+0. Executive OverviewEarned Value Management and Agile Software Development have much in common. The most important is progress to plan is measured by Physical Percent Complete with tangible evidence of working products at the end of planned period of performance.For software intensive system of systems, agile development provides powerful tools for producing working software on frequent boundaries to gain needed customer feedback to assure the program is going in the right direction.
There are only two phases to a big program: Too early to tell and too late to stop!‒ Mr. Blaise Durante, Deputy Assistant Secretary (Acquisition Integration), U. S. Air Force
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016 5
+
Integrating Earned Value and Agile Development provides credible EAC and ETC for large Software Intensive System of Systems needed
to manage in the Fog of Emergence
Why Integrate Agile Development and Earned Value Management?
Navigation
Communications
Fire Control
Engine Controls
Counter MeasuresVisualization
Flight Controls
Life Support
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
6
+ What Do We Mean When We Say Agile?
† Dr. Ashton Carter, Under Secretary of Defense for Acquisition, Technology and Logistics, Sep/Oct, 2010 Defense AT&L
Pembroke Welsh Corgi in a goat herding competition, Boulder County Fair, Longmont Colorado.Chubby body, short legs, not “lean,” but able to turn “inside the loop” of the sheep = “agile?”
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
7
+ What Is The Real Goal of Any Method – Agile or Traditional?
Increase The Probability of Program Success
1.0 Communications and Computing Infrastructure1.1 Acquisition, Logistics and Technology Enterprise Systems and Services (ALTESS)
1.2 Army Knowledge Online (AKO)/Defense Knowledge Online (DKO)1.3 Computer Hardware, Enterprise Software, and Solutions (CHESS)1.4 Defense Communications and Army Transmissions Systems (DCATS)1.5 Defense Messaging System-Army (DMS-A)1.6 Defense Wide Transmission Systems (DWTS)1.7 Force Projection Enablers (FPE)1.8 Information Technology Systems ( ITS)1.9 Installation Information Infrastructure Modernization Program ( I3MP)
1.10 Land Mobile Radio (LMR)1.11 Network Enterprise Services (NES)1.12 Network Service Center (NSC)1.13 Satellite Communications Systems (SCS)1.14 Vehicular Intercom Systems (VIS)1.15 Wideband Control (WC)2.0 Logistics
2.1 Army Enterprise Systems Integration Program (AESIP)2.2 Global Combat Support System-Army (GCSS-Army)2.3 Joint-Automatic Identification Technology ( J-AIT)2.4 Logistics Modernization Program (LMP)2.5 Movement Tracking System (MTS)2.6 Transportation Information Systems (TIS)3.0 Human Capital3.1 Army Human Resource System (AHRS)
3.2 Distributed Learning System (DLS)3.3 Force Management System (FMS)3.4 HR Solutions3.5 Installation Management Systems-Army ( IMS-A)3.6 Integrated Personnel and Pay – Army ( IPPS-A)3.7 Reserve Component Automation Systems (RCAS)4.0 Finance
4.1 General Fund Enterprise Business System (GFEBS)5.0 Medical 5.1 Medical Communications for Combat Casualty Care (MC4)6.0 Acquisition6.1 Acquisition Business (AcqBusiness)7.0 Biometrics7.1 Department of Defense (DoD) Biometrics (DoD Biometrics)7.2 Biometrics Enabling Capability (BEC)
7.3 Tactical Biometric Systems (TBS)
Army PEO EIS
1.1 Acquisition, Logistics, and Technology Enterprise Systems and Services (ATLESS)
Guidance to increasing the
PoPs
Seek ways to increase the Probability of Program Success not just apply new methods
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
8
Do these sound
familiar?
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
9
+ Is The Department of Defense Ready To Embrace Agile Methodologies?It seems so…
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
10
+ While seeking to fulfill the directives of NDAA §804 …
Plus a few more … FAR 52.234-2, 34.201, 34.202, OMB Memo(s) M-05-23, M-04-24, DFAR 252.234–7002, DoD Instruction (DoDI) 5000.02, Defense Acquisition Guidebook, Chapter 11, Section 11.3.1.3.
… let’s not forget these directives too.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
11
+ Rule for Earning Value in Agile
Each Release in Agile is a “value earning” opportunity
The next step is to connect Agile’s definition of “value”
with Earned Value’s definition of valueBusiness Value ÙÚ EV
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
12
Before Going Further, Let’s Bust Some Myths
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016 13
+ A Few Myths of Defense Acquisition†
† “Modern Acquisition Myths, “ Capt. Dan Ward, USAF, Program Management., Mar/Apr, 2003Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
14
+ 3 Ways To “Connect the Dots”
Earned Value Management Agile
Both EV and Agile Measure Progress as Physical Percent Complete
1. Measures progress in units of “physical percent complete.”
1. Each iteration produces 100% working products.
2. Forecast future performance using past performance.
2. Forecast performance in units of products produced.
3. Take a systems approach to the development of products by connecting Cost, Schedule, and Technical Performance.
3. Increasing fidelity of product and problem understanding occurs after each Sprint and Release.
+
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
15
+ 12 Principles of the Agile Manifesto
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
16
+ 11 Critical Criteria for Earned Value Managementn The 32 EVM Criteria are all designed to deliver value.
n These 11 are the basis of “connecting the dots.”
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
17
+ Here’s A Quick Look at the Connections
# EVM Criteria Agile Approach
1 Define WBS Features and Stories define tasks
2 Identify Organization Self organizing teams
5 Integrate WBS and OBS Self organized teams with a customer
6 Schedule Work Iterations and Releases
7Identify Products &
Milestones Working software at the end of iterations
8 Set time phased budget Fixed length iterations and releases
16 Record direct costs Fixed staff = Level of Effort
23 Determine variances Velocity measures missed features
25 Sum data and variance Missed features moved to next iteration
26 Manage action plans Replan missed features, adjust velocity
28 Incorporate changes Replan missed features, adjust velocityPerformance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
18
But First, Let’s Look At The Business Management Practices …
…That Must To Be Present Before Connecting Agile and EVM
Provide managers with information at a practical
level of summarization
Relate time phased budgets to specific
contract tasks
Enable statistical estimation of
completion costs
Track and monitor discrete project
metrics
Communicate project status
Provide quantitative data for decision making
Provide a documented project performance trail
Alert project managers to potential schedule and cost risk
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016 19
+
… By providing actionable information in units of measure meaningful to the decision makers
Agile + EVM is a Tool to Increase Probability of Program Success …
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
0. Executive Overview
20
+ Agile develops software Feature by Feature ‒ not Module by Module
21
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
With each Feature delivering increased maturity of the Needed Capabilities
0. Executive Overview
+ The People, Processes, and Tools for Agile Must all Come Togethern Success for agile means automation of all work processes.
n People rely on automated processes to delivery value on small grained boundaries without any burden on their time.
n Seamless development, test, integration, and deployment is enabled by automation.
n Without automation, agile development falls into trap of sequential development and degrades back to Scrum Fall.