Date post: | 01-Nov-2014 |
Category: |
Documents |
Upload: | mohamed-shamal |
View: | 424 times |
Download: | 1 times |
Industrial training report
PREFACE
During my industrial training period of past 4 months, I was cherished with practical
experiences, knowledge on site procedures and general knowledge on industry. My
training establishment was Sanken Construction (Pvt) Ltd and Isuru Engineering (Pte)
Ltd. I am very much pleased in presenting this report on which I gained there.
The period that I spent with Sanken Lanka as a trainee was diametrically different from
the life in ICBT. But during that short period I gained a lot of experiences on civil
engineering construction, realized the value of having a balanced theoretical and practical
knowledge and realized about the expected role of engineers from the industry.
What I observed about the organization, what I gained as practical experiences and my
opinions on training are agglomerated in this report.
First elaborates about my training establishment- Sanken Construction (Pvt) Ltd and
Isuru Engineering (Pte) Ltd.
The most important thing is what I gained during the training period all those things are
summarized in this report. I included there what I have done, what I have seen and what I
have come to know during that period. Site procedures including store procedures, safety
functions and financial procedures are mentioned that I observed there. Technical
experiences that I gained there are described. Functions and duties that I was involved
and technical and social matters raised are also included.
What I have gained during past 4 months physically and spiritually, my attitudes
regarding industrial tanning and the training establishment, my overall assessment on this
training session and my own suggestions to improve the training to give more effective
training to future batches are also presented.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 1
Industrial training report
ACKNOWLEDGEMENT
Theory without practice is not lead to success. The industrial training program
organized by ICBT mount campus is highly appreciated because this was a golden
opportunity to me as an undergraduate.
First of all, I would like to thank Mr. Gamini Rajakaruna for taking a few
moments of his valuable time to guide me and support me throughout the course of this
project. He all the time encouraged us to work on this module and appreciated our good
work is well. He gave us excellent feedbacks and motivated us more on this industrial
training. He did a greatest dedication regarding industrial training and encouraged us to
get maximum use of industrial training. I would also like thank our site manager Eng.
Anurudhdha.
I would also thank project Engineers Eng. Kapila Weerasinghe, Eng. H.L.N
Priyadharshani, Eng. Samitha Saparamadu and all the other staff members of project who
provided me such a good training and assisted me in many ways.
And finally my thanks also tend to my parents, family members, my colleagues
and all the others who helped me to have a successful training period.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 2
Industrial training report
Table of content
Page Number
Preface………………………………………………………………………..…….01
Acknowledgement……………………………………………………………….…02
A) Profile of the Project………..………….……………………………………….04
B).Description Of the Project...…………………………………………………….09
C).Experience Gained...………………………………………………………..…...24
D).Observations Made.…………………………………………………………..…54
F).Any problems encountered and solutions found… …………………………..…56
Conclusion………………………………………………………………………….59
Reference……………..………………………………………………………….…60
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 3
Industrial training report
A) Profile of the Project
Sanken construction (Pvt) Ltd
About Sanken Construction
Formation
Sanken construction traces its roots back to their joint venture with Mitsui Construction
Company of Japan. Mitsui Construction Company commenced their operation in Sri
Lanka in 1977 with a Branch office in Colombo. In May 1984, a Company by the name
Mitsui construction Company Lank (Pvt.) Ltd. was incorporated under FIAC
authorization to undertake Civil and Building construction work. This was extended in
December 1985 to include, the Leasing and Hiring of Industrial equipment. Four years
onwards, a name change from Mistui construction Company Lanka (Pvt) ltd took place.
Additionally in March 1991, approval was obtained for the sale of Ready mixed concrete-
a pioneering venture of construction Industry in Sri Lanka. In 2011 Sanken Lanka (Pvt)
Ltd changed its name to Sanken Construction (Pvt) Ltd in Sri Lanka.
Affiliation
Sanken Construct in one of the highest ranked construction companies (ICTAD –
C1 Grade)
Sanken Construction is a member of National Construction Association of Sri
Lanka (NCASL)
Sanken Construction is ISO 9001:2008 Quality Management System Certified
Company.
Awards
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 4
Industrial training report
ICTAD Construction Excellence Award (2007) for the construction of “Capitol
Residencies” luxury Apartments.
Bronze Award for Export of Business and Professional Services by National
Chamber Of Exporters of Sri Lank in (2007 and 2008)
Construction Excellence Award for Buildings (National) by National chamber of
Construction of Sri Lanka (2007).
Merit Award in Education and Training on Special projects by Ceylon Chamber
of Commerce (2008).
Sanken Lanka Vision
Sanken Lanka Vision
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 5
VISION
“To be Sri Lanka’s Premier construction service provider”
MISSION
“To provide Quality professional services, exceeding customer expectations, by effective utilization of all resources within the best practices of the industry”
Industrial training report
Quality Policy
At Sanken Construction (Pvt) Ltd are a team committed to provide a quality product and
services at affordable price, on time, In the execution of construction projects and the
manufacture of related products, with the support of our valuable suppliers and in total
harmony with society and the environment.
