+ All Categories
Home > Documents > Integrated Safety Management System Description TFC-PLN-41 ..._Integrated_Saf… · ISMS...

Integrated Safety Management System Description TFC-PLN-41 ..._Integrated_Saf… · ISMS...

Date post: 29-Jan-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
56
Integrated Safety Management System Description Manual Document Page Issue Date Management Plan TFC-PLN-41, REV A-4 Page 1 of 56 January 18, 2018 Ownership matrix USQ # 17-1806-S TABLE OF CONTENTS 1.0 INTRODUCTION .......................................................................................................................... 3 1.1 Background ......................................................................................................................... 3 1.2 Purpose................................................................................................................................ 4 1.3 Scope................................................................................................................................... 4 2.0 ISMS OVERVIEW ......................................................................................................................... 5 2.1 ISMS Program Requirements ............................................................................................. 5 2.2 ISMS Business Levels ........................................................................................................ 7 2.3 ISMS Guiding Principles .................................................................................................... 8 2.4 ISMS Core Functions........................................................................................................ 11 2.5 Integration of Other Initiatives and Systems..................................................................... 11 2.6 Management System ......................................................................................................... 13 3.0 RIVER PROTECTION PROJECT OVERVIEW ......................................................................... 15 3.1 River Protection Project .................................................................................................... 15 3.2 Project Integration............................................................................................................. 16 3.3 Hanford Interfaces ............................................................................................................ 16 3.4 External Regulatory and Oversight Agencies ................................................................... 17 4.0 WORK EXECUTION WITHIN ISMS ......................................................................................... 18 4.1 Guiding Principle 1 – Line Management Responsibility for Safety ................................. 18 4.2 Guiding Principle 2 – Clear Roles and Responsibilities ................................................... 21 4.3 Guiding Principle 3 – Competence Commensurate with Responsibilities ....................... 23 4.4 Guiding Principle 4 – Balanced Priorities ........................................................................ 24 4.5 Guiding Principle 5 – Identification of Safety Standards and Requirements ................... 24 4.6 Guiding Principle 6 – Hazard Controls Tailored to the Work Being Performed .............. 24 4.7 Guiding Principle 7 – Operations Authorization .............................................................. 25 4.8 Core Function 1 – Define the Scope of Work................................................................... 25 4.9 Core Function 2 – (Identify and) Analyze Hazards .......................................................... 28 4.10 Core Function 3 – Develop and Implement Hazard Controls........................................... 33 4.11 Core Function 4 – Perform Work Within Controls........................................................... 38 4.12 Core Function 5 – Provide Feedback and Continuous Improvement ............................... 42 5.0 MAINTAINING AND SUSTAINING ISMS............................................................................... 48 6.0 SOURCES ..................................................................................................................................... 49 6.1 Requirements .................................................................................................................... 49 6.2 References......................................................................................................................... 49 TABLE OF FIGURES Figure 1 DOE ISMS...................................................................................................................................... 3 Figure 2. ISMS Key Components. ............................................................................................................... 5 Figure 3 ISMS Guiding Principles and Core Functions................................................................................ 8 Figure 4 WRPS VPP ................................................................................................................................... 11 Figure 5 WRPS EMS .................................................................................................................................. 12 Figure 6. Identifying and Implementing TOC Requirements. ................................................................... 14 Figure 7. Underground Storage Tanks at the Hanford Site........................................................................ 15 Figure 8. Examples of Documents that Implement ISMS for WRPS. ....................................................... 18 Figure 9. Define Work Scope. ................................................................................................................... 25
Transcript
  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 1 of 56 January 18, 2018

    Ownership matrix

    USQ # 17-1806-S

    TABLE OF CONTENTS

    1.0 INTRODUCTION .......................................................................................................................... 3

    1.1 Background ......................................................................................................................... 3 1.2 Purpose................................................................................................................................ 4 1.3 Scope ................................................................................................................................... 4

    2.0 ISMS OVERVIEW ......................................................................................................................... 5 2.1 ISMS Program Requirements ............................................................................................. 5 2.2 ISMS Business Levels ........................................................................................................ 7 2.3 ISMS Guiding Principles .................................................................................................... 8 2.4 ISMS Core Functions ........................................................................................................ 11 2.5 Integration of Other Initiatives and Systems..................................................................... 11 2.6 Management System ......................................................................................................... 13

    3.0 RIVER PROTECTION PROJECT OVERVIEW ......................................................................... 15 3.1 River Protection Project .................................................................................................... 15 3.2 Project Integration ............................................................................................................. 16 3.3 Hanford Interfaces ............................................................................................................ 16 3.4 External Regulatory and Oversight Agencies ................................................................... 17

    4.0 WORK EXECUTION WITHIN ISMS ......................................................................................... 18 4.1 Guiding Principle 1 – Line Management Responsibility for Safety ................................. 18 4.2 Guiding Principle 2 – Clear Roles and Responsibilities ................................................... 21 4.3 Guiding Principle 3 – Competence Commensurate with Responsibilities ....................... 23 4.4 Guiding Principle 4 – Balanced Priorities ........................................................................ 24 4.5 Guiding Principle 5 – Identification of Safety Standards and Requirements ................... 24 4.6 Guiding Principle 6 – Hazard Controls Tailored to the Work Being Performed .............. 24 4.7 Guiding Principle 7 – Operations Authorization .............................................................. 25 4.8 Core Function 1 – Define the Scope of Work ................................................................... 25 4.9 Core Function 2 – (Identify and) Analyze Hazards .......................................................... 28 4.10 Core Function 3 – Develop and Implement Hazard Controls ........................................... 33 4.11 Core Function 4 – Perform Work Within Controls........................................................... 38 4.12 Core Function 5 – Provide Feedback and Continuous Improvement ............................... 42

    5.0 MAINTAINING AND SUSTAINING ISMS............................................................................... 48 6.0 SOURCES ..................................................................................................................................... 49

    6.1 Requirements .................................................................................................................... 49 6.2 References ......................................................................................................................... 49

    TABLE OF FIGURES

    Figure 1 DOE ISMS ...................................................................................................................................... 3 Figure 2. ISMS Key Components. ............................................................................................................... 5 Figure 3 ISMS Guiding Principles and Core Functions................................................................................ 8 Figure 4 WRPS VPP ................................................................................................................................... 11 Figure 5 WRPS EMS .................................................................................................................................. 12 Figure 6. Identifying and Implementing TOC Requirements. ................................................................... 14 Figure 7. Underground Storage Tanks at the Hanford Site. ....................................................................... 15 Figure 8. Examples of Documents that Implement ISMS for WRPS. ....................................................... 18 Figure 9. Define Work Scope. ................................................................................................................... 25

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 2 of 56 January 18, 2018

    Figure 10. Identify Hazards. ...................................................................................................................... 29 Figure 11. Hazard Control. ........................................................................................................................ 34 Figure 12. Perform Work. .......................................................................................................................... 39 Figure 13. Feedback. .................................................................................................................................. 43

    TABLE OF TABLES Table 1. ISMS Guiding Principles and Core Functions Correlation to Supporting Program Elements. ..... 9 Table 2. External Regulatory and Oversight for the TOC. ........................................................................ 17

    TABLE OF ATTACHMENTS ATTACHMENT A - ACRONYMS AND ABBREVIATIONS ................................................................ 55

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 3 of 56 January 18, 2018

    1.0 INTRODUCTION

    (6.1.1)

    1.1 Background

    The U.S. Department of Energy (DOE) Integrated Safety Management System (ISMS) is structured to integrate environment, safety, health, and quality (ESH&Q) into work planning and execution. In keeping with DOE O 436.1, “Departmental Sustainability,” and the waste management character of the Tank Operations Contractor (TOC) mission, a comprehensive Environmental Management System (EMS) is established and interwoven with the ISMS for all actions with potential environmental impacts. Integration is accomplished at the company, facility, and activity levels. Total ESH&Q integration enables the assigned missions to be efficient and effective while protecting the workers, the public, and the

    environment. DOE issued specific ISMS Clauses in the Code of Federal Regulations (CFR) and DOE Acquisition Regulation (DEAR) that are included as requirements under the Contract between Washington River Protection Solutions LLC (WRPS) and the Office of River Protection (DOE-ORP) (Contract DE-AC27-08RV14800, hereinafter referred to as “the Contract”). Sections of the DEAR related to the ISMS Description are discussed in Sections 1.0, 2.0, and 4.0. 48 CFR DEAR 970.5204-2, “Laws, Regulations, and DOE Directives,” requires that ESH&Q requirements applicable to work conducted under the Contract be implemented by a DOE-approved process. The process will evaluate the work and the associated hazards and identify an appropriately tailored set of standards, practices, and controls, such as a tailoring process included in a DOE-approved Safety Management System implemented under 48 CFR DEAR 970.5223-1, “Integration of Environment, Safety, and Health into Work Planning and Execution.” When such a process is used, the set of tailored (ESH&Q) requirements, approved by DOE-ORP, are incorporated into Contract requirements with full force and effect unless WRPS requests an exemption or other appropriate regulatory relief specified in the regulation. 48 CFR DEAR 970.5223-1 requires WRPS to manage and perform work in accordance with a documented ISMS. The ISMS shall describe how WRPS performs the following: • Defines the scope of work • Identifies and analyzes hazards associated with the work

    Figure 1 DOE ISMS

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 4 of 56 January 18, 2018

    • Develops and implements hazard controls • Performs work within controls • Provides feedback on adequacy of controls and continues to improve ISMS Consistent with the DEAR, the Contract requires WRPS to accomplish work “…in an integrated manner that protects the workers, public, and environment while enabling efficient cleanup.” The Contract also states WRPS:

    …shall implement a structured, standards-based approach to planning and control of work including identification and implementation of worker safety and health standards and requirements that are appropriate for the work to be performed and for identifying and controlling related hazards, while facilitating the effective and efficient delivery of work.

