INFS 724 Project and Change Management Amit Deokar, Ph.D.
Transcript
Page 1: INFS 724 Project and Change Management

INFS 724 Project and Change Management

Amit Deokar, Ph.D.

Page 2: INFS 724 Project and Change Management

Chapter 9

Human Resource Management

Page 3: INFS 724 Project and Change Management

3

Outline

What is human resource management? Why? Motivation Human resource management processes

Human resource planning Acquiring the project team Developing the project team Managing the project team

Using software for human resource management

Page 4: INFS 724 Project and Change Management

What is human resource management? Why?

Page 5: INFS 724 Project and Change Management

5

The Importance of Human Resource Management People determine the success and failure of

organizations and projects Peopleware issues have more impact on software

productivity and software quality than any other factor For example, productivity of individual programmers

with similar levels of experience vary by a factor of at least 10 to 1

For entire teams, variations can be up to 5 to 1 NASA’s SEL concluded that technology is not the

answer, The most effective practices are those that leverage the human potential of their developers

Page 6: INFS 724 Project and Change Management

6

What is Project Human Resource Management? Project human resource management includes the

processes required to make the most effective use of the people involved with a project. Processes include Human resource planning: Identifying and documenting

project roles, responsibilities, and reporting relationships. Acquiring the project team: Getting the needed

personnel assigned to and working on the project Developing the project team: Building individual and

group skills to enhance project performance. Managing the project team: Tracking team member

performance, motivating team members, providing timely feedback, resolving issues and conflicts, and coordinating changes to help enhance project performance

Page 7: INFS 724 Project and Change Management

Motivation

Page 8: INFS 724 Project and Change Management

8

Maslow’s Hierarchy of Needs

Implication: PM should know something about team members’ professional and personal lives

Relevance for people working in

IT

Page 9: INFS 724 Project and Change Management

9

Maslow’s Hierarchy – Implication for management (Sommerville, 2001) Examples of satisfying social:

allowing people to meet their co-workers and providing places for them to meet

Examples of esteem social: Show people that they are valued, e.g., through public

recognition and that they are being paid at a level that respect their skills

Examples of self-actualization social: Assign demanding (but not impossible) tasks Provide training programs for people to develop

Page 10: INFS 724 Project and Change Management

10

Comparison of motivators for programmer analyst vs. managers and general population (McConnell, S., 1996)

Page 11: INFS 724 Project and Change Management

11

Top five motivation factors - Achievement Ownership “buy-in”: Let developers create

their own schedules Goal setting: explicitly setting ambitious, yet

realistic goals

Page 12: INFS 724 Project and Change Management

12

Top five motivation factors – Possibility for growth “The principle of career progression indicates that it is

in an organization’s best interest to help determine how its employees wish to grow professionally, and to provide them with career development opportunities in those directions” Barry Boehm (1981)

Examples of support: Provide tuition reimbursement Give time off to attend classes Assign developers to projects that will expand

their skill sets Assign a mentor to each new developer

Page 13: INFS 724 Project and Change Management

13

Top five motivation factors – Work itself Dimensions of work that motivates:

Skill variety Task identity Task significance Autonomy Job feedback (from carrying out the job itself)

Page 14: INFS 724 Project and Change Management

14

Top five motivation factors – Personal life An organization can:

Schedule projects realistically Respect vacations and holidays Be sensitive to occasional requests for time off

during work-days

Page 15: INFS 724 Project and Change Management

15

Top five motivation factors – Technical supervision An opportunity to supervise technical work

implies that the developer has achieved a level of technical expertise sufficient to direct others.

Examples: Assign each person on the project to be the

technical lead for a particular area Assign all, but the junior developers to be

mentors

Page 16: INFS 724 Project and Change Management

16

Other motivators

Rewards and incentives Pilot projects Performance reviews

Source:McConnell, 1996

Page 17: INFS 724 Project and Change Management

17

Herzberg’s Motivational and Hygiene Factors (Morale killers) Frederick Herzberg wrote several famous

books and articles about worker motivation. He distinguished between motivational factors: achievement, recognition,

the work itself, responsibility, advancement, and growth, which produce job satisfaction

hygiene factors (moral killers): cause dissatisfaction if not present, but do not motivate workers to do more.

Examples include larger salaries, more supervision, and a more attractive work environment

Page 18: INFS 724 Project and Change Management

18

Examples of Hygiene Factors (Morale killers) for developers Working environment

Privacy Outside awareness (natural light with a view) Personalization Appropriate lighting, heating, and air conditioning Adequate desk and shelf space

Access to office equipment Readily available office supplies Freedom to set work hours Up-to-date computing equipment Applicable reference manual and trade publications

Page 19: INFS 724 Project and Change Management

Human resource planning

Page 20: INFS 724 Project and Change Management

20

Human resource planning

Human resource planning involves identifying, documenting, and assigning project roles, responsibilities, and reporting relationships

Outputs and processes include project organizational charts work definition and assignment process responsibility assignment matrices (RAM) resource histograms

Page 21: INFS 724 Project and Change Management

21

Sample Organizational Chart for a Large IT Project

Page 22: INFS 724 Project and Change Management

22

Work Definition and Assignment Process

Page 23: INFS 724 Project and Change Management

23

Responsibility Assignment Matrices A responsibility assignment matrix (RAM) is a

matrix that maps the work of the project, as described in the WBS, to the people responsible for performing the work, as described in the OBS.