Sanken Construction is further committed, to satisfy our customer whilst improving the
quality of life of our organization.
Sanken Construction value the team work, efficiency, responsibility and responsiveness
to achieve these goals through optimization of resources and continual improvement of
their systems, At all levels of operations, to further enhance the quality of their products
and services.
Services
Construction contracts
Property development
Ready mixed concrete
Hiring of scaffoldings
Design and build contracts
Consultancy
Hiring and leasing of machinery
Trading
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 6
Industrial training report
Sanken Construction (Pvt) Ltd
Established : 23rd May 1984
Previous Registration No : N (PVS) 1109
Present registration No : PV 9889
New date of registration : 14-10-2011
In Sanken Lanka
a) Project Name. On 320 Residential Apartment
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 7
Industrial training report
b) Name of the Client: John Keels Residential Properties (pvt) Ltd
c) Name of the Consultant: Surath Wickramasinghe Associates
d) Name of the Contractor: Sanken Construction (pvt) Ltd
e) Duration of the Project: 3 years
f) Estimated Cost: Rs. 5, 548, 275, 000.00
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 8
Industrial training report
g) Type of Contract: Lump sum
h) Defect Liability Period: 1 year
i) Percentage of Retention: 5%
j) Performance Security: 5%
B).Description Of the Project:
In Sanken Lanka
a) Project Location- No 320, Union Place, Colombo 02
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 9
Industrial training report
Escape, whilst in the hustle and bustle of town. Centrally located in the heart of
Colombo’s commercial and business hub, “OnThree20” is just minutes, if not seconds
away from hotels, schools, recreational centers, supermarkets, department stores,
cinemas, restaurants and clubs
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 10
Industrial training report
b) Organization chart
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 11
DGM (projects)
Executive Director
Manager (projects)
Industrial training report
c) Overall Scope of the project.
3 Towers of 38 Storeys with 475 Apartment Units
Over half an acre of landscape garden on the podium level, 2,000 sqft Gymnasium, 40
Visitor parking lots, Large club house, Multi-purpose function rooms, BBQ pits,
Business center, Squash Court, Steam Room and Indoor Games Rooms. HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 12
Project Manager
Site Manager IISite Manager I Site Manager III
Site Engineer II Site Engineer II Site Engineer III
Project Engineer
Project Engineer
Project Engineer
Project Engineer
Project Engineer
Project Engineer
Project Engineer
Project Engineer
Assistant
Engineer
Assistant
Engineer
Assistant
Engineer
Assistant
Engineer
Assistant
Engineer
Assistant
Engineer
Assistant
Engineer
Assistant
Engineer
Assistant
Engineer
Trainee Engineer
I
Trainee Engineer
II
Technical officer I
Trainee Engineer
III
Trainee Engineer
IV
Technical officer II
Trainee Engineer
V
Trainee Engineer
VI
Technical officer III
Supervisor I Supervisor I Supervisor I Supervisor I Supervisor I Supervisor I Supervisor I
Workers Workers Workers Workers Workers Workers Workers
Industrial training report
Facilities and Finishes
Apartments
Air Conditioning for Living / Dining Area and Bedrooms
Pantry Cupboards with Hob & Hood
Maid's Room(Available in some Apartments / Optional)
Balcony for the living area
Intercom system
Porcelain Tiled floor with wooden skirting
Veneered finish doors
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 13
Industrial training report
Aluminum Glazed windows & Sliding doors
Central Gas system
Hot Water (Geyser) in Bathrooms and Kitchen
MATV System
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 14
Industrial training report
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 15
Industrial training report
Common Areas
Covered Car parking for each apartment plus an option to purchase additional car
parks (based on availability)
Building Management System
Standby Power
Broadband Infrastructure
Separate Entrance Lobbies in each Tower
Over half an acre of landscape garden on the podium level
Swimming pool, Lap pool & Kiddies pool
2,000 SqFt Gymnasium
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 16
Industrial training report
40 Visitor parking slots
Large Club house and 2 multi-purpose function rooms
BBQ Pits
Business Centre
Squash Court
Steam Room
Indoor Games Room
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 17
Industrial training report
A) Profile of the Project:
In Isuru Engineering (PTE) LTD
Isuru Engineering (PTE) LTD, popularly referred in the Construction sector as ISURU
(IEL), true to its' vernacular meaning having achieved popularity among clients.
Isuru Engineering (PTE) LTD, popularly referred in the Construction sector as ISURU
(IEL), true to its’ vernacular meaning having achieved popularity among clients,
commenced its construction activities in 1993 and became a member of the National
Constructors Association of Sri Lanka.
