suppliers with

proven track records.

4.1.3 Owner shall establish acceptance criteria associated with suppliers

and demonstrate that these are met through conducting a pre-

qualification process.

4.1.4 This process of approval by the owner shall be fully documented for

the possible audit by NGA.

4.2 Lawful code

Line pipe and pipeline appurtenances shall be specified in compliance with

lawful codes and NGA approved specification. Before commencement of any

manufacturing, fabricating or procurement, the NGA and Owner shall have

agreement on the material specification, the manufacturing process and the

QA/QC plan in place to assure compliance of the materials with the

specification and codes in place.

4.3 Certificates

Each completed pipe or part (e.g hot bend, T, valve) shall have its own

unique manufacturing, inspection and test certificate which shall be presented

to the NGA or its appointed representative for final acceptance. The

independent third party shall accept the definitive material certificate by

signing off the original documents.

4.4 Traceability

Each pipe or part shall have a fully traceable history inclusive of its base plate

certificate and all steps of its manufacturing process and acceptance testing.

15

Page 16: Industrial Gas Installation Directive (IGID)

4.5 Material Specification

4.5.1 The Material Specification shall provide details for the manufacturing

method, limitations, acceptance and rejection criteria, inspection

method and the material traceability method, of the following related

elements (as applicable):

� Bare Line pipe

� Line pipe corrosion coating

� Line pipe weight coating and/or protection coating

� Anodes

� Line pipe bends

� Flanges, Tees, valves and any other appurtenances

� Corrosion coating for Flanges, Tees, valves and any other

appurtenances

4.5.2 As a minimum, the following data shall be verified:

� Chemical composition of base materials.

� Chemical composition shall be in compliance with chosen

material grade.

� Mechanical properties of base materials based testing as

per the relevant code

� Destructive tests may include: tensile testing (longitudinal

and traverse), fracture toughness, hardness (Charpy V,

CTOD), lamination detection, bending, etc.

� Mechanical properties of all welds inclusive HAZ

� Mechanical properties after bending, forging, heat

treatment, forming of base materials.

� Corrosion sensitivity of end product. Accelerated corrosion

testing of weld, HAZ and base material sample

� Dimensions

� Measurements of wall thickness, pipe straightness, pipe

body ovality, pipe end ovality.

16

Page 17: Industrial Gas Installation Directive (IGID)

4.5.3 Owner shall provide the NGA with the inspection and testing program and

procedures proposed to verify that the chemical and mechanical

properties are met, frequency of testing not limited to destructive and non-

destructive testing method, testing equipment, verification, acceptance

and reject criteria, etc.

� The manufacturing process shall be monitored through a pre-agreed

test and inspection plan, which shall be conducted by qualified

inspectors. The inspectors shall be employed by an independent

Certifying Body such as Lloyds, DNV, Bureau Veritas, TUV or any

party to be acceptable to the NGA.

� For already made, off the shelf materials, Owner shall supply evidence

of authenticity of base material, manufacturing specification with

reference to lawful codes, test and inspection and acceptance

certification, signed by independent Certifying Body such as Lloyds,

DNV, or any party to be acceptable to the NGA.

� The NGA reserves the right to review the material manufacturing

specification, test and inspection plan, QA/QC plan, etc and to request

for changes and/or amendments, before pipe manufacturing and

procurement of appurtenances is being initiated.

� During any phase of the manufacturing process, Owner shall provide

the NGA ample warning (minimum 2 weeks) for the NGA to witness

agreed hold points.

17

Page 18: Industrial Gas Installation Directive (IGID)

SECTION 5.0 CONSTRUCTION 5.1 Construction of the system

Upon completion of the above items, (ie design and fabrication) the owner

may commence with the construction document's submittal. NGA will review

and provide comments to the issues stated above. Owner shall provide

response to these comments in a timely manner. No construction activity

should take place prior to resolving all comments to the satisfaction of NGA.

This process may be timely and should be taken into account when

developing the schedule. 60 days prior to construction the owner will provide

the following information:

5.1.1 Quality Management System procedure

The Owner shall be responsible to supply the NGA with a detailed

Quality Management System Plan. This plan shall be assessed by the

NGA on its safety aspects through a formal and systematic review of

the installation plan with the objective of hazard identification and

execution concerns. The plan shall provide full details of the pipeline

installation aspects with emphasis on management of personnel

safety and pipeline integrity control during all phases of the

installation. Procedures shall be developed for all specific installation

aspects such as the pipe laying, pipe burial, pressure testing etc. The

procedures shall noticeably address how human safety and pipeline

integrity are managed through all steps of the installation, how this is

monitored and judged.

