+ All Categories
Home > Documents > Instrumentation Maintenance

Instrumentation Maintenance

Date post: 03-Jun-2018
Category:
Upload: renjith-varghese
View: 218 times
Download: 0 times
Share this document with a friend

of 10

Transcript
  • 8/11/2019 Instrumentation Maintenance

    1/10

    3

    Asset Management

    Establishing a balanced maintenancestrategy for field instrumentation

    Michael Herzog, Rinus van Kasteren, John Salusbury, Endress + Hauser

    Field instrumentation devices are crucial to reliable process plant operation but often they are not included

    in the maintenance plan since their reliability is relatively high, but effects of age and technological obsole-

    scence lead to reduced plant performance over time. New legislation demands more control and re-calibra-

    tion, manufacturers promise very stable and highly reliable instruments. The challenge is now to newly

    balance the maintenance efforts and their payback.

    This paper describes a methodology which allows a cost effective approach and improves the important

    issues such as safety and plant reliability.The new method for maintenance analysis takes into account the

    existing on-site equipment,considers its current maintainability and maintenance needs within the applica-

    tion and makes the manufacturers knowledge available. It suggests criteria for the maintenance manager

    to classify the criticality of the equipment within the process to focus the efforts, and finally explains how allplant data can be brought together to form an information base for the development of a new maintenance

    plan. A rule based tool allows to focus on the three planning dimensions of breakdown plan, preventive

    plan and migration plan. Exporting the maintenance related asset information to the local computerised

    maintenance management system simplifies the calibration and maintenance scheduling task that has to

    follow.

    Experience in mid-size and large process plants suggests that equipment and plant availability is improved

    whilst maintenance efforts are redirected from reactive trouble shooting to improved plant productivity. In

    some instances the result is an increase in preventive activities, in other cases a reduction and redirection of

    the efforts brings more productivity. Instrument replacement is now budgeted one year ahead and well

    managed. The spares stock is reduced through standardisation, important training needs of the mainte-

    nance staff are identified and maintenance efficiency is increased by focussed training.

    Festlegung einer ausgewogenen Instandhaltungsstrategie fr die Feldinstrumentierung

    Die Gerte der Feldinstrumentierung sind fr den zuverlssigen Betrieb der Prozessanlage von entscheiden-

    der Bedeutung,werden aber hufig nicht in die Instandhaltungsplanung einbezogen,da ihre Zuverlssigkeit

    vergleichsweise hoch ist. Durch Alterungseffekte und den Einfluss der technischen Weiterentwicklung geht

    die relative Leistungsfhigkeit der Anlage im Laufe der Zeit jedoch zurck. Neue Gesetze verlangen einerseits

    eine striktere Kontrolle und Nachkalibrierung,andererseits bieten die Hersteller immer stabilere und zuneh-

    mend hochzuverlssige Messgerte an. Nun kommt es darauf an, den Instandhaltungsaufwand und den

    dadurch erzielbaren Nutzen gegeneinander abzuwgen.

    Dieser Artikel beschreibt eine Methodik, die einerseits einen kostengnstigen Ansatz gestattet und anderer-

    seits Verbesserungen in wichtigen Aspekten wie Sicherheit und Anlagenzuverlssigkeit ermglicht. Die neue

    Methode fr die Instandhaltungsanalyse bercksichtigt die vorhandenen Betriebsmittel, betrachtet ihre

    Instandhaltbarkeit und ihren Instandhaltungsbedarf innerhalb des betreffenden Anwendungsbereichs und

    ermglicht den Zugriff auf das Know-how des Herstellers. Die Methodik schlgt Kriterien vor, mit denen derInstandhaltungsleiter die Kritikalitt der Betriebsmittel innerhalb des Prozesses klassifizieren kann, um den

    Aufwand entsprechend bndeln zu knnen. Sie erlutert, wie smtliche Anlagendaten zusammengefhrt

    werden knnen, um eine Informationsbasis fr die Erarbeitung eines neuen Instandhaltungsplans aufzu-

    bauen. Ein regelbasiertes Datenbank-Tool ermglicht, den Blick auf die drei Hauptabschnitte Ausfallpla-

    nung,vorbeugende Planung und Migrationsplanung zu richten. Die nachfolgenden Schritte der Arbeits-

    planung fr Instandhaltung und Kalibration werden durch den Export der instandhaltungsrelevanten Infor-

    mationen in das lokale Instandhaltungs-Planungssystem vereinfacht.

    Die Erfahrungen in mittelgroen und groen Prozessanlagen lassen erkennen, dass sich die Verfgbarkeit

    der Betriebsmittel und Anlagen verbessert, whrend sich die Instandhaltung von der reaktiven Strungsbe-

    seitigung zur Verbesserung der Anlagenproduktivitt verlagert. In einigen Fllen ergibt sich hieraus eine

    Zunahme der vorbeugenden Manahmen,in anderen Fllen lsst sich mehr Produktivitt durch eine Redu-

    zierung und Umlenkung der entsprechenden Manahmen erreichen. Der Austausch von Messgerten wirdjetzt bereits ein Jahr zuvor budgetiert und gut verwaltet. Die Lagerbestandsverwaltung wird durch Standar-

    disierung vereinfacht.Wichtige Schulungsanforderungen der Mitarbeiter werden ermittelt, und durch zielge-

    richtetere Schulungen wird die Effizienz der Instandhaltungsmanahmen verbessert.

