+ All Categories
Home > Documents > Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process...

Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process...

Date post: 13-Oct-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
89
© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering Integrated Process Risk Management (IPRM) for Refineries and Petrochemical Complexes K. Torabi, B. Karimi, R. Parmar, M. Oliverio and K. Dinnie Nuclear Safety Solutions Ltd. Toronto, Ontario, Canada
Transcript
Page 1: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Integrated Process Risk Management (IPRM)

for Refineries and Petrochemical Complexes

K. Torabi, B. Karimi, R. Parmar, M. Oliverio and K. Dinnie

Nuclear Safety Solutions Ltd.Toronto, Ontario, Canada

Page 2: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Why IPRM is needed?

Page 3: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Why IPRM is needed?

The operation of refineries, petrochemical complexes The operation of refineries, petrochemical complexes and nuclear power plants is so complicated that, in and nuclear power plants is so complicated that, in many situations, engineering, maintenance and many situations, engineering, maintenance and operating decisions cannot be easily prioritized nor operating decisions cannot be easily prioritized nor optimized solely on an individual’s knowledge and optimized solely on an individual’s knowledge and experience.experience.

Page 4: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Why IPRM is needed?

The operation of refineries, petrochemical complexes The operation of refineries, petrochemical complexes and nuclear power plants is so complicated that, in and nuclear power plants is so complicated that, in many situations, engineering, maintenance and many situations, engineering, maintenance and operating decisions cannot be easily prioritized nor operating decisions cannot be easily prioritized nor optimized solely on an individual’s knowledge and optimized solely on an individual’s knowledge and experience.experience.

This is where IPRM tools can play a very important This is where IPRM tools can play a very important role to integrate the human role to integrate the human knowledge & experienceknowledge & experiencewith actual with actual statisticalstatistical data & mathematical models in data & mathematical models in order to order to simplify, prioritize and optimize the decision simplify, prioritize and optimize the decision making process.making process.

Page 5: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Objective

Page 6: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Objective

The objective of this presentation is to show how The objective of this presentation is to show how the IPRM can be used to quantify and optimize the the IPRM can be used to quantify and optimize the maintenance activities in refineries, petrochemical maintenance activities in refineries, petrochemical complexes, power plants, and any other largecomplexes, power plants, and any other large--scale scale manufacturing plant.manufacturing plant.

Page 7: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Objective

The objective of this presentation is to show how The objective of this presentation is to show how the IPRM can be used to quantify and optimize the the IPRM can be used to quantify and optimize the maintenance activities in refineries, petrochemical maintenance activities in refineries, petrochemical complexes, power plants, and any other largecomplexes, power plants, and any other large--scale scale manufacturing plant.manufacturing plant.

Who would be interested in the IPRM toolbox?Who would be interested in the IPRM toolbox?

•• Plant managersPlant managers

•• Insurance companiesInsurance companies

•• InvestorsInvestors

•• Environmental and Safety Regulators or CommissionersEnvironmental and Safety Regulators or Commissioners

Page 8: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM Outputs

Page 9: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM Outputs

Daily engineering and plant management Daily engineering and plant management duties include tasks to:duties include tasks to:

Page 10: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM Outputs

Daily engineering and plant management Daily engineering and plant management duties include tasks to:duties include tasks to:

•• Quantify risks associated with equipment failures Quantify risks associated with equipment failures in different processes. in different processes. Determine the Determine the significancesignificance of the failures in term of production of the failures in term of production losses ($). losses ($).

Page 11: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM Outputs

Daily engineering and plant management Daily engineering and plant management duties include tasks to:duties include tasks to:

•• Quantify risks associated with equipment failures Quantify risks associated with equipment failures in different processes. in different processes. Determine the Determine the significancesignificance of the failures in term of production of the failures in term of production losses ($). losses ($).

•• Prioritize maintenancePrioritize maintenance activities, and plant activities, and plant modifications in different processes and units for modifications in different processes and units for different equipment.different equipment.

Page 12: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM Outputs

Daily engineering and plant management Daily engineering and plant management duties include tasks to:duties include tasks to:

•• Quantify risks associated with equipment failures Quantify risks associated with equipment failures in different processes. in different processes. Determine the Determine the significancesignificance of the failures in term of production of the failures in term of production losses ($). losses ($).

