Levee Rehabilitation ProjectsLower Rio Grande Valley
International Boundary and Water CommissionEngineering Services Division
Submitted LRGV FEMA Review Packages
1. Common Levee 2. Mission Levee Phase I 3. Mission Levee Phase II 4. DHS Levee/Wall Segment O-04A 5. DHS Levee/Wall Segment O-04C 6. DHS Levee/Wall Segment O-05 7. DHS Levee/Wall Segment O-06A 8. DHS Levee/Wall Segment O-06B & C 9. DHS Levee/Wall Segment O-07
International Boundary and Water CommissionEngineering Services Division
Submitted LRGV FEMA Review Packages
10. DHS Levee/Wall Segment O-08 11. DHS Levee/Wall Segment O-09 Phase I 12. DHS Levee/Wall Segment O-09 Phase II13. DHS Levee/Wall Segment O-1014. North Banker Floodway Levee15. Mission Levee Improvements at Bentsen Palm Drive,
UID, Penitas RR Crossing16. Main Floodway 17. North Floodway – Two Structures 172 &41318. North Floodway Phase I
International Boundary and Water CommissionEngineering Services Division
Submitted LRGV FEMA Review Packages
19. North Floodway Phase II20. Arroyo Colorado Phase I21. Arroyo Colorado Phase II22. Lower Brownsville Levee – (Donna to Brownsville Reach # 5)
International Boundary and Water CommissionEngineering Services Division
• Accredited Levee System - A FEMA accredited levee system is a levee system that meets the requirements of 44CFR65.10 and therefore is shown on the Flood Insurance Rate Map (FIRM) as providing protection from the 1-percent-annual-chance flood.
• FEMA does not own, operate, maintain, or inspect levee systems or develop certified levee-related data for accreditation purposes.
FEMA Accreditation
International Boundary and Water CommissionEngineering Services Division
• As the levee owner, USIBWC will evaluate that the levees have been constructed to required design standards and are operated appropriately.
• For FEMA to accredit a levee system with 1%-annual-chance flood hazard reduction capability on a FIRM, the levee owner/local project sponsor must submit a package containing the required data and documentation to show that the levee system meets all design and operation requirements of 44CFR 65.10.
FEMA Accreditation
International Boundary and Water CommissionEngineering Services Division
• Interior Drainage - FEMA requires an Interior Drainage Analysis. To date, no analysis exists. USIBWC is only authorized to do work on the levees within USIBWC ROW and does not have authority in assessing the interior drainage issues.
• Levees need to tie into high ground• Levee/Roadway intersections • Intake / Drainage Channels
Accreditation “Speed Bumps”
International Boundary and Water CommissionEngineering Services Division
LRGV Construction Projects Under Administrative Close Out
1. Lateral A to Retamal Dike2. Hidalgo Phase I and II3.Upper Brownsville Levee - (Donna to
Brownsville Reach #4)
International Boundary and Water CommissionEngineering Services Division
FEMA Packages Submitted - Map
International Boundary and Water CommissionEngineering Services Division
LRGV FLOOD CONTROL PROJECTS
International Boundary and Water CommissionEngineering Services Division
• Upper Brownsville Levee Improvements- (Donna to Brownsville Reach # 4)
• Los Indios to San Pedro Levee Improvements– (Donna to Brownsville Reach #3)
• Santa Maria to Los Indios Levee Improvements- (Donna to Brownsville Reach #2)
• Progreso Levee Improvements (Donna to Brownsville Reach #1)
LRGV CONSTRUCTION PROJECTS
International Boundary and Water CommissionEngineering Services Division
UPPER BROWNSVILLE LEVEE
• 12.0 levee miles (from San Pedro to International Blvd in Brownsville)• $8.8 million contract to LECON Inc.• Notice to Proceed issued June 1, 2013• Completion Date of October 2, 2014• 100% Complete, Project is in Administrative Close Out