    Detailed ISMS requirements are included in the Contract requirements and guidance to develop, implement, sustain, and continuously improve a safety management system for DOE and its contractors. By including key provisions and clauses in the Contract, DOE-ORP has a mechanism to define the mission, direct implementation, and monitor the effectiveness of ISMS, integrate ESH&Q throughout activities performed within the defined scope of work, and achieve integration of contractor internal and external activities. See Attachment A for acronyms and abbreviations associated with this plan.

    1.2 Purpose The purpose of this document is to describe the ISMS structure, policies, programs, processes, and implementing mechanisms developed and used by WRPS to ensure protection of the environment and the safety and health of the workers, the public, and the environment. This ISMS Description, along with related ISMS implementing mechanisms, fulfills the intent of the following requirements: • 48 CFR DEAR 970.5204-2, “Laws, Regulations, and DOE Directives” • 48 CFR DEAR 970.5223-1, “Integration of Environment, Safety, and Health into Work

    Planning and Execution” • ESH&Q related requirements in Contract Attachment J.2.

    1.3 Scope The scope of this document includes the WRPS ISMS policies, programs, processes, and implementing mechanisms with reference to lower-tier documents containing the detailed integration of ESH&Q into work planning and execution. The ISMS applies to work performed by WRPS under the Contract, and to work subcontracted out by WRPS. WRPS, through applicable processes and procedures, is responsible for ensuring subcontractors fully implement ISMS requirements.

    Objective of Integrated Safety Management The Department and Contractors must systematically integrate safety into management and work practices at all levels so that missions are accomplished while protecting the public, the worker, and the environment. This is to be accomplished through effective integration of safety management into all facets of work planning and execution. In other words, the overall management of safety functions and activities becomes an integral part of mission accomplishment. (DOE P 450.4)

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 5 of 56 January 18, 2018

    The scope of this document includes the Environmental Management System, safety and health management (including industrial hygiene and radiation protection), quality assurance, sustainability, waste minimization, and Security and Emergency Services. Use of the terms “ISMS” and “safety” in this document include environmental protection, safety and health management (including industrial hygiene and radiation protection), quality assurance, sustainability, waste minimization, and Security and Emergency Services.

    2.0 ISMS OVERVIEW (6.1.1) The structure of the ISMS contains seven guiding principles and five core functions. The guiding principles and core functions are interactive and iterative among elements and business levels (i.e., company level, facility level, activity level) throughout the life-cycle phases. This structure is based on the requirements and guidance contained in 48 CFR DEAR 970.5223-1 (Contract DE-AC27-08RV14800, Clause I.142); DOE M 450.4-1, “Integrated Safety Management System Manual;” and DOE G 450-4-1B Volume 1, “Integrated Safety Management System Guide (Volume 1) for use with Safety Management System Policies (DOE P 450.4, DOE P 450.5, and DOE P 450.6); the Functions, Responsibilities, and Authorities Manual; and the DOE Acquisition Regulation.”

    2.1 ISMS Program Requirements As described in TFC-POL-16, the ISMS consists of six components as shown in Figure 2.

    Figure 2. ISMS Key Components.

    TFC-PLN-01 identifies programmatic elements and requirements for the ISMS. All aspects of work planning and execution are performed within the structure of the ISMS. TFC-PLN-01 applies to the WRPS ISMS related policies, programs, processes, and implementing mechanisms with reference to lower-tier documents containing the detailed integration of ESH&Q aspects into work planning and execution. The plan implements the following requirements: • 48 CFR DEAR 970.5204-2, “Laws, Regulations, and DOE Directives” • 48 CFR DEAR 970.5223-1, “Integration of Environment, Safety, and Health into Work

    Planning and Execution” • DOE M 450.4-1, “Integrated Safety Management System Manual”

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 6 of 56 January 18, 2018

    • DOE G 450.4-1B Volume 1, “Integrated Safety Management System Guide (Volume 1)

    for Use with Safety Management System Policies (DOE P 450.4, DOE P 450.5 and DOE P 450.6); The Functions, Responsibilities, and Authorities Manual and DOE Acquisition Regulation”

    • To the extent possible, the ISMS also includes the four supplemental safety culture

    elements described in DOE M 450.4-1. TFC-PLN-12 includes relevant safety culture attributes.

    Objective

    The overall management of safety functions and activities is an integral part of mission accomplishment. WRPS systematically integrates safety into management and work practices at all levels so that our mission is accomplished while protecting the public, the worker, and the environment. This is to be accomplished through effective integration of the ISMS into all facets of work planning and execution.

    Guiding Principles The ISMS guiding principles describe the environment or context for work activities in that most principles apply to each ISMS core function. WRPS integrates these guiding principles into all aspects of work planning and execution.

    Core Functions The core functions provide the necessary structure for any work activity that could potentially affect the workers, the public, and the environment. The core functions describe what “must be done,” and are applied as a continuous cycle with the degree of rigor appropriate to the type of work activity and hazards involved.

    Mechanisms Mechanisms define how the ISMS functions are performed by WRPS. The mechanisms vary based on the hazards and the work being performed and may include the following: • DOE expectations expressed through directives (i.e., policies, rules, orders, notices,

    standards, and guidance) and Contract clauses. • Policies, procedures, and other documents established to implement safety management

    and fulfill commitments made to the DOE.

    Responsibilities Responsibilities are clearly defined in documents appropriate to the activity. WRPS responsibilities are detailed in documents such as contracts, regulations, charters, plans, and procedures.

    Implementation WRPS implements the ISMS through work definition and planning, hazards identification and analysis, definition and implementation of hazard controls, performance of work, developing and implementing operating procedures, and monitoring and assessing performance for improvement.

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 7 of 56 January 18, 2018

    2.2 ISMS Business Levels There are three business levels within the ISMS structure: the company level, the facility level and the activity level.

    The Company Level The TOC work scope for WRPS is contractually divided into seven Contract Line Item Numbers (CLIN), as follows: • CLIN 1 – Production Operations and Tank Farm Infrastructure • CLIN 2 – Single-Shell Tank Retrieval and Closure • CLIN 3 – WTP [Waste Treatment and Immobilization Plant] Support and Mission

    Integration • CLIN 4 – Supplemental Treatment • CLIN 5 – Early Feed and Operation of the WTP Low-Activity Waste Facility • CLIN 6 – Pension and Welfare Plans • CLIN 7 – American Recovery and Reinvestment Act Work Scope (Inactive). The TFC-PLN-84 provides the WRPS project execution management plan to describe the overall project management approach for execution of the identified CLINs, policies, and methods for compliance with DOE O 413.3B, “Program and Project Management for the Acquisition of Capital Assets.” In addition, integration of project-level changes and updates to maintain the Performance Measurement Baseline are described in TFC-PLN-147, including definitions and a cross-walk of Work Breakdown Structure (WBS) to Organizational Breakdown Structure (OBS) to both authorize contract work and define who will organizationally execute assigned scope based on roles, responsibilities, authorities, and accountabilities (R2A2s) maintained by Workforce Resources. Activities performed under this comprehensive management strategy utilize ISMS, as the work execution approach to embed Environmental, Safety, Health and Quality Assurance oversight, described in TFC-PLN-02, into each work area to fortify a healthy safety culture at WRPS. This approach implements a corporate “Execution with Certainty” strategic business model and establishes Earned Value Management System as the tool for measurement of project performance. The fundamental project management principles detailed in Appendix C of DOE O 413.3B are implemented with a tailored approach to assure the appropriate degree of rigor is applied to reflect the cost, risk mitigation, schedule and complexity of the project, including application of applicable lessons learned from federal and commercial projects.

