+ All Categories
Home > Documents > Integrated modelling for flood risk mitigation in Romania: case study of the Timis–Bega river...

Integrated modelling for flood risk mitigation in Romania: case study of the Timis–Bega river...

Date post: 02-Jun-2018
Category:
Upload: zlatana
View: 260 times
Download: 1 times
Share this document with a friend

of 13

Transcript
  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    1/13

    Research paper

    Integrated modelling for flood risk mitigation in Romania:case study of the TimisBega river basin

    I. POPESCU,UNESCO IHE Institute for Water Education, Westvest 7, 2601 DA Delft, The Netherlands.

    E-mail: [email protected](Author for correspondence)

    A. JONOSKI,UNESCO IHE Institute for Water Education, Westvest 7, 2601 DA Delft, The Netherlands

    S.J. VAN ANDEL, UNESCO IHE Institute for Water Education, Westvest 7, 2601 DA Delft, The Netherlands

    E. ONYARI,UNESCO IHE Institute for Water Education, Westvest 7, 2601 DA Delft, The Netherlands

    V.G. MOYA QUIROGA, UNESCO IHE Institute for Water Education, Westvest 7, 2601 DA Delft, The Netherlands

    ABSTRACTAn integrated flood modelling approach has been applied in a demonstrator of a flood management system, which was developed within the frameworof a collaborative project between Romania and the Netherlands. The developed demonstrator system had two objectives: (a) operational water management under extreme conditions when actions have to be taken quickly; (b) off-line analysis and design of flood mitigation measures and alternativeThis article presents the applied approach and the achieved results for meeting the second objective. The pilot basin for the development of the systemwas theTimis Bega river basin, in which therivers Timis and Bega were considered jointly. The system is based on modelling the flood generation anrouting processes by combined development and application of hydrological and hydrodynamic models. The modelling system HEC-HMS was usefor the hydrological model, HEC-RAS for the one-dimensional hydrodynamic model and SOBEK for the two-dimensional (2D) model used for downstream flood analysis and design of mitigation measures and alternatives. The 2D model includes alternatives of deliberate dike breaching as part of th

    analysis of the system response. The analysis presented is concentrated on a specific flood event that occurred in April 2005, which occurred due to dikbreaches along the Timis river. The combination of models is first used for reconstruction of inundation patterns resulting during this flood event. Subsequently the models were used for testing flood mitigation alternatives of deliberate (planned) breaches of flood protection dikes located in the downstream part of the Timis river at the same location where they had occurred during the 2005 flood event, but at different times with respect to the arrivaof the flood hydrograph. The demonstrated approach can enable decision-makers to analyse the behaviour of the physical system and design possiblpreventive and/or mitigation measures.

    Keywords:Flood modelling; flood mitigation; dike breaches; decision support system

    1 Introduction

    Floods remain one of the most frequent and devastating natural

    hazards worldwide. While existing forecasting and warning

    systems have made a significant contribution to the reduction

    of losses due to floods, nevertheless there remains a consider-

    able potential for further prevention of losses by making use

    of technological advances for better integration of data and

    models and consequently design of better flood mitigation

    measures and issuing of more accurate forecasts and possible

    warnings. In on-line situations, flood modelling is central in

    forecasting and warning systems as it can help us to understand

    flood generation and identify the potential areas to be inun

    dated. This allows issuing of targeted early warning to down

    stream communities located in the floodplains which will b

    affected. In off-line situations flood modelling also enable

    long-term planning for flood damage reduction, which is com

    monly carried out by using the models for evaluating variou

    flood mitigation measures in order to determine which alterna

    tive will be economically and environmentally feasible, given

    the prevailing conditions. Models have different requirement

    for on-line and off-line applications. On-line models, fo

    flood forecasting, require fast and accurate simulation of dis

    charge peaks for a known water system. Often, capabilities o

    Received 5 January 2010. Accepted 29 July 2010.

    ISSN 1571-5124 print/ISSN 1814-2060 onlineDOI:10.1080/15715124.2010.512550http://www informaworld com

    Intl. J. River Basin ManagementVol. 8, Nos. 34 (2010), pp. 269280

    # 2010 International Association for Hydro-Environment Engineering and Research

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    2/13

    hot-starts and data assimilation are a pre-requisite to fulfil these

    requirements. Off-line models need to provide a physically

    based reliable simulation of the water system behaviour for a

    wide range of conditions and for changes in the modelled

    water system itself, to allow design and analysis of structural

    flood management measures. The off-line modelling systems

    need to allow users to translate proposed measures into

    changes in the model, e.g. flood plain adjustments. Integrated

    flood modelling is increasingly being demonstrated to be a

    necessity due to the complexity of the interactions among

    different components of the river and its floodplain. Various

    flood modelling studies have been carried out that show how

    interactions between rivers and floodplains can lead to accurate

    flood forecasting and prediction at critical points. Flood model-

    ling systems usually combine rainfallrunoff models with flood

    routing models. The flood routing is carried out either by

    hydrologic routing approaches, which are used to obtain theflood peak by routing flood events between streamflow

    gauging stations, or by more complex one-dimensional (1D)

    hydrodynamic models which simulate flood propagation

    based on detailed channel geometry (Blackburn and Hicks

    2002). However, in areas with complex river flow conditions,

    especially in the presence of complex riverfloodplain inter-

    actions, two-dimensional (2D) models need to be used for

    off-line spatial hydraulic analysis (Horrit and Bates 2002).