•• Prioritize maintenancePrioritize maintenance activities, and plant activities, and plant modifications in different processes and units for modifications in different processes and units for different equipment.different equipment.

•• Optimize the frequencyOptimize the frequency of inspections and of inspections and equipment testing.equipment testing.

Page 13: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

How is IPRM model How is IPRM model developed?developed?

Page 14: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM Inputs

Plant Design Documents and Drawings Plant Design Documents and Drawings

((PFDsPFDs and and P&IDsP&IDs))

++

Operational and Maintenance DataOperational and Maintenance Data

(Process Engineers & Maintenance Staff(Process Engineers & Maintenance Staff

Historical Data, Work Orders, Human Errors Historical Data, Work Orders, Human Errors

Failure Events, Event Durations & Frequencies)Failure Events, Event Durations & Frequencies)

Page 15: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM steps

Page 16: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM steps

1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers, generator). Operating history helps to identify key components and events in each process.

Page 17: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM steps

1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers, generator). Operating history helps to identify key components and events in each process.

2. Defining the failure modes for the important components (including Human Errors).

Page 18: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM steps

1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers, generator). Operating history helps to identify key components and events in each process.

2. Defining the failure modes for the important components (including Human Errors).

3. Classifying failures into certain production loss categories (e.g., 10%, 50% or 100% production losses). These inputs are obtained from process engineers and operators.

Page 19: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM steps

Page 20: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM steps

4. Assigning failure rates to each failure mode, using either the generic data bases or plant specific data.

Page 21: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM steps

4. Assigning failure rates to each failure mode, using either the generic data bases or plant specific data.

5. Assigning recovery times to each failure event (i.e., plant experience).

Page 22: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM steps

4. Assigning failure rates to each failure mode, using either the generic data bases or plant specific data.

5. Assigning recovery times to each failure event (i.e., plant experience).

6. and finally, summarizing everything in a table, so that a fault-tree model can be produced.

Page 23: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Modeling Procedure: Start with the PFD of each process unit.

Page 24: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Modeling Procedure: From PFD to more detailed drawings (e.g., P&ID)

Page 25: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Modeling Procedure: From P&ID to Fault-Tree Diagram (Boolean algebra)

Page 26: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Modeling Procedure: From Fault-Tree Diagram to MS Excel Spreadsheet

Page 27: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Modeling Procedure: From Fault-Tree Diagram to MS Excel Spreadsheet

Page 28: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Some of the main processes in a typical refinery are:

• Fractionation (atmospheric & vacuum distillation)• Fluidized Catalytic Cracking• Hydrocracking• Alkylation• Isomerization• Reforming• Extraction• Dewaxing• MTBE unit

Integrated Process Risk Management

Page 29: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

IPRM Output

VACUUM

COOLING WATER

I&C

ISOMERIZATION

ALKYLATION

ISOMAX

FCC

ELECTRICAL

LUBE TOWER

STEAM

FRACTIONATION

Process Significance RankingProcess Significance Ranking

Page 30: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Maintenance Optimizationin

Cooling Water Supply System of a 50,000 BPD Refinery

Case Study

Page 31: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Problem DefinitionProblem Definition

With $50K budget, and known history of With $50K budget, and known history of problems in Cooling Water system:problems in Cooling Water system:Where should the money be spent to Where should the money be spent to maximize the reliability of the cooling maximize the reliability of the cooling

water supply system?water supply system?

Case Study

Page 32: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

REFORMER

VACUUM

ATMOSPHERIC

LUBE

TOWER

CRACKING

DISTILLATE

ALKYLATION

Cooling Water Supply System in a Refinery

Heat & Material Heat & Material BalanceBalance

Page 33: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

REFORMER

VACUUM

ATMOSPHERIC

LUBE

TOWER

CRACKING

DISTILLATE

ALKYLATION

Cooling Water Supply System in a Refinery

Heat & Material Heat & Material BalanceBalance

Page 34: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

REFORMER

VACUUM

ATMOSPHERIC

LUBE

TOWER

CRACKING

DISTILLATE

ALKYLATION

Cooling Water Supply System in a Refinery

Heat & Material Heat & Material BalanceBalance

Page 35: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

REFORMER

VACUUM

ATMOSPHERIC

LUBE

TOWER

CRACKING

DISTILLATE

ALKYLATION

Cooling Water Supply System in a Refinery

Heat & Material Heat & Material BalanceBalance

Page 36: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Cooling Water Supply System in a Refinery

REFORMER

VACUUM

ATMOSPHERIC

LUBE

TOWER

CRACKING

DISTILLATE

ALKYLATION

Page 37: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Cooling Water Supply System in each process unit

Page 38: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Cooling Water Supply System in each process unit

Page 39: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Maintenance Optimization and Design Prioritization

Page 40: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Maintenance Optimization and Design Prioritization

Adding a new standby cooling water supply pump for summer heat peaks?