    The Facility Level At the facility level, work is managed at the functional or sub-project level; multi-disciplinary teams implement the ISMS core functions through the graded approach established within the activity work control process (TFC-OPS-MAINT-C-01). Facility-level integrated work authorization schedules (TFC-OPS-OPER-C-65) are prepared. Authorized work is established at the company level and implemented at the facility level. For example, at Hazard Category 2 and 3 nuclear facilities, authorized work activities are analyzed and controlled by the Documented Safety Analysis (DSA) and technical safety requirements (TSR) and implemented through

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 8 of 56 January 18, 2018

    procedures and training. The safety basis (DSAs and TSRs), along with the environmental basis (e.g., environmental permits, legal agreements) and the requirements basis (Contract DE-AC27-08RV14800, TFC-PLN-100), form the Authorization Basis (as part of the Authorization Agreement, Correspondence No. 1800004) for the facility. Schedules are addressed at weekly schedule meetings, and work release is controlled to ensure work (operations, maintenance, and construction) is performed within the Authorization Basis.

    The Activity Level The activity level includes review, authorization, and expectations to execute authorized work including, but not limited to, design, engineering, operations, maintenance, construction, testing, laboratory support, and assessment. A single work-control process (TFC-OPS-MAINT-C-01) describes the work definition, graded approach classification, and processes for non-routine operational activity. This is the principal mechanism that coordinates incorporation of the ISMS guiding principles and core functions into detailed mission performance in the field. TFC-ESHQ-S_SAF-C-02 provides supplemental guidance to assure effective hazard analysis. Working documentation is prepared by means of process-trained, team-based worker engagement practices (e.g., walkdowns, comparison to General Hazard Analyses [GHAs], work packages, procedures, engineering change notices, unreviewed safety question [USQ] screenings), and safeguards (TFC-BSM-IRM-STD-08). Work is scheduled and communicated at the plan of the day meetings; field work supervisors, leads, and workers pre-brief, perform, and post-job review the work—to the extent practical as a team.

    2.3 ISMS Guiding Principles The seven guiding principles are attributes applied to and achieved through execution of the methods (e.g., processes and procedures) that implement the five core functions. Guiding Principles one through three are applied to each activity within each core function at each business level, and are specifically discussed in Section 4.0, “Work Execution within ISMS.” Guiding Principles four through seven align with specific core functions as illustrated in Table 1, and are discussed in Section 4.0. Figure 3 ISMS Guiding Principles and Core Functions

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 9 of 56 January 18, 2018

    1. Line Management Responsibility for Safety. Line management is directly responsible

    for the protection of the workers, the public, and the environment. As a complement to the line management, the Department’s Office of Health, Safety and Security provides safety policy, enforcement, and independent oversight functions.

    2. Clear Roles and Responsibilities. Clear and unambiguous lines of authority and

    responsibility for ensuring safety shall be established and maintained at all organizational levels within the Department and its contractors.

    3. Competence Commensurate with Responsibilities. Personnel shall possess the

    experience, knowledge, skills, and abilities that are necessary to discharge their responsibilities.

    4. Balanced Priorities. Resources shall be effectively allocated to address safety,

    programmatic, and operational considerations. Protecting the workers, the public, and the environment shall be a priority whenever activities are planned and performed.

    5. Identification of Safety Standards and Requirements. Before work is performed, the

    associated hazards shall be evaluated and an agreed-upon set of safety standards and requirements shall be established, which, if properly implemented, will provide adequate assurance that the public, the workers, and the environment are protected from adverse consequences.

    6. Hazard Controls Tailored to Work Being Performed. Administrative and engineering

    controls to prevent and mitigate hazards shall be tailored to the work being performed and the associated hazards.

    7. Operations Authorization. The conditions and requirements to be satisfied for

    operations to be initiated and conducted shall be clearly established and agreed upon.

    Table 1. ISMS Guiding Principles and Core Functions Correlation to Supporting Program Elements.

    ISMS Guiding Principles with Environmental Integration

    ISMS Core Functions with Environmental Integration

    Environmental Management System Elements

    DOE-VPP Elements

    Quality Assurance Criterion

    1. Line Management Responsibility

    All Five Core Functions

    1. Management Leadership

    Chapter 1, Organization Chapter 2, Quality Assurance Organization

    2. Clear Roles and Responsibilities

    2. Employee Involvement

    Chapter 1, Organization Chapter 2, Quality Assurance Organization

    3. Competence per Responsibilities

    5. Safety and Health Training

    Chapter 2, Personnel Training and Qualification

    4. Balanced Priorities 1. Define Scope of Work

    1. Establish Environmental Policy

    Chapter 1, Organization

    2. Planning

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 10 of 56 January 18, 2018

    ISMS Guiding Principles with Environmental Integration

    ISMS Core Functions with Environmental Integration

    Environmental Management System Elements

    DOE-VPP Elements

    Quality Assurance Criterion

    2. Identify and Analyze Hazards and

    Environmental Impacts

    3. Worksite Analysis

    Chapter 3, Design Control Chapter 10, Inspection

    5. Identification of Safety and Environmental Standards

    6. Tailor Hazard and

    Environmental Controls to Work

    3. Develop and Implement

    Hazard and Environmental Controls

    3. Implementation and Operations

    4. Hazard Prevention and Control

    Chapter 4, Procurement Document Control Chapter 5, Instructions, Procedures, and Drawings Chapter 6, Document, Control Chapter 7, Control of Purchased Items and Services Chapter 8, Identification and Control of Items Chapter 9, Control of Special Processes Chapter 11, Test Control Chapter 12, Control of Measuring and Test Equipment Chapter 13, Handling, Storage, and Shipping Chapter 15, Control of Nonconforming Items

    7. Operations (safety and environmental) Authorization

    4. Perform Work Within Controls

    Chapter 4, Procurement Document Control Chapter 5, Instructions, Procedures, and Drawings Chapter 6, Document, Control Chapter 7, Control of Purchased Items and Services Chapter 8, Identification and Control of Items Chapter 9, Control of Special Processes Chapter 11, Test Control Chapter 12, Control of Measuring and Test Equipment Chapter 13, Handling, Storage, and Shipping Chapter 15, Control of Nonconforming Items Chapter 17, Records

    5. Feedback and

    Continuous Improvement

    4. Checking All Five Elements Chapter 18, Audits 5. Management Review

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 11 of 56 January 18, 2018

    2.4 ISMS Core Functions

    The five core functions below provide the overall framework and structure of the ISMS: 1. Define the Scope of Work. Missions are translated into work, expectations are set, tasks

    are identified and prioritized, and resources are allocated. 2. Analyze the Hazards. Hazards associated with the work are identified, analyzed, and

    categorized. 3. Develop and Implement Hazard Controls. Applicable standards and requirements are

    identified and agreed-upon, controls to prevent/mitigate hazards are identified, the safety envelope [Authorization Agreement] is established, and controls are implemented.

    4. Perform Work Within Controls. Readiness is confirmed and work is performed safely. 5. Provide Feedback and Continuous Improvement. Feedback information on the

    adequacy of controls is gathered, opportunities for improving the definition and planning of work are identified and implemented, line and independent oversight is conducted, and, if necessary, regulatory enforcement actions occur.

    2.5 Integration of Other Initiatives and Systems

    Numerous environmental, health, and safety initiatives—such as the Voluntary Protection Program (), Safety Culture, EMS, and Human Performance Improvement (HPI)—are used to enhance the effectiveness of the ISMS. To the extent practical, the ISMS addresses the supplemental safety culture elements (individual responsibility for safety, operational excellence, oversight for performance assurance, and organizational learning for performance improvement). These initiatives, together with the Quality Assurance Program Description (QAPD) (TFC-PLN-02) and the Environmental Management System Description (TFC-PLN-123), complement ISMS implementation and support the ISMS continuous improvement objective. Table 1 illustrates the correlation between ISMS and several other structures.