Dedication and Commitment to high ideals helped IEL to achieve ICTAD M1 Category
in Building Construction, within a very short span through the support of our professional
staff consisting of a dedicated team of highly skilled and qualified Engineers and
Technical Officers trained in the latest technology.
Vision of Isuru Engineering (PTE) LTD
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 18
VISION
To be the best service provider in construction industry for
Sri Lanka.
Industrial training report
Mission of Sri Lanka Ports Authority
Company History
IEL commenced its operations in 1993 with Chairman/Managing Director and a Director.
A small Team of Engineers provided the support services at the inception. IEL received
Membership of National Construction Association of Sri Lanka in January 1997.
Since then it has undertaken Construction work in Sri Lanka and the Republic of
Maldives. Through perseverance and dedication, and with the gradual build up of the
Engineering team, it managed to rise to the highest ICTAD Grading within a short period
of 4 years. Similarly upgrading was possible in the fields of Water Supply & Drainage,
Highways and Bridge Construction. IEL has been admitted to the Dun & Bradstreet
Global Database. IEL has been assessed and certified for meeting the requirements of
ISO 9001-2000 by SGS, United Kingdom, and has reached a prime position in the
construction field through its highly successful operations in Sri Lanka and abroad.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 19
MISSION
To provide comprehensive, state-of-the-art services in
Construction Industry, using latest technology together with
competent service personnel to meet the highest standards of
the Construction Industry with honesty and integrity.
Industrial training report
Achievement
National Construction Association of Sri Lanka Membership was awarded to
Isuru Engineering (Pte) Ltd in 1997
Institute for Construction Training and Development (ICTAD) awarded higher
grading Building Construction, Water Supply & Drainage, Road Works etc in
1997
Admitted to the Dun & Bradstreet Global Database in 2003
Awarded ISO 9001-2000 System Certification in 2008
Machinery and work shop
IEL maintains a large contingent of machinery, equipment and vehicles and has access to
machinery and equipment to undertake the following works:
Earth excavation
Earth haulage
Earth compaction
Road Construction
Water Supply and Drainage Work
Water Retaining Structures
High Elevation Water Towers
Sumps
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 20
Industrial training report
Sewer Treatment and Disposal Facilities
Road construction
Fabrication of steel structures
School Buildings, Hotels and Multi Storey Buildings
a) Project Name. Proposed Office complex
b) Name of the Client: Mrs.V.J Neththikumara
c) Name of the Consultant: Mr. T.P Weerasinghe
d) Name of the Contractor: Isuru Engineering (PTE) LTD
e) Duration of the Project: 6 months
f) Estimated Cost: Rs 23,556,852/=
g) Type of Contract: Lump sum
h) Defect Liability Period: 6 month
i) Percentage of Retention: 5%
j) Performance Security: 5%
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 21
Industrial training report
B).Description Of the Project:
In Isuru Engineering (PTE) LTD
a) Project Location- Nawala road, Nugegoda
b) Organization Chart
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 22
Project Manager
Site Engineer
Technical Officer Trainee Engineer
Store keeper
Industrial training report
Project manager
Project manager is responsible for overall administration of the site. Co-ordination with
different persons involved in project, personnel management at site, take heed of
financial matters and quality control are done by project manager. All the officers
employed in the site are under project manager’s control.
Site engineer
Site engineer is responsible for all the construction works carried out at site and relevant
instructions should be given to work supervisors by site engineer. Works according to
drawings and specifications should be carried out and payments to sub contractors also
should be done under his inspection.
Checking bar bending schedules, checking financial aspects of the site, involving in
ordering material, machinery and equipments from suppliers and participating in progress
meetings are done by site engineers.
Work supervisor
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 23
Watcher
Workers
Industrial training report
Giving relevant instructions to workers, getting the plans from site engineers, controlling
laborers at work site, issuing materials to the site under approval of site engineers and
supervise the works done by workers should be done by site supervisor.
Quantity surveyor
Quantity surveyor is involved in preparing quantities of work done by measuring them,
preparing bills for sub contactors, preparing material comparisons and preparing cost
break downs.
Store keeper
Store keeper is responsible for all affairs of site stores. Most often financial aspects of
stores were conducted by store keeper in these sites. Cash floats, expenditure of the site,
pay sheets for the casual staff etc. were maintained by him.
Store helper
Stores helper maintains the stores properly with records of receiving and issuing of
materials, tools, machinery and other inventory items. Making labour records is also done
by him.
Watcher
Watcher is responsible in site security.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 24
Industrial training report
C).Experience Gained
During my industrial training period of 4 months worked under the supervision of Eng.
Kapila Weerasinghe –one of the site Engineers in On Tree 20 Project. The training
experiences are spread to a large area because this project is a huge project. The
experiences including the duties and functions which I had to perform can be categorized
as follows.