5.1.2 Spread Supervision Procedures

Spread Supervision procedures shall include a description of the

project that is to be carried out as well as the roles and responsibilities

of each supervisory entity in the project.

18

Page 19: Industrial Gas Installation Directive (IGID)

5.1.3 Inspection and Test Plan

Inspection and Test Plan shall include specific construction actions

and the inspection and supervision coverage that is required by each

entity on the project, inclusive of the contractor and supervisory

bodies. A definition of each method of coverage should be included to

assure that the definitions are fully understood by all parties.

5.1.4 Organigram

Organigram shall include the role of each person on the project

inclusive of the contractor's personnel as well as the supervisory

staff's.

5.1.5 Schedule of project

As an essential part of the preparation of the design, the Owner shall

prepare a detailed schedule providing data on all aspects of the

planned pipeline development including but not limited to design,

procurement, manufacturing, fabrication, installation, testing and

commissioning aspects.

5.1.6 Risk Assessment for construction

Risk Assessments shall include any risks that may arise during the

construction phase. This may include but is not limited to personnel

risk, equipment risk, material risk, and environmental risk.

5.1.7 Construction Procedures

Construction procedures shall include a detailed process for each and

every construction action that is expected to take place on the project.

5.1.8 WPS, PQR, welder certificates and NDT Examination for the project

Owner shall develop, test and implement approved welding and NDT

procedures for all of the welding of the pipeline in obedience of the

lawful codes and the requirements of the design code, stated in

19

Page 20: Industrial Gas Installation Directive (IGID)

section 1.4, augmented with the additional requirements to be detailed

in a project specific specification.

An independent Certifying Body shall verify compliance with the codes

for all phases of the weld procedure development inclusive its

mechanical and chemical testing. The NGA or its representative shall

have the right to witness the welding process procedure.

Owner shall apply a strict material traceability record of all base

material, weld consumables and test coupons identification and

verification procedures. Similarly Owner shall apply strict recording of

the applied welding parameters. The approved welding procedure

shall have been signed by independent Certifying Body and supplied

to the NGA for review.

Each welder or welding machine operator shall be qualified in

accordance with design code requirements prior to the start of

production welding by making a test weld using the qualified welding

procedure whereas Owner shall assure that only qualified welders and

welding operators are employed during the welding of the Industrial

Gas Installation.

Production welding shall not commence until the qualified welding

procedures, qualified welders and qualified inspection personnel lists

have been reviewed and supplied to the NGA and satisfy the

inspection requirements of the independent third party.

All pipeline and station welds (100%) shall be non-destructively

examined. (NDT) Weld quality shall be in accordance with design

code requirements.

NDT shall be carried out to written procedures, which shall be

submitted to the NGA or its representative prior to the commencement

of the work and shall be reviewed and accepted by independent third

party certifying body.

Page 21: Industrial Gas Installation Directive (IGID)

Owner shall submit detailed procedure and technique sheets for NDT

examination signed off by independent Certifying Body for approval by

NGA prior to the start of production.

5.1.9 Electrical and Instrumentation Procedures shall describe the

method of construction of these systems to the stations as well as

the SCADA systems in place.

5.1.10 The Cathodic protection procedures shall describe the methods of

installation of the CP system to assure that the system is

protected both temporarily and permanently as per the

requirements of the approved design.

5.2 NGA Supervision

The NGA will visit the project over the course of the project and review issues

such as mechanical works, welding works, NDT, CP and E&I.

5.2.1 Contact between the third party agency and the NGA should be open

and independent. The reports of the third party agency shall be

provided to NGA for information, as needed.

5.2.2 The owner shall provide the supreme supervision reports written by

the designer.

5.2.3 Owner shall routinely update the NGA with regards to the project

schedule and the foreseen upcoming construction activities.

5.2.4 In the event of a significant design change, owner shall provide

revised drawings/ documentation to the NGA.

