Transmission PlanningBasic Inputs
Generation Quantum, location and type
Load Centres
Time frame
Land/ Right of Way availability
Technology
8/7/2019 Inter-State Transmission for XII Plan
3/28
Power Supply Scenario
100
152
218
437
323
2007 2012 2017 2022 2027
Year
GW
Peak Demand
132220
306
575
425
2007 2012 2017 2022 2027Year
GW
Installed Capacity Requirement
End of X plan
During 12th
plan
During 13th
planDuring 11th
plan
8/7/2019 Inter-State Transmission for XII Plan
4/28
Capacity addition envisaged
Under Central Sector : about 28,600 MW
Under Private Sector : about 57,000 MW
Capacity Addition Envisaged in 12th Plan
Target capacity addition in 12th Plan : 100,000 MW (Tentative)
Private, 57000,
57%
Central, 28600,
29%
State, 14400,
14%
8/7/2019 Inter-State Transmission for XII Plan
5/28
Uneven Disposition of Energy Resource
Coal resources Eastern/Central India
Lignite Gujarat
Load centre Western,
Northern and Southern
States
Expected Installed Capacity (2025) : 6,00,000MW
Lara
Partabpur
Talcher/Ib Valley
Krishnapatnam
NEPAL
KorbaBhopalIndore
Tadri
Girye
Kaiga
Thiruvananthapuram
Pipavav
Kudankulam
SR
Bangalore
Kayamkulam
WR
Tarapur
Mumbai
Cuddalore
Ennore
Akaltara
Raipur
Hyderabad
RAPP
Gandhinagar
Mudra
Delhi
Ludhiana
NR
Jaipur
Jammu
Sasan
Vindhyachal
Lucknow
Load Centre Based Generatio
Ultra-Mega Generation
Hydro Based Generation
Coastal Generation
Coal Based generation
Nuclear generation
BhubaneswarDarlipali
Vizag
Simhadri
LEGEND
Load-Centre
NER
Guwahati
Koderma
SIKKIM
Kolkata
ER
PatnaNECK
CHICKEN
BHUTAN
DESHBANGLA
MYANMMAR
Mangalore
KozhikodeSouth MadrasChennai
8/7/2019 Inter-State Transmission for XII Plan
6/28
Approach for Generation Planning Emerging
Very large Power Stations located near coal mines
Orissa, Chhattisgarh, M.P, Jharkhand
Large HEPs located far off from load centers
Sikkim, North-eastern Region
Coastal Power Stations based on imported or domestic
coal
Mundra, Krishnapatnam, Tuticorin, Cuddalore, Ennore
Gas based Power Stations located along the gas-grid
Load centre based Power Stations
8/7/2019 Inter-State Transmission for XII Plan
7/28
8/7/2019 Inter-State Transmission for XII Plan
8/28
Factors considered in Transmission Planning
Need to clear the backlog of inadequacies and to take care of
future requirements
Need to add certain degree of redundancies and cushions totake care of eventualities and to promote power trading
Open Access in transmission- Need to have a strongtransmission system, to cope this dynamic requirement
Open Access in distribution- where consumer will have optionto source power from wherever it is economical
8/7/2019 Inter-State Transmission for XII Plan
9/28
Upgrading & Uprating of existing transmission corridor
High Temp endurance conductor (INVAR-230deg C)
765kV AC Transmission System
+800kV, 6000MW HVDC system
Fixed and variable (TCSC) series capacitors
GIS, substation automation & remote operation High rise & Multi ckt towers
Technologies Being Adopted
8/7/2019 Inter-State Transmission for XII Plan
10/28
Transmission Plan
8/7/2019 Inter-State Transmission for XII Plan
11/28
Development of National Grid on continual basis with sufficient
inter-regional power transfer capacity
Planned to enhance the capacity progressively to about -
National Grid
A Continuing Process
Strengthening of National Grid
20800
31000
75000
0
20000
40000
60000
80000
Present By 2011-12 By 2016-17
8/7/2019 Inter-State Transmission for XII Plan
12/28
Transmission addition Programme by
POWERGRID in 12th Plan
Sector Capacity(MW)addition
envisaged
Transmission System planned forcorresponding capacity(MW)
Under construction DPR under
preparationCentral 28,600 4,140 17,394
Private 57,000 14,740 33,676
Total 85,600 18,880 51,070
8/7/2019 Inter-State Transmission for XII Plan
13/28
IPP Generations expected in next 4-5years
Generation Pocket Capacity Approx. cost of newtransmission system
Chattisgarh 15,000 MW 22,000 Crs
Orissa 6,100 MW 8,800 Crs
Jharkhand 5,100 MW 6,000 Crs
Sikkim & West Bengal 2,350 MW 1250 Crs
Andhra Pradesh 4,700 MW 1500 Crs
Tamil Nadu 2000 MW 1850 Crs
Total 35,250 MW 41,400 Crs
8/7/2019 Inter-State Transmission for XII Plan
14/28
8/7/2019 Inter-State Transmission for XII Plan