OR

Adding a valve for cooling water supply to the fractionation main condenser?

Page 41: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Maintenance Optimization and Design Prioritization

Adding a new standby cooling water supply pump for summer heat peaks?

OR

Adding a valve for cooling water supply to the fractionation main condenser?

Page 42: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Supply CW Pump Arrangement

Page 43: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Supply CW Pump Arrangement

Page 44: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Supply CW Pump Arrangement

Fractionation HeatexchangerFractionation Heatexchanger

Page 45: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

Page 46: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

•• Existing CW loop has 3 pumps. Depending on Existing CW loop has 3 pumps. Depending on cooling loads at different time of year, 1, 2 or all 3 cooling loads at different time of year, 1, 2 or all 3 pumps are running.pumps are running.

Page 47: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

•• Existing CW loop has 3 pumps. Depending on Existing CW loop has 3 pumps. Depending on cooling loads at different time of year, 1, 2 or all 3 cooling loads at different time of year, 1, 2 or all 3 pumps are running.pumps are running.

•• In In hot summer days hot summer days (P=0.2), when all 3 pumps (P=0.2), when all 3 pumps are running there is no standby pump available.are running there is no standby pump available.

Page 48: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

•• Existing CW loop has 3 pumps. Depending on Existing CW loop has 3 pumps. Depending on cooling loads at different time of year, 1, 2 or all 3 cooling loads at different time of year, 1, 2 or all 3 pumps are running.pumps are running.

•• In In hot summer days hot summer days (P=0.2), when all 3 pumps (P=0.2), when all 3 pumps are running there is no standby pump available.are running there is no standby pump available.

•• Trip of Trip of oneone (1/3) (1/3) of the pumps in hot summer of the pumps in hot summer days, would require one or two of the processes to days, would require one or two of the processes to be shutdown be shutdown (i.e., 40% loss in total production).(i.e., 40% loss in total production).

Page 49: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

•• Existing CW loop has 3 pumps. Depending on Existing CW loop has 3 pumps. Depending on cooling loads at different time of year, 1, 2 or all 3 cooling loads at different time of year, 1, 2 or all 3 pumps are running.pumps are running.

•• In In hot summer days hot summer days (P=0.2), when all 3 pumps (P=0.2), when all 3 pumps are running there is no standby pump available.are running there is no standby pump available.

•• Trip of Trip of oneone (1/3) (1/3) of the pumps in hot summer of the pumps in hot summer days, would require one or two of the processes to days, would require one or two of the processes to be shutdown be shutdown (i.e., 40% loss in total production).(i.e., 40% loss in total production).

•• Trip of Trip of twotwo (2/3) of the pumps in summer, forces (2/3) of the pumps in summer, forces the plant to be shutdown the plant to be shutdown (i.e., 100% loss).(i.e., 100% loss).

Page 50: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Cooling Water Supply System

40% Loss40% Loss100% Loss100% Loss

10% Loss 10% Loss

REFORMER

VACUUM

ATMOSPHERIC

LUBE

TOWER

CRACKING

DISTILLATE

ALKYLATION

Page 51: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

Page 52: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

•• Build the IPRM model with 4 pumps and compare the Build the IPRM model with 4 pumps and compare the result with the same model with 3 pumps.result with the same model with 3 pumps.

Page 53: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

•• Build the IPRM model with 4 pumps and compare the Build the IPRM model with 4 pumps and compare the result with the same model with 3 pumps.result with the same model with 3 pumps.

•• Compare the total annual losses for each design; Compare the total annual losses for each design; before and after the modification:before and after the modification:

Page 54: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

•• Build the IPRM model with 4 pumps and compare the Build the IPRM model with 4 pumps and compare the result with the same model with 3 pumps.result with the same model with 3 pumps.