5.3 Notification to the NGA

The owner will provide NGA with notification of the following activities at least

72 hours in advance. NGA will have the option to attend these actions:

5.3.1 welding of sample for WPS approval

5.3.2 destructive tests at a certified lab

5.3.3 approval of welder's to the WPS

5.3.4 pressure test (strength, tightness)

20

21

Page 22: Industrial Gas Installation Directive (IGID)

5.4 Testing and Commissioning

5.4.1 Owner shall conduct and successfully complete a pipeline test before

taking the pipeline into service. The testing shall only be initiated after

all construction activities inclusive any remedial work, have been

successfully completed and the body, as a whole, shall no longer be

subjected to any loading, displacements, other than those for normal

operating. The testing program comprise three steps:

� Conclusive confirmation that the pipeline or station has

been installed without any form of buckling and without any

dents, i.e. confirmation that the pipeline has not suffered

any structural damage through measuring its Internal

Diameter (ID) over its full length. This test is normally

executed by pigging the line with a gauge plate for

pipelines. Size of gauge plate shall be as per the

specification. The AGI's shall be reviewed visually for such

confirmation during the pressure test.

� Pressure testing of the complete pipeline system, (strength

test) should be carried out to the specification and

approved procedure.

� Pressure testing of the complete pipeline system, to a

pressure of at least 1.1 times beyond the design pressure

to confirm leak tightness of the pipeline body. This leak test

is normally executed in continuation with the strength test

whereby the leak test pressure is lower than the strength

pressure.

5.4.2 Owner shall develop and present to the NGA a pipe line test

specification, which shall include the Owner's method to execute the

above three tests. This specification shall, as a minimum, incorporate

the requirements stipulated in the design code, stated in section 1.4,

but the NGA reserves the right to review the test specification and to

request for changes and/or amendments, before pipe testing begins.

22

Page 23: Industrial Gas Installation Directive (IGID)

5.4.3 The agreed Test Specification shall be accepted by the independent

third party certifying body and designer and shall contain as a

minimum the following key criteria:

� Testing criteria to meet inclusive settings, allowable margins

� Test reject criteria

� Remedial action in case any of the three test fails

5.4.4 Following the completion of the hydrotest, the owner shall provide the

NGA with an acceptance of hydrotest certificate as well as back up

documentation that includes:

� pre hydrotest checklist

� filling reports

� equalizing reports

� gauging reports

� table of pressures

� graphs of pressure

5.4.5 This certificate shall be approved and signed by the contractor, the

supervision team on behalf of the owner/operator and the third party

agency

23

Page 24: Industrial Gas Installation Directive (IGID)

SECTION 6.0 REQUEST FOR GASSING UP

6.1 Request Requirements

Upon completion of the construction and testing stage, the owner shall issue

a formal request for gassing up to NGA. This request will include the following

items:

6.1.1 A formal letter addressed to the NGA requesting an operations

permit. This letter should clearly define the system which is under

request.

6.1.2 Construction Completion certificate (as noted in section 7.2)

signed by the contractor, the supervising company, the third party

agency, the owner and other relevant supervision. This certificate

should base its approval of completion to the design code stated in

section 1.4.

6.1.3 Final mechanical completion certificate/checklist stating clearly

parts of the system completed and parts yet to be completed. This

certificate shall be related to a relevant specification. This

document shall be signed by all relevant parties.

6.1.4 The owner shall provide the letter he receives from the

downstream consumer (or upstream providing) stating the

readiness to receive/accept gas at the relevant pressures,

quantities, flows, etc.

6.1.5 If relevant to the request, a statement from the Plant Manager will

be required that states that the downstream kit (out of the scope of

the NGA) has been designed, constructed and will be operated to

a recognized, international standard.

6.1.6 Approval letters from the designer of the segment

6.1.7 Check list for cold commissioning including general diagrams and

P&IDs.

6.1.8 Operation, Maintenance and Emergency procedures are approved

by NGA and other relevant parties and in place. (as described

below)

24

Page 25: Industrial Gas Installation Directive (IGID)

6.1.9 Pressure test results and approvals inclusive of mechanical

completion checklist that was issued prior to the pressure test

commencing

6.1.10 Copies of building permits ( 2טופס )

6.1.11 List and approved copies of all NCR/CAR/ deviation reports.

6.1.12 As Made Documentation

6.2 NGA Review

The NGA shall review the documentation provided for the above items and

will provide comments and request clarification as necessary. Owner shall

allow for sufficient time for NGA review of these items.

6.3 Provision of Gassing up permit

Upon fulfillment of the requirements of this chapter, NGA shall provide a

gassing up permit to the owner for the initial start up phase.