  • 8/11/2019 Instrumentation Maintenance

    2/10

    4

    Asset Management

    1. Objective of a maintenance strategy

    1.1 Guidelines in standards

    According to the new European Standard EN 13306 Mainte-

    nance Terminology [1] it is the responsibility of any mainte-

    nance manager to define a maintenance strategy accordingto these main criteria:

    to ensure the availability of the item for the required

    function, often at the optimum costs,

    to consider the safety requirements associated with

    the item for both maintenance and

    user personnel, and where necessary, any impact on

    the environment,

    to uphold the durability of the item and/or the quality

    of the product or service provided,

    considering where necessary, costs.

    The GAMP Good Practice Guide: Calibration1

    Manage-ment[2] asks the process owner to identify the critical para-

    meters, the process variables, and to derive acceptable

    limits thus supporting a focussed approach.To obtain this

    focus, maintenance planning is preceded by maintenance

    analysis. It should include a criticality analysis as described in

    [3] as the systematic analysis for identification and evalua-

    tion of required maintenance activities, including estimation

    of time and resources needed for the maintenance perfor-

    mance.

    1.2 Strategic priorities

    This seems straightforward enough however further evalua-

    tion of the needs of the different stakeholders, representing

    business processes and functions usually reveals contradic-

    ting targets. Some typical examples are listed in Table 1.

    When a maintenance plan is produced, its defined priorities

    are likely to be challenged from a number of different angles.

    Therefore a sound approach should define the priorities first,

    get them accepted and then proceed to produce a matching

    maintenance strategy and plan. A well designed mainte-

    nance plan also needs to take into account the changes that

    occur over time its structure must be flexible enough so

    that it can be easily adapted to changing requirements.

    Field instrumentation devices are crucial to stable andproductive plant operation and yet,often they are not inclu-

    ded in the maintenance plan since their reliability is relati-

    vely high. Even the basic updating of instrument-lists in the

    item register3 is frequently neglected due to other priorities.

    This renders the maintenance plan practically useless and

    will lead to instabilities in plant operation sooner or later.

    Once the vicious circle is entered,fire-fighting will further

    reduce the available time to plan and execute the necessary

    preventive tasks. Therefore the most important feature of a

    maintenance plan is to be current and to be followed at all

    times.

    The key issues for a good maintenance plan are listed in

    Table 2.The priorities will vary from industry to industry and

    will depend on plant or corporate strategies.

    2. Contents of maintenance planning

    2.1 The activity oriented maintenance plan

    According to [1] maintenance types, strategies can be classi-

    fied in many different ways including preventive, scheduled,

    pre-determined, predictive, condition based, corrective,

    remote, deferred, immediate and on-line or off-line. On the

    other hand the resulting activities can also be vast: inspec-

    tion,monitoring,function check-out,repair, overhaul,routine

    maintenance, calibration, etc.A practical approach is to look

    at maintenance considering three main operational situati-

    ons: preparation for a failure or breakdown event (contin-

    gency plan for corrective maintenance),

    Glossary of terms

    1 Calibration is an essential element in ensuring regulatory compliance in

    the pharmaceutical industry.The ISPE issues Good Practice Guides[2] to

    provide guidance in setting up a calibration management system

    2 According to [1], maintenance effectiveness is the ratio between the

    maintenance performance target and the actual result

    3 According to [1],an item register is a record of the individually identified

    items together with location. An item is any part, component, device,

    subsystem functional unit equipment or system that can be individually

    considered.

    Table 1: Examples for objectives of maintenance planning.

    Reduce the risk to people, environment and equipment

    Satisfy regulatory requirements (Legal, Environment, Safety and

    Health)

    Reduce fluctuations of product quality (e.g.Six Sigma)

    Support management systems such as ISO 9001[4], ISO 14001[5]

    Satisfy corporate guidelines for maintenance cost (reduction) or

    outsourcing strategy

    Adapt to evolving plant requirements, e.g. an additional shift per day

    Provide a base for decision making within (new) management

    systems (TPM, RCM, RBM)

    Increase equipment reliability to reduce losses and improve delivery

    performance

    Improve maintenance effectiveness2 or other quantifiable objectives

    Optimise inventory and improve supply chain for spares

    Identify replacement needs and budget replacement ahead of time

    Reduce operating costs,e.g. unplanned shutdowns and product loss

    Table 2: Key Features of a good maintenance plan.

    Provides good maintenance effectiveness

    Reduces complexity and provide focus (do the right things)

    Offers traceability

    Is up-to-date and flexible

    Takes into account the available resources (internally and externally)

    Deals with the loss of instrumentation and calibration know-how

    Makes suppliers knowledge available to maintenance personnel

    Takes into account all devices (completeness)

    Fosters continuous improvement

  • 8/11/2019 Instrumentation Maintenance

    3/10

    5

    Asset Management

    the important planned activities (preventive mainte-

    nance),

    general life cycle issues of the field devices such as

    planned replacement or migration.

    Process plants are usually designed to operate over more

    than 710 years. Frequently, an economic life span of over

    1015 years is expected and plants often exceed 20 years of

    operation. During this period they are expected to deliver

    increasing output at an improving level of quality.

    In contrast to this,developers of field instrumentation are

    changing and improving the technical design at a much fas-ter pace in order make use of new technologies to stay com-

    petitive. The manufacturers also have to consider new legal

    requirements such as ATEX, Functional safety (IEC61508) or

    the Pressure Equipment Directive: They have triggered new

    designs or product options and made other older designs

    obsolete.Last not least, the developments in bus technology

    regularly lead to software updates.

