Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR) Billy Gibbons, MBA (Portland, OR) Ira Janowitz, PT, CPE Alan Barr, MS David Rempel, MD University of California, San Francisco University of California, Berkeley - PowerPoint PPT Presentation
Popular Tags:
44
Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR) Billy Gibbons, MBA (Portland, OR) Ira Janowitz, PT, CPE Alan Barr, MS David Rempel, MD University of California, San Francisco University of California, Berkeley Center for Occupational and Environmental Health Ergonomics Program
Transcript
Page 1: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Interventions for Overhead Drilling

Demetra Dalamagas, MS, IH (Portland, OR)Billy Gibbons, MBA (Portland, OR)Ira Janowitz, PT, CPEAlan Barr, MSDavid Rempel, MD

University of California, San FranciscoUniversity of California, Berkeley

Center for Occupational and Environmental HealthErgonomics Program

Page 2: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Overhead Drilling into Concrete

Sheet metal work

inserts/anchors/racks/straps for ducts/pipes/conduits

Building trades: sheet metal, plumbing, electrical

Page 3: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Risks from Overhead Drilling

• Falls• Dust Exposure• Noise• Shoulder and Arm Disorders

Page 4: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Shoulder/arm loads

Page 5: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Interventions

Page 6: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

5 year project

• Phase I (YR1) – Develop Interventions• Phase II (YR2-4) – Evaluate Interventions• Phase III (YR 5) – Disseminate Findings

• Funding– Center to Protect Workers Rights– NIOSH

Page 7: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase I - Development

• 20 construction workers

• Use 3 devices on one day – 1 hour each

• Outcomes– Device Questionnaire– Comparison Questionnaire

• Modify devices

• Repeat

Page 8: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase II - Evaluation

• 120 Construction workers• Use ‘best’ 2 interventions, each for 1 day• Outcomes

– Arm, shoulder and neck pain – Shoulder and neck posture (inclinometer)

• Peter Johnson (UW)• Steve Robinovitch (SFU)

– Shoulder and forearm EMG– Handle vibration (Bernard Martin (UM))

– Productivity

Page 9: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase III - Dissemination

• Trades

• Contractors

• Purchasers

• Tool Manufacturers

• H&S Construction Professionals

Page 10: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase I - Development

Page 11: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Gen 1 Gen 2

Inverted Drill Press

Page 12: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Gen 1 Gen 2

Inverted Drill Press Close Up of Gears

Page 13: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Gen 1 Gen 2

Foot LeverDrill Press

Page 14: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Drills and Saddles

Page 15: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Successful Outreach

ContractorsRosendin Electric Cherry City ElectricJH Kelly Advanced Technology GroupTemp Control Mechanical Interstate Mechanical IndustriesStreimer Sheetmetal LH SowlesElectric Construction Co Oregon Electric Group

ConstructionSkanska TurnerLayton Anderson

OwnerIntel Sea-Tac

UnionsIBEW Local 48UA Local 290SMWIA Local 16

Page 16: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

GOSH Conference Booth

Page 17: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

GOSH Conference Booth

Page 18: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Cross Industry Partnerships

• Toyota Logistics-Portland, Oregon

• Toyota safety committee member (Teamster) saw our display at a conference

• ODP /Toyota team consultation to incorporate modified version of our inverted drill press into their operation

Page 19: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Presentations

UBC/UW Annual Safety and Health Conference, 2005TNO, Amsterdam, 2005International Ergonomics Association, Maastricht, 2006

Page 20: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase I - Development

• 20 workers• Usual Overhead drilling

– Demographic Questionnaire

• Each device for 1 hr– Observer notes– Device Questionnaire

• End of day– Comparison Questionnaire

Page 21: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase I - Development

Page 22: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase I - Development

Page 23: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Device Questionnaire

Ease of DeviceOn a Scale of 0-5 where 0 is difficult and 5 is easy, how would you rate this device for the following characteristics:

Difficult EasySetting-Up 0 1 2 3 4 5Moving 0 1 2 3 4 5Fine Positioning 0 1 2 3 4 5Activating Drill 0 1 2 3 4 5Drilling 0 1 2 3 4 5Knowing when drilling 0 1 2 3 4 5 is complete

Page 24: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Device Questionnaire

Appeal On a scale of 0-5, where 0 is poor and 5 is excellent, please rate the following:

Poor ExcellentAccuracy 0 1 2 3 4 5Control 0 1 2 3 4 5 Stability 0 1 2 3 4 5Looks (aesthetics) 0 1 2 3 4 5Durability 0 1 2 3 4 5Feel 0 1 2 3 4 5

Page 25: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Device Questionnaire

How would you describe this device compared to your usual method of drilling? (circle one)

Slower Same Faster

What would you change to improve the ease of using this device?

Page 26: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Device Questionnaire

Fatigue (Tiredness)On a scale of 0-5, where 0 is no fatigued and 5 is very fatigued, please rate the following after using the device:

No Fatigue Very FatiguedNeck 0 1 2 3 4 5 Shoulders 0 1 2 3 4 5Hands & Forearms 0 1 2 3 4 5 Low Back 0 1 2 3 4 5 Legs 0 1 2 3 4 5

How would you change this device to reduce pain or fatigue to the operator?

Page 27: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Device Questionnaire

What three things do you like about this device?

What three things do you dislike about this device?

If available, would you use this device again next time? Yes No

Why or why not?

Page 28: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Comparison Questionnaire

Rank the drilling method for each characteristic, where 1 is the best, 2 is the second best, 3 is the worst.

Photo Photo UsualDevice 1 Device 2 Method

Set-Up _______ _______ _______Moving _______ _______ _______Ease of Use _______ _______ _______Accuracy_______ _______ _______Productivity _______ _______ _______Comfort _______ _______ _______Overall _______ _______ _______

Page 29: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase I - Development

• 14 workers– 14% female– 7% hispanic

• Outcomes– Subject preferred usual method for ease and speed– Video analysis: device drilling faster– Less fatigue with devices– Preference: inverted drill press over foot lever– Improve

• Mobility, balance• Decrease weight• Handle design• Ease of set-up – leveling, hitting hole mark• Cord handling

Page 30: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

• Phase 1b designs (3rd generation)– Modular (3 bases)– Rebuild gearing system– Change handles– Use aluminum for saddles and bases– Add locking castors– Channel power cords– Add depth stop

Page 31: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

Adjustable Castor Base

Page 32: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

Collar Base

Page 33: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

Page 34: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

Page 35: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

Page 36: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

Page 37: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

Page 38: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

Page 39: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

Page 40: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

Page 41: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Phase Ib - Development

FeedbackVery positiveCollar and spring - top ratings3 wheel base not 4 wheelImprove depth stop (add light)Add dust controlScissor lift

device too tall – hinge drillbase too large – attach to railing

Not tall enoughadd extension

Move switch closer to handle

Page 42: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Problems

•Construction site access•Each setting learn something new•Redesigning and building devices takes time•Budget•Involving tool companies (e.g., Hilti, Milwaukee)

•patent

Page 43: Interventions for Overhead Drilling Demetra Dalamagas, MS, IH (Portland, OR)

Plans

•Complete Phase I testing by May 31•Begin Phase II testing August 1

•Inclinometers purchased and being field tested•Vibration measurement system purchased

•Dissemination planning underway