25

Page 26: Industrial Gas Installation Directive (IGID)

SECTION 7.0 OPERATIONS AND EMERGENCY

7.1 Procedure Details

The owner shall prepare a copy of an emergency and operations procedure

that will be reviewed by NGA.

7.1.1 The emergency procedure will take into account the natural gas

facilities in the premises as well as mutual influences possible from

other, nearby gas works and/or other infrastructure in the area. This

plan shall provide all possible emergencies related to the operation of

a Industrial Gas Installation system.

7.1.2 Owner shall identify and classify emergencies and their consequences

on HSE.

7.1.3 For all cases Owner shall analyze the short term and long term effects

of such emergency and the response to the occurrence.

7.1.4 For each type of emergency, Owner shall have a pre-established

response and effect mitigation plan with the objective of avoiding or, at

least, limiting the negative effect on HSE. To accomplish this Owner

must demonstrate to the NGA that an effect mitigation /limitation

philosophy is in place, that a personnel rescue and evacuation

procedures is in place, that associated spare/repair materials are in

stock, that specialist contracts are in place, that repair and clean-up

procedures are developed, etc.

7.1.5 This emergency procedure will also include a valve by valve opening

and closing status to assure proper closure in the event of an

emergency.

7.1.6 The owner shall prepare a copy of the operations procedures that will

include venting, gassing up, start up and operations, and

commissioning and decommissioning procedures (air to N2 to NG and

NG to N2 to air) and will include specific valve maneuvering and

assurances of safe practices on site. Valve maneuvering tables shall

be prepared that clearly note the status of each and every valve

during the operation to assure safe practices. These tables will

26

Page 27: Industrial Gas Installation Directive (IGID)

provide for signature of at least two people for each and every

maneuvering action of valves.

7.1.7 The operations manual shall provide more detailed and specific

information applicable to the Industrial Gas Installation system,

complementary to the requested information therein

7.1.8 The operations manual shall address the following topics:

� Steady flow operating conditions of the pipeline.

� Planned shut-down of the pipeline

� Unplanned shut-down of the pipeline

� Planned re-start-up of the pipeline

� Emergency shut-down and blow-down

� Corrosion management

� Inspection and maintenance.

7.1.9 For the above operations, Owner shall develop detailed procedures,

inclusive of step-by-step description of necessary actions, plans,

drawings, signs, manpower requirements, organisation, names and

contacts.

7.2 Construction Completion Certificate

Upon completion of all work and documentation, the following construction

completion certificate will be provided to NGA:

# Statement Requires Signature of:

1 All materials have been fabricated and constructed

according the relevant designer documents.

Fabrication:

Owner/operator, third

party agency,

Construction: owner, third

party agency , contractor

2 All materials were purchased by Owner/operator and

supplied in accordance with the design and

standards.

Owner/operator

27

Page 28: Industrial Gas Installation Directive (IGID)

3 All welds have been checked, approved and

accepted in accordance with the standards and

design.

Contractor,

Owner/operator, third

party agency

4 All works have been constructed in accordance with

the approved design.

Contractor,

Owner/operator , third

party agency

5 Holiday detection was performed in accordance to

the standard.

Contractor,

Owner/operator, third

party agency

6 All pressure tests, dewatering and drying of the

pipeline and stations have been performed in

accordance with approved procedures and the

results have been completed and accepted in

accordance with the standards.

Contractor,

Owner/operator, third

party agency

7 Golden welds were performed and accepted by all. Contractor,

Owner/operator, third

party agency

8 All NCRs and CARs have been successfully closed

out.

Contractor,

Owner/operator, third

party agency

9 Permanent Cathodic Protection has been put in

place as per the design and relevant standards and

accepted by all.

Contractor,

Owner/operator, third

party agency

10 All electrical works have been constructed as per

design and relevant specifications and are ready for

start up of the facility.

Contractor,

Owner/operator, third

party agency

11 The SCADA system has been constructed as per

design and relevant specifications and is ready for

operation upon start up of the facility.

Contractor,

Owner/operator, third

party agency

12 The firefighting system has been constructed as per

design specifications, successfully hydrotested and

is ready for start up of the facility

Contractor,

Owner/operator, third

party agency

13 All safety and security measures are in place and are

ready for start up of the facility.

Owner/operator

28

Page 29: Industrial Gas Installation Directive (IGID)

14 Cold commissioning has taken place successfully

and accepted by all.

