Inman Middle School774 Virginia Avenue
Project Overview
March 25, 2010
Facilities Services Department
January 21, 2014
Project Description
• Grades: 6 – 8
• Site Size: +/- 4.2 acres (not including the Field of Dreams)
• Student Capacity: +/- 1,050 @ 25 students per classroom
• Core Classrooms: +/- 42
• Total Classrooms: +/- 62
• Approximate Size: +/- 186,428 sf (161,428 existing + +/-25,000 sf addition)
• Tentative Schedule: December 2014 – July 2016
• Construction of new Classrooms and support spaces
• Renovation of and expanded seating at Gymnasium
• Improved Administration Area and Entry Security
• Select Renovations in the Existing Building
• Reconfigured parking, drop-off and bus cueing areas
• Renovated Multi-Purpose Sports Field
• Fencing and hardscape improvements
• Site, storm water management and landscaping improvements
Project Timeline
• Select Architect: October 7, 2013
• Design Kick Off Meeting October 16, 2013
• Design Review Meeting November 11, 2013
• Project Committee Meeting #1: January 21, 2014
• Begin Draft Design Narrative January 21, 2014
• Preliminary Submittal to GDOE TBD
• Internal Design Review 1 TBD
• Project Committee Meeting #2 March 2014 (tentative)
• AUDC Submittal TBD
• Internal Design Review 2 TBD
• Project Committee Meeting #3 TBD
• Check Set Submittal to GDOE TBD
• Request for Proposal out to CMs TBD
• Final Submittal to GDOE TBD
• Recommend CM to Board TBD
• Project Committee Meeting #4 TBD
• Project Start December 2014 (tentative)
• Project Completion July 2016 (tentative)