Lincoln Public Schools Lincoln, Nebraska
Superintendent’s Facility Advisory Committee
Infrastructure & FinanceSession 3February 19, 2019
Lincoln Public Schools Lincoln, Nebraska
Provide historical expenditures of Operations Department.
Lincoln Public Schools Lincoln, Nebraska
2018 -2019 Operations Department BudgetBudget Salaries Percentage
Operations $36,773,730 $31,544,190 86%
• Custodial $20,720,010 $19,596,950 95%
• Maintenance/Facilities $16,053,720 $11,947,240 74%
Lincoln Public Schools Lincoln, Nebraska
Contracted Services BudgetFiscal Year Budget2008 – 2009 $ 1,865,7902009 – 2010 $ 1,898,8802010 – 2011 $ 1,809,3202011 – 2012 $ 1,809,3202012 – 2013 $ 1,809,3202013 – 2014 $ 1,764,2102014 – 2015 $ 1,764,2102015 – 2016 $ 2,014,2102016 – 2017 $ 2,014,2102017 – 2018 $ 2,109,7402018 – 2019 $ 2,309,740
Lincoln Public Schools Lincoln, Nebraska
Operations ExpendituresFiscal Year Bond / Building Funds2008 – 2009 $ 111,802,4772009 – 2010 $ 62,219,8562010 – 2011 $ 57,259,4682011 – 2012 $ 50,572,7362012 – 2013 $ 30,550,6792013 – 2014 $ 15,973,4122014 – 2015 $ 40,507,1952015 – 2016 $ 92,645,2212016 – 2017 $ 49,890,7662017 – 2018 $ 18,713,013
Lincoln Public Schools Lincoln, Nebraska
District Projects that Generate Operational Savings
Lincoln Public Schools Lincoln, Nebraska
District Projects that Generate Operational Savings• Lighting Upgrades• Building Shell Improvements
• Roofing Upgrades• Window Replacement
• Mechanical System Upgrades / Building Automation• Conventional Forced Air vs. Geothermal• Energy Recovery• Scheduling / Occupancy
Lincoln Public Schools Lincoln, Nebraska
IRVING MIDDLE SCHOOL
ORIGINAL BUILDING DATE:A/E:
SQUARE FEET:ORIGINAL BUILDING COST:
ADDITIONS:
IAQ PROJECT:IAQ PROJECT COST:
TOTAL SQUARE FEET:SITE:
1927MEGINNIS & SCHAUMBERG83,690$690,9721977 GYM / REC – 33,109 SQ FT1994 ADDITION – 34,172 SQ FT2016 IAQ/ADDITION – 523 SQ FT
2017$17,021,847222,8437.01ACRES
$0.54 per square footANNUAL UTILITY COST
Energy Star® Rating = 91Energy Star Score is a measure of performance relative to similar properties normalized for climate. Higher is better
EUI = 27Energy Use Intensity. Lower is better.
Lincoln Public Schools Lincoln, Nebraska
SCOTT MIDDLE SCHOOL
ORIGINAL BUILDING DATE:A/E:
SQUARE FEET:*ORIGINAL BUILDING COST:
ADDITIONS:
IAQ PROJECT:*IAQ PROJECT COST:
TOTAL SQUARE FEET:SITE:
1996an association of:BAHR, VERMEER & HAECKER andSINCLAIR HILLE & ASSOCIATES154,405$12,257,6302008 ADDITION – 4,850SQFT
NON/A165,84818.57 ACRES
$1.39 per square footANNUAL UTILITY COST
Energy Star® Rating = 51Energy Star Score is a measure of performance relative to similar properties normalized for climate. Higher is better
EUI = 59Energy Use Intensity. Lower is better.
Lincoln Public Schools Lincoln, Nebraska
Lighting Analysis2018 Calendar
Year GeneralSections Population Sq. Ft. Power & Light
• Rousseau ES (T8) 4 594 76,456 $ 26,564
• Wysong ES (LED) 4 494 77,143 $ 14,852
Lincoln Public Schools Lincoln, Nebraska
Provide detailed presentation of Infrastructure needs list.• How are needs prioritized?
Lincoln Public Schools Lincoln, Nebraska
LPS – Ten (10) Year Infrastructure Plan (v2)
12
Lincoln Public Schools Lincoln, Nebraska
LPS – Ten (10) Year Infrastructure Plan (v2)
13
Lincoln Public Schools Lincoln, Nebraska
Lincoln Public Schools Lincoln, Nebraska
Lincoln Public Schools Lincoln, Nebraska
Process
Lincoln Public Schools Lincoln, Nebraska
Process
Lincoln Public Schools Lincoln, Nebraska
Infrastructure Analysis – Building Envelope
Lincoln Public Schools Lincoln, Nebraska
Infrastructure Analysis – Building Envelope
Total Replacement Cost of Areas 15 Years or Older: $2,196,044
Lincoln Public Schools Lincoln, Nebraska
Infrastructure Analysis
Lincoln Public Schools Lincoln, Nebraska
Provide data on “Long Term” maintenance costs.
Lincoln Public Schools Lincoln, Nebraska
Lincoln Public Schools Lincoln, Nebraska
What is cost difference between New Construction and Renovation Costs• New Construction $260 square foot• Renovation $165 square foot