    The Netherlands has a long history of water management,

    during which significant knowledge and experience related to

    flood protectionhas been accumulated.In thiscountry, flood man-agement is currently approached as an integral part of wider water

    management and spatial planning processes. The practical

    implementation of this approach relies heavily on integrated

    flood modelling. The accumulated knowledge and experience

    in the field of forecasting excessive rainfall events, predicting

    and controlling high river water levels as well as mitigation of

    floods, can be exported to other countries in Europe and the rest

    of the world. Similar to the Netherlands, Romania is a country

    where rivers discharge into the sea. Romania is, however, a

    much larger country also characterized by mountainous catch-

    ments, which are absent in the Netherlands. Romanian Waters

    (the National Agency responsible for overall water resources

    management) complies with the legislation compatible with the

    EU regulations regarding water resources management and the

    preservation of aquatic ecosystems and water areas. In this

    respect, this agency is responsible for the ways in which surface

    and groundwater resources in the Romanian territory are used.

    The same agency is also responsible for flood management and

    control. In this area, the agencyis currently developing andimple-

    menting new, technologically advanced decision support systems

    (DSS) for flood forecasting and warning, as well as long-term

    flood risk planning and management. In these efforts, the

    agency is facing numerous challenges due to lack of modellingexperience as well as data availability and data quality assurance.

    As part of these ongoing activities, within the framework of a

    flood forecasting system demonstrator has been develope

    which can support operational water management und

    extreme conditions when rapid action has to be taken. Th

    system had a comparatively simpler (with short running time

    modelling component (only rainfall runoff model develope

    with HEC-HMS), and the focus was on the on-line integratio

    of this component with meteorological and hydrologic

    data. Next to the on-line system, integrated flood modellin

    approaches for off-line analysis and design of flood mitigatio

    alternatives were implemented, which are the focus of this pape

    This was achieved by combining the HEC-HMS model with

    1D hydrodynamic model developed with HEC-RAS and

    SOBEK 1D-2D model for flood inundation modelling. In th

    modelling approach, the Timis and Bega rivers were considere

    jointly, since their joint hydrodynamic response are conditione

    by the operation of existing hydraulic structures used for wat

    transfer between the two rivers. The present paper describes thapproach taken in the off-line integrated flood modelling an

    the usage of the models for analysis and design of possibl

    flood mitigation measure and alternatives. The focus is on th

    analysis of a particular flood event that occurred in April 2005

    when a large area close to the Romanian border with Serb

    was inundated as a consequence of dike breach failures alon

    the river Timis.Actual breaches of the dikes occurred due to stru

    tural failure (induced by poor maintenance), even though th

    water levels were barely at the overtopping level. Initially, th

    integrated modelling approach was applied for reconstructin

    this particular flood event. Subsequently the same models weused for analysis and testing of possible flood mitigation alterna

    tives. Assuming that high flood water levels and discharg

    would anyhow lead to eventual dike breaches due to overtoppin

    (even if dikes are well maintained), alternatives have been teste

    in which deliberate (planned) dike breaches are carried out at th

    same locations as those occurring during April 2005, but at diffe

    ent timingwith respect to thearrival of the flood hydrograph. Th

    approach has not been extensively researched in the past and,

    the results demonstrate, it can leadto the reduction of flood impa

    in terms of lower flood volumes and reduced area of inundatio

    2 The Timis Bega river system

    2.1 Case study location

    In terms of flooding problems, one of the most vulnerab

    regions in Romania is in the west. Furthermore, many rivers i

    this region are of a trans-boundary nature: their basins a

    either in Romania and Serbia or in Romania and Hungary. An

    event occurring in these rivers is advected downstream to th

    neighbouring country. A typical example of this situation is th

    river Timis, which in the recent past has caused severe floo

    ing in the two neighbouring countries of Romania and Serbia. the past, many dikes were constructed along this river for floo

    protection, which in return made the downstream floo

    270 I. Popescu et al.

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    3/13

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    4/13

    May 1912 was the highest, with a maximum recomputed dis-

    charge of approximately 1600 m3/s, and estimated to have a

    return period of 1 in 50 years (Hunteret al.2007).