Backfilling:
Backfill material shall be clean earth fill composed of sand, clay and sand, sand and rock,
crushed rock, or an approved combination thereof. Backfilling shall be divided into three
specified areas: First, from trench grade to a point 12 inches above the top of the utility,
called initial backfill; second, from the top of the pipe zone to the bottom of the subgrade
called final backfill; and third, from the bottom of the replacement base course to the
replacement surface. Where encasements or other below grade concrete work have been
installed, backfilling shall not proceed until the concrete has obtained sufficient strength
to support the backfill load.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 25
Industrial training report
Initial Backfill
Granular material shall be carefully placed and tamped around the lower half (springline)
of the utility. Backfilling shall be carefully continued until the fill is 12 inches above the
top of the utility in layers not exceeding 6 inches (uncompacted thickness), using the best
available material from the excavation, if approved.
The material shall be lowered to within two feet above the top of pipes before it is
allowed to fall, unless the material is placed with approved devices that protect the pipes
from impact. Initial backfill shall exclude stones, or rock fragments larger than one inch
for either ductile iron. HDPE or PVC pipe. Compacting each lift shall be equal to 100%
of maximum density as determined by AASHTO T-99.
C. Final Backfill: The remainder of the trench, above initial backfill and below the
subgrade, shall be backfilled and compacted in layers not exceeding 12 inches
(uncompacted thickness), except that the last two lifts shall not exceed six inches
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 26
Industrial training report
(uncompacted thickness) per lift. Compaction of each lift shall be equal to 100% of
maximum density as determined by AASHTO T-99.
Shoulder Restoration: All shoulder restoration shall be in accordance with the applicable
permit requirements of the agency having jurisdiction.
In excavated locations outside a 2(horizontal) to 1(vertical) slope downward from the
shoulder line or the back of the curb, backfill (initial and final) shall be compacted to a
density equal to 95% of maximum density, as determined by AASHTO T-99, or to
natural existing density of the adjacent undisturbed trench embankments, whichever is
greater.
Protective Concrete Slab: Protective concrete slabs shall be installed over the top of
trenches, where required, to protect the installed utility against excessive loads, or when
insufficient cover exists.
Compacting:
Compaction Methods: Specified compaction shall be accomplished using accepted
standard methods (powered tampers, vibrators, etc.), with the exception that the first 12
inches of backfilling over the pipe shall be compacted by hand-operated tamping devices.
Flooding or puddling with water to consolidate backfill is not acceptable, except where
sugar sand is encountered and the operation has been approved by the Engineer of Record
Location of Density Tests: Density tests for determination of the specified densities shall
be made every 1000 feet parallel to roadways and at least one test location under each
perpendicular roadway cut. Reference the standard construction details for density test
requirements for trenches at flexible pavement.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 27
Industrial training report
Test backfill compaction at each specified location, at the finished backfill surface
elevation and at a point 12 to 16 inches beneath the finished surface elevation.
Density Tests: Density tests for determination of the above-specified compaction shall be
made by a qualified testing laboratory. If any test results are unsatisfactory, the
Contractor shall re-excavate, recompact the backfill, and retest, at his expense until the
desired compaction is obtained.
Additional compaction tests shall be made to each side of an unsatisfactory test, as
directed, to determine the extent of re-excavation and re-compaction necessary. Test
results shall be made available to SLCU for their records.
Applying Screed concrete
Brick work
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 28
Industrial training report
Walls were constructed by burnt clay bricks using 1:5 cement sand mortar. External walls
were constructed into 225 mm thickness and internal walls into 112.5 mm thickness.
Setting out for brick work
Setting out for brickwork
Above figure elaborates how setting out lines should be marked for brickwork. Two
offset lines should be marked on either sides of brick wall. When the wall plaster is done,
correct measurements can be taken from those offset lines. 25 mm allowance should be
left on both sides of a door or an opening.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 29
Industrial training report
Construction of brick walls
1:5 cement sand mortar was used here. 225 mm thick walls were constructed in English
bond and 112.5 mm thick walls in stretcher bond. Concrete floor was wetted with water
before laying bricks. Column surfaces that contact with brick wall were chipped and a
grout paste was applied on that.
Verticality of brick wall should be checked while constructing. Mortar layers should be
10 mm in thickness but practically it was higher than that. That causes to over
consumption of cement and sand as I studied in my work study on brick work.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 30
Industrial training report
The walls will be carried out uniformly in all cases where the mature of the work admits
it. The work will not be built higher than 1.5m in a day. The courses will be kept
perfectly horizontal and every course will be checked for level and plump.
Bricks should be wetted with water before use in brickwork. If the bricks are not wetted
the brick will absorb all the water in mortar. So that no water will be left for hydration of
cement in the water.
The blocks should not be wetted before use. Wetting will produce moisture expansion in
the block, which will subsequently increase the shrinkage of the wall.
Verticality of walls is checked with the plumb bob and straight edge. In usual practice we
have certain restriction for the proper vertical alignment.
