+ All Categories
Home > Documents > Inter-State Transmission for XII Plan

Inter-State Transmission for XII Plan

Date post: 08-Apr-2018
Category:
Upload: anon835454184
View: 217 times
Download: 0 times
Share this document with a friend

of 28

Transcript
  • 8/7/2019 Inter-State Transmission for XII Plan

    1/28

  • 8/7/2019 Inter-State Transmission for XII Plan

    2/28

    Transmission PlanningBasic Inputs

    Generation Quantum, location and type

    Load Centres

    Time frame

    Land/ Right of Way availability

    Technology

  • 8/7/2019 Inter-State Transmission for XII Plan

    3/28

    Power Supply Scenario

    100

    152

    218

    437

    323

    2007 2012 2017 2022 2027

    Year

    GW

    Peak Demand

    132220

    306

    575

    425

    2007 2012 2017 2022 2027Year

    GW

    Installed Capacity Requirement

    End of X plan

    During 12th

    plan

    During 13th

    planDuring 11th

    plan

  • 8/7/2019 Inter-State Transmission for XII Plan

    4/28

    Capacity addition envisaged

    Under Central Sector : about 28,600 MW

    Under Private Sector : about 57,000 MW

    Capacity Addition Envisaged in 12th Plan

    Target capacity addition in 12th Plan : 100,000 MW (Tentative)

    Private, 57000,

    57%

    Central, 28600,

    29%

    State, 14400,

    14%

  • 8/7/2019 Inter-State Transmission for XII Plan

    5/28

    Uneven Disposition of Energy Resource

    Coal resources Eastern/Central India

    Lignite Gujarat

    Load centre Western,

    Northern and Southern

    States

    Expected Installed Capacity (2025) : 6,00,000MW

    Lara

    Partabpur

    Talcher/Ib Valley

    Krishnapatnam

    NEPAL

    KorbaBhopalIndore

    Tadri

    Girye

    Kaiga

    Thiruvananthapuram

    Pipavav

    Kudankulam

    SR

    Bangalore

    Kayamkulam

    WR

    Tarapur

    Mumbai

    Cuddalore

    Ennore

    Akaltara

    Raipur

    Hyderabad

    RAPP

    Gandhinagar

    Mudra

    Delhi

    Ludhiana

    NR

    Jaipur

    Jammu

    Sasan

    Vindhyachal

    Lucknow

    Load Centre Based Generatio

    Ultra-Mega Generation

    Hydro Based Generation

    Coastal Generation

    Coal Based generation

    Nuclear generation

    BhubaneswarDarlipali

    Vizag

    Simhadri

    LEGEND

    Load-Centre

    NER

    Guwahati

    Koderma

    SIKKIM

    Kolkata

    ER

    PatnaNECK

    CHICKEN

    BHUTAN

    DESHBANGLA

    MYANMMAR

    Mangalore

    KozhikodeSouth MadrasChennai

  • 8/7/2019 Inter-State Transmission for XII Plan

    6/28

    Approach for Generation Planning Emerging

    Very large Power Stations located near coal mines

    Orissa, Chhattisgarh, M.P, Jharkhand

    Large HEPs located far off from load centers

    Sikkim, North-eastern Region

    Coastal Power Stations based on imported or domestic

    coal

    Mundra, Krishnapatnam, Tuticorin, Cuddalore, Ennore

    Gas based Power Stations located along the gas-grid

    Load centre based Power Stations

  • 8/7/2019 Inter-State Transmission for XII Plan

    7/28

  • 8/7/2019 Inter-State Transmission for XII Plan

    8/28

    Factors considered in Transmission Planning

    Need to clear the backlog of inadequacies and to take care of

    future requirements

    Need to add certain degree of redundancies and cushions totake care of eventualities and to promote power trading

    Open Access in transmission- Need to have a strongtransmission system, to cope this dynamic requirement

    Open Access in distribution- where consumer will have optionto source power from wherever it is economical

  • 8/7/2019 Inter-State Transmission for XII Plan

    9/28

    Upgrading & Uprating of existing transmission corridor

    High Temp endurance conductor (INVAR-230deg C)

    765kV AC Transmission System

    +800kV, 6000MW HVDC system

    Fixed and variable (TCSC) series capacitors

    GIS, substation automation & remote operation High rise & Multi ckt towers

    Technologies Being Adopted

  • 8/7/2019 Inter-State Transmission for XII Plan

    10/28

    Transmission Plan

  • 8/7/2019 Inter-State Transmission for XII Plan

    11/28

    Development of National Grid on continual basis with sufficient

    inter-regional power transfer capacity

    Planned to enhance the capacity progressively to about -

    National Grid

    A Continuing Process

    Strengthening of National Grid

    20800

    31000

    75000

    0

    20000

    40000

    60000

    80000

    Present By 2011-12 By 2016-17

  • 8/7/2019 Inter-State Transmission for XII Plan

    12/28

    Transmission addition Programme by

    POWERGRID in 12th Plan

    Sector Capacity(MW)addition

    envisaged

    Transmission System planned forcorresponding capacity(MW)

    Under construction DPR under

    preparationCentral 28,600 4,140 17,394

    Private 57,000 14,740 33,676

    Total 85,600 18,880 51,070

  • 8/7/2019 Inter-State Transmission for XII Plan

    13/28

    IPP Generations expected in next 4-5years

    Generation Pocket Capacity Approx. cost of newtransmission system

    Chattisgarh 15,000 MW 22,000 Crs

    Orissa 6,100 MW 8,800 Crs

    Jharkhand 5,100 MW 6,000 Crs

    Sikkim & West Bengal 2,350 MW 1250 Crs

    Andhra Pradesh 4,700 MW 1500 Crs

    Tamil Nadu 2000 MW 1850 Crs

    Total 35,250 MW 41,400 Crs

  • 8/7/2019 Inter-State Transmission for XII Plan

    14/28

  • 8/7/2019 Inter-State Transmission for XII Plan

    15/28

    Transmission Addition

    Programme (Physical)