    For comparison purposes, the hydrographs of four recorded

    floods, including the 2005 flood, are represented on the graph

    in Figure 2 and centred at the time of peak. The 2005 total

    flood volume was three times greater (about 720 million m3)

    than that of the flood in 2000, though the peaks of these two

    events were very close. In 2005, as a result of the high flood

    peak, the embankment of the right-side bank of the river Timis

    was barely overtopped, but still collapsed and multiple dike

    breaks were reported. The volume of inundation was approxi-

    mately 300 350 million m3. After the 2005 flood, a significant

    financial investment was made to restore the structural com-

    ponents of the various affected water dikes.

    In these conditions, the question naturally arises as to what

    measures need to be taken so that new flood events of thesame magnitude as the one in 2005 will not cause further

    damage in the future.

    The current flood forecasting and warning system in the

    TimisBega basin is based on empirical models which show

    the relationships of the flow at a downstream point versus the

    one at an upstream station. During the flooding crisis in Banat

    in 2005, specifically with regard to the Timis and Bega River

    basins, there were three significant time periods with high rain-

    fall. Warnings of high water levels associated with these three

    high rainfall periods were issued, but the established procedure

    did not provide sufficiently accurate forecasts, which led to flood-ing and consequently to severe flood damage. While the precipi-

    tation data have been quite reliable, lack of good rainfall runoff

    model that could produce forecasts of upstream discharges

    together with the unreliable empirical approach used for flood

    routing were the main reasons for the inaccurate forecasts.

    This event proved that better, more accurate models were

    required. It led to the conclusion that the elaboration of an inte-

    grated hydrological-hydraulic model for the TimisBega river

    basin is needed, comprising different flooding scenarios and

    indicating the spatial extension of the inundation, water depths

    and velocities.

    2.3 Availability of data for a flood event in the basin

    Before setting up an integrated model for the TimisBeg

    system, the analysis of the April 2005 flood which was carrie

    out by the Romanian Banat Water Board was taken into conside

    ation. This analysis was done on the basis of the dischargrecords at 20 gauging stations. The analysis checks the degre

    of reliability of the data concerning the gauged and ratin

    curve, i.e. the extrapolation discharges.

    The check was made for the total runoff hydrograph, th

    surface runoff and the base runoff. This analysis reported unu

    sually high estimates of the runoff coefficients a (surfac

    runoff versus rainfall) (Stanescu and Drobot 2005).

    The analysis of the available observed data for the Timis

    Bega basin for the year 2005 refers to the amount of precipitatio

    and climatic conditions prior to the flood period and to the perio

    of the flood itself (1422 April 2005) (Figure 3).The period covering two weeks before the flood event wa

    characterized by comparatively small amounts of rainfall (10

    15 mm recorded between 27 March and 1 April). Howeve

    the same period, especially the days between 8 and 13 Apri

    was characterized by a sudden increase in temperature (468

    daily average in the hilly and mountain zones). These condition

    contributed to significant snow melt in the mountainous zones.

    was estimated that the increase in soil moisture during this perio

    ranged between 24 and 40 mm, and the larger part of this so

    moisture increase was because of snowmelt (compared wi

    the contribution from precipitation).

    By the time of the big precipitation events that eventuall

    caused the flooding, the snow cover in the catchment has bee

    limited to very small areas at very high altitudes. Under the alt

    tude of 1000 m.a.s.l (corresponding to 96% of the entire area o

    the river basin) there was no snowpack. However, due to th

    above-described conditions in the previous period, the who

    catchment was already quite wet when the big flood-causing pr

    cipitation events came.

    This analysis led to the conclusion that the flood event itse

    was in fact entirely of pluvial nature and there was insignifican

    snowmelt contribution provided by the small mountainous area

    which was anyhow retained in two reservoirs in the basin (PoianMarului at 650 m.a.s.l. and Trei Ape at 870 m.a.s.l.)

    During the flood event period (1422 April 2005), significa

    rainfall occurred in three distinct time intervals separated by n

    rainfall periods which varied between 3045 h during 161

    April and 9.0015.00 h on 21 April (Figure 4). Periods

    time with reduced rainfall quantities continued after 22 Apr

    but they only fed the high discharges without contributing

    the increase of the water levels over the alarm threshold. Th

    core of the biggest rainfall, in terms of quantity, in the floo

    zone ranged between 15 and 24 h.

    According to the data recorded at the pluvial stations, th

    cumulative rainfall (1422 April) that caused the outstandin

    April 2005 flood ranged between 60 and 221 mm. The small

    272 I. Popescu et al.

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    5/13

    western mountainous zone. The spatial distribution of the

    cumulative rainfall during the flood event period is presented

    in Figure 4.

