+ All Categories
Home > Documents > Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement...

Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement...

Date post: 24-Apr-2020
Category:
Upload: others
View: 6 times
Download: 0 times
Share this document with a friend
45
1 For the period ending 31 Aug 2012 Interim results presentation 2013FY
Transcript
Page 1: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

1

For the period ending 31 Aug 2012

Interim results presentation

2013FY

Page 2: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

2

TABLE OF CONTENTS • WELCOME

• SALIENT FEATURES

• SUSTAINABILITY ACHIEVEMENTS

• FINANCIAL REVIEW

• STRATEGY

• Short-term challenges & progress

• Medium to long-term strategy

• OPERATIONAL REVIEW

• Products, services & clients

• Competitors & value proposition

• Geographical footprint and key contracts

• RISK MANAGEMENT

• SEGMENTAL REVIEW

• ORDERBOOK & OUTLOOK

• CAPEX

• CONCLUSION

Page 3: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

3

WELCOME

Page 4: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

4

SALIENT FEATURES

Page 5: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

5

Salient Features – 31 August 2012

• Revenue up 33% to R1.14bn (2011:R857m)

• EBITDA up 437% to R136.4 m (2011:R25.4m)

• Headline earnings up 295% to R29.2m (2011:R15m loss)

• HEPS up 300% to 7.8cents (2011:3.9 cents loss)

• PAT up 353% to R47.3m (2011:R18.7m loss)

• EPS up 363% to 12.6cents (2011:4.8 cents loss)

• Order book up 35% to R2.43b (2011:R1.8b)

• Operating cash increased by R100.8m

Page 6: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

6

Sustainability Achievements

• Continued improved profitability in H1 FY 2013

• Our order book continues to strengthen with more long term contracts

• We have cemented our expansion into Ghana and continue our focus on Uganda & DRC

• We have successfully entered the housing development market through the purchase of

Safdev Land 1 for the Orchards Project

• ISO 9001 quality accreditation remains in all divisions

• OHSA 18001 safety accreditation has been obtained in all divisions

• Our LTIFR of 0.74 is significantly better than the industry norm of 1.33 and our tolerance

threshold of 1.0

• A High Yield Bond Programme for R202.5m was successfully concluded

• We have retained or replaced key staff

Page 7: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

7

FINANCIAL REVIEW 31 August 2012

Page 8: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

8

Statement of Income (as at 31st August 2012)

Salient Features

Aug 2011

R’ 000

% Aug 2012

R’ 000

Revenue 857 524 33.3% 1 142 776

EBITDA 25 407 437% 136 405

Profit/(loss) after tax (18 677) 353% 47 336

Headline earnings/(loss) (15 047) 294% 29 211

HEPS (3.90) 300% 7.80

Page 9: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

9

Statement of Financial Position (as at 31st August 2012)

Salient Features

Aug 2011

R’ 000

Aug 2012

R’ 000

Assets

Non-current assets 1 085 923 1 230 999

Current assets 626 951 960 341

Total assets 1 712 874 2 191 340

Equities and liabilities

Share capital and reserves 893 375 1 003 921

Non-current liabilities 298 564 535 757

Current liabilities 520 935 651 662

Total equity and liabilities 1 712 874 2 191 340

Net asset value per share (cents) 230.1 267.9

Page 10: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

10

Statement of Financial Position (as at 31st August 2012)

Salient Features Aug 2011 Aug 2012

• Cash

• Trade & other receivables

• No impairment of intangibles

R49.5m

R556.7m

R218.1m

R640.1m

• Investment in construction equipment

• Book value of PPE

R152.3m

R678.2m

R126.0m

R807.1m

• Operational cash-flow generated

• Dividends paid

• Net secured borrowings

• Debt/(debt+equity) ratio

(R55.7m)

Nil

R271.8m

23.3%

R45m

Nil

R268.7m

21.1%

• Profit after tax

• FCTR

• Dividend paid

(R18.7m)

R26.3m

Nil

R47.3m

R3.1m

Nil

Total assets

PPE

Cash reserves

Equity

Page 11: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

11

STRATEGY

Page 12: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

12

Short-Term Challenges & Progress

CHALLENGE

• Continued slowdown in public sector infrastructure spend (large scale projects)