International Boundary and Water CommissionEngineering Services Division
UPPER BROWNSVILLE LEVEE
International Boundary and Water CommissionEngineering Services Division
LOS INDIOS TO SAN PEDRO LEVEE
• 11.9 levee miles• $11.5 million contract to LECON Inc.• Notice to Proceed issued December 26, 2013• Anticipated completion August 28, 2015• 52% Complete
International Boundary and Water CommissionEngineering Services Division
LOS INDIOS TO SAN PEDRO LEVEE
International Boundary and Water CommissionEngineering Services Division
SANTA MARIA TO LOS INDIOS LEVEE
• 11.7 levee miles total• $9.6 million contract to EISG Inc.• Notice to Proceed issued September 25, 2014.• Anticipated completion January 23, 2016 • 0% Complete
International Boundary and Water CommissionEngineering Services Division
SANTA MARIA TO LOS INDIOS LEVEE
International Boundary and Water CommissionEngineering Services Division
PROGRESO LEVEE
• 6.0 levee miles total (west segment is 2.0 miles; east segment is 4.0 miles)• $3.7 million contract to EISG Inc.• Notice to Proceed issued July 9, 2014• Anticipated completion August 13, 2015• 1% Complete
International Boundary and Water CommissionEngineering Services Division
PROGRESO LEVEE
International Boundary and Water CommissionEngineering Services Division
• Arroyo Colorado Levee, Phase 3• North Floodway North & South Levees
(Phase 3)• North Floodway North & South Levees
(Phase 4)• Edinburg Pump Levee Rehabilitation
LRGV DESIGN PROJECTS
International Boundary and Water CommissionEngineering Services Division
Arroyo Colorado Phase 3 – Brown Line
ARROYO COLORADO PHASE 3 DESIGN
• Design : 16.1 miles of levee
• $1.9 million design contract awarded to Tetra Tech Inc.
• Notice to Proceed issued on March 11, 2010
• Design completed Sept. 2013
• Construction will be done in 3 sub phases: 3A to 3C
International Boundary and Water CommissionEngineering Services Division
North Floodway Phase 3 – Light Blue Line
NORTH FLOODWAY PHASE 3 DESIGN
• Design : 23.5 miles of levee
• $5.6 million design contract URS Group, Inc. (NF Phases 3 and 4)
• Notice to Proceed issued on June 16, 2010
• Design completed Oct. 2013
• Construction will be done in 4 sub phases: Phases 3A to 3D
International Boundary and Water CommissionEngineering Services Division
North Floodway Phase 4 – Medium Blue Line
NORTH FLOODWAY PHASE 4 DESIGN
• Design : 29.2 miles of levee
• $5.6 million design contract URS Group, Inc. (NF Phases 3 and 4)
• Notice to Proceed issued on June 16, 2010
• Design completed Nov. 2013
• Construction will be done in 5 sub phases: Phases 4A to 4E
International Boundary and Water CommissionEngineering Services Division
Edinburg Pump – Yellow Line
EDINBURG PUMP LEVEE REHABILITATION DESIGN
• Design : .7 miles of levee
• $400,000.00 design contract URS Group, Inc.
• Notice to Proceed issued on October 1, 2014
• Design completion anticipated by June 25, 2015
• Construction will be done in 1 phase
International Boundary and Water CommissionEngineering Services Division
ACCOMPLISHMENTS
• 262 miles of levee improvements completed
• 22 certification packages submitted to FEMA
• Visit www.ibwc.gov to learn more about the Levee Improvement Status
International Boundary and Water CommissionUnited States SectionEngineering Services Division
Construction Projects InquiriesIsela Canava
Lead Civil Engineer(915) 832-4748
Jose A. NuñezPrincipal Engineer
IBWC – US Section Head Quarters(915) 832-4749
FEMA Certification InquiriesValentin ArzolaCivil Engineer
(915) 832-4712