•• Compare the total annual losses for each design; Compare the total annual losses for each design; before and after the modification:before and after the modification:

REDUCED RISK> REDUCED RISK> 350,000 lit/yr (with 3 pumps)350,000 lit/yr (with 3 pumps)--348,000 lit/yr (with 4 pumps) x $0.1/lit (net348,000 lit/yr (with 4 pumps) x $0.1/lit (net--profit)= profit)= $200 profit loss prevented/yr $200 profit loss prevented/yr

Page 55: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

•• Build the IPRM model with 4 pumps and compare the Build the IPRM model with 4 pumps and compare the result with the same model with 3 pumps.result with the same model with 3 pumps.

•• Compare the total annual losses for each design; Compare the total annual losses for each design; before and after the modification:before and after the modification:

REDUCED RISK> REDUCED RISK> 350,000 lit/yr (with 3 pumps)350,000 lit/yr (with 3 pumps)--348,000 lit/yr (with 4 pumps) x $0.1/lit (net348,000 lit/yr (with 4 pumps) x $0.1/lit (net--profit)= profit)= $200 profit loss prevented/yr $200 profit loss prevented/yr

MODIFICATION COSTS>MODIFICATION COSTS> $50,000 investment.$50,000 investment.

Page 56: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

•• Build the IPRM model with 4 pumps and compare the Build the IPRM model with 4 pumps and compare the result with the same model with 3 pumps.result with the same model with 3 pumps.

•• Compare the total annual losses for each design; Compare the total annual losses for each design; before and after the modification:before and after the modification:

REDUCED RISK> REDUCED RISK> 350,000 lit/yr (with 3 pumps)350,000 lit/yr (with 3 pumps)--348,000 lit/yr (with 4 pumps) x $0.1/lit (net348,000 lit/yr (with 4 pumps) x $0.1/lit (net--profit)= profit)= $200 profit loss prevented/yr $200 profit loss prevented/yr

MODIFICATION COSTS>MODIFICATION COSTS> $50,000 investment.$50,000 investment.

•• 250yrs ROI; Obviously not a high priority proposal!250yrs ROI; Obviously not a high priority proposal!

Page 57: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

Page 58: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

The numbers were based on a plant located in The numbers were based on a plant located in Ontario, Canada. However, if the plant was located Ontario, Canada. However, if the plant was located in Texas or somewhere in Saudi Arabia, the in Texas or somewhere in Saudi Arabia, the decision could be different!decision could be different!

Page 59: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

The numbers were based on a plant located in The numbers were based on a plant located in Ontario, Canada. However, if the plant was located Ontario, Canada. However, if the plant was located in Texas or somewhere in Saudi Arabia, the in Texas or somewhere in Saudi Arabia, the decision could be different!decision could be different!

•• The probability of hot summer days would be The probability of hot summer days would be different (P>0.2)different (P>0.2)

Page 60: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

The numbers were based on a plant located in The numbers were based on a plant located in Ontario, Canada. However, if the plant was located Ontario, Canada. However, if the plant was located in Texas or somewhere in Saudi Arabia, the in Texas or somewhere in Saudi Arabia, the decision could be different!decision could be different!

•• The probability of hot summer days would be The probability of hot summer days would be different (P>0.2)different (P>0.2)

•• The plant operating experience (i.e., historical The plant operating experience (i.e., historical failure rate) of the pumps could be different.failure rate) of the pumps could be different.

Page 61: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 4th pump to the existing 3 parallel pumps in the CW loop?

The numbers were based on a plant located in The numbers were based on a plant located in Ontario, Canada. However, if the plant was located Ontario, Canada. However, if the plant was located in Texas or somewhere in Saudi Arabia, the in Texas or somewhere in Saudi Arabia, the decision could be different!decision could be different!

•• The probability of hot summer days would be The probability of hot summer days would be different (P>0.2)different (P>0.2)

•• The plant operating experience (i.e., historical The plant operating experience (i.e., historical failure rate) of the pumps could be different.failure rate) of the pumps could be different.

As a result, the conclusion could be different.As a result, the conclusion could be different.

Page 62: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Maintenance Optimization and Design Prioritization

Adding a new standby cooling water supply pump for summer heat peaks?

OR

Adding a valve for cooling water supply to the fractionation main condenser?