PROGRESS

• Management intervention to improve profitability and synergy of divisions by focusing on tender submissions, contract execution & operational delivery

• Expansion into Ghana and Uganda (Esorfranki Geotechnical)

• Private sector clients targeted and market share grown through efficient project execution, high safety standards and timeous delivery

• Enhance brand awareness locally and cross-border

CHALLENGE

• B-BBEE focus

PROGRESS

• Level 4 B-BBEE certification maintained

• Proposed share deal

Page 13: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

13

Short-Term Challenges & Progress

CHALLENGE

• Price competitive environment and increasingly difficult contract terms and

conditions

PROGRESS

• Project execution capabilities improved

• Contract portfolio reviewed and profitability maintained by improving cost reporting standards

and standardising policies and procedures across all divisions

• Civil plant capacity expansion (enhancing efficiency and resource optimisation)

• Focus on brand awareness

• Group operations integrated into a single entity to harness cost effectiveness and

standardisation

• Group driven by common values, business philosophies and practices

• Resources rationalised to enhance shared values and cohesiveness

• CIDB level 9 achieved in CE, GB, SC and SJ categories

Page 14: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

14

Short-Term Challenges & Progress

CHALLENGE

• Organisational development

PROGRESS

• Succession and development plans implemented

CHALLENGE

• The Competition Commission investigation into alleged anti-competitive

behaviour in the piling and drilling markets is currently inactive after having the

matter referred to a tribunal following a failed settlement offer to the

Commissioner.

PROGRESS

• The board has raised an estimated provision in the financial statements for the

likely penalty.

• There has been no further progress on the fast track settlement

• Any further developments will be communicated to all stakeholders as they

occur.

Page 15: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

15

Short-Term Challenges & Progress

CHALLENGE

• Delayed payment cycles from government and main contractors

PROGRESS

• Significant advance payments on foreign contracts secured

• Strict working capital management and reporting enforced

• Short-term working capital facilities secured to accommodate growth and delayed payment

cycles

• Capital asset expansion programmes secured on the back of long-term contracts, boosting

price competitiveness and efficiency and plant resource expansion

• Successful implementation of High Yield Bond Programme

Page 16: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

16

Medium to Long-Term Strategy

• Harness synergy within the group

• Expand product offering and maintain market share

• Geographical diversity in Civils, Pipelines & Geotechnical

• Environmental accreditation ISO 14001

• Further securing of long-term contracts to create future visibility and to

underpin sustainability

• Focus on sustainable growth nodes within government infrastructure

programmes

• Carbon emissions will be measured and managed

• Addressing Construction Charter requirements to improve BEE scoring by

31 December 2013

• Focus on concession and development projects

• Focus on private sector clients to balance dependency on government

contracts

Page 17: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

17

OPERATIONAL REVIEW 31 Aug 2012

Page 18: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

18

Products & Services

GEOTECHNICAL PIPELINES CIVILS

• Pilling

• Lateral support

• Marine structures

• Pipejacking

• Thrust boring

• Bridgejacking

• Diaphragm walls

• Ground improvement

• Dynamic compaction

• Ground remediation

• Soils investigation

• Geotechnical design

• Gas & petrochemical

steel pipelines

• Water & wastewater

pipelines

• Sewer pipelines

• Pump stations

• Pipeline refurbishments

• Cement mortar lining

• Valve chambers

• Associated concrete

structures

• Associated

infrastructure

• Road construction

• Bridge construction

• Township infrastructure

• Mining infrastructure

• Water reticulation

• Water towers

• Reservoirs

• Sewer reticulation

• Bulk earthworks

• Building

• Housing

• Development

Products & Services

Page 19: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

19

Clients

GEOTECHNICAL PIPELINES CIVILS

• Civil contractors

• Building contractors

• Listed & private

contractors

• Government at:

• Central

• Provincial

• Municipal levels

• Property development

companies

• Parastatals:

• Eskom

• Transnet

• Rand Water

• Umgeni Water

• Portnet, etc

• Mining sector including

most major mining houses

• Government at:

• Central

• Provincial

• Municipal level

• Parastatals:

• Transnet

• Rand Water

• Umgeni Water

• Portnet

• TCTA & DWAF

• Mining sector

• Private clients

• RBM

• Foscor

• Mondi

• Cross-border

• FIPAG Mocambique

• Botswana Government

• Mining sector

• Zimbabwe & DRC

• Eskom

• Sanral

• Anglo Coal

• Xstrata

• RAL

• Gauteng Province

• Government

• Central

• Provincial

• Municipal

• Private developers

• Bakwena Concessions

• Debswana

Clients

Page 20: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

20

Competitors

GEOTECHNICAL PIPELINES CIVILS

• Steffanutti Stocks in-

house geotechnical

division

• Aveng in-house

geotechnical division

• Dura (Solentache Bachy

is a large global

contractor)

• Wepex

• Gauteng Piling

• Offshore – international

geotechnical contractors

• WK Pipelines

• WBHO

• Group 5

• Steffanutti Stocks

• Cycad

• Aveng

• Cerimele Construction

• Murray & Dixen

• Concor

• Ikon

• Murray & Roberts

• Aveng

• WBHO

• Group 5

• Steffanutti Stocks

• Basil Read

• Raubex

• Erbacon

• Protech-Khutheli

• Diesel Power

• Haw & Inglis

Competitors

Page 21: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

21

Value Proposition

GEOTECHNICAL PIPELINES CIVILS • Geotechnical market

leader in South Africa with

good reputation and well

known brand in SSA

• Design alternatives

constantly investigated

• Geographical diversity

entrenched and expanded

• Depth of management

know-how with well

established business

processes for over 65

years

• Plant capacity retooled

and modernised

• ISO 9001 accredited

• OHSA 18001 accredited

• Niche leader in welded

pipelines

• Supply and install all

aspects of cross-

country pipelines

• Supply and install

pipelines in a myriad of

materials

• Experienced and

talented management

team

• Excellent track record

with blue-chip clients

• ISO 9001 accreditation

• OHSA 18001

accredited

• Diversified range of

construction services

• Plant capacity and

capability expanded

• Excellent workshop

facilities

• Strong relationships

with mines and

consulting engineers

• Experienced and

talented management

team

• ISO 9001 accredited

• OHSA 18001

accredited

Value Proposition

Page 22: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

22

Geographical footprint

Currently

working in Ghana

5th contract

awarded.

New awards in

Kenya & Uganda

Page 23: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

23

Geotechnical - Key Contracts

Country & Contract Description

Angola, Kinaxixi MXD complex Phase I – 1 150 soil nails, 4 200m² of gunite, 310 micropiles and over 370 soldier

piles. Phase II comprised the installation of up to five rows of Titan anchors, 7 500m²

of gunite arches and approximately 90 jet grout columns.

Duration: 15 months – in progress

Ghana, ADA Groynes Construction of 7 jetties for rock placement ranging in length from 112-212m. Jetties

are 700m apart and require sheetpile cofferdams and side jetties extending 65m to

120m out to sea. Jetties support 75t service cranes, 100t excavators and 60t rock

bogeys. ADA Groynes Ghana.pptx

Duration: 15 months

South Africa, 102 Rivonia Road,

Lateral Support to Basement

Excavation

5600m2 of permanent lateral support to basement excavation, comprising 182No x

600mm diam perimeter piles up to 22m deep with reinforced gunite arches and

540No ground anchors 450-750kn capacity up to 19m in length. 30No internal

structural piles of maximum diam 1200mm.

Duration: 5 months – complete 102 Rivonia Road.pptx

South Africa, The Bluff Military Base

(KZN)

Duration: 5 months – current Bluff Military Base - Stormwater Disposal - New.pptx

Mozambique, Beira Stacker and

Quay Upgrade

Deep piling to 28 metres for new coal export facility.

