+ All Categories
Home > Documents > Innovations in transport and installation methods

Innovations in transport and installation methods

Date post: 12-Feb-2016
Category:
Upload: gerry
View: 21 times
Download: 0 times
Share this document with a friend
Description:
Innovations in transport and installation methods. Henrik Fomsgaard Lynderup September 2009. Future trends in offshore wind energy. Larger projects. More projects installed per year. Financing and equipment availability are key challenges. Large projects are stretched over more seasons. - PowerPoint PPT Presentation
8
© Siemens Wind Power A/S. All rights reserved Innovations in transport and installation methods Henrik Fomsgaard Lynderup September 2009
Transcript
Page 1: Innovations in transport and installation methods

© Siemens Wind Power A/S. All rights reserved

Innovations in transport and installation methodsHenrik Fomsgaard LynderupSeptember 2009

Page 2: Innovations in transport and installation methods

© Siemens Wind Power A/S. All rights reserved

Future trends in offshore wind energy

More projects installed per yearLarger projects

Page 3: Innovations in transport and installation methods

© Siemens Wind Power A/S. All rights reserved

Financing and equipment availability are key challenges

Large projects are stretched over more seasons Financing becomes more difficult

More projects each year More competition for ports and vessels

Page 4: Innovations in transport and installation methods

© Siemens Wind Power A/S. All rights reserved

The solution is simple!

By optimized installation methods By pre-commissioning onshore

Requires specialized vessels

Requires flexible start dates

Faster project execution

Year-round operations

Staggered projects

Page 5: Innovations in transport and installation methods

© Siemens Wind Power A/S. All rights reserved

Minimizing offshore work is a good idea!

% man hours used onshore

Cost index for installation, commissioning and testing

10 20 30 40 50 60 70 80 90 100

0,1

0,2

0,3

0,4

0,5

0,6

0,7

0,8

0,9

1,0Siemens approach today

Fully-assembled offshore

Fully-assembled onshore

Page 6: Innovations in transport and installation methods

© Siemens Wind Power A/S. All rights reserved

It all links together…

Fully assembled turbines in the port

Specialized quay and equipment

An accessible market

Minimum 250 turbines per year in 5 years within reach

Specialized vessels with 350 Nm reach

High utilization to minimize price

Page 7: Innovations in transport and installation methods

© Siemens Wind Power A/S. All rights reserved

Serial assembly at the quay wall

A centralized setup will improve efficiency

Page 8: Innovations in transport and installation methods

© Siemens Wind Power A/S. All rights reserved

Specialized vessels are required to increase volumes and utilization

Faster More WTGs on board Less weather-sensitive

Larger volume in port

Source: Beluga Hochtief Offshore High utilization of vessel and port

Specialized vessels

Sea Installer

Larger range from port

Year-round installation

Source: A2SEA


Recommended