    Figure 4 WRPS VPP

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 12 of 56 January 18, 2018

    The EMS component of the ISMS drives implementation of the applicable environmental requirements in a manner consistent with the requirements of DOE O 436.1. The Environmental Protection organization identifies all applicable statutory, regulation, permit, and other environmental requirements in support of the Tank Operations Project execution and operations elements. The suite of applicable Environmental requirements is maintained current by continual review of requirements sources, emerging DOE requirements and expectations, and through active interfaces with other Hanford contractors and environmental stakeholders. The programs comprising the WRPS EMS are implemented by the Environmental Protection organization (TFC-POL-30 and

    TFC-PLN-123), the Waste Services organization (TFC-PLN-33), Operations (consisting of line management), and the Safety organization (TFC-PLN-13 and TFC-PLN-58). These documents also address EMS elements performed by other contractors per DOE-ORP contract direction, but not directly implemented by WRPS. WRPS has an expanded comprehensive work planning process. Teamwork is used at multiple stages of the work control lifecycle for project performance. Incorporating lessons learned and best practices, robust hazard analysis and control are used to evaluate and improve the way higher-risk or complex work is identified, planned, approved, controlled, and executed. Key elements of the work planning process include line management ownership and a graded approach to work management based on risk and complexity, worker engagement and integrated work planning teams. As a part of this process, workers—in multi-disciplinary teams—are directly engaged in work planning, hazard identification and control, work execution, and post-job reviews when performed. A graded approach to work planning is integrated into the work control process, which is defined in TFC-OPS-MAINT-C-01. As a defense-in-depth measure, WRPS employs the concepts and principles of HPI as an approach to error reduction that has been developed in other sectors of the DOE and nuclear industry at large (TFC-PLN-150). WRPS maintains its awareness current in DOE-wide HPI activities through participation with the Energy Facility Contractors Group (EFCOG). This includes active collaboration with many DOE elements that share interest in improved work execution performance. Human factors and performance considerations are variables considered during the work planning process (TFC-OPS-MAINT-STD-02). Planners enter limitations, precautions, safety concerns, and other information that will enhance field performance for the specific job. Planners are cautioned not to assume that a given work activity will necessarily be performed by a particular individual or team. The Quality Assurance (QA) program is established and implemented in compliance with 10 CFR 830, Subpart A, “Quality Assurance Requirements;” and DOE O 414.1D, “Quality Assurance.” The QA program is documented in TFC-PLN-02 and ATS-MP-1032. The QAPD is

    Figure 5 WRPS EMS

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 13 of 56 January 18, 2018

    organized to address the management, performance, and assessment criteria of paragraph 830.122. The QA program's key implementing documents are contained within the Quality Implementing Plan (QIP) of the QAPD and were developed to provide a correlation between regulatory consensus standards invoked for implementation of the QA criteria (ASME-NQA-1-2008, including NQA-1a-2009 Addenda), QA program requirements, and implementing documents. The QIP provides visibility to implementing procedures and serves to ensure consistency in the management and implementation of QA program requirements. The QA criteria and practices are embedded in all work processes, including those that relate to nuclear safety. Therefore, the actions to implement the QA criteria are integrated and consistent with the ISMS structure. The DOE VPP promotes safety and health excellence through cooperative efforts among labor, management, and government at DOE contractor sites. Key tenets of VPP include management leadership and commitment, employee involvement, work site analysis, hazard prevention and control, and safety and health training. WRPS achieved STAR status, which is the highest level of recognition awarded within the VPP for outstanding contractor safety and health programs that have successfully implemented the program elements. The WRPS VPP program is defined in TFC-PLN-47. The worker safety and health requirements in 10 CFR 851 apply to the conduct of contractor activities at DOE sites. The requirements are intended to reduce or prevent occupational injuries, illnesses, and accidental losses by providing DOE contractors and their workers with safe and healthful workplaces at DOE sites. 10 CFR 851 contains programmatic requirements for management responsibilities and worker rights and responsibilities, hazard identification and assessment, hazard prevention and abatement, safety and health standards, functional areas, training and information, recordkeeping, and reporting. TFC-PLN-47 is a description of how the 10 CFR 851 requirements are met by procedure implementation. The ISMS is structured to integrate environment, safety, health, and quality into work planning and execution. Total ESH&Q integration enables the assigned missions to be efficiently and effectively accomplished while protecting the workers, the public, and the environment.

    2.6 Management System The management system is multi-tiered, beginning with the Contract and Authorization Agreement (Correspondence No. 1800004) executed between DOE-ORP and WRPS. The document hierarchy (TFC-PLN-80) employs a tiered graded approach: Policies convey company position on important-to-safety topics; Management Plans establish the ISMS mechanisms to accomplish a given scope of work or a specific task; Charters establish cross-functional groups and teams that assure coordination in employment of the ISMS Core Functions is effective. The Implementing procedures contain specific activity-level methods that provide direction where a common product or service is desired. Laws, regulations, and DOE directives will flow through the hierarchy, placing the requirements associated with specific activities within the procedures that govern those activities. When changes occur in the ISMS regulatory requirement documents, these changes are flowed down through the hierarchy of documents via the procedure change process and are reflected in new revisions of policies, procedures, plans, and implementing documents. The organizations responsible for these documents implement requirements that include environmental requirements, derived from the Authorization Agreement (Correspondence No.

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 14 of 56 January 18, 2018

    1800004), into their internal procedures. Figure 6 shows the identifying and implementing of TOC requirements as established by WRPS. TFC-PLN-100 identifies implementing documents associated with the WRPS Contract requirements. As implemented by the TOC, TFC-PLN-100 addresses applicable laws and regulations, as well as the applicable requirements from DOE orders, directives, or standards. As part of this process, any exceptions, clarifications, or alternate means of implementation for these requirements are identified by TFC-PLN-100.

    Figure 6. Identifying and Implementing TOC Requirements.

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 15 of 56 January 18, 2018

    External implementing documents for activities controlled by other site contractors as described in Section J.3 of the Contract are allowed if controlled in accordance with equivalent TOC processes and the applicable interface document. When necessary, management directives are used/issued on an interim basis to establish and (or) clarify a process or expectation on an immediate basis that is important to the tank operations mission until the proceduralized process is established or revised.

    3.0 RIVER PROTECTION PROJECT OVERVIEW This section provides an overview of the River Protection Project (RPP), project integration, and the TOC outside interfaces.

    3.1 River Protection Project Since 1944, highly radioactive waste from the chemical processing of irradiated reactor fuel has been stored in underground storage tanks at the Hanford Site. Approximately 204 million liters (56 million gallons) of caustic liquid, salt cake, and sludge are currently stored in 177 underground storage tanks in 18 tank farms. The tanks represent about 60 percent (by volume) of the nation’s and 80 percent (by radioactivity) of the Hanford Site’s radioactive waste resulting from nuclear weapons development (see Figure 7).

    Figure 7. Underground Storage Tanks at the Hanford Site.

    The DOE-ORP was established at the Hanford Site in December 1998, as directed by Congress in Section 3139 of the Strom Thurmond National Defense Authorization Act for Fiscal Year 1999, to execute and manage the RPP. The mission of the RPP is to retrieve and treat Hanford’s tank waste and close the tank farms to protect the Columbia River. In support of this mission, DOE-ORP has three prime contractors that are responsible for executing the assigned project work scope. WRPS is the TOC responsible for ensuring safe storage and retrieval of current and future tank waste, sampling and analyzing tank waste and storage of the immobilized waste, decontamination and decommissioning, initiation of post-closure monitoring of the tank farms, and early feed to the WTP Low-Activity Waste Facility. Bechtel National, Inc. (BNI) is the Waste Treatment Contractor (WTC) responsible for designing, constructing, and commissioning of the WTP. Wastren Advantage, Inc. (WAI) is responsible for performing the analytical services

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 16 of 56 January 18, 2018

    production functions of receiving, handling, analyzing, storing samples, performing special tests, and reporting the results of these analyses and tests to the other Hanford Site contractors. WAI is co-located at the 222-S Laboratory managed by WRPS, and is the Analytical Services Production Contractor (ASPC). The EPC organization (TFC-CHARTER-01) is responsible for development of the work processes and procedures associated with EPC construction activities to deliver early feed to the WTP Low-Activity Waste Facility, commonly known as Direct Feed Low Activity Waste (DFLAW).

    3.2 Project Integration Support to the DOE-ORP is provided in managing the RPP integrated baseline (TFC-PLN-84); coordinating RPP activities in support of baseline communications and interface management; and assisting in decision-making to identify key strategic issues, possible outcomes, and optimization (TFC-PLN-39). This function also assists with the RPP integration activities among DOE-ORP, BNI, and WAI. WRPS performs cost-effective integration of RPP activities. This is done by establishing processes and systems to accomplish this integration, identify and track integration issues to resolution, communicating plans and accomplishments at the RPP level, and providing project status information (TFC-PLN-83). Interface control documents are collaboratively developed to define the requirements and acceptance criteria to meeting infrastructure, waste feed, product delivery, and waste management functional needs within the RPP.

    3.3 Hanford Interfaces At the Hanford Site, the TOC’s primary interface is with the ORP. In addition, there may be interfaces with DOE’s Richland Operations Office (DOE-RL) and Pacific Northwest Science Office. WRPS relies on support services from the other Hanford contractors in order to meet its mission commitments (TFC-BSM-CP_CPR-C-17). WRPS interfaces with other DOE prime contractors for services as outlined in the Attachment J.3 of the Contract. Contractors that interface with the TOC include the following: • Mission Support Alliance provides most of the Hanford Site infrastructure support

    services (Mission Support Contractor) such as safeguards, security, protective forces, emergency management support, crane and rigging services, roads, grounds, electricity, sewer and water services, biological, ecological, and cultural resource reviews, etc.