    Table 3 suggests some change ratesfor plant instrumen-

    tation.Technology check-ups can open up important impro-

    vement potentials: Better and tighter process control, higher

    process efficiency and longer up time due to longer time to

    failure4 and reduced repair time5 are observed when techno-

    logy upgrades are implemented on critical components of a

    plant.

    Evolution of technology can be advantageous, but also

    has its drawbacks: Whilst spare parts for older generation

    equipment may become unavailable, the new devices may

    have different dimensions that need adaptation to the

    installation. Also, the electrical connection specifications

    may have changed. Successor compatibility can be impossi-

    ble to achieve for the instrument manufacturer, for example

    when new standards for external dimensions arrive as was

    the case for electromagnetic flowmeters. The implications

    for the spare parts stock and training requirements must be

    examined as well.

    The three main aspects of the maintenance plan for

    instrumentation are therefore:

    breakdown plan and associated aspects preparation for

    the development of a contingency, streamlining of spares stock according to the chosen

    repair strategy,

    planning for the training of personnel, managing the

    know-how,

    support requirements from (internal or external) service

    provider(s),

    preventive plan includes triggered (predictive) and all

    scheduled activities,

    definition of verification and calibration intervals and

    methods,

    streamlining consumables and wear parts stock (supply

    chain), definition of outsourcing needs,

    migration plan Managing technological improvements,

    controlling actively the move to new generation devi-

    ces,

    implementing improvements in process control,

    planning ahead to secure the investment.

    2.2 Opportunities and considerations with smartdevices

    Hart-Protocol, ProfiBus and Foundation Fieldbus have arri-

    ved and web technology is now emerging in the field of pro-

    cess automation. In combination with so called asset mana-

    gement systems (or solutions) they are promising to sim-

    plify the maintenance of all connected devices. Every

    re-calibration, every exchange of a device can be registered

    and becomes traceable for any inspector that has to verify

    the action.(A risk of omission exists,though, if not all devices

    are connected to the bus). As field devices are becoming

    more sophisticated, some will report their maintenance

    needs and send an alert via the communication link to the

    asset management system to enable predictive mainte-

    nance. This ability can be used as a base to consider exten-

    ded inspection or calibration intervals in some applications.

    But unless two or more redundant sensors are used, a self-diagnostic function cannot be very reliable in detecting a

    calibration drift, resulting in a measurement error induced by

    an effect (physical/chemical) to the primary sensing ele-

    ment.The big advantage that bus-system based field device

    architectures offer is the self-documenting feature that

    allows no change (or tampering) to go unnoticed, particu-

    larly concerning device parameterisation. For maintenance

    planning the advantage is that the instrument lists in the

    item register can be electronically updated. Table 4 depicts

    the areas of improvement that suppliers typically indicate for

    technologically more advanced field instrumentation equip-

    ment.If considering such an electronic recording system it is

    worth noting the FDA standard 21CFR Part 11 [6] that speci-

    fically deals with this topic. As the food industry is moving

    Table 3: Technological life cycles in comparison.

    Software design,patches and improvements 618 months

    Hardware design (internal modifications) 1 3 years

    New generation, complete design overhaul 4 8 years

    Basic technology change (e.g.PD-meters Coriolis) 1020 years

    4 Repair time[1] is defined as Part of active corrective maintenance time

    during which repair is carried out on an item.5Time to failure[1] is defined as Total time duration of operating time of

    an item, from the instant it is first put in an up state, until failure or, from

    the instant of restoration until next failure.

    Table 4: Improvements & benefits offered by newtechnology.

    Improvement Benefit

    Modular design Quicker repair time, flexibility (stock)

    Improved accuracy,stability Tighter process control

    Higher ratings (e.g.temperature) Better reliability in the application

    Lower energy consumption Energy savings

    Scalable, upgradeable software Better price/benefit ratio

    Digital Communication Many bus related advantages

    Better support tools Easier and more efficient

    maintenance

  • 8/11/2019 Instrumentation Maintenance

    4/10

    towards adoption of Good Automated Manufacturing Prac-

    tices (GAMP) the correct maintainability of the existing

    installations needs to be examined. Thus the gap between

    the current plant status and the required level of maintaina-bility is documented. Upgrading to smart devices can be an

    effective way to close this gap.

    3. Review and classification of field devices

    The starting point to introducing or upgrading a mainte-

    nance strategy is to audit and review all applications. Some-

    times an instrument register does already exist but needs

    updating. A complete inventory of all field devices needs to

    be carried out.The quality of this review process is crucial to

    the determination of maintenance priorities later on: Any

    shortcomings of the installation, such as inadequate up-

    stream or downstream straight runs for a flowmeter or

    improper cabling need to be registered.

    All special applications should be verified to identify

    heavy conditions that demand special attention. If instru-

    mentation hasnt been tagged before, this is the time to do

    it. For a practical example on what could be registered when

    sampling the installed base, see Fig. 1. If the plant has hazar-

    dous areas, then it is worthwhile to include the zone rating

    for the individual sub-locations.

    Some field devices are more important than others and

    should be classified as Critical to the process. If they fail, or

    even worse, if their output signal slowly drifts away from thecorrect value, the correct operation of the production pro-

    cess, the plant, personnel or the environment are in danger.

    Sometimes this information can be deducted from the origi-

    nal plant design or a Hazard and Operability Study (HAZOP)

    that was conducted. Rather elaborate and very systematic

    methods to assess each plant components criticality exist

    for example the Norsok Standard Z008 [3].