Contractor,

Owner/operator, third

party agency

15 The system is ready for gassing up as per the design

and relevant specifications.

Contractor,

Owner/operator, third

party agency

16 Operations, Maintenance and Emergency

Procedures are complete and approved, all

operators have been trained, all parties are aware

and knowledgeable of the emergency procedures.

Owner/operator

17 All issues and recommendations raised in the risk

assessment (carried out during the design phase)

have been successfully addressed.

Owner/operator, risk

assessor

18 All issues and recommendations raised in the

geotechnical assessment and structural assessment

(carried out during the design phase) have been

successfully addressed.

Owner/operator, geo

technical designer and/or

structural engineer

Any request for concession from the above language shall be raised, in writing, prior

to construction to NGA.

7.3 System Completion Approval

Upon successful completion of the commissioning of the system, and

completion of the necessary adjustments to the downstream systems the

owner shall provide a "completion of hot commissioning and transfer to

normal operations" certificate to the NGA with language as follows:

Please be aware that the system (enter system title here) has undergone a

successful start up process as per the approved start up procedures and best

engineering practice. To date, the following systems are gassed up at the

following pressures, flows and temperatures:

Pressure:

Flow:

Temperature:

29

Page 30: Industrial Gas Installation Directive (IGID)

We, _____, hereby state that the system is ready and capable of regular operations

as per the design flows and pressures dictated.

Signed by:

Plant Manager Operations Manager

Upon receipt of this certificate, NGA shall provide approval for operations permit.

30

Page 31: Industrial Gas Installation Directive (IGID)

SECTION 8.0 PROVISION OF AS BUILT DOCUMENTATION

8.1 As built Documentation Provision

The Owner shall supply the NGA with three hard copies and three electronic

copies of the As Built Documentation (ABD). The ABD shall encompass as-

manufactured, as-built and as-installed data of the completed pipeline system

and all its parts. This includes but is not limited to:

8.1.1 All line pipe-manufacturing records, approved and signed by a

recognised and by the NGA accepted independent Certifying

Authority. (CA) This includes for the coating records.

8.1.2 Inspection and acceptance certificates of all associated materials

such as flanges, elbows, anodes, valves, etc, signed by a

recognised and by the NGA accepted independent Certifying

Authority. (CA) and procured from pre-qualified

supplier/manufacturer.

8.1.3 All welding and NDT records of the girth welds.

8.1.4 Pipe log book and welding log book

8.1.5 All inspection and test reports of the field joint coating.

8.1.6 All other construction reports pertinent to the pipeline.

8.1.7 As laid co-ordinates of the pipeline and stations on the original

design layout

8.1.8 As buried data of the buried pipeline and station sections with

confirmed depth of bury, soil cover, bury data shall be given at

each pipe girth weld.

8.1.9 Civil engineering as made documentation

8.1.10 Cathodic protection as made documentation

8.1.11 Electrical and instrumentation documentation

31

Page 32: Industrial Gas Installation Directive (IGID)

SECTION 9.0 FINAL COMPLETION APPROVAL

The following are the steps that should be taken by the operator/owner which will

allow FINAL Completion Approval to be provided by NGA:

9.1 A formal letter addressed to the NGA requesting a completion approval

signed by the operator/owner of the system.

9.2 A copy of the NGA Temporary Gassing Up Permit that includes the caveats

that were found therein. The documents' package should include a

comprehensive list of the actions taken by the owner/operator in an attempt

to close out these caveats.

9.3 A formal approval of Hot Commissioning by the owner/ operator which

includes the approvals of the relevant supervisory bodies. This approval

should include any relevant documentation needed.

9.4 A formal approval that the system has been shifted to "normal operations"

and is running safely.

9.5 Formal close out of the As Made process including any reviews and

comments made by NGA or their representative.

9.6 Approved and signed Building Permits ( 4וטופס 3טופס )

9.7 Approval of the designer that the system was completed. Specific mention

to the geotechnical design and the approval of the system to the relevant

risk assessment is to be included.

32

Page 33: Industrial Gas Installation Directive (IGID)

SECTION 10.0 HEALTH SAFETY AND ENVIRONMENT PLAN

10.1 General safety

Health, Safety and care of the Environment is of prime importance to the

NGA. Owner shall be committed to maintain a safe, healthy and injury free

workplace for its employees and any person working on behalf of the Owner.

Furthermore, Owner shall be committed to avoid damage to the environment.