    3. The integrated model for the TimisBega system

    The Dutch Romanian project mentioned in this paper had

    Timis Bega basin. Because of the high stakes involved concern

    ing water management during a crisis, it is important that a fore

    cast of the emerging situation occurs in a structured an

    reproducible manner. These requirements are met nowadays by

    making use of hydrologic and hydrodynamic models, which

    are used by water managers in both forecasting situations awell as planning situations.

    The development and implementation of a DSS demands an

    integration of water management, knowledge management and

    hydroinformatics (Abbott 1991, 1999). Besides extended knowl

    edge of ICT and software development, attention to the quality o

    modelling and also the users demands concerning the presen

    tation and communication of the model results are require

    (Abbott and Jonoski 1998). If not enough attention is paid to

    these aspects, the DSS will not satisfy the users expectation

    and consequently the adoption by its users may be difficu

    (Jonoski and Popescu 2004).

    The developed demonstrator system of the above-mentioned

    Dutch Romanian project had two objectives: (a) operationa

    water management under extreme conditions when actions hav

    to be taken quickly; and (b) off-line analysis and design of floo

    mitigation measures and alternatives. The focus of this paper i

    to present the models which were used for developing the secon

    objectivefor theDSS forfloodprotection in theTimis Bega basin

    The integrated model used in the off-line analysis of th

    system is based on a sequential combination of hydrologica

    and hydrodynamic models. The integrated model starts wit

    the development of a hydrological model using the USACE

    HEC-HMS modelling system (a hydrological model). After thdevelopment of the HEC-HMS model, the second phase wa

    the development of a 1D hydraulic model of the major river

    Figure 3 Isohyets of precipitation, 14 22 April 2005

    Figure 4 Temporal distribution of rainfall in the Timis Bega basin

    between 14 and 22 April 2005

    Integrated modelling for flood risk mitigation in Romania 27

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    6/13

    hydrologic model. The third phase of the model development

    entailed a refinement of the second phase by integrating the

    1D-2D SOBEK model for modelling river floodplain inter-

    actions. The whole suite of models used comprised therefore

    HEC-HMS (0D), HEC-RAS (1D) and a 1D-2D SOBEK.

    All the models were calibrated and checked for sensitivity.

    Figure 5 shows the coverage of the various models as used in

    the study. The rainfall runoff model HEC-HMS was used in

    the whole catchment and the 1D hydraulic model HEC-RAS

    was used in the main channel starting at the gauging stations at

    Balint and Lugoj for the Bega and Timis rivers, respectively,

    and up to their outlets. The SOBEK 1D-2D was used for

    the floodplain starting at the gauging stations for Remetea

    and Brod.

    In transforming several rainfall time series into a flood inun-

    dation map, various interconnected components were involved,

    as shown in Figure 5. HEC-DSS was used for data storage.The measured precipitation was provided to the data storage

    HEC-DSS, which was used as input for the HEC-HMS model.

    The system, when provided with these rainfall time series, trans-

    forms them into runoff through hydrologic simulations in HEC-

    HMS. The hydrograph obtained from the rainfall runoff model

    was fed into the hydraulic model HEC-RAS that computed the

    water surface elevations. This computed discharge hydrographs

    of the HEC-RAS model were used as input into the SOBEK 1D-

    2D model that simulated the floodplain inundation.

    The elements that were used to support the full integration

    include HEC-RAS, HECDSS, HEC-HMS and SOBEK 1D-2Dmodel configurations.

    The procedure was as follows:

    (1) Inputting precipitation data into HEC-DSS for HEC-HMS.

    (2) Executing HEC-HMS.

    (3) Transferring flow values of HEC-HMS into HEC-RAS b

    establishing connection points in HEC-DSS file (output o

    HMS) and updating related input files.

    (4) Executing HEC-RAS.

    (5) Transferring discharge and waterlevel data from HEC-RA

    as boundary conditions to SOBEK 1D-2D.

    (6) Executing SOBEK 1D-2D (Figure 6).

    A good understanding of the HEC-DSS system was critical i

    this implementation to make available relevant time seri

    records from the database time series tables to the HEC-HM

    and HEC-RAS models and to allow the transfer of records.

    unique identifier (model codification) to support the connectivi

    between the features in each model was needed to spatially rela

    features across the models.

    Figure 6 Flow chart showing the coupling of HRC-HMS, HEC-RA

    and SOBEK1D-2D

    274 I. Popescu et al.

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    7/13

    The HEC-HMS model covers an area which includes the

    HEC-RAS model. HEC-HMS output was used as upstream

    boundary condition to the HEC-RAS model. Some sub-basin

    HEC-HMS hydrographs located downstream of the upstream

    boundary condition in HEC-RAS were provided as lateral

    inflow to the HEC-RAS model.