    • BNI manages the design and construction of the WTP project, managed by DOE-ORP,

    for final treatment of tank waste. WRPS has explicit interfaces with BNI to prepare for the commencement of WTP receipt of tank waste.

    • CH2M Hill Plateau Remediation manages the Plateau Remediation Contract, which

    provides groundwater/vadose zone integration; site well drilling and decommissioning; low-activity waste disposal; industrial and radioactive liquid effluent treatment and disposal; low-level waste and mixed low-level waste treatment, storage, and disposal; operation and maintenance of the Solid Waste Integrated Forecast Technical database; operates the Environmental Restoration Disposal Facility; etc.

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 17 of 56 January 18, 2018

    • HPMC Occupational Medical Services manages Hanford Site occupational health

    services for Hanford workers. HPMC provides medical qualifications, medical monitoring, and occupational medical services.

    • WAI is the ASPC, which provides analytical laboratory services to the TOC. • Johnson Controls provides the TOC with steam service. • Unitech Services Group provides contaminated laundry services to the TOC. • Pacific Northwest National Laboratory provides research, development, and

    demonstration support services, as well as radiological instrumentation, dosimetry services, and other environmental monitoring and analysis support services to the TOC.

    • Interface documents including Memorandums of Agreements, Administrative Interface

    Agreements, and interface controls documents. Inter-contractor work orders/task orders support delivery and receipt of safe and reliable services between the many Hanford contractors. The Interface Management Program is controlled by TFC-PLN-102.

    3.4 External Regulatory and Oversight Agencies

    Table 2 provides an overview of the TOC’s external regulatory and oversight agencies that are in addition to DOE, and their primary focus. DOE is discussed in Section 4.2, “Guiding Principle 2 – Clear Roles and Responsibilities,” and Section 4.12.4, “Oversight and Enforcement.”

    Table 2. External Regulatory and Oversight for the TOC.

    External Regulatory and Oversight Activities

    Environmental Protection

    Agency

    Washington Department of

    Ecology

    Washington Department of

    Health

    U.S. Department of Transportation

    Defense Nuclear Facilities

    Safety Board

    Benton Clean

    Air Agency Regulates all treatment/storage/ disposal activities under Resource Conservation and Recovery Act, Toxics Substance Control Act, Comprehensive Environmental Resource Conservation Liability Act, Tri-Party Agreement, Solid Waste Management Act, and the Washington State Hazardous Waste Management Act

    X X

    Regulates radioactive air emissions X X Regulates non-radioactive air emissions X X

    Regulates liquid effluents X X Regulates offsite transportation of radioactive and non-radioactive hazardous wastes

    X X

    Ensures and enhances the safety of DOE’s defense nuclear facilities operations

    X

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 18 of 56 January 18, 2018

    4.0 WORK EXECUTION WITHIN ISMS (6.1.1) The preceding portions of this document discussed the basic structure of an ISMS and the RPP. Expectations are communicated. Programs are established to provide management and workers with the guiding principles and structure to ensure safety, quality, and environmental protection is an integral part of each work activity. A comprehensive work planning process evaluates and improves the way higher risk, more complex work is identified, planned, approved, controlled, and executed. TFC-PLN-100 cross-references specific TOC implementing documents to the Contract requirements each satisfies. Figure 8 provides an illustration of example documents that implement the five ISMS Core Function.

    Figure 8. Examples of Documents that Implement ISMS for WRPS.

    The hazards and complexity of the work determines the level of rigor applied to training, procedures, and control of work. This section describes in detail how the integration of ESH&Q within management processes establishes a common set of controls essential for the safe and efficient performance of work.

    4.1 Guiding Principle 1 – Line Management Responsibility for Safety WRPS fully endorses the guiding principle that line management is directly responsible and accountable for the protection of the workers, the public, and the environment by integrating ESH&Q into the planning, hazard analysis and control, and performance of work. Clearly defining the term “line management” is important so safety management roles and responsibilities are understood. As published in DOE G 450.4-1B, Volume 1, line management is defined as

    1. Define the Scope of Work• TFC-BSM-CP_CPR-C-05• TFC-PLN-39• TFC-OPS-MAINT-C-01

    2. Identify Hazards• TFC-ESHQ-S_SAF-C-02• TFC-ESHQ-RP_RWP-C-

    03

    3. Develop and Implement Hazard Controls• TFC-PLN-07• TFC-ESHQ-S_IH-C-07

    4. Perform Work Within Controls• TFC-OPS-OPER-C-13

    5. Provide Feedback and Continuous Improvement• TFC-PLN-10• TFC-ESHQ-Q_C-C-01

    ISMS Core

    Functions

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 19 of 56 January 18, 2018

    “any management level within the line organization, including contractor management, which is responsible and accountable for directing and conducting work.” Work is broadly defined to include physical work, design, engineering, maintenance, operations, testing, administrative, and assessment. An ISMS provides line management with the technical resources necessary to fulfill their responsibility. To strengthen its ISMS, WRPS implemented the attributes of a healthy safety culture, which includes free flow of communication and an environment free of retaliation for raising safety concerns. Consistent with strong safety culture principles, management conducts periodic employee safety meetings, further enhancing the flow of communications regarding relevant safety information. TFC-PLN-12 identifies the focus areas and attributes associated with a healthy safety culture. These attributes include providing an environment where individuals will feel free to raise safety concerns without fear of harassment, intimidation, retaliation, or discrimination.

    WRPS Flowdown of Authority Line direction for company and facility/project work activities flows down from the DOE-ORP through the Project Manager to the work area and functional managers pursuant to TFC-CHARTER-01.

    Tank Operations Field Activities Under the organization structure established to implement the Area Team approach, the work area managers are responsible for the overall tank farms facility operation and work execution. The Shift Managers are directly accountable for work release, monitoring, and control of field activities (supported by the Senior Supervisor Watch when assigned) (TFC-PLN-05). ESH&Q experts provide monitoring and oversight of field activities to ensure the protection of the workers, the public, and the environment. Every employee is empowered and expected to exercise “stop work” authority to prevent performance of an unsafe act or to correct an unsafe condition (DOE-0343, “Hanford Site Stop Work Procedure”). The Business Services organization manages the non-nuclear facilities on the tank farms and is responsible for procurement of materials and contract services.

    Safety Integration Forums Various forums are used to assist with integration and oversight of organizations and activities. The TOC-sponsored committees and councils have formal charters, defined responsibilities, and lines of authority in TOC administrative procedures. Other forums discussed below, such as boards and safety meetings, have applicable governing documents. • Executive Safety Review Board (ESRB) (TFC-CHARTER-32) provides oversight of

    identification, causal analysis, reporting, and corrective action plan development for issues identified in significant problem evaluation requests (PER). The ESRB also provides feedback and senior management direction concerning the focus and conduct of assessments; reviews the health of the Safety Management Programs and Price-Anderson Amendments Act (PAAA) program performance; and reviews issues that have crosscutting organizational implications.

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 20 of 56 January 18, 2018

    • WRPS Safety Councils (TFC-CHARTER-02) are WRPS’ safety leadership councils.

    The Employee Accident Prevention Councils and subcommittees report to the President’s Accident Prevention Council. These councils provide employee leadership and ensure employee involvement, thereby achieving maximum accident prevention and injury reduction by application of the VPP and ISMS principles. The ALARA Committee is a subcommittee of the President’s Accident Prevention Council and periodically reports on ALARA Committee activities.

    • Joint Test Group (TFC-CHARTER-15) conducts thorough reviews of test procedures

    to ensure they can be performed safely, to ensure compliance with applicable procedure requirements, and to demonstrate accomplishment of test objectives.

    • WRPS Baseline Change Control Board (TFC-PRJ-PC-C-12) is composed of WRPS

    managers from the project and support functions. The Board is responsible for reviewing and approving baseline change requests as defined in TFC-PRJ-PC-C-12. The Change Control Board is also responsible for approving baseline change requests identified by the Program Change Control Board as requiring senior management decision on company-wide strategy and priority prior to submittal to DOE-ORP.

    • Safety Meetings (TFC-ESHQ-S_SAF-CD-10) promote safety by addressing different

    health or safety topics, including information on basic issues, control methods, and established programs. Employees are encouraged to use a questioning attitude and engage in each meeting by sharing their ideas on safety issues.