1. Un-uniformity brick sizes.
2. When aligning the top course of the brick, bottom brick alignment deviate.
3. Careless of masons and lack of supervision.
4. Tools error.
Construction of columns
Setting out for columns
Setting out for columns was done using theodolite and steel tape. Marking lines was done
using marking chord. It is very important to set out columns accurately otherwise they
can be buckle or fail due to excentric loads applied on them.
Laying kickers
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 31
Industrial training report
After setting out was done, kickers were laid in to 75 mm thickness. Steel kicker boxes or
plywood sheet boxes were used for its formwork. Grade 40 concrete was used there.
Curing kickers should be done at least for 7 days.
Reinforcement for columns
Overlapping and cranking main bars and tying stirrups into correct spacing are main
functions of column formwork. Column reinforcement and dimensions were different by
place to place according to loads applied on them. It should be checked whether correct
bar type is used, correct spacing were left between stirrups, lap length and crank length is
correct and good quality reinforcement is used. Column formwork required 30 mm
covering.
Lap length (LL) = D2 x 50
Crank length (CL) = (D1 + D2+ 5) x 10
Formwork for columns
Column formwork was fixed to kickers. Steel column boxes or formwork done by
plywood sheets were used. Sponge sheets were placed in joints of formwork to avoid
leakage of grout. Before fixing formwork internal surfaces of formwork were covered
with form oil. After fixing jacks and props, laying electrical conduits and placing cover
blocks were done. Then verticality of column formwork was checked. Checking
verticality was done at two edges of each face, to avoid twisting of column.
Concerting columns
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 32
Industrial training report
Existing surface of concrete should be made rough in order to have strong bond between
newly concreted part and older part. Existing surface was also wet with grout for same
purpose. Concreting was done using grade 25 machine-mixed concrete. Since free fall
height of concrete should not be higher than 1200 mm, each lift of column concreting
was not exceeded that height. Poker vibrator was used for compact concrete well.
Lap length & Crank length
Striking column formwork & curing
Column formwork was removed after a day (24 hr) from concreting. Then curing was
done for 7 days applying moist gunny bags.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 33
Industrial training report
Construction of beams and slab
Setting out for beams & slab
1000 mm height level of columns was marked on column surfaces. Level instrument was
used there. Level of beam bottom was marked using that level.
Formwork of beams and slab
Formwork for beam & Slab
Beam and column formwork was fixed using plywood sheets, 2” x 2” wooden bars,
galvanized iron pipes, separates, p-cones and form ties. Props were placed at 600 mm x
600 mm distances to support beam and slab formwork. A “U-head” was placed on each
prop and then galvanized iron pipes were laid horizontally and tied them. Power saw was
used for cutting plywood sheets and then fixed side boards for beams and formwork for
slab. Verticality of side boards and dimensions of formworks should be checked. Painting
form oil was done on formwork. HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 34
Industrial training report
Form ties, P-cones and separates were placed at 600 mm distance, after laying
reinforcement.
Reinforcement for beams and slab
Tor steel bars for beam reinforcement were re-bended and tied in another place. They
were placed on 2” x 2” wooden bars laid at beam formwork and they were jointed at
columns. They were lowered in to beam formwork after tying cover blocks. Slab
reinforcement was laid on slab formwork. Stools (bent tor steel bars) were placed to keep
space between top and bottom layers.
Slab & beam reinforcement; Stop board is set at 2/3 of span and sponge sheets
are used for prevent leakage.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 35
Industrial training report
Level check for beams & slab
Level check of slab & beams
Leveling the slab and beam formwork should be done after laying reinforcement.
Although slab and beams were fixed to right level, it can be deviated due to loads applied
and exposure to bad weather conditions. Level check is done using level instrument and
inverted staff.
According to the figure 2.2,
Instrument reading = b
Then,
1000 mm + a + b = (floor to floor height) - (thickness of plywood sheet) + 5 mm
b = [(floor to floor height) - (thickness of plywood sheet) + 5 mm- (1000 mm+ a)]
Jacks are tightened and loosen until slab and beams are leveled (until value “b” is
achieved). 5-mm clearance is left to be settled when laying concrete.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 36
Industrial training report
Concreting beams and slab
Concreting slab and beams was done using ready mix concrete. Supplier was ELS
Constructions (Pvt) LTD.
Ready mix concrete is used when concreting is done in large scale. Concrete is mixed at
batch plant and then transported to site by truck mixers with rotating drum. Pumping
concrete up to slab is done by a pump car. Slump test and preparing concrete cubes to test
compressive strength are done for concrete transferred by each truck mixer. Retarders
have been added to concrete not to be hardened until it is transported to the destination.
Generally pump car is provided with a flexible hose / pipe to drive concrete. A grout
mixer is driven through the pipe in order to lubricate the internal surface. Concrete should
be poured not to be segregated and should be compacted well and leveled in to relevant
thickness before it is hardened.