    A simple and practical approach is to first sort all field

    devices into three different categories. If no other guidelines

    exist, then for common process plants the three-tier distri-

    bution can be targeted as a starting point.Table 5 highlights

    examples of the important criteria that can be applied. Fur-ther refinements can then be made by looking at external

    (e.g. regulatory) requirements for regular inspection or cali-

    bration.The final defining of criticality values should be done

    with a team that includes as much experience and know-

    ledge of the process as possible.

    The next step is to assess the risk from a possible lack of

    maintainability. All devices must be evaluated (refer to

    Table 6) in order to assess the remaining useful lifetime and

    the fitness for the purpose within the process.Depending on

    the chosen repair strategy you need to know whether a suc-

    cessor product is compatible:Can it be installed in lieu of the

    old device in case of a breakdown without mechanical or

    electrical modifications? Spares availability has to be asses-

    sed and obsolete equipment to be identified.The instrument

    manufacturers can usually provide a lot of support and infor-

    mation providing opportunities for optimising spares and

    managing consumables and guidelines about maintenance

    needs for the more than thirty different measurement para-

    meters that exist.Keep it practical and limit the technical and

    commercial questions you ask the suppliers to the really

    necessary! A spreadsheet or database should be set up for

    this purpose to align information on the level of device-ty-

    pes and individual tag numbers. It should list the respective

    ratings for criticality to the process as well.

    6

    Asset Management

    Fig.1: Example of information to register.

    Table 5: Parameters defining criticality of devices to the process.

    Criticality Description

    High High, direct safety impact (GAMP Safety critical, IEC 61508:

    SIL 2/3/4, Ex-Zone)

    High, direct impact on product quality (GAMP Product

    critical, ISO9000)

    High, direct environmental impact (GAMP Environmentalcritical, ISO14000)

    High production cost (GAMP Process/System critical,

    e.g.costly secondary failures)

    High financial cost (e.g.custody transfer duty,product loss)

    Medium Medium safety impact (IEC 61508:SIL 1)

    Medium impact on product quality

    Possible indirect environmental impact

    Medium production cost (manual control for some time

    possible)

    Medium financial cost

    Low Low or no safety/environmental/product quality process

    impact (GAMP Non-critical)

    Negligible financial impact

    Table 6: Check-Points to evaluate the maintainability of field devices.

    The product is current,spares, documentation and training areavailable and the lead time to reorder product/spares is fitting

    the need

    The supplier has announced some special product status, such as

    phase-out,obsolete,sales-stop or other

    The supplier has gone out of business,the product has been

    discontinued for some years

    An identical replacement product is not readily available any more

    The successor may not be fully compatible (e.g.mechanical/

    electrical connection,bus connectivity)

    Spare parts and repairs availability is difficult, the spare parts are not

    manufactured any more (used parts!)

    Operating experience of the product highlights the need for regular

    intervention

    The product has a much higher need for regular maintenance than

    state of the artdevices

    Combinations of the above

  • 8/11/2019 Instrumentation Maintenance

    5/10

    7

    Asset Management

    4. Structure of the maintenance plan

    Once a picture of the installed base has been established,the

    analysis which will lead to the first view of the maintenance

    requirements can begin. Any serious attempt at bringing all

    this information together for more than 100 instruments and

    organise it along the lines of the main chapters of break-down, preventive and migration plans should involve the

    use of a database tool. In the process of maintenance analy-

    sis a rule based tool significantly reduces complexity and

    places data within a well structured frame to provide usable

    information from the abundant data. Ideally the tool will

    enable collaborative work between the team that conducts

    the maintenance analysis and the instrument suppliers.

    The Installed Base Analystwas conceived as a rule based

    software tool to support Endress+ Hausers service advisors

    in their consulting service Instrument Management Soluti-

    ons [7] which utilises the methodology described in this

    paper.It has the ability to register the entire installed base ofinstruments and group them into over 40 classes of measu-

    rement principles and types.

    In the following paragraphs the general logic used to

    structure the information about the installed base are high-

    lighted.

    4.1 Breakdown plan

    In case of a breakdown, either the complete device or parts

    of it need to be replaced.

    The focus here is on the devices with the highest critica-

    lity ratings. For them, repair training and on-site spare-parts

    or spare devices must be considered to keep down time

    short. These decisions depend on the processes require-

    ments for repair times and current repair time performance.

    Fig. 2 shows the areas of attention.

    Two basic repair strategies are utilised mainly:

    replacement of the complete device in case of a failure or

    repair of the device without taking it off the process

    physically by use of spare parts (modules).

    The first method may be achieved with less trained per-

    sonnel. On the other hand, emptying a vessel or pipe to

    replace a complete device can be very time consuming and

    expensive. Unless the application produces heavy wear onthe sensor, it is statistically speaking the part that will rarely

    fail in an instrument without moving parts. Even pressure

    peaks are generally handled well by the newer transmitters.

    Changing the electronics insert (module) can be an easy

    repair if it is prepared properly.This is where standardisation

    plays an important role: The preparation work is not econo-

    mical for only a few instruments.

    4.2 Preventive plan

    To prevent unnecessary maintenance and to reduce the risk

    of costly downtime, the tool performs queries to highlight

    the priorities for periodic maintenance,calibration or inspec-tion related to the specific requirement of the instrument

    types and the process. Time based replacement require-

    ments of consumables and wear parts are highlighted in

    addition. Fig. 3 shows the guidelines to select the instru-

    ments that might need attention.