Duration: 10 months - completed

Mauritius, La Balisle

La Balisle Mauritius.pptx

Page 24: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

24

Pipelines - Key Contracts

Province & Contract Description

KwaZulu-Natal Umlaas Road

Contract for Umgeni Water

Installation of 13 km of 1 200mm diameter steel pipeline and associated concrete

structures consisting of air-valves, scour valves, 15m vertical shaft and 120m

pipejack under N3 freeway. An energy dissipating intake works will take 500m3 of

concrete to construct.

Duration: 18 months – in progress

Limpopo, Nebo Plateau Bulk Water

Pipeline

Installation of 32km of a 450mm diameter steel pipeline from Nebo to Jane Furst.

Duration: 24 months - completed

Gauteng, BG3 Delivering water from the Vaal Dam, a distance of 8.6km, in a 3 500mm diameter

steel pipe to the canal feeding Zuikerbos Pump Station.

Duration: 24 months – in progress BG3 Contract Progress.pptx

KwaZulu-Natal, Lower Thukela Water

Pipeline

Installation of 30km of a 900mm diameter bulk potable water steel pipeline and

associated structures including pipejacking under essential services.

Duration: 18 months – still to commence

Eastern Cape, Mbizana Pipeline Installation of 13km of a 500mm diameter steel pipeline from the Ludeke dam

site to the Nomlaqu treatment works.

Duration: 12 months – completed

KwaZulu-Natal, Eshowe

Kwahlokohloko Pipeline

Installation of 5.7kms of continuous welded steel waterpipe for Kwahlokohloko

including associated structures.

Duration: 8 months

Page 25: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

25

Civils - Key Contracts

Province & Contract Description

North West, Bakwena N4 Toll Road Construction of a second 21km carriageway along a section of the N4. Including 7No

major structures, 5 large culverts and 160 No cross drainage structures

Duration: 30 months – in progress

Mpumalanga, Kusile Power Station Package 26 - Underground service ducts to completed terraces.

Package 25 - general services pipeline. General terraces earthworks and crushing

contracts.

Duration: 36 months – in progress

Gauteng, K71/R55 Phase 1 of the 6.5km R55 from the N14 to the Wierda Road (Kl03) intersection

including two road-over-river bridges.

Duration: 24 months - completed

Final phase comprising 4.2km construction of a dual carriageway from the Kl03

intersection to Laudium and an additional two road-over-river bridges.

Duration 24 months – complete

Gauteng, Orchards Development The servicing and sale of 1373 residential 1 erven near Rosslyn and Acacia to “top-

structure developers”

Duration: 40 months – in progress

Northern Cape, Kathu Construction of infrastructure to 1437 stands, houses and apartments for Bestwood

development

Duration 42 months – in progress Bestwood D evelopment.pptx

Page 26: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

26

RISK MANAGEMENT

Boardroom Engineering at its BEST_1.pdf

Page 27: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

27

Matrix of Major Risks

Material Risks Mitigation

Dependency on government

infrastructure spend

Product & market diversification, Strategic B-BBEE rating &

geographical diversity

Working capital management Monthly cash flow forecast, working capital facilities, tougher on debt

collection & KPAs of divisional managers

BEE Promotion from within & careful management of transformation process

Material shortages

material delivery delays

Proper planning, qualifying bids, site contracts and manuals & KPAs of

divisional managers

Credit risk and cost reporting Monthly review at EXCO meeting, monthly review of contract financials

& KPAs of divisional managers

Bribery and corruption Obtain court interdicts, exposure of corruption through whistle-blowing &

enforce Code of Ethics and Conduct. Internal resource investigator

appointed.

Competition Build on reputation through strong brand, be competitive in terms of

price and quality, include alternative bids & in-house design

Underperforming contracts Immediate identification and response, follow up with possible

disciplinary action, ensure accountability, appoint the right people to the

right jobs, minimise non-conforming reports & compliance reviews

against policies and procedures

Page 28: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

28

Risk Management

Meetings

Tender committees

Site visits

Risk management officer &

internal audit

Monthly cost and resource

meetings

Authority levels

Board, Risk, EXCO, Divisional & Site

Finalisation meetings

Regular and varied

Continuous programme of checking and

assessment

Attended by CEO & CFO in all divisions

Regularly updated and adhered to

Basic conditions of tender

Pricing

Project management software

Costs

Scope

Margins

Tendering process

Quality ISO 9001

Safety ISO 18001

Environmental ISO 14001

FIDIC, NEC, GCC, client specific

Overhead, mark-up, risk

Production, programme, current prices

Resource planning & management (people &

plant)