Advantages of ready mix concrete,
Labour associated with mixing concrete is saved.
There will not be wastage of basic materials.
Noise and dust pollution created at site is reduced.
Ready mix concrete has better quality.
Striking beam and slab formwork & curing
The striking time of formwork depends on type of cement, grade of concrete, dimension
of the section and the temperature of the concrete. High striking time requires in cold
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 37
Industrial training report
weather. Minimum striking time for side formwork of beams, under side formwork of
slabs according to its span is mentioned in table 2.1. Curing was done for slab and beams
for 7 days using moist gunny bags.
Sticking time of formwork
Type of formwork Striking time
Side formworks of beams, columns or
walls
24 hr
Slab formwork up to 4.5 m span 7 days
Slab formwork above 4.5 m span &
under side of beams up to 6 m span
14 days
Under sides of beams and arches over
6 m and up to 9 m span
21 days
Cantilever slab and beams 21 days
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 38
Industrial training report
Safety Procedures
Introduction
According to the Health and Safety Policy statement of the company there are
several objectives as follows
Preventing accidents
Maintaining site safety at reasonably high standards
Providing appropriate training to workers
Supplying adequate resources to work in safety
Auditing the effectiveness of the safety management system regularly
In the site there were workers with different educational and social levels.
Sometimes they got quick decisions which create huge accidents. An accident is an
unpredictable event or steps of events, with a result of a personal injury or property
damage. The situations and places which essential to insert risk analysis can be listed as
follows. It is the responsibility of the safety management board to minimize the risks of
this kind of situations.
1. Working at high places or confined places
2. Falling objects from high places
3. Working with fire
4. Preparing for a blasting operation
5. Working on temporary scaffolds and platforms
6. Using temporary access and ladders
7. Operating machinery with temporary electrical installations
8. Places of excavation
9. Working in underground
10. Using chemicals and hazards substances
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 39
Industrial training report
In this project the safety rules and regulation that the authorities have taken can be
categorized as general site rules, specific safety rules and personal protective equipments
and Safety Promotion and Communication Methods.
General site rules
Persons under 18 years old should not be employed in the site
At the site all the persons should wear safety helmets and other personal
protective equipments
Any person who enter to the site without permissions, is not allowed
No allowance to enter into confined places in the site without permissions
Using of alcohol, drugs are prohibited in the site
The working place and the environment should be cleaned
All persons in the site have same right to report any accidents, incidents or unsafe
conditions immediately
Specific safety rules
There were specific safety rules for special works like fire work, electrical work,
scaffolding work, welding work, machinery work, marine work, and works of confined
work etc. These rules should be communicated the relevant working people in a simple
manner. Following the safety rules are highly affected to minimize the accidents.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 40
Industrial training report
Personal protective equipments (PPE)
1. Safety helmet
All the persons who entered into the site and working areas should wear as a
protection against injuries to head from falling objects.
2. Eye goggles
It should be wear in the process of material grinding, chipping, and breaking.
3. Ear protectors
Ear protectors should be worn when participate the noisy operations above 85 dB
4. Safety shoes
Safety shoes and boots should be worn when instances like slab concreting is
going on, as the cement can adversely affect the human skin, when walking on grounds
having harmful particles such as unwanted nails, parts of steel bars etc.
5. Reflective vests
It should be worn the workers who are working in tunnels, near the temporary
roads, near to blasting places for easily identifications.
6. Gloves
Cotton gloves should be worn when operating and handling of general
equipments and materials.
PVC gloves should be used when handling of chemical substances.
Leather gloves should be used when handling of hot working processes
and machineries like drilling machines.
7. Face masks
When doing the operations like grinding, breaking processes or working at dusty
conditions masks should be worn.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 41
Industrial training report
8. Safety belts
It is a must when working in higher elevations.
Safety Promotion and Communication Methods
Safety notice boards
Safety posters
Safety warnings and alarm tones – specially in blasting operations
In addition to above methods the contractor of the project has been provided one
first aid box for every 50 workers in the site. And first aid box is placed accessible
location and has marked “FIRST AID”.
Financial Procedures
The financial procedure Of Sanken Lanka development project is Measure and
Pay method. They measure the quantities according to the standard drawings and pay
money according to the unit rates in BOQ.
I also involved in calculating quantities by referring relevant drawings. The
financial procedure of Tank farm project which is a simultaneous project of and
construction is Lump-sum method.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 42
Industrial training report
Financial matters were mainly conducted by store keeper under the inspection of site
engineer.
Payments for sub contractors
Work done by each sub contractor is measured and quantities are calculated. Prepared bill
for that quantity is sent to the base office and payment is done by the base office.
Petty cash payment
Expenditure for daily conduct of site is recorded and cash float is sent to base office with
bills. Generally cash float is sent when cumulative cost reaches to Rs. 25,000. Then the
payment is done from the base office.