    The schedule of a maintenance plan for critical devices is

    influenced by several factors such as the level of self-diag-

    nostics and the effect on the process when a failure or an

    error condition exists:Would a drift be noticed in time to pre-

    vent quality problems or is a periodic inspection [1] or even

    calibration necessary and what should the periodicity6 be?

    Some instruments do have a clear demand for inspection,

    maintenance or calibration. pH-sensors, for example, need

    regular calibration and electrode replacement irrespective

    of the criticality to the process and other demands. Their

    exchange schedule can be optimised and very cost effective

    delivery contracts can be established with the supplier

    thus reducing the cost of keeping stock. Standardisation is

    very helpful in this domain.

    In other cases the need to maintain an instrument on a

    regular basis is influenced by particular process- and envi-

    ronmental conditions a typical example for this is strong

    abrasion in a flow line.

    In addition, internal or external quality demands and the

    criticality determine the recommended periodic inspection,maintenance or calibration regime.

    The devices that now emerge with a defined maintenance

    need must undergo scheduling. Exporting the maintenance

    related asset information to the local (CMMS) system simpli-

    fies the calibration and maintenance scheduling task that has

    to follow. A particular situation exists for flow calibration.

    Since this type of calibration is not easily feasible on a plant

    and since indirect methods are not standardised, flowmeters

    are often excluded from the calibration schedule even

    though they can be crucial to plant performance. On the

    other hand you can find pressure and temperature calibrati-

    ons that many plants carry out on a monthly basis. Often

    Breakdown plan

    priority area

    Risk to the maintainability

    Critical

    ity

    tot

    he

    process

    High Medium Low

    High

    Medium

    Low

    Fig. 2: Priority area

    for the breakdown

    plan.

    Guidelines to analyse the needfor maintenance

    Instrument demands? Application demands? Internal demands? External demands? Criticality?Fig. 3: Guidelines for

    the preventive plan.

    6 Calibration periodicity[2] is defined as frequency of scheduled calibra-

    tions.

  • 8/11/2019 Instrumentation Maintenance

    6/10

    these easy to do check-ups are repeated too frequently as

    modern instruments rarely need calibration intervals of less

    than several years under normal industrial conditions.

    4.3 Migration plan

    The field devices need to be examined for updating require-

    ments. Managing the migration / modernisation process

    over time allows control of the level of variety or degree of

    standardisation and tighter budget control.Instruments that

    are critical to the process and are close to or beyond its use-

    ful life or no longer suitable due to changes in legislation or

    requirements from the duty must be identified. Fig. 4 shows

    the areas of attention for updating/migration needs. Along

    with the migration policy for the instruments, the upgrade

    path for spares and must be defined.This is also an opportu-

    nity for the reduction in spares variety.

    Taking the migration need of an instrument as an oppor-

    tunity for process optimisation can yield helpful side effects.

    A positive displacement flowmeter that gets replaced by a

    Coriolis mass flowmeter can continue to give a volumetric

    output but also offers a massflow reading that can be used

    to optimise the chemical process through improved accu-

    racy of mixture ratios. Sometimes the replacement of an

    electromagnetic flowmeter by a newer model can reduce

    the energy consumption by over 50%, and other examples

    can be given for improvements of control loop response or

    dosing and batching applications.

    5. Practical experience

    5.1 Benefits of the method

    Well-defined priorities in the overall maintenance plan can

    be successfully defined by following the described process.

    The method allows an estimation of the required resources

    to carry out the defined tasks as well as defining an effective

    migration plan. Since the method combines a bottom-up

    approach (application and device audit) with general top-

    down strategies for the most important business cases, the

    work generates transparency and traceability. The outcome

    is a view of the installed base from three perspectives whichallow the design of a plan of maintenance activities in order

    to get a good balance between plant availability and all

    maintenance efforts. Fig. 5 shows the relationship between

    the degree of maintenance done and the corresponding

    total cost for the plant.Doing too little maintenance leads to

    increased cost because of reduced process availability and

    fire-fighting. It may also compromise product quality and

    cause problems in the spare parts supply. Exercising too

    much maintenance (or not the most effective measures!) will

    unnecessarily increase the cost of labour and inventory, andit usually leads to other problems: The saying if it aint bro-

    ken dont fix it has its virtues still.

    The described method will greatly assist in deciding on

    the individual optimum strategy: Its focus on critical and dif-

    ficult to maintain instruments as well as on good preparation

    for failure events will decrease down-time while keeping

    maintenance efforts focussed. The migration plan will keep

    the instrumentation easy to maintain.

    5.2 Case examples

    The methodology described has evolved from practicalexperience working with many maintenance managers and

    their teams. It was checked in process by the joint efforts of

    the service provider and end user in real situations.The out-

    come of this work has always shown that equipment reliabi-

    lity can be improved, process plants can be optimised and

    total cost can be reduced.The two following representative

    case stories highlight the wealth of individual options and

    the flexibility: Case A is an example of an under-serviced

    situation in a food-production plant, Case B is an over-ser-

    viced coating plant serving the automobile industry.The two

    cases are constructed from real experience. The results and

    comments are typical.

    5.3 Case A

    The management of one of the biggest and successful cho-

    colate factories in Germany took stock of the business risk

    from possible problems in the production process:An instru-

    ment failure on a critical measurement point with no spares

    in stock would lead to in a complete shutdown of the manu-

    facturing plant for 24 hours.Such a shutdown could result in

    lost production to the value of about one million Euro.

