BY JOHN H. O’KUMA BY JOHN H. O’KUMA AUGUST 20-25, 2000 AUGUST 20-25, 2000 INNOVATIVE RADIATION TOLERANCE DMSMS MANAGEMENT INNOVATIVE RADIATION TOLERANCE DMSMS MANAGEMENT DMSMS Conference 2000
Transcript

BY JOHN H. O’KUMABY JOHN H. O’KUMA AUGUST 20-25, 2000AUGUST 20-25, 2000

INNOVATIVERADIATION TOLERANCEDMSMS MANAGEMENT

INNOVATIVERADIATION TOLERANCEDMSMS MANAGEMENT

DMSMSConference

2000

JUNE_6_00

OUTLINEOUTLINE

=DMSMS=Background=What Is RTA?=RTA DMSMS=Defining the Problem=Solution What is RTASSC?

Essential Element - Partnerships RTA’s DMSMS And RT DMSMS Approach

RTA DMSMS ElementsSolutions ToolsRTASSC ProcessRTA Certification EvolutionMonitoring and Tracking System

=Summary=Conclusion

JUNE_6_00

BACKGROUNDBACKGROUND PIECE-PART FACTS PIECE-PART FACTS

Basically, Every Type Of QML Device And An Ever Increasing Number Of COTS DevicesAre Used In Military Platforms, Systems And Equipment.

Most Of These Same Devices Are Classified as Hardness Critical Items (HCIs) and Used InNuclear Survivable Platforms, Systems And Equipment; However,u < 2% Of All HCIs Are Radiation Hardened/Tolerant and Guaranteed By

the Device Manufactureru > 98% Of All HCIs Are Classified as Radiation Tolerance (RT) and

Evaluated By An Independent Radiation Test Facility.In Contrast; HCIs for Most Space and Missile Platforms, Systems and Equipment,

u > 60% Of All HCIs Are Radiation Hardened/Tolerant and Guaranteed By the Device Manufacturer

u < 40% Of All HCIs Are Classified as Radiation Tolerance (RT) and Evaluated By An Independent Radiation Test Facility.

u This Ratio is Shifting Towards Greater Usage of RT Devices

All RT Devices are DMSMS Candidates

JUNE_6_00

BACKGROUNDBACKGROUNDRADIATION TOLERANCE FACTORRADIATION TOLERANCE FACTOR

Basically, Every Type Of QML Device And An Ever Increasing Number Of COTS Devices AreUsed In Military Platforms, Systems And Equipments That are Nuclear Survivable

Each RTA Device Is RT Certified, Usually Through A Detailed Characterization-Test-Qualification- (CTQ) Process

CTQ Process Basically “Discovers” The inherent RT Hardness Level Of Each ProposedManufacturer’s Device

RT Assured Means RT Threshold of A Manufacturing Process is Known and Meets Requirementwith Adequate Safety Margin

Critical: RTA Certification Is Actually On A Manufacturer’s Process, Therefore: RT Thresholds Are Very Process Dependent

RT Thresholds Are Process Consistency DependentNo Intrusive Process Controls Allowed“Controls” Driven By Market And Efficiencies - NOT RT

Each RTA Certified Process Must Be:Monitored (30 Day Cycle)Assessed Prior to Each Procurement

JUNE_6_00

WHAT IS RTA?RADIATION TOLERANCE ASSURED

WHAT IS RTA?WHAT IS RTA?RADIATION TOLERANCE ASSUREDRADIATION TOLERANCE ASSURED

RTA is Not Radiation Hardness AssuredRTA is a Methodology Based Upon Knowledge of the Inherent RT

Hardness Level Possessed by a Microelectronic Device’s ProcessRTA is a Methodology Used To Achieve Nuclear Survivability inTactical Platforms, Systems and Equipments

=Evolved Over 20 Years On Many Different Army Systems=Designed for “Cradle-To-Grave” Nuclear Survivability

Enables Effective “Cradle-to-Grave” DMSMS And RT DMSMSManagement

Originally, used for Design, Production and MaintenanceNow, used for DMSMS and Sustainment in addition to above

