Integrated Regional Water Management Grant Program

Date post: 22-Jan-2016
Category:
Upload: jam
View: 29 times
Download: 0 times
Share this document with a friend
Description:
Integrated Regional Water Management Grant Program. Proposition 50 Implementation Round 2, Step 2 Applicant Informational Workshop Sacramento – December 5, 2007 Riverside – December 6, 2007. Agenda. Welcome & Introductions Workshop Format Presentations Questions Break - PowerPoint PPT Presentation
Popular Tags:
13
Integrated Regional Water Management Grant Program Proposition 50 Implementation Round 2, Step 2 Applicant Informational Workshop Sacramento – December 5, 2007 Riverside – December 6, 2007
Transcript
Page 1: Integrated Regional Water Management Grant Program

Integrated Regional Water Management Grant Program

Proposition 50 Implementation Round 2, Step 2

Applicant Informational Workshop

Sacramento – December 5, 2007

Riverside – December 6, 2007

Page 2: Integrated Regional Water Management Grant Program

Agenda

Welcome & Introductions Workshop Format Presentations Questions Break Workshop Breakout Tables

Page 3: Integrated Regional Water Management Grant Program

Welcome and Introductions

Page 4: Integrated Regional Water Management Grant Program

Workshop Format

Presentations (45 Minutes) – Available Funding and Schedule– Economics

Break (10 Minutes) Workshop Tables (3 hours with 30 Minute Rotation)

1. General Questions & What is an Adopted Plan 2. Economic Analysis and Other Expected Benefits 3. Workplan / Budget and Schedule 4. Scientific and Technical Merit, Monitoring Assessment and

Performance Measures 5. Program Preferences 6. FAAST

Page 5: Integrated Regional Water Management Grant Program

Final Call Back List

The Step 2 application due date has been extended to January 28, 2008 at 5:00 p.m.

DWR and SWRCB have released the final nine (9) Step 2 Call Back list

Northern California– 10796 Humboldt– 10789 Kings River Conservation District– 10800 Nevada Irrigation District (CABY)– 10791 San Luis Obispo, County – 10777 Tomales Bay Watershed Council Foundation

Southern California– 10803 Antelope Valley – 10775 Orange County – 10768 San Diego County Water Authority– 10758 Santa Barbara County Water Agency

Page 6: Integrated Regional Water Management Grant Program

Available Funding

Approximately $51.8 million available DWR has approximately $20.7 million SWRCB has approximately $31.1 million

Page 7: Integrated Regional Water Management Grant Program

Schedule

Step 2 Application Due (FAAST and Hard Copies) Monday, January 28, 2008 at 5:00 PM

Page 8: Integrated Regional Water Management Grant Program

Some Additional Notes

Your Step 1 Score will not be carried forward to Step 2

A copy of the DWR contract template is on the DWR WEB Site

Contact the SWRCB for information on their contract template

Page 9: Integrated Regional Water Management Grant Program

Some Additional Notes

For the purpose of Scoring, “Schedule”, will use July 1, 2008 as the “contract start date.”  (see page 39)

Costs incurred after March 20, 2007 and prior to the actual effective date of a grant agreement are not eligible for reimbursement. However might be able to be considered, as part of the applicant’s funding match (see page 15)

Page 10: Integrated Regional Water Management Grant Program

Corrections

Page 38, Budget

The Budget categories of Exhibit “B” should be Exhibit “2”

An updated economic table was placed on the WEB Site

Page 11: Integrated Regional Water Management Grant Program

Economic Analysis (Attachment 8) and Other Expected Benefits (Attachment 9)

Any Questions before the Economics Presentation ?

Economics Presentation

Page 12: Integrated Regional Water Management Grant Program

Questions

Page 13: Integrated Regional Water Management Grant Program

BREAK AND BREAK OUT TABLES

1. General Questions & What is an Adopted Plan

2. Economic Analysis and Other Expected Benefits

3. Workplan / Budget and Schedule

4. (Scientific and Technical Merit, Monitoring Assessment and Performance Measures

5. Program Preferences

6. FAAST