    The discharge hydrographs from the 1D HEC-RAS hydraulic

    model were provided to the 1D-2D SOBEK model as boundary

    conditions on the upstream part, and water levels were used as

    downstream boundary conditions. 2D model simulations were

    then performed with the aim of providing information about

    the inundation patterns in the riverfloodplain system of the

    TimisBega basins.

    3.1 The HEC-HMS model

    In the HEC-HMS model, the Timis Bega catchment was discre-

    tized into 20 sub-basins, based on their common physical charac-

    teristics. The other components of the system are junctions and

    reaches, which collect water from different sub-basins and

    route it downstream.

    The river network was schematized from the upstream station

    Sadova to the downstream station, at the border between

    Romania and Serbia, which in total covers a distance of

    about 275 km. In setting up the HEC-HMS model, each sub-

    basin is associated with a schematization point, called a junction,

    which represents the outlet of the sub-basin. The reaches repre-

    senting the channels are straight line connections of the junc-tions, through which the routing takes place from upstream to

    downstream.

    The HEC-HMS model was calibrated for the year 2003, a year

    without any extreme events, and then used to reproduce the 2005

    flood event.

    Each sub-basin was assumed to have uniform hydrological

    characteristics, thus the model parameters were lumped at the

    sub-basin level. The characteristics that are required in the

    model include precipitation, evaporation, physical character-

    istics such as slope, Manning roughness, channel length, etc. Pre-

    cipitation was given as input according to measuring gauges in

    the basin. The spatial distribution and contribution of the precipi-

    tation for various sub-basins, according to the measuring gauges,

    was provided by the Romanian water hydrology department,

    along with the gauge weights. The soil moisture accounting

    method (SMA) (Bennett 1998) was used to compute the losses

    in the catchment, taking into account the precipitation and poten-

    tial evapotranspiration. This method uses different storage reser-

    voirs to represent components of the runoff generation processes,

    such as canopy, soil, surface and groundwater storages. The

    exchange of water in between the components is controlled by

    exchange parameters. The storage capacity of each component,

    i.e. canopy, soil, surface and groundwater, together with theexchange parameters, was inputted into the model. The initial

    conditions of canopy, soil, surface, and groundwater were speci-

    beginning of the simulation. The potential evapotranspiration

    in the catchment was computed using the Blaney Criddl

    method, where the monthly percentage of daylight hours in the

    year, p, was computed using the maximum possible sunshin

    hours for the latitude 468north.

    Besides the junctions, the other routing elements from

    upstream to downstream are the reaches. The runoff wa

    routed downstream using the Kinematic wave method, and there

    fore the sub-basin length, slope and roughness coefficient neede

    to be specified.

    The simulation results of this HEC-HMS model for the floo

    event of 2005 were hydrographs at junctions, some of which

    were further used as upstream boundary condition for th

    HEC-RAS model, which was developed and calibrated only

    for the 2005 event. The resulting hydrographs from th

    HEC-HMS model for the river Timis at Lugoj was compared

    with the observed discharge at the same station. The result is presented in Figure 7.

    The two hydrographs show a very good match; however, th

    computed hydrograph has a higher peak than the measured one

    and a slightly later arrival of the peak. As mentioned earlier, the

    HEC-HMS model was calibrated using data from 2003, and i

    was not re-calibrated for the simulation of the 2005 event

    Given that the SMA model that was used in this HEC-HMS

    set-up requires physically meaningful parameters, the goo

    match between the measured and modelled hydrographs for con

    siderable extent can be attributed to the sufficient calibration o

    the original HEC-HMS model. This contention could be confirmed by testing the model performance with other floo

    events,but this could not be done due to thelack of available data

    3.2 The HEC-RAS model

    To schematize the river network, the river reach was introduced

    first, and then the cross-sections were provided to the model

    Figure 7 Measured and HEC-HMS modelled hydrograph on Timi

    Integrated modelling for flood risk mitigation in Romania 27

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    8/13

    An example of cross-sections that were provided is shown in

    Figure 8 (Sag station).

    Flow data were provided by the HEC-HMS-calibrated output

    hydrographs.

    The most upstream boundary condition was introduced as an

    inflow hydrograph. Downstream boundary conditions werespecified as normal depths calculated for different flow con-

    ditions. The initial conditions were provided as discharge. In

    between the upstream and the downstream HEC-RAS points,

    the sub-basins contributions were provided as lateral inflows,

    as calculated by the HEC-HMS.

    The initial purpose of the HEC-RAS model was to determine

    water levels in the downstream part of the TimisBega river

    system, especially during flood conditions. The development

    of different models was carried out in stages. During the stage

    of the HEC-RAS development, it became apparent that results

    of the HEC-RAS model could not represent well the waterlevels in the most downstream part of the TimisBega catch-

    ment, where most of the flooding occurred during the 2005

    event. Therefore, in the next stage, it was decided to model

    this last part with the SOBEK 1D-2D modelling system and

    the results from HEC-RAS served only as inputs to this last

    model (Figure 9).