Key: Partnerships

JUNE_6_00

RTA DMSMSRTA DMSMS

RTA Devices Can Become RTA Obsolete Only, Due to ProcessAlterations

Known or Unknown Process or Design ChangeKnown or Unknown Yield or Performance EnhancementsInadequate Quality Control

Any of Above Alterations Can Drastically Reduce RT ThresholdsEffectively Making the Device Obsolete Even Though Available

Usually, Users Unaware of “MINOR” Process Alterations Some ofWhich Degrades Thresholds

Probability of a Process Alteration Occurrence Has Been IncreasingDue to Scaling, COTS Usage, and Economies

Probability of Resulting RTA Impact Has Also IncreasedDramatically

BOTTOM LINE: All Device That Become DMSMS Become RT DMSMS All Devices That Become RT DMSMS Do Not Become DMSMS

JUNE_6_00

DEFINING THE PROBLEMDEFINING THE PROBLEMDESIGNDESIGN

5-10 YRS.

UTILIZE MOSTLYMATURE TECHNOLOGIES

ALREADY 3-5 YRS OLD

LIMITED DESIGN FLEXIBILITY FOR FUTURE

INSERTIONS RTA, COTSTECHNOLOGY, AND DMSMS INSERTIONS

LIMITED COORDINATIONBETWEEN PARTICIPANTS

BOTTOM LINE: OBSOLESCENCE DESIGNED INTO SYSTEM.

RESULT: 1 - 2 OBSOLESCENCE CYCLES DURING DESIGNRESULT: 2 - 4 RT OBSOLESCENCE CYCLES

NEW FACTORS DMSMS PROCESS ALTERATIONS COTS TECHNOLOGY CHANGES

JUNE_6_00

DEFINING THE PROBLEMDEFINING THE PROBLEMPRODUCTIONPRODUCTION

BOTTOM LINE: OBSOLESCENCE BECOMES AN INTEGRAL PART OF PRODUCTION AND IS BUILT INTO SYSTEM’S CONFIGURATION

1-4 OBSOLESCENCE CYCLES DURING PRODUCTION2-9 RT OBSOLESCENCE CYCLES

RESULT:

LOW RATE PRODUCTION 5-25

LIMITEDCOORDINATIONBETWEEN ALLPARTICIPANTS

SEVERAL CAPABILITYENHANCEMENTS/ADDITIONS

NEW FACTORS DMSMS PROCESS ALTERATIONS COTS TECHNOLOGY CHANGES

SEVERAL UPGRADESDURING PRODUCTION LIMITED FLEXIBILITY

FOR FUTURE COTS,TECHNOLOGY, RTA AND

DMSMS INSERTIONS

JUNE_6_00

DEFINING THE PROBLEMDEFINING THE PROBLEMDEPLOYMENTDEPLOYMENT

BOTTOM LINE: MAJOR OBSOLESCENCE AND RT OBSOLESCENCE PROBLEMS THROUGHOUT DEPLOYMENT

6-13 OBSOLESCENCE CYCLES DURING DEPLOYMENT14-33 RT OBSOLESCENCE CYCLES

RESULT:

LIMITEDCOORDINATIONBETWEEN ALLPARTICIPANTS

NEW FACTORS DMSMS PROCESS ALTERNATIONS COTS TECHNOLOGY RATES

BUILT-IN LIMITED FLEXIBILITY FOR FUTURE TECHNOLOGY, COTS , RTA,

AND DMSMS INSERTIONS

LONGER DEPLOYMENTS;WAS 20 YEARS

NOW 40-83 YEARS

UPGRADE/MODERNIZATION

CYCLES, WAS 1NOW 6-10

MULTITUDE OFCAPABILITY

ENHANCEMENTS/ADDITIONS

MODERNIZATION-THROUGH-SPARES

JUNE_6_00

SOLUTIONSOLUTION

SYSTEM PRODUCTION/DEPLOYMENTSYSTEM PRODUCTION/DEPLOYMENTPARTNERSHIPS WITH OTHER GOVERNMENT PROCURING ACTIVITIES PLUS ABOVE MEMBERS AREMAINTAINED THROUGHOUT THE SYSTEM’S LIFE CYCLE, WHICH ASSURES RTA PRODUCT AVAILABILITY ANDPROVIDES FOR MANAGEMENT OF COSTS AND DMSMS, WHILE ASSURING NUCLEAR SURVIVABILITY.

