B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U R I T Y www.inogate.org 1 “Interconnectivity: Helping INOGATE PCs to adopt adequate regulatory frameworks, methodologies & tools” Nick Tourlis – Electricity Markets/Convergence Expert– INOGATE Technical Secretariat 14th Meeting of the Eastern Partnership Platform 3 on Energy Security Brussels, Belgium, 11 December 2015
Transcript
Page 1: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U R I T Y

www.inogate.org 1

“Interconnectivity: Helping INOGATE PCs to adopt adequate

regulatory frameworks, methodologies & tools” Nick Tourlis – Electricity Markets/Convergence Expert– INOGATE Technical Secretariat

14th Meeting of the Eastern Partnership Platform 3 on Energy Security Brussels, Belgium, 11 December 2015

Page 2: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

Contents of the Presentation

1. INOGATE and the yesterday’s workshop a. What is INOGATE ? b. A bit of history c. SoS and E- Interconnectivity workshop

2. Security of Supply Conclusions a. Projections and Policy b. Challenges and Project identification c. Regional coordination and inter. cooperation

3. Electricity Interconnectivity Conclusions a. Geography b. Existing situation and foreseeable future c. Overview of the findings

Page 3: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

Contents of the Presentation

1. INOGATE and the yesterday’s workshop a. What is INOGATE ? b. A bit of history c. SoS and E- Interconnectivity workshop

2. Security of Supply Conclusions a. Projections and Policy b. Challenges and Project identification c. Regional coordination and inter. cooperation

3. Electricity Interconnectivity Conclusions a. Geography b. Existing situation and foreseeable future c. Overview of the findings

Page 4: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

What is INOGATE? An EU-funded programme for regional energy cooperation

between the European Union and its Partner Countries

in Eastern Europe, Caucasus and Central Asia

12 INOGATE Partner Countries: Armenia, Azerbaijan, Belarus, Georgia, Kazakhstan, Kyrgyzstan,

Moldova, Tajikistan, Turkey (O), Turkmenistan, Ukraine and Uzbekistan.

Note: this map is with out prejudice to the status of sovereignty over any territory, to the delimitation

of international frontiers and boundaries, and to the name of any territory, city or area

Page 5: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

INOGATE Development 1996-2016

Expansion Phase

Launch of Baku Initiative, Energy Road Map adopted by Ministers at 2nd Ministerial Conference in Astana providing long-term strategy

Phase 3: Nov 2004 - present

Demonstration Phase

Proves the impact of small-scale demonstration projects such as cross-border gas metering stations helping to improve transparency of gas trade

Phase 2: 2000-2004

Technical audits phase reveals the need for over 5 billion EUR in investments for rehabilitating energy infrastructures

Phase 1: 1996-1999

INOGATE Launch

The Interstate Oil & Gas Transport to Europe (INOGATE) Programme as first-ever regional energy cooperation of this scale

Launch 1996

Page 6: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

New ITS - Fact Box

• Project title: INOGATE Technical Secretariat (ITS)

• Budget: € 16.5 + 3 = 19.5 million • Duration: 36 months (02.2012 – 01.2015) • Extension: up to 30/4/2016 • Partner Countries:

– Eastern Europe - Belarus, Moldova, Ukraine, – Caucasus - Armenia, Azerbaijan, Georgia – Central Asia - Kyrgyzstan, Turkmenistan,

Kazakhstan, Uzbekistan, Tajikistan

• Four Project Components: Electricity & Gas, RES/EE, Statistics, Communication

Page 7: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

• Projections, Legislation, Barriers, Regional/International cooperation

Security of Supply

• Energy Charter, ITS, DG ENER, EnCS, DG NEAR

Policy, Regulation and Financing

• Case examples: Planning, development, barriers, stakeholders' engagement

Electricity Interconnectivity

Overview of yesterday’s workshop

7

Page 8: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

Contents of the Presentation

1. INOGATE and the yesterday’s workshop a. What is INOGATE ? b. A bit of history c. SoS and E- Interconnectivity workshop

2. Security of Supply Conclusions a. Projections and Policy b. Challenges and Project identification c. Regional coordination and inter. cooperation

3. Electricity Interconnectivity Conclusions a. Geography b. Existing situation and foreseeable future c. Overview of the findings

Page 9: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

Security of Supply Conclusions (1/2)

9

Evolution of Long Term Supply/Demand Balance:

Electricity: Surplus (AM, AZ, GE:2016, UA) / Deficit (BY, MD)

Natural gas: Surplus (AZ) / Deficit (AM, BY, GE, MD, UA)

Policy and Legislation:

Legislation in place: All

Legislation in progress: (EnC parties on EU Acquis requirements)

Challenges:

Diversification: All except AZ (in surplus)

Infrastructure: Electricity (All), Natural Gas (All except AZ, BY)

Page 10: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

Security of Supply Conclusions (2/2)

10

Projects’ Identification:

Transmission planning functions similar to EU: No (except GE)

Decision making: Political/IFI led (not always properly consulted)

Regional Coordination:

Formalised: Only MD, UA (EnC WG on SoS)

Non-formalised: Mostly bilateral & occasional (int. forums)

International Cooperation:

Participation: (Yes! – comparably less in AZ and BY)

Coordination: Room for improvement (AM ECG a good example)

Page 11: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

Contents of the Presentation

1. INOGATE and the yesterday’s workshop a. What is INOGATE ? b. A bit of history c. SoS and E- Interconnectivity workshop

2. Security of Supply Conclusions a. Projections and Policy b. Challenges and Project identification c. Regional coordination and inter. cooperation

3. Electricity Interconnectivity Conclusions a. Geography b. Existing situation and foreseeable future c. Overview of the findings

Page 12: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

ENTSO-E to IPS/UPS Interface tie-lines

Source: C. Rehtanz et al. 2014

Page 13: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

The structure of IPS/UPS and neighboring countries

Source: C. Rehtanz et al. 2014 & own BRELL representation

BRELL Agreement 2002

Armenia

Page 14: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

Map © ENTSO-E, 2014

Interconnectivity: Transfer Capacities, New Infrastructure, Synchronisation

14

GE-AM Asynchronous Interconnection

350/700/1050 MW DC 2018-20, NIF, KfW, EIB

RO-MD Asynchronous Interconnection Project 1. Vulcanesti (MD) – Isaccea (RO)

Project 2. Straseni - Ungheni (MD) – Iasi (RO) Project 3. Balti (MD) – Suceava (RO) (PECI-ET015)

“Feasibility Study on the Synchronous

Interconnection of the Ukrainian and Moldovan

Power Systems to ENTSO-E Continental

Europe Power System”, 2015

BY-PL Asynchronous Interconnection Project1. Ros (BY) – Narew/Bialystok (PL) – 300 MW

Project2. Brest (BY) – Wolka Dobrynska (PL) – 140 to 250 MW

Baltics synchronis

ation to ENTSO-E System”, planned for 2025

BY-LT Synchronous Interconnection Project1. Grondo (BY) – Alytus (LT) Litpol Link

Project2. Maladzyechna (BY) – Vilnius (LT) Project3. Pastavy (BY) – Ingnalina (LT) – 3 lines

Page 15: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

E - Interconnectivity Conclusions (1/2)

15

Planning at transmission level:

Formalized TYNDP: GE, MD (in progress), UA (in progress)

Integrated power system planning: AM, AZ, BY

Project identification and appraisal:

Standardised: GE (via TYNDP incl. CBA & consultation)

Ad-hoc: AM, AZ, BY, MD, UA

Financing & regulatory treatment of new interconnection:

Financing: Mostly on state budget & grant and loan

Regulation: No experience with risks & incentives, no use of congestion rent

Page 16: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

16

Main barriers for investment:

Commonly recongnised: lack of capital and legal/regulatory framework, transaction cost

Other: Stranded assets (usage), market rules (MD-UA coupling)

Consultation & Cost sharing:

Consultation: No sufficient evidence (NRA powers and coordination of TSOs are generally limited)

Cost sharing: Mostly territorial based on bilateral agreement

The big picture: Divergence with the EU practices

Regulations 714/2009 and 347/2013 are in the verge to be adopted only by Energy Community Contracting Parties

E - Interconnectivity Conclusions (2/2)

Page 17: Interconnectivity: Helping INOGATE PCs to adopt adequate …archive.eap-csf.eu/assets/files/ITS Interconnectivity... · 2015. 12. 15. · Synchronous Interconnection of the Ukrainian

Спасибо! Thank you!

Nick Tourlis

Electricity Markets/Convergence Expert INOGATE Technical Secretariat

[email protected]

INOGATE Technical Secretariat and Integrated Programme in support of the Baku Initiative and the Eastern Partnership energy objectives