    • Joint Review Group (TFC-ESHQ-RP_ADM-C-11) is a senior, experienced,

    multi-disciplinary team that ensures work documents categorized as high risk are comprehensive and thoroughly reviewed, including contingency plans for emergent situations. The Joint Review Group (JRG) performs a balanced review of high-hazard work evolutions to ensure potential hazards are identified in various permits and supporting documents and appropriate controls are incorporated into technical work documents that direct the work. The JRG ensures the five ISMS core functions have been adequately applied to the work evolution under consideration.

    • Behavior Based Safety (TFC-CHARTER-20) is a program that involves conduct of

    peer safety behavior observations resulting in immediate feedback to help identify and extinguish at-risk work practices in the tank farms, thus preventing injuries. This program is proactive and provides positive reinforcement of good safety behaviors and practices.

    • Safety Culture Improvement (TFC-PLN-12) establishes and defines the roles and

    responsibilities assigned to the Safety Culture Monitoring Panel and the Safety Culture Improvement Team. The Safety Culture Monitoring Panel monitors inputs most indicative of the company’s Safety Culture health to identify potential concerns in the work environment that merit additional attention by the organization. The Safety Culture Improvement Team provides safety culture inputs to the Safety Culture Monitoring Panel.

    • Lockout/Tagout Hazardous Energy Control Committee (TFC-CHARTER-41)

    functions to ensure the effective implementation of the Hanford Site Lockout/Tagout program DOE-0336 in the servicing and maintenance of machines and equipment in

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 21 of 56 January 18, 2018

    which unexpected energization, start up, or release of stored energy could cause injury to employees.

    • Plant Review Committee (TFC-ENG-SB-C-09) applies to multiple committees

    established for field operation organizations. Among other duties, the Plant Review Committee (PRC) evaluates safety basis related topics such as new information (e.g., potential inadequacy in the safety analysis, safety basis amendments, justification for continued operations) presented to the PRC by the USQ, evaluator, Nuclear Safety engineer or designee.

    • Chemical Vapor Solutions Team (TFC-CHARTER-21), which includes Hanford

    Atomic Metal Trades Council (HAMTC), professional, and management representatives, is engaged in a collaborative effort to increase and improve the flow of information to the workforce and the public, including: (1) access to field data and sampling results; (2) more complete information as to how WRPS protects workers; (3) an explanation of technologies being developed and tested in the field; and (4) expanded definitions and background on a number of vapors-related topics.

    The TOC participates in committees and boards sponsored by other DOE or Hanford organizations. Participation on these committees and boards facilitates information exchange, the development of common approaches where appropriate and cost effective, and networking to enhance functional area cooperation. These committees further strengthen those internal to WRPS, while providing valuable site-wide perspectives and sharing of lessons learned information. The responsibility for determining participation is with the appropriate TOC functional organization.

    4.2 Guiding Principle 2 – Clear Roles and Responsibilities Roles and responsibilities are defined by: (1) assignment within the organization; and (2) the function or activity being performed, which are contained in TOC policies and procedures such as the institutionalized ISMS process, roles and responsibilities related to company level, facility level, and activity level, with an on-going iterative interaction between the management levels. The process and relationship between WBS, OBS, and R2A2s at the company level are described in TFC-CHARTER-01. Management and workers at every level are responsible and accountable for understanding and implementing established company standards for safety, environmental protection, quality, and efficiency. Personnel are accountable for their personal safety and the safety of their peers, the public, and the environment. The “ISMS Expectations for Implementation of the Integrated Safety Management System” were communicated to the workforce, both formally and informally. These expectations continue to be discussed and emphasized during formal training, safety meetings, lessons learned reports, weekly tailgates, employee performance management activities, all-employee meetings, staff meetings, Conduct of Operations activities, My Safety Focus Program, Anti-Harassment Training, Supervisory Skills, Safety Culture program, Human Performance Improvement activities, and VPP activities. Posters containing these expectations are displayed throughout the various WRPS-controlled locations. The annual performance appraisal process (TFC-BSM-HR_EP-C-01) provides the mechanism for formal annual review. Positive recognition of personnel accountability is applied when warranted, as is “Employee Discipline” (TFC-BSM-HR_EP-C-02).

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 22 of 56 January 18, 2018

    Management at every level ensures that employees understand their role in implementing these standards as an integral part of meeting company objectives and customer expectations. TFC-ESHQ-AP-C-03 provides interaction between management and the workforce to assess and reinforce behaviors, knowledge, and compliance with WRPS expectations, policies, and procedures. • Workers are responsible for participating in the activity level of each ISMS core

    function. Workers from cross-disciplines are actively engaged in work planning (TFC-OPS-MAINT-C-01); hazard identification and control; work performance within the controls, including feedback and continuous improvement (TFC-ESHQ-S_SAF-C-02); and stop work responsibility (DOE-0343).

    • Field Work Supervisors and Leads are responsible for directing work activities and

    managing safety culture. Their focus is on the activity level for each ISMS core function. Field work supervisors and leads participate in work planning, hazard identification and control, work performance within the controls, and feedback and continuous improvement.

    • First Line Managers are responsible for ensuring that the work environments created by

    field work supervisors and leads are producing safe results that support and advance company and customer objectives. Their focus is on the activity and facility level for each ISMS core function. First line managers also ensure company policies and procedures are effectively implemented. These managers coordinate resources and work activities with other organizations, provide technical direction according to their qualification, provide direction for work, and report work progress and the quality of performance.

    • Mid-Level Managers (project, department, technical support) are involved in providing

    technical direction, resources, planning, reporting, personnel, and issue management in support of specific projects and their WRPS areas of responsibility. The managers’ focus is on the programmatic and facility level, with support to senior management on company-level matters. Managers ensure barriers affecting the safe performance of work are addressed, and that activities support established budgets, milestones, and customer expectations.

    • Senior Managers are responsible for ensuring that company standards are established

    and implemented that meet customer expectations for executing work in a safe, proper, and efficient manner. Their focus is on the company level, with overall project and program management and support to the customer. Senior management interfaces with the customer, regulators, stakeholders, HAMTC, and the public on company and project matters.

    • The Project Manager (WRPS Company President and Chief Executive Officer) is

    responsible for the overall management and safe operation of the TOC and is supported by the Work Area and Functional Senior Managers.

    • DOE-ORP interfaces with WRPS to ensure continued excellence in mission execution

    and ESH&Q management. ORP and WRPS senior managers collaborate to clearly define company and project performance expectations and priorities.

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 23 of 56 January 18, 2018

    4.3 Guiding Principle 3 – Competence Commensurate with Responsibilities Workforce Resources, Organizational Performance Improvement (OPI), and line management work together to ensure qualified workers perform work safely using approved procedures. The work to be performed by an organization is evaluated against standards and requirements. Management determines the staffing levels, training, and identifies the mix of knowledge, skills, and abilities typically required for the organization’s positions. For exempt and non-exempt positions, career matrices are established that define position titles, minimum education and experience requirements, and potential career progression. New and (or) revised career matrices are generated as needed. Job applicants may come from sources within or outside the company depending on the specialization of the position. Individual training, education, and experience of job applicants are evaluated before candidates are considered qualified to fill a position (TFC-BSM-HR_EM-C-02). Within the OPI organization, the Training organization supports management in this activity by administering the training program as established in the company-level management plan TFC-PLN-61. This plan identifies the process to ensure employees are trained and qualified to safely, competently, and effectively perform their job functions. The Training organization works with line organizations to develop the training to meet applicable requirements and to maintain an electronic training database for the implementation of training requirements and enhancements. The electronic training database and the employee job task analysis (EJTA) process (TFC-ESHQ-S_IH-C-17) assists managers in determining the following: • Training requirements based on working conditions (i.e., hazards to which the individual

    will be exposed, such as bloodborne pathogens or heat stress)

    • Tasks the employees will perform (e.g., crane operations, lock and tag)

    • Requirements based on worker classification (e.g., field work supervisors, radiological worker), and

    • Technical staff position qualifications (e.g., Design Authority, QA Engineer, Operations

    Engineer). The systematic approach to training process is required by DOE O 426.2 for positions identified in the Training Implementation Matrix (TIM). This model applies the elements of Analysis, Design, Development, Implementation, and Evaluation, referred to as the ADDIE model. A graded approach is applied to the degree necessary to ensure efficiency, but still adequately transfers knowledge and skills to the workforce. The systematic approach to training process may be applied to other training programs as deemed necessary by line management, TOC training management, and instructional staff (TFC-BSM-TQ_ADD-C-01). The TOC has an approved TIM encompassing the tank farms, 242-A Evaporator, and the 222-S Laboratory. The TIM identifies which DOE O 426.2 requirements are applicable and identify exceptions and clarifications. The TIM is approved by DOE-ORP and became the only contractually bounding DOE O 426.2 requirements for TOC and 222-S Laboratory. The approved TIM for the TOC identifies operations and support personnel who require a qualification program defined in DOE O 426.2. Associated training program descriptions have

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 24 of 56 January 18, 2018

    been developed to establish standards for technical staff positions requiring qualification and are located within Business Services and ESH&Q procedures. Any person who performs or observes work within a hazardous waste zone must have the necessary training to enter TOC nuclear facilities via the Access Control Entry System (ACES) (TFC-ESHQ-RP_ADM-C-15 or ATS-310, Section 1.5 for 222-S Laboratory). The process that assists managers in determining necessary employee medical qualifications and monitoring is the EJTA. The EJTA is the mechanism to obtain necessary medical monitoring based on the individual’s job requirements, hazards, exposures, and overall risk associated with the assigned work scope. This process supports the collection of data necessary for a risk-based approach to medical qualification and monitoring. An EJTA is prepared for each employee (TFC-ESHQ-S_IH-C-17), including subcontracted personnel when required (TFC-BSM-CP_CPR-C-05).