SYSTEM DESIGNSYSTEM DESIGNPARTNERSHIPS ARE ESTABLISHED FOR THE PURPOSE OF DEVELOPING A PRODUCIBLE, SUSTAINABLE,UPGRADEABLE AND SUPPORTABLE NUCLEAR SURVIVABLE SYSTEM.

OTHER GOVERNMENTPROCURING ACTIVITIES

CONTRACTORS/SUB-CONTRACTORS

DEVICE MANUFACTURERS/ASSEMBLY FACILITIES AND DISTRIBUTORS

RTASSC

GOVERNMENT

CONTRACTORS/SUB-CONTRACTORS

DEVICE MANUFACTURERS/ASSEMBLY FACILITIES AND DISTRIBUTORS

RTASSC

GOVERNMENT

JUNE_6_00

WHAT IS RTASSC?WHAT IS RTASSC?WHAT IS RTASSC?

Genesis of the Radiation Tolerance Assured Source and Supply Center (RTASSC) is1980 with the Initiation of the Life-Cycle Nuclear Survivability Program at WhiteSands Missile Range. Now, RTASSC Is a Full Service Center Dedicated toprovisioning of Certified RTA Standard and Custom Semiconductors and HigherLevels of Assembly Used in Military and Space Systems.

The RTASSC Utilizes primarily the RTA Methodology to Achieve Nuclear andSpace Survivability

The RTASSC Develops Partnerships With Program Offices, Contractors and Sub-contractors, Device Manufacturers, Distributors, Third Party Manufacturers andTesting Facilities, and Other Government Agencies for the Sole Purpose ofdesigning, producing, maintaining and sustaining Nuclear and Space SurvivableSystems.

RTASSC supports the entire life-cycle of Nuclear and Space Survivable SystemsRTASSC IS A DMSMS SOLVER! AND RT DMSMS SOLVER!

JUNE_6_00

Ben

efit

s

Assures ProductAvailability

Manages DMSMSand RTA DMSMS

Reduces System Costs

Increases Confidence inSurvivability, Reliability& PerformanceFenced Long TermStorage

Promotes theMTS Concept

Manages Insertionsand Changes

PARTNERSHIPSPARTNERSHIPS

WSDsAdded

RT/RHCertified

PartsRTASSC

PROGRAM OFFICESGOVERNMENT AGENCIES

PROGRAM OFFICESGOVERNMENT AGENCIES

CONTRACTORSCONTRACTORSSUB-CONTRACTORSSUB-CONTRACTORS

SUPPLIERSSUPPLIERS

DEFENSE SEMICONDUCTORASSOCIATION (DSA)

DEFENSE SEMICONDUCTORASSOCIATION (DSA)

DEVICE MANUFACTURERSDEVICE MANUFACTURERSDISTRIBUTORSDISTRIBUTORS

ASSEMBLY FACILITIESASSEMBLY FACILITIES

JUNE_6_00

AS42C

4064-12/883CA

S42C4064-12/883C

AS42C

4064-12/883CA

S42C4064-12/883C

AS42C

4064-12/883CA

S42C4064-12/883C

AS42C

4064-12/883CA

S42C4064-12/883C

RTACCS/SEi PartnershipRTACCS/SEi PartnershipVideo Random Access Memory (VRAM)Video Random Access Memory (VRAM)

256K X 3274 LEAD PIN GRID ARRAY

Cost = $3000.00

This Module Replaces theConfiguration Shown BelowAnd:n Is a Form-Fit-FunctionDirect Replacement,Designed By SpaceElectronics Inc..

n Is Radiation Tolerant Certified to 3K rads Total Dose and5x1012 n/cm2 by the RTASSC on a White Sands Drawing.n W99M55166 (PIN # W99M5516601EPX).n Has 4 times the memory at twice the access speed.

n Is 1/3 the cost of the presentconfigurationn Is Truly a DMSMS and an RTDMSMS success story.