10.2 Adherence to Procedures

Adherence to agreed procedures, work-plan, operating philosophy, etc., of all

personnel is fundamental to ensuring safe and efficient working conditions. It

should be stressed that the responsibility for Health, Safety and care for the

Environment is the responsibility of the owner and shall be an integral part of

and, is inseparable from all daily operations.

10.3 HSE Objectives

Owner’s HSE objective shall be to:

10.3.1 Provide effective safety systems and plans for managing HSE in

all his operations to ensure those risks are assessed and reduced

to level: As Low As Reasonably Possible (ALARP).

10.3.2 Properly inspect and maintain all equipment and tools.

10.3.3 Promote safety awareness, near miss reporting and a healthy,

responsible attitude amongst all personnel.

10.3.4 Ensure effective emergency response arrangements, backed-up

with trained and exercised personnel.

10.3.5 Establish and maintain clear written standards and procedures to

control the risk to HSE and ensure these are adhered to

10.3.6 Ensure that all personnel involved, either staff or subcontractors,

are competent and able to perform their tasks safely.

33

Page 34: Industrial Gas Installation Directive (IGID)

10.3.7 Ensure prompt investigation of incidents and that adequate

corrective actions are taken.

10.3.8 Promote joint consultation and lateral learning for all personnel

10.3.9 Provide sufficient resources for HSE advisory and audit services

to assist management to meet set HSE policy objectives.

10.3.10 Co-operate with statutory and professional bodies to promote

workable, practical standards and improve codes of practice and

legislation in relation to HSE matters.

10.4 Training and Material Maintenance

10.4.1 The NGA requires that all work under supervision of the Owner shall

be carried out with due observance of all legal requirements to achieve

the required statutory standards for Health, Safety and Environment.

10.4.2 Owner shall ensure that for all parties, personnel, contractors, working

on behalf of Owner, are fully familiar with and will adhere to statutory

health, safety and environmental standards and regulations. The HSE-

Plan shall include for regular audits, inspections, HAZIDs and

HAZOPs. The NGA reserves the right to witness audits, inspections,

HAZOPs, HAZIDs and if considered required, the NGA request for

changes and/or amendments of the plans prior to implementation.

10.5 Safety Management System

10.5.1 Owner shall develop and implement a safety management system

(SMS).

10.5.2 The SMS is a systematic approach to safety and health aspects in the

execution of onshore pipeline installation operations.

10.5.3 The approach must be laid down in a formal description in which it

must be demonstrated that the work is organized in such a way that it

can be executed safely.

34

Page 35: Industrial Gas Installation Directive (IGID)

10.5.4 The SMS relates to all phases and combination of phases involved in

installation operations.

10.5.5 The SMS must in general contain objectives relating to safety and

heath:

� The way it is intended to accomplish these objectives.

� The standards applicable to accomplish these objectives.

� The way in which observance of these standards will be

monitored.

10.5.6 The description of the SMS should satisfy the principles of quality

management as formulated in the ISO-9000 series and should

contain, as a minimum, the following elements:

� Safety policy and control.

� Establishment of safety management evaluation criteria.

� Design, safety margins, review, applicable codes.

� Operations, HAZOPs, compliance with statutory regulations

and industry standards, environmental limitations,

� Personnel, required training standards, required courses, job

selection criteria.

� Supervision, required experience, job analysis, risk

identification, incident and near miss reporting, accident

and incident investigation

� Emergency planning and drills

10.6 Items to be Addressed in HSE Procedures

10.6.1 Disposal of chemicals used for the commissioning and conservation

of pipelines such as dye, corrosion inhibitors, oxygen scavengers,

biocides, etc.

10.6.2 Any limitations to exposure to the environment of chemicals, i.e. zinc

anodes.

35

Page 36: Industrial Gas Installation Directive (IGID)

10.6.3 For each project installation a HSE plan shall be developed. This plan

needs to address all measures taken to support safe and healthy

working conditions for all personnel involved and all measures taken

to avoid pollution of the environment. The HSE shall include safety

training of personnel, health and safety measures related to

personnel transport to and from the offshore installation sites, health

and safety training and standards applied for hazardous.

10.6.4 The HSE plan shall provide details of and schedule for safety audits.

10.7 Environmental Responsibility

An Environmental Management Plan shall be prepared by the Owner. The

EMP shall address the effects of materials, anodes, and coating on its

environment. With respect to cleaning and testing of the pipeline/AGI's using

inhibited water, the used chemicals shall be of a biodegradable nature. The

EMP will specify all areas of possible impacts due to the construction of the

pipeline and all proposed mitigation measures.