    Reason enough to turn attention to integrated mainte-

    nance strategies and to look for new solutions to optimise

    the life cycle of the field devices. In particular, one plantwhich had been modified and expanded over many years

    was considered the highest risk despite a most modern pro-

    cess control system and routine maintenance. Smaller inci-

    dents in the recent past had demonstrated the difficulties

    and led to inquiries into the following subjects:

    8

    Asset Management

    Migration

    planpriority

    area

    Risk to the maintainability

    Criticalitytoth

    eprocess

    High Medium Low

    High

    Medium

    Low

    Fig. 4: Priority area

    for the migration

    plan.

    Totalcost

    Degree of Maintenance

    Nomaintenance

    Too muchmaintenance

    Optimum point:

    Minimum cost

    Fig.5: Total cost as a

    function of mainte-

    nance activities.

  • 8/11/2019 Instrumentation Maintenance

    7/10

    9

    Asset Management

    Identification of the manufacturer and evaluation of the

    reparability of the device

    Availability, specification and lead time of a replacement

    device

    Possibility to replace a device by a similar one located in a

    non-critical application

    Since the plant had been modified several times to incre-

    ase capacity and to allow continuous operation (24/7), what

    was needed most was:

    clear information of the status of all on-site devices,

    assessment of the process-critical devices,

    creation of a schedule for maintenance and calibration,

    standardisation and type reduction in production and

    spares stock.

    As a first step all 800 instruments were registered and the

    spare parts stock was checked.Several meetings of the main-

    tenance team and Endress+ Hausers service advisor yieldeda common view on the priorities:

    high dependence on quality,

    high importance for a smooth process operation,

    safety or process critical.

    The service advisor discussed every important measure-

    ment point with the team. He provided useful hints on how

    to improve the level of preventive maintenance without

    increasing costs too much and provided alternatives for dis-

    cussion, for example about maintenance-intensive devices:

    Replace by a modern type or continue to maintain?

    Based on the maintenance analysis an action plan was

    worked out by the maintenance team with the objective to

    improve the existing maintenance, inspection and calibra-

    tion intervals to reduce the risk of unplanned shutdowns.

    Some obsolete devices were identified and replacements

    were ordered and commissioned.The spares stock was clea-

    ned of unusable parts. Complete replacement devices and

    up-to-date spare parts were added. These devices were con-

    figured in a way that they would fit several applications

    when needed.

    The preventive measures within the system have now

    improved instrumentation availability, operating safety of

    the plant and product quality. The final Installed Base

    Report records the results of the analysis and the commondiscussion.It served as a basis for the decisions in the action

    plan. The registration tool was obtained from End-

    ress+ Hauser and an operator was trained.All future additi-

    ons or changes to the instruments will now be registered.

    Some maintenance and calibration measures were out-

    sourced for lack of resource and tools. A training pro-

    gramme for the maintenance team was defined and agreed

    to. The budget for the following planning period was well

    detailed and signed off quickly by management since the

    reasons were convincing and traceable to the Installed Base

    Report.

    For this plant, the main benefits of Instrument Manage-ment Solutions were given as:

    transparency of the installed device basis,with the ability

    to register devices from all manufacturers

    improved quality control through better control of mea-

    surement devices,

    cost reduction through higher plant availability and

    reduction of fire fighting.

    5.4 Case B

    Serving the automobile industry, this coating plant was

    always maintained in a very complete way. As the business

    environment had become increasingly competitive, the new

    owner had reduced the staff in several cuts. The mainte-

    nance team was organised as a cost centre.The workload for

    annual the re-calibration of the more than 2000 sensors was

    exceeding the available resources by more than 30%. The

    site manager was faced with two challenges:

    1. to keep the high standards of quality without increasing

    cost or taking unknown risks

    2. to check the instrumentation for its ATEX7 status?

    Since the calibration team maintained records for every

    instrument, only the instruments that were not being re-ca-

    librated had to be registered in to the tool.The site audit was

    carried out jointly by a member of the maintenance team

    and the E+H service advisor. Eventually, further data were

    downloaded from the calibration database. After the down-

    load was completed and the data imported to the tool the

    team noticed that the exact model numbers of the instru-

    ments had never been completely recorded. The available

    application information was not detailed enough for the

    common discussions.Therefore,all other devices were regis-

    tered as well.

    In a previous attempt to streamline plant operations all

    devices critical to the process had been identified.The main-

    tenance team reviewed the criticality. An interesting point

    was noted: Most of the process critical flowmeters had never

    been wet-calibrated.For some of them there were no spares

    available any more since the technology had become obso-

    lete.

    After several working sessions, it was demonstrated by

    the team leader in a management meeting, that the scree-

    ning process had resulted in a new calibration schedule that

    could be handled by the current organisation without pus-

    hing the resources to their limits any more. The increase in

    risk through the reduction of calibration frequency on theless critical devices and by avoiding the re-calibration of

    uncritical instruments was seen to be completely acceptable

    by management and was thought to be easy enough to

    explain to any auditors. In fact, the project team was compli-

    mented on their good practice.

    A download to Excel allowed the easy collating of an

    instrument list that was segmented by manufacturer.This lis-

    ting will then be used to check compliance with the ATEX

    regulations in order to to determine replacement needs well

    in advance of the 2006 deadline. All existing hazardous area

    work places in use before June 30, 2003 must comply with

    7The new European Use Directivewill soon require (by law) that a com-

    plete,documented analysis has been conducted on sites that may have a

    potentially explosive atmosphere.

  • 8/11/2019 Instrumentation Maintenance

    8/10

    10

    Asset Management

    the appropriate minimum requirements of ATEX 137 [8] no

    later then June 30, 2006. The main benefits noted here were

    the following:

    establishment of technological status of all devices,

    maintain quality control at reduced maintenance levels,

    detection of obsolete material in the plant and in the spa-

    res stock, well documented results in the Installed Base Report offer

    traceability for inspectors and auditors.