Circuit Card Assembly(CCA)

for ABRAMS M1A2Tank

8 X 64K X 424 LEAD DUAL IN-LINE PACKAGES

Cost = 8 x $800 =$6400.00

JUNE_6_00

Goal: Prevent DMSMS Problems Manage Life-Cycle DMSMS Provide Life-Cycle Solutions

RTA’S DMSMS AND RT DMSMSAPPROACH

RTA’S DMSMS AND RT DMSMSRTA’S DMSMS AND RT DMSMSAPPROACHAPPROACH

Overall, Proactive Approach That Can Be As Reactive AsNecessary

Proactive Centerpiece Is Integrated Roadmaps Derived From:Technology Migration And Growth Roadmaps Per

ManufacturerSystem’s Technology And Growth RoadmapsDMSMS Trends Per Manufacturer And OverallRTA And RTASSC DatabasesCommercial DatabasesWSD And Monitoring Database

JUNE_6_00

DMSMS AND RT DMSMSDMSMS AND RT DMSMS SOLUTION TOOLS SOLUTION TOOLS

In the event of DMSMS or RT non-conformance/discontinuation,RTASSC will recommend one or more of the following solutions:

a. Available Parts A form-fit-function (f3) insertion of a newer technology:

Same manufacturer Alternate manufacturer

f3 Replacement from an alternate manufacturer. A non form-fit-function (nf3) insertion of a newer technology:

Same manufacturer Alternate manufacturer nf3 Replacement from an alternate manufacturer GEMb. Wafer or Die (storage)c. Minor Circuit Re-designd. Design Consolidation/Upgrade

JUNE_6_00

e. Third Party ManufacturingThe RTASSC has Partnerships with Third Party QML Manufacturing Companies.

Die Mounting.Environmental Testing (MIL-STD-883, Methods A, B, C, and D).New design OptionNew Technology OptionCustom Testing (temperature, vibration, etc.)GEMRTA CertificationElectrical Specification CertificationEmulationReverse Engineering and Manufacturing (consolidation/upgrade)

DMSMS AND RT DMSMSDMSMS AND RT DMSMSSOLUTIONS TOOLSSOLUTIONS TOOLS

Continued -

JUNE_6_00

RTA-CTQ Process FlowRTA-CTQ Process Flow

Co-located SemiconductorTest Laboratory

CUSTOMER APPROVALDEVICE

POST-TEST(DATA

EVALUATION)

PRE-TEST(EVALUATION)

REVISIONS

LTR DESCRIPTION DATE (YR-MO-DA) APPROVED

INITIAL RELEASE 98-03-18

CONVERSION OF WSD (SHORT FORM) TO WSD (FULL FORM) 98-12-03

HITE SANDS DRAWINGCONTRACT NUMBER

1-VC-080-1A2-036SS OTHERWISE SPECIFIEDNSIONS ARE IN INCHESRANCES ONCES 3 PLACES ±

CONTRACTOR

CMDR, USAWSMRSTEWS-DT-AWSMR,NM 88002

Microcircuit, Linear, High Common-ModeRejection Differential Line Receiver,Monolithic Silicon

PREPARED BY DATE (YR-MO-DA)Lawrence S.N. Wang 98-12-03

CHECKED BYRoger Sloan

ENGINEERM. Klein

DRAWING APPROVALJohn H. O’kuma

SIZE

ACAGE CODE

09WF0 W98M2141DESIGN APPROVAL

Jim NicklausSHEET 1 OF 12

WSDPOST

IRRADIATIONTABLE

Co-located SemiconductorTest Laboratory

Gamma Total Dose (Co60)50 - 300 Rads/(Si)sec

Gamma Total Dose(Co60)

.01 - 300 Rads/(Si)sec

Neutron (Fast Burst Reactor)Fluence 10E14n/cm2

SIMULATION

Linear Accelerator (LINAC)Dose Rate 1E6-1E12Rads/Si sec

ASSESSMENT(DESIGN MARGIN)