    3.3 The 1D-2D Sobek model

    In general, the 1D models are computationally efficient.

    However, when applied to flooding situations, especially whenfloodplain flows are modelled, there are a number of disadvan-

    tages of 1D models, such as inability to model lateral diffusion,

    than representing it as a surface (Popescu et al. 2007). The

    are constraints, which have been addressed with the use o

    1D-2D or 2D codes. The use of 1D-2D codes rather than ju

    2D codes is necessary because during flooding events, it

    critical to have a good representation of the channel conveyanc

    processes.

    The Sobek model was used in this paper for the 1D-2D mod

    elling of the river in the downstream part of the catchment, whe

    the area is very flat. The Timis and Bega rivers were schematize

    as a 1D channel, and the floodplain was represented by a 2D gri

    using cell sizes of 100 100 m. The elevations for the 2D gr

    cells were obtained from a 30 30 m Digital Elevation Mod

    (DEM). The flooding was allowed to occur from the 1

    channel into the 2D grid. Two boundary nodes were introduce

    at the upstream and downstream side of each river reach. Floo

    ing was allowed to the 2D from 1D using a dummy branch whic

    has a weir with a control structure. The weir crest level walowered over time to simulate gradual breach developmen

    For a given crest level of the weir, the weir itself functions a

    Figure 8 Cross-section example data for the river Timis at Sag station

    Figure 9 Plan view schematizationof theTimis Bega system in HEC

    RAS

    276 I. Popescu et al.

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    9/13

    Boundary conditions for the Sobek 2D model were obtained

    from the 1D hydraulic model HEC-RAS. For the upstream

    boundary conditions flow hydrographs were used. The down-

    stream boundary condition for both rivers Timis and Bega was

    provided as water level.

    Flood maps of the event are available from MODIS remote-

    sensing images taken during the 2005 event. The extent of the

    flood from the MODIS images (Flueraru et al. 2007) was com-

    pared with the results of the Sobek model (Figure 10). The sat-

    ellite image (available in colour online) presents flooded area

    on 23 April 2005 (light blue colour, which is of our interest)

    together with the flooded area on 30 April 2005 (dark blue

    not of interest here as it was not covered by the model).

    The comparison shows a good match between the flood

    extent obtained from the Sobek model and the one registered

    by the satellite. The model simulations show that an area of

    22,088 ha was affected by the flood (at the time of theevent, this area was estimated at 25,000 ha).

    The total volume of inundation was the second criteria to

    evaluate the result obtained with the Sobek model. The simulated

    volume of inundation was around 278.9 M m3, which is similar

    to the 300 M m3 reported by Stanescu and Drobot (2005). The

    simulated water depths in the inundated area were up to 2.5 m.

    Some sensitivity analysis of the developed model was carried

    out with respect to the friction coefficient used for the 2D

    modelling grid. The Manning roughness for the 2D grid wa

    varied with values of 0.12, 0.15 and 0.08. Lower Mannin

    roughness coefficients resulted in higher velocities and increased

    flood extent downstream, as expected.

    4 Flood mitigation alternatives

    The aim of the downstream 1D/2D modelling was to simulat

    various flooding extents and propose different methods of mana

    ging the flood.

    The proposed alternatives for flood mitigation involved delib

    erate inundation by making intentional dike breaches along th

    Timis and Bega rivers.

    Depending on the magnitude of flood events, differen

    mitigation measures can be taken. One of the possible measure

    is dike breaching, though is not always the preferred one, no

    the best. However, in case of extreme events, and if the rive

    shows a history of dike failures, intentional breaching is one o

    the solutions for flood mitigation because it gives control on th

    place where flooding occurs and it releases the stresses on

    the dike.

    The location of the intentional breaches were selected in thi

    study, exactly at the same locations with the natural breaches

    formed during the 2005 event. The difference with the bas

    case is the timing of the breaches.

    These alternatives were modelled and mapped out under th

    same conditions as the 2005 flood. The section of the floodedpart of the river stretches from the gauging station Sag to Gran

    iceri for the river Timis and from Remetea to Otelec for the rive

    Bega. The total length of this section is about 120 km. The area i

    between these rivers is a highly populated area with a high econ

    omic value.

    Before an intentional dike breach is made, hydrological fore

    casts or measurements have to be carried out to realize that ther

    is a flood event that might occur. Again, different authorities and

    people have to be involved directly or indirectly either becaus

    they have to give consent and/or because they will be affecte

    by the decisions. Most important is when to take the decision

    to breach, which means that the flood timeline becomes very

    important. The flood timeline starts from the forecast moment

    and runs up to the time when pre-established critical threshold

    is exceeded. This timeline needs to be determined as accurately

    as possible so that decisions are not taken too early or too late, to

    ensure effectiveness.