Page 63: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

CW supply control valve

Fractionation Fractionation HeatexchangerHeatexchanger

i non

Page 64: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

CW supply control valve

Fractionation Fractionation HeatexchangerHeatexchanger

i non

Page 65: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 2nd valve parallel to the existing CW supply valve (PV501)

Page 66: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 2nd valve parallel to the existing CW supply valve (PV501)

The most important The most important sequences of events?sequences of events?

Page 67: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 2nd valve parallel to the existing CW supply valve (PV501)

Page 68: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 2nd valve parallel to the existing CW supply valve (PV501)

Create a new version of the IPRM model with two Create a new version of the IPRM model with two valves in parallel, and compare with the baseline.valves in parallel, and compare with the baseline.

Page 69: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 2nd valve parallel to the existing CW supply valve (PV501)

Create a new version of the IPRM model with two Create a new version of the IPRM model with two valves in parallel, and compare with the baseline.valves in parallel, and compare with the baseline.

REDUCED RISK> REDUCED RISK> 350,000 lit/yr (loss before)350,000 lit/yr (loss before)--23,000 lit/yr (loss after modification) x $0.1/lit 23,000 lit/yr (loss after modification) x $0.1/lit (net(net--profit)= profit)= $33,000 profit loss prevented/yr$33,000 profit loss prevented/yr

Page 70: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 2nd valve parallel to the existing CW supply valve (PV501)

Create a new version of the IPRM model with two Create a new version of the IPRM model with two valves in parallel, and compare with the baseline.valves in parallel, and compare with the baseline.

REDUCED RISK> REDUCED RISK> 350,000 lit/yr (loss before)350,000 lit/yr (loss before)--23,000 lit/yr (loss after modification) x $0.1/lit 23,000 lit/yr (loss after modification) x $0.1/lit (net(net--profit)= profit)= $33,000 profit loss prevented/yr$33,000 profit loss prevented/yr

MODIFICATION COSTS>MODIFICATION COSTS> $50,000 investment.$50,000 investment.

Page 71: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

AAdding a 2nd valve parallel to the existing CW supply valve (PV501)

Create a new version of the IPRM model with two Create a new version of the IPRM model with two valves in parallel, and compare with the baseline.valves in parallel, and compare with the baseline.

REDUCED RISK> REDUCED RISK> 350,000 lit/yr (loss before)350,000 lit/yr (loss before)--23,000 lit/yr (loss after modification) x $0.1/lit 23,000 lit/yr (loss after modification) x $0.1/lit (net(net--profit)= profit)= $33,000 profit loss prevented/yr$33,000 profit loss prevented/yr

MODIFICATION COSTS>MODIFICATION COSTS> $50,000 investment.$50,000 investment.

2yrs ROI;2yrs ROI; Implement this modification as soon as Implement this modification as soon as possiblepossible √√

Page 72: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Summary

Page 73: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Summary

IPRM is a simple tool for risk quantification that can IPRM is a simple tool for risk quantification that can be used to: be used to:

Page 74: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Summary

IPRM is a simple tool for risk quantification that can IPRM is a simple tool for risk quantification that can be used to: be used to:

•• Optimizing maintenance decisions Optimizing maintenance decisions

Page 75: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Summary

IPRM is a simple tool for risk quantification that can IPRM is a simple tool for risk quantification that can be used to: be used to:

•• Optimizing maintenance decisions Optimizing maintenance decisions

•• Prioritizing design modifications.Prioritizing design modifications.

Page 76: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Summary

IPRM is a simple tool for risk quantification that can IPRM is a simple tool for risk quantification that can be used to: be used to:

•• Optimizing maintenance decisions Optimizing maintenance decisions

•• Prioritizing design modifications.Prioritizing design modifications.

•• Ranking processes and units that can help to Ranking processes and units that can help to adopt better asset management strategies.adopt better asset management strategies.

Page 77: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Summary

IPRM is a simple tool for risk quantification that can IPRM is a simple tool for risk quantification that can be used to: be used to:

•• Optimizing maintenance decisions Optimizing maintenance decisions

•• Prioritizing design modifications.Prioritizing design modifications.

•• Ranking processes and units that can help to Ranking processes and units that can help to adopt better asset management strategies.adopt better asset management strategies.

•• Optimizing logistics and spareOptimizing logistics and spare--part procurementpart procurement

Page 78: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Conclusions

Page 79: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Conclusions

•• The IPRM is a decision support system. It can be The IPRM is a decision support system. It can be used for engineering, operational and financial used for engineering, operational and financial decision making.decision making.