CHARACTERIZATION TEST QUALIFICATION

JUNE_6_00

WSD DOCUMENTATIONWSD DOCUMENTATION

A White Sands Drawing (WSD) is prepared for each RT HCI, CCA orSRU

WSDs Follows SMD Format Plus:

RTASSC listed as Source of Supply

RT Table

WSD Package Includes

WSD

Certificate of Conformance to Manufacturers Specifications

Certificate of Conformance for RTA

All RTA Certified Products are Supplied to White Sands Drawings(WSDs)

WSDs are Stock Listed By DLA (To Establish Usage Data)

JUNE_6_00

DOCUMENTATIONDOCUMENTATIONWSDs FOR HCIsWSDs FOR HCIs

=Radiation Tolerance Assured performancebased documents.

=Describe Commercial, Industrial, andMilitary Grade Electronic Devices.

=Accepted by the Government and theElectronics Industry.

=The RTASSC Certifies all products listedin the WSDs to the RTA levels specifiedwithin.

=All Sources of Supply are audited andapproved by the RTASSC.

=Provides Process Monitoring

=Manufacturer’s performancespecifications are included

=RTASSC is Approved Source of Supply

REVISIONS

LTR DESCRIPTION DATE (YR-MO-DA) APPROVED

INITIAL RELEASE 98-03-18CONVERSION OF WSD (SHORT FORM) TO WSD (FULL FORM) 98-12-03

HITE SANDS DRAWINGCONTRACT NUMBER

1-VC-080-1A2-036SS OTHERWISE SPECIFIEDNSIONS ARE IN INCHESRANCES ONCES 3 PLACES ±

CONTRACTOR

CMDR, USAWSMRSTEWS-DT-AWSMR,NM 88002

Microcircuit, Linear, High Common-ModeRejection Differential Line Receiver,Monolithic Silicon

PREPARED BY DATE (YR-MO-DA)Lawrence S.N. Wang 98-12-03

CHECKED BYRoger Sloan

ENGINEERM. Klein

DRAWING APPROVALJohn H. O’kuma

SIZE

ACAGE CODE

09WF0W98M2141

DESIGN APPROVAL

Jim NicklausSHEET 1 OF 12

JUNE_6_00

From Chip

To CircuitBoard

RTARTA CERTIFICATION EVOLUTION CERTIFICATION EVOLUTION

JUNE_6_00

VALIDATIONOF CONFORMANCE

(CTQ)

VALIDATIONOF CONFORMANCE

(CTQ)

CUSTOMER’SASSESSMENT

CUSTOMER’SASSESSMENT

CUSTOMERNOTIFIED

CUSTOMERNOTIFIED

RTASSC RECOMMENDATION(S)

TO CUSTOMER

RTASSC RECOMMENDATION(S)

TO CUSTOMER

WSD Procurement WSD Procurement

WSD

RTASSC ENGINEERINGASSESSMENT

RTASSC ENGINEERINGASSESSMENT

WSDPROCUREMENT

WSDPROCUREMENT

AP

PR

OV

ED

REVISE/CREATEWSD

REVISE/CREATEWSD

CUSTOMERREVIEW

CUSTOMERREVIEW

RT DMSMS?RT DMSMS?WSD PARTAVAILABLE

WSD PARTAVAILABLE

YES

YES

YES

YESNO

NO

NO

NO

JUNE_6_00

RECEIVING AND SHIPPINGRECEIVING AND SHIPPING

RTA LAB.

SHIPPINGAND

RECEIVINGOF

FIC

EO

FF

ICE

DR

Y

NIT

RO

GE

NS

TO

RA

GE

REMSTAR STORAGE

PACKAGINGAND

PRESERVATION

SU

PP

LIE

S

Bld

g. 9

0121

Sout

h E

nd

Computerized state of theart paperless system

Requires only 4 people tooperate entire facility

All purchase requestedmade through Master Database

program

Computerized state of theComputerized state of theart paperless systemart paperless system

Requires only 4 people toRequires only 4 people tooperate entire facilityoperate entire facility

All purchase requestedAll purchase requestedmade through Master Databasemade through Master Database

programprogram

Guaranteed on-timeDeliveries within 72 hrs.