Can be created in different ways to meet unique project needs.

Page 24: INFS 724 Project and Change Management

24

Sample Responsibility Assignment Matrix (RAM)

Page 25: INFS 724 Project and Change Management

25

RAM Showing Stakeholder Roles

Page 26: INFS 724 Project and Change Management

26

Staffing Management Plans and Resource Histograms A staffing management plan describes

when and how people will be added to and taken off the project team.

Often part of the project management plan (refer Chapter 4)

A resource histogram is a column chart that shows the number of resources assigned to a project over time. (part of the staffing management plan)

Page 27: INFS 724 Project and Change Management

27

Sample Resource Histogram

Page 28: INFS 724 Project and Change Management

Acquiring the project team

Page 29: INFS 724 Project and Change Management

29

Acquiring the project team

Staffing plans and good hiring procedures are important in staff acquisition, as are incentives for recruiting and retention

Some organizations allow people to work from home as an incentive

Research shows that people leave their jobs because: they don’t make a difference, don’t get proper recognition, aren’t learning anything new, don’t like their coworkers, and want to earn more money

Page 30: INFS 724 Project and Change Management

30

Five principles of software staffing (Boehm, 1981) Top talent

Use fewer and better people Job matching

Fit the tasks to the skills and motivation of the people Career progression

Help people self-actualize Team balance

Select people to complement each other Misfit elimination

Replace problem team members as quickly as possible

Page 31: INFS 724 Project and Change Management

31

Resource Loading

Resource loading refers to the amount of individual resources an existing project schedule requires during specific time periods

Resource histograms show resource loading Overallocation means more resources than

are available are assigned to perform work at a given time

Page 32: INFS 724 Project and Change Management

32

Sample Histogram Showing an Over-allocated Individual

Page 33: INFS 724 Project and Change Management

33

Resource Leveling

Resource leveling is a technique for resolving resource conflicts by delaying tasks

The main purpose of resource leveling is to create a smoother distribution of resource usage and reduce over-allocation.

Benefits include: When resources are used on a more constant basis,

they require less management. It results in fewer problems for project personnel and

the accounting department. It often improves morale.

Page 34: INFS 724 Project and Change Management

34

Resource Leveling Example

Page 35: INFS 724 Project and Change Management

Developing the project team

Page 36: INFS 724 Project and Change Management

36

Team Development

It takes teamwork to successfully complete most projects

Training can help people understand themselves, each other, and how to work better in teams

Team building activities include physical challenges psychological preference indicator tools

Page 37: INFS 724 Project and Change Management

37

Myers-Briggs Type Indicator (MBTI)

MBTI is a popular tool for determining personality preferences and helping teammates understand each other

In total, you have 16 personality types

http://www.humanmetrics.com/cgi-win/JTypes2.asp

Extrovert (E): Draws energy from other people

Introvert (I): Draws energy from inside

Sensation (S): Take in fact, detail, and reality

Intuition (N): Imaginative, ingenious, and attentive to intuition

Thinking (T): Objective and logical

Feeling (F): Subjective and personal

Judgment (J): Structured

Perception (P): Less structured

Page 38: INFS 724 Project and Change Management

38

MBTI for IS professionals

NTs are classified as rational.

They tend to be attracted to technology fields

No more than 7% of the population are rational

Implication are clear: To appeal to IT people,

use logical arguments By knowing your team

members’ MBTI profile, you can adjust your management style for each individual

ISGeneral population

E/I 75% are I 25% are I

S/N 55% are N 25% are N

T/F 80% are T 50% are T

J/PSlightly > 50% are J

Slightly > 50% are J

Page 39: INFS 724 Project and Change Management

Managing the project team

Page 40: INFS 724 Project and Change Management

40

Managing the Project Team

Project managers must lead their teams in performing various project activities.

After assessing team performance and related information, the project manager must decide: If changes should be requested to the project. If corrective or preventive actions should be

recommended. If updates are needed to the project

management plan or organizational process assets.

Page 41: INFS 724 Project and Change Management

41

Tools and Techniques for Managing Project Teams Observation and conversation Project performance appraisals Conflict management Issue logs

Page 42: INFS 724 Project and Change Management

42

Reward and Recognition Systems

Team-based reward and recognition systems can promote teamwork

Focus on rewarding teams for achieving specific goals Allow time for team members to mentor and help each

other to meet project goals and develop human resources

Page 43: INFS 724 Project and Change Management

43

General Advice on Teams

Focus on meeting project objectives and producing positive results

Fix the problem instead of blaming people Establish regular, effective meetings Nurture team members and encourage them

to help each other Acknowledge individual and group

accomplishments

Page 44: INFS 724 Project and Change Management

44

Using Software to Assist in Human Resource Management Software can help in producing RAMs and

resource histograms Project management software includes

several features related to human resource management such as viewing resource usage information identifying under and overallocated resources leveling resources

Page 45: INFS 724 Project and Change Management

45

Resource Usage View from Microsoft Project

Page 46: INFS 724 Project and Change Management

46

Resource Usage Report from Microsoft Project