Tender finalisations, limits of authority, policies &

procedures

Accreditation certificate received

Currently in accreditation process

Management

Contracts

Page 29: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

29 SEGMENTAL REVIEW

Page 30: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

30

Segmental Review - Geotechnical

GEOTECHNICAL Aug 2011

R’ 000

Aug 2012

R’ 000

Segment revenue 405 611 410 327

PBIT 15 211 39 246

Segment assets 674 136 726 991

No of employees 1 408 1013

Revenue growth (4.2%) 1.2%

Operating margins 3.75% 9.6%

Order book 244 017 311 154

Pending awards 94 775 193 700

Prospects 1 246 870 944 639

Non-government 58% 65.5%

Government 42% 34.5%

Page 31: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

31

Segmental Review - Pipelines

PIPELINES Aug 2011

R’ 000

Aug 2012

R’ 000

Segment revenue 113 320 149 163

PBIT 637 10 418

Segment assets 115 445 125 166

No of employees 475 387

Revenue growth 10.8% 32%

Operating margins 0% 7%

Order book 567 618 314 808

Pending awards 170 000 688 000

Prospects 500 000 1 540 000

Non-government - -

Government 100% 100%

Page 32: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

32

Segmental Review - Civils

CIVILS Aug 2011

R’ 000

Aug 2012

R’ 000

Segment revenue 354 366 598 765

PBIT (25 958) 28 670

Segment assets 718 654 795 274

No of employees 1 544 2499

Revenue growth 57% 69%

Operating margins (7.3%) 4.8%

Order book 983 954 1 803 838

Pending awards 2 200 000 1 005 000

Prospects 3 000 000 2 400 000

Non-government 34% 41.7%

Government 66% 58.3%

Page 33: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

33

ORDER BOOK AND OUTLOOK

Page 34: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

34

Order book as at 31 August 2012

Business Unit Order Book

(R millions)

Secured Revenue

FY 2013

(R millions)

Secured Revenue

FY 2014+

(R millions)

Geotechnical 311 283 28

Civils 1 804 581 1 223

Pipelines 315 195 120

Total 2 430 1 059 1 371

Page 35: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

35

Geotechnical Outlook as at 31 Aug 2012

Awarded Pending & Key

R94m R227m

R44m R301m

R17m R209m

R38m R102m

R90m R326m

TOTAL R1 441m R283m R1 165m

Johannesburg

Cape Town (including Ghana)

Angola

Durban, KwaZulu-Natal

Mauritius Mozambique, Tanzania & East Coast

Page 36: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

36

Pipelines Outlook as at 31 Aug 2012

Description Value

• BG3 near Vaal

• Kwahlokohloko bulk water supply

• Bluff military base

• Umlaas Road

• Thulele/ Woodmead

• Ezenzeleni raw water treatment works & pump

station

R314m

• Palmiet pump station Rand Water

• Lower Tukhela (Stanger)

• Xonza Dam (Eastern Cape)

• Shakaskraal Starr Family Trust

• Balcombe Ilembe

R689m

• Western Aqueduct

• Northern Aqueduct

• Mooihoek 4

R1 540m

TOTAL R2 543m

Current contracts

Pending & potential awards

Key contracts

Page 37: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

37

Civils Outlook as at 31 Aug 2012

Description Value

• K71/R55

• RAL current road contract

• Bakwena N4 (Mooinooi)

R187m (10%)

• Package 26 Terraces contract

• Package 25 General Services Pipeline

• General Terraces

• Crushing

R324m (18%)

• 7 mines

R158m (9%)

• The Rose in Rosebank (5 storey)

• Roedean

• Bestwood Development

• Orchards

R545m (30%)

• Vryberg pipeline

• Pipejacking

• Botswana

R589m (33%)