Page 80: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Conclusions

•• The IPRM is a decision support system. It can be The IPRM is a decision support system. It can be used for engineering, operational and financial used for engineering, operational and financial decision making.decision making.

•• The IPRM model is different than process The IPRM model is different than process simulation. It is much simpler and quicker than simulation. It is much simpler and quicker than process simulation. process simulation.

Page 81: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Conclusions

•• The IPRM is a decision support system. It can be The IPRM is a decision support system. It can be used for engineering, operational and financial used for engineering, operational and financial decision making.decision making.

•• The IPRM model is different than process The IPRM model is different than process simulation. It is much simpler and quicker than simulation. It is much simpler and quicker than process simulation. process simulation.

•• The results are plant specific and should be The results are plant specific and should be updated with new operating experience every few updated with new operating experience every few years, and after any change in process design.years, and after any change in process design.

Page 82: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Conclusions

•• The IPRM is a decision support system. It can be The IPRM is a decision support system. It can be used for engineering, operational and financial used for engineering, operational and financial decision making.decision making.

•• The IPRM model is different than process The IPRM model is different than process simulation. It is much simpler and quicker than simulation. It is much simpler and quicker than process simulation. process simulation.

•• The results are plant specific and should be The results are plant specific and should be updated with new operating experience every few updated with new operating experience every few years, and after any change in process design.years, and after any change in process design.

•• The model maintenance is very simple and The model maintenance is very simple and straightforward.straightforward.

Page 83: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

Thank You

Page 84: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

PM frequency optimizationPM frequency optimization

Page 85: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

PM frequency optimizationPM frequency optimization

Any other options?Any other options?

Page 86: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

PM frequency optimizationPM frequency optimization

Any other options?Any other options?

•• Number of hot summer days not within our Number of hot summer days not within our control! But, improving the reliability of the control! But, improving the reliability of the existing 3 pumps is.existing 3 pumps is.

Page 87: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

PM frequency optimizationPM frequency optimization

Any other options?Any other options?

•• Number of hot summer days not within our Number of hot summer days not within our control! But, improving the reliability of the control! But, improving the reliability of the existing 3 pumps is.existing 3 pumps is.

•• Additional preventive maintenance, upgrading Additional preventive maintenance, upgrading pumps, or glandpumps, or gland--seals would reduce the failure seals would reduce the failure frequency from frequency from 0.01 trips/yr to 0.001 trips/yr 0.01 trips/yr to 0.001 trips/yr

Page 88: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

PM frequency optimizationPM frequency optimization

Any other options?Any other options?

•• Number of hot summer days not within our Number of hot summer days not within our control! But, improving the reliability of the control! But, improving the reliability of the existing 3 pumps is.existing 3 pumps is.

•• Additional preventive maintenance, upgrading Additional preventive maintenance, upgrading pumps, or glandpumps, or gland--seals would reduce the failure seals would reduce the failure frequency from frequency from 0.01 trips/yr to 0.001 trips/yr 0.01 trips/yr to 0.001 trips/yr

•• Additional preventive maintenance would cost Additional preventive maintenance would cost $3,000/yr$3,000/yr

Page 89: Integrated Process Risk Management (IPRM)€¦ · 1. Identifying major components for each process in which their failures lead to production loss (e.g., pumps, valves, heat-exchangers,

© 2005 Nuclear Safety Solutions Limited Enhancing performance through partnering

PM frequency optimizationPM frequency optimization

Any other options?Any other options?

•• Number of hot summer days not within our Number of hot summer days not within our control! But, improving the reliability of the control! But, improving the reliability of the existing 3 pumps is.existing 3 pumps is.

•• Additional preventive maintenance, upgrading Additional preventive maintenance, upgrading pumps, or glandpumps, or gland--seals would reduce the failure seals would reduce the failure frequency from frequency from 0.01 trips/yr to 0.001 trips/yr 0.01 trips/yr to 0.001 trips/yr

•• Additional preventive maintenance would cost Additional preventive maintenance would cost $3,000/yr$3,000/yr

•• The new ROI would be The new ROI would be 25yrs25yrs. Still you may decide . Still you may decide against the additional maintenance, and allocate against the additional maintenance, and allocate the existing resources to other equipment.the existing resources to other equipment.


Recommended