    4.4 Guiding Principle 4 – Balanced Priorities Through the WRPS Project line organizations, resources are allocated to balance ESH&Q, programmatic, and operational considerations. Through the Earned Value Management System (EVMS), the Project Integration support organization assists projects and their support functions to generate risk-balanced schedule and resource plans. These estimates are based upon anticipated uncertainty when budget and upper-tier WBS decisions are made; work control processes provide for uncertainty reduction as detailed planning progresses (e.g., by early worker engagement and risk register development in sub-projects). As efforts reach the stage of physical work in the field, uncertainties are reduced to specific work controls that are proportionate to the need based upon detailed work planning and hazard analysis.

    4.5 Guiding Principle 5 – Identification of Safety Standards and Requirements TFC-PLN-100 is identified in the ORP-WRPS Authorization Agreement (Correspondence No. 1800004) as the mechanism for the flowdown of the TOC, including laws, regulations, and DOE directives, into WRPS implementing policies, procedures, plans, and other work control documents. For purposes of general requirements, policies and plans describe work control processes for each type of requirement source (i.e., among ESH&Q upper-tier governing documents). Key specific procedures, such as TFC-OPS-MAINT-C-01, detail how multi-disciplinary teams implement the ISM Core Functions to identify hazard controls. In this process, subject matter experts (SME) ensure that all applicable requirements are incorporated into these work controls.

    4.6 Guiding Principle 6 – Hazard Controls Tailored to the Work Being Performed Tailoring of controls is conducted in accordance with WRPS procedures for the implementation of the graded approach (TFC-PLN-112). The variety of mission activities within the TOC Projects result in work descriptions being at the upper levels of the WBS; such descriptions typically describe outcomes or end-state conditions with only limited identification of the specific mechanisms used to achieve those states. Through the Project Integration processes, project planning and other decision-making processes are detailed and hazard analyzed to ensure they can be accomplished with controls tailored to the actual work. An important aspect of tailoring is identification of conservative controls that reflect appropriate consideration of the residual uncertainty that may be present when work is begun. Procedures such as TFC-OPS-MAINT-C-01, DOE-0336, and TFC-ESHQ-S_SAF-C-02 detail how multi-disciplinary

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 25 of 56 January 18, 2018

    teams implement the ISM Core Functions to assure hazard controls are representative of actual work plans and anticipated hazards.

    4.7 Guiding Principle 7 – Operations Authorization At the Contract business level in the TOC Project, work performance is authorized in a top-to-bottom manner through the delegation of line management responsibility to formulate plans, budgets, and schedules for mission work. In keeping with the EVMS (TFC-PLN-147), cost account managers are assigned duties for overseeing the allocation of authorized resources as needed to conduct project work safely. Through the facility and activity levels of control, actions are subject to additional authorization points in accordance with work release procedures and practices (TFC-PLN-05) designed to ensure that the initial conditions, established by field work control requirements (e.g., isolation of hazardous energy sources) are in place in accordance with the associated procedures. Operations shift management coordinates for assurance that all applicable permits (e.g., Radiation Work Permits) are in place and in conformance with pertinent procedures.

    4.8 Core Function 1 – Define the Scope of Work Defining work scope (see Figure 9) is a process in which DOE mission expectations are defined, prioritized, and divided into discrete activities that account for the associated hazards, requirements, controls, and funding needed to complete the mission. DOE-ORP, as the facility owner, defines the mission and requirements. The TOC establishes the mechanisms for accomplishing the mission, to assign responsibility, and to implement work priorities through risk-informed planning for the effective and efficient use of resources.

    Figure 9. Define Work Scope. Sections 4.8.1 through 4.8.4 describe definition of work scope and balanced priorities primarily at the company level as part of the TOC business, budget, and contract process. Section 4.8.5 describes how this element is accomplished at the facility/activity level.

    Translate Mission into Work The processes, tools, and controls used to translate the TOC lifecycle baseline into Contract period plans and execution year work is described in TFC-PLN-147. Execution year

    work is captured and authorized by DOE-ORP for performance through the WRPS Contract. Work is then performed in accordance with the Contract and associated ESH&Q commitments and performance objectives. The TOC lifecycle baseline is an integral subset of the RPP integrated baseline, which describes the combined activities of DOE-ORP, WTC, ASPC, and the TOC. The scope and requirements of the TOC lifecycle baseline are described and assigned

    Applicable Guiding Principles

    1. Line Management Responsibility 2. Clear Roles and Responsibilities 3. Competence per Responsibilities 4. Balanced Priorities

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 26 of 56 January 18, 2018

    through the RPP System Plan and the Contract. Scope and requirements are then translated into a more specific scope, schedule, and cost basis at the activity level and implemented through the application of WRPS procedures. The current set of plans and procedures used to define, schedule, resource load, assess and mitigate risk, release, execute, and control changes to the work are as listed below: • TFC-PLN-147 • TFC-BSM-CP_CPR-C-17 • TFC-OPS-MAINT-C-01 • TFC-PLN-03 • TFC-PLN-39 • TFC-PLN-84

    • TFC-PLN-102 • TFC-PLN-123 • TFC-PRJ-PC-C-02 • TFC-PRJ-PC-C-05 • TFC-PRJ-PC-C-12 • TFC-PRJ-PM-C-02

    The processes described in these plans, including multi-disciplinary teams comprised of technical, operational, management, ESH&Q, customer representatives, and SME that execute these processes, implement procedures. During this process, these team members implement ISMS principles through the following: • Clear definition of scope and technical requirements • Identification of discrete activities and their potential hazards • Scheduling activities in a safe and logical progression • Estimating the resources required to successfully and safely perform the work • Identifying and maintaining critical interface agreements • Mitigation and control of identified risks and hazards • Assignment and controlled release of the work for execution • Safe performance of the work • Continuous feedback that leads to changing how the work is performed with particular

    attention to the potential for accumulation of risk through multiple changes. In addition, control of safely configured equipment, facilities, materials, qualified staff, and enabling documentation required to execute mission work is described in TFC-PLN-03.

    Set Expectations The WBS development process establishes the expectations for accomplishing work, prioritizing tasks, and allocating resources. A hierarchy of mechanisms is used such that each successive lower tier provides an increasing level of detail on “what” work is to be performed and “how” integration occurs (i.e., broad mission objectives are translated into discrete tasks). Expectations are set by establishing performance objectives, including ESH&Q performance, whereby cost and schedule considerations can never override safety considerations for the assigned work. The formality of these objectives depends on the scope of work, its complexity, and the hazards associated with the work.

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 27 of 56 January 18, 2018

    At the activity level, as stated in Section 4.2, “Guiding Principle 2 – Clear Roles and Responsibilities,” employee expectations are set annually and periodically reviewed.

    Prioritize Tasks and Allocate Resources Potential hazards are considered in prioritizing and scheduling work during the integrated planning process (TFC-PLN-147) and work package preparation (TFC-OPS-MAINT-C-01 and TFC-ESHQ-S_SAF-C-02). WRPS maintains a Plan of the Day and Plan of the Week to manage near-term work (TFC-OPS-OPER-C-65). Work scheduled beyond the Plan of the Week timeframe is planned and scheduled in the Integrated Management Meeting and other departmental scheduling meetings.