Direct access to participatingDistributors

RTASSC US

Storage Areais

Environmentally & ESDControlled

WSD PROCUREMENT

JUNE_6_00

16”x20”RTASSC RTRTASSC RT Database Database Monitoring and Tracking SystemMonitoring and Tracking System

16”x20”

APPROVEDHCI PART

APPROVEDHCI PART

NON- RECOMMENDEDPARTS

NON- RECOMMENDEDPARTS

CUSTOMEREVALUATION

(PERFORMANCE)

RTASSC DATABASE AND TRACKING SYSTEM YES

ENTER RTPARTS INTODATABASE

CUSTOMERSENDS NEW

DESIGN PARTS LIST

RTTESTING?

FORWARDED WITH

RECOMMENDATIONS

FORWARDED WITH

RECOMMENDATIONS

ENGINEERING EVALUATION

ENGINEERING EVALUATION

HCI PARTS LISTGENERATED

HCI PARTS LISTGENERATED

YES

NO

DMSMS?

DATACOLLECTION

CHARACTERIZATIONBEGINS

CHARACTERIZATIONBEGINS

ROUTINETRACKINGPROCESS

(EVERY 30 DAYS)

PROCESS CHECK@

TIME OF BUY

RTACCS TRACKING PROCESS = CHANGE NOTIFICATION = RT DMSMS IDENTIFICATION =AND SOLUTION PROCESS

DMSMS?DMSMS?

YESWSDNOENGINEERING

ASSESSMENT

ENGINEERINGASSESSMENT

NO

NO

JUNE_6_00

RTASSC Tracking SystemRTASSC Tracking SystemRTASSC Tracking System

Accesses All AlertsFor the Listed Part

PIRs Can Be Submitted byThe Customer, Vendor or

ContractorProvides a Direct Link to theArmy Materiel Command’s

Information System

Provides a Direct Link to theDefense Supply Center Columbus’s

Home Page

View White SandsDrawings in

Progress

JUNE_6_00

SUMMARYSUMMARY> Partnerships> “Cradle-to-Grave”> DMSMS and RT DMSMS Program Management Support> Third Party Manufacturing and Environmental Testing.> Initial Nuclear Radiation and Space Level Certifications> Cradle-To-Grave Nuclear Survivability Management > White Sands Drawings and Process Monitoring> HCI, Component and Circuit Card RTA Certifications.> DSCC Approved (9 February 2000) Receiving, Storage (Dry Nitrogen and Controlled

Environment), and Shipping.> Procurements> Co-located

u Semiconductor Test Laboratory with 8 Automated Testersu RTA Test laboratoryu Nuclear and Space Test Facilitiesu Circuit Analystsu Nuclear and Space Environments and Effects Expertsu Nuclear Survivability Expertsu Electromagnetic Environmental Facilities and Effects Expertsu Databases (RT, DMSMS and RT DMSMS)

JUNE_6_00

CONCLUSIONCONCLUSION

Although DMSMS Is A Major Problem, RT DMSMS Is A Larger Problem

However, With A “Good Program”, Both DMSMSs Can Be EffectivelyManaged

“Good Program” Must be Effective And Affordable Which Means Proactive,Progressive, And Flexible To Reflect Ever Changing Market, TechnologyAnd Program Factors

RTASSC Utilizes The RTA Approach, A Comprehensive Approach DevelopedOver 20 Years

RTASSC is A “Good Program” That Addresses All DMSMS and RT DMSMSConcerns During A System’s Entire Life-Cycle

JUNE_6_00

=Addressesu DMSMS and RT

DMSMS Problemsu Availabilityu Documentationu Procurements and

Deliveryu Designu Productionu Deploymentu Maintenanceu Sustainmentu Long Term Storage

=Providesu RT, NEW and Space

Effects Expertiseu Facilities and Analysisu Survivability Expertiseu RT Certificationu Databaseu RT Process Monitoring

and Trackingu Proactive DMSMS

Preventionu Reactive DMSMS

Solutionu Long-Term “Fenced”

Storage

CONCLUSION (continued)CONCLUSION (continued)RTASSCRTASSC


Recommended