  • 8/7/2019 Inter-State Transmission for XII Plan

    16/28

    Transmission Addition Programme

    Tr. Lines, Voltage

    level

    End of 10th

    Plan (Ckm)

    End of 11th Plan

    (Ckm)

    Estimated

    additions in12th Plan

    (Ckm)

    765 KV 2,184 7,612 25000-30000

    HVDC Bi-pole 5,872 11,078 4000 - 6000

    400 KV 75,722 1,25,000 50000

    220 KV 1,14,629 1,50,000 40000

    Total Tr. Lines 1,98,569 2,93,852 119,000

    126,000

  • 8/7/2019 Inter-State Transmission for XII Plan

    17/28

    Transmission Addition ProgrammeContd

    Sub-Stn. Voltage level End of10th Plan

    (MVA/MW)

    End of 11th

    Plan

    (MVA/MW)

    Estimatedaddition in12th Plan

    (MVA/MW)

    765 KV - 53,000 110,000

    HVDC 8,200 14,700 16,000 -22,000

    400 KV 92,942 145,000 80,000

    220/230 KV 156,497 230,000 95,000

    Inter Regional TransferCapacity

    14,000 31,000 75,000

  • 8/7/2019 Inter-State Transmission for XII Plan

    18/28

    POWERGRIDs Transmission

    Addition Programme (Physical)

  • 8/7/2019 Inter-State Transmission for XII Plan

    19/28

    Transmission Lines : 54,000 66,000 Ckt.kms

    + 600kV/800kV HVDC: 4,000 6,000 ckt km

    765 kV AC : 25,000 30,000 ckt km

    400kVkV AC : 25,000 30,000 ckt. km

    New Substations 75 - 90 Nos.

    765/400kV : 25 30 Nos.

    400/220/132kV : 50 - 60 Nos.

    1200/400kV : 1 2 Nos.

    Transformation Capacity (MVA)- 1,30,000 1,50,000 MVA

    765/400kV : 90,000 1,00,000 MVA

    400/220/132kV : 40,000 50,000 MVA

    POWERGRID Physical Target (12th Plan)

  • 8/7/2019 Inter-State Transmission for XII Plan

    20/28

    POWERGRIDs Requirements in 12th Plan

    Requirement of S/S equipment (Number)765 kV

    HVDC Bipole projects 2

    765 kV 500 MVA 1 ph units 210

    765 kV 80 MVAR reactors 1 ph units 180

    765 kV Circuit Breakers 475

    765 kV Current Transformers (sets) 1400765 kV CVT's (sets) 500

    765 kV Isolators (sets) 1300

  • 8/7/2019 Inter-State Transmission for XII Plan

    21/28

    POWERGRIDs Requirements in 12th Plan

    Requirement of S/S equipment (Number)400 kV

    400 kV Class transformer 120

    400kV 80, 63 & 50 MVAR reactor 3 ph units 120

    400 kV Circuit Breakers 1300

    400 kV Current Transformers (sets) 4000

    400 kV CVT's (sets) 1100

    400 kV Isolators (sets) 3400

  • 8/7/2019 Inter-State Transmission for XII Plan

    22/28

    Supply Quantity Requirements for Line in 12th Plan

    Item Unit Annual quantity Total quantity

    Conductor Km 128,000- 152,000 6,40,000 7,62,000

    Tower Steel MT 5,22,000 6,18,000 26,08,000

    30,91,000Hardware Sets 1,77,000 2,10,000 8,84,000 10,52,000

    Insulators Disc unit 157,19,000 186,38,000

    785,94,000-931,88,000

  • 8/7/2019 Inter-State Transmission for XII Plan

    23/28

    Estimated Investment in Transmission

    12th Plan (2012-2017)

    Estimated total fund requirement : Rs. 2,00,000 Cr

    Inter-State Sector : Rs. 1,00,000 Cr

    State Sector : Rs. 1,00,000 Cr

  • 8/7/2019 Inter-State Transmission for XII Plan

    24/28

    Issues/Concerns

    Private generation

    Uncertainty w.r.t time, beneficiaries

    Funding and payment security mechanism

    Commensurate development of intra-state network

    Timely statutory clearances like forest, aviation, PTCC,

    Defence etc.

    Availability of ROW as well as Land Enhancement of manufacturing capacity of main

    equipment viz. transformers, reactors, CB, CT etc.

    Availability of EPC contractors & right/trained manpower

  • 8/7/2019 Inter-State Transmission for XII Plan

    25/28

    POWERGRIDs Efforts

    Parallel processing of various activities

    Standardized design

    Continuous Vendor Development

    Effective Project Monitoring

  • 8/7/2019 Inter-State Transmission for XII Plan

    26/28

  • 8/7/2019 Inter-State Transmission for XII Plan

    27/28

    Technologies in Transmission

  • 8/7/2019 Inter-State Transmission for XII Plan

    28/28

    Initiatives by POWERGRID for indigenous vendordevelopment

    Substation equipments

    For 800kV Transformers/Reactors qualification criteria relaxed forindigenous manufacturers for certain portion of supplies

    800kV indigenous developed Circuit breakers being installed at SeoniSubstation for trial purposes

    Transmission Line equipments

    Conductor manufacturers not meeting POWERGRID qualificationcriteria for 400kV being developed for supply against trial order.

    Trial orders placed on indigenous composite insulator manufacturers

    Civil construction firms, tower manufacturers and small contractorsbeing allowed for participation against Tower vendor developmentpackages


Recommended