    The exercise described was repeated on another plants of

    the same site later on.

    6. Conclusion

    The described collaborative effort between manufacturer

    and end-user to carry out maintenance analysis and define a

    well balanced maintenance strategy has proven to be aneffective approach. Its focus on process-critical and diffi-

    cultto-maintain instruments as well as on good preparation

    for failure events reduces down-time while keeping mainte-

    nance efforts focussed. The migration plan will keep the

    instrumentation easy to maintain.

    The traceability simplifies budgeting and cost control.

    Plant reliability is enhanced through better control of main-

    tenance risks.

    References

    [1] EN 13306:2001 de/fr/en European Standard on Maintenance Termi-

    nology.

    [2] ISPE, GAMP Good Manufacturing Practice Guide: Calibration Mana-

    gement.

    [3] Norsok Standard,Z-008,Rev.2, Nov 2001, Criticality analysis for main-

    tenance purposes.

    [4] ISO 9001 covering quality management system.

    [5] ISO 14001 covering environmental management system.

    [6] FDA 21 CFR Part 11: FDA regulations concerning compliance for elec-

    tronic Records and Signatures.

    [7] Instrument Management Solutions: Service Overview SD007H/29/

    en/08.01 Endress+Hauser.

    [8] Use Directive ATEX 137, Directive 99/92/EC of the European Parlia-

    ment of 28. January, 2000.

    Acronyms

    ATEX from the French phrase atmosphres explosives

    CFR Code of Federal Regulations

    CMMS Computerised Maintenance Management System

    FDA Food and Drug Administration (U.S. Department of Health &

    Human Services)

    GMP Good Manufacturing Practice

    GAMP Good Automated Manufacturing Practice

    HAZOP Hazard and Operability

    IEC International Electrotechnical Commission

    ISO International Organization for Standardization

    ISPE International Society for Pharmacoepidemiology

    PD Positive Displacement

    RBM Risk Based Maintenance

    RCM Reliability Centered Maintenance

    SIL Safety Integrity Level

    TPM Total Productive Maintenance

    Dipl.-Ing.ETH Michael Herzog has worked in various

    management positions in Marketing, R&D and Ser-

    vices at European and North American End-

    ress +Hauser group companies since 1984 when he

    joined the group. He grew up in Japan and holds a

    diploma in electrical engineering from the ETH in

    Zrich/Switzerland. Today, as Director Customer

    Services he is responsible for the development of

    the world-wide group activities in after-sales ser-vices. He is based in the corporate headquarters in

    Reinach, Switzerland.

    Adresse: Endress+ Hauser Consult AG, Kgenstr. 7,

    CH-4153 Reinach, Tel. +41-61-715-7756, Fax -7758,

    E-mail: [email protected]

    Rinus van Kasteren joined the E+H group in 1990

    and is based in the Sales and Service organisation

    of Endress+ Hauser in the Netherlands.As a service

    advisor he is responsible for the realisation of main-

    tenance projects with a specific focus towards the

    implementation of maintenance strategies for field

    instrumentation. He has worked closely with main-

    tenance managers and/or reliability engineers from

    production companies such as Cargill, Unilever,Heinz, DSM, Huntsman and so on. In his 20 years in

    various positions in customer service and mainte-

    nance he assimilated valuable knowledge about

    the problems and solutions in this field that he

    makes available to customers of Endress+ Hauser

    today.

    Adresse:Endress +Hauser NL B.V., Nikkelstraat 612,

    NL-1411 AK Naarden, Tel. +31 (0) 356 958-611, Fax

    -825, E-mail: [email protected]

    John A.Salusburys present position is within corpo-

    rate management of Endress+ Hauser, based in

    Switzerland, responsible for global marketing of

    products and services. He started his career with

    British Steel serving a four year apprenticeship inInstrumentation combined with studies at the

    North E Wales Institute resulting in a diploma in

    Industrial Measurement and Control. As an Instru-

    ment Engineer he has worked for various compa-

    nies including ICI, Sasol, Shell (both onshore and

    offshore) and Kraft foods. He joined the E+ H group

    in 1985 holding various management positions

    including responsibility for the UK Flow measure-

    ment division.

    Adresse: Endress+Hauser Consult AG, Kgenstr. 7,

    CH-4153 Reinach, Tel. +41 61715-7769, Fax 7762,

    E-mail: [email protected]

  • 8/11/2019 Instrumentation Maintenance

    9/10

    Instrument Management SolutionsStriking the right balance in maintenance

    The pressure on maintenance depart-

    ments today is greater than ever before.

    Companies are constantly looking atdownsizing, a genuine skill shortage existsand yet the overall company demand isconstantly to produce more. It becomesseemingly impossible for maintenancemanagers to improve planned maintenanceand at the same time reduce their costs.

    The maintenance strategy is howeverexpected to fall in line with that of theoverall requirements of the companystrategy! If this is not difficult enough its

    probably not appreciated that themaintenance engineer is constantly faced

    with different types of equipment, fromdifferent generations of technology, someof which you may no longer be able toobtain spares for...

    So management of the installed baserapidly turns into a headache!

    If you recognise just some of these

    points within your organisation, you

    could undoubtedly benefit from

    Endress + Hausers unique solution.