10.8 Incident reporting

10.8.1 Any incident occurring during the course of the manufacturing,

construction, installation and commissioning phase shall be reported,

by written statement, to the NGA within 48 hours of the incident. Such

Incident Report shall provide a full description of the course of such

an incident and the measures to mitigate reoccurrence of a similar

type of incident. Owner shall maintain statistics with respect to the

incidents occurring. These statistics shall be evaluated against

threshold values, pre-agreed between the NGA and Owner. In case

unacceptable level of incidents take place, the NGA shall instruct

Owner to re-assess his SMS and might stop all work until such re-

assessment has been undertaken.

10.8.2 Similarly Owner shall report ’near-misses’, situations that have not

caused incidents but had the potential to do so. Owner shall actively

36

Page 37: Industrial Gas Installation Directive (IGID)

pursue near miss reporting amongst all personnel involved in the

work.

10.9 Hazard Identification Study (HAZID)

10.9.1 Owner shall apply a structured manner in hazard identification, by

conducting frequent assessments of the work. These HAZIDs shall

be in the form of a meeting in which a multidisciplinary brainstorming

season shall be held about the work activities, the circumstances on

the work place, the human factor, etc. The end result of a HAZID

should lead to identification of potential hazards, shortcomings and

out of this, possible recommendation, improvements could be

accomplished.

10.9.2 The objective of HAZIDS is to provide the NGA assurance that:

� The Owner selected technology can be applied with

confidence so as to provide a safe and operable Industrial

Gas Installation system.

� The manufacturing, fabrication and installation of the

system can and will be achieved without unacceptable

dilution of design intent.

� That the Owner is adequately prepared to commission and

operate the pipeline

� The system is achieving an acceptable level of safe

operation consistent with commercial intend.

37

Page 38: Industrial Gas Installation Directive (IGID)

SECTION 11.0 QA/QC SYSTEM QUALITY ASSURANCE AND

CONTROL PLAN

11.1 Owner shall develop, implement, maintain and report using an approved

Quality System, which shall be in accordance with ISO 9000 series.

Owner shall present the NGA his quality system as a document

hereinafter referred to as the Quality Plan (QP). The QP shall address the

measures taken to assure that all aspects of manufacturing,

procurement, installation and commissioning are executed to

internationally and/or domestically recognised standards and, as a

minimum, to ISO 9000 series.

11.2 The QP shall include for hold points related to, witnessing, inspection and

acceptance hold points by the NGA. The NGA reserves the right to

review the QP and to request for changes and/or amendments, before

the QP is implemented.

11.3 Upon implementation of the QP, Owner shall timely invite the NGA for

witnessing the agreed hold points. It will be up to the NGA’s discretion to

witness these hold points.

11.4 The independent third party shall further check the quality of the work and

the effectiveness of Owner’s quality system on spot check basis. Owner

shall carry out all remedial actions as a result of such sampling.

11.5 Contractors, sub-contractors, suppliers, fabrication and installation

contractors, proposed by Owner for the pipeline work, shall be reputable,

pre-qualified entities. Owner shall, on request, supply the NGA

information regarding the proposed entities track record, reputation, pre-

qualification criteria and compliance with these, audit results. On request,

Owner shall supply the list of pre-qualified entities.

11.6 The QP plan shall further include for an inspection, test and audit plan.

38

Page 39: Industrial Gas Installation Directive (IGID)

SECTION 12.0 INSPECTION AND MAINTENANCE PROGRAM

12.1 Owner shall develop and submit to the NGA a system inspection and

maintenance program for the lifetime of the complete system including all

sections. The inspection of the pipeline shall be internal and external.

12.2 The internal inspection shall confirm the internal pipe body integrity. The

pipeline internal integrity could be jeopardized as the result of corrosion,

pitting, and buckling resulting from internal or eternal accidental loads.

12.3 The external inspection shall confirm that the external pipeline body has

not suffered from accidental loads.

12.4 External inspection shall be conducted using approved methods of

inspection.

12.5 The NGA or its appointed representative shall be invited by Owner to

witness the inspection.

12.6 If the inspection results give reason for concern and the pipeline integrity

is considered to become a HSE concern, the NGA has the right and will

request Owner to shut-down the system and to make it safe without

delay.