TOTAL R1 803m

Roads

Kusile

Mine work at Xstrata & Anglo Coal

Current contracts rolled over from last year as at 31 Aug 2012

Building & Development

General

Page 38: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

38

Civils Outlook as at 31 Aug 2012

Description Value

• N4 next phase

• Mpumalanga Roads

R900m

• Terraces bulk earthworks

• Housing (details unknown)

R106m

• Kromdraai Pipeline

R180m

• Moz housing & infrastructure (4-5yrs)

• Bestwood (4-5yrs)

• Gauteng housing contract

R4 930m

• Waste water treatment works

R240m

TOTAL R6 356m

Roads

Kusile

Mine work at

Anglo Coal

Pending awards and targeted key contracts

Building

General

Page 39: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

39

General Outlook 2013FY and beyond

• Sandton

• Rosebank

• Hatfield

• Park Station surrounds & Braamfontein

• I have no doubt that significant development

will occur around Park Station and into the

Braamfontein surrounds now that this leg is

operational as is evidenced elsewhere.

• Mozambique Coal & Gasfields

• Iron ore & manganese

• Coal

• Platinum

• There is still significant work to be done to

benefit from South Africa’s own huge

resource base as well as that of our

neighbours.

• Private & Commercial Developments

• African new markets

• Presidential infrastructure initiative

• Integrated Housing Developments

• Indication that this is starting to pick up

• Ghana, Kenya, Uganda & Zambia

• As per State of the Nation address

• High priority for government

Gautrain Private Development Spinoff

Resource Arena

General

Page 40: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

40

General Outlook 2013FY and beyond

• Medupi & Kusile Power Stations

• Nuclear Power Station/s

• 3rd Coal fired Power Station

• Transmission Lines

• Solar and Wind initiatives

• Some housing still to happen

• Has been in the press extensively lately

• Rumours (independent energy company)

• Geotechnical foundation solutions

• Geotechnical foundation solutions

• 15 000km non-toll roads

• R9.5-billion in 2012 budget

• Coal haul-road upgrades R20-billion

• GFIP phase 2

• Sanral are obviously in a state of flux after

the e-tolling debacle but will ultimately be

supported by central government

• This is due to come out to tender again

• Dependent on e-tolling resolution

• Transnet

• Port authorities

• PetroSA

• Coega

• R330-billion capex spend

• Drydocks and general harbour upgrades

• Refined product line from Maputo

• Refinery, smelter or both

Energy sector

Sanral & other roads

Other parastatals

Page 41: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

41

CAPEX

Page 42: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

42

Capex

Segments

(R ‘000’s)

Financial years

2013

Total

2013

H1

Actual

2012 2011

Geotechnical 47 000 35 100 51 100 11 793

Civils 151 000 87 700 205 317 17 964

Pipelines 30 000 3 000 620 6 104

Corporate 7 000 0 685 14 512

Total 235 000 125 800 257 722 50 373

Revenue 2 200 000 1 140 000 1 727 000 1 366 433

Page 43: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

43

CONCLUSION

THANK YOU

Page 44: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

44

Disclaimer

Forward-looking statements

This presentation contains forward-looking statements that, unless

otherwise indicated, reflect the company’s expectations as at 31

August 2012. Actual results may differ materially from the company’s

expectations if known and unknown risks or uncertainties affect its

business or if estimates or assumptions prove inaccurate. The

company cannot guarantee that any forward-looking statement will

materialise and, accordingly, readers are cautioned not to place

undue reliance on these forward-looking statements. The company

disclaims any intention and assumes no obligation to update or

revise any forward-looking statement even if new information

becomes available as a result of future events or for any other

reason.

Page 45: Interim results presentation - Esor Pipelines · 2019-03-22 · Lateral Support to Basement Excavation 5600m2 of permanent lateral support to basement excavation, comprising 182No

45

www.esorfranki.co.za

Esorfranki Limited | 30 Activia Road Activia Park Germiston 1401

PO Box 6478 Dunswart 1508 South Africa

+ 27 83 259 2584

+27 11 776 8700

+27 11 822 1158

[email protected]

Bernie Krone| CEO

+ 27 82 498 3518

+27 11 776 8700

+27 11 822 1158

Wessel. [email protected]

Wessel van Zyl | CFO


Recommended