Innovative Delivery Systems for Bridge Preservation Contracts
Transcript
Page 1: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

Innovative Delivery Systems for Bridge Preservation Contracts

Page 2: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget
Page 3: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

CM/GC Construction Manager/General Contractor

Owner Construction

Manager Designer

Owner, Designer, & CM collaboratively work to

develop project scope, optimize the design,

improve quality, manage costs, and deliver

projects early & under budget 3

Page 4: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget
Page 5: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

You are a victim of the rules you live by.

- Jenny Holzer

Page 6: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

adversarial

relationships

Page 7: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

disputes and

change orders

Page 8: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

delays and claims

Page 9: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

high risk

Page 10: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

no incentive for innovation

Page 11: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

loss of control

Page 12: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

STRESS!

Page 13: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

late and over budget projects

Page 14: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget
Page 15: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

Connection

Page 16: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget
Page 17: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

Why Change Systems

“Management actions are responsible for 85% of all problems.”

- W. Edwards Deming

Union of Japanese Scientists and Engineers Managing Director Kenichi Koyanagi, and

W. Edwards Deming

Page 18: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget
Page 19: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

You can’t justify CM/GC for bridge

preservation projects…just use

low bid or design build.

Page 20: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

Pennywash Creek Bridge CM/GC delivery method

5 week delivery – 1 week ahead of schedule

10% under initial budget

Designed around pre-fab girder

No claims, no change orders

Kemper Road Bridge Low- Bid system

5 week delivery – 1 month behind schedule

30% over budget

Change orders and claims during construction

Page 21: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

Parker Bridge – Palm Beach $10M Saved ~ 1.5M

Successful collaboration with USCG & N. Palm Beach & 3rd Parties

$177K in unused Contingency

Significantly Reduced Original Closure Times

FDOT / PCL BASCULE BRIDGES

Page 22: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

Atlantic Blvd – Broward $4M

Saved ~ $275k

~40k in unused contingency

Significantly Reduced Closures

Extensive Innovations

Successful collaboration with USCG & Pompano Beach

FDOT / PCL BASCULE BRIDGES

after

Page 23: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

23

Page 24: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

0

0.2

0.4

0.6

0.8

1

1.2

Design-Bid-Build CM/GC Design-Build

Contingencies & Allowances

Overruns & Change Orders

Base Cost

100%

13%

106% 84%

4%

4%

Award Award

GMP

24

Page 25: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

The opposite of courage in our society is not cowardice,

it is conformity - Rollo May

“It’s Too Much

Work for the

Benefit”

Page 26: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget
Page 27: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

Sir Roger Gilbert Bannister

"We are too young to realize that certain things are

impossible... So we will do them anyway."

— William Wiberforce

27

Page 28: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

28

RFP

Award

Design

Construction

Design

RFP

Design Build

Traditional Design Bid Build

Early Construction Selection of both Designer and Builder

CM/GC Design

Early Construction Selection of both Designer and CM

Construction

Construction

Page 29: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

“THINKING is hard work. It’s Why So Few People Do It.” - Henry Ford

Page 30: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

Bitter Creek Bridge Grand County , Utah

100% Plans

Originally slated for full replacement at $4.0 M

Resulted in simple bridge girder repair

Final cost was $400 K

30

Page 31: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

“IT’S RISKY BRINGING

A CONGRACTOR IN

THAT EARLY” 31

“It’s Risky Bringing in

a Contractor that

Early”

Page 32: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

32

Total Risk

Contractor Risk

Contractor Risk Agency Risk

Agency Risk

D-B-B CM/GC D-B

Page 33: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget
Page 34: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

1. Innovation

2. Reduction of Risk

3. Aggressive Delivery

4. Cost Control

5. Team Selection

6. Constructability

7. Streamlined Plans

8. Quality

9. Early Work Packages

10. Flexibility in Changing Project Scope 34

Page 35: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget
Page 36: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

“Take the first step in faith. You don’t have to

see the whole staircase. Just take the first

step” - Martin Luther King JR.

Page 37: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget

Kenneth E. Atkins, P.E.

[email protected]

(720) 963-3416

Lakewood, CO

Gregg A. Hostetler, P.E.

[email protected]

(405) 227-0531

Edmond, OK

QUESTIONS