    Since areas with a high economic value were to be affected b

    the flood, actions have to be taken in order to reduce the impac

    on these areas. Thus, actions that would protect people and prop

    erty from the rising water could include intentional breaching o

    dikes and inundating areas that are of low economic value, whil

    protecting areas of high economic value. This intentional breaching was modelled in this study and it was realized that the area

    that were to be affected could be greatly reduced with intentionaFigure 10 Flood extent of Sobek model in comparison with MODIS

    Integrated modelling for flood risk mitigation in Romania 27

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    10/13

    The following mitigation alternatives were considered:

    (1) Base case with no mitigation measures

    (2) Dike breaching after the arrival of the peak.

    (3) Dike breaching at the start of the flood event.

    4.1 The base case

    The 2005 flood event was modelled by taking into account the

    breaching at three locations on right embankment of Timis

    river. The breaches were located at 6.7, 6.9 and 8.25 km, respect-

    ively, upstream of the Romanian Serbian border. The two

    breaches at 6.7 and 6.9 km joined together very quickly,

    forming just one breach, which in the model was considered

    to be located at 6.8 km. The width of the breaches was modelled

    to be 250 m for the one at 6.8 km and 180 m, for the one at

    8.25 km. In all subsequent figures, the most upstream breach isreferred as breach 1 (8.25 km) and the most downstream one

    is referred as breach 2 (6.8 km).

    The model covered the period from 14 April 2005 to 24 April

    2005, midnight. The breaches were reported to be formed on 20

    April, around 15.00. The total inflow volume of the 2005 flood

    event was up to 513.3 M m3 and the outflow volume as it was

    modelled was 234.4 M m3, meaning that all the remaining

    volume inundated the floodplain (278.9 M m3). Figure 10

    shows the flood map for the TimisBega basin for the 2005

    flood event, and the area of 22,088 ha which resulted to be

    affected by the flood.

    The model first overtops the dikes and overflows and then

    finally the dike breach occurs. The simulation shows that the

    area in between the Bega and Timis rivers is highly affected:

    54% of the area was covered by a water depth of less than

    1 m, 33% of the area was covered by a water depth of

    between 1 and 2 m and the rest was covered by a water depth

    that was more than 2 m. The total area that was actually

    covered during the flooding event was estimated to be

    25,000 ha (Stanescu and Drobrot 2005). The model was able

    to show the areas that were affected by the flood as a total o

    22,088 ha, which means that the model under-predicted we

    with an error of about 12%.

    The input hydrograph together with the hydrograph at the tw

    breach locations and the outflow hydrograph as resulted from th

    model are presented in Figure 11.

    Due to the high volume of water flooding the area ju

    before the border with Serbia, several pumps were used

    evacuate the water. These pumps evacuated 99.6 M m3

    water from 3 May to 5 July 2005 (Nicoara and Ion 2005). I

    the same period, according to Stanescu and Drobrot (2005

    from the measured hydrographs between the Sag station, o

    Timis and Graniceri, at the border of the model, a volume o

    213 M m3 more than the usual flow on the same sector, flo

    out on Graniceri section. These two values add up to wh

    the model simulated.

    Figure 12 presents the area affected by floods in 2005, and thdepth of the flooding.

    Figure 11 Computed hydrographs before the breaches after the

    278 I. Popescu et al.

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    11/13

    4.2 Dike breach after the arrival of the flood peak

    The second case taken into consideration was an intentional

    breaching carried out after the arrival of the flood peak in

    the TimisBega catchment, on 21 April 2005, at 15.00.

    Taking such a mitigation measure reduced the floodingeffects, since the model shows that the total area affected by

    the flood was 13,122 ha (Figure 13). In this case the inundation

    water depths dropped, as compared with the base case; there

    was only 10% of the area with water depth between 1.5 and

    2.5 m. The volume of the inundation was computed to be

    161 M m3.

    The inflow, outflow and breaches hydrographs for the case of

    dike breaching after the arrival of the flood peak are presented in

    Figure 14.

    4.3 Dike breach at the start of the flood event

    The effect of dike breaching at the start of the event can beseen in

    Figure 15. The start of the event was on 20 April, 4 h later than

    the actual breaching, in the base case. In the case of breaching at

    the start of the event, the simulation showed that the extent of the

    flood on the area in between the Timis and Bega rivers can be

    reduced considerably. In this case, the inundation water depth

    were as high as in the base case, more than 50% of the are

    with water depth between 1.5 and 2.5 m. The volume of the inun

    dation was computed to be 141 M m3

    .

    Figure 13 The 2005 flood extent taking into consideration dike breach

    Figure 14 Computed hydrographs before breaches, after breaches an

    at the breach location in the case of breaching after the arrival of th

    flood peak

    Figure 15 The 2005 flood extent in the case of a dike breach at th

    Integrated modelling for flood risk mitigation in Romania 27

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    12/13

    The inflow, outflow and breaches hydrographs for the case of

    dike breaching before the arrival of the flood peak are presented

    in Figure16. The area affectedby the flood in this case is 10,127 ha.