  • 8/11/2019 Instrumentation Maintenance

    10/10

    Austria

    Endress+Hauser Ges.m.b.H.Lehnergasse 4

    A-1230 WienTel.: +43 (1) 88 05 6-0Fax: +43 (1) 88 05 6-335E-Mail: [email protected]

    Belgium

    Endress+Hauser S.A./N.V.Rue Carli Straat 13B-1140 Bruxelles

    Tel.: +32 (2) 2 48 06 00Fax: +32 (2) 2 48 05 53E-Mail: [email protected]

    Canada

    Endress+Hauser (Canada) Ltd1440 Grahams Lane, #1CDN-Burlington. OntarioCanada L7S 1W3

    Tel.: +1 (905) 6 81 92 92Fax: +1 (905) 6 81 94 44E-Mail: [email protected]

    Denmark

    Endress+Hauser A/SPoppelgrdvej 10-12DK-2860 Sborg

    Tel.: +45 (70) 13 11 32Fax: +45 (70) 13 21 33E-Mail: [email protected]

    Finland

    Metso Endress+Hauser OyLaippatie 4CP.O. Box 310FIN-00881 Helsinki

    Tel.: +358 (0) 20 48 31 60Fax: +358 (0) 20 48 31 61E-Mail: [email protected]

    France

    Endress+Hauser3 rue du Rhin B.P. 150F-68331 Huningue Cedex

    Tel.: +33 (389) 69 67 68Fax: +33 (389) 69 48 02E-Mail: [email protected]

    Germany

    Endress+HauserMesstechnik GmbH+Co. KGColmarer Str. 6D-79576 Weil am RheinGermany

    Tel.: +49 (76 21) 9 75 01Fax: +49 (76 21) 9 75 55 5E-Mail: [email protected]

    Italy

    Endress+Hauser S.p.A.Via Donat Cattin 2/AI-20063 Cernusco s/N -MI-

    Tel.: +39 (02) 92 19 21Fax: +39 (02) 92 19 23 62E-Mail: [email protected]

    Netherlands

    Endress+Hauser B.V.Nikkelstraat 6-12Postbus 5102NL-1410 AC Naarden

    Tel.: +31 (35) 6 95 86 11Fax: +31 (35) 6 95 86 25E-Mail: [email protected]

    Norway

    Endress+Hauser A/SPostboks 62N-3420 Lierskogan

    Tel.: +47 32 85 98 50Fax: +47 32 85 98 51E-Mail: [email protected]

    Poland

    Endress+HauserPolska Sp. e o.o.ul. Pilsudskiego 49-57PL-50-032 Wroclaw

    Tel.: +48 (71) 78 03 700Fax: +48 (71) 78 03 760E-Mail: [email protected]

    Rep. South Africa

    Endress+Hauser (Pty.) Ltd5 Commerce Crescent West.Eastgate Ext. 13P.O. Box 783996RSA-2146 Sandton

    Tel.: +27 (11) 2 62 80 00Fax: +27 (11) 2 62 80 62E-Mail: [email protected]

    Singapore

    Endress+Hauser(S.E.A.) Pte. Ltd01-11/12 The Synergy1 International Business ParkSGP-609817 Singapore

    Tel.: +65 65 66 82 22Fax: +65 65 66 68 48E-Mail: [email protected]

    Spain

    Endress+Hauser S.A.Constitucion 3. Bloque A.E-08960 Sant Just Desvem

    Tel.: +34 (93) 4 80 33 66Fax: +34 (93) 4 73 38 39E-Mail: [email protected]

    Sweden

    Endress+Hauser ABP.O. Box 7006S-19207 Sollentuna

    Tel.: +46 (8) 55 51 16 00Fax: +46 (8) 55 51 16 55E-Mail: [email protected]

    Switzerland

    Endress+Hauser Metso AGSternenhofstr. 21CH-4153 Reinach / BL1

    Tel.: +41 (61) 7 15 75 75Fax: +41 (61) 7 11 16 50E-Mail: [email protected]

    United Kingdom

    Endress+Hauser Ltd.Floats RoadGB-Manchester M23-9NF

    Tel.: +44 (161) 2 86 50 00Fax: +44 (161) 9 98 18 41E-Mail:[email protected]

    USA

    Endress+Hauser Inc.2350 Endress PlaceP.O. Box 246USA-46143 Greenwood,Indiana

    Tel.: +1 (317) 5 35 71 38Fax: +1 (317) 5 35 84 98E-Mail: [email protected]

    All other countries

    Endress+HauserInstruments InternationalColmarer Str. 6D-79576 Weil am RheinGermany

    Tel.: +49 (76 21) 9 75-02Fax: +49 (76 21) 9 75-345E-Mail: [email protected]

    Endress+Hauser Sales Centers

    W@M Life Cycle Management with Endress+Hauser

    At Endress+Hauser we have concentratedon the support of our instrumentationwithin all process industries for over fiftyyears. This expertise is now focused on arange of tools, products and services thatoffer a complete life cycle supportpackage for your process.

    Under the umbrella of our revolutionaryW@M concept, an unique set of toolsallow you to plan your installation andconfirm the suitability plus expectedperformance of your application whilst still

    in the engineering phase. A portfolio ofe-business solutions allows easy, costeffective procurement of goods. The newField Check (and Installed Base Analyst)allows you to manage test and validateyour installed instrumentation during itscomplete operating life.

    Couple this with Endress+Hausersrenowned range of products and acomplete suite of on-site services and youcan be confident that your instrumentation

    and process are supported properly andrunning at their optimum.The result - maximum process

    efficiency and complete peace of mind.


Recommended