    Subcontractor ISMS Flowdown The procurement process is described in RPP-8411, “Procurement Process Description,” that defines an integrated supply chain to consistently acquire the highest quality and best value products and services while ensuring necessary technical standards and requirements are met. The following paragraphs describe the specific mechanisms by which WRPS ensures flowdown of ISMS and performs oversight of subcontractor safety, health, and quality work performance. Specific requirements for subcontractors, including safety requirements, are documented during the procurement process. Subcontracts are developed and managed within two major categories: (1) products that include materials, supplies, equipment and commercial items; and (2) technical services obtained from subcontractors. These subcontracts contain standard provisions and may include Special Provision 5 (Contract DE-AC27-08RV14800), which contains the ISMS DEAR Clause 970.5223-1 depending on the magnitude and complexity of the task order. Regardless of the type of contract issued, each element of work is issued to the subcontractor via a task order, which includes a specific statement of work (SOW) governed by the following procedures: • TFC-BSM-CP_CPR-C-05 • TFC-BSM-CP_CPR-C-06. A Buyer’s Technical Representative (BTR) is assigned by the requisitioning organization, activity, or cost account manager to a task order to act as the day-to-day technical representative. The primary duty of the BTR is to provide technical direction and clarification to the subcontractor to ensure performance of all elements in accordance with the SOW without placing emphasis on schedule or cost to the detriment of quality, safety, or the environment (TFC-BSM-CP_CPR-C-05). The BTR is responsible for internal coordination of, and interface with, the subcontractor regarding the various technical requirements such as quality assurance, safety, health, security and emergency services, protective forces, environmental, PAAA, and ISMS principles applicable to the performance of the Contract pursuant to the TOC implementing procedures. The TOC ESH&Q organizations provide subcontractor management support to the BTR by: (1) communicating requirements; and (2) performing assessments, inspections, and (or) surveillances to ensure compliance (TFC-PLN-116). When applicable, the task is evaluated against the approved safety basis in accordance with TFC-ENG-SB-C-03.

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 28 of 56 January 18, 2018

    Facility/Activity Level For operational, maintenance, and construction activities, the scope of authorized work is captured on a schedule, is addressed at the plan-of-the-week meetings, and is communicated during the plan-of-the-day meetings within the work control process. Line supervisors and managers ensure activities relating to ESH&Q issues (e.g., worker safety and health, environmental compliance monitoring, waste management, safety system operability, radiological control, and quality assurance) are resource loaded by coordination with ESH&Q managers. Operations personnel analyze facility and equipment conditions and resources, and initiate actions to ensure activities significant to ESH&Q are promptly resolved. Safety basis and environmental basis controls, such as those specified in the TSRs and environmental specification requirements, are monitored through surveillance testing, equipment status control programs, and operator rounds. At the individual task level, work control processes, such as job hazard analyses and radiological work permits, may be standing documents used for pre-defined standard work scopes or may be job-specific. The work control processes use face-to-face work planning engagement of workers, line management, and the ESH&Q support personnel for higher risk or complex work. A comprehensive work planning process is also used to involve the workers in hazard identification. In this way, preparations are identified to: (1) reduce the possibility of injury or exposure of the worker and minimize the impact on the public and the environment; and (2) ensure the work scope is properly defined. This process works because of the worker engagement and attention of personnel to each other’s safety needs as a result of the ESH&Q training provided to the TOC workforce. The entire process of defining and planning the work is improved through the TOC Assessment program, which provides feedback to the planning process. The scope of maintenance, operations, and construction work is defined using the TOC work control process (TFC-OPS-MAINT-C-01). The hazards are identified during the planning stage using integrated work planning/review teams or job hazard analyses/radiological work permits. The rigor or level of work planning required (e.g., verbally directed, routine, planning required, work planning with JRG review) is determined by initial work screening. The required planning elements for conducting the various levels of work planning are graded to the complexity of the work, the hazards encountered in performing the work, and the uncertainty about the work and hazards it entails.

    4.9 Core Function 2 – (Identify and) Analyze Hazards Identifying and analyzing potential hazards and environmental impacts is important to ensuring hazards are adequately controlled and requirements are met. Hazards and environmental impacts (e.g., tank vapors or beryllium) are identified as part of baseline development, a process that continues throughout the facility or project lifecycle. Work performed as part of the mission is evaluated against the bounding conditions of the safety basis. For the TOC, hazard identification and analysis are defined at the company level, but they are implemented at the facility and activity level.

    Applicable Guiding Principles

    1. Line Management Responsibility 2. Clear Roles and Responsibilities 3. Competence per Responsibilities

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 29 of 56 January 18, 2018

    The job hazard analyses process for identifying, evaluating, controlling, and communicating potential hazards associated with work performed by the TOC is described in TFC-ESHQ-S_SAF-C-02. This procedure applies to all TOC work activities involving general plant maintenance, building maintenance, construction, facility operations, environmental remediation, subcontractors, and service organizations. Job Hazard Analysis (JHA) within the work scope and responsibility of other Hanford prime contractor service organizations (e.g., Fire Systems Maintenance, Refrigerated Equipment Service) are prepared in accordance with their work processes as described by their work programs per contract with DOE and as described in their approved ISMS descriptions. The GHA and worker training and qualifications provide the worker with the proper skills and abilities to perform routine work activities. If work activities are covered by the GHA and performed using a general Radiological Work Permit (RWP), for radiological work, no additional hazard analysis is required. Work processes and hazard identification and controls are integrated with HPI processes, and the appropriate amount of rigor is applied to ensure resources are concentrated on the critical tasks to be performed. Hazards, error-likely situations, and error precursors that may be associated with the critical tasks are identified (see Figure 10).

    Figure 10. Identify Hazards.

    At the activity level, the workers are trained to identify and select the appropriate controls for a broad range of hazards that may be encountered. These hazards and controls are provided in a JHA checklist, which is a tool that reminds workers of the types of hazards that may exist and the controls identified for mitigating the hazards. The JHA is used by workers, supervisors, and SMEs throughout the work processes. Additional requirements and special controls are also included, such as the need for any special work permits, checklists, or authorizations (TFC-ESHQ-S_SAF-C-02).

    Technical procedures are developed for routine operations and incorporate task specific hazard controls, as discussed in TFC-OPS-OPER-C-13. For both new procedures and revisions, a JHA walkdown is performed in accordance with TFC-ESHQ-S_SAF-C-02 by the procedure writer, with hazard mitigation reviewed by personnel such as the procedure user and representatives from Operations, Environmental, Radiological Control, Industrial Safety, and Industrial Hygiene. Hazards and hazard controls are subsequently validated during the procedure validation walkdown. The process to develop, implement, and maintain the primary facility safety basis is contained in TFC-ENG-SB-C-06 and TFC-ENG-SB-C-01. Similarly, the TOC environmental basis is administratively implemented by TFC-PLN-123. Projects are designed using an iterative process focused on enabling assumptions, risk management, and decision analysis. TFC-PRJ-PM-C-02 addresses construction projects. TFC-ESHQ-RP-STD-03 addresses radiological aspects of new designs. Multi-disciplinary design

  • Integrated Safety Management System Description

    Manual Document Page Issue Date

    Management Plan TFC-PLN-41, REV A-4

    Page 30 of 56 January 18, 2018

    review teams help identify and resolve design and lifecycle issues for their respective disciplines. This activity is coordinated with hazard identification and analyses. Identified hazards are mitigated by design or engineered controls as part of the design process. Analysis of facility hazards, environmental impacts, and job hazards is an essential process for ensuring that construction and facility operations and maintenance are conducted in a safe and environmentally protective manner. Facility hazard analyses provide for the development of facility-specific controls to protect workers, the public, and the environment. The JHA process identifies hazards (facility and activity specific) to establish effective work controls and provide for safe performance of work. Hazard and environmental impact identification and analyses are performed per TFC-ESHQ-S_SAF-C-02. For Level 1 work packages (ref. TFC-OPS-MAINT-C-01), new technical procedures, or major revisions to technical procedures (ref. TFC-OPS-OPER-C-13), a walkdown of the job site with the supervisor is performed to identify potential hazards relating to tasks to be performed. The supervisor ensures engagement by the worker representative(s). These may include Industrial Safety, Industrial Hygiene, Health Physics Technician, Environmental Representative, and other SMEs, as determined necessary by the planner/procedure writer and supervisor. Work activities classified as high risk receive review by the JRG to ensure that relevant work documents are comprehensively and thoroughly reviewed, including contingency plans for emergent situations (TFC-ESHQ-RP_ADM-C-11). This review of work activities is meant to be independent upon the mechanism (e.g., work instructions, procedures, work plans, etc.) used to control the process. Bargaining unit personnel engaged in the JRG are expected to provide additional information, as needed, regarding work planning assumptions and workability of the work documentation. From a worker’s standpoint, bargaining unit personnel also ensure work documentation adequately addresses job hazards. A table-top discussion performed in lieu of a required field walkdown, as noted above, requires approval of the responsible Level 2 manager. For activities conducted by the TOC, site-specific environmental impact statements, environmental analyses, applicable supplemental analyses, and approved site-wide categorical exclusions are prepared under the National Environmental Policy Administration (NEPA).

    Identify the Hazards WRPS’ EMS (


Recommended