Plant, equipment & machinery
Backhoe loader
Backhoe loader is a most commonly used engineering vehicle which can be used for
excavation of soil, light transportation of material, breaking asphalt etc. It consists of a
shovel in front side and a back hoe in back side. At work sites where I worked we hired
backhoe loaders when they were needed.
Concrete mixer
Concrete mixer is used to combine cement, water, fine aggregate (sand) and coarse
aggregate to form concrete. It is a portable machine driven by a diesel engine. Concrete
mixer contains of a revolving drum to mix components. Generally cement of one cement
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 43
Industrial training report
bag with aggregate and water in relevant proportions could be mixed in one turn to be
well mixed.
Vibrating rammer
Vibrating rammer is usually used for compact soil in small scale. The base plate at the
bottom vibrates when operating.
Vibrating rammer
Plate vibrator
Plate vibrator also used for compaction. But it doesn’t give heavy compaction strength as
vibrating rammer
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 44
Industrial training report
Angle grinder
Angle grinder can be practically used for many purposes such as grinding surfaces,
cutting steel bars, cutting tiles, wire brushing etc
Plate vibrator
Electric drill
Electric drill contains of removable bit from which drilling can be done. This can be used
for drill wood, concrete etc. Bits can be fixed according to the purpose.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 45
Industrial training report
Electric drill
Poker vibrator
Poker vibrator is a machine powered by petrol, and consists of a cable with vibrating
edge. Vibrating cable is put in to green concrete to be compacted it well.
Circular power saw
Power saw is an electric machine that is used for cutting wood. It consists of a rotating
serrated circular blade.
Bar cutter
Bar cutter is also an electric machine from which steel bars can be cut efficiently.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 46
Industrial training report
Bar cutter
Sander
Wooden surfaces can be grinded using sander. This also is an electric machine.
Sander
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 47
Industrial training report
Field Tests
a) Slump Test
The slump test was conducted to examine the workability of the concrete in fresh
stages. As the apparatus for the test, a conical shaped mould and a tamping rod were
used.
Slump Test Apparatus
The concrete was poured into the mould in three layers and 25 blows were applied
for each layer using the tamping rod. Then the mould was removed and let to concrete
behave itself. Then the decrease in the height of the center of the slumped concrete was
measured to nearest 5 mm as the slump value. According to the shape of the concrete
after removing the mould the slump was called as a true slump, shear slump and
collapsed slump.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 48
100mm
300mm
600mm
Mould
Tamping rod
200mm
Plate
Industrial training report
Laboratory Tests
There were several tests in the site laboratory which were done by the contractor’s
engineers.
a) Cube crushing
Casting tests cubes were conducted also in site laboratory at least one sets of
cubes for each continuous operation and any event of concreting more than 75 m3. I
examined the casting of cubes using vibrators. The moulds of 150 mm × 150 mm × 150
mm were used for casting cubes and vibrating period was 60 s for one set. Six cubes were
included for one set of cubes and they were marked at the same time. For identification of
the cubes the date casting, the grade of the concrete and a symbol to identify the relevant
concreting at the site were marked. After 24 hours of
casting the moulds were removed.
The testing of cubes was carried out after 7 days
and 28 days of casting using Cube Testing Machine
and with software called “Super Test 5”.
Using the software is very convenience to get
results quickly and accurately. It shows a relevant
graph of Time Vs Applied load for each cube. And it
also clearly indicates the crushing point of the cube.
As the results we can obtain the force applied (kN), force applying rate (kN/s),
strength of the concrete cube (MPa) and average strength.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 49
Cubes Testing Machine
Industrial training report
Concrete Core Testing
The Concrete Core Testing is done if there was an unexpected failure in test cubes
without reaching the required strength. Cylindrical core specimen with a diameter of
100mm and a depth of 100 mm are taken out from the hardened concrete of relevant
location. And it is examined and tested by engineers.
Some picture of On three20 site
Anti termite for Screed concrete
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 50
Industrial training report
Arrangement of column form work
Concrete curing
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 51
Industrial training report
Arrangement of form work for slab
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 52
Industrial training report
Applying form oil for beams
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 53
Industrial training report
Arrangement of form work for lift wall
Applying concrete for lift wall and stair case area HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 54
Industrial training report
Concrete chipping
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 55
Industrial training report
Arrangement of Slab reinforcement
D).Observations made:
Major delay cause in this project
Weather
Main problem sites was flood and heavy rain. Sometimes we couldn’t even reach
to the site due to flood.
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 56
Industrial training report
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 57
Industrial training report
Lack of labors
Lack of subcontractor’s skill
Design changes
Additional works / Quantity variation
Unclear site drawings supplied to the contractor
Lack of labor
Absence of consultant’s site staff.
Lack of experience on the part of the consultant.