    5 Conclusion

    The hydrodynamic model developed for the TimisBega system

    is a demonstrator which presents forecasted water levels and dis-

    charges for the rivers TimisBega. This is an efficient way todemonstrate the possibilities of implementation of a model,

    with the aim of helping decision-makers to understand flood

    propagation and take the appropriate mitigation measures in

    case of a flooding event. In Romania these models could be of

    great help to the Romanian authorities.

    Modelling can support decision-makers in responding to a

    flood event, although there are uncertainties that can be expected

    from forecasting and the involved models. In the TimisBega

    basin the flood timeline that was deduced from the 2005 flood

    showed that there were 8 h in Timis and 6 h in Bega available

    as the maximum possible warning time after the falling of the

    peak rainfall to the arrival of the runoff peak at the outlet.

    The timing for the intentional breaching was while the rainfall

    was still on the rising limb of the hydrograph. Modelling of

    breaching is a difficult task, because it requires description of

    the breach development, which has a lot of uncertainties. Taking

    into account the effects of breach development and the related

    uncertainties of that process was beyond the scope of this study.

    One of the consequences of applying different mitigation

    measures, in order to protect one area in the basin, can have as

    an effect, flooding of another area further downstream in the

    basin. This type of problem was not part of the present study.

    Although the work presented here in is case-specific, the pro-posed mitigation measures proved to be efficient in reducing the

    impacts of flood downstream and therefore can be used in similar

    Aknowledgements

    The financial support for this work was provided by the Dutc

    Government, through Partners for Water. All the data require

    for modelling were provided by Romanian Waters, Ban

    region.

    References

    Abbott, M.B., 1991. Hydroinformatics: information technolog

    and the aquatic environment. Aldershot, UK/Brookfiel

    USA: Ashgate.

    Abbott, M.B., 1999. Introducing hydroinformatics. Journal

    Hydroinformatics, 1, 319.

    Abbott, M.B. and Jonoski, A., 1998. Promoting collaborativdecision-making through electronic networking. Proc. 3r

    Int. conference on hydroinformatics, Copenhagen, Denmark

    Bennett, T.H., 1998.Development and application of a contin

    ous soil moisture accounting algorithm for the Hydrolog

    Engineering Center NHydrologic Modeling System (HEC

    HMS). Thesis (MSc). Department of Civil and Environment

    Engineering, University of California, Davis.

    Blackburn, J. and Hicks, F.E., 2002. Combined flood routing an

    flood level forecasting.Canadian Journal of Civil Enginee

    ing, 29, 6475.

    Flueraru, C., et al., 2007. Mapping and monitoring th20052006 floods in Romania, using remote sensing tech

    niques. Proceedings of geomatics for disaster and ri

    management conference, Toronto, Canada, May, 2007.

    Horrit, M.S. and Bates, P.D., 2002. Evaluation of 1D and 2

    numerical models for predicting river flood inundatio

    Journal of Hydrology, 268, 8799.

    Hunter, N.,et al., 2007. Simple spatially-distributed models fo

    predicting flood inundation: a review. Geomorphology, 9

    (3 4), 208 225.

    INHGA, 2004. Life-Timis: protection of the river life by mitigatio

    of flood damages-European Commission, Directorate Enviro

    ment, Direction (LIFE-LIFE00ENV/RO/000986).2000 200Jonoski, A. and Popescu, I., 2004. The hydroinformati

    approach to integrated river basin management. Proceeding

    of the water observation and information system for decisio

    support conference, Ohrid, Macedonia, May 2004.

    Nicoara, S. and Ion, M., 2005. Aspects regarding the crisis man

    agement during the flood period in Banat province, Apr

    14-July 5. Flood hazards mitigation seminar proceeding

    Timisoara, November 2022, 2005.

    Popescu, I, Lobbrecht, A., and Jonoski, A., 2007. Final proje

    report for DSS feasibility study in Romania. Project repor

    UNESCO-IHE, Delft, The Netherlands.Stanescu, V.A. and Drobot, R., 2005. Viitura din perioad

    14-30 aprilie n bazinul hidrografic Timis Bega. Revis

    Figure 16 Computed hydrographs before breaches, after breaches and

    at the breach location in the case of breaching before the arrival of theflood peak

    280 I. Popescu et al.

  • 8/10/2019 Integrated modelling for flood risk mitigation in Romania: case study of the TimisBega river basinmania

    13/13

    Copyright of International Journal of River Basin Management is the property of Taylor & Francis Ltd and its

    content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's

    express written permission. However, users may print, download, or email articles for individual use.


Recommended