15/28
Transmission Addition
Programme (Physical)
8/7/2019 Inter-State Transmission for XII Plan
16/28
Transmission Addition Programme
Tr. Lines, Voltage
level
End of 10th
Plan (Ckm)
End of 11th Plan
(Ckm)
Estimated
additions in12th Plan
(Ckm)
765 KV 2,184 7,612 25000-30000
HVDC Bi-pole 5,872 11,078 4000 - 6000
400 KV 75,722 1,25,000 50000
220 KV 1,14,629 1,50,000 40000
Total Tr. Lines 1,98,569 2,93,852 119,000
126,000
8/7/2019 Inter-State Transmission for XII Plan
17/28
Transmission Addition ProgrammeContd
Sub-Stn. Voltage level End of10th Plan
(MVA/MW)
End of 11th
Plan
(MVA/MW)
Estimatedaddition in12th Plan
(MVA/MW)
765 KV - 53,000 110,000
HVDC 8,200 14,700 16,000 -22,000
400 KV 92,942 145,000 80,000
220/230 KV 156,497 230,000 95,000
Inter Regional TransferCapacity
14,000 31,000 75,000
8/7/2019 Inter-State Transmission for XII Plan
18/28
POWERGRIDs Transmission
Addition Programme (Physical)
8/7/2019 Inter-State Transmission for XII Plan
19/28
Transmission Lines : 54,000 66,000 Ckt.kms
+ 600kV/800kV HVDC: 4,000 6,000 ckt km
765 kV AC : 25,000 30,000 ckt km
400kVkV AC : 25,000 30,000 ckt. km
New Substations 75 - 90 Nos.
765/400kV : 25 30 Nos.
400/220/132kV : 50 - 60 Nos.
1200/400kV : 1 2 Nos.
Transformation Capacity (MVA)- 1,30,000 1,50,000 MVA
765/400kV : 90,000 1,00,000 MVA
400/220/132kV : 40,000 50,000 MVA
POWERGRID Physical Target (12th Plan)
8/7/2019 Inter-State Transmission for XII Plan
20/28
POWERGRIDs Requirements in 12th Plan
Requirement of S/S equipment (Number)765 kV
HVDC Bipole projects 2
765 kV 500 MVA 1 ph units 210
765 kV 80 MVAR reactors 1 ph units 180
765 kV Circuit Breakers 475
765 kV Current Transformers (sets) 1400765 kV CVT's (sets) 500
765 kV Isolators (sets) 1300
8/7/2019 Inter-State Transmission for XII Plan
21/28
POWERGRIDs Requirements in 12th Plan
Requirement of S/S equipment (Number)400 kV
400 kV Class transformer 120
400kV 80, 63 & 50 MVAR reactor 3 ph units 120
400 kV Circuit Breakers 1300
400 kV Current Transformers (sets) 4000
400 kV CVT's (sets) 1100
400 kV Isolators (sets) 3400
8/7/2019 Inter-State Transmission for XII Plan
22/28
Supply Quantity Requirements for Line in 12th Plan
Item Unit Annual quantity Total quantity
Conductor Km 128,000- 152,000 6,40,000 7,62,000
Tower Steel MT 5,22,000 6,18,000 26,08,000
30,91,000Hardware Sets 1,77,000 2,10,000 8,84,000 10,52,000
Insulators Disc unit 157,19,000 186,38,000
785,94,000-931,88,000
8/7/2019 Inter-State Transmission for XII Plan
23/28
Estimated Investment in Transmission
12th Plan (2012-2017)
Estimated total fund requirement : Rs. 2,00,000 Cr
Inter-State Sector : Rs. 1,00,000 Cr
State Sector : Rs. 1,00,000 Cr
8/7/2019 Inter-State Transmission for XII Plan
24/28
Issues/Concerns
Private generation
Uncertainty w.r.t time, beneficiaries
Funding and payment security mechanism
Commensurate development of intra-state network
Timely statutory clearances like forest, aviation, PTCC,
Defence etc.
Availability of ROW as well as Land Enhancement of manufacturing capacity of main
equipment viz. transformers, reactors, CB, CT etc.
Availability of EPC contractors & right/trained manpower
8/7/2019 Inter-State Transmission for XII Plan
25/28
POWERGRIDs Efforts
Parallel processing of various activities
Standardized design
Continuous Vendor Development
Effective Project Monitoring
8/7/2019 Inter-State Transmission for XII Plan
26/28
8/7/2019 Inter-State Transmission for XII Plan
27/28
Technologies in Transmission
8/7/2019 Inter-State Transmission for XII Plan
28/28
Initiatives by POWERGRID for indigenous vendordevelopment
Substation equipments
For 800kV Transformers/Reactors qualification criteria relaxed forindigenous manufacturers for certain portion of supplies
800kV indigenous developed Circuit breakers being installed at SeoniSubstation for trial purposes
Transmission Line equipments
Conductor manufacturers not meeting POWERGRID qualificationcriteria for 400kV being developed for supply against trial order.
Trial orders placed on indigenous composite insulator manufacturers
Civil construction firms, tower manufacturers and small contractorsbeing allowed for participation against Tower vendor developmentpackages