F).Any problems encountered and solutions found:
Identification of weather pattern in the early stage of the project will help in
prepare accurate time schedules for the project work that might be affected due to
bad weather. The planer will be able to identify and sequence the activities
accurately. Also daily or weekly planning can be carried out according to the
weather pattern. For example finishing work and plastering work of a building
project can be carried out in rainy days while excavations work can be carried out
during dry periods.
To prevent frequent or late changes at critical stages of design and construction,
all parties involved must know what’s going on with each phase of the project.
With thousands of documents and pieces of correspondence that flow between
participants, it’s easy to have misunderstandings and errors. One way to keep HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 58
Industrial training report
track of everything is by having a collaborative information management system
that everyone involved has access to.
Ensure the document is easily understood and all points are clear. Once the
contract is drafted, ensure that the project team is familiar with all the details of
the contract and that everyone (contractor, client, financier, etc.) is fully aware of
their obligations. “As the work progresses, make certain that the procedural
requirements under the contract are followed,” Always Associates adds. The same
meticulousness for detail should be applied to plans and specifications.
Build an ideology for project manager, engineers, architects etc so that they can
recognize delay problems which will lead to large losses as well as the project
completion on time. Simultaneously, top management should establish a fair
reward and punishment policy which has to be strictly applied.
The working conditions should be improved gradually aiming at building proper
working atmosphere; this will help work done more effectively.
The human resource training towards professionalism in the management and
professional ethic improvement need to be set out and prioritized.
If the consultant’s managerial skill is weak; it is not be able to satisfy the size and
the demand of project. It is not only necessary to promote professionalism in the
work of quantity estimates and design, but also very strict in choosing the
consultant, designer and the basic of collecting consultant must rely on their
capacity. Simultaneously, the responsibility must be assigned to definite
individual.
Get early warning of delays due to the client. Client delays arise because they
change their minds, give their instructions too late or are slow in approving
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 59
Industrial training report
drawings etc. To overcome this issue contractor and client should have proper
coordination and understanding.
CONCLUSION
In retrospection of past 4 months when I had industrial training I think it was a precious
era of my life.
I was involved in three construction sites during the industrial training period. I think
each and every thing that I gathered there widened my knowledge and also my
experiences. I could realize the worth of practical knowledge against theoretical
knowledge. As it is not worthwhile theoretical knowledge without practical experiences,
it is also not worthwhile practical experiences without theoretical knowledge. There must
be a good combination of both those aspects to be a good civil engineer.
Being exposed to supervision of works done at site, doing setting outs etc, I could grasp
many things regarding technical side. I also could get a good practice on using theodolite
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 60
Industrial training report
and level instrument. Labour management at site and work studies improved the
management skills in to a considerable state.
I could recognize many people in the industry and also could realize the roles played by
persons from upper levels to the lower level of organization structure. I noticed about the
duties and responsibilities of each personnel in organization structure. I observed the
conduct of them, how they motivate personnel under them and how they carry out works.
Those good features may cherish my future career. Getting an idea about site engineer’s
role was important to me since I didn’t have a clear idea about that before.
Training site was a pleasant place for me since all the staff members treated me in a
friendly manner. The establishment denoted a good attitude on trainees. Site engineers
gave me valuable advices and helped to widen my knowledge. Work supervisors also
helped to gather experiences on technical aspects. Works that were given to me were
interesting. I was given freedom to learn there. It was trainee’s responsibility to get
maximum use of training period. Considering my own experiences, I recommend Sanken
construction (Pvt) Ltd as a good training establishment for future trainees.
I have got the real vision on civil engineering construction from this industrial training.
The experiences gained there, focused me to my future ambition – to be a salutary good
civil engineer and serve to my motherland. So I think arranging a training session at the
end of the level 2 is good since it will be a real motivation to undergraduates for their
further studies. If the semesters containing subjects relevant to construction management
were sandwiched between two industrial training sessions, it would be easy to grasp the
scope of those subjects.
In overall assessment regarding my industrial training, I can satisfy with things what I
have gained. Gained a good experience on technical matters and had an idea about site
management. It is very important to know the interaction between theory and its
application. Designing should be done through a good practical knowledge. I learnt many
things that should be grasped only through practical experiences.
I could capture the real picture of civil engineering construction during this period. As a
civil engineering undergraduate, I got an idea about WHAT should I practice and WHY
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 61
Industrial training report
should I do that. Good attitudes were created towards the industry. So the industrial
training period worthwhile to me as it gave me a confidence to fulfill my future ambitions
- to be a good civil engineer and also a salutary person to the country.
REFERENCE
Contract Document of the project
Method Statements
Drawings
Official web page of Sanken construction (Pvt) Ltd
Official web page of “On three20”
Official web page of Isuru Engineering (Pvt) Ltd
Lecture Notes of Soil Mechanic
HND/CV/MT/02/24 Higher National Diploma in Civil Engineering
International College of Business and Technology Page 62